Loading...
HomeMy WebLinkAbout1_-_Original_Submission__Exhibit_A_Timeline_20252025 Project Timeline Specific Tasks Start Date End Date Receipt of Award Letter for Funding Authorization from CDBG 12/1/25 12/31/2025 Environmental Review and NEPA Certification 01/01/2026 NTP / Mobilization / Utility Locates 1/2/2026 2/2/2026 Construction 2/2/2026 6/30/2026 Project Closeout 7/1/2026 7/31/2026 List the specific tasks to complete and manage this project, including the start and end dates for each task. The tasks include such things as obtaining other funding/financing, bidding process, identifying clients, marketing, planning and permit process, construction, environmental review, rent-up or project completion, site control, market studies, relocation, community meetings (if applicable). Docusign Envelope ID: 7D42CC04-2C5F-8237-80EA-66598D4C49EE