HomeMy WebLinkAbout1 - Original Submission_ CO #10 - DBE - O'Bunco Added Scope - ACI ExecutedDocusign Envelope ID: 3D15766B-16DE-470E-BE46-C39517B4D8EB City of Bremerton, City Attorney 3/17/2025 3/17/2025 Docusign Envelope ID: 3D15766B-16DE-470E-BE46-C39517B4D8EB CHANGE ORDER SUPPLEMENTAL DOCUMENTS 1. Change Order Checklist 2. DBE Utilization Certification Form (Active Construction, Inc.) 3. UDBE Written Confirmation Document (O'Bunco) 4. DBE Bid Item Breakdown 5. Bid Proposal (Survey Bid Items) 6. O'Bunco Prior Billing - Application #4. (billing for WCD #7 & RFI 15) 7. WCD007 - Modified Curb Design Revisions 8. RFI-015 - CB27 Conflict with Modified Curb 9. WCD #013 - Median Nose RRFB 10. WCD-013-014-CO-03 (O'Bunco Forward Pricing - COR #03) 11. Change Order Independent Cost Estimate Docusign Envelope ID: 3D15766B-16DE-470E-BE46-C39517B4D8EB WSDOT Local Agency Guidelines M 36-63.42 Page 52-17 September 2023 Appendix 52.106 Change Order Checklist Change Order Question Yes No N/A 1.Does the change order alter the termini, character, or scope of the work?☐☐☐ If yes, you must have H & LP approval to be eligible for federal funds.☐☐☐ If yes, you must submit a revised Page 1 of the prospectus.☐☐☐ 2.Is the Change Order over $7,500.00 and outside the scope of work?☐☐☐ If yes, the change cannot be a change order and must be an independent work.☐☐☐ 3.Does the Change Order detail all items involved with the change?☐☐☐ 4.Does the Change Order include an adjustment in working days?☐☐☐ If yes, the time extension must be stated in the Change Order.☐☐☐ If yes, an independent engineer’s estimate of time must be included to document the extension. ☐☐☐ If no, that must be stated in the Change Order.☐☐☐ 5.Does the Change Order alter the DBE Condition of Award?☐☐☐ If yes, you must obtain concurrence form Local Programs.☐☐☐ If yes, you must obtain the DBE’s signature on the Change Order.☐☐☐ 6.Does the Change Order involve a material substitution?☐☐☐ If yes, you must determine if a material credit is appropriate.☐☐☐ 7.If Change Order work started prior to it’s execution, prior verbal approval by the Approving Authority must be granted and documented. ☐☐☐ 8.Has the Change Order been signed by the contractor?☐☐☐ 9.Has the Change Order been executed by the Approving Authority?☐☐☐ If you are a “non CA Agency”, you must have the acting CA Authority’s approval.☐☐☐ 10.Has an independent engineer’s estimate justifying the costs and time extensions been completed and documented? ☐☐☐ 11.Has a detailed memo outlining the chronology of events, basis of need, costs and working days been prepared and placed in the file accompanying the Change Order? ☐☐☐ Appendix 52.106 Change Order Page 1 of 1Revised 4/30/2014 X X X X X X X X X X X PENDING X X X PENDING PENDING PENDING X X X Docusign Envelope ID: 3D15766B-16DE-470E-BE46-C39517B4D8EB Docusign Envelope ID: 3D15766B-16DE-470E-BE46-C39517B4D8EB Docusign Envelope ID: 3D15766B-16DE-470E-BE46-C39517B4D8EB Docusign Envelope ID: 3D15766B-16DE-470E-BE46-C39517B4D8EB DBE BID ITEM BREAKDOWN CITY OF BREMERTON WASHINGTON & 11TH STREET IMPROVEMENTS BID DATE:6/1/2023 11:00AM Name of DBE:Bid Item:Full/Partial:Description:Unit Price:Total Unit Cost: Amt Applied Towards Goal: O'BUNCO ENGINEERING A1 PARTIAL 1 LS SUB MOBILIZATION $9,689.00 $9,689.00 $9,689.00 O'BUNCO ENGINEERING A114 FULL 1 LS STRUCTURE SURVEYING $7,940.00 $7,940.00 $7,940.00 O'BUNCO ENGINEERING A115 FULL 1 LS ROADWAY SURVEYING $41,685.00 $41,685.00 $41,685.00 O'BUNCO ENGINEERING A122 PARTIAL 2 EA MONUMENT SURVEY $568.00 $1,136.00 $1,136.00 O'BUNCO ENGINEERING A123 PARTIAL 4 EA MONUMENT SURVEY $568.00 $2,272.00 $2,272.00 O'BUNCO ENGINEERING A127 FULL 1 LS ADA FEATURES SURVEYING $5,955.00 $5,955.00 $5,955.00 O'BUNCO ENGINEERING B33 FULL 1 LS ROADWAY SURVEYING $3,970.00 $3,970.00 $3,970.00 O'BUNCO ENGINEERING B35 PARTIAL 1 EA MONUMENT SURVEY $568.00 $568.00 $568.00 O'BUNCO ENGINEERING B42 FULL 1 LS ADA FEATURES SURVEYING $1,985.00 $1,985.00 $1,985.00 O'BUNCO ENGINEERING C17 FULL 1 LS ROADWAY SURVEYING $1,985.00 $1,985.00 $1,985.00 Subtotal:$77,185.00 $77,185.00 Name of DBE:Bid Item:Full/Partial:Description:Unit Price:Total Unit Cost:Amt Applied Towards Goal: CASTANEDA LANDSCAPING A42 FULL 6 EA PSIPE - EASTERN WHITE PINE (6' HT)$300.00 $1,800.00 $1,800.00 CASTANEDA LANDSCAPING A43 FULL 3 EA PSIPE - EXCELSA CEDAR (6' HT)$300.00 $900.00 $900.00 CASTANEDA LANDSCAPING A44 FULL 3 EA PSIPE - INCENSE CEDAR (6' HT)$300.00 $900.00 $900.00 CASTANEDA LANDSCAPING A45 FULL 2 EA PSIPE - SHORE PINE (6' HT)$300.00 $600.00 $600.00 CASTANEDA LANDSCAPING A46 FULL 11 EA PSIPE - MUSASHINO ZELKOVA (2" CAL)$500.00 $5,500.00 $5,500.00 CASTANEDA LANDSCAPING A47 FULL 7 EA PSIPE - SCARLET SENTINEL MAPLE (2" CAL)$500.00 $3,500.00 $3,500.00 CASTANEDA LANDSCAPING A48 FULL 83 EA PSIPE - PACIFIC NINEBARK $25.00 $2,075.00 $2,075.00 CASTANEDA LANDSCAPING A49 FULL 66 EA PSIPE - OCEANSPRAY $25.00 $1,650.00 $1,650.00 CASTANEDA LANDSCAPING A50 FULL 33 EA PSIPE - THIMBLEBERRY $25.00 $825.00 $825.00 CASTANEDA LANDSCAPING A51 FULL 82 EA PSIPE - RED FLOWERING CURRANT $25.00 $2,050.00 $2,050.00 CASTANEDA LANDSCAPING A52 FULL 67 EA PSIPE - LEWIS MOCKORANGE $23.00 $1,541.00 $1,541.00 CASTANEDA LANDSCAPING A53 FULL 17 EA PSIPE - LITTLE BUNNY FOUNTAIN GRASS $18.00 $306.00 $306.00 CASTANEDA LANDSCAPING A54 FULL 4 EA PSIPE - DWARF MUGO PINE $25.00 $100.00 $100.00 CASTANEDA LANDSCAPING A55 FULL 55 EA PSIPE - MOUNT VERNON LAUREL $20.00 $1,100.00 $1,100.00 CASTANEDA LANDSCAPING A56 FULL 198 EA PSIPE - GEORGIA BLUE SPEEDWELL $20.00 $3,960.00 $3,960.00 CASTANEDA LANDSCAPING A57 FULL 60 EA PSIPE - EVERGREEN CANDYTUFT $20.00 $1,200.00 $1,200.00 CASTANEDA LANDSCAPING A58 FULL 88 EA PSIPE - LITTLE GEM CANDYTUFT $20.00 $1,760.00 $1,760.00 CASTANEDA LANDSCAPING A59 FULL 88 EA PSIPE - CREEPING OREGON GRAPE $18.00 $1,584.00 $1,584.00 CASTANEDA LANDSCAPING A60 FULL 70 EA PSIPE - WALL GERMANDER $20.00 $1,400.00 $1,400.00 CASTANEDA LANDSCAPING A61 FULL 52 EA PSIPE - GOLDMOSS STONECROP $20.00 $1,040.00 $1,040.00 CASTANEDA LANDSCAPING A62 FULL 53 EA PSIPE - ANGELINA SPREADING STONECROP $20.00 $1,060.00 $1,060.00 CASTANEDA LANDSCAPING A63 FULL 52 EA PSIPE - BROADLEAF STONECROP $20.00 $1,040.00 $1,040.00 CASTANEDA LANDSCAPING A64 FULL 53 EA PSIPE - WOODLAND STONECROP $20.00 $1,060.00 $1,060.00 CASTANEDA LANDSCAPING A65 FULL 715 LF ROOT BARRIER $16.00 $11,440.00 $11,440.00 CASTANEDA LANDSCAPING A66 FULL 285 SY SEEDED LAWN INSTALLATION $3.60 $1,026.00 $1,026.00 CASTANEDA LANDSCAPING A67 FULL 60 SY MEDIUM COMPOST $11.60 $696.00 $696.00 CASTANEDA LANDSCAPING A68 FULL 430 SY TOPSOIL TYPE A $8.50 $3,655.00 $3,655.00 CASTANEDA LANDSCAPING A69 FULL 100 CY SANDY LOAM $50.00 $5,000.00 $5,000.00 CASTANEDA LANDSCAPING A70 FULL 910 SY BARK OR WOOD CHIP MULCH $5.50 $5,005.00 $5,005.00 CASTANEDA LANDSCAPING A72 FULL 1 LS IRRIGATION SYSTEM $109,250.00 $109,250.00 $109,250.00 Subtotal:$173,023.00 $173,023.00 Name of DBE:Bid Item:Full/Partial:Description:Unit Price:Total Unit Cost: Amt Applied Towards Goal: SUBSURFACE CONSTRUCTION A1 PARTIAL 1 LS SUB MOBILIZATION $21,600.00 $21,600.00 $21,600.00 SUBSURFACE CONSTRUCTION A29 FULL 1040 LF SHAFT 30 IN. DIAM $142.00 $147,680.00 $147,680.00 SUBSURFACE CONSTRUCTION A30 FULL 940 LF FURNISHING SOLDIER PIPE HP14 X 73 $100.00 $94,000.00 $94,000.00 SUBSURFACE CONSTRUCTION A31 FULL 200 LF FURNISHING SOLDIER PIPE HP12 X 53 $75.00 $15,000.00 $15,000.00 SUBSURFACE CONSTRUCTION A32 FULL 3270 SF LAGGING $21.00 $68,670.00 $68,670.00 Subtotal:$346,950.00 $346,950.00 Name of DBE:Bid Item:Full/Partial:Description:Unit Price:Total Unit Cost: Amt Applied Towards Goal: BURLEY PRODUCTS A1 PARTIAL 1 LS SUB MOBILIZATION $3,000.00 $3,000.00 $3,000.00 BURLEY PRODUCTS A116 FULL 540 LF PEDESTRIAN HANDRAIL $288.25 $155,655.00 $155,655.00 Subtotal:$158,655.00 $158,655.00 $755,813.00 Quantity: Quantity: TOTAL DBE AMOUNT: Quantity: Quantity: Docusign Envelope ID: 3D15766B-16DE-470E-BE46-C39517B4D8EB O'Bunco Prior Billing - Application #4. (billing for WCD #7 & RFI 15) Docusign Envelope ID: 3D15766B-16DE-470E-BE46-C39517B4D8EB CO #6 - PE#4 - Below the line payment+12% = $1624+12% = $1304.80BI #33 - PE#5Docusign Envelope ID: 3D15766B-16DE-470E-BE46-C39517B4D8EB WCD007 - Modified Curb Design Revisions Docusign Envelope ID: 3D15766B-16DE-470E-BE46-C39517B4D8EB Docusign Envelope ID: 3D15766B-16DE-470E-BE46-C39517B4D8EB RFI-015 - CB27 Conflict with Modified Curb Docusign Envelope ID: 3D15766B-16DE-470E-BE46-C39517B4D8EB Public Works and Utilities Department 345 6th Street, Suite 100 · Bremerton, WA 983 · (360) 473-5270 · FAX (360) 473-5398 Request for Information Date: _____________________________________________ Request No.: _________________________________________ Project: ____________________________________________________________________________________________________ Project No.: __________________________________________ Contractor: ___________________________________________ Information Request Initiated By: _______________________________________________________________________________ Regarding: ___________________________________________ Specification Section: ___________________________________ Prepared By: ________________________________________________________________ Date: _______________________ Request: (For Contractor’s Use) Response Assigned To: Project Manager Project Engineer Resident Project Representative Response: (For City’s Use) Signed: ______________________________________________________________________ Date: ______________________ cc: ____________________________________________________________________________________________________ 112 RFIs\112.015 RFI No_015 CB27 Conflict with Modified Curb\RFI-015 - CB27 Conflict with Modified Curb - Sub.07.08.23 Response.pdf 8/7/23 015 Washington & 11th St. Improvements 315-026 Active Construction, Inc. Steven Crandall, Sr. CB27 Conflict with Modified Curb sheets 38, 40 & 88 Plan sheet 38 & 40 depict CB27 being installed into a portion of the modified curb. The back of the grate for CB27 would be at the face of the curb, which would put the frame, including the flange, and the CB into the modified curb approximately .33' - .5'. Also, CB27 is deeper than the 1' of space between finish grade and the top of the footing for the modified curb. Please advise how the modified curb and footing are built around this structure. Steven Crandall, Sr 8/3/23 Nick Ataie (City of Bremerton), Ian Lee (Skillings) 4 4 A forthcoming revision to Plan Sheets 37 (CB 29), 38 (CB 27), and 40 (CB 27 Profile) will be provided to show relocation of CB 27 and CB 29 in order to eliminate overlap of structures at the proposed modified curb. The proposed (revised) CB station and offsets are as follows: CB 27 - WA 20+30.82, 30.60’ LT CB 29 - WA 18+03.98, 34.98’ LT Per verbal discussions, relocation of the CB's noted above away from the wall will require installation of an asphalt wedge curb (at each relocated CB) during paving operations in order to direct storm water flow. 8/11/23 per email response Docusign Envelope ID: 3D15766B-16DE-470E-BE46-C39517B4D8EB WCD #013 - Median Nose RRFB Docusign Envelope ID: 3D15766B-16DE-470E-BE46-C39517B4D8EB PAGE 1 OF 1 CITY OF BREMERTON WORK CHANGE DIRECTIVE (WCD) WCD #: _______ Date: ________ YOU ARE DIRECTED TO PROCEED PROMPTLY WITH THE FOLLOWING CHANGE(S): ATTACHMENT(S): If a claim is made that the above change(s) have affected Contract Price or Contract Times any claim for a Change Order is based thereon will involve one or more of the following methods of determining the effect of the change(s). The Change Order will be executed in accordance with Section 1-04.4 of the WSDOT Standard Specifications, or Article 10 of the General Conditions. Method of determining change in Contract Price: Method of determining change in Contract Times: Unit Price Contractor’s Records Lump Sum Engineer’s Records Time & Materials Other: Other: Estimated increase (decrease) in Contract Price: Estimated increase (decrease) in Contract Times: $ . Substantial Completion: 0 days; If the change involves an increase, the estimated Ready for final payment: 0 days; amount is not to be exceeded without further If the change involves an increase, the estimated times authorization. are not to be exceeded without further authorization. RECOMMENDED: AUTHORIZED: CONTRACTOR CITY OF BREMERTON By: ____________________________________________ By: _________________________________________ Project Name: _______________ Project #: _______________ Contractor: _______________ NTP Date: _______________ Modifications associated with minor adjustment of median island nose geometry at the intersection of 11th Street and Pleasant Ave. The engineer has provided associatedrevisions on Plan Sheet 25 (Traffic Islands) and Plan Sheet 75 (Pavement Marking Plan). Modifications associated with minor shifting of the Rectangular Rapid FlashingBeacon (RRFB) at the northeast corner of the roundabout in order to provide an acceptable push button reach distance from the proposed curb ramp. The engineer hasprovided associated revisions on Plan Sheet 55 (Curb Ramp), Plan Sheet 58 (Illumination / Electrical), Plan Sheet 64 (RRFB), and Plan Sheet 77 (Pavement Marking). The changes provided under this WCD do not include significant alternation of estimated quantities, bid items, or scope of work in accordance with 1-04.4 (Changes).Minor additional survey costs associated with the changes included in this WCD, as attached, for DBE subcontractor O’Bunco Engineering Inc will be processed through aformal change order requiring WSDOT concurrence in accordance with special provision 1-07.11 (Requirements for Nondiscrimination) and will include allowablesubcontractor markup. Method of determining any change(s) in contract price will be based on existing unit price items. There is no change in contract time. WASHINGTON AND 11TH STREET IMPROVEMENTS 315026, STPUL-9918(017) ACTIVE CONSTRUCTION, INC. 8/7/2023 Plan Sheet 25, 75 Revisions (Median Nose Traffic Island), Plan Sheet 55, 58, 64, 77 Revisions (RRFB) _______________________________ Nick Ataie, PE (Project Manager) X 728.00 013 04/25/24 Existing Unit Price Items N/A - No Change X Additional survey cost proposal from O’Bunco Engineering Inc Change OrderX Nick Ataie Digitally signed by Nick AtaieUser: Nick.AtaieCity of Bremerton - PW&U Engineering Divisionnick.ataie@ci.bremerton.wa.usDate: 04/25/2024Time: 9:45:33 AMFile: WCD #013 - Median Island Nose.pdf Docusign Envelope ID: 3D15766B-16DE-470E-BE46-C39517B4D8EB WCD-013 PLAN SHEET MARKUPS (Median Nose TrafficIsland) Docusign Envelope ID: 3D15766B-16DE-470E-BE46-C39517B4D8EB BREMERTON WA TRAFFIC ISLANDS WASHINGTON & 11TH IMPROVEMENT PROJECT 11TH STREET WA LINE 11TH STREET WA LINE 5016 Lacey Boulevard SE, Lacey, Washington 98503 (360) 491-3399 Fax (360) 491-385704/17/2024 Docusign Envelope ID: 3D15766B-16DE-470E-BE46-C39517B4D8EB 5016 Lacey Boulevard SE, Lacey, Washington 98503 (360) 491-3399 Fax (360) 491-3857 BREMERTON WA PAVEMENT MARKING PLAN 1 WASHINGTON & 11TH IMPROVEMENT PROJECT 11TH STREET PACIFIC AVENUEPLEASANT AVE.04/17/2024 Docusign Envelope ID: 3D15766B-16DE-470E-BE46-C39517B4D8EB WCD-013PLAN SHEET MARKUPS (RRFB) Docusign Envelope ID: 3D15766B-16DE-470E-BE46-C39517B4D8EB XXXXXXXXXX\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\S\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\S5016 Lacey Boulevard SE, Lacey, Washington 98503 (360) 491-3399 Fax (360) 491-3857 BREMERTON WA EAST RAB ADA RAMPS & SOUTH OF MANNETE BIKE RAMPS WASHINGTON & 11TH IMPROVEMENT PROJECT 04/17/2024 Docusign Envelope ID: 3D15766B-16DE-470E-BE46-C39517B4D8EB CO """X X CCCCCCCCCC\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\\ W W W W W W W W W W W W W W W W W W W W W W W W W W W W G G G G G G G G G G G G G G G G G G G G G G G G G G GGGSS SS SS SS SS SS SS SS SS SS SS SS SS SS X X X X X X X X X X X TS TS TS TS TS TS TS TS TS TSTSTSTSTSTSTS TS TS TS XXXXTBTBTB TB TB TBTBTB LPLPLPLPTT T TT TTE S SEEE LP ECO CO WWW W W W W W OHU OHU OHU OHU OHU OHU OHU OHUOHUOHU OHUOHUOHU OHUOHUOHUOHUSDSDSDSD SD SD SD SD SD SD SD SD SD SD SD SD SD SD SD SD SD SDSDSDSDSDSDSDSDSDSDSDSDSDSDSDSDSDLPBREMERTON WA ILLUMINATION PLANS WASHINGTON & 11TH IMPROVEMENT PROJECT WASHINGTON AVE.MANETTE BRIDGEMB LINEWA LINE WA LINE · · · · · · ·· ·· 5016 Lacey Boulevard SE, Lacey, Washington 98503 (360) 491-3399 Fax (360) 491-385704/17/2024 Docusign Envelope ID: 3D15766B-16DE-470E-BE46-C39517B4D8EB "C C C C C C C C C CCCCCCCC C C C WWWWWWWWWWWWWGGGGGGGGGGGGG G SSSSWOHUOHUOHUSD SD SDSDSD SDSDSDSDSDSDSD SD SD SD "C C C C C C C C C CCCCCCCC C C C WWWWWWWWWWWWWGGGGGGGGGGGGG G SSSSWOHUOHUOHUSD SD SDSDSD SDSDSDSDSDSDSD SD SD SD "C C C C C C C C C CCCCCCCC C C C WWWWWWWWWWWWWGGGGGGGGGGGGG G SSSSWOHUOHUOHUSD SD SDSDSD SDSDSDSDSDSDSD SD SD SD XXXLPTTTTWOHUSDSDSDSDSDSDSDSDSDSD SD SD SD SD SD SD SDSDSDSDSDXXXLPTTTTWOHUSDSDSDSDSDSDSDSDSDSD SD SD SD SD SD SD SDSDSDSDSDXXXLPTTTTWOHUSDSDSDSDSDSDSDSDSDSD SD SD SD SD SD SD SDSDSDSDSDBREMERTON WA RRFB PLANS WASHINGTON & 11TH IMPROVEMENT PROJECTMANETTE BRIDGEWASHINGTON AVE5016 Lacey Boulevard SE, Lacey, Washington 98503 (360) 491-3399 Fax (360) 491-385704/17/2024 Docusign Envelope ID: 3D15766B-16DE-470E-BE46-C39517B4D8EB 5016 Lacey Boulevard SE, Lacey, Washington 98503 (360) 491-3399 Fax (360) 491-3857 BREMERTON WA PAVEMENT MARKING PLAN 3 WASHINGTON & 11TH IMPROVEMENT PROJECT WASHINGTON AVE.MANETTE BRIDGEMB LINEWA LINE WASHINGTON A V E . WA LINE 04/17/2024 Docusign Envelope ID: 3D15766B-16DE-470E-BE46-C39517B4D8EB WCD-013ADDITIONAL SURVEYCOST PROPOSAL (O’Bunco Engineering Inc) Docusign Envelope ID: 3D15766B-16DE-470E-BE46-C39517B4D8EB O’bunco Engineering Inc Rev 5/16/06 O’Bunco Engineering Inc. 1042 West James Street Kent, WA 98032 (425) 451-7300 Change Order Change Order No: 3____________________________ Date: 04/24/2024 Project Name: Washington & 11th Street Improv. Client Name: ACI Project No.: 2023-113 Address: PO Box 430 Requested By: Steve Crandall Puyallup, WA 98371 Phone/Cell: 253-722-8852 Change Order Needs: EXTRA-WCD-013 MEDIAN NOSE REVISION & WCD-014-RRFB, ILLUMINATION & CURB RAMP: 1) Re-calculations and quality control checks on the field data for the revision of the ada ramp, RRFB at the ada ramp, Median nose revision and illumination revision. A total cost of $650.00. Requested by: Steve Crandall Cost for this Change Order is: $650.00 O’Bunco Engineering Inc. Acknowledgment and Authorization to Proceed: Name: Eric Sepolen The undersigned hereby acknowledges this change order request and authorizes O’bunco Engineering to proceed accordingly. Project Manager Signature: 33650 6th Ave. S, Ste. 102 Steve Crandall Federal Way, Wa 98003 By: Title: Project Manager : Date: Docusign Envelope ID: 3D15766B-16DE-470E-BE46-C39517B4D8EB WCD-013ADDITIONAL SURVEYCOST PROPOSAL (O’Bunco Engineering Inc) Docusign Envelope ID: 3D15766B-16DE-470E-BE46-C39517B4D8EB CHANGE ORDER Independent Cost Estimate Docusign Envelope ID: 3D15766B-16DE-470E-BE46-C39517B4D8EB Project Name:Washington and 11th ImprovementsProject No:315026CO No.:10Date:Description of Work:Work by Subcontractor?:X (mark "x" if yes)Prime Contractor:Active ConstructionSub-Contractor:O'BuncoLABORSTRAIGHT TIME OVERTIME DOLLARNAME OCCUPATION HOURS WWR HOURS WWR AMOUNTO'Bunco - Office Construction Site Surveyor683.95$ -$ 503.70$ O'Bunco - Site