CONTRACT MODIFICATION AGREEMENT NO. 1 BETWEEN THE CITY OF BREMERTON AND CONSOR ENGINEERS
PROJECT: Well 9R Site Development
CONSULTANT: CONSOR North America, Inc (doing business as Murraysmith, Inc.)
DATE: March 30, 2023
THIS CONTRACT MODIFICATION AGREEMENT SPECIFICALLY AMENDS THE
Well 9R Site Development AGREEMENT (the "Contract") entered into between the City of Bremerton and CONSOR Engineers on April 22, 2022.
All provisions in the Contract shall remain in full force and effect except as expressly modified by this document.
For valuable consideration and by mutual consent of the parties, the modifications to the Contract are as follows: I.
Section I. Scope , is modified as follows:
See attached Exhibit A.
Section II. Term_____, is modified as follows: The Consultant shall complete the work described in this Contract Modification Agreement by
December 31, 2023.
Section III. Compensation_______, is modified as follows: The original contract amount was $95,599.00. The City shall pay the Consultant for the additional work described above, based on time and materials, up to an amount not to exceed $22,300, for
a total amended contract amount of $117,899 including this Contract Modification. Fees and
compensation are shown in both Exhibit A and Exhibit B.
II.
Consultant accepts all requirements of this Contract Modification by endorsing below. Consultant further agrees that this Contract Modification constitutes full and final settlement of all of the Consultant’s claims for contract time and for all costs of any kind, including without limitation, costs of delays related to any work either covered or affected by this Contract Modification, claims related to on-site or home office overhead, or lost
profits. This Contract Modification does not limit the City’s right to bring a claim for past performance.
The undersigned consultant approves the foregoing Contract Modification as to the changes, if any, in the contract price specified for each item, including any and all supervision costs
DocuSign Envelope ID: 62D93BC3-D5E8-446E-AB31-F39C600EA3D7
Page 2 of 2 Contract Modification #1 Well 9R Site Development Bremerton/CONSOR March 2023
and other miscellaneous costs relating to the change in work, and as to the extension of time allowed, if any, for completion of the entire work due to said Contract Modification.
This document will become a supplement of the contract and all provisions will apply hereto. It is understood that this Contract Modification shall be effective when approved by the City of Bremerton.
The parties whose names appear below warrant that they are authorized to enter into a contract modification that is binding on the parties of this contract. In addition, Consultant warrants that it has or will inform the surety of this change, and shall take appropriate action to modify any bonds required under the contract to address this change.
IN WITNESS WHEREOF, the parties have executed this Contract Modification on the day and year first written above.
City Engineer / Public Works Director approved to process _________________________ (Initials and Date)
CONSULTANT THE CITY OF BREMERTON
By: By:
Print Name: Print Name:
Its: Its:
Date:
ATTEST:
By:
ANGELA HOOVER, City Clerk
NOTICES TO BE SENT TO:
Angela Hoover City of Bremerton 345 Sixth Street, Suite 100 Bremerton, WA 98337
Date:
APPROVED AS TO FORM:
By:
KYLIE J. FINNELL, Bremerton City Attorney
NOTICES TO BE SENT TO:
Erika Schuyler CONSOR North America, Inc600 University Street, Suite 300 Seattle, WA 98101
R:\Legal\Legal\Forms\FORMS ON COBWEB\Contract Modification Rev. 09 2021.docx
Greg Wheeler
Mayor
Erika Schuyler
Regional Manager
DocuSign Envelope ID: 62D93BC3-D5E8-446E-AB31-F39C600EA3D7
4/18/2023
4/18/2023 4/18/2023
Contract Modification #1 Well 9 Site Development
Bremerton/CONSOR March 2023
EXHIBIT A – SCOPE OF WORK
Well 9 Site Development with CONSOR Engineering (formerly known as Murraysmith)
SUMMARY OF ADDITIONAL SCOPE:
Task 4 – Management Reserve: $15,000 is added to Management Reserve for additional scope
to be determined. Additional scope will support the follow-on well drilling contract and
activities will include: preparing plans, details, and specifications for erosion control and pump
test discharge water conveyance; coordinating with permitting agencies including Kitsap
County, WDFW and DNR; providing additional geotechnical support.
Task 5 (New Task) – Geotechnical Construction Support Services: Added to the contract to
support the geotechnical observation and any other additional consultation services as
requested during construction. The following 6 pages are the scope of work from Robinson
Noble to support this task.
DocuSign Envelope ID: 62D93BC3-D5E8-446E-AB31-F39C600EA3D7
2105 South C Street 17625 130th Avenue NE, Suite 102
Tacoma, Washington 98402 www.robinson-noble.com Woodinville, Washington 98072
P: 253.475.7711 | F: 253.472.5846 P: 425.488.0599 | F: 425.488.2330
February 23, 2023
Mr. Peter Cunningham
Consor Engineers
600 University Street, Suite 300
Seattle, Washington 98101
Dear Peter,
Robinson Noble is pleased to present this proposal for geotechnical consultation services for
the City of Bremerton Well 9R Site Development project. Well 9 is currently located at 318
Northwest Firway Lane.
We have previously prepared a Revised Geotechnical Report dated July 19, 2022 and Ultrablock wall
designs for the project dated July 20, 2022. You have requested that we provide geotechnical
observation and consultation services for the Bremerton Well 9R Site Development project.
Scope of Work
The scope of services to be provided by Robinson Noble, Inc. is for construction observation and
consultation services, including the following:
Review our previous report and wall designs for the site.
Review contractor submittals.
Evaluate preparation of foundation subgrade.
o We have budgeted for 4, half-day site visits.
Evaluate pavement subgrade prior to paving.
o We have budgeted for 1, half-day site visit.
Observe construction of drainage for the block walls.
o We have budgeted for 2, half-day site visits.
Provide geotechnical consultation as requested.
Prepare daily field reports to document our observations and conclusions.
Attend meetings as needed. We anticipate one, 2-hour on-site meeting.
Additional services as requested by you.
Cost Estimate
Our services will be completed on a time-and-expense basis in accordance with our GENERAL
FEE SCHEDULE. The estimated cost of our services for the tasks described above is presented
in Table 1, below.
EXHIBIT A
CONSTRUCTION OBSERVATION SCOPE AND FEES FROM ROBINSON NOBLE (page 1 of 6)
DocuSign Envelope ID: 62D93BC3-D5E8-446E-AB31-F39C600EA3D7
Bremerton Well 9R Site Development
February 23, 2023
Page 2
Robinson Noble, Inc.
Table 1 – Estimated Costs
Task Estimated Robinson Noble Fees
Geotechnical Report and Submittals Review $500
Seven, half-day site visits including field reports $4,550
One, on-site meeting $1,250
Consultation as requested $1,000
Total Estimated Fees $7,300
A cost estimate indicates that Consultant will not invoice fees and expenses in excess of the
estimate or limitation amount without obtaining the Client’s agreement to do so, but it is not a
guarantee that the services will be completed for that amount.
We appreciate the opportunity to submit this proposal, and look forward to working with you on
this project. If this scope meets your approval, please let us know how you would like to
proceed with contracting.
Sincerely,
Robinson Noble, Inc.
Barbara A. Gallagher, PE
Associate Engineer
BAG:RBP:am
EXHIBIT A
CONSTRUCTION OBSERVATION SCOPE AND FEES FROM ROBINSON NOBLE (page 2 of 6)
DocuSign Envelope ID: 62D93BC3-D5E8-446E-AB31-F39C600EA3D7
EXHIBIT A
CONSTRUCTION OBSERVATION SCOPE AND FEES FROM ROBINSON NOBLE (page 3 of 6)
DocuSign Envelope ID: 62D93BC3-D5E8-446E-AB31-F39C600EA3D7
EXHIBIT A
CONSTRUCTION OBSERVATION SCOPE AND
FEES FROM ROBINSON NOBLE (page 4 of 6)
DocuSign Envelope ID: 62D93BC3-D5E8-446E-AB31-F39C600EA3D7
EXHIBIT ACONSTRUCTION
OBSERVATION SCOPE AND
FEES FROM ROBINSON NOBLE (page 5 of 6)
DocuSign Envelope ID: 62D93BC3-D5E8-446E-AB31-F39C600EA3D7
EXHIBIT A
CONSTRUCTION
OBSERVATION SCOPE AND FEES FROM ROBINSON
NOBLE (page 6 of 6)
DocuSign Envelope ID: 62D93BC3-D5E8-446E-AB31-F39C600EA3D7
Contract Modification #1 Well 9 Site Development
Bremerton/CONSOR March 2023
EXHIBIT B – COMPENSATION
Well 9 Site Development with CONSOR Engineering (formerly known as Murraysmith)
CONTRACT MODIFICATION #1
Item Description Amount
Task 4 Management Reserve $15,000
Task 5 Geotechnical construction observation and
support
$7,300
TOTAL $22,300
Notes:
1)Use of Management Reserve requires written authorization by the City. The Consultant
shall prepare a detailed scope with hourly breakdown upon request. Upon approval of
scope and cost, the City will provide written authorization to proceed with the work.