HomeMy WebLinkAbout07/03/2024 4N
AGENDA BILL
CITY OF BREMERTON
4N
CITY COUNCIL
SUBJECT:Study SessionDate: June 26, 2024
Construction Contract with Tucci & Sons, COUNCIL MEETING Date: July 3, 2024
Inc.for Anderson Creek Dam Removals
Department: Public Works & Utilities
Project
Presenter: DavidDinkuhn
Phone: (360) 473-5331
SUMMARY:
This Contract provides for the improvement of the west and east forks of Anderson Creek. Work
includes removal of existing dams and stream channel construction, installation and maintenance of
erosion and sediment controls. Four bids were received and were opened on May 30, 2024. Tucci &
Sons, Inc. was the lowest responsive bidder with a total bid in the amount of $1,391,656.81
(including sales tax).
ATTACHMENTS:
1)Contract
2)Vicinity Map
3)Bid Tabulation
FISCAL IMPACTS(Include Budgeted Amount): Project is included in the 2024 Water budget.
STUDY SESSION ACTION:Consent Agenda General Business Public Hearing
RECOMMENDED MOTION:
Move to approve the contract with Tucci & Sons, Inc.in the amount of $1,391,656.81(including sales
tax) for the Anderson Creek Dam Removals Project;and authorize the Mayor to finalize and execute
the agreement with substantially the same terms and conditions as presented.
COUNCIL ACTION: Approve Deny Table Continue No Action