PUBLIC UTILITIES CONSTRUCTION AGREEMENT
The City of Bremerton, a first class municipal corporation of the State of Washington, (hereinafter
"City") and Victor Targett (hereina~er "Constructor"), in consideration of the mutual covenants
herein defined, enter imo this agreement for the construction and public dedication of a sewer main
(hereinafter "Project") in accordance with the following terms and conditions. The Constructor will
retain a licensed Professional Engineer registered in the State of Washington (hereina~er "Design
Engineer") who shall design the Project.
1. DESCRIPTION OF THE PROJECT: The project to be constructed by the Constructor
and dedicated to the City for public use, consists ot~
Approximately 110 linear feet of 8" PVC class 35 SDR 3034 sewer pipe, one manhole
assembly, and a clean out assembly.
The Project is more fully described in the plans and specifications incorporated by reference
herein.
2. FEES AND EXPENSES:
A. The Constructor agrees to pay in advance the following fees and expenses associated
with the project and required by the Bremerton Municipal Code:
· Design and construction engineering services $ N/A
· Plan check and inspection fees - plan check-S154, insp. - $300.00 $ 454.00
· Total parcel FFF $ N/A
Payment of appropriate General Facilities Fees and Front Footage Fees will be required prior
to redeving utility service fi.om the City. (per lot cost - $177.89 per unit & $40.00 lateral
inspection fee)
PUBLIC UTILITIES CONSTRUCTION AGREEMENT -1-
3i00 ~SE Street
sewer extension
5. The bond must be approved by the City's Risk Manager and may include one
or more surety bonds issued by any surety company licensed to do business in
the State of Washington. The Surety bond may be substituted by a cash
deposit in the full required mount deposited with the City Treasurer or an
assignment of funds on deposit in a licensed bank or credit union, in the full
required amount.
3. REPRESENTATIVES: lhe Constructor hereby names the following person as the
representative of the Con7 tbr all purposes required by this agreement:
The Constructor warrants that the Constructor's representative has flail authority to bind the
Constructor in all respects required by this agreement, and all applicable government
requirements imposed by any agency with jurisdiction.
The City hereby designates Ned Lever, P.E. , of its Department of Public Works and Utilities
as its Project Manager and warrants that the Project Manager has flail authority to exercise
such discretion as does the Director of Public Works and Utilities under the ordinance of the
City lbr purpose of caring out the terms of this agreement.
4. PROJECT DESIGN: The Constructor will retain a licensed Professional En~neer who shall
design the project, prepare the necessary plans, and provide construction engineering to the
extent reasonably necessary.
PUBLIC UTILITIES CONSTRUCTION AGREEMENT -3-
3100 ~st Street
sewer extension
6. INSURANCE AND INDEMNITY: The Constructor shall provide liability and property
damage insurance covering all work under this agreement for construction within the public
ri,grit-of-way, including all work provided by the Constructor and its Contractors. Said
insurance shall name the City of Bremerton as additional insured and provide the following
limits:
- Bodily injury~ $1,000,000.00 each person;
- $1~000,000.00 each accident;
- Property damage~ $500~000.00
Evidence of such insurance shall be provided to the Risk Manager prior to issuance of the
Public Works Project Permit. The Constructor shall hold harmless the City of Bremerton, its
elected officials, employees, and agents, for all liabilities and claims arising out of or related to
performance of the work identified in this agreement.
7. PROSECUTION OF WORK:
A. Construction of the project shall be initiated within one (I) year of execution o£this
agreement by the Constructor and within 30 days of issuance of the Project Permit.
Failure to be~n work within the one year limit shall result in forfeiture of all
Constructor's rights under the agreement regardless of any other provisions of this
agreement.
B. Constructor a~'ees to continuously pursue work and complete the project within six
(6) months of permit issuance.
8. ADDITIONAL CONSTRUCTION WORK REQUIREMENTS: The Constructor in
addition to other duties included in this agreement shall comply with the following:
A. Schedule system connections with the Project Manager and meet all requirements for
the connection and testing of their improvements in the presence me the City's
authorized representative. Major system connections to the City's system shall not be
authorized on Ffidays. Subsequent operation of system valves must be performed by
City personnel.
PUBLIC UTILITIES CONSTRUCTION AGREEMENT -5-
3i00 ls~ Street
sewer ~xtension
B. No work shall be performed by the Constructor other than Monday through Friday
between 7:30 a.m. and 6:00 p.m., exclusive of City holidays, except with written prior
consent of the City. If consent is given by the City for work on Saturday, Sunday or
holidays or before or after the normal working hours above, the Constructor shall pay
to the City the reasonable cost of furnishing the required inspection and supervision
during said periods.
C. Remove and correct at the expense of the Constructor any improvements not
authorized or constructed in compliance with the Utilities Development and
Construction Standards.
D. Restore all public and private property disrupted by the installation of the project to its
original condition upon completion. The entire job site will be maintained in a neat and
workman like appearance. The Constructor will provide landscape restoration
including sodding, seeding or barking as may be required by the Citb"s Project
Manager. Landscape restoration shall follow installation of the various segments of the
project as closely as is practicable. When, in the opinion of the City's Project Manager,
landscape restoration has fallen behind installation of the segments of the project, the
Project Manager may halt all construction work until restoration catches up,
E Noti'_~ the City when the project is ready tbr final inspection and approval by the
Utility.
9. INSPECTION AND FINAL ACCEPTANCE:
A The City will provide periodic inspection during construction to ensure that the work
complies with plans and City Utilities and Construction Standards for the City.
Inspections by the City shall not relieve the Constructor of its responsibility to
construct the project in full accord with the standards of the City. Nor shall inspection
be deemed to be supervision of the project, methods or means of performance,
compliance with construction site safety requirements, or the Constructor's
subcontractors or employees.
PUBLIC UTILITIES CONSTRUCTION AGREEMENT -6-
3100 1st Street
sewer extension
Sewer acceptance requires an initial television inspection of all lines. This inspection
may be conducted by the City for the cost of time and materials or by a private agency.
Costs incurred for this inspection shall be paid by the Constructor following thirty (30)
days written notice.
C. All easements necessary for the project have been obtained in the name of the City,
accepted by the Project Manager, and recorded with the County Auditor.
D. Within thirty (30) days of final inspection, fi~mish a complete set of mylar record
drawings of the project improvements which have been prepared and stamped by the
Design Engineer.
E. Upon final approval of project construction by the City's Project Manager, the City
shall accept and approve a Deed of Conveyance of the project improvements for the
Constructor on a tbrm approved by the City Attorney. Approval of the deed shall
constitute completion of the project for the purposes ot2
I. Computing the guarantee period required by this agreement for bonding.
2. Commencement by the City of its usual and customary maintenance of the
project improvements.
3. Commencement of sewer or water services upon payment of service fees.
10. REIMBURSEMENT AGREEMENT: If this agreement is for the construction of either
water or sewer line. the City agrees to arrange for a partial reimbursement to be made to the
Constructor for the cost of the line as permitted by state law and the municipal code.
Reimbursement shall be subject to reasonable charges by the City for administration and shall
be payable only if the Constructor executes a City Reimbursement Agreement and files the
same with the County Auditor as a lien on properties to be served in the future by the water or
sewer line.
PUBLIC UTILITIES CONSTRUCTION AGREEMENT -7-
3100 Ist Street
sewer extension
11. NON-COMPLIANCE: Failure to comply with the terms of this agreement within 60 days
following written notice by the Project Manager shall automatically result in the termination of
service and forfeiture of bonds and shall not relieve the Constructor of the duty to comply with
all the terms of this agreement, paying all sums due thereunder together with reasonable
attorney's fees incurre,,~py.~ the City in, enforcing the terms of this agreement.
Mai ling Address: Victor Targett
9414 Ridgetop Blvd. NW
Silverdale, Wa. 98383
Telephone No.: (360) 692-9777
EXECUTED this~day of ~/~ , 19~,~
PUBLIC UTILITIES CONSTRUCTION AGREEMENT -8-
3100 1st Street
sewer extension
CITY OF BREMERTON:
L~rN HORTON, Mayor
DEPARTMENTAL APPROVAL:
~¢--W. EUGENE SAMPLEY, Director of Public Works and Utilities
ATTEST:
KATHLEEN McCLUSKEY, Clerk
APP~V/ED AS TO FORM:
lan Sievers, City Attomey
PUBLIC UTILITIES CONSTRUCTION AGREEMENT -9-