HomeMy WebLinkAbout1 - Original Submission_ 060922_ CM #03Page 1 of 2 Contract Modification Rev. 09/2021
CONTRACT MODIFICATION AGREEMENT NO. 003 to CITY CONTRACT # 5972 BETWEEN THE CITY OF BREMERTON AND KPFF CONSULTING ENGINEERS PROJECT East 11th Street and Perry Avenue Complete Streets Improvement Project #315018
CONSULTANT KPFF Consulting Engineers DATE May 27, 2022 THIS CONTRACT MODIFICATION AGREEMENT SPECIFICALLY AMENDS THE CONSULTANT AGREEMENT (the "Contract") entered into between the City of Bremerton and KPFF Consulting Engineers on April 16, 2019 and as modified on January 1,
2021 on Contract Modification #001 and again modified on June 10, 2021 on Contract Modification #002.
All provisions in the Contract shall remain in full force and effect except as expressly modified
by this document. For valuable consideration and by mutual consent of the parties, the modifications to the Contract are as follows:
I.
Section I. Scope , is modified as follows: See Amended Scope of Work attached as Exhibit A
Section II. Term , is modified as follows:
The Consultant shall complete the work described in this Contract Modification Agreement by No Change. Section III. Compensation , is modified as follows:
The original contract amount was $ 534,002.58. The current contract amount, including all previous amendments is $ 743,916.73. The City shall pay the Consultant for the additional work described above, based on time and materials, an amount not to exceed $ 20,045.54 for a total amended contract amount of $ 763,962.27 , including this Contract Modification.
II.
Consultant accepts all requirements of this Contract Modification by endorsing below. Consultant further agrees that this Contract Modification constitutes full and final settlement of all of the Consultant’s claims for contract time and for all costs of any kind,
including without limitation, costs of delays related to any work either covered or affected by this Contract Modification, claims related to on-site or home office overhead, or lost
DocuSign Envelope ID: A1E742B4-2A47-482D-8BB8-F16AB2483A5D
Page 2 of 2 Contract Modification Rev. 09/2021
profits. This Contract Modification does not limit the City’s right to bring a claim for past performance.
The undersigned consultant approves the foregoing Contract Modification as to the changes, if any, in the contract price specified for each item, including any and all supervision costs and other miscellaneous costs relating to the change in work, and as to the extension of time allowed, if any, for completion of the entire work due to said Contract Modification.
This document will become a supplement of the contract and all provisions will apply hereto. It is understood that this Contract Modification shall be effective when approved by the City of Bremerton.
The parties whose names appear below warrant that they are authorized to enter into a contract modification that is binding on the parties of this contract. In addition, Consultant warrants that it has or will inform the surety of this change, and shall take appropriate action to modify any bonds required under the contract to address this change.
IN WITNESS WHEREOF, the parties have executed this Contract Modification on the day and year first written above.
City Engineer / Public Works Director approved to process _________________________ (Initials and Date)
CONSULTANT THE CITY OF BREMERTON
By: By: Print Name: Print Name: Greg Wheeler
Its: Its: Mayor_____________________
Date: Date:
APPROVED AS TO FORM: ATTEST:
By: By: KYLIE J. FINNELL, Bremerton City Attorney ANGELA HOOVER, City Clerk
NOTICES TO BE SENT TO: NOTICES TO BE SENT TO:
Ron Leimkuhler Vicki Grover Principal Engineering Project Manager
KPFF Consulting Engineers City of Bremerton
1601 5th Avenue, Suite 1600 345 6th Street Suite 100 Seattle, WA 98101 Bremerton, WA 98337
R:\Legal\Legal\Forms\FORMS ON COBWEB\Contract Modification Rev. 09 2021.docx
Ned Lever
Digitally signed by Ned LeverDN: C=US, E=ned.lever@ci.bremerton.wa.us, O=City of Bremerton, OU=Engineering, CN=Ned Lever
Reason: I have reviewed this documentDate: 2022.06.13 10:09:21-07'00'
DocuSign Envelope ID: A1E742B4-2A47-482D-8BB8-F16AB2483A5D
6/16/2022
RJL
Ron Leimkuhler
6/16/2022
EAST 11TH STREET AND PERRY AVENUE
DESIGN SCOPE OF WORK
AMENDMENT 3
This amendment supplements the existing CONSULTANT agreement with the City of Bremerton for
the East 11th Street and Perry Avenue project.
Services performed under this amendment will be invoiced at current consultant rates.
EXHIBIT A
DocuSign Envelope ID: A1E742B4-2A47-482D-8BB8-F16AB2483A5D
Task 1: Project Management
Add the following section.
1.5 Contract Administration – Construction Phase
The CONSULTANT shall develop and manage the project scope, schedule, and budget and execute
contract administration activities as needed to complete the scope of work during the Bid
advertisement phase of the project.
Monthly invoices for work completed to date shall be submitted to the City with cost tracking at the
Task Level.
The CONSULTANT shall prepare SUBCONSULTANT contracts and manage SUBCONSULTANTS to
ensure accurate and timely implementation of the work plan and the appropriate coordination of work
activities, including the review of all SUBCONSULTANTS’ work on various project elements. In
addition, the CONSULTANT shall conduct reviews of SUBCONSULTANTS’ progress and invoices.
Assumption(s):
1. Bid advertisement period services will last 2 invoicing cycles
Deliverable(s):
1. Scope, schedule, and budget updates as warranted (electronic PDF)
2. Monthly progress report summary (electronic PDF)
3. Monthly invoices (electronic PDF)
DocuSign Envelope ID: A1E742B4-2A47-482D-8BB8-F16AB2483A5D
Task 4: PS&E Design
Add the following section.
4.11 Bid Support Services
The CONSULTANT shall support the City during bidding periods, including addendum production.
·Up to five addendums will be produced by the Consultant.
·Up to ten questions will be responded to in writing.
Assumption(s):
1. Bid period will be four – 6 weeks
Deliverable(s):
1. Written responses to bidder questions
2. Addendum PS&E documents including:
a. Addendum notification documentation and instructions
b. Updated Plans
c. Updated Specifications and project manual materials
d. Updated Estimates
3. Bidding support services as needed by the City within the approved budget
DocuSign Envelope ID: A1E742B4-2A47-482D-8BB8-F16AB2483A5D
City of Bremerton - East 11th and Perry Project
Amendment 3 Proposed Fee
Total
Task Task Name Fee KPFF HDR HBB
1.5 Contract Administration 1,774.33$ 1,500.00$ 274.33$
4.1 Bid Support Services 16,448.89$ 15,645.00$ 803.89$
Sub total 18,223.22$ 17,145.00$ 1,078.22$
Management Reserve @ 10%1,822.32$
Total=20,045.54$
Prepared by :John McMillan
Date:5/25/2022
Firm
DocuSign Envelope ID: A1E742B4-2A47-482D-8BB8-F16AB2483A5D
Principal
Project
Manager Senior Engineer III
Senior
Engineer II
Senior
Engineer I
Engineer
II Engineer i Cad Lead
CAD
Drafter
Project
Coordinator
Task # Task Name Proposed Fee 215.00$ 185.00$ 190.00$ 180.00$ 145.00$ 115.00$ 100.00$ 127.00$ 77.00$ 95.00$
1.5 Contract Administration 1,500.00$ 4 8
4.1 Bid Support Services 15,645.00$ 10 45 10 10 10 10
Total 17,145.00$ 10.0 49.0 0.0 10.0 10.0 10.0 0.0 0.0 10.0 8.0
REIMBURSABLES
Item Quantity Unit Unit Cost Totals
KPFF Travel / Ferry Allowance LS -$
Notes: Rates updated to 2022 KPFF all inclusive rates
Assumes
Task 1.5
2 invoices 2 hours PM and 4 hours Project Coordinator
Task 4.1
5 amendments Each amendment 1 hour Principal - 8 hours PM, 2 hours Senior Engineer II, I, Engineer II, 2 hours CAD
5 responses to questions 1 hr. PM for each
Prepared by John McMillan
5/25/2022
2022 all inclusive Rate
Principal 215.00$
Project Manager 185.00$
Senior Engineer III 190.00$
Senior Engineer II 180.00$
Senior Engineer I 145.00$
Engineer II 115.00$
Engineer i 100.00$
Cad Lead 127.00$
CAD Drafter 77.00$
Project Coordinator 95.00$
KPFF Bremerton East 11th and Perry Amendment 3 Hour Fee Back Up
DocuSign Envelope ID: A1E742B4-2A47-482D-8BB8-F16AB2483A5D
Fee Proposal
East 11th & Perry
Hough Beck & Baird
Description Notes Principal
Project
Manager Design Staff
Comp. Tech
Staff
Business
Management Total Hours
Total Direct
Salary Cost
Task 1 Project Management
1.5 Contract Administration - Bid Phase 1 1 2 274.33$
Task 4 PS&E Design
4.10 Bid Support Services 1 2 1 4 8 803.89$
1 3 1 4 1 10 1,078.22$
168.65$ 148.41$ 98.94$ 80.95$ 125.92$ Sub-Totals
84.33$ 445.23$ 98.94$ 323.80$ 125.92$ 1,078.22$
Hough Beck & Baird Total Project Costs 1,078$
Amendment 3
4/26/2022
Total Hours per person
Current Hourly Rates
Direct Salary Cost (DSC)