Introduction
This document describes Parametrix’s proposed scope of work (SOW) for Change Order 5 under our
existing contract. The purpose for Change Order 5 is to request budget for completion of engineering
services for the redesign of the storm drainage system and associated grading in order to simplify
the permitting process.
A proposed schedule is included in this scope as Exhibit B and our proposed budget is attached as
Exhibit C.
Scope of Work
Task 1 – Project Management and Meetings
Objective
Continue project management through the final design of the project.
Activities
The following activities will be performed as part of this task:
Manage and direct the project technical team.
Provide routine project management and communications (scope, schedule, budget, and
invoicing).
Prepare monthly progress reports and progress billings and submit to the City for approval
and payment.
Deliverables
The following deliverables are associated with this task:
Routine correspondence and monthly invoices and progress reports
Meeting agendas and notes
Assumptions
The following assumptions apply to this task:
Project duration is expected to take an additional 3 months beyond the previous estimate because of the additional redesign effort.
ATTACHMENT 1Docusign Envelope ID: C44B026B-86C5-4AE9-82F2-51A3BC490F70
Scope of Work
City of Bremerton 233-1896-174
Kitsap Lake Park Renovation Project 2 November 2023 Change Order 5 – Additional Engineering Services
Task 2 – Permitting
Objective
Provide additional services to assist the City in complying with state and federal permitting requirements.
Activities
The following activities will be performed as part of this task:
Submit required information to the U.S. Army Corps of Engineers, to support their issuance of
a Determination of No Jurisdiction.
Submit a request to the Washington Department of Fish and Wildlife (WDFW) for a minor
modification to the Hydraulic Project Approval (HPA) that was issued on February 10, 2022.
Communicate and coordinate with City of Bremerton Department of Community
Development staff concerning the status of the Shoreline Substantial Development Permit
and SEPA Determination of Nonsignificance that were issued on February 18, 2022.
Deliverables
The following deliverables are associated with this task:
Revised design drawings, showing that no fill will be placed within Waters of the U.S.
A draft HPA minor modification request, for review by City of Bremerton Parks Department
staff
A final HPA minor modification request, submitted to WDFW
Documentation of correspondence with the U.S. Army Corps of Engineers, WDFW, and the
City of Bremerton Department of Community Development
Assumptions
The following assumptions apply to this task:
These additional services under Task 2, estimated at 16 labor hours, will use some of the
remaining funds from Change Order 04.
The U.S. Army Corps of Engineers will concur that, by avoiding the placement of fill within
Waters of the U.S. (including associated wetlands), the project does not trigger requirements
for compliance with Section 404 of the Clean Water Act.
WDFW will concur that the proposed design adjustment (i.e., eliminating the placement of fill
material within Waters of the state) constitutes a minor modification.
The proposed design adjustment will not trigger any additional review requirements with the
City of Bremerton Department of Community Development.
Task 4 – 60%, 90%, 100%, and Final Plans, Specifications, and Estimates (PS&E)
Objective
Redesign storm drainage system and grading and update current project PS&E documents for
bidding in 2024.
Docusign Envelope ID: C44B026B-86C5-4AE9-82F2-51A3BC490F70
Scope of Work
City of Bremerton 233-1896-174
Kitsap Lake Park Renovation Project 3 November 2023 Change Order 5 – Additional Engineering Services
Activities
The following activities will be performed as part of this task:
Redesign of the storm drainage system and associated grading.
Update plan sheets and specifications in accordance with the redesign.
Sheet # Dwg # Sheet Modified Republished
1 G1 Cover Sheet No Yes
2 G2 Legend and Abbreviations No Yes
3 G3 General, Erosion/Sediment Control & Construction Notes No Yes
4 G4 Survey and Horizontal Control Yes Yes
5 DM1 Demolition and TESC Plan Yes Yes
6 C1 Site Plan Yes Yes
7 C2 Parking Lot and Boat Launch Access Layout Plan and Profile Yes Yes
8 C3 Restroom and Fishing Pier Access Layout Plan and Profile No Yes
9 C4 Parking Lot and Boat Ramp Grading Plan Yes Yes
10 C5 Restroom and Fishing Pier Access Grading Plan No Yes
11 C6 Upland Path Layout Plan and Profile No Yes
12 C7 Upland Area Layout Details and Points No Yes
13 C8 Picnic Shelter Grading Plan and Details No Yes
14 C9 Play Area Grading, Details, and Drainage Plan No Yes
15 D1 Details No Yes
16 D2 Details Yes Yes
17 D3 Details No Yes
18 D4 Details Yes Yes
19 FL1 Boat Ramp and Boat Ramp Float Plan and Profiles Yes Yes
20 FL2 Fishing Pier Gangway and Float Plan and Profile No Yes
21 UT1 Utility Plan Yes Yes
22 WA1 Wall Plans and Details No Yes
23 LS1 Landscape Plan Yes Yes
Update drainage report.
Update cost estimate using bid tabulations from recent projects and as published by the
Washington State Department of Transportation (WSDOT).
Compare general special provisions (GSPs) with 2025 WSDOT and American Public Works
Association (APWA) GSPs and update as needed.
Docusign Envelope ID: C44B026B-86C5-4AE9-82F2-51A3BC490F70
Scope of Work
City of Bremerton 233-1896-174
Kitsap Lake Park Renovation Project 4 November 2023 Change Order 5 – Additional Engineering Services
Deliverables
The deliverable for this task is final stamped PS&E documents for bidding.
Assumptions
The following assumptions apply to this task:
Draft bid set will be prepared and submitted to the City for review.
City will provide a consolidated set of comments.
This draft bid set will be sent to the Army Corps of Engineers for review with a response of
“Determination of No Jurisdiction”.
City and Army Corps of Engineers comments will be addressed during preparation of the final bid set submittal.
Exhibit B - Schedule
Work Element Completed By
Notice to Proceed November 8, 2023
Draft Bid submittal (6 weeks) December 15, 2023
City Review (4 weeks) January 10, 2024
Bid Set Submittal (2 weeks) January 24, 2024
Advertisement
Contract Award
Construction Begins
Construction Complete
February 7, 2024
March 1, 2024
May 1, 2024
November 1, 2024
Docusign Envelope ID: C44B026B-86C5-4AE9-82F2-51A3BC490F70
Exhibit C
Client: City of Bremerton
Project:Kitsap Lake Park Improvements
Project No:233-1896-174
Shanon L. HarrisJason CeraldeJoanna JohnsonJosephine CrofootCooper OdegardClara OlsonJeff DyeKyle HaleAmanda LucasJean Johnson3.0 Project Controls SpecialistProject ManagerEngineer IVEngineer IIEngineer IIIEngineer IIIQuality Control (SD)Project AccountantProduction SupervisorSr. Contracts Specialist$138.81 $146.91 $161.31 $125.10 $142.59 $142.62 $306.54 $102.39 $136.05 $174.93
Task Description Labor Dollars Labor Hours
01 Project Management and Meetings $2,784.06 20 6 10 0 0 0 0 0 3 0 1
Virtual Project Meetings (3)$881.46 6 6
Project Management (3 mo.)$1,902.60 14 6 4 3 1
04 Final Design $24,947.73 166 0 54 45 23 2 30 4 0 8 0
Bid Set Review Meeting $616.44 4 2 2SHEETS
Survey and Horizontal Control (1 sheet @ 30' scale)$286.41 2 1 1
Demolition and TESC (1 sheet @ 30' scale)$705.33 5 2 1 2
Site Plan (1 sheet @ 20' scale)$705.33 5 2 1 2Parking Lot and Boat Launch Access Layout Plan and Profile
(1 sheet @ 20' scale)$2,053.56 14 4 4 2 4
Parking Lot and Boat Ramp Grading Plan (1 sheet @ 20' scale)$7,015.68 48 20 12 8 8
Site, Utility, and Drainage Details (2 of 4 sheets)$1,552.47 11 1 2 8
Boat Ramp and Boat Ramp Float Plan and Profile (1 sheet)$1,160.46 8 4 2 2
Utility Plan (1 sheet)$1,042.35 7 1 4 2
Landscape Plan (1 sheet)$558.42 4 1 1 2
SHEET TOTAL - 17
Bid Documents and Engineer's Opinion of Probable Cost $2,649.96 18 8 4 2 4
Drainage Report Update $4,135.56 24 2 4 2 8 4 4
QAQC $2,465.76 16 8 8
Labor Totals:186 6 64 45 23 2 30 4 3 8 1
Totals:$27,731.79 $832.86 $9,402.24 $7,258.95 $2,877.30 $285.18 $4,278.60 $1,226.16 $307.17 $1,088.40 $174.93
Other Direct Expenses
Mileage - $0.625/mile $150.00
Other Direct Expenses Total:$150.00
Project Total $27,881.79