February 14, 2023
Prospect Construction, Inc.
ATTN: Seth Crites
116 23rd Street SE
Puyallup, WA 98372
Project: Pump Station 14 Relocation
City of Bremerton Project No. 4545
Re: Notice to Proceed
Dear Seth:
The City issued the Limited Notice to Proceed for the pre-construction phase of the
project on November 17, 2022. This phase lasted 90 calendar days. We are now
issuing the Notice to Proceed for the remainder of the project, which allows you
to perform construction activities at the site. The effective date for this notice is
February 14, 2023. The contract time is 450 calendar days for this phase, therefore,
the current Substantial Completion Date is May 9, 2024. Please send invoices
for this project to: engineeringap@ci.bremerton.wa.us.
Please contact me at (360) 473-2312 or via e-mail at william.davis@ci.bremerton.wa.us
if you have any questions or concerns.
Sincerely,
Bill Davis
Managing Engineer – Utilities
Cc: Project File
Ned Lever, City Engineer
Noreen Bolo, Project Assistant