HomeMy WebLinkAbout1 - Original Submission_ 090822_315032_SCJ CM#001CONTRACT MODIFICATION AGREEMENT NO. 001
To CITY CONTRACT # 6263
BETWEEN THE CITY OF BREMERTON AND
SHEA CARR & JEWELL, Inc. (dba SCJ Alliance)
PROJECT: Warren Avenue Bridge Pedestrian Improvements
CONSULTANT: Shea Carr & Jewell, Inc. (dba SCJ Alliance)
DATE September 1, 2022
THIS CONTRACT MODIFICATION AGREEMENT SPECIFICALLY AMENDS THE
Professional Services AGREEMENT (the "Contract") entered into between the City of
Bremerton and Shea Carr & Jewell, Inc. (dba SCJ Alliance)on August 10, 2021.
All provisions in the Contract shall remain in full force and effect except as expressly modified
by this document.
For valuable consideration and by mutual consent of the parties, the modifications to the
Contract are as follows:
I.
Section I. Scope , is modified as follows:
See Amended Scope of Work attached as Exhibit A
Section II. Term , is modified as follows:
The Consultant shall complete the work described in this Contract Modification Agreement by Extended thru February 28, 2023.
Section III. Compensation , is modified as follows:
The original contract amount was $ 255,435.38. The City shall pay the Consultant for the
additional work described above, based on time and materials, an amount not to exceed$
1 for a total amended contract amount of $ , including this Contract
Modification.
II.
Consultant accepts all requirements of this Contract Modification by endorsing below.
Consultant further agrees that this Contract Modification constitutes full and final
settlement of all of the Consultant’s claims for contract time and for all costs of any kind,
including without limitation, costs of delays related to any work either covered or affected
by this Contract Modification, claims related to on-site or home office overhead, or lost
profits. This Contract Modification does not limit the City’s right to bring a claim for past
performance.
Page 1 of 2
Contract Modification
Rev. 09/2021
DocuSign Envelope ID: 56E31058-AB91-4A0D-86DB-96732F10BBBB
Page 2 of 2
Contract Modification
Rev. 09/2021
The undersigned consultant approves the foregoing Contract Modification as to the changes,
if any, in the contract price specified for each item, including any and all supervision costs
and other miscellaneous costs relating to the change in work, and as to the extension of time
allowed, if any, for completion of the entire work due to said Contract Modification.
This document will become a supplement of the contract and all provisions will apply hereto.
It is understood that this Contract Modification shall be effective when approved by the City
of Bremerton.
The parties whose names appear below warrant that they are authorized to enter into a
contract modification that is binding on the parties of this contract. In addition, Consultant
warrants that it has or will inform the surety of this change, and shall take appropriate action
to modify any bonds required under the contract to address this change.
IN WITNESS WHEREOF, the parties have executed this Contract Modification on the day
and year first written above.
City Engineer / Public Works Director
CONSULTANT THE CITY OF BREMERTON
By:By:
Print Name: Scott Sawyer Print Name: Greg Wheeler________
Its: Principal Its: Mayor
Date:Date:
APPROVED AS TO FORM: ATTEST:
By:By:
KYLIE J. FINNELL, Bremerton City Attorney ANGELA HOOVER, City Clerk
NOTICES TO BE SENT TO: NOTICES TO BE SENT TO:
Aaron Knight, P.E. Vicki Grover, P.E.
Project Manager Project Manager
SCJ Alliance City of Bremerton Engineering Dept.
2727 Hollycroft Street, Suite 230 345 6th Street, Suite 100
Gig Harbor, WA 98335 Bremerton, WA 98337
R:\Legal\Legal\Forms\FORMS ON COBWEB\Contract Modification Rev. 09 2021.docx
approved to process (Initials and Date)Ned Lever
Digitally signed by Ned Lever
DN: C=US, E=ned.lever@ci.bremerton.wa.us,
O=City of Bremerton, OU=Engineering, CN=Ned
LeverReason: I have reviewed this documentDate: 2022.10.03 15:08:07-07'00'
DocuSign Envelope ID: 56E31058-AB91-4A0D-86DB-96732F10BBBB
10/20/2022 10/20/2022
2727 Hollycroft Street, Suite 230 w Gig Harbor, WA 98335 w Office 253.201.0777 w www.scjalliance.com
CONTRACT AMENDMENT #1
SCOPE OF WORK AND FEE ESTIMATE
for
Warren Avenue Bridge Pedestrian Improvements
Bremerton, WA
Prepared For: Vicki Grover, PE
City of Bremerton
345 6th Street, Suite 100
Bremerton, WA 98337
Prepared By: Aaron Knight, PE, Project Manager
Date Prepared: September 26, 2022
OVERVIEW
The feasibility and alternatives analysis has concluded the evaluation of the four alternatives identified by the
City as included in the original scope of work. At the request of the City, five additional alternatives will be
developed, three of which will receive a structural evaluation, in addition to other tasks as specified herein.
This Contract Amendment adds the following work:
1. Add three additional alternatives to the structural feasibility analysis
a. Alternative 2 - 10-foot sidewalk on both sides
b. (new) Alternative 7 – 12-foot sidewalk on the west side of the bridge, including a tunnel under
SR303 near 18th Street
c. (new) Alternative 8 – 10-foot shared use path (14-foot total width) west side of the bridge,
including a tunnel under SR303 near 18th Street
2. Preparation of a technical memorandum by Sargent Engineers to summarize Alternative 5 requiring a
seismic retrofit for the bridge.
3. Preparation of language in the report document defining Alternative 6 as a bicycle lane on the bridge
deck and separated sidewalk. A technical memorandum will be prepared by Sargent Engineers to
summarize Alternative 6 requiring a seismic retrofit for the bridge.
4. Add all five of the aforementioned alternatives into the project alternative analysis report.
5. Meetings with Washington Department of Fish and Wildlife to scope the level of effort for addressing
impacts to nesting cormorants on the bridge
y,//d
DocuSign Envelope ID: 56E31058-AB91-4A0D-86DB-96732F10BBBB
City of Bremerton
Warren Avenue Bridge Pedestrian Improvements
Contract Amendment #1
September 26, 2022
Page ii
2727 Hollycroft Street, Suite 230 w Gig Harbor, WA 98335 w Office 253.201.0777 w www.scjalliance.com
6. Additional Public Involvement efforts:
a. Increased level of effort for stakeholder and public outreach events resulting from the additional
project alternatives.
b. Add one (1) additional in-person stakeholder meeting
c. Revise one (1) of the community open house events to be in-person instead of virtual
7. Extension of the project duration through February 2023. Management Reserve Request #1 extended
the project duration through October 2022, therefore this amendment will add four (4) additional
months.
This contract amendment will also cover costs already incurred for the following tasks. Note that the schedule
impacts on additional project management effort was previously addressed in Management Reserve Request #1
(June 2022).
1.Project Website and Stakeholder Survey Launch: The website launch and stakeholder survey were
scheduled to be completed in September 2021, but were delayed until January/February 2022 due to
extended City review and scheduling conflicts. The additional effort associated with additional reviews
and updates to the deliverables is included.
2.Stakeholder Survey Review: the stakeholder survey was shared by members of the project stakeholder
group with the general public. This resulted in approximately 700 additional responses beyond the 30
(or so) anticipated. There was a delay of approximately two months in the project schedule while this
data was processed, and the team determined how to proceed. This concluded with the hosting of an
additional stakeholder meeting to receive their direction for how to proceed.
All assumptions and deliverables included in the original scope of work shall still apply, unless modified herein.
DocuSign Envelope ID: 56E31058-AB91-4A0D-86DB-96732F10BBBB
City of Bremerton
Warren Avenue Bridge Pedestrian Improvements
Contract Amendment #1
September 26, 2022
Page 1 of 6
2727 Hollycroft Street, Suite 230 w Gig Harbor, WA 98335 w Office 253.201.0777 w www.scjalliance.com
Work Element 1: Project Management
This Work Element includes tasks to plan, manage, and administer the work; attend project meetings; and
coordinate with subconsultants. The level of effort included in the fee estimate assume four (4) additional
months of duration.
Task 1 Management
Task 1.1 Management: Manage the project by directing and supervising staff and reviewing work for
the duration of the project. This management is for the overall work rather than specific tasks.
Task 1.2 Schedule and Budget: Periodic updates to the a critical path project schedule to match the
scope of work.
Task 2 Contract Administration
Task 2.1 Progress Billings: Prepare a monthly progress invoice with a summary of work performed.
Invoices will show staff hours for each Work Element (i.e., Work Element 1: Project Management).
Task 2.2 Filing: Develop a project filing system and maintain project files in one centralized location.
Periodically purge draft and redundant documents.
Task 2.3 Subconsultant Administration: Execute and administer subconsultant contracts. Review
and approve monthly invoices.
Task 3 Subconsultant Coordination
Task 3.1 Coordination with subconsultants for scheduling, exchanging files, and additional
coordination as needed.
Task 4 Project Coordination Meetings
Task 4.1 Bi-weekly (every other week) progress meetings with City and SCJ project managers.
Assume one (1) Consultant staff member for eight (8) additional virtual meetings.
Task 4.3 Up to two (2) meetings with the Washington Department of Fish and Wildlife (WDFW) to
discuss the level of effort for addressing impacts to nesting cormorants on the bridge and other
environmental concerns.
Understanding
• Project management for the feasibility analysis will be provided through December 2022. Extension of
the project timeframe will require a contract amendment.
Deliverables
• Biweekly Progress Report submitted via email in PDF format. Assume four (4).
• Monthly Progress billings submitted via email in PDF format. Assume two (2).
• MS Project schedule updates submitted via email in PDF format.
DocuSign Envelope ID: 56E31058-AB91-4A0D-86DB-96732F10BBBB
City of Bremerton
Warren Avenue Bridge Pedestrian Improvements
Contract Amendment #1
September 26, 2022
Page 2 of 6
2727 Hollycroft Street, Suite 230 w Gig Harbor, WA 98335 w Office 253.201.0777 w www.scjalliance.com
Work Element 2: Survey and Right of Way Determination
(by Mtn2Coast)
No Changes
Work Element 3: Public Involvement
Task 1 Interactive Project Website
Task 1.1 Interactive Project Website: The level of effort included in the fee estimate accounts
work previously completed and documented in the project bi-weekly reports.
Task 1.2 Website Updates: extend the project website update/maintenance period through the
extension of the contract; duration as specified in the Overview section of this scope of work.
Task 2 Stakeholder Meetings for Feasibility Analysis
Task 2.3 Stakeholder Survey: The level of effort included in the fee estimate accounts work
previously completed and documented in the project bi-weekly reports, including review of additional
survey results and hosting of Stakeholder Meeting #2 to review the results of the survey.
Task 2.4 Stakeholder Alternative Review Meeting: The level of effort included in the fee
estimate accounts for the addition of five (5) additional project alternatives. All other assumptions in the
original scope of work apply. This virtual meeting is also referred to as “Stakeholder Workshop #3” and
was held on September 12, 2022.
Task 2.5 Stakeholder Preferred Alternative Meeting: The level of effort included in the fee
estimate accounts for the addition of five (5) additional project alternatives. All other assumptions in the
original scope of work apply. This virtual meeting is also referred to as “Stakeholder Workshop #5” and
is scheduled for early November 2022.
Task 2.6 Stakeholder Criteria Review Meeting: This additional meeting will be conducted to
discuss the criteria used as part of the Alternatives Analysis, and receive stakeholder direction for how
the criteria should be developed and how the alternatives should be reviewed against the criteria. This
in-person meeting is also referred to as “Stakeholder Workshop #4” and is scheduled for late
October 2022.
DocuSign Envelope ID: 56E31058-AB91-4A0D-86DB-96732F10BBBB
City of Bremerton
Warren Avenue Bridge Pedestrian Improvements
Contract Amendment #1
September 26, 2022
Page 3 of 6
2727 Hollycroft Street, Suite 230 w Gig Harbor, WA 98335 w Office 253.201.0777 w www.scjalliance.com
Task 3 Public Meetings for Feasibility Analysis
Task 3.1 Public Alternative Review Meeting and Online Open House: Revise this task to assume
an in-person open house event located at the Norm Dicks building in Bremerton. Assume four (4)
Consultant staff for one (1) meeting. The level of effort included in the fee estimate accounts additional
work required to host the in-person open house as opposed to the previously scoped virtual open house
and the addition of five (5) additional project alternatives. All other assumptions in the original scope of
work apply. This in-person event is also referred to as “Community Open House #1” and is scheduled for
late October 2022.
Task 3.2 Public Preferred Alternative Presentation: No Changes. This virtual event is also
referred to as “Community Open House #2” and is scheduled for late November 2022.
Task 4 Council Briefings
No Changes
Work Element 4: Feasibility and Alternatives Analysis
Task 1 Project Background
No Changes
Task 2 Prepare Alternatives
The level of effort included in the fee estimate accounts additional work required to prepare five (5)
additional alternatives included in this scope of work.
Task 2.1 Develop Alternatives: In addition to the four (4) alternatives developed as part of the
original scope of work, develop five (5) additional project alternatives for the bridge crossing and
associated off structure improvements. The added alternatives include:
a. Alternative 2 - 10-foot sidewalk on both sides
b. Alternative 5 – 14-foot shared use path on both sides
c. Alternative 6 – Bicycle lane on the bridge deck and separated sidewalk
d. (new) Alternative 7 – 12-foot sidewalk on the west side of the bridge, including a tunnel under
SR303 near 18th Street
e. (new) Alternative 8 – 10-foot shared use path (14-foot total width) west side of the bridge,
including a tunnel under SR303 near 18th Street
Provide a written description of each alternative. A conceptual sketch and cross section for each
alternative will be developed (see Work Element 6).
Task 2.2 Alternative Detailed Descriptions: In addition to the four (4) alternatives developed as
part of the original scope of work, prepare detailed descriptions for five (5) additional alternatives using
the process as outlined in the original scope of work.
DocuSign Envelope ID: 56E31058-AB91-4A0D-86DB-96732F10BBBB
City of Bremerton
Warren Avenue Bridge Pedestrian Improvements
Contract Amendment #1
September 26, 2022
Page 4 of 6
2727 Hollycroft Street, Suite 230 w Gig Harbor, WA 98335 w Office 253.201.0777 w www.scjalliance.com
Task 3 Screening of Alternatives
The level of effort included in the fee estimate accounts additional work required for the screening of
the five (5) additional alternatives included in this scope of work.
Task 3.1 Screening of Alternatives: Based on stakeholder input during the Stakeholder
Alternative Review Meeting, provide a summary of the stakeholder inputs and impacts of proposed
alternatives. Revise alternative detailing as required.
Work Element 5: Structural Engineering (by Sargent Engineers)
The level of effort included in the fee estimate accounts additional work required for the preparation of
feasibility analysis for the three (3) additional alternatives included in this scope of work.
Task 1 Site Reconnaissance and Data Collection
No Changes
Task 2 Feasibility & Alternative Analysis
The Consultant will prepare conceptual framing designs to support up to three (3) additional alternatives
for bridge structure improvements. A technical memorandum will also be provided for “Alternative 5”
and “Alternative 6” summarizing the need for extensive strengthening and/or seismic retrofit and
determination that they are not feasible; this determination will be made based on the results of the
other alternatives analyzed and engineering judgement, no structural analysis will be performed specific
to “Alternative 5” or “Alternative 6”.
All other assumptions from the original scope of work are unchanged.
Task 3 Public Involvement
Task 3.1 Public Meetings for Feasibility Analysis: No Changes
Task 3.2 Council Briefings for Feasibility Analysis: No Changes
DocuSign Envelope ID: 56E31058-AB91-4A0D-86DB-96732F10BBBB
City of Bremerton
Warren Avenue Bridge Pedestrian Improvements
Contract Amendment #1
September 26, 2022
Page 5 of 6
2727 Hollycroft Street, Suite 230 w Gig Harbor, WA 98335 w Office 253.201.0777 w www.scjalliance.com
Work Element 6: Conceptual Designs for Feasibility Analysis
The level of effort included in the fee estimate accounts additional work required for the preparation of
conceptual design for the five (5) additional alternatives identified in Work Element 4, Task 2.1.
Task 1 Data Collection
No Changes
Task 2 Roadway Conceptual Design
Task 2.1 Horizontal Layout
• Develop 2-dimensional conceptual roadway and shared use path layout for five (5)
additional alternative layouts. Show travel lanes, turn lanes, shoulders, curb/gutter, planter,
shared use path, sidewalks, and driveways. Curb returns at side streets will match existing
street width for side streets.
• Develop five (5) additional typical sections.
Vertical location of improvements will not be specified, however anticipated wall locations will be
included.
Task 2.2 Conceptual Design Technical Memorandum: Revise the conceptual design technical
memorandum to include the five (5) additional alternatives.
Task 2.3 Conceptual Design Cost Estimate: Develop cost estimations for the five (5) additional
alternatives.
Understandings
•Warren Avenue (SR 303) is a Urban Other Principal Arterial per WSDOT Functional Class.
Deliverables
•Five (5) additional Conceptual Design scroll plots
•Updated Conceptual Design technical memorandum
•Five (5) additional Conceptual Design cost estimates
Work Element 7: Multimodal Feasibility and Alternatives Analysis
(by MacLeod Reckord)
This Work Element was originally included in the scope of work to provide additional support for Public
Outreach, however upon progression of the work, it was determined that the additional support was not
required by the project team.
This Work Element will be deleted and is reflected as negative values in the fee estimate.
DocuSign Envelope ID: 56E31058-AB91-4A0D-86DB-96732F10BBBB
City of Bremerton
Warren Avenue Bridge Pedestrian Improvements
Contract Amendment #1
September 26, 2022
Page 6 of 6
2727 Hollycroft Street, Suite 230 w Gig Harbor, WA 98335 w Office 253.201.0777 w www.scjalliance.com
Work Element 98: Management Reserve
Funding provided for additional, out of scope services requested of the Consultant by the City. Prior to utilization
of these funds, the Consultant shall receive a written authorization from the City. This fund is budgeted as
noted in the Fee Estimate.
Additional Services
The City may require additional services of the Consultant. The scope of those services will be determined
based on unanticipated project needs or other considerations at the sole discretion of the City. This work may
include items identified in the current task authorizations as well other items, which may include, but are not
necessarily limited to the following:
•Preliminary (30%) and Final Design (60%, 90%, 100%, BID documents)
•Right of way determination
•Public Involvement during Preliminary and Final Design
•Environmental Permitting and Documentation
•Cultural Resources Evaluation and Permitting
•Geotechnical Engineering
•Coordination with WSDOT
•Design of temporary utility modifications during construction
•Construction Administration and Inspection
•As-Built Drawings
•Irrigation System Design
•Right of Way acquisition documentation and negotiations
These services will be authorized under a future contract amendment if necessary. At the time these services
are required, the Consultant shall provide a detailed scope of work and estimate of costs. The Consultant shall
not proceed with the work until the City has authorized the work and issued a notice to proceed.
END OF SCOPE OF SERVICE
DocuSign Envelope ID: 56E31058-AB91-4A0D-86DB-96732F10BBBB
Exhibit C Contract Amendment #1
September 26, 2022
Consultant Labor Hour Estimate
SCJ Alliance
Client:City of Bremerton
Project:Warren Avenue Bridge Pedestrian Improvements
Job #:20-000248
Work Element
& Task No.Principal Project
Manager
Project
Engineer II
Project
Engineer I
Design
Engineer
Senior
Designer
Senior Project
Manager
Project
Engineer II
Senior
Consultant
Principal
Planner Planner Graphic
Designer
Project
Coordinator II
Project
Accountant
Total Labor
Hours Total Cost
$272.37 $174.09 $151.63 $123.55 $117.93 $115.12 $210.59 $126.36 $230.25 $193.75 $103.89 $92.66 $106.70 $95.47
WORK
ELEMENT 01
Task 01
1 4.0 16.0 20.0 3,874.92$
2 8.0 8.0 1,392.72$
Subtotal Hours: 4.0 24.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 28.0
Task 02
1 2.0 4.0 16.0 22.0 2,768.62$
2 6.0 8.0 14.0 1,898.14$
3 8.0 20.0 28.0 3,526.72$
Subtotal Hours: 2.0 18.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 28.0 16.0 64.0
Task 03
1 16.0 8.0 8.0 32.0 4,649.84$
Subtotal Hours: 0.0 16.0 0.0 0.0 8.0 8.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 32.0
Task 04
1 20.0 20.0 3,481.80$
3 8.0 8.0 16.0 3,234.72$
Subtotal Hours: 0.0 28.0 0.0 0.0 0.0 0.0 0.0 0.0 8.0 0.0 0.0 0.0 0.0 0.0 36.0
Total Work Element Hours: 6.0 86.0 0.0 0.0 8.0 8.0 0.0 0.0 8.0 0.0 0.0 0.0 28.0 16.0 160.0
Total Work Element Labor:24,827.48$
WORK
ELEMENT 03
Task 01
1 8.0 10.0 18.0 36.0 5,200.24$
2 4.0 16.0 2,358.60$
Subtotal Hours: 0.0 12.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 10.0 34.0 0.0 0.0 0.0 36.0
Task 02
3 16.0 32.0 10.0 58.0 10,024.34$
4 4.0 4.0 8.0 1,471.36$
5 2.0 2.0 4.0 735.68$
6 16.0 12.0 8.0 36.0 5,941.56$
Subtotal Hours: 0.0 38.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 50.0 18.0 0.0 0.0 0.0 106.0
Task 03
1 2.0 2.0 6.0 4.0 14.0 1,729.66$
Subtotal Hours: 0.0 2.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 2.0 6.0 4.0 0.0 0.0 14.0
Total Work Element Hours: 0.0 52.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 62.0 58.0 4.0 0.0 0.0 156.0
Total Work Element Labor:27,461.44$
Work Element & Task Title
Management
Management
Schedule and Budget
Project Management (2 Months)
Stakeholder Survey
WDFW Meetings
Interactive Project Website
Interactive Project Website
Contract Administration
Progress Billings (assume 4)
Filing
Subconsultant Administration
Subconsultant Coordination
Coordination with subconsultants
Public Involvement
Stakeholder Meetings for Feasibility Analysis
Progress Meetings
Bi-Weekly Progress Meetings
Website Updates
Stakeholder Alternative Review Meeting (5 add'l alternatives)
Stakeholder Preferred Alternative Meeting (5 add'l alternatives)
Public Meetings for Feasibility Analysis
Public Alternative Review Open House (5 add'l alternatives)
Stakeholder Criterial Review Meeting
DocuSign Envelope ID: 56E31058-AB91-4A0D-86DB-96732F10BBBB
Exhibit C Contract Amendment #1
September 26, 2022
Consultant Labor Hour Estimate
SCJ Alliance
Client:City of Bremerton
Project:Warren Avenue Bridge Pedestrian Improvements
Job #:20-000248
Work Element
& Task No.Principal Project
Manager
Project
Engineer II
Project
Engineer I
Design
Engineer
Senior
Designer
Senior Project
Manager
Project
Engineer II
Senior
Consultant
Principal
Planner Planner Graphic
Designer
Project
Coordinator II
Project
Accountant
Total Labor
Hours Total Cost
$272.37 $174.09 $151.63 $123.55 $117.93 $115.12 $210.59 $126.36 $230.25 $193.75 $103.89 $92.66 $106.70 $95.47
Work Element & Task Title
WORK
ELEMENT 04
Task 02
1 6.0 6.0 6.0 18.0 2,493.42$
2 2.0 12.0 32.0 24.0 8.0 8.0 86.0 12,944.46$
Subtotal Hours: 2.0 18.0 0.0 38.0 30.0 0.0 8.0 0.0 8.0 0.0 0.0 0.0 0.0 0.0 104.0
Task 03
1 2.0 16.0 12.0 10.0 4.0 4.0 48.0 7,755.44$
Subtotal Hours: 2.0 16.0 0.0 12.0 10.0 0.0 4.0 0.0 4.0 0.0 0.0 0.0 0.0 0.0 48.0
Total Work Element Hours: 4.0 34.0 0.0 50.0 40.0 0.0 12.0 0.0 12.0 0.0 0.0 0.0 0.0 0.0 152.0
Total Work Element Labor:23,193.32$
WORK
ELEMENT 05
WORK
ELEMENT 06
Task 02
1 4.0 24.0 30.0 80.0 40.0 28.0 206.0 27,393.82$
2 2.0 18.0 12.0 32.0 5,093.52$
3 2.0 6.0 12.0 20.0 3,004.44$
Subtotal Hours: 8.0 48.0 30.0 0.0 104.0 40.0 0.0 28.0 0.0 0.0 0.0 0.0 0.0 0.0 258.0
Total Work Element Hours: 8.0 48.0 30.0 0.0 104.0 40.0 0.0 28.0 0.0 0.0 0.0 0.0 0.0 0.0 258.0
Total Work Element Labor:35,491.78$
WORK
ELEMENT 07
Total Hours All Work Elements 18.0 220.0 30.0 50.0 152.0 48.0 12.0 28.0 20.0 62.0 58.0 4.0 28.0 16.0 726.0
Total Labor Estimate All Work Elements 110,974.02$
Indirect Costs
Subconsultants:
Sargent Engineers 24,016.56$
MacLeod Reckord (5,890.16)$
Subconsultant Total 18,126.40$
Reimburseable Expenses: Mileage 200 Miles @ $0.625/Mile 125.00$
Expenses Total:125.00$
Total Indirect Costs:18,251.40$
Subtotal 129,225.42$
Additional Management Reserve:20,000.00$
Total:149,225.42$
Multimodal Feasibility and Alternatives Analysis (by MacLeod Reckord)
10% Cost Estimates (assume 3 estimates)
See Subconsultants
Alternative Detailed Descriptions
Screening of Alternatives
Screening of Alternatives
Structrual Engineering (by Sargent Engineers)
Conceptual Designs for Feasibility Analysis
See Subconsultants
Roadway Conceptual Design
Horizontal Layouts (assume 5 layouts)
Conceputal Design Technical Memorandum Updates
Develop Alternatives
Feasibility and Alternatives Analysis
Prepare Alternatives
DocuSign Envelope ID: 56E31058-AB91-4A0D-86DB-96732F10BBBB
Exhibit C Contract Amendment #1
September 26, 2022
SubConsultant Labor Hour Estimate
Sargent Engineers
Client:City of Bremerton
Project:Warren Avenue Bridge Pedestrian Improvements
Job #:20-000248
Work Element
& Task No.Principal Sen. Project
Engineer
Project
Engineer
Design
Engineer
Total Labor
Hours Total Cost
$171.54 $134.79 $124.06 $87.30
WORK
ELEMENT 05
Task 02
1 Framing Concepts (3 span types, 3 alternatives)30.0 60.0 90.0 13,233.60$
2 Bridge Load Rating Effects Determination 6.0 6.0 12.0 1,837.98$
3 Bridge Seismic Effects Determination 6.0 6.0 12.0 1,837.98$
4 Feasibility Memo 2.0 4.0 6.0 882.24$
5 Bridge Cross-sections 6.0 24.0 30.0 4,264.20$
6 2.0 12.0 14.0 1,960.56$
0.0 -$
Subtotal Hours: 52.0 112.0 0.0 0.0 164.0 24,016.56$
Total Hours All Work Elements 52.0 112.0 0.0 0.0 164.0
Total Labor Estimate All Work Elements 24,016.56$
Reimburseable Expenses:
Expenses Total:-$
Total:24,016.56$
Work Element & Task Title
Structrual Engineering (by Sargent Engineers)
Feasibility & Alternative Analysis
Cost Estimates
DocuSign Envelope ID: 56E31058-AB91-4A0D-86DB-96732F10BBBB
Exhibit C Contract Amendment #1
September 26, 2022
Consultant Rate Determination
Client:City of Bremerton
Project:Warren Avenue Bridge Pedestrian Improvements
Job #:
SCJ Alliance
Principal Project
Manager
Project
Engineer II
Project
Engineer I
Design
Engineer
Senior
Designer
Senior
Project
Manager
Project
Engineer II
Senior
Consultant
Principal
Planner Planner Graphic
Designer
Project
Coordinator
II
Project
Accountant
Direct Rate 97.00$ 62.00$ 54.00$ 44.00$ 42.00$ 41.00$ 75.00$ 45.00$ 82.00$ 69.00$ 37.00$ 33.00$ 38.00$ 34.00$
WSDOT OH
Rate 151.79% 147.24$ 94.11$ 81.97$ 66.79$ 63.75$ 62.23$ 113.84$ 68.31$ 124.47$ 104.74$ 56.16$ 50.09$ 57.68$ 51.61$
Negotiated
Profit 29.00% 28.13$ 17.98$ 15.66$ 12.76$ 12.18$ 11.89$ 21.75$ 13.05$ 23.78$ 20.01$ 10.73$ 9.57$ 11.02$ 9.86$
Billing Rate 272.37$ 174.09$ 151.63$ 123.55$ 117.93$ 115.12$ 210.59$ 126.36$ 230.25$ 193.75$ 103.89$ 92.66$ 106.70$ 95.47$
MTN2COAST, LLC
Senior
Surveyor
Surveyor -
LSIT
Senior
Survey
Technician
Survey
Technician
Jr Survey
Technician
Direct Rate 57.69$ 48.08$ 38.46$ 28.00$ 22.00$
WSDOT OH
Rate 75.74% 43.69$ 36.42$ 29.13$ 21.21$ 16.66$
Negotiated
Profit 29.00% 16.73$ 13.94$ 11.15$ 8.12$ 6.38$
Billing Rate 118.11$ 98.44$ 78.74$ 57.33$ 45.04$
Sargent Engineers
Principal Sen. Project
Engineer
Project
Engineer
Design
Engineer
Direct Rate 56.00$ 44.00$ 40.50$ 28.50$
WSDOT OH
Rate 177.33% 99.30$ 78.03$ 71.82$ 50.54$
Negotiated
Profit 29.00% 16.24$ 12.76$ 11.75$ 8.27$
Billing Rate 171.54$ 134.79$ 124.06$ 87.30$
MacLeod Reckord
PR 1 Assoc. LD 1 Admin 1 Admin 4
Senior
Advisor
Direct Rate 50.00$ 40.00$ 36.00$ 32.00$ 30.00$ 50.00$
WSDOT OH
Rate 174.93% 87.47$ 69.97$ 62.97$ 55.98$ 52.48$ 87.47$
Negotiated
Profit 29.00% 14.50$ 11.60$ 10.44$ 9.28$ 8.70$ 14.50$
Billing Rate 151.97$ 121.57$ 109.41$ 97.26$ 91.18$ 151.97$
Classification
Classification
Classification
Classification
20-000248
DocuSign Envelope ID: 56E31058-AB91-4A0D-86DB-96732F10BBBB
Contract Amendment #1
September 26, 2022
Contract Amendment Summary
Client: City of Bremerton
Project: Warren Avenue Bridge Pedestrian Improvements
Job #: 20-000248
Work
Element #Phase Title
Original
Contract
Management
Reserve
Request #1
Contract
Amendment #1 Total
SCJ Labor
01 Project Management 25,633.32$ 19,046.77$ 24,827.48$ 69,507.57$
03 Public Involvement 33,290.46$ -$ 27,461.44$ 60,751.90$
04 Feasibility and Alternatives Analysis 28,983.15$ -$ 23,193.32$ 52,176.47$
06 Conceptual Designs for Feasibility Analysis 44,241.27$ -$ 35,491.78$ 79,733.05$
Subtotal $132,148.20 $19,046.77 $110,974.02 $262,168.99
Subconsultants
02 Survey and Right of Way Determination (by Mtn2Coast) 34,170.11$ -$ -$ 34,170.11$
05 Structural Engineering (by Sargent Engineers) 59,487.51$ -$ 24,016.56$ 83,504.07$
07 Multimodal Feasibility and Alternatives Analysis (by MacLeod Reckord) 5,890.16$ -$ (5,890.16)$ -$
Subtotal $99,547.78 $0.00 $18,126.40 $117,674.18
Reimbursable Expenses
99 Reimbursable Expenses 518.00$ 350.00$ 125.00$ 993.00$
Subtotal $518.00 $350.00 $125.00 $993.00
Management Reserve Fund (MRF)
98 Management Reserve Fund 23,221.40$ -$19,396.77 $20,000.00 $23,824.63
Subtotal $23,221.40 -$19,396.77 $20,000.00 $23,824.63
Summary
Total $255,435.38 $0.00 $149,225.42 $404,660.80