HomeMy WebLinkAbout1 - Original Submission_ 090822_315032_SCJ CM#001CONTRACT MODIFICATION AGREEMENT NO. 001 To CITY CONTRACT # 6263 BETWEEN THE CITY OF BREMERTON AND SHEA CARR & JEWELL, Inc. (dba SCJ Alliance) PROJECT: Warren Avenue Bridge Pedestrian Improvements CONSULTANT: Shea Carr & Jewell, Inc. (dba SCJ Alliance) DATE September 1, 2022 THIS CONTRACT MODIFICATION AGREEMENT SPECIFICALLY AMENDS THE Professional Services AGREEMENT (the "Contract") entered into between the City of Bremerton and Shea Carr & Jewell, Inc. (dba SCJ Alliance)on August 10, 2021. All provisions in the Contract shall remain in full force and effect except as expressly modified by this document. For valuable consideration and by mutual consent of the parties, the modifications to the Contract are as follows: I. Section I. Scope , is modified as follows: See Amended Scope of Work attached as Exhibit A Section II. Term , is modified as follows: The Consultant shall complete the work described in this Contract Modification Agreement by Extended thru February 28, 2023. Section III. Compensation , is modified as follows: The original contract amount was $ 255,435.38. The City shall pay the Consultant for the additional work described above, based on time and materials, an amount not to exceed$ 1 for a total amended contract amount of $ , including this Contract Modification. II. Consultant accepts all requirements of this Contract Modification by endorsing below. Consultant further agrees that this Contract Modification constitutes full and final settlement of all of the Consultant’s claims for contract time and for all costs of any kind, including without limitation, costs of delays related to any work either covered or affected by this Contract Modification, claims related to on-site or home office overhead, or lost profits. This Contract Modification does not limit the City’s right to bring a claim for past performance. Page 1 of 2 Contract Modification Rev. 09/2021 DocuSign Envelope ID: 56E31058-AB91-4A0D-86DB-96732F10BBBB Page 2 of 2 Contract Modification Rev. 09/2021 The undersigned consultant approves the foregoing Contract Modification as to the changes, if any, in the contract price specified for each item, including any and all supervision costs and other miscellaneous costs relating to the change in work, and as to the extension of time allowed, if any, for completion of the entire work due to said Contract Modification. This document will become a supplement of the contract and all provisions will apply hereto. It is understood that this Contract Modification shall be effective when approved by the City of Bremerton. The parties whose names appear below warrant that they are authorized to enter into a contract modification that is binding on the parties of this contract. In addition, Consultant warrants that it has or will inform the surety of this change, and shall take appropriate action to modify any bonds required under the contract to address this change. IN WITNESS WHEREOF, the parties have executed this Contract Modification on the day and year first written above. City Engineer / Public Works Director CONSULTANT THE CITY OF BREMERTON By:By: Print Name: Scott Sawyer Print Name: Greg Wheeler________ Its: Principal Its: Mayor Date:Date: APPROVED AS TO FORM: ATTEST: By:By: KYLIE J. FINNELL, Bremerton City Attorney ANGELA HOOVER, City Clerk NOTICES TO BE SENT TO: NOTICES TO BE SENT TO: Aaron Knight, P.E. Vicki Grover, P.E. Project Manager Project Manager SCJ Alliance City of Bremerton Engineering Dept. 2727 Hollycroft Street, Suite 230 345 6th Street, Suite 100 Gig Harbor, WA 98335 Bremerton, WA 98337 R:\Legal\Legal\Forms\FORMS ON COBWEB\Contract Modification Rev. 09 2021.docx approved to process (Initials and Date)Ned Lever Digitally signed by Ned Lever DN: C=US, E=ned.lever@ci.bremerton.wa.us, O=City of Bremerton, OU=Engineering, CN=Ned LeverReason: I have reviewed this documentDate: 2022.10.03 15:08:07-07'00' DocuSign Envelope ID: 56E31058-AB91-4A0D-86DB-96732F10BBBB 10/20/2022 10/20/2022 2727 Hollycroft Street, Suite 230 w Gig Harbor, WA 98335 w Office 253.201.0777 w www.scjalliance.com CONTRACT AMENDMENT #1 SCOPE OF WORK AND FEE ESTIMATE for Warren Avenue Bridge Pedestrian Improvements Bremerton, WA Prepared For: Vicki Grover, PE City of Bremerton 345 6th Street, Suite 100 Bremerton, WA 98337 Prepared By: Aaron Knight, PE, Project Manager Date Prepared: September 26, 2022 OVERVIEW The feasibility and alternatives analysis has concluded the evaluation of the four alternatives identified by the City as included in the original scope of work. At the request of the City, five additional alternatives will be developed, three of which will receive a structural evaluation, in addition to other tasks as specified herein. This Contract Amendment adds the following work: 1. Add three additional alternatives to the structural feasibility analysis a. Alternative 2 - 10-foot sidewalk on both sides b. (new) Alternative 7 – 12-foot sidewalk on the west side of the bridge, including a tunnel under SR303 near 18th Street c. (new) Alternative 8 – 10-foot shared use path (14-foot total width) west side of the bridge, including a tunnel under SR303 near 18th Street 2. Preparation of a technical memorandum by Sargent Engineers to summarize Alternative 5 requiring a seismic retrofit for the bridge. 3. Preparation of language in the report document defining Alternative 6 as a bicycle lane on the bridge deck and separated sidewalk. A technical memorandum will be prepared by Sargent Engineers to summarize Alternative 6 requiring a seismic retrofit for the bridge. 4. Add all five of the aforementioned alternatives into the project alternative analysis report. 5. Meetings with Washington Department of Fish and Wildlife to scope the level of effort for addressing impacts to nesting cormorants on the bridge y,//d DocuSign Envelope ID: 56E31058-AB91-4A0D-86DB-96732F10BBBB City of Bremerton Warren Avenue Bridge Pedestrian Improvements Contract Amendment #1 September 26, 2022 Page ii 2727 Hollycroft Street, Suite 230 w Gig Harbor, WA 98335 w Office 253.201.0777 w www.scjalliance.com 6. Additional Public Involvement efforts: a. Increased level of effort for stakeholder and public outreach events resulting from the additional project alternatives. b. Add one (1) additional in-person stakeholder meeting c. Revise one (1) of the community open house events to be in-person instead of virtual 7. Extension of the project duration through February 2023. Management Reserve Request #1 extended the project duration through October 2022, therefore this amendment will add four (4) additional months. This contract amendment will also cover costs already incurred for the following tasks. Note that the schedule impacts on additional project management effort was previously addressed in Management Reserve Request #1 (June 2022). 1.Project Website and Stakeholder Survey Launch: The website launch and stakeholder survey were scheduled to be completed in September 2021, but were delayed until January/February 2022 due to extended City review and scheduling conflicts. The additional effort associated with additional reviews and updates to the deliverables is included. 2.Stakeholder Survey Review: the stakeholder survey was shared by members of the project stakeholder group with the general public. This resulted in approximately 700 additional responses beyond the 30 (or so) anticipated. There was a delay of approximately two months in the project schedule while this data was processed, and the team determined how to proceed. This concluded with the hosting of an additional stakeholder meeting to receive their direction for how to proceed. All assumptions and deliverables included in the original scope of work shall still apply, unless modified herein. DocuSign Envelope ID: 56E31058-AB91-4A0D-86DB-96732F10BBBB City of Bremerton Warren Avenue Bridge Pedestrian Improvements Contract Amendment #1 September 26, 2022 Page 1 of 6 2727 Hollycroft Street, Suite 230 w Gig Harbor, WA 98335 w Office 253.201.0777 w www.scjalliance.com Work Element 1: Project Management This Work Element includes tasks to plan, manage, and administer the work; attend project meetings; and coordinate with subconsultants. The level of effort included in the fee estimate assume four (4) additional months of duration. Task 1 Management Task 1.1 Management: Manage the project by directing and supervising staff and reviewing work for the duration of the project. This management is for the overall work rather than specific tasks. Task 1.2 Schedule and Budget: Periodic updates to the a critical path project schedule to match the scope of work. Task 2 Contract Administration Task 2.1 Progress Billings: Prepare a monthly progress invoice with a summary of work performed. Invoices will show staff hours for each Work Element (i.e., Work Element 1: Project Management). Task 2.2 Filing: Develop a project filing system and maintain project files in one centralized location. Periodically purge draft and redundant documents. Task 2.3 Subconsultant Administration: Execute and administer subconsultant contracts. Review and approve monthly invoices. Task 3 Subconsultant Coordination Task 3.1 Coordination with subconsultants for scheduling, exchanging files, and additional coordination as needed. Task 4 Project Coordination Meetings Task 4.1 Bi-weekly (every other week) progress meetings with City and SCJ project managers. Assume one (1) Consultant staff member for eight (8) additional virtual meetings. Task 4.3 Up to two (2) meetings with the Washington Department of Fish and Wildlife (WDFW) to discuss the level of effort for addressing impacts to nesting cormorants on the bridge and other environmental concerns. Understanding • Project management for the feasibility analysis will be provided through December 2022. Extension of the project timeframe will require a contract amendment. Deliverables • Biweekly Progress Report submitted via email in PDF format. Assume four (4). • Monthly Progress billings submitted via email in PDF format. Assume two (2). • MS Project schedule updates submitted via email in PDF format. DocuSign Envelope ID: 56E31058-AB91-4A0D-86DB-96732F10BBBB City of Bremerton Warren Avenue Bridge Pedestrian Improvements Contract Amendment #1 September 26, 2022 Page 2 of 6 2727 Hollycroft Street, Suite 230 w Gig Harbor, WA 98335 w Office 253.201.0777 w www.scjalliance.com Work Element 2: Survey and Right of Way Determination (by Mtn2Coast) No Changes Work Element 3: Public Involvement Task 1 Interactive Project Website Task 1.1 Interactive Project Website: The level of effort included in the fee estimate accounts work previously completed and documented in the project bi-weekly reports. Task 1.2 Website Updates: extend the project website update/maintenance period through the extension of the contract; duration as specified in the Overview section of this scope of work. Task 2 Stakeholder Meetings for Feasibility Analysis Task 2.3 Stakeholder Survey: The level of effort included in the fee estimate accounts work previously completed and documented in the project bi-weekly reports, including review of additional survey results and hosting of Stakeholder Meeting #2 to review the results of the survey. Task 2.4 Stakeholder Alternative Review Meeting: The level of effort included in the fee estimate accounts for the addition of five (5) additional project alternatives. All other assumptions in the original scope of work apply. This virtual meeting is also referred to as “Stakeholder Workshop #3” and was held on September 12, 2022. Task 2.5 Stakeholder Preferred Alternative Meeting: The level of effort included in the fee estimate accounts for the addition of five (5) additional project alternatives. All other assumptions in the original scope of work apply. This virtual meeting is also referred to as “Stakeholder Workshop #5” and is scheduled for early November 2022. Task 2.6 Stakeholder Criteria Review Meeting: This additional meeting will be conducted to discuss the criteria used as part of the Alternatives Analysis, and receive stakeholder direction for how the criteria should be developed and how the alternatives should be reviewed against the criteria. This in-person meeting is also referred to as “Stakeholder Workshop #4” and is scheduled for late October 2022. DocuSign Envelope ID: 56E31058-AB91-4A0D-86DB-96732F10BBBB City of Bremerton Warren Avenue Bridge Pedestrian Improvements Contract Amendment #1 September 26, 2022 Page 3 of 6 2727 Hollycroft Street, Suite 230 w Gig Harbor, WA 98335 w Office 253.201.0777 w www.scjalliance.com Task 3 Public Meetings for Feasibility Analysis Task 3.1 Public Alternative Review Meeting and Online Open House: Revise this task to assume an in-person open house event located at the Norm Dicks building in Bremerton. Assume four (4) Consultant staff for one (1) meeting. The level of effort included in the fee estimate accounts additional work required to host the in-person open house as opposed to the previously scoped virtual open house and the addition of five (5) additional project alternatives. All other assumptions in the original scope of work apply. This in-person event is also referred to as “Community Open House #1” and is scheduled for late October 2022. Task 3.2 Public Preferred Alternative Presentation: No Changes. This virtual event is also referred to as “Community Open House #2” and is scheduled for late November 2022. Task 4 Council Briefings No Changes Work Element 4: Feasibility and Alternatives Analysis Task 1 Project Background No Changes Task 2 Prepare Alternatives The level of effort included in the fee estimate accounts additional work required to prepare five (5) additional alternatives included in this scope of work. Task 2.1 Develop Alternatives: In addition to the four (4) alternatives developed as part of the original scope of work, develop five (5) additional project alternatives for the bridge crossing and associated off structure improvements. The added alternatives include: a. Alternative 2 - 10-foot sidewalk on both sides b. Alternative 5 – 14-foot shared use path on both sides c. Alternative 6 – Bicycle lane on the bridge deck and separated sidewalk d. (new) Alternative 7 – 12-foot sidewalk on the west side of the bridge, including a tunnel under SR303 near 18th Street e. (new) Alternative 8 – 10-foot shared use path (14-foot total width) west side of the bridge, including a tunnel under SR303 near 18th Street Provide a written description of each alternative. A conceptual sketch and cross section for each alternative will be developed (see Work Element 6). Task 2.2 Alternative Detailed Descriptions: In addition to the four (4) alternatives developed as part of the original scope of work, prepare detailed descriptions for five (5) additional alternatives using the process as outlined in the original scope of work. DocuSign Envelope ID: 56E31058-AB91-4A0D-86DB-96732F10BBBB City of Bremerton Warren Avenue Bridge Pedestrian Improvements Contract Amendment #1 September 26, 2022 Page 4 of 6 2727 Hollycroft Street, Suite 230 w Gig Harbor, WA 98335 w Office 253.201.0777 w www.scjalliance.com Task 3 Screening of Alternatives The level of effort included in the fee estimate accounts additional work required for the screening of the five (5) additional alternatives included in this scope of work. Task 3.1 Screening of Alternatives: Based on stakeholder input during the Stakeholder Alternative Review Meeting, provide a summary of the stakeholder inputs and impacts of proposed alternatives. Revise alternative detailing as required. Work Element 5: Structural Engineering (by Sargent Engineers) The level of effort included in the fee estimate accounts additional work required for the preparation of feasibility analysis for the three (3) additional alternatives included in this scope of work. Task 1 Site Reconnaissance and Data Collection No Changes Task 2 Feasibility & Alternative Analysis The Consultant will prepare conceptual framing designs to support up to three (3) additional alternatives for bridge structure improvements. A technical memorandum will also be provided for “Alternative 5” and “Alternative 6” summarizing the need for extensive strengthening and/or seismic retrofit and determination that they are not feasible; this determination will be made based on the results of the other alternatives analyzed and engineering judgement, no structural analysis will be performed specific to “Alternative 5” or “Alternative 6”. All other assumptions from the original scope of work are unchanged. Task 3 Public Involvement Task 3.1 Public Meetings for Feasibility Analysis: No Changes Task 3.2 Council Briefings for Feasibility Analysis: No Changes DocuSign Envelope ID: 56E31058-AB91-4A0D-86DB-96732F10BBBB City of Bremerton Warren Avenue Bridge Pedestrian Improvements Contract Amendment #1 September 26, 2022 Page 5 of 6 2727 Hollycroft Street, Suite 230 w Gig Harbor, WA 98335 w Office 253.201.0777 w www.scjalliance.com Work Element 6: Conceptual Designs for Feasibility Analysis The level of effort included in the fee estimate accounts additional work required for the preparation of conceptual design for the five (5) additional alternatives identified in Work Element 4, Task 2.1. Task 1 Data Collection No Changes Task 2 Roadway Conceptual Design Task 2.1 Horizontal Layout • Develop 2-dimensional conceptual roadway and shared use path layout for five (5) additional alternative layouts. Show travel lanes, turn lanes, shoulders, curb/gutter, planter, shared use path, sidewalks, and driveways. Curb returns at side streets will match existing street width for side streets. • Develop five (5) additional typical sections. Vertical location of improvements will not be specified, however anticipated wall locations will be included. Task 2.2 Conceptual Design Technical Memorandum: Revise the conceptual design technical memorandum to include the five (5) additional alternatives. Task 2.3 Conceptual Design Cost Estimate: Develop cost estimations for the five (5) additional alternatives. Understandings •Warren Avenue (SR 303) is a Urban Other Principal Arterial per WSDOT Functional Class. Deliverables •Five (5) additional Conceptual Design scroll plots •Updated Conceptual Design technical memorandum •Five (5) additional Conceptual Design cost estimates Work Element 7: Multimodal Feasibility and Alternatives Analysis (by MacLeod Reckord) This Work Element was originally included in the scope of work to provide additional support for Public Outreach, however upon progression of the work, it was determined that the additional support was not required by the project team. This Work Element will be deleted and is reflected as negative values in the fee estimate. DocuSign Envelope ID: 56E31058-AB91-4A0D-86DB-96732F10BBBB City of Bremerton Warren Avenue Bridge Pedestrian Improvements Contract Amendment #1 September 26, 2022 Page 6 of 6 2727 Hollycroft Street, Suite 230 w Gig Harbor, WA 98335 w Office 253.201.0777 w www.scjalliance.com Work Element 98: Management Reserve Funding provided for additional, out of scope services requested of the Consultant by the City. Prior to utilization of these funds, the Consultant shall receive a written authorization from the City. This fund is budgeted as noted in the Fee Estimate. Additional Services The City may require additional services of the Consultant. The scope of those services will be determined based on unanticipated project needs or other considerations at the sole discretion of the City. This work may include items identified in the current task authorizations as well other items, which may include, but are not necessarily limited to the following: •Preliminary (30%) and Final Design (60%, 90%, 100%, BID documents) •Right of way determination •Public Involvement during Preliminary and Final Design •Environmental Permitting and Documentation •Cultural Resources Evaluation and Permitting •Geotechnical Engineering •Coordination with WSDOT •Design of temporary utility modifications during construction •Construction Administration and Inspection •As-Built Drawings •Irrigation System Design •Right of Way acquisition documentation and negotiations These services will be authorized under a future contract amendment if necessary. At the time these services are required, the Consultant shall provide a detailed scope of work and estimate of costs. The Consultant shall not proceed with the work until the City has authorized the work and issued a notice to proceed. END OF SCOPE OF SERVICE DocuSign Envelope ID: 56E31058-AB91-4A0D-86DB-96732F10BBBB Exhibit C Contract Amendment #1 September 26, 2022 Consultant Labor Hour Estimate SCJ Alliance Client:City of Bremerton Project:Warren Avenue Bridge Pedestrian Improvements Job #:20-000248 Work Element & Task No.Principal Project Manager Project Engineer II Project Engineer I Design Engineer Senior Designer Senior Project Manager Project Engineer II Senior Consultant Principal Planner Planner Graphic Designer Project Coordinator II Project Accountant Total Labor Hours Total Cost $272.37 $174.09 $151.63 $123.55 $117.93 $115.12 $210.59 $126.36 $230.25 $193.75 $103.89 $92.66 $106.70 $95.47 WORK ELEMENT 01 Task 01 1 4.0 16.0 20.0 3,874.92$ 2 8.0 8.0 1,392.72$ Subtotal Hours: 4.0 24.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 28.0 Task 02 1 2.0 4.0 16.0 22.0 2,768.62$ 2 6.0 8.0 14.0 1,898.14$ 3 8.0 20.0 28.0 3,526.72$ Subtotal Hours: 2.0 18.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 28.0 16.0 64.0 Task 03 1 16.0 8.0 8.0 32.0 4,649.84$ Subtotal Hours: 0.0 16.0 0.0 0.0 8.0 8.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 32.0 Task 04 1 20.0 20.0 3,481.80$ 3 8.0 8.0 16.0 3,234.72$ Subtotal Hours: 0.0 28.0 0.0 0.0 0.0 0.0 0.0 0.0 8.0 0.0 0.0 0.0 0.0 0.0 36.0 Total Work Element Hours: 6.0 86.0 0.0 0.0 8.0 8.0 0.0 0.0 8.0 0.0 0.0 0.0 28.0 16.0 160.0 Total Work Element Labor:24,827.48$ WORK ELEMENT 03 Task 01 1 8.0 10.0 18.0 36.0 5,200.24$ 2 4.0 16.0 2,358.60$ Subtotal Hours: 0.0 12.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 10.0 34.0 0.0 0.0 0.0 36.0 Task 02 3 16.0 32.0 10.0 58.0 10,024.34$ 4 4.0 4.0 8.0 1,471.36$ 5 2.0 2.0 4.0 735.68$ 6 16.0 12.0 8.0 36.0 5,941.56$ Subtotal Hours: 0.0 38.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 50.0 18.0 0.0 0.0 0.0 106.0 Task 03 1 2.0 2.0 6.0 4.0 14.0 1,729.66$ Subtotal Hours: 0.0 2.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 2.0 6.0 4.0 0.0 0.0 14.0 Total Work Element Hours: 0.0 52.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 62.0 58.0 4.0 0.0 0.0 156.0 Total Work Element Labor:27,461.44$ Work Element & Task Title Management Management Schedule and Budget Project Management (2 Months) Stakeholder Survey WDFW Meetings Interactive Project Website Interactive Project Website Contract Administration Progress Billings (assume 4) Filing Subconsultant Administration Subconsultant Coordination Coordination with subconsultants Public Involvement Stakeholder Meetings for Feasibility Analysis Progress Meetings Bi-Weekly Progress Meetings Website Updates Stakeholder Alternative Review Meeting (5 add'l alternatives) Stakeholder Preferred Alternative Meeting (5 add'l alternatives) Public Meetings for Feasibility Analysis Public Alternative Review Open House (5 add'l alternatives) Stakeholder Criterial Review Meeting DocuSign Envelope ID: 56E31058-AB91-4A0D-86DB-96732F10BBBB Exhibit C Contract Amendment #1 September 26, 2022 Consultant Labor Hour Estimate SCJ Alliance Client:City of Bremerton Project:Warren Avenue Bridge Pedestrian Improvements Job #:20-000248 Work Element & Task No.Principal Project Manager Project Engineer II Project Engineer I Design Engineer Senior Designer Senior Project Manager Project Engineer II Senior Consultant Principal Planner Planner Graphic Designer Project Coordinator II Project Accountant Total Labor Hours Total Cost $272.37 $174.09 $151.63 $123.55 $117.93 $115.12 $210.59 $126.36 $230.25 $193.75 $103.89 $92.66 $106.70 $95.47 Work Element & Task Title WORK ELEMENT 04 Task 02 1 6.0 6.0 6.0 18.0 2,493.42$ 2 2.0 12.0 32.0 24.0 8.0 8.0 86.0 12,944.46$ Subtotal Hours: 2.0 18.0 0.0 38.0 30.0 0.0 8.0 0.0 8.0 0.0 0.0 0.0 0.0 0.0 104.0 Task 03 1 2.0 16.0 12.0 10.0 4.0 4.0 48.0 7,755.44$ Subtotal Hours: 2.0 16.0 0.0 12.0 10.0 0.0 4.0 0.0 4.0 0.0 0.0 0.0 0.0 0.0 48.0 Total Work Element Hours: 4.0 34.0 0.0 50.0 40.0 0.0 12.0 0.0 12.0 0.0 0.0 0.0 0.0 0.0 152.0 Total Work Element Labor:23,193.32$ WORK ELEMENT 05 WORK ELEMENT 06 Task 02 1 4.0 24.0 30.0 80.0 40.0 28.0 206.0 27,393.82$ 2 2.0 18.0 12.0 32.0 5,093.52$ 3 2.0 6.0 12.0 20.0 3,004.44$ Subtotal Hours: 8.0 48.0 30.0 0.0 104.0 40.0 0.0 28.0 0.0 0.0 0.0 0.0 0.0 0.0 258.0 Total Work Element Hours: 8.0 48.0 30.0 0.0 104.0 40.0 0.0 28.0 0.0 0.0 0.0 0.0 0.0 0.0 258.0 Total Work Element Labor:35,491.78$ WORK ELEMENT 07 Total Hours All Work Elements 18.0 220.0 30.0 50.0 152.0 48.0 12.0 28.0 20.0 62.0 58.0 4.0 28.0 16.0 726.0 Total Labor Estimate All Work Elements 110,974.02$ Indirect Costs Subconsultants: Sargent Engineers 24,016.56$ MacLeod Reckord (5,890.16)$ Subconsultant Total 18,126.40$ Reimburseable Expenses: Mileage 200 Miles @ $0.625/Mile 125.00$ Expenses Total:125.00$ Total Indirect Costs:18,251.40$ Subtotal 129,225.42$ Additional Management Reserve:20,000.00$ Total:149,225.42$ Multimodal Feasibility and Alternatives Analysis (by MacLeod Reckord) 10% Cost Estimates (assume 3 estimates) See Subconsultants Alternative Detailed Descriptions Screening of Alternatives Screening of Alternatives Structrual Engineering (by Sargent Engineers) Conceptual Designs for Feasibility Analysis See Subconsultants Roadway Conceptual Design Horizontal Layouts (assume 5 layouts) Conceputal Design Technical Memorandum Updates Develop Alternatives Feasibility and Alternatives Analysis Prepare Alternatives DocuSign Envelope ID: 56E31058-AB91-4A0D-86DB-96732F10BBBB Exhibit C Contract Amendment #1 September 26, 2022 SubConsultant Labor Hour Estimate Sargent Engineers Client:City of Bremerton Project:Warren Avenue Bridge Pedestrian Improvements Job #:20-000248 Work Element & Task No.Principal Sen. Project Engineer Project Engineer Design Engineer Total Labor Hours Total Cost $171.54 $134.79 $124.06 $87.30 WORK ELEMENT 05 Task 02 1 Framing Concepts (3 span types, 3 alternatives)30.0 60.0 90.0 13,233.60$ 2 Bridge Load Rating Effects Determination 6.0 6.0 12.0 1,837.98$ 3 Bridge Seismic Effects Determination 6.0 6.0 12.0 1,837.98$ 4 Feasibility Memo 2.0 4.0 6.0 882.24$ 5 Bridge Cross-sections 6.0 24.0 30.0 4,264.20$ 6 2.0 12.0 14.0 1,960.56$ 0.0 -$ Subtotal Hours: 52.0 112.0 0.0 0.0 164.0 24,016.56$ Total Hours All Work Elements 52.0 112.0 0.0 0.0 164.0 Total Labor Estimate All Work Elements 24,016.56$ Reimburseable Expenses: Expenses Total:-$ Total:24,016.56$ Work Element & Task Title Structrual Engineering (by Sargent Engineers) Feasibility & Alternative Analysis Cost Estimates DocuSign Envelope ID: 56E31058-AB91-4A0D-86DB-96732F10BBBB Exhibit C Contract Amendment #1 September 26, 2022 Consultant Rate Determination Client:City of Bremerton Project:Warren Avenue Bridge Pedestrian Improvements Job #: SCJ Alliance Principal Project Manager Project Engineer II Project Engineer I Design Engineer Senior Designer Senior Project Manager Project Engineer II Senior Consultant Principal Planner Planner Graphic Designer Project Coordinator II Project Accountant Direct Rate 97.00$ 62.00$ 54.00$ 44.00$ 42.00$ 41.00$ 75.00$ 45.00$ 82.00$ 69.00$ 37.00$ 33.00$ 38.00$ 34.00$ WSDOT OH Rate 151.79% 147.24$ 94.11$ 81.97$ 66.79$ 63.75$ 62.23$ 113.84$ 68.31$ 124.47$ 104.74$ 56.16$ 50.09$ 57.68$ 51.61$ Negotiated Profit 29.00% 28.13$ 17.98$ 15.66$ 12.76$ 12.18$ 11.89$ 21.75$ 13.05$ 23.78$ 20.01$ 10.73$ 9.57$ 11.02$ 9.86$ Billing Rate 272.37$ 174.09$ 151.63$ 123.55$ 117.93$ 115.12$ 210.59$ 126.36$ 230.25$ 193.75$ 103.89$ 92.66$ 106.70$ 95.47$ MTN2COAST, LLC Senior Surveyor Surveyor - LSIT Senior Survey Technician Survey Technician Jr Survey Technician Direct Rate 57.69$ 48.08$ 38.46$ 28.00$ 22.00$ WSDOT OH Rate 75.74% 43.69$ 36.42$ 29.13$ 21.21$ 16.66$ Negotiated Profit 29.00% 16.73$ 13.94$ 11.15$ 8.12$ 6.38$ Billing Rate 118.11$ 98.44$ 78.74$ 57.33$ 45.04$ Sargent Engineers Principal Sen. Project Engineer Project Engineer Design Engineer Direct Rate 56.00$ 44.00$ 40.50$ 28.50$ WSDOT OH Rate 177.33% 99.30$ 78.03$ 71.82$ 50.54$ Negotiated Profit 29.00% 16.24$ 12.76$ 11.75$ 8.27$ Billing Rate 171.54$ 134.79$ 124.06$ 87.30$ MacLeod Reckord PR 1 Assoc. LD 1 Admin 1 Admin 4 Senior Advisor Direct Rate 50.00$ 40.00$ 36.00$ 32.00$ 30.00$ 50.00$ WSDOT OH Rate 174.93% 87.47$ 69.97$ 62.97$ 55.98$ 52.48$ 87.47$ Negotiated Profit 29.00% 14.50$ 11.60$ 10.44$ 9.28$ 8.70$ 14.50$ Billing Rate 151.97$ 121.57$ 109.41$ 97.26$ 91.18$ 151.97$ Classification Classification Classification Classification 20-000248 DocuSign Envelope ID: 56E31058-AB91-4A0D-86DB-96732F10BBBB Contract Amendment #1 September 26, 2022 Contract Amendment Summary Client: City of Bremerton Project: Warren Avenue Bridge Pedestrian Improvements Job #: 20-000248 Work Element #Phase Title Original Contract Management Reserve Request #1 Contract Amendment #1 Total SCJ Labor 01 Project Management 25,633.32$ 19,046.77$ 24,827.48$ 69,507.57$ 03 Public Involvement 33,290.46$ -$ 27,461.44$ 60,751.90$ 04 Feasibility and Alternatives Analysis 28,983.15$ -$ 23,193.32$ 52,176.47$ 06 Conceptual Designs for Feasibility Analysis 44,241.27$ -$ 35,491.78$ 79,733.05$ Subtotal $132,148.20 $19,046.77 $110,974.02 $262,168.99 Subconsultants 02 Survey and Right of Way Determination (by Mtn2Coast) 34,170.11$ -$ -$ 34,170.11$ 05 Structural Engineering (by Sargent Engineers) 59,487.51$ -$ 24,016.56$ 83,504.07$ 07 Multimodal Feasibility and Alternatives Analysis (by MacLeod Reckord) 5,890.16$ -$ (5,890.16)$ -$ Subtotal $99,547.78 $0.00 $18,126.40 $117,674.18 Reimbursable Expenses 99 Reimbursable Expenses 518.00$ 350.00$ 125.00$ 993.00$ Subtotal $518.00 $350.00 $125.00 $993.00 Management Reserve Fund (MRF) 98 Management Reserve Fund 23,221.40$ -$19,396.77 $20,000.00 $23,824.63 Subtotal $23,221.40 -$19,396.77 $20,000.00 $23,824.63 Summary Total $255,435.38 $0.00 $149,225.42 $404,660.80 DocuSign Envelope ID: 56E31058-AB91-4A0D-86DB-96732F10BBBB