CHANGE ORDER
CONTRACT CHANGE ORDER NO: 2
PROJECT NAME: Oyster Bay Ave Force Main Replacement
PROJECT NO: 5867 CONTRACTOR: Pape and Sons Construction, Inc.
ORIGINAL CONTRACT AMOUNT: $892,511.62 DAYS: 100
PREVIOUSLY APPROVED CHANGES: $223,149.11 DAYS: 0
THIS CHANGE: $18,559.27 DAYS: 0
REVISED CONTRACT AMOUNT: $1,134,220.00 DAYS: N/A
This Change Order covers changes to the subject contract as described herein. The Contractor shall construct, furnish equipment and materials, and perform all work as necessary or required to complete the Change Order Items. The increase or decrease in contract price shown below includes any applicable taxes. ________________________________________________________________________________ Rule 170 Rule 171 DESCRIPTION OF CHANGES INCREASE IN CONTRACT AMOUNT ($)
(DECREASE) IN CONTRACT AMOUNT ($)
X Item 1: Install channelization (striping) per the abbreviated channelization plan. The cost for this work is shown in the attached Work Change Directive #5.
Item 2: Contract amount is increased to add additional sales tax due to the tax rate increase from 9.0% to 9.2 that occurred during the project. NOTE: This amount is not included in the NET CHANGE IN THE CONTRACT AMOUNT below. This item adds sales tax only to the original contract amount and is not taxed further.
15,496.00
1,637.64
N/A
N/A
NET CHANGE IN CONTRACT AMOUNT INCREASE OR (DECREASE), Item 1 only 15,496.00 N/A
ESTIMATED SALES TAX AT 9.2%, Item 1 only 1,425.63 N/A
TOTAL (Item 1 plus Sales tax on Item 1 plus Item 2) 18,559.27 N/A
Contractor acknowledges and accepts that this Change Order constitutes final settlement of all claims
of any kind or nature arising from or connected with any work either covered or affected by this Change Order, including, without limitation, claims related to contract time, on-site or home office
DocuSign Envelope ID: 705ADACE-F8D5-483B-9DF0-640C9743EA6A
8/22/22Michele M. Filley
Ned Lever
Digitally signed by Ned LeverDN: C=US, E=ned.lever@ci.bremerton.wa.us,
O=City of Bremerton, OU=Engineering, CN=Ned Lever
Reason: I have reviewed this documentDate: 2022.08.22 13:12:50-07'00'
DocuSign Envelope ID: 705ADACE-F8D5-483B-9DF0-640C9743EA6A
8/24/2022
8/24/2022
OYSTER BAY AVE FORCE MAIN REPLACEMENT
STRIPING - TRAFFIC CONTROL ESTIMATE
LABOR
DESC QTY RATE HRS AMT
FOREMAN 1 80.00$ 8 640.00$
SUBTOTAL 640.00$
MARKUP (29%) 825.60$
EQUIPMENT
DESC QTY RATE HRS AMT
SERVICE TRUCK 1 70.00$ 8 560.00$
SUBTOTAL 560.00$
MARKUP (21%) 677.60$
TOTAL 2,000.00$
Striping contractor
Base bid 9,550.00$
12% Markup 1,146.00$
10,696.00$
Surveyor
12% Markup 2,500.00$
300.00$
2,800.00$ Total 15,496.00$
DocuSign Envelope ID: 705ADACE-F8D5-483B-9DF0-640C9743EA6A
DocuSign Envelope ID: 705ADACE-F8D5-483B-9DF0-640C9743EA6A
OFSHEETVERT.HORIZ.SCALECITY OF BREMERTONREVISIONSDEPARTMENT OF PUBLIC WORKS & UTILITIESCAD FILE:ENGINEERING DIVISIONIF NOT SCALE ACCORDINGLYTWO INCHES AT FULL SCALE1"02"PN:OYSTER BAY AVEFORCE MAIN REPLACEMENTCHANNELIZATION PLAN7115867
T:\PROJECT FILES\PROJECT - Utility Files\4557 - Northlake Way PRV Relocation\500 DESIGN PHASE\5 CAD\NLW-PRV.DWG
GORE AREA PLANR50.0'WHITE EDGE LINE (TYP)CONSTRUCTION NOTES1.CENTERLINE, EDGE LINE, WIDE LANE LINE,DOUBLE CENTER AND DOTTED EXTENSIONLINE PER WSDOT STD PLAN M-20.10-03.2.STOP LINE PER WSDOT STD PLAN M-24.60-04.3.TRAFFIC ARROW PER WSDOT STD PLANM-24.40-02.4.TRAFFIC LETTERS PER WSDOT STD PLANM-80.30-00.W ARSENAL WAY RUSSELL RD S
S OYSTER BAY AVETIE INTO EXISTING EDGE LINEKITSAP WY YELLOW EDGE LINE1"=5'S OYSTER BAY AVERUSSELL RD DocuSign Envelope ID: 705ADACE-F8D5-483B-9DF0-640C9743EA6A
175 Roy Rd SW Bldg C * Pacific, WA 98047Tel: 253-299-1200 * 253-299-1250
Lic. # SPECIPM781B9
ATTENTION:BRAD APPLEMAN ---PAPE & SONS
PROJECT:22-0518 OYSTER BAY AVE FORCEMAIN CITY OF BREMERTON
BID DATE:7/14/2022
ITEM DESCRIPTION PLAN UNIT UNIT TOTAL
#QTY BID BID
PER OYSTER BAY AVE FORCE MAIN REPLACEENT -$ -$
CHANNELIZATION PLAN NOT DATED -$ -$
-$ -$
1 PAINT LINE 8000.00 LF 0.65$ 5,200.00$
2 PAINTED WIDE LINE 200.00 LF 1.00$ 200.00$
3 PLASTIC 18-IN STOP LINE 11.00 LF 50.00$ 550.00$
4 PLASTIC TRAFFIC ARROW 6.00 LF 250.00$ 1,500.00$
5 PLASTIC TRAFFIC LETTER 4.00 LF 150.00$ 600.00$
6 OPTIONAL RAISED PAVEMENT MARKER TYPE 2 100.00 EA 15.00$ 1,500.00$
TOTAL 9,550.00$
STIPULATIONS:1. GENERAL CONTRACTOR TO PROVIDE TRAFFIC CONTROL & LAYOUT
2. PROPOSAL EXCLUDES BOND. BOND CAN BE PROVIDED AT 1.35% OF CONTRACT TOTAL
3. THIS PROPOSAL TO BE INCLUDED WITH CONTRACT DOCUMENTS.
4. PROPOSAL TO INCLUDE 1 MOBILIZATION. EACH ADDITIONAL MOBILIZATION TO BE $ 2,500.00.
For questions regarding this quote, please contact Larry Burgua - (360) 516-9656 / Larry.Burgua@SPMNW.com
Larry Burgua
Specialized Pavement Marking, LLC proposes to furnish all labor, equipment and materials necessary to complete referenced project
Quote good for 30 days from above date, after which time a price adjustment may be necessary.
PROPOSAL
PLEASE NOTIFY US RIGHT AWAY IF WE GOT THIS JOB SO WE CAN PROCESS AND CREATE A FILE
Page 1 of 1
DocuSign Envelope ID: 705ADACE-F8D5-483B-9DF0-640C9743EA6A
From:Brad Appleman
To:Michele Filley
Subject:FW: OBFM - striping plan
Date:Thursday, July 14, 2022 10:22:58 AM
Attachments:image001.png
CAUTION: This email originated from outside of the organization. Do not click links or open attachments unless
you recognize the sender and know the content is safe.
Cost if you want it surveyed
From: Brett Garr <bgarr@asesurvey.com>
Sent: Thursday, July 14, 2022 10:08 AM
To: Brad Appleman <brada@papeinc.com>
Cc: Michael Sjolin <msjolin@asesurvey.com>
Subject: RE: OBFM - striping plan
Brad,
$2,500, one mobilization and traffic control needs to be provided.
Regards,
Brett Garr ¦ Principal & Project ManagerAmerican Surveying & Environmental, LLC
1495 NW Gilman Boulevard, Suite 14Issaquah, Wa 98027Office: (425)881-7430 · FAX (425)881-7731 · CELL (206)719-0905http://asesurvey.com/
LAND SURVEYORS & CONSULTANTS
The information transmitted is intended only for the person or entity to which it is addressed and may contain confidential and/orprivileged material. Any review, retransmission, dissemination or other use of, or taking of any action in reliance upon, this information bypersons or entities other than the intended recipient is prohibited. If you receive this in error, please contact the sender and delete thematerial from any computer.
From: Brad Appleman <brada@papeinc.com>
Sent: Thursday, July 14, 2022 8:57 AM
To: Brett Garr <bgarr@asesurvey.com>
Subject: FW: OBFM - striping plan
Brett,
This is for that Oyster Bay project in Bremerton Could I get a price to have you lay this out?
Thanks
Bradley Appleman
DocuSign Envelope ID: 705ADACE-F8D5-483B-9DF0-640C9743EA6A
Project Manager
Pape & Sons Construction Inc.
9401 Bujacich Rd
Gig Harbor, WA 98332
Office (253) 851 6040
Mobile (253) 255 3802
From: Michele Filley <Michele.Filley@ci.bremerton.wa.us>
Sent: Thursday, July 14, 2022 8:13 AM
To: Brad Appleman <brada@papeinc.com>
Subject: OBFM - striping plan
Hi Brad,
Attached is the final striping plan for Oyster Bay Ave. It’s a bit more detailed that we were
anticipating so I think it will need to be staked. Let me know if you have questions. This will take a CO
to complete.
Thanks,
M
DocuSign Envelope ID: 705ADACE-F8D5-483B-9DF0-640C9743EA6A
Oyster Bay Avenue Force Main Replacement
Summary Table of Contract Amount Increase due to change in sales tax
Change Order #2 8/9/2022
At Bid During construction
Tax Rate 9%9.2%
Base Amount 818,818.00$ 818,818.00$
Sales Tax 73,693.62$ 75,331.26$
Total 892,511.62$ 894,149.26$
Difference 1,637.64$
Contract Amount
DocuSign Envelope ID: 705ADACE-F8D5-483B-9DF0-640C9743EA6A