SUBJECT:Study SessionDate: June 11, 2025
Professional Services Agreement with COUNCIL MEETING Date: June 18, 2025
Northwest Hydraulic Consultants, Inc. for the
Department: Public Works & Utilities
Parish Creek Fish Passage Barrier Removal
Presenter: D. Dinkuhn
Project
Phone: (360) 473-5331
SUMMARY:
The project consists of design and permitting for the removal ofa fish barrier culvert on Parish Creek
at West Belfair Valley Road. A new bridge crossing will be constructed with an approximate 40-foot
span.A scope of work was submitted, and a contract was negotiated in the amount of $690,749.
ATTACHMENTS:
1.Project Vicinity Map
2.Professional Services Agreementwith Northwest Hydraulic Consultants, Inc.
FISCAL IMPACTS(Include Budgeted Amount):
Project is included in the 2025 budget.
STUDY SESSION ACTION:Consent Agenda General Business Public Hearing
RECOMMENDED MOTION:
Move to approve the Professional Services Agreement with Northwest Hydraulic Consultants, Inc. for
the Parish Creek Fish Passage Barrier Removal Project in the amount of $690,749.00 and authorize
the Mayor to finalize and execute the agreement with substantially the same terms and conditions as
presented.
COUNCIL ACTION: Approve Deny Table Continue No Action