CHANGE Contract Transactions
Contract Number 4372
+
~Vendor Name STAN PALMER CONSTRUCTION INC
~Subject W650 PRESSURE ZONE - WATER MAINS ULID 2002-01
~Department ENGINEERING
~Status Code CON
Amount $1716294.68
Begin Date 06/27/2003
Insurance End Date 03/31/2004
Type Amount Review Date 02/15/2007
+ GL $2oooooo.oo
+ AL $1OOOOOO.OO
Insurance Total $3000000.00
Insurance Review Date 07/01/2003
+
Comments CHANGE ORDER #1-11/03 #2-11/03 ~3-1/05 #4-1/05
VAULT 01/01/2007
+
CITY OF BREMERTON
CHANGE ORDER
CONTRACT CHANGE ORDER NO: 4
PROJECT NAME: W-650 Pressure Zone Improvements and Distribution Main
PROJECT NO: 436 CONTRACTOR: Stan Palmer Construction
ORIGINAL CONTRACT AMOUNT: $1,686,160.52 DAYS: 170
PREVIOUSLY APPROVED CHANGES: $23,835.09 DAYS: 0
THIS CHANGE: $6,299.07 DAYS: 0
REVISED CONTRACT AMOUNT: $1,716,294.68 DAYS: 0
This Change Order covers changes to the subject contract as described herein. The Contractor shall
construct, furnish equipment and materials, and perform all work as necessary or required to
complete the Change Order Items. The increase or decrease in contract price shown below includes
any applicable taxes.
DESCRIPTION OF CHANGES INCREASE IN (DECREASE) IN CONTRACT
CONTRACT CONTRACT TIME
AMOUNT AMOUNT EXTENSION
($) ($) (DAYS:)
Installation of fiber optic cable, includes connection at terminal $5805.59 0 0
ends and testing (ref Stan Palmer X-103 and X-104)
Tax
$493~48
NET CHANGE IN CONTRACT AMOUNT $6299.07 6 0
INCREASE OR (DECREASE)
Contractor acknowledges and accepts that this Change Order constitutes final settlement of all claims
of any kind or nature arising from or connected with any work either covered or affected by this
Change Order, including, without limitation, claims related to contract time, on-site or home office
overhead, or lost profits. Nothing in this Change Order shall limit the City's right to bring a claim for
past performance.
The undersigned Contractor approves the foregoing Change Order as to the changes, if any, in the
contract price specified for each item, including any and all supervision costs and other miscellaneous
CONTRACT CHANGE ORDER NO:
PROJECT NAME:
costs relating to the change in work, and as to the extension of time allowed, if any, for completion of
the entire work due to said Change Order.
This document will become a supplement of the contract and ali provisions will apply hereto. It is
understood that this Change Order shall be effective when approved by the City of Bremerton.
The parties whose names appear below warrant that they are authorized to enter into a change order
that is binding on the parties of this contract. In addition, Contractor warrants that it has or will inform
the surety of this change, and shall take appropriate action to modify any bonds required under the
contract to address this change.
PROJECT ENGINEER '/ /Date
CITY ENGINEER / DIRECTOR OF PUBLIC WORKS /' Date
ACCEPTED: ~"
COIqTR,IkC"rO ~ ' -
MAYOR Date
APPROVED AS TO FORM: ATTEST,.-,
Brementon City Attorney '~'~ty- C'[e-r~',~'
/
Page 2 of 2
CITY OF BREMERTON
CHANGE ORDER
CONTRACT CHANGE ORDER NO: 3
PROJECT NAME: W-650 Pressure Zone Improvements and Distribution Main
PROJECT NO: 436 CONTRACTOR: Stan Palmer Construction
ORIGINAL CONTRACT AMOUNT: $1,686,150.52 DAYS: 170
PREVIOUSLY APPROVED CHANGES: $12,120.37 DAYS: 0
THIS CHANGE: $11,7t4.72 DAYS: 0
REVISED CONTRACT AMOUNT: $1,709,995.61 DAYS: 0
This Change Order covers changes to the subject contract as described herein. The Contractor shall
construct, furnish equipment and materials, and perform all work as necessary or required to
complete the Change Order Items. The increase or decrease in contract price shown below includes
any applicable taxes.
DESCRIPTION OF CHANGES INCREASE IN (DECREASE) IN CONTRACT
o ,,- CONTRACT CONTRACT TIME
~- ,- AMOUNT AMOUNT EXTENSION
= = ($) ($) (DAYS:)
X Additional grading on the service road Schedule A (ref Start $222.17 0
Palmer Construction X-14)
X Re-pressure D-line after thrust thrust block Schedule A (ref Start $331.66
Palmer Construction X-15)
X Hydroseed Schedule A (ref Stan Palmer Construction X-17) $7759.92
X Repair at D-line drainage Schedule A (ref Start Palmer $258.91
Construction X-18)
X Ditch grading at PRV curtain drain Schedule A (ref Stan Palmer $1661.68
Construction X-019)
X Replace 6" Storm line at Adult Center Schedule A (ref Start $389.51
Palmer Construction X-020)
X Expose 2" Conduit at the top of hill Schedule A (ref Stan Palmer $173.14
Construction X-21)
Tax $917.74
NET CHANGE IN CONTRACT AMOUNT
INCREASE OR (DECREASE) $11,714.72 0 0
Contractor acknowledges and accepts that this Change Order constitutes final settlement of all claims
of any kind or nature arising from or connected with any work either covered or affected by this
Chanae Order. includina, without limitation, claims related to contract time. on-site or home office
CONTRACT CHANGE ORDER NO: 3
PROJECT NAME: W-650 Pressure Zone Improvements and Distribution Main~
overhead, or lost profits. Nothing in this Change Order shall limit the City's right to bring a claim for
past performance.
The undersigned Contractor approves the foregoing Change Order as to the changes, if any, in the
contract price specified for each item, including any and all supervision costs and other miscellaneous
costs relating to the change in work, and as to the extension of time allowed, if any, for completion of
the entire work due to said Change Order.
This document will become a supplement of the contract and all provisions will apply hereto. It is
understood that this Change Order shall be effective when approved by the City of Bremerton.
The parties whose names appear below warrant that they are authorized to enter into a change order
that is binding on the parties of this contract. In addition, Contractor warrants that it has or will inform
the surety of this change, and shall take appropriate action to modify any bonds required under the
contract to address this change.
PROJECT ENGINEER / I~ate
CITY ENGINEER ! DIRECTOR OF PUBLIC WORKS Date
ACCEPTED:
CONTRACTOR Date
MAYOR Date
APPROVED AS TO FORM: ATTEST:
Bremerton City Attorney zC'ity Clerl~
Page 2 of 2
IEnter Search Criteria, Press Esc Key to Transmit
Press Del Key to Terminate Delete Mode
CHANGE Contract Transactions
I~ Contract Number 4372
:Vendor Name STAN PALMER CONSTRUCTION INC
Subject W650 PRESSURE ZONE - WATER MAINS ULID 2002-01
tDepartment ENGINEERING
~Status Code CON
Amount $1698280.89
Begin Date 06/27/2003
Insurance End Date 12/31/2003
Type Amount Review Date 02/15/2006
AL $1000000.00
Insurance Total $3000000.00
Insurance Review Date 07/01/2003
+
Comments CHANGE ORDER #1 - 11/03/#2 - 11/03
VAULT 01/01/2006
+
CONTRACT CHANGE ORDER NO: 2
PROJECT NAME: W-650 Pressure Zone Improvements Transmission and Distribution Main
SALES TAX 8.5% 379.00
TOTAL 4837.82
Contractor acknowledges and accepts that this Change Order constitutes final settlement of all claims
of any kind or nature adsing from or connected with any work either covered or affected by this
Change Order, including, without limitation, claims related to contract time, on-site or home office
overhead, or lost profits. Nothing in this Change Order shall limit the City's right to bdng a claim for
past performance.
The undersigned Contractor approves the foregoing Change Order as to the changes, if any, in the
contract price specified for each item, including any and all supervision costs and other miscellaneous
costs relating to the change in work, and as to the extension of time allowed, if any, for completion of
the entire work due to said Change Order.
This document will become a supplement of the contract and all provisions will apply hereto. It is
understood that this Change Order shall be effective when approved by the City of Bremerton.
The parties whose names appear below warrant that they are authorized to enter into a change order
that is binding on the paAies of this contract. In addition, Contractor warrants that it has or will inform
the surety of this change, and shall take appropriate action to modify any bonds required under the
contract to address this change.
I~JE~(~T EN{~II~-EER / Dat~
~IT~-EN(~INEER /DIRECTOR OF PUBLIC WORKS / Dat~
CONI /l~ate
MAYOR ~ Date'
APPROVED AS TO FORM: ATTEST:
Bremerton City Attorney ~"C'ity (~1~i~"" "--- ! y- /
Page 2 of 2
~Press Esc Key to Insert new record, Ctrl-Z to Clear form
Press Del Key to Terminate Insert Mode
INSERT Contract Maintenance
Contract Number 4372
Vendor Name STAN PALMER CONSTRUCTION INC
=Subject W650 PRESSURE ZONE - WATER MAINS ULID 2002-01
·Department ENGINEERING
=Status Code CON
Amount $1686160.52
Begin Date 06/27/2003
Insurance End Date 12/31/2003
Type Amount Review Date 12/01/2003
Press FI for GL $2000000.00
valid insuranceAL $1000000.00
type codes
Insurance Total $3000000.00
Insurance Review Date 07/01/2003
i Comments
Enter Search Criteria, Press Esc Key to Transmit
Press Del Key to Terminate Delete Mode
CHANGE Contract Transactions
Contract Number 4372
~Vendor Name STAN PALMER CONSTRUCTION INC
~Subject W650 PRESSURE ZONE - WATER MAINS ULID 2002-01
~Department ENGINEERING
~Status Code CON
Amount $1698280.89
Begin Date 06/27/2003
Insurance End Date 12/31/2003
Type Amount Review Date 02/15/2006
GL $2000000.00
AL $1000000.00
iInsurance Total $3000000.00
Insurance Review Date 07/01/2003
Comments CHANGE ORDER #1 - 11/03/~2 - 11/03
VAULT 01/01/2006
+
CITY OF BREMERTON
CHANGE ORDER
CONTRAlto: 1
PROJECT NAME: W-650 Pressure Zone Improvements Transmission an~-Distribution Main
PROJECT NO: 436 CONTRACTOR: Stan Palmer Construction
ORIGINAL CONTRACT AMOUNT: $1,686,160.52 DAYS: 17(%.
PREVIOUSLY APPROVED CHANGES: 0.00 DAYS: 0
THIS CHANGE: $7661.55 DAYS: 0
REVISED CONTRACT AMOUNT: $1,693,822.07 DAYS: 170
This Change Order covers changes to the subject contract as described herein. The Contractor shall
construct, furnish equipment and materials, and perform all work as necessary or required to
complete the Change Order Items. The increase or decrease in contract price shown below includes
any applicebJe taxes.
DESCRIPTION OF CHANGES iNCREASE IN (DECREASE) IN CONTRACT
o ,- CONTRACT CONTRACT TIME
~- ,- AMOUNT AMOUNT EXTENSION
· e ($) ($) (DAYS:)
~, ~y
X Repair abandoned water service at sta. 3+19 schedule A 431.75 0
(ref. Start Palmer Construction X-01)
X Repair unlocated abandoned water service at sta 11+00 1643,61
Schedule A
(ref.. Satan Palmer Construction X-02)
X Removal of fence for fire hydrant installation Schedule A 573.44
(ref. Start Palmer Construction X-04)
X Additional Patch on Linden Schedule A 376.00
(ref. Start Palmer Construction X-07)
X Remove broken curb on Linden Schedule A 118.28
(ref Start Palmer Constm~on X-010
X Additional tie in expense at Linden and Union Schedule A 3918.26
(ref. Start Palmer Construction X-100)
NET CHANGE IN CONTRACT AMOUNT 706'1.34
INCREASE OR (DECREASE)
SALES TAX 8.5% 600.21
TOTAL 7661.55
CITY OF BREMERTON
CHANGE ORDER
CONTRACT CHANGE ORDER NO: 2
PROJECT NAME: W-650 Pressure Zone Improvements Transmission and Distribution Main
PROJECT NO: 436 CONTRACTOR:Stan Palmer Construction
ORIGINAL CONTRACT AMOUNT: $1,686,160.52 DAYS: 170
PREVIOUSLY APPROVED CHANGES: $7661.55 DAYS: 0
THIS CHANGE: $4458.82 DAYS: 0
REVISED CONTRACT AMOUNT: $1,698,280.89 DAYS: 0
This Change Order covers changes to the subject contract as described herein. The Contractor shall
construct, furnish equipment and materials, and perform all work as necessery or required to
complete the Change Order Items. The increase or decrease in contract price shown below includes
any applicable taxes.
DESCRIPTION OF CHANGES INCREASE IN (DECREASE) IN CONTRACT
o ,- CONTRACT CONTRACT TIME
~- ,- AMOUNT AMOUNT EXTENSION
e · ($) ($) (DAYS:)
Pothole for unmarked forcemain and re-lay 12'DJ water pipe 1690.41 0
Schedule B (ref Stan Palmer Construction X-009)
Pothole for mismarked water service at 5842 Wemer Road
Schedule B (ref. Start Palmer Construction X-008) 219.52
Additional labor to hand dig and avoid undocumented tee
Schedule B (ref Stan Palmer Construction X-006) 234.68
Locate unmarked water stub Schedule B (ref. Stan Palmer
Construction X-005) 105.22
Pothole on Nollwood for the City to find forcemain sewer
Schedule B (ref. Stan Palmer Construction X-003) 106.35
Remove valve at sta 40+35 Schedule B (ref. Stan Palmer
Construction X-016) 1188.57
Lost time for valve closure Schedule B (ref. Start Palmer
Construction X-013) 178.37
Reset 12 foot gate Schedule B (ref> Stan Palmer Construction
X-012) 213.64
Excavate for additional air vac Schedule B (ref Slan Palmer X-
011) 522.06
NET CHANGE IN CONTRACT AMOUNT 4458.82