HomeMy WebLinkAbout1 - Original Submission_ 20230726_325011_Contract Modification No. 4 with HDRPage 1 of 2 Wastewater Salinity Impact Study Contract Modification No. 4
CONTRACT MODIFICATION AGREEMENT NO. 4 BETWEEN THE CITY OF BREMERTON AND HDR ENGINEERING, INC. PROJECT: Wastewater Salinity Impact Study CONSULTANT: HDR Engineering, Inc. DATE: July 26, 2023 THIS CONTRACT MODIFICATION AGREEMENT SPECIFICALLY AMENDS THE
Wastewater Salinity Impact Study AGREEMENT (the "Contract") entered into between the City of Bremerton and HDR Engineering, Inc. on September 5, 2019, and as modified on September 1, 2020, May 13, 2021 and May 26, 2022. All provisions in the Contract shall remain in full force and effect except as expressly modified by this document.
For valuable consideration and by mutual consent of the parties, the modifications to the Contract are as follows: I. Section I. Scope , is modified as follows:
There is no change to the contract scope. Section II. Term , is modified as follows: The contract end date is extended to July 31, 2024. Section III. Compensation , is modified as follows: There is no change to the contract amount. The original contract amount of $231,900 has not
been modified by previous contract modifications. II. Consultant accepts all requirements of this Contract Modification by endorsing below. Consultant further agrees that this Contract Modification constitutes full and final settlement of all of the Consultant’s claims for contract time and for all costs of any kind, including without limitation, costs of delays related to any work either covered or affected by this Contract Modification, claims related to on-site or home office overhead, or lost profits. This Contract Modification does not limit the City’s right to bring a claim for past performance. The undersigned consultant approves the foregoing Contract Modification as to the changes, if any, in the contract price specified for each item, including any and all supervision costs and other miscellaneous costs relating to the change in work, and as to the extension of time allowed, if any, for completion of the entire work due to said Contract Modification.
DocuSign Envelope ID: ECDC45C6-C227-4E55-BCE1-E933C59B1017
Page 2 of 2 Wastewater Salinity Impact Study Contract Modification No. 4
This document will become a supplement of the contract and all provisions will apply hereto. It is understood that this Contract Modification shall be effective when approved by the City
of Bremerton. The parties whose names appear below warrant that they are authorized to enter into a contract modification that is binding on the parties of this contract. In addition, Consultant warrants that it has or will inform the surety of this change, and shall take appropriate action
to modify any bonds required under the contract to address this change. IN WITNESS WHEREOF, the parties have executed this Contract Modification on the day and year first written above.
City Engineer / Public Works Director approved to process _________________________ (Initials and Date) HDR ENGINEERING, INC. THE CITY OF BREMERTON
By: By:
Print Name: Rob Berman Print Name: Greg Wheeler Its: Senior Vice President Its: Mayor Date: Date:
APPROVED AS TO FORM: ATTEST: By: By:
KYLIE J. FINNELL, Bremerton City Attorney ANGELA HOOVER, City Clerk NOTICES TO BE SENT TO: NOTICES TO BE SENT TO: HDR Engineering, Inc. Attn: Angela Hoover
Attn: Eric Bergstrom City of Bremerton 929 108th Avenue NE, Suite 1300 345 6th Street, Suite 100 Bellevue, WA 98004 Bremerton, WA 98337-1891
R:\Legal\Legal\Forms\FORMS ON COBWEB\Contract Modification Rev. 09 2021.docx
Ned Lever
Digitally signed by Ned Lever
DN: C=US, E=ned.lever@ci.bremerton.wa.us, O=City of Bremerton, OU=Engineering, CN=Ned LeverReason: I am approving this documentDate: 2023.07.28 09:29:35-07'00'
DocuSign Envelope ID: ECDC45C6-C227-4E55-BCE1-E933C59B1017
8/2/2023 8/2/2023