Executive Correspondence Routing Memo
(For electronic routing only)
Date: January 14, 2022
Description: Execute Change Order No. 1 with Active Construction, Inc. for the Oyster Bay Beach
Sewer Upgrades project. This change order will increase the contract amount by $187,317.59. The work
includes the addition of roadway, excavation and grinding along Shorewood Drive, additional
sawcutting, and two additional grinder pumps systems.
Fiscal Impact: This project is included in the 2022 Wastewater Capital Budget. This change order may be
administratively approved by the Mayor per BMC 2.76.110 and does not require City Council approval.
Action Requested: Review and signature and e-mail back to Noreen Bolo. This contract is being routed
electronically only.
Approval / Recommendation:
Managing Engineer: Recommended Initials/date _______________
City Engineer: Recommended Initials/date _______________
Contract Administrator: LASERFICHE
Finance: LASERFICHE
City Attorney: LASERFICHE/DOCUSIGN
Public Works Director: LASERFICHE/DOCUSIGN
City Clerk: LASERFICHE/DOCUSIGN
Please advise Noreen Bolo/Bill Davis when executed. Thank you.
1/14/22