HomeMy WebLinkAbout07/02/2025 4J
AGENDA BILL
CITY OF BREMERTON
4J
CITY COUNCIL
SUBJECT:Study SessionDate: June 25, 2025
Grant Agreement with WSDOT for Safe COUNCIL MEETING Date: July 2, 2025
Routes to Schools Improvements
Department: PW&U-Engineering
View Ridge Elementary Phase II
Presenter: Nick Ataie
Phone: (360) 473-2306
SUMMARY:
The 20252030Capital Improvement Plan(CIP)includes programmed funding for Phase 2 of Safe
Routes to School (SRTS) improvements serving View Ridge Elementary. The project scope of work
consists of a continuation of non-motorized improvements along Almira Drive between Ivy Road and
Riddell Rdas a continuation of Phase 1 improvements.In early 2025, the City was notified by
WSDOT that the project was selected to receive $5.9
Supplemental Transportation Budget under
appropriations from the Climate Commitment Act (CCA). The grant funding would be allocated to all
project phases includingpreliminary engineering, right of way, and construction. The original grant
request from the City included $600,000 in local matching funds, however, additional local revenues
will be required for non-eligible project costs and will be reflected in a mid-year budget adjustment.
The offered grant will be in WSDOT Standard Forms, with their standard terms and conditions.
ATTACHMENTS:
1.WSDOT Award Letter
2.Project Location Map
3.WSDOT State Funding Agreement (Blank)
FISCAL IMPACTS(Include Budgeted Amount):
This project is included inthe 20252030CIP. The preliminary estimated overall project budget is
approximately $7.5 millionincluding local revenues in transportation, stormwater, and wastewater
capital funds.
STUDY SESSION ACTION:Consent Agenda General Business Public Hearing
RECOMMENDED MOTION:
Move to approve the Grant Agreement with the Washington State Department of Transportation; and
authorize the Mayor to finalize and execute the agreement with substantially the same terms and
conditions as presented.
COUNCIL ACTION: Approve Deny Table Continue No Action
Form Updated 04/19/2024