HomeMy WebLinkAboutHMI / OHMAN PUBLIC UTILITIES CONSTRUCTION AGREEMENT
The City of' Bremerton, a first class municipal corporation of the State of Washington, (hereinafter
"City") and HMI/Bob Ohman (hereinafter "Owner"), in consideration of the mutual covenants
herein defined, enter imo this agreement for the construction and public dedication of Water, Sewer,
and Storm Mains (hereinafter "Project") in accordance with the following terms and conditions. The
Owner will retain a licensed Professional Engineer registered in the State of Washington (hereinafter
"Design Engineer") who shall design the Project.
1. DESCRI]rI~ION OF THE PROJECT: The project to be constructed by the Owner and
dedicated to the City for public use, consists of:
Approximately 637 lineal feet of 8-inch ductile iron water pipe, one fire hydrant
assemblies, approximately 1055 lineal feet of 12-inch ductile iron water pipe, two (2) fire
hydrant a~emblies, approximately 38 lineal feet of 8-inch ductile iron water pipe,
approximtely 42 lineal feet of 6-inch ductile iron water pipe, and miscellaneous
appurtenances.
And
Approximately 654 lineal feet of 8-inch PVC sewer pipe, four (4) manhole assemblies,
and miscellaneous appurtenances.
And
Approximately 375 lineal feet of 15-inch CpeP storm pipe, approximately 337 lineal feet
of 12-inch CpeP storm pipe, approximately 102 lineal feet of 60-inch cmp storm pipe,
approximately 72 lineal feet of 72-inch cmp storm pipe, approximately 35 lineal feet 8-
inch storm pipe, 11 ~ype 1 catch basins, 3 type 2 catch basins and miscellaneous
appurtenances.
The Project is more fully described in the plans and specifications incorporated by reference herein.
PUBLIC UTILITIES CONSTRUCTION AGREEMENT -1-
2. FEES AND EXPENSES:
A. The Owner agrees to pay in advance the following fees and expenses associated with
the projec~ and requi~xl by the Bremer~on Municipal Code:
· Plancheck (water 177.20, sewer 100.00, storm 150.00) $ 427.20
· Inspection fees (water 1,329.00, sewer 817.50, storm 108.50) $ 2,255.00
· Total parcel FFF (water 2,123.00, sewer 482.60) $ 2,605.60
· Connection fees (2 Wet Taps) $ 4358.00
· Total $ 9,645.60
Payment of appropriate General Facilities Fees and Front Footage Fees will be required prior
to receiving utility service from the City.
B. The Owner shall he responsible for obtaining and paying for necessary permits from
other governmental agencies and shall be responsible for any additional costs for
inspection billed to the City by any government agency, including but not limited to the
City ofBremerton, Kitsap County, or the State of Washington.
C. The owner shall pay all costs associated with easement acquisition and insuring title to
the properties.
D. The owner shall post with the City Treasurer a Performance Bond prior to construction
and a Warranty Bond upon completion of the work. The bonds shall be posted in the
amounts as follows:
Performance Bond
1. One hundred and fifty percent (150%) of the Design Engineers estimated cost
of construction for all work occurring within public fight-of-way or on City
Property.
2. Twenty percent (20%) of the Design Engineers estimated cost of construction
for all work occurring on Private Property.
PUBLIC UTILITIES CONSTRUCTION AGREEMENT -2-
Warranty Bond
1. Twenty percent (20%) of the actual cost of construction.
E. The bonds shall provide, as a minimum, the following:
1. The Owner shall complete the project in accordance with good and accepted
engineering and construction practice.
2. The Owner shall comply with all the terms of this agreement.
3. The Owner shall fully comply with all requirements of law in carrying out the
project, and shall comply with all lawful requirements imposed by any agency
with jurisdiction relating to the project.
4. The Warramy Bond shall be effective for at least two years after completion of
construction unless a~mmtively released sooner by the City, and shall
guarantee the completed projects against defects in workmanship and
materials.
5. The bond must be approved by the City's Risk Manager and may include one or more
surety bonds issued by any surety company licensed to do business in the State
of Washington. The Surety bond may be substituted by a cash deposit in the
full-required amount deposited with the City Treasurer or an assignment of
funds on deposit in a licensed bank or credit union, in the fi~ii required amount.
3. REPRESENTATIVES: The Owner hereby names the following person as the representative
of the Owner for all purposes reqg&ired by this agr .ee~t:
The Owner warrants that the Owners representative has flail authority to bind the Owner in all
respects required by this agreement, and all applicable government requirements imposed by
any agency with jurisdiction. The City hereby designates Ned Lever , of its
Department of Pubtic Works and Utilities as its Project Manager and warrants that the Project
Manager has full authority to exercise such discretion as does the Director of Public Works and
PUBLIC UTILITIES CONSTRUCTION AGREEMENT -3-
Utilities under the ordinance of the City for purpose of carrying out the terms of this
agreement.
4. PROJECT I)ESIGN: The Owner will retain a licensed Professional Engineer who shall
design the project, prepare the necessary plans, and provide construction engineering to the
extent reasonably necessary.
Owner shall use the following standards for design and construction of the project. Deviation
from standard plans will not be accepted.
· Standard plans and specification provided by the City.
· Bremerton Utilities Development and Construction Standards.
· Washington State Department of Ecology's Stormwater Management Manual for the
Puget Sound Basin.
· American Waterworks Association Standards.
· Washington State Department of Transportation's Standard Specifications for Road,
Bridge, and Municipal Construction.
5. PUBLIC WORKS PROJECT PERMIT: The City's Project Manager will review the
project design, plans, and specifications, and when satisfied the work is in accordance with City
standards, shall approve the plans by stamping and signing four (4) copies of the plan sheets.
The City reserves the right to require modification of the plans in the event of errors or
mistakes in the drawings, or if new information becomes available which requires a change in
the plans to properly accomplish the project. Plan changes initiated by the Owner must be
approved in writing by the City prior to commencement or alteration of the work.
The City will isme a Public Works Project Permit upon submittal or completion of the
following:
A. Construction Plans and Specifications have been approved by the City's Project
Manager.
B. Deposit of advance cash deposits as stated in this agreement with the City Treasurer.
C Approved bonds posted with the City Clerk.
D. Proof of insurance approved by the Risk Manager.
PUBLIC UTILITIES CONSTRUCTION AGREEMENT -4-
E. A copy of the City or County right-of-way permit submitted to the Utility.
6. INSURANCE AND INDEMNITY: The Owner shall provide liability and property damage
insurance covering all work under this agreement for construction within the public right-of-
way, including all work provided by the Owner and its Contractors. Said insurance shall name
the City of Bremerton as additional insured and provide the following limits:
- Bodily injury, $1,000,000.00 each person;
- $1,000,000.00 each accidem;
- Property damage, $500,000.00
Evidence of such insurance shall be provided to the Risk Manager prior to issuance of the
Public Works Project Permit. The Owner shall hold harmless the City of Bremerton, its elected
officials, employees, and agents, for all liabilities and claims arising out of or related to
performance of the work identified in this agreement.
7. PROSECUTION OF WORK:
A. Construction of the project shall be initiated within one (1) year of execution of this
agreement by the Owner and within 30 days of issuance of the Project Permit. Failure
to begin work within the one-year limit shall result in forfeiture of all Owners' rights
under the agreement regardless of any other provisions of this agreement.
B Owner agrees to continuously pursue work and complete the project within six (6)
months of permit issuance.
& ADDITIONAL CONSTRUCTION WORK REQUIREMENTS: The Owner in addition
to other duties included in this agreemem shall comply with the following:
A. Schedule system connections with the Project Manager and meet all requiremems for
the connection and testing of their improvements in the presence of the City's
authorized representative. Major system connections to the City's system shall not be
authorized on Fridays. Subsequent operation of system valves must be performed by
City personnel.
PUBLIC UTILITIES CONSTRUCTION AGREEMENT -5-
B. No work shall be performed by the Owner other than Monday through Friday between
7:30 a.m. and 6:00 p.m., exclusive of City holidays, except with written prior consent
of the City. If consent is given by the City for work on Saturday, Sunday or holidays
or before or after the normal working hours above, the Owner shall pay to the City the
reasonable cost of furnishing the required inspection and supervision during said
periods.
C Remove and correct at the expense of the Owner any improvements not authorized or
constructed in compliance with the Utilities Development and Construction Standards.
D. Restore all public and private property disrupted by the installation of the project to its
original condition upon comple~ion. The entire job site will be maintained in a neat and
workman like appearance. The Owner will provide landscape restoration including
sodding seeding or barking as may be required by the City's Project Manager.
Landscape restoration shall follow installation oftbe various segments oftbe project as
closely as is practicable. When, in the opinion oftbe Ci~s Project Manager, landscape
restoration has fallen behind installation of the segments of the project, the Project
Manager may halt all construction work until restoration catches up.
E. Notify the City when the project is ready for final inspection and approval by the
utility.
9. INSPECTION AND FINAL ACCEPTANCE:
A. The City wilt provide periodic inspection during construction to ensure that the work
complies with plans and City Utilities and Construction Standards for the City.
Inspections by the City shall not relieve the Owner of its responsibility to construct the
project in full accord with the standards of the City. Nor shall inspection be deemed to
be supendsion of the project, methods or means of performance, compliance with
construction site safety requirements, or the Owner's subcontractors or employees.
B. Sewer acceptance requires an initial television inspection of all lines. This inspection
may be conducted by the City for the cost of time and materials or by a private agency.
PUBLIC UTILITIES CONSTRUCTION AGREEMENT -6-
Costs incurred for this inspection shall be paid by the Owner following thirty (30) days
written notice.
C. All easements necessary for the project have been obtained in the name of the City,
accepted by the Project Manager, and recorded with the County Auditor.
D. Within thirty (30) days of final inspection, furnish a complete set of mylar record
drawings of the project improvements which have been prepared and stamped by the
Desi~ Engineer.
E Upon final approval of project construction by the City's Project Manager, the City
shall accept and approve a Deed of Conveyance of the project improvements for the
Owner on a form approved by the City Attorney. Approval of the deed shall constitute
completion of the project for the purposes of.'
1. Computing the guarantee period required by this agreement for bonding.
2. Commencement by the City of its usual and customary maintenance of the
project improvements.
3.Commencement of sewer or water services upon payment of service fees.
10. REIMBURSEMENT AGREEMENT: If this agreement is for the construction of either
water or sewer line, the City agrees to arrange for a partial reimbursement to be made to the
Owner for the cost of the line as permitted by state law and the municipal code.
Reimbursement shall be subject to reasonable charges by the City for administration and shall
be payable only if the Owner executes a City Reimbursement Agreement and fries the same
with the County Auditor as a lien on properties to be served in the future by the water or sewer
line.
11. NON-COMPLIANCE: Failure to comply with the terms of this agreement within 60 days
following written notice by the Project Manager shall automatically result in the termination of
service and forfeiture of bonds and shall not relieve the Owner of the duty to comply with all
the terms of this agreement, paying all sums due thereunder together with reasonable attomey's
fees incurred by the City in enforcing the terms of this agreement.
PUBLIC UTILITIES CONSTRUCTION AGREEMENT -7-
OWNER: HMI/Bob Ohman
Mailing Address: P.O. Box 4999
Bremerton, WA 9831
Telephone Number: '.~D~5'- ~?~0~
EXECUTED this..z~ of~z.~, 19 q~
CITY OF BREMERTON:
L~ HOI~TON, Mayor
1)EP~ APPROVAL:
W. EUGENE SAM ~, Director of Public Works and Utilities
AI~PROVEI) AS TO FORM:
GLENNA MALANCA, City Attorney
~] HSPTPUCADOC
PUBLIC UTILITIES CONSTRUCTION AGREEMENT -8-