Loading...
HomeMy WebLinkAbout1 - Original Submission_ 20240327_4545_Change Order No. 1 with Prospect_CITY OF BREMERTON CHANGE ORDER CONTRACT CHANGE ORDER NO:1 PROJECT NAME:Pump Station 14 Relocation PROJECT NO:4545 CONTRACTOR: Prospect Construction, Inc. ORIGINAL CONTRACT AMOUNT:$2,694,200.96 DAYS: 540 PREVIOUSLY APPROVED CHANGES: N/A DAYS: 0 THIS CHANGE:N/A DAYS: 52 REVISED CONTRACT AMOUNT:N/A DAYS: 592 This Change Order covers changes to the subject contract as described herein. The Contractor shall construct, furnish equipment and materials, and perform all work as necessary or required to complete the Change Order Items. The increase or decrease in contract price shown below includes any applicable taxes. ________________________________________________________________________________Rule 170Rule 171DESCRIPTION OF CHANGES INCREASE IN CONTRACT AMOUNT ($) (DECREASE) IN CONTRACT AMOUNT ($) Due to delays associated with receiving Cummins emergency power generation equipment, 52 calendar days are added to the contract. Contract calendar days are increased from 540 to 592 days. The Substantial Completion date is revised from May 9, 2024 to June 30, 2024. 0 0 NET CHANGE IN CONTRACT AMOUNT INCREASE OR (DECREASE) 0 0 ESTIMATED SALES TAX AT 9.2%0 0 TOTAL INCLUDING SALES TAX 0 0 Contractor acknowledges and accepts that this Change Order constitutes final settlement of all claims of any kind or nature arising from or connected with any work either covered or affected by this Change DocuSign Envelope ID: 2F38EFC0-9D8F-4279-B175-E3F5B8ECCC00 CONTRACT CHANGE ORDER NO:_1_ PROJECT NAME:Pump Station 14 Relocation Page 2 of 2 Order, including, without limitation, claims related to contract time, on-site or home office overhead, or lost profits. Nothing in this Change Order shall limit the City’s right to bring a claim for past performance. The undersigned Contractor approves the foregoing Change Order as to the changes, if any, in the contract price specified for each item, including any and all supervision costs and other miscellaneous costs relating to the change in work, and as to the extension of time allowed, if any, for completion of the entire work due to said Change Order. This document will become a supplement of the contract and all provisions will apply hereto. It is understood that this Change Order shall be effective when approved by the City of Bremerton. The parties whose names appear below warrant that they are authorized to enter into a change order that is binding on the parties of this contract. In addition, Contractor warrants that it has or will inform the surety of this change, and shall take appropriate action to modify any bonds required under the contract to address this change. CONTRACTOR Accepted: DATE: PROJECT MANAGER Recommended: DATE: CITY ENGINEER Council action is required as project cost will exceed approved budget.†Yes †No Council action is required as change exceeds Mayors authority per BMC 2.76.110. †Yes † No Recommended: DATE: DIRECTOR OF PUBLIC WORKS AND UTILITIES Recommended: DATE: MAYOR Approved: DATE: APPROVED AS TO FORM:ATTEST: Bremerton City Attorney City Clerk Seth Crites Digitally signed by Seth CritesDN: C=US, E=scrites@prospectconst.com, O=Prospect Construction, OU=Project Manager, CN=Seth Crites Date: 2024.03.29 07:31:50-07'00' 3/29/24 3/29/24 Ned Lever Digitally signed by Ned LeverDN: E=Ned.Lever@ci.bremerton.wa.us, CN=Ned Lever, OU=PW Engineering, OU=Domain Users, DC=ci, DC=bremerton, DC=wa, DC=us Reason: I am approving this document Date: 2024.03.29 08:39:44-07'00' DocuSign Envelope ID: 2F38EFC0-9D8F-4279-B175-E3F5B8ECCC00 4/8/2024