Contract Award to Nisqually Construction COUNCIL MEETING Date: July 3, 2024
Services, LLC for Construction of Haddon
Department: Parks & Recreation
Park Improvement Project
Presenter: C. Berna/B. Hauschel
Phone: (360) 473-5429
SUMMARY:Sealed bids for construction of the Haddon Park Renovation Project were opened on
May 24, 2024. Seven (7) bids were received. Nisqually ConstructionServices, LLC was the lowest
responsive, responsible bidder with a bid of $775,237.01 (WSST included).
ATTACHMENTS:1) Bid Tabulation; 2) Project Budget SummaryUpdated 7/3/24 2:25PM;
3) Haddon Park Concept; 4) Contract5) Presentation6) Email with Attachments: Irrigation Plan and
Project Plans Added 7/3/24 11:50 AM
FISCAL IMPACTS(Include Budgeted Amount): Funding for the project includes: $939,700from
State of Washington RCO grants; $6,500 from Bremerton Parks Foundation grant;$132,000 CDBG
(for playground, not-in-contract), and $400k REET. Total project estimate is $1,715,817.
STUDY SESSION ACTION:Consent Agenda General Business Public Hearing
RECOMMENDED MOTION:
Move to award a contract in the amount of $775,237.01(WSST included) to Nisqually Construction
Services, LLC for construction of the Haddon Park Renovation Project;and authorize the Mayor to
finalize and execute the agreement with substantially the same terms and conditions as presented;and
further authorize a budget adjustment of$237,617per the attached project budget summary.
COUNCIL ACTION: Approve Deny Table Continue No Action