HomeMy WebLinkAbout1 - Original Submission_ 6th St Ph3_CN Submittal CompleteLocal Programs Authorization Package Checklist
Agency:City of Bremerton
Project Title:6th Street Pavement Preservation Phase 3 - Naval Avenue to Warren Avenue
Fed Aid/State Project #: STPUL-6566(014)
Funding Request PL*PE**RW CN Non-Funding Request
New Phase Authorization X
*PL - Planning. Used for stand-alone planning and study projects.
**PE - Preliminary Engineering. This is the full design phase of a construction project. Once PE is authorized,Region HQ
the construction phase must be completed, or all federal expenditures must be repaid.Agency Check Check
Miscellaneous Items X X
In addition to this checklist, all Region submittals must utilize the standard Region IDC, memo, or cover letter.
If authorizing a subsequent phase on an existing project, has at least one bill for the prior phase been fully
processed by Local Programs (Posted date is present in SPORT)? If not, supplement can't be processed.
Has the scope changed (description of work, limits, staging, RW needs, etc.) since previous submittal?
Project Prospectus (DOT Form 140-101 01/22) - LAG Chapter 21 X
Are all three pages of the current form included?
Does information (title, termini, description, RW needs, cost, etc.) agree with STIP/LAA/NEPA-CE?
Is the project description written such that the project scope is clear to an average person?
Are pages 1 and 3 signed?
If the LPE or another agency is acting as CA, enter CA agency name below and include copy of CA agreement (PAA, etc).
CA Agency:City of Bremerton
Are the Latitude and Longitudes (decimal format preferred) included and correct?
Are Congressional and Legislative Districts included and correct?
Project Zip Code includes the +4?
Are estimated costs included for all phases of the project?
Are the Functional Classification and Urban/Rural designation correct?
Are the Right of Way, Utilities, and Railroad sections filled out?
Typical Sections & Vicinity Map - LAG Chapter 21 X
When necessary, are the Vicinity Map(s) and Roadway Section(s) included?
Can someone unfamiliar with the project's location easily tell where it's located using the vicinity map?
Are the project limits clearly marked on the map?
Does the section include all elements, with dimensions, of the roadway prism?
Are section changes, if applicable, throughout the project limits noted/displayed?
STIP/Funding Documentation - LAG Chapter 12 X
Is the currently approved STIP page included?
Does STIP information (termini, description, etc.) match the LAA and Prospectus?
Is the phase being authorized (or a later phase) programmed in the STIP?
Is funding from all requested programs shown in the STIP?
Are the requested funds supported by the STIP?
If funded through a HQ managed program (ex. Bridge, HSIP), is the award letter included when these
first obligated?
If funded through a HQ managed program, does the submitted scope match the project summary scope?
Local Agency Agreement (DOT Forms 140-039 4/22 & 140-041 4/22 - LAG Chapter 22 x
State Funded Local Agency Agreement (DOT forms 140-087 6/22 140-087A 6/22)
Is at least one LAA or LAA supplement, with an original signature, included? (Do NOT fill in Date Executed)
Current form used? (check revision date at bottom left)
All pages of Agreement included?
Are the Agency information, Project #, LAA #, Supplement #, and date of original agreement execution correct?
Does project information (title, termini, length, description, etc.) agree with STIP/Prospectus/NEPA-CE?
HQ
Phase Modification
By Phase (check all that apply)
Authorization Package Checklist WSDOT/Local Programs 1 of 2
Docusign Envelope ID: F2A6866C-8A13-4D49-909C-11401DD9EE8E
Local Programs Authorization Package Checklist
Check
Local Agency Agreement (DOT Forms 140-039 & 140-041 4/22) - LAG Chapter 22 [CONT.]
State Funded Local Agency Agreement (DOT forms 140-087 6/22 & 140-087A 6/22)
Is the reason for supplement accurate and up to date?
Is the Project Agreement End Date (month, day, and year) included? Does it follow LAG guidance?
When not authorizing a new phase, is the end date the same as shown on the previous agreement?
If not, is adequate justification (see LAG 22.3) included to support changing the end date?
Is the Advertisement Date (month, day, and year) included? Is it within 6 weeks of estimated CN authorization?
If the ICR box is checked 'Yes', is the agency's current approved/self-certifed rate documentation provided?
Must clearly show a single rate to be used, timeframe it covers, & actual signature of approval.
If corrections made, are they initialed? If made by WSDOT is permission from Agency provided?
Are all federal aid participation ratios being used listed?
If de-obligating funds on any line, does it reduce obligation below expenditures?
Are amounts calculated correctly and shown in the correct columns? Amounts must be rounded to whole dollars.
Documented Cost Estimate - LAG 22.4 and Appendix 22.56 X
Is a Documented Cost Estimate included for each phase requesting/changing funds?
Are total dollars on the LAA supported by the phase estimates?
Does the estimate sufficiently demonstrate how the costs were determined?
Right of Way - LAG Chapter 25 X
If authorizing RW, is a true cost estimate summary sheet included?
Does the true cost estimate summary sheet support RW amounts shown on the LAA?
If authorizing RW and Relocation is required, is the signature page of the approved Relocation Plan included?
If authorizing CN, is the Local Programs approved RW Certification included?
If RW acquired under the Government Acquisitions Provision, is approval documentation included?
Environmental Documentation/Approval (NEPA) - LAG Chapter 24 X
Is an approved NEPA package (at least signature page) included?
Does the description of work match the Prospectus/LAA/STIP?
Is the footprint of the project within the limits of the NEPA approval?
Do the NEPA-CE Part 3 RW responses agree with the STIP and Prospectus?
Is the approval date within the last 3 years?
If approval is older than 3 years, has the approval been re-evaluated by the environmental engineer?
DBE Goals (LAG Chapter 26) - Tied Bid (LAG Chapter 44) - Local Forces (LAG Chapter 61)X
If using a fed funding for a consultant in any phase, is the DBE goal letter/email included, or are the goals in SPORT?
If authorizing construction, is the DBE goal letter/e-mail included, or are the goals in SPORT?
If construction includes a tied bid project, is the approved PIF included or noted in SPORT?
If construction by Local Forces, is the approved PIF included or noted in SPORT?
PROJECT NOTES (Provide additional information or explanation as necessary)
Authorization Package Checklist WSDOT/Local Programs 2 of 2
Docusign Envelope ID: F2A6866C-8A13-4D49-909C-11401DD9EE8E
Local Agency Federal AidProject Prospectus
Prefix Route ( )
Federal Aid Project Number
Local Agency Project Number WSDOT Use Only
Date
DUNS Number
Federal Employer Tax ID Number
Agency CA Agency
Yes No
Federal Program Title
20.205 Other
Project Title Start Latitude N
End Latitude N
Start Longitude W
End Longitude W
Project Termini From-To Nearest City Name Project Zip Code (+4)
Begin Mile Post End Mile Post Length of Project Award Type
Local Local Forces State Railroad
Route ID Begin Mile Point End Mile Point City Number County Number County Name
WSDOT Region Legislative District(s) Congressional District(s) Urban Area Number
Phase Total
Estimated Cost (Nearest Hundred Dollar)
Local Agency
Funding (Nearest Hundred Dollar)
Federal Funds
(Nearest Hundred Dollar)
Phase Start
Date Month Year
P.E.
R/W
Const.
Total
Description of Existing Facility (Existing Design and Present Condition)
Roadway Width Number of Lanes
Description of Proposed Work
Description of Proposed Work (Attach additional sheet(s) if necessary)
Local Agency Contact Person Title Phone
Mailing Address City State Zip Code
Project Prospectus
By Approving Authority
Title Date
DOT Form 140-101Revised 01/2022 Previous Editions Obsolete
( )
Page 1
5/28/24
55684970
315043 91-6001231
City of Bremerton
6th Street Preservation Phase 3
47.567338
47.567332
-122.645964
-122.632873
Naval Avenue Warren Avenue Bremerton 98337-1432
0.60 Miles
0115 18 Kitsap
Olympic Region 26 6 7
$478,500 $278,500 $200,000 July 2021
0 0 0
$4,405,400 $2,774,100 $1,631,300 July 2024
$4,883,900 $3,052,600 $1,831,300
44 Feet 4
6th Street is a 4 lane facility (2 lanes each direction), with 11' wide lanes, curb and gutter and 5' sidewalks on
each side. There are traffic signals at Naval, Veneta, and Warren Avenues and a hybrid beacon at High Avenue
Pavement preservation of 6th Street between Naval Avenue and Warren Avenue. The work includes grinding
and overlay, pavement markings, curb ramps, pedestrian signals, traffic signal replacement, base paving,
signage, and other street related improvements.
Shane Weber, P.E.Managing Engineer (360) 473-2354
345 6th Street Suite 100 Bremerton WA 98337
Mayor, City of Bremerton
STPUL 6566 014
Docusign Envelope ID: F2A6866C-8A13-4D49-909C-11401DD9EE8E
8/16/2024
Agency Project Title Date
Type of Proposed Work
Project Type (Check all that Apply)
New Construction
Reconstruction
Railroad
Bridge
Path / Trail
Pedestrian / Facilities
Parking
3-R
2-R
Other
Roadway Width Number of Lanes
Geometric Design Data
Description
Federal Functional Classification
Terrain
Posted Speed
Design Speed
Existing ADT
Design Year ADT
Design Year
Design Hourly Volume (DHV)
Through Route
Urban
Rural
NHS
Principal Arterial
Minor Arterial
Collector
Major Collector
Minor Collector
Local Access
Flat Roll Mountain
Crossroad
Urban
Rural
NHS
Principal Arterial
Minor Arterial
Collector
Major Collector
Minor Collector
Local Access
Flat Roll Mountain
Performance of Work
Preliminary Engineering Will Be Performed By Others
%
Agency
%
Construction Will Be Performed By Contract
%
Agency
%
Environmental Classification
Class I - Environmental Impact Statement (EIS)
Project Involves NEPA/SEPA Section 404 Interagency Agreement
Class III - Environmental Assessment (EA)
Project Involves NEPA/SEPA Section 404 Interagency Agreements
Class II - Categorically Excluded (CE)
Projects Requiring Documentation (Documented CE)
Environmental Considerations
DOT Form 140-101Revised 01/2022 Previous Editions Obsolete
Page 2
City of Bremerton 6th Street Preservation Phase 3 5/28/24
444 Feet
25 mph
30 mph
11,664
N/A
N/A
N/A
Consultant 100
Contractor 100
30 mph
35 mph
15,000
N/A
N/A
N/A
Docusign Envelope ID: F2A6866C-8A13-4D49-909C-11401DD9EE8E
Agency Project Title Date
Right of Way
No Right of Way Needed
* All construction required by the contract can be accomplished within the existing right of way.
Right of Way Needed
No Relocation Relocation Required
Utilities
No utility work required
All utility work will be completed prior to the startof the construction contract
All utility work will be completed in coordinationwith the construction contract
Railroad
No railroad work required
All railroad work will be completed prior to the start ofthe construction contract
All the railroad work will be completed in coordinationwith the construction contract
Description of Utility Relocation or Adjustments and Existing Major Structures Involved in the Project
FAA Involvement
Is any airport located within 3.2 kilometers (2 miles) of the proposed project? Yes No
Remarks
This project has been reviewed by the legislative body of the administration agency or agencies, or it’s designee, and is not inconsistent with the agency’s comprehensive plan for community development.
Agency
ByDate Mayor/Chairperson
DOT Form 140-101Revised 01/2022 Previous Editions Obsolete Page 3
City of Bremerton 6th Street Preservation Phase 3 5/28/24
Adjustments to City storm, water, and sewer facilities will be necessary to accommodate the proposed asphalt
grinding and overlay. There will also be utility relocation work by overhead franchise utilities in advance of
the City project.
4
City of Bremerton
Docusign Envelope ID: F2A6866C-8A13-4D49-909C-11401DD9EE8E
8/16/2024
Docusign Envelope ID: F2A6866C-8A13-4D49-909C-11401DD9EE8E
Washington State S. T. I. P.
2024 to 2027
(Project Funds to Nearest Dollar)
MPO/RTPO:PSRC Y Inside N Outside August 8, 2024
County:Kitsap
Agency:Bremerton
Func
Cls
Project
Number PIN STIP ID
Imp
Type
Total
Project
Length Environmental
Type
RW
Required
Begin
Termini
End
Termini
Total Est.
Cost of
Project
STIP
Amend.
No.
04 6566(014)BRE-26 06 0.600 DCE No Naval Avenue Warren Avenue 2,170,816 2403
AdMod
6th Street Preservation Phase 3, Naval Ave to Warren Ave
Grind and overlay of HMA pavement, including upgrading ADA curb ramps and replacement of signal at Veneta.
Funding
Phase Start Date Federal Fund Code
Federal Funds
State Fund Code State Funds Local Funds Total
CN 2024 STBG(UM)1,631,231 0 254,585 1,885,816
Project Totals 1,631,231 0 254,585 1,885,816
Expenditure Schedule
Phase 1st 2nd 3rd 4th 5th & 6th
ALL 1,885,816 0 0 0 0
Totals 1,885,816 0 0 0 0
Page 1
Docusign Envelope ID: F2A6866C-8A13-4D49-909C-11401DD9EE8E
Washington State
Department of Transportation
Local Agency Agreement Supplement
Agency Supplement Number
Federal Aid Project Number Agreement Number CFDA No. 20.205 - Highway Planning and Construction
All provisions in the basic agreement remain in effect except as modified by this supplement.
The Local Agency certifies that it is not excluded from receiving Federal funds by a Federal suspension or debarment
(2 CFR Part 180). Additional changes to the agreement are as follows:
Project Description
Name Length
Termini
Description of Work No Change
Reason for Supplement
Are you claiming indirect cost rate? Yes No Project Agreement End Date
Advertisement Date
Type of Work
PE % a. Agency
b. Other
Estimate of Funding(1) Previous Agreement/Suppl.
(2) Supplement
(3) Estimated Total Project Funds
(4) Estimated Agency Funds
(5) Estimated Federal Funds
Federal Aid Participation Ratio for PE
c. Other
d. State Services
e. Total PE Cost Estimate (a+b+c+d)Right of Way %f. Agency
g. OtherFederal Aid Participation Ratio for RW
h. Other
i. State Services
j. Total R/W Cost Estimate (f+g+h+i)Construction % k. Contract
l. Other
m. Other Federal Aid Participation Ratio for CN
n. Other
o. Agency
p. State Services
q. Total CN Cost Estimate (k+l+m+n+o+p)
r. Total Project Cost Estimate (e+j+q) The Local Agency further stipulates that pursuant to said Title 23, regulations and policies and procedures, and as a
condition to payment of the Federal funds obligated, it accepts and will comply with the applicable provisions.
Agency Official
By
Title
Agency Date
Washington State Department of Transportation
By
Director, Local Program
Date Executed
DOT Form 140-041 Revised 04/2022 Page 1
6th Street Pavement Preservation Phase III 0.60 Miles
Naval Avenue to Warren Avenue
Pavement preservation of 6th Street between Naval Avenue and Warren Avenue. The work includes grinding and overlay, pavement markings, curb ramps, pedestrian
signals, traffic signal replacement, base paving, signage, and other street related improvements.
Construction Phase Obligation
12/31/27
8/8/24
City of Bremerton 01
STPUL-6566(014)LA10087
49,953.00 49,953.00 6,744.00 43,209.00
Consultant 176,261.00 176,261.00 23,795.00 152,466.0086.5
Non-Elig Non-Funded 71,817.00 175,391.00 247,208.00 247,208.00 0.00
5,000.00 5,000.00 675.00 4,325.00
303,031.00 175,391.00 478,422.00 278,422.00 200,000.00
0.00 0.00 0.00 0.00
Consultant 0.00 0.00 0.00 0.000
0.00
0.00
0.00 0.00 0.00 0.00 0.00
1,636,213.00 1,636,213.00 220,889.00 1,415,324.00
Consultant 84,604.00 84,604.00 11,422.00 73,182.00
Elig Non-Funded 623,269.00 623,269.00 623,269.00 0.00
86.5
Non-Elig Non-Funded 1,896,167.00 1,896,167.00 1,896,167.00 0.00
160,000.00 160,000.00 21,600.00 138,400.00
5,000.00 5,000.00 675.00 4,325.00
0.00 4,405,253.00 4,405,253.00 2,774,022.00 1,631,231.00
86.5 303,031.00 4,580,644.00 4,883,675.00 3,052,444.00 1,831,231.00
Docusign Envelope ID: F2A6866C-8A13-4D49-909C-11401DD9EE8E
8/16/2024
Greg Wheeler
Mayor
Agency Supplement Number
Federal Aid Project Number Agreement Number CFDA No. 20.205 - Highway Planning and Construction
VI. Payment and Partial Reimbursement
The total cost of the project, including all review and engineering costs and other expenses of the State, is to be paid
by the Agency and by the Federal Government. Federal funding shall be in accordance with the Federal Transportation
Act, as amended, 2 CFR Part 200. The State shall not be ultimately responsible for any of the costs of the project. The
Agency shall be ultimately responsible for all costs associated with the project which are not reimbursed by the Federal
Government. Nothing in this agreement shall be construed as a promise by the State as to the amount or nature of federal
participation in this project.
The Agency shall bill the state for federal aid project costs incurred in conformity with applicable federal and state laws.
The agency shall minimize the time elapsed between receipt of federal aid funds and subsequent payment of incurred
costs. Expenditures by the Local Agency for maintenance, general administration, supervision, and other overhead
shall not be eligible for federal participation unless a current indirect cost plan has been prepared in accordance with
the regulations outlined in 2 CFR Part 200 - Uniform Admin. Requirements, Cost Principles and Audit Requirements for
Federal Awards, and retained for audit.
The State will pay for State incurred costs on the project. Following payment, the State shall bill the Federal Government
for reimbursement of those costs eligible for federal participation to the extent that such costs are attributable and properly
allocable to this project. The State shall bill the Agency for that portion of State costs which were not reimbursed by the
Federal Government (see Section IX).
VII. Audit of Federal Consultant Contracts
The Agency, if services of a consultant are required, shall be responsible for audit of the consultant’s records to determine
eligible federal aid costs on the project. The report of said audit shall be in the Agency’s files and made available to the
State and the Federal Government.
An audit shall be conducted by the WSDOT Internal Audit Office in accordance with generally accepted governmental
auditing standards as issued by the United States General Accounting Office by the Comptroller General of the United
States; WSDOT Manual M 27-50, Consultant Authorization, Selection, and Agreement Administration; memoranda of
understanding between WSDOT and FHWA; and 2 CFR Part 200.501 - Audit Requirements.
If upon audit it is found that overpayment or participation of federal money in ineligible items of cost has occurred, the
Agency shall reimburse the State for the amount of such overpayment or excess participation.
IX. Payment of Billing
The Agency agrees that if payment or arrangement for payment of any of the State’s billing relative to the project (e.g.,
State force work, project cancellation, overpayment, cost ineligible for federal participation, etc.) is not made to the State
within 45 days after the Agency has been billed, the State shall effect reimbursement of the total sum due from the regular
monthly fuel tax allotments to the Agency from the Motor Vehicle Fund. No additional Federal project funding will be
approved until full payment is received unless otherwise directed by the Director, Local Programs.
Project Agreement End Date - This date is based on your projects Period of Performance (2 CFR Part 200.309).
Any costs incurred after the Project Agreement End Date are NOT eligible for federal reimbursement. All eligible costs
incurred prior to the Project Agreement End Date must be submitted for reimbursement within 90 days after the Project
Agreement End Date or they become ineligible for federal reimbursement.
VIII. Single Audit Act
The Agency, as a subrecipient of federal funds, shall adhere to the federal regulations outlined in 2 CFR Part 200.501 as
well as all applicable federal and state statutes and regulations. A subrecipient who expends $750,000 or more in federal
awards from all sources during a given fiscal year shall have a single or program-specific audit performed for that year in
accordance with the provisions of 2 CFR Part 200.501. Upon conclusion of the audit, the Agency shall be responsible for
ensuring that a copy of the report is transmitted promptly to the State.
XVII. Assurances
Local Agencies receiving Federal funding from the USDOT or its operating administrations (i.e., Federal Highway
Administration, Federal Transit Administration, Federal Aviation Administration) are required to submit a written policy
statement, signed by the Agency Executive and addressed to the State, documenting that all programs, activities and
services will be conducted in compliance with Section 504 and the Americans with Disabilities Act (ADA).
DOT Form 140-041 Revised 04/2022 Page 2
City of Bremerton 01
STPUL-6566(014)LA10087
Docusign Envelope ID: F2A6866C-8A13-4D49-909C-11401DD9EE8E
Instructions
1. Agency – Enter the agency name as entered on the original agreement.
2. Supplemental Number – Enter the number of the supplement. Supplement numbers will be assigned in sequence beginning
with Number 1 for the first supplement.
3. Project Number – Enter the federal aid project number assigned by WSDOT on the original agreement.
4. Agreement Number – Enter the agreement number assigned by WSDOT on the original agreement.
5. Project Description – Enter the project name, length, and termini.
6. Description of Work – Clearly describe if there is a change in work such as the addition or deletion of work elements and/or
changes to the termini. If the work has not changed, put a check mark in the “No Change” box.
7. Reason for Supplement – Enter the reason for this supplement, i.e., increase PE funding to cover design changes presented
in the revised prospectus; request funding of construction phase; decrease construction funding to the contract bid amount.
If the supplement is authorizing a construction phase, the project’s proposed advertisement date must be included in the
space provided.
8. Claiming Indirect Cost Rate – Check the Yes box if the agency will be claiming indirect costs on the project. For those projects
claiming indirect costs, supporting documentation that clearly shows the indirect cost rate being utilized must be provided with
the supplement. Indirect cost rate approval by your cognizant agency or through your agency’s self-certification and supporting
documentation is required to be available for review by FHWA, WSDOT and /or State Auditor. Check the No box if the agency will
not be claiming indirect costs on the project. See Section 23.5 for additional guidance.
9. Project Agreement End Date – Enter your previously established Project Agreement End Date. If authorizing a new phase of the
project, update the Project Agreement End Date based on the following guidance:
a. For PE and RW – WSDOT recommends agencies estimate when the phase will be completed and add three years to
determine the “Project Agreement End Date”.
b. For Construction – WSDOT recommends agencies estimate when construction will be completed and add three years to
determine the “Project Agreement End Date”.
c. If an extension to a Project Agreement End Date is required between phase authorizations, the need for the extension must
be described in the Reason for Supplement. Adequate justification to approve the extension must be submitted with the
supplement. See Section 22.3 for additional guidance.
10.Type of Work and Funding (Round all amounts to the nearest whole dollar).
a. Column 1 – Enter the amounts from column 1 of the original local agency agreement. If the agreement has already been
supplemented, enter the amounts by type of work from column 3 of the last supplemental agreement.
b. Column 2 – Enter increase/decrease to total amounts requested by type of work.
c. Column 3 – Add the amounts in columns 1 and 2.
d. Columns 4 and 5 – Enter the appropriate amounts based on the participation ratio recorded on the original agreement.
11.Signatures – An authorized official of the local agency signs the Supplemental Agreement and enters their title and date of
signature (mm/dd/yy). Note: Do NOT enter a date on the Date Executed line.
DOT Form 140-041 Revised 04/2022 Page 3
Docusign Envelope ID: F2A6866C-8A13-4D49-909C-11401DD9EE8E
Project Name
Estimated By: M. Kendall, H. Migita Checked By: C. Schott
Date: 4/18/24 Date: 4/19/24
ITEM SPEC STD. ITEM
NO. SECTION NUMBER DESCRIPTION UNIT QUANTITY UNIT PRICE TOTAL COST
1 1-04.4(1) 7728 MINOR CHANGE F.A. 1 $50,000 $50,000
2 SP 1-05.4 7038 ROADWAY SURVEYING L.S. 1 $20,000 $20,000
3 SP 1-05.4 7040 LICENSED SURVEYING FA 1 $10,000 $10,000
4 GSP 1-05.4 7042 ADA FEATURES SURVEYING L.S. 1 $5,000 $5,000
5 GSP 1-05.18 --- RECORD DRAWING (MINIMUM BID $3,000) L.S. 1 $3,000 $3,000
6 1-07 7736 SPCC PLAN L.S. 1 $1,000 $1,000
7 SP 1-07 --- POTHOLING EACH 5 $900 $4,500
8 SP 1-07 --- ACCESS ACCOMMODATIONS F.A. 1 $10,000 $10,000
9 GSP 1-08.3 7003 TYPE B PROGRESS SCHEDULE L.S. 1 $7,800 $7,800
10 1-09.7 0001 MOBILIZATION L.S. 1 $203,000 $203,000
11 1-10 6974 TRAFFIC CONTROL SUPERVISOR LS 1 $50,000 $50,000
12 1-10 6980 FLAGGERS HR 1200 $85 $102,000
13 1-10 6992 OTHER TRAFFIC CONTROL LABOR HR 120 $85 $10,200
14 1-10 6982 CONSTRUCTION SIGNS CLASS A SF 860 $25 $21,500
15 1-10 6993 PORTABLE CHANGEABLE MESSAGE SIGN HR 5760 $6 $34,560
16 1-10 6973 OTHER TEMPORARY TRAFFIC CONTROL DEVICES L.S. 1 $58,800 $58,800
17 SP 1-10 --- TEMPORARY RRFB SYSTEM L.S. 1 $25,000 $25,000
18 GSP 1-10 --- CONTRACTOR PROVIDED UNIFORMED POLICE OFFICER HR 100 $150 $15,000
19 SP 2-01 0035 CLEARING AND GRUBBING L.S. 1 $6,000 $6,000
20 SP 2-02 0050 REMOVAL OF STRUCTURES AND OBSTRUCTIONS L.S. 1 $8,000 $8,000
21 SP 2-02 0080 REMOVING BITUMINOUS PAVEMENT S.Y. 840 $15 $12,600
22 SP 2-02 0090 REMOVING CEMENT CONC. PAVEMENT S.Y. 1590 $30 $47,700
23 SP 2-02 0100 REMOVING CEMENT CONC. SIDEWALK S.Y. 1000 $30 $30,000
24 SP 2-02 0108 REMOVING CEMENT CONC. CURB AND GUTTER L.F. 1230 $15 $18,450
25 2-03 0310 ROADWAY EXCAVATION INCL. HAUL C.Y. 360 $150 $54,000
26 4-04 5120 CRUSHED SURFACING BASE COURSE TON 990 $50 $49,500
27 5-04 5711 PLANING BITUMINOUS PAVEMENT S.Y. 17090 $5 $85,450
28 GSP 5-04 5738 HMA FOR PAVEMENT REPAIR CL. 1/2 IN. PG 58H-22 TON 140 $190 $26,600
29 GSP 5-04 5766 HMA CL. 1/2 IN. PG 58H-22 TON 440 $120 $52,800
30 SP 5-04 5766 HMA CL. 1/2 IN. PG 58H-22 - FIBER REINFORCED TON 2150 $180 $387,000
31 SP 7-05 --- ADJUST FRANCHISE UTILITY MANHOLE EACH 5 $1,000 $5,000
32 SP 7-12 --- ADJUST WATER VALVE EACH 8 $600 $4,800
33 8-01 6471 INLET PROTECTION EACH 68 $100 $6,800
34 8-01 6488 EROSION CONTROL AND WATER POLLUTION PREVENTION L.S. 1 $3,000 $3,000
35 SP 8-02 --- ROADSIDE RESTORATION F.A. 1 $10,000 $10,000
36 SP 8-04 6700 CEMENT CONC. TRAFFIC CURB AND GUTTER L.F. 1250 $38 $47,500
37 SP 8-04 6701 CEMENT CONC. PEDESTRIAN CURB L.F. 342 $38 $12,996
38 8-06 7059 CEMENT CONC. DRIVEWAY ENTRANCE TYPE II (COMMERCIAL) S.Y. 83 $100 $8,300
39 SP 8-14 7055 CEMENT CONC. SIDEWALK S.Y. 556 $60 $33,360
40 8-14 7058 CEMENT CONC. CURB RAMP TYPE PARALLEL EACH 14 $3,500 $49,000
41 8-14 7058 CEMENT CONC. CURB RAMP TYPE COMBINATION EACH 5 $4,000 $20,000
42 8-14 7058 CEMENT CONC. CURB RAMP TYPE PERPENDICULAR EACH 15 $3,500 $52,500
43 SP 8-20 6904 ILLUMINATION SYSTEM MODIFICATIONS L.S. 1 $5,000 $5,000
44 SP 8-20 6912 TRAFFIC SIGNAL SYSTEM, VENETA L.S. 1 $504,000 $504,000
45 SP 8-20 6912 TRAFFIC SIGNAL SYSTEM, HIGH L.S. 1 $15,000 $15,000
46 SP 8-20 6912 TRAFFIC SIGNAL SYSTEM, WARREN L.S. 1 $22,000 $22,000
47 SP 8-21 6890 PERMANENT SIGNING L.S. 1 $13,700 $13,700
48 8-22 6806 PAINT LINE L.F. 8789 $2 $17,578
49 8-22 6817 PAINTED WIDE LINE L.F. 281 $3 $842
50 8-22 6856 PLASTIC CROSSWALK LINE S.F. 864 $14 $12,096
51 8-22 6858 PLASTIC STOP LINE L.F. 145 $30 $4,350
52 8-22 6860 PAINTED TRAFFIC ARROW EACH 11 $200 $2,200
53 8-23 6895 TEMPORARY PAVEMENT MARKING - SHORT DURATION L.F. 400 $1 $400
54 8-23 6896 TEMPORARY PAVEMENT MARKING - LONG DURATION L.F. 19800 $2 $39,600
55 8-23 6872 TEMPORARY MISC. PAVEMENT MARKING - SHORT DURATION EACH 6 $50 $300
56 8-23 6842 TEMPORARY STOP LINE - SHORT DURATION L.F. 24 $4 $96
$2,259,482
$0
$2,259,482
6th Street Preservation - Phase III
Final Estimate of Probable Cost
Project No. Date
214-1896-186 April 18, 2014
TOTAL SCHEDULE A COST
SCHEDULE A - ROADWAY IMPROVEMENTS
Location
City of Bremerton
Owner
City of Bremerton
Construction Cost
0% Contingency
Docusign Envelope ID: F2A6866C-8A13-4D49-909C-11401DD9EE8E
Project Name
Estimated By: MWV Checked By: J. Wright
Date: 01/19/24 Date:1/18/24
ITEM SPEC STD. ITEM Total
NO. SECTION NUMBER DESCRIPTION UNIT QUANTITY UNIT PRICE TOTAL COST
1 1-04.4(1) 7728 MINOR CHANGE F.A. 1 $25,000 $25,000
2 GSP 1-05.4 7042 ADA FEATURES SURVEYING L.S. 1 $500 $500
3 GSP 1-05.18 - RECORD DRAWING (MINIMUM BID $1000) L.S. 1 $1,000 $1,0004
1-07.17 POTHOLING EACH 10 $500 $5,000
5 GSP 1-08.3 7003 TYPE B PROGRESS SCHEDULE L.S. 1 $1,000 $1,000
6 1-09.7 0010 MOBILIZATION L.S. 1 $29,000 $29,000
7 1-10 6974 TRAFFIC CONTROL SUPERVISOR L.S. 1 $6,400 $6,400
8 1-10 6980 FLAGGERS HR 128 $85 $10,880
9 1-10 6992 OTHER TRAFFIC CONTROL LABOR HR 16 $85 $1,360
10 1-10 6982 CONSTRUCTION SIGNS CLASS A SF 250 $25 $6,250
11 1-10 6993 PORTABLE CHANGEABLE MESSAGE SIGN HR 768 $6 $4,608
12 1-10 6973 OTHER TEMPORARY TRAFFIC CONTROL DEVICES L.S. 1 $10,000 $10,000
13 GSP 1-10 CONTRACTOR PROVIDED UNIFORMED POLICE OFFICER HR 96 $150 $14,400
14 SP 2-01 0035 CLEARING AND GRUBBING L.S. 1 $1,000 $1,000
15 SP 2-02 0050 REMOVAL OF STRUCTURES AND OBSTRUCTIONS L.S. 1 $5,000 $5,000
16 SP 2-02 0080 REMOVING BITUMINOUS PAVEMENT S.Y. 440 $15 $6,600
17 SP 2-02 0090 REMOVING CEMENT CONC. PAVEMENT S.Y. 440 $30 $13,200
18 SP 2-02 0100 REMOVING CEMENT CONC. SIDEWALK S.Y. 81 $30 $2,430
19 SP 2-02 0108 REMOVING CEMENT CONC. CURB AND GUTTER L.F. 159 $15 $2,385
20 SP 2-02 ABANDON EXISTING STORM SYSTEM L.S. 1 $5,000 $5,000
21 2-02 REMOVING DRAINAGE STRUCTURE EACH 12 $800 $9,600
22 2-03 0431 GRAVEL BORROW INCL. HAUL TON 501 $40 $20,040
23 2-09 SHORING OR EXTRA EXCAVATION CLASS B L.S. 1 $30,000 $30,000
24 4-04 5120 CRUSHED SURFACING BASE COURSE TON 177 $50 $8,850
25 GSP 5-04 5738 HMA FOR PAVEMENT REPAIR CL. 1/2 IN. PG 58H-22 TON 150 $250 $37,500
26 SP 7-04 3577 SOLID WALL PVC STORM SEWER PIPE 12 IN. DIAM. L.F. 381 $100 $38,100
27 SP 7-04 3774 DUCTILE IRON SEWER PIPE 8 IN. DIAM. L.F. 282 $115 $32,430
28 SP 7-05 3091 CATCH BASIN TYPE 1 EACH 13 $2,500 $32,500
29 SP 7-05 CATCH BASIN TYPE 1 FRAME AND GRATE EACH 14 $1,500 $21,000
30 SP 7-05 3100 ADJUST CATCH BASIN EACH 2 $500 $1,000
31 SP 7-05 3105 CATCH BASIN TYPE 2 48 IN. DIAM. EACH 7 $4,500 $31,500
32 SP 7-05 3080 ADJUST MANHOLE EACH 9 $500 $4,500
33 SP 7-05 RECONNECT EXISTING PIPE EACH 14 $500 $7,000
34 SP 7-05 DECORATIVE STORM RING AND COVER EACH 3 $2,000 $6,000
35 SP 7-08 3810 REMOVAL AND REPLACEMENT OF UNSUITABLE MATERIAL C.Y. 295 $25 $7,375
36 SP 8-01 6488 EROSION CONTROL AND WATER POLLUTION PREVENTION L.S. 1 $5,000 $5,000
37 SP 8-02 ROADSIDE RESTORATION F.A. 1 $5,000 $5,000
38 SP 8-04 6700 CEMENT CONC. TRAFFIC CURB AND GUTTER L.F. 159 $35 $5,565
39 SP 8-04 6707 CEMENT CONC. PEDESTRIAN CURB L.F. 7 $35 $245
40 SP 8-14 7055 CEMENT CONC. SIDEWALK S.Y. 68 $50 $3,400
41 SP 8-14 7058 CEMENT CONC. CURB RAMP TYPE PARALLEL EACH 1 $3,500 $3,500
$461,118
$0
$461,118
0% Contingency
TOTAL SCHEDULE B COST
Location
City of Bremerton
Owner
City of Bremerton
SCHEDULE B STORMWATER IMPROVEMENTS
Construction Cost
6th Street Preservation (100% Submittal)
Final Estimate of Probable Cost
Project No. Date
214-1896-186 Rev. April 19, 2024
Docusign Envelope ID: F2A6866C-8A13-4D49-909C-11401DD9EE8E
Project Name
Estimated By: MWV Checked By:
Date: 3/20/2024 Date:
ITEM SPEC STD. ITEM Total
NO. SECTION NUMBER DESCRIPTION UNIT QUANTITY UNIT PRICE TOTAL COST
1 1-04 7728 MINOR CHANGE F.A. 1 $3,000 $3,0002
GSP 1-05.18 RECORD DRAWING (MINIMUM BID $500) L.S. 1 $500 $5003
1-07.17 POTHOLING EACH 3 $500 $1,5004
GSP 1-08.3 TYPE B PROGRESS SCHEDULE L.S. 1 $250 $2505
1-09.7 0001 MOBILIZATION L.S. 1 $8,000 $8,000
6 1-10 6974 TRAFFIC CONTROL SUPERVISOR L.S. 1 $1,600 $1,600
7 1-10 6980 FLAGGERS HR 32 $85 $2,720
8 1-10 6992 OTHER TRAFFIC CONTROL LABOR HR 4 $85 $340
9 CONSTRUCTION SIGNS CLASS A SF 100 $25 $2,500
10 1-10 6993 PORTABLE CHANGEABLE MESSAGE SIGN HR 192 $6 $1,152
11 1-10 6973 OTHER TEMPORARY TRAFFIC CONTROL DEVICES L.S. 1 $6,000 $6,000
12 SP 2-01 CLEARING AND GRUBBING L.S. 1 $500 $500
13 SP 2-02 0050 REMOVAL OF STRUCTURES AND OBSTRUCTIONS L.S. 1 $3,000 $3,000
14 SP 2-02 0080 REMOVING BITUMINOUS PAVEMENT S.Y. 113 $15 $1,695
15 SP 2-02 0090 REMOVING CEMENT CONC. PAVEMENT S.Y. 44 $30 $1,320
16 SP 2-02 0100 REMOVING CEMENT CONC. SIDEWALK S.Y. 119 $30 $3,570
17 SP 2-02 0108 REMOVING CEMENT CONC. CURB AND GUTTER L.F. 199 $15 $2,985
18 SP 2-02 REMOVING DRAINAGE STRUCTURE EACH 3 $800 $2,400
19 2-03 GRAVEL BORROW INCL. HAUL TON 99 $45 $4,455
20 SP 2-09 SHORING OR EXTRA EXCAVATION CLASS B L.S. 1 $2,500 $2,500
21 SP 2-13 CONTAMINATED SOIL MITIGATION F.A. 1 $15,000 $15,000
22 4-04 5120 CRUSHED SURFACING BASE COURSE TON 64 $50 $3,200
23 GSP 5-04 5738 HMA FOR PAVEMENT REPAIR CL. 1/2 IN. PG 58H-22 TON 15 $190 $2,850
24 SP 7-04 3774 DUCTILE IRON SEWER PIPE 8 IN. DIAM. L.F. 210 $115 $24,150
25 7-05 3091 CATCH BASIN TYPE 1 EACH 4 $2,500 $10,000
26 7-05 3080 ADJUST MANHOLE EACH 12 $500 $6,000
27 SP 7-05 CATCH BASIN TYPE 1 FRAME AND GRATE EACH 1 $1,500 $1,500
28 SP 7-08 3810 REMOVAL AND REPLACEMENT OF UNSUITABLE MATERIAL C.Y. 58 $25 $1,450
29 SP 8-01 6488 EROSION CONTROL AND WATER POLLUTION PREVENTION L.S. 1 $1,000 $1,000
30 SP 8-02 ROADSIDE RESTORATION F.A. 1 $3,000 $3,000
31 SP 8-04 6700 CEMENT CONC. TRAFFIC CURB AND GUTTER L.F. 199 $35 $6,965
32 SP 8-06 7059 CEMENT CONC. DRIVEWAY ENTRANCE TYPE III (COMMERCIAL) S.Y. 63 $100 $6,300
33 SP 8-14 7055 CEMENT CONC. SIDEWALK S.Y. 55 $50 $2,750
$134,152
$0
$12,342
$146,494
0% Contingency
TOTAL SCHEDULE C COST
Location
City of Bremerton
Owner
City of Bremerton
SCHEDULE C CSO SEPARATION
Construction Cost
Sales Tax (9.2%)
6th Street Preservation
Final Estimate of Probable Cost
Project No. Date
214-1896-186 Rev. April 19,2024
Docusign Envelope ID: F2A6866C-8A13-4D49-909C-11401DD9EE8E
PARAMETRIX Form 05-PD-189/Rev. 07/05
Project Name
Estimated By: MWV Checked By:
Date: 03/20/24 Date:
ITEM SPEC WSDOT
NO. SECTION STD ITEM DESCRIPTION UNIT Total Qty UNIT PRICE TOTAL COST
1 1-04.4(1) 7728 MINOR CHANGE EST 1 $5,000 $5,000
2 GSP 1-05.18 RECORD DRAWING (MINIMUM BID $1,000) L.S. 1 $1,000 $1,000
3 1-07.17 POTHOLING EA 15 $500 $7,500
4 GSP 1-08.3 7003 TYPE B PROGRESS SCHEDULE L.S. 1 $3,900 $3,900
5 1-09.7 0001 MOBILIZATION LS 1 $78,500 $78,5006
1-10 6974 TRAFFIC CONTROL SUPERVISOR L.S. 1 $24,000 $24,0007
1-10 6980 FLAGGERS HR 480 $85 $40,8008
1-10 6992 OTHER TRAFFIC CONTROL LABOR HR 60 $85 $5,1009
1-10 6982 CONSTRUCTION SIGNS CLASS A SF 550 $25 $13,750
10 1-10 6993 PORTABLE CHANGEABLE MESSAGE SIGN HR 2880 $6 $17,280
11 1-10 6973 OTHER TEMPORARY TRAFFIC CONTROL DEVICES L.S. 1 $24,000 $24,000
12 SP 1-10 CONTRACTOR PROVIDED UNIFORMED POLICE OFFICER HR 96 $150 $14,400
13 SP 2-01 CLEARING AND GRUBBING L.S. 1 $2,000 $2,000
14 SP 2-02 0050 REMOVAL OF STRUCTURES AND OBSTRUCTIONS LS 1 $10,000 $10,000
15 SP 2-02 REMOVE AND SALVAGE HYDRANT ASSEMBLY EA 3 $1,500 $4,500
16 SP 2-02 REMOVE WATER VALVE CAN EA 11 $500 $5,500
17 SP 2-02 0080 REMOVING BITUMINOUS PAVEMENT SY 1,077 $15 $16,155
18 SP 2-02 0090 REMOVING CEMENT CONC. PAVEMENT SY 1,163 $30 $34,890
19 SP 2-02 0100 REMOVING CEMENT CONC. SIDEWALK SY 574 $30 $17,220
20 SP 2-02 0108 REMOVING CEMENT CONC. CURB AND GUTTER LF 290 $15 $4,350
21 2-03
GRAVEL BORROW INCL. HAUL TON 1,042 $40 $41,680
22 SP 2-09 SHORING OR EXTRA EXCAVATION CLASS B LS 1 $55,000 $55,000
23 4-04 5120 CRUSHED SURFACING BASE COURSE TN 435 $50 $21,750
24 5-01 REPLACE CEMENT CONCRETE PANEL SY 82 $150 $12,300
25 GSP 5-04 5738 HMA FOR PAVEMENT REPAIR CL. 1/2 IN. PG 58H-22 TN 397 $190 $75,430
26 SP 7-08 3810 REMOVAL AND REPLACEMENT OF UNSUITABLE MATERIAL CY 613 $60 $36,780
27 SP 7-09 3866 DUCTILE IRON PIPE FOR WATER MAIN 6 IN. DIAM. LF 140 $150 $21,000
28 SP 7-09 3867 DUCTILE IRON PIPE FOR WATER MAIN 8 IN. DIAM. LF 1,436 $160 $229,760
29 SP 7-09 ABANDON WATER MAIN LINE AND SERVICE CONNECTIONS LS 1 $10,000 $10,000
30 7-12 6155 GATE VALVE 6 IN. EA 4 $2,000 $8,000
31 7-12 6160 GATE VALVE 8 IN. EA 8 $3,000 $24,000
32 SP 7-12 ADJUST WATER VALVE CAN EA 6 $600 $3,600
32 SP 7-14 3846 HYDRANT ASSEMBLY EA 3 $8,000 $24,000
33 SP 7-15 SINGLE SERVICE NEAR SIDE ___IN. CONNECTION EA 17 $2,000 $34,000
34 SP 7-15 SINGLE SERVICE FAR SIDE ___IN. CONNECTION EA 42 $4,500 $189,000
35 SP 8-02 ROADSIDE RESTORATION F.A.1$25,000 $25,000
36 SP 8-04 6700 CEMENT CONC. TRAFFIC CURB AND GUTTER LF 290 $35 $10,150
37 SP 8-14 7055 CEMENT CONC. SIDEWALK SY 574 $50 $28,700
$1,179,995
$0
$108,560
$1,288,555
0% Contingency
Sales Tax (9.2%)
TOTAL SCHEDULE D COST
Location
City of Bremerton
Owner
City of Bremerton
SCHEDULE D WATER IMPROVEMENTS
Final Estimate of Probable Cost
Date
Rev. April 19,2024
Subtotal
Project No.
214-1896-186
6th Street Preservation
Page 1 of 1Rev. May 8, 202433 34 35 3637 38 Docusign Envelope ID: F2A6866C-8A13-4D49-909C-11401DD9EE8E
Independent Estimate For Consultant Services Worksheet
Agency:
Date:
Comments
Indirect Cost Rate Cost (in percent) 171.54%$31,166.42
Fix Fee (in percent) 29.00%$5,268.89
Reimbursable
A. Travel and Per Diem
B. Reproduction Expenses
C. Computer Expense
D. Communication
E. Sampling and Testing
F. Outside Consultants
G. Other Material Testing $30,000.00
Total: $30,000.00
Sub-Total $84,603.91
*Contingencies *Contingencies $0.00
* Use only on Cost plus Fix Fee agreement Grand Total $84,604
Federal Project No.: STPUS-6566(014)
6th St Phase III Pavement Preservation
Chris Dimmitt, P.E. 6/4/24
Type of Services
Planning
Surveying
Project Management
Estimated Cost
Construction Support Services
$18,168.60Total
Geometrics / Hydraulics Engineering
Structural Engineering
Traffic Engineering
Environmental & permitting
Real Estates Services
$18,168.60
Public Involvement
Project Name:
Prepared By:
Geotechnical Engineering
City of Bremerton
Docusign Envelope ID: F2A6866C-8A13-4D49-909C-11401DD9EE8E
Lever, NedWeber, Shane0Chris DimmittBilly MorrisSara GomezBonsell, CathyTotal Hours Total Labor Dollars Task #Tasks & Subtasks
City Engineer
Managing
Engineer
(Transpo)
Civil Engineer
III
Engineering
Tech III
Engineering
Tech IV
Project
Assistant
Billing Rates 80.00 75.00 70.00 70.00 55.00 50.00 45.00
1 Pre-Construction 0 12 0 220 62 0 0 294 19,710.00$
Pre-Construction meeting 2 5 2 9
Submittal Review 10 115 25 150
RAM/ROM documentation 80 25 105
Project Paperwork Verifcation 20 10 30
0
2 Construction 0 80 0 705 935 90 20 1830 112,175.00$
Project Management/Engineering 80 500 0 580
Construction Inspection 135 700 70 905
Daily Quantity Tabulation 0 100 10 110
Inspectors Daily Reports 50 100 10 160
Progress Pay Estimates 0 20 35 20 75
0
3 Construction Meetings 0 60 0 70 35 2 30 197 12,775.00$
Weekly Project Meeting 60 60 30 2 30 182
Utility Coordination Meetings 10 5 15
0
0
0
4 Project Closeout 0 30 0 100 100 0 10 240 15,200.00$
project closeout paperwork 30 40 40 10 120
Project final progress payment 20 10 30
Punch List 20 30 50
Substantial Completion 10 10 20
Physical Completion 10 10 20
0
Task Total Hours 0 182 0 1095 1132 92 60 2561
Task Cost -$ 13,650.00$ -$ 76,650.00$ 62,260.00$ 4,600.00$ 2,700.00$ 159,860.00$
Avg Hrs/Wk Construction (T3+T4)0.0 7.0 0.0 38.8 48.5 4.6 2.5 (159,860.00)$
COB ENGINEERING LABOR ESTIMATE
CONSTRUCTION
6th St Pavement Preservation Phase 3 -
Naval Ave to Warren Ave
T:\PROJECT FILES\PROJECT - Transportation Files\315043 - 6th Street Preservation Phase 3\100 FINANCIAL\2 LOANS AND GRANTS\4- Obligation- CN\Revised CN ob.v2\6th St Phase III Staff Time Estimate.v4.xlsx Printed 5/28/20243:02 PM
Docusign Envelope ID: F2A6866C-8A13-4D49-909C-11401DD9EE8E
________________________________________________________________________________
Public Works & Utilities │ 345 6th Street Suite 100, Bremerton, WA 98312 * Phone (360) 473-5920 * Fax (360) 473-5398
Working for and with our citizens to establish Bremerton as Puget Sound’s most beautiful and livable waterfront city!
June 6, 2024
July 17, 2024
John Ho, P.E.
Local Programs Engineer
WSDOT Olympic Region
PO Box 47390
Olympia, WA 98504-7390
RE: Federal Aid #: STPUL-6566(014)
Project Title: 6th Street Preservation - Phase 3
Anticipated Ad Date: 9/10/24
Anticipated Bid Opening: 10/1/24
Local Agency: City of Bremerton
RIGHT OF WAY CERTIFICATE (#1)
NO RELOCATION
Dear Mr. Ho:
As per 23 CFR 635.309(c), right of way has been acquired in accordance with current FHWA
regulations (49 CFR Part 24) and policies covering the acquisition of real property and the
following applies:
I hereby certify that all necessary rights of way, including control of access rights have been
acquired including legal and physical possession for the following project:
The project will grind and overlay asphalt pavement on 6th Street from Naval Avenue to Warren
Avenue, including upgrading ADA curb ramps, watermain replacement, stormwater
improvements, and Veneta Avenue signal replacement.
No residential and/or non-residential relocation is required. There are no improvements to be
removed or demolished for the above-cited project.
I further certify that there were no residential individuals or families displaced by the above cited
project. Therefore, the provisions of current FHWA directives covering the relocation of
Docusign Envelope ID: F2A6866C-8A13-4D49-909C-11401DD9EE8E
________________________________________________________________________________
Public Works & Utilities │ 345 6th Street Suite 100, Bremerton, WA 98312 * Phone (360) 473-5920 * Fax (360) 473-5398
Working for and with our citizens to establish Bremerton as Puget Sound’s most beautiful and livable waterfront city!
displaced person(s) to DS&S housing and availability of adequate replacement housing are not
applicable to this project.
Sincerely,
Shane Weber, P.E., PTOE
Managing Engineer – Transportation Capital
Eva Betts
Local Agency Coordinator, WSDOT Local Programs
Olympic & Southwest Region
cc: Ned Lever, City Engineer
Chris Dimmitt, P.E., Project Engineer
Cathy Bonsell, Project Assistant
Chuck Schott, Senior Engineer (Parametrix)
Sonya Davis, Real Estate Agent
PROJECT FILE
Attachment: Project Survey Control and Right of Way Plans (Sheets RW00-RW04)
Shane Weber
Digitally signed by Shane Weber
DN: C=US,
E=Shane.Weber@ci.bremerton.wa.us,
O=City of Bremerton, OU=Engineering,
CN=Shane Weber
Reason: I am the author of this document
Date: 2024.07.17 13:53:28-07'00'
Eva
Betts
Digitally signed
by Eva Betts
Date:
2024.08.13
08:38:04 -07'00'
Docusign Envelope ID: F2A6866C-8A13-4D49-909C-11401DD9EE8E
LPA-399
Rev. 4/2024
August 13, 2024
Mr. Ralph Rizzo
Division Administrator
Federal Highway Administration
Olympia, WA 98501
RE: Fed. Aid #: STPUL-6566(014)
Project Title: 6th Street Preservation-Phase 3
Agency: City of Bremerton
Anticipated Ad Date: September 10, 2024
Anticipated Bid Opening: October 1, 2024
County: Kitsap
RIGHT OF WAY CERTIFICATE #1
NO RELOCATION
Dear Sir:
As per title 23 CFR 635.309(c), right of way has been acquired in accordance with current
FHWA regulations (49 CFR Part 24) and policies covering the acquisition of real property.
I hereby concur with the Local Agency and the Local Agency Coordinator; this project is
certified for construction.
Sincerely,
Michelle Newlean
Local Programs Right of Way Manager
Project Certification
MN:mn
cc: John Ho, Olympic Region Local Programs Engineer
Eva Betts, Olympic Region Local Agency Coordinator
Michelle
Newlean
Digitally signed by
Michelle Newlean
Date: 2024.08.13
09:51:16 -07'00'
Docusign Envelope ID: F2A6866C-8A13-4D49-909C-11401DD9EE8E
JB
CE per PA 9/28/23
9/28/23Jodie Beall Digitally signed by Jodie Beall
Date: 2023.09.28 08:18:45
-07'00'
Docusign Envelope ID: F2A6866C-8A13-4D49-909C-11401DD9EE8E
March 5, 2024
Mr. Thomas Knuckey Public Works Director City of Bremerton 100 Oyster Bay Avenue N
Bremerton, Washington 98312 City of Bremerton 6th Street Preservation - Phase 3 STPUL-6566(014) DBE Goal & Training Hours Dear Mr. Knuckey: The WSDOT Disadvantaged Business Enterprise (DBE) program, approved by FHWA, requires the evaluation of each local agency project to determine the feasibility of including DBE goals (See chapter 26 of the Local Agency Guidelines (LAG) manual). This office applied the criteria and established a Ten percent mandatory DBE goal for this project.
This evaluation of the mandatory DBE goal will remain in effect for one year from the date of this letter. If the advertisement is scheduled for a date more than one year after the date of this letter or the cost estimate changes more than twenty percent prior to going to advertisement, reevaluation of
the DBE goal is required. The following specifications must be included in your contract: WSDOT GSP 1-02.6.OPT3.New.GR1 APWA GSP 1-02.9 Option A, B, C, or D APWA GSP 1-03.3 Option A APWA GSP 1-07.11, Option B
In addition, a training goal of Zero hours were established for this project. Please note that failure to receive concurrence to award from Local Programs in accordance with the LAG manual will result in loss of federal participation. If you have any questions about the goal set, please feel free to contact Nina Jones at 360.947.6788, or by email at jonesni@wsdot.wa.gov.
Sincerely, Michele L. Britton, PE
Asst. State Local Programs Engineer Local Programs
MLB:jd:ml cc: John Ho, Olympic Region Local Programs Engineer, MS 47440
Docusign Envelope ID: F2A6866C-8A13-4D49-909C-11401DD9EE8E