HomeMy WebLinkAbout1_-_Original_Submission__exhibit_a_final.docx2025 Project Timeline Specific Tasks Start Date End Date Receipt of Award Letter for Funding Authorization from CDBG 12/1/25 12/31/2025 Environmental Review and NEPA Certification 01/01/2026 Contract Execution 4/20/2026 5/31/2026 Pre Repair/Construction 4/20/2026 5/31/2026 Repair/Construction 6/1/2026 Contract Closeout 4/30/2027 List the specific tasks to complete and manage this project, including the start and end dates for each task. The tasks include such things as obtaining other funding/financing, bidding process, identifying clients, marketing, planning and permit process, construction, environmental review, rent-up or project completion, site control, market studies, relocation, community meetings (if applicable). Docusign Envelope ID: 62E11585-A60F-85C1-8080-3B5AB7A51A21Docusign Envelope ID: 16000D54-01E9-8036-8091-B26AC80BC333