HomeMy WebLinkAbout1 - Original Submission_ 2021-06-25_Contract Documents (1) Contract Documents For Downtown Bicycle Pedestrian Circulation Improvements City of Bremerton Project No. 315027 Bid Opening: 1:00 p.m., July 14, 2021 City Clerk’s Office, City Hall 345 Sixth Street, Suite 600 Bremerton, WA 98337-1873 Contact Person: Shane Weber, P.E. Public Works & Utilities 345 6th Street, Suite 500 Bremerton, WA 98337 Tel: (360) 473-2354 Shane.Weber@ci.bremerton.wa.us DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 City of Bremerton 233-1896-178 Downtown Bicycle Pedestrian Circulation Improvements I-3 June 2021 Contract Documents Certificate of Engineer CERTIFICATE OF ENGINEER The technical material and data contained in these Specifications for the Downtown Bicycle Pedestrian Circulation Improvements project were prepared under the supervision and direction of the undersigned, whose seal, as a professional engineer licensed to practice as such, is affixed below. Prepared by: Rhiannon Sayles, PE Project Engineer, Parametrix Recommended by: Shane Weber, PE Managing Engineer Approved by: Ned Lever, PE City Engineer 6/25/2021 Shane Weber Digitally signed by Shane Weber DN: C=US, E=Shane.Weber@ci.bremerton.wa.us, O=City of Bremerton, OU=Engineering, CN=Shane Weber Reason: I have reviewed this document Date: 2021.06.28 15:18:28-07'00' Ned Lever Digitally signed by Ned Lever DN: C=US, E=ned.lever@ci.bremerton.wa.us, O=City of Bremerton, OU=Engineering, CN=Ned Lever Date: 2021.06.29 13:50:22-07'00' DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 City of Bremerton 233-1896-178 Downtown Bicycle Pedestrian Circulation Improvements I-i June 2021 Contract Documents Table of Contents TABLE OF CONTENTS PAGE PART I – BIDDING REQUIREMENTS AND CONTRACT FORMS NOTICE INVITING BIDS .......................................................................................................... I-1 BIDDER’S CHECKLIST ........................................................................................................... I-5 BID PROPOSAL ...................................................................................................................... I-9 SCHEDULE OF VALUES ......................................................................................................I-11 PROPOSAL BOND .................................................................................................................I-15 CONTRACTOR’S REGISTRATION ........................................................................................I-17 STATEMENT OF BIDDER’S QUALIFICATIONS ....................................................................I-19 NON-COLLUSION DECLARATION ........................................................................................I-21 BIDDER’S SUBCONTRACTOR CONTACT REPORT ............................................................I-23 LOCAL AGENCY SUBCONTRACTOR LIST ..........................................................................I-25 BID CERTIFICATE – CORPORATION ...................................................................................I-27 BID CERTIFICATE – LIMITED LIABILITY COMPANY ............................................................I-29 BID CERTIFICATE – PARTNERSHIP ....................................................................................I-31 BID CERTIFICATE – JOINT VENTURE ..................................................................................I-33 INFORMATION REQUIRED OF BIDDER ...............................................................................I-35 PROPOSAL FOR INCORPORATING RECYCLED MATERIALS INTO THE PROJECT .........I-37 PUBLIC WORKS AGREEMENT .............................................................................................I-41 LOCAL AGENCY PROPOSAL BOND ....................................................................................I-57 LOCAL AGENCY PERFORMANCE BOND ............................................................................I-59 LOCAL AGENCY PAYMENT BOND .......................................................................................I-61 INSURANCE QUESTIONNAIRE.............................................................................................I-63 STATEMENT OF INTENT TO PAY PREVAILING WAGES, DEPARTMENT OF LABOR AND INDUSTRIES ...............................................................................................I-65 CERTIFICATION OF COMPLIANCE WITH WAGE PAYMENT STATUTES ...........................I-67 DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 TABLE OF CONTENTS (Continued) City of Bremerton 233-1896-178 Downtown Bicycle Pedestrian Circulation Improvements I-ii June 2021 Contract Documents Table of Contents PAGE PART II – SPECIAL PROVISIONS DIVISION 1 – GENERAL REQUIREMENTS ............................................................................II-3 DIVISION 2 – EARTHWORK ................................................................................................. II-41 DIVISION 8 – MISCELLANEOUS CONSTRUCTION ............................................................. II-43 DIVISION 9 – MATERIALS .................................................................................................... II-57 STANDARD PLANS (January 13, 2021) ................................................................................ II-61 APPENDICES A WAGE RATES B CONSTRUCTION PLANS C CONSTRUCTION FORMS D INADVERTENT DISCOVERY PLAN E KITSAP TRANSIT PROPERTY LETTER F VENDOR INFORMATION DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 PART I BIDDING REQUIREMENTS AND CONTRACT FORMS DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 City of Bremerton 233-1896-178 Downtown Bicycle Pedestrian Circulation Improvements I-1 June 2021 Contract Documents Notice Inviting Bids NOTICE INVITING BIDS for Downtown Bicycle Pedestrian Circulation Improvements City of Bremerton, Washington NOTICE INVITING BIDS RECEIPT OF BIDS: Sealed Bids for the Downtown Bicycle Pedestrian Circulation Improvements will be accepted by mail or in person by the City Clerk or designated staff on July 14, 2021, between 10:30 A.M. and 11:00 A.M. in front of the Norm Dicks Government Center located at 345 6th Street, Suite 100, Bremerton, WA 98337. The Government Center is closed to the public due to the COVID-19 pandemic and bidders will not be allowed in the building. The City will also accept bids via email. Bids via email shall be submitted to city.clerk@ci.bremerton.wa.us, with the Project Name noted on the subject line of the email to ensure property handling and delivery. All electronic documents shall be in PDF format and shall not exceed 10 MB in size. It is recommended under Message Properties the box for “Request a delivery receipt for this message” be checked as this is the only method by which verification of delivery will be given. Emailed bids will be received until 1:00 P.M. PST as shown on the wall clock inside the City Clerk’s office on July 14th, 2021. Bids received after the specified times and date specified will not be considered. Prospective bidders are hereby notified that they are solely responsible for ensuring timely delivery of their bid to the City of Bremerton. OPENING OF BIDS: The Bids will be publicly opened and read via Zoom at 1:00 p.m. PST on July 14, 2021. The link for the bid opening is located on the City’s website at: http://www.bremertonwa.gov/Bids.aspx. COMPLETION OF WORK: The WORK must be completed within thirty-five (35) working days after the commencement date stated in the Notice to Proceed. DESCRIPTION OF WORK: This contract provides for improvements to Washington Avenue, Pacific Avenue, Burwell Street, 1st Street, 2nd Street, and Austin Drive and includes, but is not limited to, temporary traffic control, hydroblasting existing pavement markings, illumination, traffic signal systems, permanent signing, and pavement marking, all in accordance with the Contract Plans, these Contract Provisions, and the Standard Specifications. Engineer’s Estimate range for this project is $411,000 to $566,000. All work shall be performed in accordance with the Contract Plans, these Contract Provisions, and the latest edition of the WSDOT/APWA Standard Specifications. PREVIEWING CONTRACT DOCUMENTS: Contract Documents may be previewed on printer ARC (formerly Reprographics Northwest) internet site before ordering (Go to ww.repronw.com, click on Public Planroom, and select project). PURCHASING CONTRACT DOCUMENTS: The Contract Documents may be ordered from ARC. Payment is typically cost of reproduction (non-refundable). Contact Bid Services at ARC in DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 City of Bremerton 233-1896-178 Downtown Bicycle Pedestrian Circulation Improvements I-2 June 2021 Contract Documents Notice Inviting Bids Tacoma: 1(800) 337-8103; FAX (253) 272-4064; E mail: seattle.id.bidservices@e-arc.com. Please call for availability and fax your request prior to picking up. Will-call option is available at ARC Tacoma, Seattle, or Bellevue offices. Subcontractors and those needing additional sets or partial sets may be purchased at cost of reproduction (non-refundable) from ARC. Bid sets can be mailed upon request and after receipt of reproduction costs and a non-refundable shipping and handling fee. Bid documents will be available beginning June 30, 2021. PROPOSALS: All bid proposals must be made on the blank forms furnished in the Contract Documents. Sealed envelopes containing bids shall be entitled: Downtown Bicycle Pedestrian Circulation Improvements. PROPOSAL BOND: Each bid proposal shall be accompanied by a bid proposal deposit in cash, certified check, cashier’s check, or surety bond in an amount equal to five percent (5%) of the amount of such bid proposal. The failure to furnish a bid deposit of a minimum of 5 percent shall make the bid nonresponsive and shall cause the bid to be rejected by the Contracting Agency. CONTRACT BOND: The successful bidder will also be required to provide a Performance Bond for 100 percent of the Contract Price. Should the successful bidder fail to enter into such contract and furnish satisfactory performance bond within the time stated in the specifications, the bid proposal deposit shall be forfeited to the City of Bremerton. BIDS TO REMAIN OPEN: The Bidder shall guarantee the Total Bid Price for a period of seventy-five (75) calendar days from the date of bid opening. WAGE RATES: The attention of Bidders is directed to the requirements and conditions of employment to be observed and the minimum wage rates to be paid under the Contract. PROJECT ADMINISTRATION: All communications relative to this WORK prior to opening bids shall be directed to: Communication by phone/email: Shane Weber, P.E. Telephone: (360) 473-2354 Email: shane.weber@ci.bremerton.wa.us Communication by mail: Department of Public Works and Utilities 645 6th Street, Suite 100 Bremerton, WA 98312 ATTN: Shane Weber, P.E. CITY’S RIGHTS RESERVED: The City of Bremerton reserves the right to reject any and all bids on any or all schedules or alternates or to waive any informalities in the bidding and shall determine which bid or bidders is the most satisfactory and responsible bidder and shall be the sole judge thereof. No plea of mistake in the bid shall be available to the bidder for the recovery of his/her deposit or as a defense to any action based upon the neglect or refusal to execute a contract. EQUAL EMPLOYMENT OPPORTUNITY STATEMENT: In the hiring of employees for the performance of work under this Contract, the Contractor, its subcontractors, or any person acting on behalf of the Contractor shall not discriminate in any employment practice on the basis of age DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 City of Bremerton 233-1896-178 Downtown Bicycle Pedestrian Circulation Improvements I-3 June 2021 Contract Documents Notice Inviting Bids (40+), sex, race, creed, color, national origin, sexual orientation/gender identity, marital status, military status, or the presence of any physical, mental, or sensory disability. ADA STATEMENT: The City of Bremerton does not discriminate on the basis of disability in programs and activities, which it operates pursuant to the requirements of the Americans with Disabilities Act of 1990, and ADA Amendments Act. This policy extends to both employment and admission to participation in the programs, services, and activities of the City of Bremerton. Reasonable accommodation for employees or applicants for employment will be provided. The City of Bremerton in accordance with Title VI of the Civil Rights Act of 1964, 78 Stat. 252, 42 U.S.C. 2000d to 2000d-4 and Title 49, Code of Federal Regulations, Department of Transportation, subtitle A, Office of the Secretary, Part 21, nondiscrimination in federally assisted programs of the Department of Transportation issued pursuant to such Act, hereby notifies all bidders that it will affirmatively insure that in any contract entered into pursuant to this advertisement, disadvantaged business enterprises will be afforded full opportunity to submit bids in response to this invitation and will not be discriminated against on the grounds of race, color, national origin, or sex in consideration for an award. Published: Daily Journal of Commerce: 06/30/2021 and 07/07/2021 Kitsap Sun: 06/30/2021 and 07/07/2021 OWMBE: 06/30/2021 and 07/07/2021 END OF NOTICE INVITING BIDS DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 City of Bremerton 233-1896-178 Downtown Bicycle Pedestrian Circulation Improvements I-4 June 2021 Contract Documents Notice Inviting Bids This Page Intentionally Left Blank DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 City of Bremerton 233-1896-178 Downtown Bicycle Pedestrian Circulation Improvements I-5 June 2021 Contract Documents Bidder’s Checklist BIDDER’S CHECKLIST This section lists the contract forms required for this project. The bidder’s attention is especially directed to the forms that must be executed in full as required and submitted with the bidder’s bid. These are indicated as follows in the section titled “Bid Documents.” BID DOCUMENTS These documents must be executed and submitted to the City with your bid, no later than the designated bid closing date and time. Bids that do not include all of the required forms, properly completed, may be declared unresponsive at the sole option of the City and as further specified on each form. 1. Bid Proposal 2. Schedule of Values 3. Proposal Bond This form to be executed by the bidder and the surety company unless bid is accompanied by a certified check. The amount of this bond shall be not less than five percent (5%) of the total amount bid and may be shown in dollars or on a percentage basis. 4. Contractor’s Registration The successful Bidder shall acquire and/or possess a current City of Bremerton Business License and any other licenses and permits which may be required to fulfill the obligations of the Contract as specified. Business and occupancy (B&O) taxes shall be paid when due and the CONTRACTOR will agree to assign any payments due to the City Clerk for payment of such taxes which have been declared delinquent. 5. Statement of Bidder’s Qualifications 6. Non-Collusion Declaration 7. Bidder’s Subcontractor Contact Report 8. Local Agency Subcontractor List 9. Bid Certificate Bids by corporations must be executed in the corporate name by the president, a vice-president, or other corporate officer. Such Bid shall be accompanied by the enclosed Certificate of Authority to sign, attested by the secretary or assistant secretary, and with the corporate seal affixed. The corporate address and state of incorporation must appear below the signature. Bids by partnerships must be executed in the partnership name and be signed by a managing partner, accompanied by the enclosed Certificate of Authority to sign, and his/her title must appear under the signature and the official address of the partnership must appear below the signature. DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 City of Bremerton 233-1896-178 Downtown Bicycle Pedestrian Circulation Improvements I-6 June 2021 Contract Documents Bidder’s Checklist Bids by joint ventures must be executed in the joint venture name and be signed by a joint venture managing partner, accompanied by the enclosed Certificate of Authority to sign, and his/her title must appear under the signature and the official address of the joint venture must appear below the signature. Bids by limited liability companies must be executed in the limited liability company name and be signed by a member, accompanied by the enclosed Certificate of Authority to sign, and his/her title must appear under the signature and the official address of the joint venture must appear below the signature. 10. Information Required of Bidder In selecting the lowest responsive, responsible Bidder, consideration will be given to the general competency of the Bidder for the performance of the WORK covered by the Bid. To this end, each Bid shall be supported by a statement of the Bidder’s experience as of recent date on the form entitled “INFORMATION REQUIRED OF BIDDER” bound herein. 11. Proposal for Incorporating Recycled Materials into the Project DOCUMENTS TO BE EXECUTED BY THE SUCCESSFUL BIDDER The following forms are to be executed after the contract is awarded. These forms must be submitted within five (5) calendar days after the date of Notice of Award of Contract. 1. Public Works Agreement 2. Local Agency Proposal Bond 3. Local Agency Performance Bond 4. Local Agency Payment Bond 5. Insurance Questionnaire 6. Statement of Intent to Pay Prevailing Wages, Department of Labor and Industries 7. Certification of Compliance with Wage Payment Statutes DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 SUBMIT THE ENCLOSED PROPOSAL BOND WITH YOUR PROPOSAL USE OF OTHER FORMS MAY SUBJECT YOUR BID TO REJECTION DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 This Page Intentionally Left Blank DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 City of Bremerton 233-1896-178 Downtown Bicycle Pedestrian Circulation Improvements I-10 June 2021 Contract Documents Bid Proposal This Page Intentionally Left Blank DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 City of Bremerton 233-1896-178 Downtown Bicycle Pedestrian Circulation Improvements I-14 June 2021 Contract Documents Schedule of Values This Page Intentionally Left Blank DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 City of Bremerton 233-1896-178 Downtown Bicycle Pedestrian Circulation Improvements I-16 June 2021 Contract Documents Proposal Bond This Page Intentionally Left Blank DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 City of Bremerton 233-1896-178 Downtown Bicycle Pedestrian Circulation Improvements I-18 June 2021 Contract Documents Contractor’s Registration This Page Intentionally Left Blank DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 City of Bremerton 233-1896-178 Downtown Bicycle Pedestrian Circulation Improvements I-21 June 2021 Contract Documents Non-Collusion Declaration NON-COLLUSION DECLARATION DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 City of Bremerton 233-1896-178 Downtown Bicycle Pedestrian Circulation Improvements I-22 June 2021 Contract Documents Non-Collusion Declaration This Page Intentionally Left Blank DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 City of Bremerton 233-1896-178 Downtown Bicycle Pedestrian Circulation Improvements I-24 June 2021 Contract Documents Bidder’s Subcontractor Contact Report This Page Intentionally Left Blank DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 City of Bremerton 233-1896-178 Downtown Bicycle Pedestrian Circulation Improvements I-26 June 2021 Contract Documents Local Agency Subcontractor List This Page Intentionally Left Blank DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 City of Bremerton 233-1896-178 Downtown Bicycle Pedestrian Circulation Improvements I-30 June 2021 Contract Documents Bid Certificate This Page Intentionally Left Blank DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 City of Bremerton 233-1896-178 Downtown Bicycle Pedestrian Circulation Improvements I-38 June 2021 Contract Documents Proposal for Incorporating Recycled Materials into the Project This Page Intentionally Left Blank DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 CONTRACT DOCUMENTS and CONTRACT BOND FORMS WILL BE PROVIDED TO THE SUCCESSFUL BIDDER ONLY DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 City of Bremerton Downtown Bicycle Pedestrian Circulation Improvements I-42 July 2021 Contract Documents Public Works Agreement PUBLIC WORKS AGREEMENT THIS AGREEMENT is entered into between the City of Bremerton, a Washington Municipal Corporation (“City”), and Sound Pacific Construction LLC (“Contractor”), whose mailing address is 6708 144th Street NW, Suite A; Gig Harbor, WA 98332. The parties agree as follows: 1.CONTRACTOR SERVICES. The Contractor shall perform the followingservices for the City: Downtown Bicycle Pedestrian Circulation Improvements Project 2.TIME OF COMPLETION. Contractor shall complete the work within 35 working days from the date of issuance of the City’s Notice to Proceed. 3.COMPENSATION. The City shall pay the Contractor the total amount of$__672,477.00 Applicable Washington State Retail Sales Tax on this contract shall be governed by WAC 458-20-171 and its related rules for the work contemplated in this agreement. The Contractor shall invoice the City monthly. The City will pay for the portion of the work described in the invoice that has been completed by the Contractor and approved by the City. The City payment shall not constitute a waiver of the City’s right to final inspection and acceptance of the project. A.Performance Bond. Pursuant to Chapter 39.08 RCW, the Contractor shallprovide the City a performance bond for the full contract amount to be in effect until thirty (30) days after the date of final acceptance, or until receipt of all necessary releases from the State Department of Revenueand the State Department of Labor and Industries and until settlement ofany liens filed under Chapter 60.28 RCW, whichever is later. B.Retainage. The City shall hold back a retainage in the amount of five percent (5%) of any and all payments made to contractor for a period ofthirty (30) days after the date of final acceptance, or until receipt of allnecessary releases from the State Department of Revenue and the StateDepartment of Labor & Industries and until settlement of any liens filed under Chapter 60.28 RCW, whichever is later. C.Defective or Unauthorized Work. The City reserves its right to withholdpayment from Contractor for any defective or unauthorized work.Defective or unauthorized work includes, without limitation: work and materials that do not conform to the requirements of this agreement; and DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 City of Bremerton Downtown Bicycle Pedestrian Circulation Improvements I-43 July 2021 Contract Documents Public Works Agreement extra work and materials furnished without the City’s written approval. If Contractor is unable, for any reason, to satisfactorily complete any portion of the work, the City may complete the work by contract or otherwise, and Contractor shall be liable to the City for any additional costs incurred by the City. “Additional costs” shall mean all reasonable costs, including legal costs and attorney fees, incurred by the City beyond the maximum Contract price specified above. The City further reserves its right to deduct the cost to complete the Contract work, including any Additional Costs, from any and all amounts due or to become due the Contractor. D.Final Payment: Waiver of Claims. THE MAKING OF FINALPAYMENT (EXCLUDING WITHHELD RETAINAGE) SHALL PRECLUDE ALL CLAIMS, EXCEPT THOSE PREVIOUSLY AND PROPERLY MADE AND IDENTIFIED BY CONTRACTOR ASUNSETTLED AT THE TIME REQUEST FOR FINAL PAYMENT ISMADE. 4.INDEPENDENT CONTRACTOR. Contractor is and shall be at all times acting as an independent contractor and not as an employee of the City. The Contractor shall secure at its expense, and shall be responsible for all payments of income tax, social security, state disability insurance compensation, unemployment compensation, and all other payroll deductions for the Contractor, officer, agents, employees and sub-contractors. The Contractor shall also secure all applicable business licenses, if required, in connection with the contract services, including all required licenses for Contractor's officers, agents, employees and sub-contractors. 5.TERMINATION. The City may terminate this agreement for good cause. “Good cause” shall include, without limitation, any one or more of the following events: A.The Contractor’s refusal or failure to supply a sufficient number ofproperly skilled workers or proper materials for completion of theContract work. B.The Contractor’s failure to complete the work within the time specified inthis agreement. C.The Contractor’s failure to make full and prompt payment to sub- contractors or for material or labor. D.The Contractor’s persistent disregard of federal, state or local laws, rulesor regulations. E.The Contractor’s filing for bankruptcy or becoming adjudged bankrupt. If the City terminates this agreement for good cause, the Contractor shall not receive any further monies due under this agreement until the Contract work is completed. DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 City of Bremerton Downtown Bicycle Pedestrian Circulation Improvements I-44 July 2021 Contract Documents Public Works Agreement 6.PREVAILING WAGES. Contractor shall file a “Statement of Intent to Pay Prevailing Wages” with the State of Washington Department of Labor & Industries prior to commencing the Contract work. Contractor shall pay prevailing wages and comply with Chapter 39.12 of the Revised Code of Washington, as well as any other applicable prevailing wage rate provisions. The latest prevailing wage rate revision issued by the Department of Labor and Industries is attached. 7.CHANGES. The City may issue a written work change directive for any changein the Contract work during the performance of this agreement. If the Contractor determines, for any reason, that a change order is necessary, Contractor must submit a written change order request to the City’s project manager within two (2) business days of the date the Contractor knew or should have known of the facts and events giving rise to the requested change. If the City determines that the change increases or decreases the Contractor’s costs or time for performance, the City will make an equitable adjustment. The City will attempt, in good faith, to reach agreement with the Contractor on all equitable adjustments. However, if the parties are unable to agree, the City will determine the equitable adjustment as it deems appropriate. The Contractor shall proceed with the change order work upon receiving a written work change directive or change order from the City. If the Contractor fails to require a change order within the time allowed, the Contractor waives its right to make any claim or submit subsequent change order requests for that portion of the contract work. If the Contractor disagrees with the equitable adjustment the Contractor must complete the change order work; however, the Contractor may elect to protest the adjustment as provided below: A.Procedure and Protest by the Contractor. If the Contractor disagrees withanything required by a work change directive or change order, includingany direction, instruction, interpretation, or determination by the City, the Contractor shall: 1.Immediately give a signed written notice of protest to the City; 2.Supplement the written protest within fourteen (14) calendar days with a written statement that provides the following information: a. The date of the Contract’s protest.b.The nature and circumstances that caused the protest.c.The provisions in this agreement that support the protest. d. The estimated dollar cost, if any, of the protested work and how that estimate was determined.e.An analysis of the progress schedule showing the schedulechange or disruption if the Contractor is asserting aschedule change or disruption. The Contractor shall keep complete records of extra costs and time incurred as a result of the protested work. The City shall have DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 City of Bremerton Downtown Bicycle Pedestrian Circulation Improvements I-45 July 2021 Contract Documents Public Works Agreement access to any of the Contractor’s records needed for evaluating the protest. 3.The City will evaluate all protests, provided the procedures in thissection are followed. If the City determines that a protest is valid,the City will adjust payment for work or time by an equitableadjustment. No adjustment will be made for an invalid protest. B.Contractor’s Duty to Complete Protested Work. In spite of any protest,the Contractor shall proceed promptly with the work as the City hasordered. C.Contractor’s Acceptance of Changes. The Contractor accepts all requirements of a change order by: (1) endorsing it, (2) writing a separateacceptance, or (3) not protesting in the way this section provides. Achange order that is accepted by Contractor as provided in this sectionshall constitute full payment and final settlement of all claims for contract time and for direct, indirect and consequential costs, including costs of delays related to any work, either covered or affected by the change. D.Failure to Protest Constitutes Waiver. By not protesting as this sectionprovides, the Contractor also waives any additional entitlement and accepts from the City any written order (including directions, instructions, interpretations, and determination). E.Failure to Follow Procedures Constitutes Waiver. By failing to follow theprocedures of this section, the Contractor completely waives any claims for protested work and accepts form the City any written order (including directions, instructions, interpretations, and determination). 8.CLAIMS. The Contractor shall give written notice to the City of all claims otherthan change orders within fourteen (14) calendar days of the occurrence of the events giving rise to the claims. Any claim for damages, additional payment for any reason, or extension of time, whether under this agreement or otherwise, shall be conclusively deemed to have been waived by the Contractor unless a timely written claim is made in strict accordance with the applicable provisions of this agreement; or, if (and only if) no such provision is applicable, unless that claim is set forth in detail in writing and received by the City within seven (7) calendar days from the date Contractor knew, or should have known, of the facts giving rise to the claim. At a minimum, a Contractor’s written claim must include the information set forth regarding protests in Section 7.A.2.a.-e. FAILURE TO PROVIDE A COMPLETE, WRITTEN NOTIFICATION OF CLAIM WITHIN THE TIME ALLOWED SHALL BE AN ABSOLUTE WAIVER OF ANY CLAIMS ARISING IN ANY WAY FROM THE FACTS OR EVENTS SURROUNDING THAT CLAIM OR CAUSED BY THAT DELAY. DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 City of Bremerton Downtown Bicycle Pedestrian Circulation Improvements I-46 July 2021 Contract Documents Public Works Agreement Contractor must, in any event, file any claim or bring any suit arising from or connected with this agreement within 120 calendar days from the date the contract work is complete. 9.WARRANTY. The Contractor shall correct all defects in workmanship andmaterials within one year from the date of the City’s acceptance of the Contract work. When defects are corrected, the warranty for that portion of the work shall extend for one year form the date such correction is completed and accepted by the City. The Contractor shall begin to correct any defects within seven (7) calendar days of its receipt of notice from the City of the defect. If the Contractor does not accomplish the corrections within a reasonable time, the City may complete the corrections and the Contractor shall pay all costs incurred by the City in order to accomplish the correction. 10.INDEMNIFICATION. Contractor shall defend, indemnify and hold the City, its officer, officials, employees, agents and volunteers harmless from any and all claims, injuries, damages, losses or suits including all legal costs and attorney fees, arising out of or in connection with the performance of this agreement, except for injuries and damages caused by the City’s sole negligence. The City’s inspection or acceptance of any of Contractor’s work when completed shall not be grounds to avoid any of these covenants of indemnification. Should a court of competent jurisdiction determine that this agreement is subject to RCW 4.24.115, then, in the event of liability for damages arising out of bodily injury to persons or damages to property caused by or resulting from the concurrent negligence of the Contractor and the City, its officials, employees, agents and volunteers, the Contractor’s liability hereunder shall be only to the extent of the Contractor’s negligence. IT IS FURTHER SPECIFICALLY AND EXPRESSLY UNDERSTOOD THAT THIS INDEMNIFICATION CONSTITUTES THE CONTRACTOR’S WAIVER OF IMMUNITY UNDER INDUSTRIAL INSURANCE, TITLE 51 RCW, SOLELY FOR THE PURPOSE OF THIS INDEMNIFICATION. THE PARTIES ACKNOWLEDGE THAT THEY HAVE MUTUALLY NEGOTIATED THIS WAIVER. The provisions of this section shall survive the expiration or termination of this agreement. PUBLIC WORKS CONTRACTS: 11.INSURANCE. The Contractor shall procure and maintain for the duration of this agreement insurance of the types and in the amounts described below against claims for injuries to persons or damage to property which may arise from or in connection with the performance of the work by the Contractor, its agents, representative, employees, sub-consultants or sub-contractors. Before beginning work on the project described in this agreement, the Contractor shall provide a Certificate of Insurance evidencing: DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 City of Bremerton Downtown Bicycle Pedestrian Circulation Improvements I-47 July 2021 Contract Documents Public Works Agreement A.Automobile Liability insurance with limits no less than $1,000,000 combined single limit per accident for bodily injury and property damage; and B.Commercial General Liability insurance written on an occurrence basiswith limits no less than $1,000,000 combined single limit per occurrence and $2,000,000 general aggregate for personal injury, bodily injury and property damage. Coverage shall include but not be limited to: blanketcontractual; products/completed operations/broad form property damage;explosion, collapse and underground (XCU); and C.Excess Liability insurance with limits not less than $1,000,000 per occurrence and aggregate; and B.Workers Compensation insurance as statutorily required by the IndustrialInsurance Act of the State of Washington, Title 51, Revised Code of Washington and employer's liability with limits not less than $1,000,000. Any payment of deductible or self-insured retention shall be the sole responsibility of the Contractor. The City, its officials, employees, agents and volunteers shall be named as an additional insured on the insurance policy, as respects work performed by or on behalf of the Contractor and a copy of the endorsement naming the City as additional insured shall be attached to the Certificate of Insurance. The Contractor’s insurance shall contain a clause stating that coverage shall apply separately to each insured against whom claim is made or suit is brought, except with respects to the limits of the insurer’s liability. The Consultant's insurance shall be primary and non-contributory insurance as respects the City and shall contain a waiver of subrogation against the City for claims arising out of any operations, liabilities and obligations to which coverage applies. It shall be an affirmative obligation upon Consultant to advise the City’s Risk Manager by fax at (360) 473-5161, or by certified mail, return receipt requested to City of Bremerton, attn: Risk Management, 345 6th Street, Suite 100, Bremerton, WA 98337 within two days of the cancellation, suspension or substantive change of any insurance policy set out herein, and failure to do so shall be construed to be a breach of this Agreement. The City reserves the right to receive a certified copy of all the required insurance policies. DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 City of Bremerton Downtown Bicycle Pedestrian Circulation Improvements I-48 July 2021 Contract Documents Public Works Agreement 12.MISCELLANEOUS. A.Equal Employment Opportunity Statement. In the hiring of employees forthe performance of work under this Agreement, the Contractor, its subcontractors, or any person acting on behalf of Contractor shall not discriminate in any employment practice on the basis of age (40+), sex, race, creed, color, national origin, sexual orientation/gender identity, marital status, military status, or the presence of any physical, mental or sensory disability. B.ADA Statement. The City of Bremerton does not discriminate on thebasis of disability in programs and activities, which it operates pursuant to the requirements of the Americans with Disabilities Act of 1990, and ADA Amendments Act. This policy extends to both employment and admission to participation in the programs, services and activities of the City of Bremerton. Reasonable accommodation for employees or applicants for employment will be provided. C.Compliance with Laws. Contractor shall comply with all federal, state and local laws, rules and regulations throughout every aspect in the performance of this agreement. D.Work Performed at Contractor’s Risk. Contractor shall take allprecautions necessary and shall be responsible for the safety of its employees, agents, and subcontractors in the performance of this agreement. All work shall be done at Contractor’s own risk, and Contractor shall be responsible for any loss of or damage to materials, tools, or other articles used or held for use in connection with the work. E.Nonwaiver of Breach. The failure of the City to insist upon strict performance of any of the terms and rights contained herein, or to exercise any option herein conferred in one or more instances, shall not be constructed to be a waiver or relinquishment of those terms and rights and they shall remain in full force and effect F.Governing Law. This agreement shall be governed and construed in accordance with the laws of the State of Washington. If any dispute arises between the City and Contractor under any of the provisions of this agreement, resolution of that dispute shall be available only through the jurisdiction, venue and rules of the Kitsap County Superior Court, Kitsap County, Washington. G.Attorney’s Fees. To the extent not inconsistent with RCW 39.04.240, inany claim or lawsuit for damages arising from the parties’ performance of this agreement, each party shall be responsible for payment of its own legal costs and attorney’s fees incurred in defending or bringing such claim or lawsuit; however, nothing in this subsection shall limit the City’s right to indemnification under Section 10 of this agreement. H.Written Notice. All communications regarding this agreement shall besent to the parties at the addresses listed on the signature page of this agreement, unless otherwise notified. Any written notice shall become effective upon delivery, but in any event three (3) calendar days after the date of mailing by registered or certified mail, and shall be deemed sufficiently given if sent to the addressee at the address stated on this agreement. DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 City of Bremerton Downtown Bicycle Pedestrian Circulation Improvements I-49 July 2021 Contract Documents Public Works Agreement I. Assignment. Any assignment of this agreement by the Contractor without the written consent of the City shall be void. J.Modification. No waiver, alteration, or modification of any of theprovisions of this agreement shall be binding unless in writing and signed by a duly authorized representative of the City and Contractor. K.Severability. If any one or more sections, sub-sections, or sentences ofthis agreement are held to be unconstitutional or invalid, that decision shall not affect the validity of the remaining portion of this agreement and the remainder shall remain in full force and effect. L.Entire Agreement. The written provisions and terms of this agreement,together with any attached Exhibits, supersede all prior verbal statements by any representative of the City, and those statements shall not be construed as forming a part of or altering in any manner this agreement. This agreement and any attached Exhibits contain the entire agreement between the parties. Should any language in any Exhibit to this agreement conflict with any language contained in this agreement, the terms of this agreement shall prevail. IN WITNESS WHEREOF, the parties below have executed this agreement. SOUND PACIFIC CONSTRUCTION LLC THE CITY OF BREMERTON Print Name: Print Name: Greg Wheeler________ Title: Title: Mayor DATE DATE Notices to be sent to: Notices to be sent to: SOUND PACIFIC CONSTRUCTION LLC CITY OF BREMERTON: 6708 144th Street NW, Suite A Shane Weber Gig Harbor, WA 98332 345 6th Street, Suite 100 (253) 614-6226 Bremerton, WA 98337 (253) 444-0049 (facsimile)(360) 473-2354 Shane.weber@ci.bremerton.wa.us Tom Abplanalp Managing Member DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 8/24/2021 8/24/2021 City of Bremerton Downtown Bicycle Pedestrian Circulation Improvements I-50 July 2021 Contract Documents Public Works Agreement APPROVED AS TO FORM: Bremerton City Attorney ATTEST: Angela Hoover, City Clerk R:\Legal\Legal\Forms\FORMS ON COBWEB\Public Works Agreement (short form) Rev. 06 2020.DOC DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 City of Bremerton 233-1896-178 Downtown Bicycle Pedestrian Circulation Improvements I-56 June 2021 Contract Documents Public Works Agreement This Page Intentionally Left Blank DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 City of Bremerton 233-1896-178 Downtown Bicycle Pedestrian Circulation Improvements I-58 June 2021 Contract Documents Local Agency Proposal Bond This Page Intentionally Left Blank DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 City of Bremerton 233-1896-178 Downtown Bicycle Pedestrian Circulation Improvements I-59 June 2021 Contract Documents Local Agency Performance Bond LOCAL AGENCY PERFORMANCE BOND DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 City of Bremerton 233-1896-178 Downtown Bicycle Pedestrian Circulation Improvements I-60 June 2021 Contract Documents Local Agency Performance Bond This Page Intentionally Left Blank DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 City of Bremerton 233-1896-178 Downtown Bicycle Pedestrian Circulation Improvements I-61 June 2021 Contract Documents Local Agency Payment Bond LOCAL AGENCY PAYMENT BOND DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 City of Bremerton 233-1896-178 Downtown Bicycle Pedestrian Circulation Improvements I-62 June 2021 Contract Documents Local Agency Payment Bond This Page Intentionally Left Blank DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 City of Bremerton 233-1896-178 Downtown Bicycle Pedestrian Circulation Improvements I-63 June 2021 Contract Documents Insurance Questionnaire INSURANCE QUESTIONNAIRE NOTE: THIS QUESTIONNAIRE MUST BE COMPLETED AND ATTACHED TO THE CERTIFICATE OF INSURANCE For (Name of Insured) Project Name Project Owner ARE THE FOLLOWING COVERAGES AND/OR CONDITIONS IN EFFECT? YES NO The Policy form is ISO Commercial General Liability from CG 00 01 or CG 00 02 (circle one). If NO, attach a copy of the policy with required coverage clearly identified. Products and Completed Operation coverage. Cross Liability Clause (or equivalent wording). Personal Injury Liability (with employee exclusion deleted). Broad Form Property Damage with X, C, U Hazards included Blanket Contractual Liability coverage applying to this Contract Employers Liability – Stop Gap Deductibles or SIR's GL AL Excess Insurer's Best Rating GL AL Excess This Questionnaire is issued as a matter of information. This Questionnaire is not an insurance policy and does not amend, extend or alter the coverage afforded by the policies indicated on the attached Certificate of Insurance. Agency/Broker Completed by (print or type) Address Completed by (signature) Name of Person to Contact Telephone Number Sound Pacific Construction LLC X X X X X X X 0 0 10,000 A+A+A+ Rice Insurance LLC 1400 Broadway, Bellingham WA 98225 Rita Larsen Rita Larsen 360-734-1161 DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 08/11/2021 Rice Insurance LLC 1400 Broadway P.O. Box 639 Bellingham WA 98227 Rita Larsen (360) 734-1161 (360) 734-1173 rita@riceinsurance.com Sound Pacific Construction LLC 6708 144th St. NW Suite A Gig Harbor WA 98332 BITCO Insurance Companies 20095 Ironshore Specialty Insurance Company 25445 CL2172185210 A Y Y CLP3708275 07/25/2021 07/25/2022 1,000,000 5,000 10,000 1,000,000 2,000,000 2,000,000 A Y Y CAP3708274 07/25/2021 07/25/2022 1,000,000 A 10,000 Y Y CUP2821428 07/25/2021 07/25/2022 2,000,000 2,000,000 A CLP3708275 07/25/2021 07/25/2022 1,000,000 1,000,000 1,000,000 B Pollution Liability ICELLUW00111264 07/25/2020 07/25/2021 Aggregate 1,000,000 Each Incident 1,000,000 Certificate Holder is Additional Insured on the General Liability coverage. Coverage is primary and non-contributory, Waiver of Subrogation, Ongoing Operations and Completed Operation for the General Liability. Per GL3085 & GL2784 attached. Auto Liability- Additional Insured, Waiver of Subrogationand Primary Non Contributory per AP04011017. Umbrella follows form for General Liability, Employers Liability and Auto Liability. City of Bremerton Public Works & Utilities 345 6th Street Suite 100 Bremerton WA 98337 SHOULD ANY OF THE ABOVE DESCRIBED POLICIES BE CANCELLED BEFORE THE EXPIRATION DATE THEREOF, NOTICE WILL BE DELIVERED IN ACCORDANCE WITH THE POLICY PROVISIONS. INSURER(S) AFFORDING COVERAGE INSURER F : INSURER E : INSURER D : INSURER C : INSURER B : INSURER A : NAIC # NAME:CONTACT (A/C, No):FAX E-MAILADDRESS: PRODUCER (A/C, No, Ext):PHONE INSURED REVISION NUMBER:CERTIFICATE NUMBER:COVERAGES IMPORTANT: If the certificate holder is an ADDITIONAL INSURED, the policy(ies) must have ADDITIONAL INSURED provisions or be endorsed. If SUBROGATION IS WAIVED, subject to the terms and conditions of the policy, certain policies may require an endorsement. A statement on this certificate does not confer rights to the certificate holder in lieu of such endorsement(s). THIS CERTIFICATE IS ISSUED AS A MATTER OF INFORMATION ONLY AND CONFERS NO RIGHTS UPON THE CERTIFICATE HOLDER. THIS CERTIFICATE DOES NOT AFFIRMATIVELY OR NEGATIVELY AMEND, EXTEND OR ALTER THE COVERAGE AFFORDED BY THE POLICIES BELOW. THIS CERTIFICATE OF INSURANCE DOES NOT CONSTITUTE A CONTRACT BETWEEN THE ISSUING INSURER(S), AUTHORIZED REPRESENTATIVE OR PRODUCER, AND THE CERTIFICATE HOLDER. OTHER: (Per accident) (Ea accident) $ $ N / A SUBR WVD ADDL INSD THIS IS TO CERTIFY THAT THE POLICIES OF INSURANCE LISTED BELOW HAVE BEEN ISSUED TO THE INSURED NAMED ABOVE FOR THE POLICY PERIOD INDICATED. NOTWITHSTANDING ANY REQUIREMENT, TERM OR CONDITION OF ANY CONTRACT OR OTHER DOCUMENT WITH RESPECT TO WHICH THIS CERTIFICATE MAY BE ISSUED OR MAY PERTAIN, THE INSURANCE AFFORDED BY THE POLICIES DESCRIBED HEREIN IS SUBJECT TO ALL THE TERMS, EXCLUSIONS AND CONDITIONS OF SUCH POLICIES. LIMITS SHOWN MAY HAVE BEEN REDUCED BY PAID CLAIMS. $ $ $ $PROPERTY DAMAGE BODILY INJURY (Per accident) BODILY INJURY (Per person) COMBINED SINGLE LIMIT AUTOS ONLY AUTOSAUTOS ONLY NON-OWNED SCHEDULEDOWNED ANY AUTO AUTOMOBILE LIABILITY Y / N WORKERS COMPENSATION AND EMPLOYERS' LIABILITY OFFICER/MEMBER EXCLUDED?(Mandatory in NH) DESCRIPTION OF OPERATIONS belowIf yes, describe under ANY PROPRIETOR/PARTNER/EXECUTIVE $ $ $ E.L. DISEASE - POLICY LIMIT E.L. DISEASE - EA EMPLOYEE E.L. EACH ACCIDENT EROTH-STATUTEPER LIMITS(MM/DD/YYYY)POLICY EXP(MM/DD/YYYY)POLICY EFFPOLICY NUMBERTYPE OF INSURANCELTRINSR DESCRIPTION OF OPERATIONS / LOCATIONS / VEHICLES (ACORD 101, Additional Remarks Schedule, may be attached if more space is required) EXCESS LIAB UMBRELLA LIAB $EACH OCCURRENCE $AGGREGATE $ OCCUR CLAIMS-MADE DED RETENTION $ $PRODUCTS - COMP/OP AGG $GENERAL AGGREGATE $PERSONAL & ADV INJURY $MED EXP (Any one person) $EACH OCCURRENCEDAMAGE TO RENTED $PREMISES (Ea occurrence) COMMERCIAL GENERAL LIABILITY CLAIMS-MADE OCCUR GEN'L AGGREGATE LIMIT APPLIES PER: POLICY PRO-JECT LOC CERTIFICATE OF LIABILITY INSURANCE DATE (MM/DD/YYYY) CANCELLATION AUTHORIZED REPRESENTATIVE ACORD 25 (2016/03) © 1988-2015 ACORD CORPORATION. All rights reserved. CERTIFICATE HOLDER The ACORD name and logo are registered marks of ACORD HIREDAUTOS ONLY DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 BITCO GENERAL INSURANCE CORPORATION BITCO NATIONAL INSURANCE COMPANY AP-0401 (10/17) -1- THIS ENDORSEMENT CHANGES THE POLICY. PLEASE READ IT CAREFULLY. BROADENED COVERAGE - AUTOMOBILES The following modifies insurance provided under: BUSINESS AUTO COVERAGE FORM With respect to coverage provided by this endorsement, the provisions of the Coverage Form apply unless modified by this endorsement. 1 - Broad Form Named Insured 11 - Bodily Injury Extension 2 - Automatic Waiver of Subrogation 12 - Hired Auto Physical Damage 3 - Automatic Additional Insured 13 - Enhanced Supplementary Payments 4 - Primary and Noncontributory - Other Insurance Condition 14 - Fellow Employee Coverage for Designated Positions 5 - Unintentional Failure to Disclose Hazards 15 - Physical Damage – Transportation Expenses 6 - Extended Notice of Cancellation, Non-Renewal 16 - Rental Reimbursement Coverage 7 - When We Do Not Renew 17 - Loan/Lease Gap Coverage 8 - Notice of Knowledge of Accident or Loss 18 - Accidental Air Bag Discharge Coverage 9 - Employees as Insured 19 - Glass Repair – Waiver of Deductible 10 - Employee Hired Autos 1. BROAD FORM NAMED INSURED SECTION II. A. 1. -WHO IS AN INSURED - Paragraph d. is added: d. Any organization you newly acquire or form, except for a partnership, joint venture or limited liability company, and over which you maintain majority ownership or interest (51% or more) or for which you have assumed the active management, will qualify as a Named Insured if there is no other similar insurance available to that organization. However, coverage under this provision is only afforded until the end of the policy period or the 12-month anniversary of the policy inception date, whichever is earlier. 2. AUTOMATIC WAIVER OF SUBROGATION Section IV – Business Auto Conditions, Paragraph A.5., Transfer of Rights of Recovery Against Others to Us, is deleted and replaced with the following: a. If the insured has rights to recover all or part of any payment we have made under this Coverage Form, those rights are transferred to us. The insured must do nothing after loss to impair those rights. At our request, the insured will bring "suit" or transfer those rights to us and help us enforce them. b. If required by a written contract executed prior to loss, we waive any right of recovery we may have against any person or organization because of payments we make for damages under this coverage form. DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 AP-0401 (10/17) -2- 3. AUTOMATIC ADDITIONAL INSURED SECTION II – WHO IS AN INSURED, Paragraph A.1, is amended to include as an "insured" any person or organization who is required by written contract or agreement to be an additional insured on your policy, but only with respect to liability arising out of operations performed by you or on your behalf for the additional insured. 4. PRIMARY AND NONCONTRIBUTORY - OTHER INSURANCE CONDITION The following is added to the Other Insurance Condition in the Business Auto Coverage Form and the Other Insurance - Primary And Excess Insurance Provisions in the Motor Carrier Coverage Form and supersedes any provision to the contrary: This Coverage Form's Covered Autos Liability Coverage is primary to and will not seek contribution from any other insurance available to an "insured" under your policy provided that: 1. Such "insured" is a Named Insured under such other insurance; and 2. You have agreed in writing in a contract or agreement that this insurance would be primary and would not seek contribution from any other insurance available to such "insured". 5. UNINTENTIONAL FAILURE TO DISCLOSE HAZARDS Although we relied on your representations as to existing and past hazards, if unintentionally you should fail to disclose all such hazards at the inception date of your policy, we will not deny coverage under this Coverage Form because of such failure. 6. EXTENDED NOTICE OF CANCELLATION, NON-RENEWAL The COMMON POLICY CONDITIONS, Item A.2.b. is deleted and replaced with the following: A.2.b. 60 days before the effective date of the cancellation if we cancel for any other reason. 7. WHEN WE DO NOT RENEW SECTION IV – BUSINESS AUTO CONDITIONS, is amended to add Item B.9.: a. If we choose to nonrenew this policy, we will mail or deliver to the first Named Insured shown in the Declarations written notice of the nonrenewal not less than 60 days before the expiration date. b. If we do not give notice of our intent to nonrenew as prescribed in a. above, it is agreed that you may extend the period of this policy for a maximum additional sixty (60) days from its scheduled expiration date. Where not otherwise prohibited by law, the existing terms, conditions and rates will remain in effect during that extension period. It is further agreed that so long as it is not otherwise prohibited by law, this one-time sixty-day extension is the sole remedy and liquidated damages available to the insured as a result of our failure to give the notice as prescribed in 9. a. above. 8. NOTICE OF KNOWLEDGE OF ACCIDENT OR LOSS SECTION IV - BUSINESS AUTO CONDITIONS, Item A.2.a. is deleted and replaced with the following: 2. Duties in the Event of Accident, Claim Suit or Loss: a. You must see to it that we are notified of an "accident", "claim", "suit" or "loss" which may result in a claim as soon as practicable after the "occurrence" has been reported to you, a partner, a member, an officer, or an employee designated to give notice to us. Notice should include: DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 AP-0401 (10/17) -3- (1) How, when and where the "accident" or "loss" occurred; (2) The "insured's" name and address; and (3) To the extent possible, the names and addresses of any injured persons and witnesses. 9. EMPLOYEES AS INSURED The following is added to the Section II - Covered Autos Liability Coverage, Paragraph A.1. Who Is An Insured provision: Any "employee" of yours is an "insured" while using a covered "auto" you don't own, hire or borrow in your business or your personal affairs. 10. EMPLOYEE HIRED AUTOS A. Changes In Covered Autos Liability Coverage The following is added to the Who Is An Insured Provision: An "employee" of yours is an "insured" while operating an "auto" hired or rented under a contract or agreement in an "employee's" name, with your permission, while performing duties related to the conduct of your business. B. Changes In General Conditions Paragraph 5.b. of the Other Insurance Condition in the Business Auto Coverage Form and Paragraph 5.f. of the Other Insurance - Primary And Excess Insurance Provisions Condition in the Motor Carrier Coverage Form are replaced by the following: For Hired Auto Physical Damage Coverage, the following are deemed to be covered "autos" you own: 1. Any covered "auto" you lease, hire, rent or borrow; and 2. Any covered "auto" hired or rented by your "employee" under a contract in an "employee's" name, with your permission, while performing duties related to the conduct of your business. However, any "auto" that is leased, hired, rented or borrowed with a driver is not a covered "auto". 11. BODILY INJURY EXTENSION SECTION V - DEFINITIONS, Paragraph C. is deleted and replaced by the following: C. "Bodily injury" means bodily injury, sickness or disease sustained by a person, including mental anguish or death resulting from any of these, at any time. Mental anguish means any type of mental or emotional illness or disease. 12. HIRED AUTO PHYSICAL DAMAGE SECTION III.A.4. - Coverage Extensions - Paragraph c. is added: c. Hired Auto Physical Damage If Comprehensive, Specified Causes of Loss or Collision coverage is provided under this policy, then Hired Auto Physical Damage is provided for that coverage part subject to the following: DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 AP-0401 (10/17) -4- (1) The most we will pay for any one "accident" or "loss" under this Hired Auto Physical Damage Coverage is the lesser of: (a) The any one "Accident" or "Loss" amount of $100,000; (b) The actual cash value; or (c) Cost of repair. Our obligation to pay for a loss in c.(1) above will be reduced by a deductible. The deductible will be equal to the largest deductible applicable to any owned "auto" for that coverage. The deductible will be waived for "loss" caused by fire or lightning. (2) Subject to paragraph c.(1). above, we will provide coverage equal to the broadest physical damage coverage applicable to any covered "auto" shown in the declarations. (3) When you are required by written contract to indemnify a lessor for actual financial loss because of loss of use of a hired "auto" resulting from a covered "accident" or "loss", we will cover that financial loss subject to the limit specified in paragraph c.(1). 13. ENHANCED SUPPLEMENTARY PAYMENTS SECTION II.A.2.a. COVERAGE EXTENSIONS, Supplementary Payments (2) and (4) are replaced by the following: (2) Up to $2,500 for the cost of bail bonds (including bonds for related traffic laws violations) required because of an "accident" we cover. We do not have to furnish these bonds. (4) All reasonable expenses incurred by the "insured" at our request, including actual loss of earnings up to $350 a day because of time off from work. 14. FELLOW EMPLOYEE COVERAGE FOR DESIGNATED POSITIONS The Fellow Employee Exclusion contained in Section II.B.5. does not apply to the following positions or job titles: foreman, supervisor, manager, officer, partner or other senior level "employee". Coverage is excess over all other collectible insurance. 15. PHYSICAL DAMAGE - TRANSPORTATION EXPENSES SECTION III.A.4.a. Transportation Expenses is replaced by the following: a. Transportation Expenses We will pay up to $50 per day to a maximum of $1,500 for temporary transportation expense incurred by you because of the total theft of a covered "auto". We will pay only for those covered "autos" for which you carry either Comprehensive or Specified Cause of Loss Coverage. We will pay for temporary transportation expenses incurred during the period beginning 48 hours after the theft and ending, regardless of the policy's expirations, when the covered "auto" is returned to use or we pay for its "loss". For autos provided with temporary transportation expense, the following physical damage coverage will apply: (1) The most we will pay for any one "accident" or "loss" under the temporary transportation expense physical damage coverage is the lessor of: (a) The any one "Accident" or "Loss" amount of $100,000; (b) The actual cash value; or DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 AP-0401 (10/17) -5- (c) Cost of repair. Our obligation to pay for a loss in a.(1) above will be reduced by a deductible. The deductible will be equal to the largest deductible applicable to any owned "auto" for that coverage. The deductible will be waived for "loss" caused by fire or lightning. (2) Subject to paragraph a.(1). above, we will provide coverage equal to the broadest physical damage coverage applicable to any covered "auto" shown in the declarations. (3) When you are required by written contract to indemnify a lessor for actual financial loss because of loss of use of a hired "auto" resulting from a covered "accident" or "loss", we will cover that financial loss subject to the limit specified in paragraph a.(1). 16. RENTAL REIMBURSEMENT COVERAGE SECTION III.A.4. - Coverage Extensions - Paragraph d. is added. d. If you carry Comprehensive, Specified Causes of Loss or Collision coverage for the damaged covered "auto" as provided under this policy, then Rental Reimbursement Coverage is provided for that coverage part subject to the following: 1. We will pay for rental reimbursement expenses incurred by you for the rental of an "auto" because of "loss" other than theft, to a covered "auto". Payment applies in addition to the otherwise applicable amount of each coverage you have on a covered "auto". No deductibles apply to this coverage. 2. We will only pay for those expenses incurred during the policy period beginning 24 hours after the "loss" and ending, regardless of the policy's expiration, with the lesser of the following number of days: (a) The number of days reasonably required to repair or replace the covered "auto"; or, (b) 30 days. (c) Our payment is limited to the lesser of the following amounts: (1) Necessary and actual expenses incurred; or (2) $50 per day. 17. LOAN/LEASE GAP COVERAGE Physical Damage Coverage is amended by the addition of the following: In the event of a total "loss" to a covered "auto", we will pay your additional legal obligation for any difference between the actual cash value of the "auto" at the time of the loss and the "outstanding balance" of the loan/lease, not to exceed $2,500 for any one vehicle or $25,000 annually in aggregate. For the purposes of this endorsement, "outstanding balance" means the amount you owe on the loan/lease at the time of loss less any amounts representing taxes, overdue payments, penalties, interest or charges resulting from overdue payments, additional mileage charges, excess wear and tear charges or lease termination fees, costs for extended warranties, credit Life Insurance; Health, Accident or Disability Insurance purchased with the loan or lease; and carry-over balances from previous loans or leases. 18. ACCIDENTAL AIR BAG DISCHARGE COVERAGE SECTION III.B.3.a - Exclusions. This exclusion does not apply to the accidental discharge of an air bag. DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 AP-0401 (10/17) -6- 19. GLASS REPAIR - WAIVER OF DEDUCTIBLE SECTION III.D - Deductible is replaced with the following: For each covered "auto", our obligation to pay for, repair, return or replace damaged or stolen property will be reduced by the applicable deductible shown in the Declarations. Any Comprehensive Coverage deductible shown in the Declarations does not apply to "loss" caused by fire or lightning. The deductible does not apply to glass damage if the glass is repaired rather than replaced. DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 THIS ENDORSEMENT CHANGES THE POLICY. PLEASE READ IT CAREFULLY. TRANSPORTATION CONTRACTORS EXTENDED LIABILITY COVERAGE This endorsement modifies insurance provided under the following: COMMERCIAL GENERAL LIABILITY COVERAGE FORM It is agreed that the provisions listed below apply only upon the entry of an X in the box next to the caption of such provision. A. Partnership and Joint Venture Extension B. Contractors Automatic Additional Insured Coverage – Ongoing Operations C. Automatic Waiver of Subrogation D. Extended Notice of Cancellation, Nonrenewal E. Unintentional Failure to Disclose Hazards F. Broadened Mobile Equipment G. Personal and Advertising Injury - Contractual Coverage H. Nonemployment Discrimination I. Liquor Liability J. Broadened Conditions K. Automatic Additional Insureds – Equipment Leases L. Suits Against Dredges and Barges M. Insured Contract Extension - Railroad Property and Construction Contracts N. Construction Project General Aggregate Limits O. Fellow Employee Coverage P. Property Damage Liability - Elevators Q. Property Damage to the Named Insured's Work R Care, Custody or Control S Electronic Data Liability Coverage T. Consolidated Insurance Program Residual Liability Coverage U. Automatic Additional Insureds – Managers or Lessors of Premises V. Automatic Additional Insureds – State or Governmental Agency or Political Subdivisions – Permits or Authorizations W Contractors Automatic Additional Insured Coverage – Completed Operations X. Additional Insured – Engineers, Architects or Surveyors A. PARTNERSHIP AND JOINT VENTURE EXTENSION The following provision is added to SECTION II - WHO IS AN INSURED: The last full paragraph which reads as follows: No person or organization is an insured with respect to the conduct of any current or past partnership, joint venture or limited liability company that is not shown as a Named Insured in the Declarations. is deleted and replaced with the following: GL-3086 (09/11) -1- x x x x x x x x x x x x x x x x x x x x x x x x DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 With respect to the conduct of any past or present joint venture or partnership not shown as a Named Insured in the Declarations and of which you are or were a partner or member, you are an insured, but only with respect to liability arising out of "your work" on behalf of any partnership or joint venture not shown as a Named Insured in the Declarations, provided no other similar liability insurance is available to you for "your work" in connection with your interest in such partnership or joint venture. B. CONTRACTORS AUTOMATIC ADDITIONAL INSURED COVERAGE – ONGOING OPERATIONS SECTION II – WHO IS AN INSURED is amended to include as an additional insured any person or organization who is required by written contract to be an additional insured on your policy, but only with respect to liability for "bodily injury", "property damage" or "personal and advertising injury" caused, in whole or in part, by: 1. Your acts or omissions; or 2. The acts or omissions of those acting on your behalf; in the performance of your ongoing operations for the additional insured(s) at the project(s) designated in the written contract. With respect to the insurance afforded to these additional insureds, the following additional exclusions apply: This insurance does not apply to "bodily injury" or "property damage" occurring after: 1. All work, including materials, parts or equipment furnished in connection with such work, on the project (other than service, maintenance or repairs) to be performed by or on behalf of the additional insured(s) at the location of the covered operations has been completed; or 2. That portion of "your work" out of which the injury or damage arises has been put to its intended use by any person or organization other than another contractor or subcontractor engaged in performing operations for a principal as a part of the same project. This insurance is excess of all other insurance available to the additional insured, whether primary, excess, contingent or on any other basis, unless the written contract requires this insurance to be primary. In that event, this insurance will be primary relative to insurance policy(s) which designate the additional insured as a Named Insured in the Declarations and we will not require contribution from such insurance if the written contract also requires that this insurance be non-contributory. But with respect to all other insurance under which the additional insured qualifies as an insured or additional insured, this insurance will be excess. C. AUTOMATIC WAIVER OF SUBROGATION Item 8. of SECTION IV - COMMERCIAL GENERAL LIABILITY CONDITIONS, is deleted and replaced with the following: 8. Transfer of Rights of Recovery Against Others to Us and Automatic Waiver of Subrogation. a. If the insured has rights to recover all or part of any payment we have made under this Coverage Form, those rights are transferred to us. The insured must do nothing after loss to impair those rights. At our request, the insured will bring "suit" or transfer those rights to us and help us enforce them. b. If required by a written contract executed prior to loss, we waive any right of recovery we may have against any person or organization because of payments we make for injury or damage arising out of "your work" for that person or organization. GL-3086 (09/11) -2- DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 D. EXTENDED NOTICE OF CANCELLATION, NONRENEWAL Item A.2.b. of the COMMON POLICY CONDITIONS, is deleted and replaced with the following: A.2.b. 60 days before the effective date of the cancellation if we cancel for any other reason. Item 9. of SECTION IV - COMMERCIAL GENERAL LIABILITY CONDITIONS, is deleted and replaced with the following: 9. WHEN WE DO NOT RENEW a. If we choose to nonrenew this policy, we will mail or deliver to the first Named Insured shown in the Declarations written notice of the nonrenewal not less than 60 days before the expiration date. b. If we do not give notice of our intent to nonrenew as prescribed in a. above, it is agreed that you may extend the period of this policy for a maximum additional sixty (60) days from its scheduled expiration date. Where not otherwise prohibited by law, the existing terms, conditions and rates will remain in effect during that extension period. It is further agreed that so long as it is not otherwise prohibited by law, this one time sixty day extension is the sole remedy and liquidated damages available to the insured as a result of our failure to give the notice as prescribed in 9. a. above. E. UNINTENTIONAL FAILURE TO DISCLOSE HAZARDS Although we relied on your representations as to existing and past hazards, if unintentionally you should fail to disclose all such hazards at the inception date of your policy, we will not deny coverage under this Coverage Form because of such failure. F. BROADENED MOBILE EQUIPMENT Item 12.b. of SECTION V - DEFINITIONS, is deleted and replaced with the following: 12.b. Vehicles maintained for use solely on or next to premises, sites or locations you own, rent or occupy. G. PERSONAL AND ADVERTISING INJURY - CONTRACTUAL COVERAGE Exclusion 2.e. of SECTION I, COVERAGE B is deleted. H. NONEMPLOYMENT DISCRIMINATION Unless "personal and advertising injury" is excluded from this policy: Item 14. of SECTION V - DEFINITIONS, is amended to include: "Personal and advertising injury" also means embarrassment or humiliation, mental or emotional distress, physical illness, physical impairment, loss of earning capacity or monetary loss, which is caused by "discrimination." SECTION V - DEFINITIONS, is amended to include: "Discrimination" means the unlawful treatment of individuals based on race, color, ethnic origin, age, gender or religion. GL-3086 (09/11) -3- DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 Item 2. Exclusions of SECTION I, COVERAGE B, is amended to include: "Personal and advertising injury" arising out of "discrimination" directly or indirectly related to the past employment, employment or prospective employment of any person or class of persons by any insured; "Personal and advertising injury" arising out of "discrimination" by or at your, your agents or your "employees" direction or with your, your agents or your "employees" knowledge or consent; "Personal and advertising injury" arising out of "discrimination" directly or indirectly related to the sale, rental, lease or sub-lease or prospective sale, rental, lease or sub-lease of any dwelling, permanent lodging or premises by or at the direction of any insured. Fines, penalties, specific performance or injunctions levied or imposed by a governmental entity, or governmental code, law, or statute because of "discrimination." I. LIQUOR LIABILITY Exclusion 2.c. of SECTION I, COVERAGE A, is deleted. J. BROADENED CONDITIONS Items 2.a. and 2.b. of SECTION IV - COMMERCIAL GENERAL LIABILITY CONDITIONS, are deleted and replaced with the following: 2. Duties In The Event Of Occurrence, Offense, Claim Or Suit: a. You must see to it that we are notified of an "occurrence" or an offense which may result in a claim as soon as practicable after the "occurrence" has been reported to you, one of your officers or an "employee" designated to give notice to us. Notice should include: (1) How, when and where the "occurrence" or offense took place; (2) The names and addresses of any injured persons and witnesses; and (3) The nature and location of any injury or damage arising out of the "occurrence" or offense. b. If a claim is made or "suit" is brought against any insured, you must: (1) Record the specifics of the claim or "suit" and the date received as soon as you, one of your officers, or an "employee" designated to record such information is notified of it; and (2) Notify us in writing as soon as practicable after you, one of your officers, your legal department or an "employee" you designate to give us such notice learns of the claims or "suit." Item 2.e. is added to SECTION IV - COMMERCIAL GENERAL LIABILITY CONDITIONS: 2.e. If you report an "occurrence" to your workers compensation insurer which develops into a liability claim for which coverage is provided by the Coverage Form, failure to report such "occurrence" to us at the time of "occurrence" shall not be deemed in violation of paragraphs 2.a., 2.b., and 2.c. However, you shall give written notice of this "occurrence" to us as soon as you are made aware of the fact that this "occurrence" may be a liability claim rather than a workers compensation claim. GL-3086 (09/11) -4- DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 K. AUTOMATIC ADDITIONAL INSUREDS - EQUIPMENT LEASES SECTION II - WHO IS AN INSURED is amended to include any person or organization with whom you agree in a written equipment lease or rental agreement to name as an additional insured with respect to liability for "bodily injury", "property damage" or "personal and advertising injury" caused, at least in part, by your maintenance, operation, or use by you of the equipment leased to you by such person or organization, subject to the following additional exclusions. The insurance provided to the additional insured does not apply to: 1. "Bodily injury" or "property damage" occurring after you cease leasing the equipment. 2. "Bodily injury" or "property damage" arising out of the sole negligence of the additional insured. 3. "Property damage" to: a. Property owned, used or occupied by or rented to the additional insured; or b. Property in the care, custody or control of the additional insured or over which the additional insured is for any purpose exercising physical control. This insurance is excess of all other insurance available to the additional insured, whether primary, excess, contingent or on any other basis, unless the written contract requires this insurance to be primary. In that event, this insurance will be primary relative to insurance policy(s) which designate the additional insured as a Named Insured in the Declarations and we will not require contribution from such insurance if the written contract also requires that this insurance be non-contributory. But with respect to all other insurance under which the additional insured qualifies as an insured or additional insured, this insurance will be excess. L. SUITS AGAINST DREDGES AND BARGES We agree that any "suit" in rem against any dredge or barge owned, operated by or for you, and used in your operations, shall in all respects be treated in the same manner as though the "suit" were against you. This coverage is excess over and above any specific insurance on any dredge or barge owned, operated by or for you, and used in your operations. M. INSURED CONTRACT EXTENSION - RAILROAD PROPERTY AND CONSTRUCTION CONTRACTS Item 9. of SECTION V - DEFINITIONS, is deleted and replaced with the following. 9. "Insured Contract" means: a. A contract for a lease of premises. However, that portion of the contract for a lease of premises that indemnifies any person or organization for damage by fire to premises while rented to you or temporarily occupied by you with permission of the owner is not an "insured contract"; b. A sidetrack agreement; c. Any easement or license agreement; d. An obligation, as required by ordinance, to indemnify a municipality, except in connection with work for a municipality; e. An elevator maintenance agreement; GL-3086 (09/11) -5- DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 f. That part of any other contract or agreement pertaining to your business (including an indemnification of a municipality in connection with work performed for a municipality) under which you assume the tort liability of another party to pay for "bodily injury" or "property damage" to a third person or organization. Tort liability means a liability that would be imposed by law in the absence of any contract or agreement. Paragraph f. does not include that part of any contract or agreement: (1) That indemnifies an architect, engineer or surveyor for injury or damage arising out of: (a) Preparing, approving, or failing to prepare or approve, maps, shop drawings, opinions, reports, surveys, field orders, change orders or drawings and specifications; or (b) Giving directions or instructions, or failing to give them, if that is the primary cause of the injury or damage; or (2) Under which the insured, if an architect, engineer or surveyor, assumes liability for an injury or damage arising out of the insured's rendering or failure to render professional services, including those listed in (1) above and supervisory, inspection, architectural or engineering activities. N. CONSTRUCTION PROJECT GENERAL AGGREGATE LIMITS This modifies SECTION III - LIMITS OF INSURANCE. A. For all sums which can be attributed only to ongoing operations at a single construction project for which the insured becomes legally obligated to pay as damages caused by an "occurrence" under SECTION I - COVERAGE A, and for all medical expenses caused by accidents under SECTION I - COVERAGE C: 1. A separate Construction Project General Aggregate Limit applies to each construction project, and that limit is equal to the amount of the General Aggregate Limit shown in the Declarations. 2. The Construction Project General Aggregate Limit is the most we will pay for the sum of all damages under COVERAGE A, except damages because of "bodily injury" or "property damage" included in the "products-completed operations hazard," and for medical expenses under COVERAGE C regardless of the number of: a. Insureds; b. Claims made or "suits" brought; or c. Persons or organizations making claims or bringing "suits." 3. Any payments made under COVERAGE A for damages or under COVERAGE C for medical expenses shall reduce the Construction Project General Aggregate Limit for that construction project Such payments shall not reduce the General Aggregate Limit shown in the Declarations nor shall they reduce any other Construction Project General Aggregate Limit for any other construction project. 4. The limits shown in the Declarations for Each Occurrence, Fire Damage and Medical Expense continue to apply. However, instead of being subject to the General Aggregate Limit shown in the Declarations, such limits will be subject to the applicable Construction Project General Aggregate Limit. GL-3086 (09/11) -6- DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 B. For all sums which cannot be attributed only to ongoing operations at a single construction project for which the insured becomes legally obligated to pay as damages caused by an "occurrence" under SECTION I - COVERAGE A, and for all medical expenses caused by accidents under SECTION I - COVERAGE C: 1. Any payments made under COVERAGE A for damages or under COVERAGE C for medical expenses shall reduce the amount available under the General Aggregate Limit or the Products-Completed Operations Aggregate Limit, whichever is applicable; and 2. Such payments shall not reduce any Construction Project General Aggregate Limit. C. Payments for damages because of "bodily injury" or "property damage" included in the "products-completed operations hazard" will reduce the Products-Completed Operations Aggregate Limit, and not reduce the General Aggregate Limit nor the Construction Project General Aggregate Limit. D. If a construction project has been abandoned, delayed, or abandoned and then restarted, or if the authorized contracting parties deviate from plans, blueprints, designs, specifications or timetables, the project will still be deemed to be the same construction project. E. The provisions of SECTION III - LIMITS OF INSURANCE not otherwise modified by this endorsement shall continue to be applicable. O. FELLOW EMPLOYEE COVERAGE Exclusion 2.e. Employers Liability of SECTION I, COVERAGE A, is deleted and replaced with the following: 2.e. "Bodily injury" to (1) An "employee" of the insured arising out of and in the course of: (a) Employment by the insured; or (b) Performing duties related to the conduct of the insured's business; or (2) The spouse, child, parent, brother or sister of that "employee" as a consequence of paragraph (1) above. This exclusion applies: (1) Whether the insured may be liable as an employer or in any other capacity; and (2) To any obligation to share damages with or repay someone else who must pay damages because of the injury. This exclusion does not apply to: (1) Liability assumed by the insured under an "insured contract"; or (2) Liability arising from any action or omission of a co-"employee" while that co-"employee" is either in the course of his or her employment or performing duties related to the conduct of your business. GL-3086 (09/11) -7- DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 Item 2.a. (1)(a) of SECTION II - WHO IS AN INSURED, is deleted and replaced with the following: 2.a. (1)(a) To you, to your partners or members (if you are a partnership or joint venture) or to your members (if you are a limited liability company), or to your "volunteer workers" while performing duties related to the conduct of your business. P. PROPERTY DAMAGE LIABILITY - ELEVATORS "Property damage" liability is changed as follows: 1. Exclusions 2.j.(3) and 2.j.(4) of SECTION I, COVERAGE A, do not apply to the use of elevators. 2. The insurance afforded by reason of this provision is excess over any valid and collectible property insurance (including any deductible portion thereof) available to the insured whether primary, excess, contingent or on any other basis, and the OTHER INSURANCE condition is changed accordingly. Q. PROPERTY DAMAGE TO THE NAMED INSURED'S WORK Exclusion l of SECTION I, COVERAGE A. is deleted and replaced with the following: l. Damage to Your Work "Property damage" to "your work" arising out of it or any part of it and included in the "products completed operation hazard." This exclusion applies only to that portion of any loss in excess of $50,000 per occurrence if the damaged work and the work out of which the damage arises was performed by you. This exclusion does not apply if the damaged work or the work out of which the damage arises was performed on your behalf by a subcontractor. R. CARE, CUSTODY OR CONTROL Exclusion 2.j.4 of SECTION I, COVERAGE A. is deleted and replaced with the following: 2.j.4 Personal property in the care, custody or control of the insured. However, for personal property in the care, custody or control of you or your "employees," this exclusion applies only to that portion of any loss in excess of $25,000 per occurrence, subject to the following terms and conditions; (a) The most that we will pay under this provision as an annual aggregate is $100,000, regardless of the number of occurrences. (b) This provision does not apply to "employee" owned property or any property that is missing where there is not physical evidence to show what happened to the property. (c) The aggregate limit for this coverage provision is part of the General Aggregate Limit and SECTION III - LIMITS OF INSURANCE is changed accordingly. (d) In the event of damage to or destruction of property covered by this exception, you shall, if requested by us, replace the property or furnish the labor and materials necessary for repairs thereto, at actual cost to you, exclusive of prospective profit or overhead charges of any nature. GL-3086 (09/11) -8- DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 (e) $2,500 shall be deducted from the total amount of all sums you became obligated to pay as damages on account of damage to or destruction of all property of each person or organization, including the loss of use of that property, as a result of each "occurrence." Our limit of liability under the endorsement as being applicable to each "occurrence" shall be reduced by the amount of the deductible indicated above; however, our aggregate limit of liability under this provision shall not be reduced by the amount of such deductible. The conditions of the policy, including those with respect to duties in the event of "occurrence," claims or "suit" apply irrespective of the application of the deductible amount. We may pay any part or all of the deductible amount to effect settlement of any claim or "suit" and, upon notification of the action taken, you shall promptly reimburse us for such part of the deductible amount as has been paid by us. S. ELECTRONIC DATA LIABILITY COVERAGE 1. Exclusion 2.p. Electronic Data of SECTION I, COVERAGE A, is deleted and replaced with the following: 2.p. Damages arising out of the loss of, loss of use of, damage to, corruption of, inability to access, or inability to manipulate “electronic data” that does not result from physical injury to tangible property. 2. The following definition is added to SECTION V – DEFINITIONS: “Electronic data” means information, facts or programs stored as or on, created or used on, or transmitted to or from computer software (including systems and applications software), hard or floppy disks, CD-ROMS, tapes, drives, cells, data processing devices or any other media which are used with electronically controlled equipment. 3. For the purposes of this coverage, the definition of “property damage” in SECTION V – DEFINITIONS is replaced by the following: “Property damage” means: a. Physical injury to tangible property, including all resulting loss of use of that property. All such loss of use shall be deemed to occur at the time of the physical injury that caused it; b. Loss of use of tangible property that is not physically injured. All such loss of use shall be deemed to occur at the time of the "occurrence" that caused it; or c. Loss of, loss of use of, damage to, corruption of, inability to access, or inability to properly manipulate "electronic data", resulting from physical injury to tangible property. All such loss of "electronic data" shall be deemed to occur at the time of the "occurrence" that caused it. For the purposes of this insurance, "electronic data" is not tangible property. T. CONSOLIDATED INSURANCE PROGRAM RESIDUAL LIABILITY COVERAGE With respect to “bodily injury”, “property damage”, or ‘personal and advertising injury” arising out of your ongoing operations; or operations included within the “products-completed operations hazard”, the policy to which this coverage is attached shall apply as excess insurance over coverage available to “you” under a Consolidated Insurance Program (such as an Owner Controlled Insurance Program or Contractors Controlled Insurance Program). Coverage afforded by this endorsement does not apply to any Consolidated Insurance Program involving a “residential project” or any deductible or insured retention, specified in the Consolidated Insurance Program. GL-3086 (09/11) -9- DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 The following is added to Section V – Definitions “Residential project” means any project where 30% or more of the total square foot area of the structures on the project is used or is intended to be used for human residency. This includes but is not limited to single or multifamily housing, apartments, condominiums, townhouses, co-operatives or planned unit developments and appurtenant structures (including pools, hot tubs, detached garages, guest houses or any similar structures). A “residential project” does not include military owned housing, college/university owned housing or dormitories, long term care facilities, hotels, motels, hospitals or prisons. All other terms, provisions, exclusions and limitations of this policy apply. U. AUTOMATIC ADDITIONAL INSUREDS - MANAGERS OR LESSORS OR PREMISES SECTION II – WHO IS AN INSURED is amended to include: Any person or organization with whom you agree in a written contract or written agreement to name as an additional insured but only with respect to liability arising out of the ownership, maintenance or use of that part of the premises, designated in the written contract or written agreement, that is leased to you and subject to the following additional exclusions: This insurance does not apply to: 1. Any “occurrence" which takes place after you cease to be a tenant in that premises. 2. Structural alterations, new construction or demolition operations performed by or on behalf of the additional insured listed in the written contract or written agreement. This insurance is excess of all other insurance available to the additional insured, whether primary, excess, contingent or on any other basis, unless the written contract requires this insurance to be primary. In that event, this insurance will be primary relative to insurance policy(s) which designate the additional insured as a Named Insured in the Declarations and we will not require contribution from such insurance if the written contract also requires that this insurance be non-contributory. But with respect to all other insurance under which the additional insured qualifies as an insured or additional insured, this insurance will be excess. V. AUTOMATIC ADDITIONAL INSUREDS – STATE OR GOVERNMENTAL AGENCY OR POLITICAL SUBDIVISIONS – PERMITS OR AUTHORIZATIONS SECTION II – WHO IS AN INSURED is amended to include any state or governmental agency or subdivision or political subdivision with whom you are required by written contract, ordinance, law or building code to name as an additional insured subject to the following provisions: This insurance applies only with respect to operations performed by you or on your behalf for which the state or governmental agency or subdivision or political subdivision has issued a permit or authorization. This insurance does not apply to: 1. “Bodily injury”, “property damage” or “personal and advertising injury” arising out of operations performed for the federal government, state or municipality; or 2. “Bodily injury” or “property damage” included within the “products-completed operations hazard”. This insurance is excess of all other insurance available to the additional insured, whether primary, excess, contingent or on any other basis, unless the written contract requires this insurance to be primary. In that event, this insurance will be primary relative to insurance policy(s) which designate the additional insured as a Named Insured in the Declarations and we will not require contribution GL-3086 (09/11) -10- DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 from such insurance if the written contract also requires that this insurance be non-contributory. But with respect to all other insurance under which the additional insured qualifies as an insured or additional insured, this insurance will be excess. W. CONTRACTORS AUTOMATIC ADDITIONAL INSURED COVERAGE – COMPLETED OPERATIONS SECTION II – WHO IS AN INSURED is amended to include as an additional insured any person or organization who is required by written contract to be an additional insured on your policy for completed operations, but only with respect to liability for "bodily injury" or "property damage" caused, in whole or in part, by "your work" at the project designated in the contract, performed for that additional insured and included in the "products-completed operations hazard". This insurance is excess of all other insurance available to the additional insured, whether primary, excess, contingent or on any other basis, unless the written contract requires this insurance to be primary. In that event, this insurance will be primary relative to insurance policy(s) which designate the additional insured as a Named Insured in the Declarations and we will not require contribution from such insurance if the written contract also requires that this insurance be non-contributory. But with respect to all other insurance under which the additional insured qualifies as an insured or additional insured, this insurance will be excess. X. ADDITIONAL INSURED – ENGINEERS, ARCHITECTS OR SURVEYORS SECTION II – WHO IS AN INSURED is amended to include as an additional insured any architect, engineer or surveyor who is required by written contract to be an additional insured on your policy, but only with respect to liability for "bodily injury", "property damage" or "personal and advertising injury" caused, in whole or in part, by: 1. Your acts or omissions; or 2. The acts or omissions of those acting on your behalf; in the performance of your ongoing operations performed by you or on your behalf. This includes such architect, engineer or surveyor, who may not be engaged by you, but is contractually required to be added as an additional insured to your policy. With respect to the insurance afforded to these additional insureds, the following additional exclusion applies: This insurance does not apply to "bodily injury", "property damage" or "personal and advertising injury" arising out of the rendering of or the failure to render any professional services, including: 1. The preparing, approving, or failing to prepare or approve maps, drawings, opinions, reports, surveys, change orders, designs or specifications; or 2. Supervisory, inspection or engineering services. This insurance is excess of all other insurance available to the additional insured, whether primary, excess, contingent or on any other basis, unless the written contract requires this insurance to be primary. In that event, this insurance will be primary relative to insurance policy(s) which designate the additional insured as a Named Insured in the Declarations and we will not require contribution from such insurance if the written contract also requires that this insurance be non-contributory. But with respect to all other insurance under which the additional insured qualifies as an insured or additional insured, this insurance will be excess. GL-3086 (09/11) -11- DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 GL-2784 (09/11) -1- THIS ENDORSEMENT CHANGES THE POLICY. PLEASE READ IT CAREFULLY. EXTENDED LIABILITY COVERAGE This endorsement modifies insurance provided under the following: COMMERCIAL GENERAL LIABILITY COVERAGE FORM It is agreed that the provisions listed below apply only upon the entry of an X in the box next to the caption of such provision. A. Broad Form Named Insured F. Chartered Aircraft B. Bodily Injury Extension G. Coverage Territory Broadened C. Employee As Insureds - Health Care Services H. Medical Payments - Increased Limits D. Non-Owned Watercraft Liability I. Expanded Expected or Intended Exception E. Liberalization J. Property Perils Legal Liability K. Broadened Supplementary Payments A. BROAD FORM NAMED INSURED SECTION II - WHO IS AN INSURED , Paragraph 3is deleted and replaced by the following: 3.Any organization you newly acquire or form, except for a partnership, joint venture or limited liability company, and over which you maintain majority ownership or interest (51%or more) or for which you have assumed theactive management, will qualify as aNamed Insured if there is no other similar insurance available to that organization. However: a.Coverage under this provision is afforded only until theend of thepolicy period or the12- month anniversary of the policy inception date, whichever is earlier; b. Coverage A does not apply to "bodily injury" or "property damage" that occurred before you acquired or formed the organization; c. Coverage B does not apply to "personal and advertising injury" arising out of an offense committed before you acquired or formed the organization. B. BODILY INJURY EXTENSION SECTION V - DEFINITIONS , Paragraph 3, is deleted and replaced by the following: 3."Bodily injury" means bodily injury, sickness or disease sustained by a person, including mental anguish or death resulting fromany of these, at any time. Mental anguish means any type of mental or emotional illness or disease. C. EMPLOYEES AS INSUREDS - HEALTH CARE SERVICES SECTION II - WHO IS AN INSURED , Item 2.a.(1)(d)is deleted. X X X X X X X X X X X DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 GL-2784 (09/11) -2- D. NON-OWNED WATERCRAFT LIABILITY SECTION I - COVERAGES, COVERAGE A, 2. EXCLUSIONS , Item g.(2)is replaced with: (2)A watercraft you do not own that is: (a)Less than 51 feet long; and (b)Not being used to carry persons or property for a charge. E. LIBERALIZATION SECTION IV - CONDITIONS , is amended to include: 10.Liberalization If we adopt a change in our forms or rules which would broaden the coverage of this policy without an additional premium charge, the broader coverage will apply. This extension is effective upon the approval of such broader coverage in your state of domicile. F. CHARTERED AIRCRAFT SECTION I - COVERAGES , Coverage A, Exclusions, Item 2.g.(6)is added: (6)An aircraft in which you have no ownership interest and that you have chartered with crew. G. COVERAGE TERRITORY BROADENED SECTION V - DEFINITIONS , Item 4.a.is replaced with: a.The United States of America (including its territories and possessions), Canada, Bermuda, the Bahamas, the Cayman Islands, British Virgin Islands and Puerto Rico. H. MEDICAL PAYMENTS - INCREASED LIMITS Unless COVERAGE C. - MEDICAL PAYMENTS is excluded from this policy: SECTION I - COVERAGES , Coverage C, Insuring Agreement , Item c.is added: c.The medical expense limit provided by this policy shall be the greater of: (1)$10,000; or (2)The amount shown in the declarations. I. EXPANDED EXPECTED or INTENDED EXCEPTION SECTION I - COVERAGES , 2. Exclusions Item a. is amended as follows: a. Expected or Intended Injury - "bodily injury" or "property damage" expected or intended from the standpoint of the insured. This exclusion does not apply to "bodily injury" or "property damage" resulting from the use of reasonable force to protect persons or property. DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 GL-2784 (09/11) -3- J. PROPERTY PERILS LEGAL LIABILITY A. SECTION I - COVERAGES, COVERAGE A,2. Exclusions, the last paragraph following exclusion q.is replaced with: Exclusion c.through n., do not apply to damage by fire, explosion, smoke, water damage, sprinkler leakage, or lightning to premises while rented to you or temporarily occupied by you with the permission of the owner. A separate limit of insurance applies to this coverage as described in SECTION III - LIMITS OF INSURANCE . B. SECTION III - LIMITS OF INSURANCE , Item 6.is replaced with: 6.Subject to 5.above, the Damage toPremises Rented toYou Limit is the most we will pay under Coverage A for damages because of "property damage" to any one premises while rented to you, or in the case of damages by fire, explosion, smoke, water damage, sprinkler leakage or lightning, while rentedtoyou or temporarily occupied by you with the permission of the owner, arising out of any one fire, explosion, smoke, water damage, sprinkler leakage or lightning incident. TheDamage toPremises Rented toYou Limit provided bythis policy shall bethegreater of: 1.$300,000 or 2.The amount shown in the declarations. C. SECTION IV - COMMERCIAL GENERAL LIABILITY CONDITIONS, Item 4.b.(1)(a)(ii)is replaced with: (ii)That is fire, explosion, smoke, water damage, sprinkler leakage or lightning insurance for premises while rented to you or temporarily occupied by you with the permission of the owner. D. SECTION V - DEFINITIONS , Item 9.a.is replaced with: a.A contract for a lease of premises. However, that portion of the contract for a lease of premises that indemnifies any person or organization for damage by fire, explosion, smoke, water damage, sprinkler leakage or lightning to premises while rented to you or temporarily occupied by you with the permission of the owner is not an "insured contract." K. BROADENED SUPPLEMENTARY PAYMENTS SECTION I - COVERAGES, SUPPLEMENTARY PAYMENTS -Coverages A and B, Item 1.b. and 1.d.are replaced with: 1.b.The cost of bail bonds required because of accidents or traffic law violations arising out of the use of any vehicle to which the Bodily Injury Liability Coverage applies. We do not have to furnish these bonds. 1.d.All reasonable expenses incurred by the insured at our request to assist us in the investigation or defense of the claim or "suit," including actual loss of earnings up to $500 a day because of time off from work. DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 City of Bremerton 233-1896-178 Downtown Bicycle Pedestrian Circulation Improvements I-64 June 2021 Contract Documents Insurance Questionnaire This Page Intentionally Left Blank DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 City of Bremerton 233-1896-178 Downtown Bicycle Pedestrian Circulation Improvements I-65 June 2021 Contract Documents Statement of Intent to Pay Prevailing Wages, Department of Labor and Industries STATEMENT OF INTENT TO PAY PREVAILING WAGES, DEPARTMENT OF LABOR AND INDUSTRIES DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 City of Bremerton 233-1896-178 Downtown Bicycle Pedestrian Circulation Improvements I-66 June 2021 Contract Documents Statement of Intent to Pay Prevailing Wages, Department of Labor and Industries This Page Intentionally Left Blank DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 City of Bremerton 233-1896-178 Downtown Bicycle Pedestrian Circulation Improvements I-67 June 2021 Contract Documents Certification of Compliance with Wage Payment Statutes CERTIFICATION OF COMPLIANCE WITH WAGE PAYMENT STATUTES The undersigned bidder hereby certifies that, within the three-year period immediately preceding the bid solicitation date for this Project, that the bidder is not a “willful” violator, as defined in RCW 49.48.082, of any provision of chapters 49.46, 49.48, or 49.52 RCW, as determined by a final and binding citation and notice of assessment issued by the Department of Labor and Industries or through a civil judgment entered by a court of limited or general jurisdiction. “I certify under penalty of perjury under the laws of the State of Washington that the foregoing is true and correct.” Signature: Date: Print Name and Title: Location or Place executed: (City, State) Check One: Individual ☐ Partnership ☐ Joint Venture ☐ Corporation ☐ State of Incorporation, or if not a corporation, State where business entity was formed: If a co-partnership, give firm name under which business is transacted: * If a corporation, proposal must be executed in the corporate name by the president or vice- president (or any other corporate officer accompanied by evidence of authority to sign). If a co-partnership, proposal must be executed by a partner. DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 City of Bremerton 233-1896-178 Downtown Bicycle Pedestrian Circulation Improvements I-68 June 2021 Contract Documents Certification of Compliance with Wage Payment Statutes This Page Intentionally Left Blank DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 PART II SPECIAL PROVISIONS DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 City of Bremerton 233-1896-178 Downtown Bicycle Pedestrian Circulation Improvements II-i May 2021 Contract Documents Introduction to the Special Provisions TABLE OF CONTENTS INTRODUCTION TO THE SPECIAL PROVISIONS .................................................................... 1 DIVISION 1 3 GENERAL REQUIREMENTS .................................................................................................. 3 DESCRIPTION OF WORK.......................................................................................................... 3 1-01 DEFINITIONS AND TERMS ................................................................................ 3 1-01.3 DEFINITIONS ...................................................................................................... 3 1-02 BID PROCEDURES AND CONDITIONS ............................................................. 5 1-02.1 QUALIFICATIONS OF BIDDER ........................................................................... 5 1-02.2 PLANS AND SPECIFICATIONS .......................................................................... 5 1-02.5 PROPOSAL FORMS ........................................................................................... 6 1-02.6 PREPARATION OF PROPOSAL ......................................................................... 6 1-02.7 BID DEPOSIT ...................................................................................................... 6 1-02.9 DELIVERY OF PROPOSAL ................................................................................. 7 1-02.13 IRREGULAR PROPOSALS ................................................................................. 7 1-02.14 DISQUALIFICATION OF BIDDERS ..................................................................... 8 1-02.15 PRE-AWARD INFORMATION ........................................................................... 11 1-03 AWARD AND EXECUTION OF CONTRACT ..................................................... 12 1-03.1 CONSIDERATION OF BIDS .............................................................................. 12 1-03.3 EXECUTION OF CONTRACT ........................................................................... 12 1-03.4 CONTRACT BOND ............................................................................................ 12 1-03.7 JUDICIAL REVIEW ............................................................................................ 13 1-04 SCOPE OF THE WORK .................................................................................... 14 1-04.2 COORDINATION OF CONTRACT DOCUMENTS, PLANS, SPECIAL PROVISIONS, SPECIFICATIONS, AND ADDENDA ......................................... 14 1-05 CONTROL OF WORK ....................................................................................... 14 1-05.4 CONFORMITY WITH AND DEVIATIONS FROM PLANS AND STAKES ........... 14 1-05.7 REMOVAL OF DEFECTIVE AND UNAUTHORIZED WORK ............................. 17 1-05.11 FINAL INSPECTIONS AND OPERATIONAL TESTING ..................................... 18 1-05.11(1) SUBSTANTIAL COMPLETION DATE ................................................................ 18 1-05.11(2) FINAL INSPECTION AND PHYSICAL COMPLETION DATE ............................ 19 1-05.11(3) OPERATIONAL TESTING ................................................................................. 19 1-05.13 SUPERINTENDENTS, LABOR, AND EQUIPMENT OF CONTRACTOR ........... 20 1-05.14 COOPERATION WITH OTHER CONTRACTORS ............................................. 20 1-05.15 METHOD OF SERVING NOTICES .................................................................... 20 1-05.16 WATER AND POWER (NEW SECTION) ........................................................... 20 1-07 LEGAL RELATIONS AND RESPONSIBILITIES TO THE PUBLIC ..................... 20 1-07.1 LAWS TO BE OBSERVED ................................................................................ 20 1-07.2 SALES TAX ....................................................................................................... 21 DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 City of Bremerton 233-1896-178 Downtown Bicycle Pedestrian Circulation Improvements II-ii May 2021 Contract Documents Introduction to the Special Provisions 1-07.2(1) STATE SALES TAX — RULE 171 ..................................................................... 22 1-07.2(2) STATE SALES TAX — RULE 170 ..................................................................... 22 1-07.2(3) SERVICES......................................................................................................... 22 1-07.4 SANITATION ..................................................................................................... 23 1-07.4(2) HEALTH HAZARDS ........................................................................................... 23 1-07.9 WAGES ............................................................................................................. 23 1-07.9(5) REQUIRED DOCUMENTS ................................................................................ 23 1-07.13 CONTRACTOR’S RESPONSIBILITY FOR WORK ............................................ 24 1-07.13(4) REPAIR OF DAMAGE ....................................................................................... 24 1-07.15 TEMPORARY WATER POLLUTION PREVENTION ......................................... 24 1-07.16 PROTECTION AND RESTORATION OF PROPERTY ...................................... 25 1-07.16(4) ARCHAEOLOGICAL AND HISTORICAL OBJECTS .......................................... 25 1-07.16(5) PAYMENT ......................................................................................................... 25 1-07.17 UTILITIES AND SIMILAR FACILITIES ............................................................... 25 1-07.17(3) PROTECTION AND SUPPORT OF EXISTING UTILITIES (NEW SECTION) .... 27 1-07.18 INSURANCE ...................................................................................................... 27 1-07.18(1) GENERAL REQUIREMENTS ............................................................................ 27 1-07.18(2) ADDITIONAL INSURED .................................................................................... 28 1-07.18(3) SUBCONTRACTORS ........................................................................................ 28 1-07.18(4) VERIFICATION OF COVERAGE ....................................................................... 29 1-07.18(5) COVERAGES AND LIMITS ............................................................................... 29 1-07.18(5)A COMMERCIAL GENERAL LIABILITY ................................................................ 30 1-07.18(5)B AUTOMOBILE LIABILITY .................................................................................. 30 1-07.18(5)C WORKERS’ COMPENSATION .......................................................................... 30 1-07.23 PUBLIC CONVENIENCE AND SAFETY ............................................................ 31 1-07.23(1) CONSTRUCTION UNDER TRAFFIC ................................................................. 31 1-08 PROSECUTION AND PROGRESS ................................................................... 33 1-08.0 PRELIMINARY MATTERS (NEW SECTION) .................................................... 33 1-08.0(1) PRECONSTRUCTION CONFERENCE (NEW SECTION) ................................. 33 1-08.0(2) HOURS OF WORK (NEW SECTION) ................................................................ 34 1-08.3 PROGRESS SCHEDULE .................................................................................. 35 1-08.3(2) PROGRESS SCHEDULE TYPES ...................................................................... 35 1-08.3(2)A TYPE A PROGRESS SCHEDULE ..................................................................... 35 1-08.4 NOTICE TO PROCEED AND PROSECUTION OF WORK ................................ 35 1-08.5 TIME FOR COMPLETION ................................................................................. 35 1-08.6 SUSPENSION OF WORK ................................................................................. 35 1-08.9 LIQUIDATED DAMAGES ................................................................................... 36 1-09 MEASUREMENT AND PAYMENT .................................................................... 37 1-09.6 FORCE ACCOUNT ............................................................................................ 37 1-09.9 PAYMENTS ....................................................................................................... 37 DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 City of Bremerton 233-1896-178 Downtown Bicycle Pedestrian Circulation Improvements II-iii May 2021 Contract Documents Introduction to the Special Provisions 1-09.9(1) VACANT ............................................................................................................ 38 1-09.11 DISPUTES AND CLAIMS .................................................................................. 38 1-09.11(3) TIME LIMITATION AND JURISDICTION ........................................................... 38 1-09.13 CLAIMS RESOLUTION ..................................................................................... 39 1-09.13(3) CLAIMS $250,000 OR LESS ............................................................................. 39 1-09.13(3)A ADMINISTRATION OF ARBITRATION .............................................................. 39 1-10 TEMPORARY TRAFFIC CONTROL .................................................................. 39 1-10.2 TRAFFIC CONTROL MANAGEMENT ............................................................... 39 1-10.2(1) GENERAL.......................................................................................................... 39 1-10.2(2) TRAFFIC CONTROL PLANS ............................................................................. 40 1-10.4 MEASUREMENT ............................................................................................... 40 1-10.4(1) LUMP SUM BID FOR PROJECT (NO UNIT ITEMS) ......................................... 40 DIVISION 2 41 EARTHWORK ....................................................................................................................... 41 2-02 REMOVAL OF STRUCTURES AND OBSTRUCTIONS ..................................... 41 2-02.1 DESCRIPTION .................................................................................................. 41 2-02.3 CONSTRUCTION REQUIREMENTS ................................................................. 41 2-02.3(3) REMOVAL OF PAVEMENT, SIDEWALKS, CURBS, AND GUTTERS ............... 41 2-02.4 VACANT ............................................................................................................ 42 2-02.4 MEASUREMENT ............................................................................................... 42 2-02.5 PAYMENT ......................................................................................................... 42 DIVISION 8 43 MISCELLANEOUS CONSTRUCTION ................................................................................... 43 8-02 ROADSIDE RESTORATION.............................................................................. 43 8-02.1 DESCRIPTION .................................................................................................. 43 8-02.4 MEASUREMENT ............................................................................................... 43 8-02.5 PAYMENT ......................................................................................................... 43 8-04 CURBS, GUTTERS, AND SPILLWAYS ............................................................. 43 8-04.3 CONSTRUCTION REQUIREMENTS ................................................................. 43 8-04.3(1) CEMENT CONCRETE CURBS, GUTTERS, AND SPILLWAYS ........................ 43 8-04.3(1)C PAINTED CURB (NEW SECTION) .................................................................... 43 8-04.4 MEASUREMENT ............................................................................................... 44 8-04.5 PAYMENT ......................................................................................................... 44 8-09 RAISED PAVEMENT MARKERS ...................................................................... 44 8-09.3 CONSTRUCTION REQUIREMENTS ................................................................. 44 8-09.3(2) SURFACE PREPARATION ............................................................................... 44 8-14 CEMENT CONCRETE SIDEWALKS ................................................................. 45 8-14.1 DESCRIPTION .................................................................................................. 45 8-14.3 CONSTRUCTION REQUIREMENTS ................................................................. 45 DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 City of Bremerton 233-1896-178 Downtown Bicycle Pedestrian Circulation Improvements II-iv May 2021 Contract Documents Introduction to the Special Provisions 8-14.3(6) CURB RAMPS (NEW SECTION) ...................................................................... 45 8-14.4 MEASUREMENT ............................................................................................... 46 8-14.5 PAYMENT ......................................................................................................... 46 8-20 ILLUMINATION, TRAFFIC SIGNAL SYSTEMS, INTELLIGENT TRANSPORTATION SYSTEMS, AND ELECTRICAL ........................................ 46 8-20.1 DESCRIPTION .................................................................................................. 46 8-20.1(1) REGULATIONS AND CODE ............................................................................. 47 8-20.2 MATERIALS ...................................................................................................... 48 8-20.2(1) EQUIPMENT LIST AND DRAWINGS ................................................................ 49 8-20.3 CONSTRUCTION REQUIREMENTS ................................................................. 50 8-20.3(1) GENERAL.......................................................................................................... 50 8-20.3(2) EXCAVATING AND BACKFILLING ................................................................... 50 8-20.3(4) FOUNDATIONS ................................................................................................. 51 8-20.3(5) CONDUIT .......................................................................................................... 51 8-20.3(6) JUNCTION BOXES, CABLE VAULTS, AND PULL BOXES ............................... 51 8-20.3(9) BONDING, GROUNDING .................................................................................. 52 8-20.3(11) TESTING ........................................................................................................... 52 8-20.3(14) SIGNAL SYSTEMS ............................................................................................ 52 8-20.4 MEASUREMENT ............................................................................................... 52 8-20.5 PAYMENT ......................................................................................................... 53 8-21 PERMANENT SIGNING .................................................................................... 53 8-21.1 DESCRIPTION .................................................................................................. 53 8-21.5 PAYMENT ......................................................................................................... 53 8-22 PAVEMENT MARKING...................................................................................... 53 8-22.2 MATERIALS ...................................................................................................... 53 8-22.3 CONSTRUCTION REQUIREMENTS ................................................................. 54 8-22.3(6) REMOVAL OF PAVEMENT MARKINGS ........................................................... 54 8-22.4 MEASUREMENT ............................................................................................... 54 8-22.5 PAYMENT ......................................................................................................... 55 DIVISION 9 57 MATERIALS .......................................................................................................................... 57 9-29 ILLUMINATION, SIGNAL, ELECTRICAL ........................................................... 57 9-29.5 VACANT ............................................................................................................ 57 9-29.5 RECTANGULAR RAPID FLASHING BEACON (RRFB) ..................................... 57 9-29.19 PEDESTRIAN PUSH BUTTONS ....................................................................... 58 STANDARD PLANS.................................................................................................................. 61 DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 City of Bremerton 233-1896-178 Downtown Bicycle Pedestrian Circulation Improvements II-1 May 2021 Contract Documents Introduction to the Special Provisions INTRODUCTION TO THE SPECIAL PROVISIONS (December 10, 2020 APWA GSP) The work on this project shall be accomplished in accordance with the Standard Specifications for Road, Bridge and Municipal Construction, 2021 edition, as issued by the Washington State Department of Transportation (WSDOT) and the American Public Works Association (APWA), Washington State Chapter (hereafter “Standard Specifications”). The Standard Specifications, as modified or supplemented by these Special Provisions, all of which are made a part of the Contract Documents, shall govern all of the Work. These Special Provisions are made up of both General Special Provisions (GSPs) from various sources, which may have project-specific fill-ins; and project-specific Special Provisions. Each Provision either supplements, modifies, or replaces the comparable Standard Specification, or is a new Provision. The deletion, amendment, alteration, or addition to any subsection or portion of the Standard Specifications is meant to pertain only to that particular portion of the section, and in no way should it be interpreted that the balance of the section does not apply. The project-specific Special Provisions are not labeled as such. The GSPs are labeled under the headers of each GSP, with the effective date of the GSP and its source. For example: (March 8, 2013 APWA GSP) (April 1, 2013 WSDOT GSP) Also incorporated into the Contract Documents by reference are: • Manual on Uniform Traffic Control Devices for Streets and Highways, currently adopted edition, with Washington State modifications, if any • Standard Plans for Road, Bridge and Municipal Construction, WSDOT/APWA, current edition • City of Bremerton Design and Construction Standards, Divisions 2-8. Contractor shall obtain copies of these publications, at Contractor’s own expense. DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 City of Bremerton 233-1896-178 Downtown Bicycle Pedestrian Circulation Improvements II-2 May 2021 Contract Documents Introduction to the Special Provisions This Page Intentionally Left Blank DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 City of Bremerton 233-1896-178 Downtown Bicycle Pedestrian Circulation Improvements II-3 May 2021 Contract Documents Division 1 DIVISION 1 GENERAL REQUIREMENTS DESCRIPTION OF WORK (March 13, 1995, WSDOT GSP) This Contract provides for the improvement of *** Washington Avenue, Pacific Avenue, Burwell Street, 1st Street, 2nd Street, and Austin Drive, and includes, but is not limited to, temporary traffic control, hydroblasting existing pavement markings, illumination, traffic signal systems, permanent signing, and pavement marking *** all in accordance with the Contract Plans, these Contract Provisions, and the Standard Specifications. 1-01 DEFINITIONS AND TERMS 1-01.3 Definitions (January 4, 2016 APWA GSP) Delete the heading Completion Dates and the three paragraphs that follow it, and replace them with the following: Dates Bid Opening Date The date on which the Contracting Agency publicly opens and reads the Bids. Award Date The date of the formal decision of the Contracting Agency to accept the lowest responsible and responsive Bidder for the Work. Contract Execution Date The date the Contracting Agency officially binds the Agency to the Contract. Notice to Proceed Date The date stated in the Notice to Proceed on which the Contract time begins. Substantial Completion Date The day the Engineer determines the Contracting Agency has full and unrestricted use and benefit of the facilities, both from the operational and safety standpoint, any remaining traffic disruptions will be rare and brief, and only minor incidental work, replacement of temporary substitute facilities, plant establishment periods, or correction or repair remains for the Physical Completion of the total Contract. Physical Completion Date The day all of the Work is physically completed on the project. All documentation required by the Contract and required by law does not necessarily need to be furnished by the Contractor by this date. DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 City of Bremerton 233-1896-178 Downtown Bicycle Pedestrian Circulation Improvements II-4 May 2021 Contract Documents Division 1 Completion Date The day all the Work specified in the Contract is completed and all the obligations of the Contractor under the contract are fulfilled by the Contractor. All documentation required by the Contract and required by law must be furnished by the Contractor before establishment of this date. Final Acceptance Date The date on which the Contracting Agency accepts the Work as complete. Supplement this Section with the following: All references in the Standard Specifications, Amendments, or WSDOT General Special Provisions, to the terms “Department of Transportation”, “Washington State Transportation Commission”, “Commission”, “Secretary of Transportation”, “Secretary”, “Headquarters”, and “State Treasurer” shall be revised to read “Contracting Agency”. All references to the terms “State” or “state” shall be revised to read “Contracting Agency” unless the reference is to an administrative agency of the State of Washington, a State statute or regulation, or the context reasonably indicates otherwise. All references to “State Materials Laboratory” shall be revised to read “Contracting Agency designated location”. All references to “final contract voucher certification” shall be interpreted to mean the Contracting Agency form(s) by which final payment is authorized, and final completion and acceptance granted. Additive A supplemental unit of work or group of bid items, identified separately in the Bid Proposal, which may, at the discretion of the Contracting Agency, be awarded in addition to the base bid. Alternate One of two or more units of work or groups of bid items, identified separately in the Bid Proposal, from which the Contracting Agency may make a choice between different methods or material of construction for performing the same work. Business Day A business day is any day from Monday through Friday except holidays as listed in Section 1-08.5. Contract Bond The definition in the Standard Specifications for “Contract Bond” applies to whatever bond form(s) are required by the Contract Documents, which may be a combination of a Payment Bond and a Performance Bond. Contract Documents See definition for “Contract”. DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 City of Bremerton 233-1896-178 Downtown Bicycle Pedestrian Circulation Improvements II-5 May 2021 Contract Documents Division 1 Contract Time The period of time established by the terms and conditions of the Contract within which the Work must be physically completed. Notice of Award The written notice from the Contracting Agency to the successful Bidder signifying the Contracting Agency’s acceptance of the Bid Proposal. Notice to Proceed The written notice from the Contracting Agency or Engineer to the Contractor authorizing and directing the Contractor to proceed with the Work and establishing the date on which the Contract time begins. Traffic Both vehicular and non-vehicular traffic, such as pedestrians, bicyclists, wheelchairs, and equestrian traffic. 1-02 BID PROCEDURES AND CONDITIONS 1-02.1 Prequalification of Bidders Delete Section 1-02.1 and replace it with the following: 1-02.1 Qualifications of Bidder (January 24, 2011 APWA GSP) Before award of a public works contract, a bidder must meet at least the minimum qualifications of RCW 39.04.350(1) to be considered a responsible bidder and qualified to be awarded a public works project. 1-02.2 Plans and Specifications Delete this section and replace it with the following: Information as to where Bid Documents can be obtained or reviewed will be found in the Call for Bids (Advertisement for Bids) for the work. After award of the contract, plans and specifications will be issued to the Contractor at no cost as detailed below: To Prime Contractor No. of Sets Basis of Distribution Color Copy Reduced plans (11 x 17) *** 4 *** Furnished automatically upon award. Contract Provisions *** 4 *** Furnished automatically upon award. Color Copy Large plans (e.g., 22 x 34) and Contract Provisions *** 2 *** Furnished only upon request. Additional plans and Contract Provisions may be obtained by the Contractor from the source stated in the Call for Bids, at the Contractor’s own expense. DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 City of Bremerton 233-1896-178 Downtown Bicycle Pedestrian Circulation Improvements II-6 May 2021 Contract Documents Division 1 1-02.5 Proposal Forms (July 31, 2017 APWA GSP) Delete this section and replace it with the following: The Proposal Form will identify the project and its location and describe the work. It will also list estimated quantities, units of measurement, the items of work, and the materials to be furnished at the unit bid prices. The bidder shall complete spaces on the proposal form that call for, but are not limited to, unit prices; extensions; summations; the total bid amount; signatures; date; and, where applicable, retail sales taxes and acknowledgment of addenda; the bidder’s name, address, telephone number, and signature; the bidder’s UDBE/DBE/ M/WBE commitment, if applicable; a State of Washington Contractor’s Registration Number; and a Business License Number, if applicable. Bids shall be completed by typing or shall be printed in ink by hand, preferably in black ink. The required certifications are included as part of the Proposal Form. The Contracting Agency reserves the right to arrange the proposal forms with alternates and additives, if such be to the advantage of the Contracting Agency. The bidder shall bid on all alternates and additives set forth in the Proposal Form unless otherwise specified. 1-02.6 Preparation of Proposal Supplement the second paragraph with the following: 4. If a minimum bid amount has been established for any item, the unit or lump sum price must equal or exceed the minimum amount stated. 5. Any correction to a bid made by interlineation, alteration, or erasure, shall be initialed by the signer of the bid. Delete the last two paragraphs, and replace them with the following: The Bidder shall submit with their Bid a completed Contractor Certification Wage Law Compliance form, provided by the Contracting Agency. Failure to return this certification as part of the Bid Proposal package will make this Bid Nonresponsive and ineligible for Award. A Contractor Certification of Wage Law Compliance form is included in the Proposal Forms. The Bidder shall make no stipulation on the Bid Form, nor qualify the bid in any manner. A bid by a corporation shall be executed in the corporate name, by the president or a vice president (or other corporate officer accompanied by evidence of authority to sign). 1-02.7 Bid Deposit (March 8, 2013 APWA GSP) Supplement this section with the following: Bid bonds shall contain the following: 1. Contracting Agency-assigned number for the project; 2. Name of the project; DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 City of Bremerton 233-1896-178 Downtown Bicycle Pedestrian Circulation Improvements II-7 May 2021 Contract Documents Division 1 3. The Contracting Agency named as obligee; 4. The amount of the bid bond stated either as a dollar figure or as a percentage which represents five percent of the maximum bid amount that could be awarded; 5. Signature of the bidder’s officer empowered to sign official statements. The signature of the person authorized to submit the bid should agree with the signature on the bond, and the title of the person must accompany the said signature; 6. The signature of the surety’s officer empowered to sign the bond and the power of attorney. If so stated in the Contract Provisions, bidder must use the bond form included in the Contract Provisions. If so stated in the Contract Provisions, cash will not be accepted for a bid deposit. 1-02.9 Delivery of Proposal Delete this section and replace it with the following: Each Proposal shall be submitted in a sealed envelope, with the Project Name and Project Number as stated in the Call for Bids clearly marked on the outside of the envelope, or as otherwise required in the Bid Documents, to ensure proper handling and delivery. Proposals that are received as required will be publicly opened and read as specified in Section 1-02.12. The Contracting Agency will not open or consider any Bid Proposal that is received after the time specified in the Call for Bids for receipt of Bid Proposals, or received in a location other than that specified in the Call for Bids. The Contracting Agency will not open or consider any “Supplemental Information” (UDBE confirmations, or GFE documentation) that is received after the time specified above, or received in a location other than that specified in the Call for Bids. If an emergency or unanticipated event interrupts normal work processes of the Contracting Agency so that Proposals cannot be received at the office designated for receipt of bids as specified in Section 1-02.12 the time specified for receipt of the Proposal will be deemed to be extended to the same time of day specified in the solicitation on the first work day on which the normal work processes of the Contracting Agency resume. 1-02.13 Irregular Proposals Delete this section and replace it with the following: 1. A Proposal will be considered irregular and will be rejected if: a. The Bidder is not prequalified when so required; b. The authorized Proposal form furnished by the Contracting Agency is not used or is altered; c. The completed Proposal form contains any unauthorized additions, deletions, alternate Bids, or conditions; DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 City of Bremerton 233-1896-178 Downtown Bicycle Pedestrian Circulation Improvements II-8 May 2021 Contract Documents Division 1 d. The Bidder adds provisions reserving the right to reject or accept the award, or enter into the Contract; e. A price per unit cannot be determined from the Bid Proposal; f. The Proposal form is not properly executed; g. The Bidder fails to submit or properly complete a Subcontractor list, if applicable, as required in Section 1-02.6; h. The Bid Proposal does not constitute a definite and unqualified offer to meet the material terms of the Bid invitation; or i. More than one Proposal is submitted for the same project from a Bidder under the same or different names. 2. A Proposal may be considered irregular and may be rejected if: a. The Proposal does not include a unit price for every Bid item; b. Any of the unit prices are excessively unbalanced (either above or below the amount of a reasonable Bid) to the potential detriment of the Contracting Agency; c. Receipt of Addenda is not acknowledged; d. A member of a joint venture or partnership and the joint venture or partnership submit Proposals for the same project (in such an instance, both Bids may be rejected); or e. If Proposal form entries are not made in ink. 1-02.14 Disqualification of Bidders (May 17, 2018 APWA GSP, Option B) Delete this section and replace it with the following: A Bidder will be deemed not responsible if the Bidder does not meet the mandatory bidder responsibility criteria in RCW 39.04.350(1), as amended; or does not meet Supplemental Criteria 1-7 listed in this Section. The Contracting Agency will verify that the Bidder meets the mandatory bidder responsibility criteria in RCW 39.04.350(1), and Supplemental Criteria 1-2. Evidence that the Bidder meets Supplemental Criteria 3-7 shall be provided by the Bidder as stated later in this Section. 1. Delinquent State Taxes A. Criterion: The Bidder shall not owe delinquent taxes to the Washington State Department of Revenue without a payment plan approved by the Department of Revenue. B. Documentation: The Bidder, if and when required as detailed below, shall sign a statement (on a form to be provided by the Contracting Agency) that the Bidder does not owe delinquent taxes to the Washington State Department of Revenue, or if delinquent taxes are owed to the Washington State Department of Revenue, the Bidder must submit a written payment plan approved by the Department of Revenue, to the Contracting Agency by the deadline listed below. DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 City of Bremerton 233-1896-178 Downtown Bicycle Pedestrian Circulation Improvements II-9 May 2021 Contract Documents Division 1 2. Federal Debarment A. Criterion: The Bidder shall not currently be debarred or suspended by the Federal government. B. Documentation: The Bidder shall not be listed as having an “active exclusion” on the U.S. government’s “System for Award Management” database (www.sam.gov). 3. Subcontractor Responsibility A. Criterion: The Bidder’s standard subcontract form shall include the subcontractor responsibility language required by RCW 39.06.020, and the Bidder shall have an established procedure which it utilizes to validate the responsibility of each of its subcontractors. The Bidder’s subcontract form shall also include a requirement that each of its subcontractors shall have and document a similar procedure to determine whether the sub-tier subcontractors with whom it contracts are also “responsible” subcontractors as defined by RCW 39.06.020. B. Documentation: The Bidder, if and when required as detailed below, shall submit a copy of its standard subcontract form for review by the Contracting Agency, and a written description of its procedure for validating the responsibility of subcontractors with which it contracts. 4. Claims Against Retainage and Bonds A. Criterion: The Bidder shall not have a record of excessive claims filed against the retainage or payment bonds for public works projects in the three years prior to the bid submittal date, that demonstrate a lack of effective management by the Bidder of making timely and appropriate payments to its subcontractors, suppliers, and workers, unless there are extenuating circumstances and such circumstances are deemed acceptable to the Contracting Agency. B. Documentation: The Bidder, if and when required as detailed below, shall submit a list of the public works projects completed in the three years prior to the bid submittal date that have had claims against retainage and bonds and include for each project the following information: • Name of project; • The owner and contact information for the owner; • A list of claims filed against the retainage and/or payment bond for any of the projects listed; • A written explanation of the circumstances surrounding each claim and the ultimate resolution of the claim. 5. Public Bidding Crime A. Criterion: The Bidder and/or its owners shall not have been convicted of a crime involving bidding on a public works contract in the five years prior to the bid submittal date. B. Documentation: The Bidder, if and when required as detailed below, shall sign a statement (on a form to be provided by the Contracting Agency) that the Bidder and/or its owners have not been convicted of a crime involving bidding on a public works contract. DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 City of Bremerton 233-1896-178 Downtown Bicycle Pedestrian Circulation Improvements II-10 May 2021 Contract Documents Division 1 6. Termination for Cause/Termination for Default A. Criterion: The Bidder shall not have had any public works contract terminated for cause or terminated for default by a government agency in the five years prior to the bid submittal date, unless there are extenuating circumstances and such circumstances are deemed acceptable to the Contracting Agency. B. Documentation: The Bidder, if and when required as detailed below, shall sign a statement (on a form to be provided by the Contracting Agency) that the Bidder has not had any public works contract terminated for cause or terminated for default by a government agency in the five years prior to the bid submittal date; or if Bidder was terminated, describe the circumstances. 7. Lawsuits A. Criterion: The Bidder shall not have lawsuits with judgments entered against the Bidder in the five years prior to the bid submittal date that demonstrate a pattern of failing to meet the terms of contracts, unless there are extenuating circumstances and such circumstances are deemed acceptable to the Contracting Agency. B. Documentation: The Bidder, if and when required as detailed below, shall sign a statement (on a form to be provided by the Contracting Agency) that the Bidder has not had any lawsuits with judgments entered against the Bidder in the five years prior to the bid submittal date that demonstrate a pattern of failing to meet the terms of contracts, or shall submit a list of all lawsuits with judgments entered against the Bidder in the five years prior to the bid submittal date, along with a written explanation of the circumstances surrounding each such lawsuit. The Contracting Agency shall evaluate these explanations to determine whether the lawsuits demonstrate a pattern of failing to meet of terms of construction related contracts. As evidence that the Bidder meets the Supplemental Criteria stated above, the apparent low Bidder must submit to the Contracting Agency by 12:00 P.M. (noon) of the second business day following the bid submittal deadline, a written statement verifying that the Bidder meets the supplemental criteria together with supporting documentation (sufficient in the sole judgment of the Contracting Agency) demonstrating compliance with the Supplemental Criteria. The Contracting Agency reserves the right to request further documentation as needed from the low Bidder and documentation from other Bidders as well to assess Bidder responsibility and compliance with all bidder responsibility criteria. The Contracting Agency also reserves the right to obtain information from third-parties and independent sources of information concerning a Bidder’s compliance with the mandatory and supplemental criteria, and to use that information in their evaluation. The Contracting Agency may consider mitigating factors in determining whether the Bidder complies with the requirements of the supplemental criteria. The basis for evaluation of Bidder compliance with these mandatory and supplemental criteria shall include any documents or facts obtained by Contracting Agency (whether from the Bidder or third parties) including but not limited to: (i) financial, historical, or operational data from the Bidder; (ii) information obtained directly by the Contracting Agency from others for whom the Bidder has worked, or other public agencies or private enterprises; and (iii) any additional information obtained by the Contracting Agency which is believed to be relevant to the matter. DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 City of Bremerton 233-1896-178 Downtown Bicycle Pedestrian Circulation Improvements II-11 May 2021 Contract Documents Division 1 If the Contracting Agency determines the Bidder does not meet the bidder responsibility criteria above and is therefore not a responsible Bidder, the Contracting Agency shall notify the Bidder in writing, with the reasons for its determination. If the Bidder disagrees with this determination, it may appeal the determination within two (2) business days of the Contracting Agency’s determination by presenting its appeal and any additional information to the Contracting Agency. The Contracting Agency will consider the appeal and any additional information before issuing its final determination. If the final determination affirms that the Bidder is not responsible, the Contracting Agency will not execute a contract with any other Bidder until at least two business days after the Bidder determined to be not responsible has received the Contracting Agency’s final determination. Request to Change Supplemental Bidder Responsibility Criteria Prior To Bid: Bidders with concerns about the relevancy or restrictiveness of the Supplemental Bidder Responsibility Criteria may make or submit requests to the Contracting Agency to modify the criteria. Such requests shall be in writing, describe the nature of the concerns, and propose specific modifications to the criteria. Bidders shall submit such requests to the Contracting Agency no later than five (5) business days prior to the bid submittal deadline and address the request to the Project Engineer or such other person designated by the Contracting Agency in the Bid Documents. 1-02.15 Pre-Award Information (August 14, 2013 APWA GSP) Revise this section to read: Before awarding any contract, the Contracting Agency may require one or more of these items or actions of the apparent lowest responsible bidder: 1. A complete statement of the origin, composition, and manufacture of any or all materials to be used, 2. Samples of these materials for quality and fitness tests, 3. A progress schedule (in a form the Contracting Agency requires) showing the order of and time required for the various phases of the work, 4. A breakdown of costs assigned to any bid item, 5. Attendance at a conference with the Engineer or representatives of the Engineer, 6. Obtain, and furnish a copy of, a business license to do business in the city or county where the work is located. 7. Any other information or action taken that is deemed necessary to ensure that the bidder is the lowest responsible bidder DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 City of Bremerton 233-1896-178 Downtown Bicycle Pedestrian Circulation Improvements II-12 May 2021 Contract Documents Division 1 1-03 AWARD AND EXECUTION OF CONTRACT 1-03.1 Consideration of Bids (January 23, 2006 APWA GSP) Revise the first paragraph to read: After opening and reading proposals, the Contracting Agency will check them for correctness of extensions of the prices per unit and the total price. If a discrepancy exists between the price per unit and the extended amount of any bid item, the price per unit will control. If a minimum bid amount has been established for any item and the bidder’s unit or lump sum price is less than the minimum specified amount, the Contracting Agency will unilaterally revise the unit or lump sum price, to the minimum specified amount and recalculate the extension. The total of extensions, corrected where necessary, including sales taxes where applicable and such additives and/or alternates as selected by the Contracting Agency, will be used by the Contracting Agency for award purposes and to fix the Awarded Contract Price amount and the amount of the contract bond. 1-03.3 Execution of Contract (October 1, 2005 APWA GSP) Revise this section to read: Copies of the Contract Provisions, including the unsigned Form of Contract, will be available for signature by the successful bidder on the first business day following award. The number of copies to be executed by the Contractor will be determined by the Contracting Agency. Within ***7*** calendar days after the award date, the successful bidder shall return the signed Contracting Agency-prepared contract, an insurance certification as required by Section 1-07.18, and a satisfactory bond as required by law and Section 1-03.4. Before execution of the contract by the Contracting Agency, the successful bidder shall provide any pre-award information the Contracting Agency may require under Section 1-02.15. Until the Contracting Agency executes a contract, no proposal shall bind the Contracting Agency nor shall any work begin within the project limits or within Contracting Agency-furnished sites. The Contractor shall bear all risks for any work begun outside such areas and for any materials ordered before the contract is executed by the Contracting Agency. If the bidder experiences circumstances beyond their control that prevents return of the contract documents within the calendar days after the award date stated above, the Contracting Agency may grant up to a maximum of ***7*** additional calendar days for return of the documents, provided the Contracting Agency deems the circumstances warrant it. 1-03.4 Contract Bond (July 23, 2015 APWA GSP) Delete the first paragraph and replace it with the following: The successful bidder shall provide executed payment and performance bond(s) for the full contract amount. The bond may be a combined payment and performance bond; or be DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 City of Bremerton 233-1896-178 Downtown Bicycle Pedestrian Circulation Improvements II-13 May 2021 Contract Documents Division 1 separate payment and performance bonds. In the case of separate payment and performance bonds, each shall be for the full contract amount. The bond(s) shall: 1. Be on Contracting Agency-furnished form(s); 2. Be signed by an approved surety (or sureties) that: a. Is registered with the Washington State Insurance Commissioner, and b. Appears on the current Authorized Insurance List in the State of Washington published by the Office of the Insurance Commissioner, 3. Guarantee that the Contractor will perform and comply with all obligations, duties, and conditions under the Contract, including but not limited to the duty and obligation to indemnify, defend, and protect the Contracting Agency against all losses and claims related directly or indirectly from any failure: a. Of the Contractor (or any of the employees, subcontractors, or lower tier subcontractors of the Contractor) to faithfully perform and comply with all contract obligations, conditions, and duties, or b. Of the Contractor (or the subcontractors or lower tier subcontractors of the Contractor) to pay all laborers, mechanics, subcontractors, lower tier subcontractors, material person, or any other person who provides supplies or provisions for carrying out the work; 4. Be conditioned upon the payment of taxes, increases, and penalties incurred on the project under titles 50, 51, and 82 RCW; and 5. Be accompanied by a power of attorney for the Surety’s officer empowered to sign the bond; and 6. Be signed by an officer of the Contractor empowered to sign official statements (sole proprietor or partner). If the Contractor is a corporation, the bond(s) must be signed by the president or vice president, unless accompanied by written proof of the authority of the individual signing the bond(s) to bind the corporation (i.e., corporate resolution, power of attorney, or a letter to such effect signed by the president or vice president). 1-03.7 Judicial Review (November 30, 2018 APWA GSP) Revise this section to read: Any decision made by the Contracting Agency regarding the Award and execution of the Contract or Bid rejection shall be conclusive subject to the scope of judicial review permitted under Washington Law. Such review, if any, shall be timely filed in the Superior Court of the county where the Contracting Agency headquarters is located, provided that where an action is asserted against a county, RCW 36.01.050 shall control venue and jurisdiction. DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 City of Bremerton 233-1896-178 Downtown Bicycle Pedestrian Circulation Improvements II-14 May 2021 Contract Documents Division 1 1-04 SCOPE OF THE WORK 1-04.2 Coordination of Contract Documents, Plans, Special Provisions, Specifications, and Addenda (December 10, 2020 APWA GSP) Revise the second paragraph to read: Any inconsistency in the parts of the contract shall be resolved by following this order of precedence (e.g., 1 presiding over 2, 2 over 3, 3 over 4, and so forth): 1. Addenda, 2. Proposal Form, 3. Special Provisions, 4. Contract Plans, 5. Standard Specifications, 6. Contracting Agency’s Standard Plans or Details (if any), and 7. WSDOT Standard Plans for Road, Bridge, and Municipal Construction. 1-04.4 Changes 1-04.4(1) Minor Changes (May 30, 2019 APWA GSP) Delete the first paragraph and replace it with the following: Payments or credits for changes amounting to 20,000 or less may be made under the Bid item “Minor Change”. At the discretion of the Contracting Agency, this procedure for Minor Changes may be used in lieu of the more formal procedure as outlined in Section 1-04.4, Changes. All “Minor Change” work will be within the scope of the Contract Work and will not change Contract Time. 1-05 CONTROL OF WORK 1-05.4 Conformity With and Deviations From Plans and Stakes Section 1-05.4 is supplemented with the following: Contractor Surveying – Roadway Copies of the Contracting Agency provided primary survey control data are available for the bidder’s inspection at the office of the Engineer. The Contractor shall be responsible for setting, maintaining, and resetting all alignment stakes, slope stakes, and grades necessary for the construction of the roadbed, drainage, surfacing, paving, channelization and pavement marking, illumination and signals, guardrails and barriers, and signing. Except for the survey control data to be furnished by the Contracting Agency, calculations, surveying, and measuring required for setting and maintaining the necessary lines and grades shall be the Contractor’s responsibility. The Contractor shall inform the Engineer when monuments are discovered that were not identified in the Plans and construction activity may disturb or damage the monuments. All DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 City of Bremerton 233-1896-178 Downtown Bicycle Pedestrian Circulation Improvements II-15 May 2021 Contract Documents Division 1 monuments noted on the plans “DO NOT DISTURB” shall be protected throughout the length of the project or be replaced at the Contractors expense. Detailed survey records shall be maintained, including a description of the work performed on each shift, the methods utilized, and the control points used. The record shall be adequate to allow the survey to be reproduced. A copy of each day’s record shall be provided to the Engineer within three working days after the end of the shift. The meaning of words and terms used in this provision shall be as listed in “Definitions of Surveying and Associated Terms” current edition, published by the American Congress on Surveying and Mapping and the American Society of Civil Engineers. The survey work shall include but not be limited to the following: 1. Verify the primary horizontal and vertical control furnished by the Contracting Agency, and expand into secondary control by adding stakes and hubs as well as additional survey control needed for the project. Provide descriptions of secondary control to the Contracting Agency. The description shall include coordinates and elevations of all secondary control points. 2. Establish, the centerlines of all alignments, by placing hubs, stakes, or marks on centerline or on offsets to centerline at all curve points (PCs, PTs, and PIs) and at points on the alignments spaced no further than 50 feet. 3. Establish clearing limits, placing stakes at all angle points and at intermediate points not more than 50 feet apart. The clearing and grubbing limits shall be 5 feet beyond the toe of a fill and 10 feet beyond the top of a cut unless otherwise shown in the Plans. 4. Establish grading limits, placing slope stakes at centerline increments not more than 50 feet apart. Establish offset reference to all slope stakes. If Global Positioning Satellite (GPS) Machine Controls are used to provide grade control, then slope stakes may be omitted at the discretion of the Contractor 5. Establish the horizontal and vertical location of all drainage features, placing offset stakes to all drainage structures and to pipes at a horizontal interval not greater than 25 feet. 6. Establish roadbed and surfacing elevations by placing stakes at the top of subgrade and at the top of each course of surfacing. Subgrade and surfacing stakes shall be set at horizontal intervals not greater than 50 feet in tangent sections, 25 feet in curve sections with a radius less than 300 feet, and at 10-foot intervals in intersection radii with a radius less than 10 feet. Transversely, stakes shall be placed at all locations where the roadway slope changes and at additional points such that the transverse spacing of stakes is not more than 12 feet. If GPS Machine Controls are used to provide grade control, then roadbed and surfacing stakes may be omitted at the discretion of the Contractor. 7. Establish intermediate elevation benchmarks as needed to check work throughout the project. DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 City of Bremerton 233-1896-178 Downtown Bicycle Pedestrian Circulation Improvements II-16 May 2021 Contract Documents Division 1 8. Provide references for paving pins at 25-foot intervals or provide simultaneous surveying to establish location and elevation of paving pins as they are being placed. 9. For all other types of construction included in this provision, (including but not limited to channelization and pavement marking, illumination and signals, guardrails and barriers, and signing) provide staking and layout as necessary to adequately locate, construct, and check the specific construction activity. 10. Contractor shall determine if changes are needed to the profiles or roadway sections shown in the Contract Plans in order to achieve proper smoothness and drainage where matching into existing features, such as a smooth transition from new pavement to existing pavement. The Contractor shall submit these changes to the Engineer for review and approval 10 days prior to the beginning of work. The Contractor shall provide the Contracting Agency copies of any calculations and staking data when requested by the Engineer. To facilitate the establishment of these lines and elevations, the Contracting Agency will provide the Contractor with primary survey control information consisting of descriptions of two primary control points used for the horizontal and vertical control, and descriptions of two additional primary control points for every additional three miles of project length. Primary control points will be described by reference to the project alignment and the coordinate system and elevation datum utilized by the project. In addition, the Contracting Agency will supply horizontal coordinates for the beginning and ending points and for each Point of Intersection (PI) on each alignment included in the project. The Contractor shall ensure a surveying accuracy within the following tolerances: Vertical Horizontal Slope stakes 0.10 feet 0.10 feet Subgrade grade stakes set 0.04 feet below grade 0.01 feet 0.5 feet (parallel to alignment) 0.1 feet (normal to alignment) Stationing on roadway N/A 0.1 feet Alignment on roadway N/A 0.04 feet Surfacing grade stakes 0.01 feet 0.5 feet (parallel to alignment) 0.1 feet (normal to alignment) Roadway paving pins for surfacing or paving 0.01 feet 0.2 feet (parallel to alignment) 0.1 feet (normal to alignment) The Contracting Agency may spot-check the Contractor’s surveying. These spot-checks will not change the requirements for normal checking by the Contractor. DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 City of Bremerton 233-1896-178 Downtown Bicycle Pedestrian Circulation Improvements II-17 May 2021 Contract Documents Division 1 When staking roadway alignment and stationing, the Contractor shall perform independent checks from different secondary control to ensure that the points staked are within the specified survey accuracy tolerances. The Contractor shall calculate coordinates for the alignment. The Contracting Agency will verify these coordinates prior to issuing approval to the Contractor for commencing with the work. The Contracting Agency will require up to seven calendar days from the date the data is received. Contract work to be performed using contractor-provided stakes shall not begin until the stakes are approved by the Contracting Agency. Such approval shall not relieve the Contractor of responsibility for the accuracy of the stakes. Stakes shall be marked in accordance with Standard Plan A10.10. When stakes are needed that are not described in the Plans, then those stakes shall be marked, at no additional cost to the Contracting Agency as ordered by the Engineer. Payment Payment will be made for the following bid item per lump sum breakdown which is included in the proposal: “Roadway Surveying”, lump sum. The lump sum contract price for “Roadway Surveying” shall be full pay for all labor, equipment, materials, and supervision utilized to perform the Work specified, including any resurveying, checking, correction of errors, replacement of missing or damaged stakes, and coordination efforts. 1-05.7 Removal of Defective and Unauthorized Work (October 1, 2005 APWA GSP) Supplement this section with the following: If the Contractor fails to remedy defective or unauthorized work within the time specified in a written notice from the Engineer, or fails to perform any part of the work required by the Contract Documents, the Engineer may correct and remedy such work as may be identified in the written notice, with Contracting Agency forces or by such other means as the Contracting Agency may deem necessary. If the Contractor fails to comply with a written order to remedy what the Engineer determines to be an emergency situation, the Engineer may have the defective and unauthorized work corrected immediately, have the rejected work removed and replaced, or have work the Contractor refuses to perform completed by using Contracting Agency or other forces. An emergency situation is any situation when, in the opinion of the Engineer, a delay in its remedy could be potentially unsafe, or might cause serious risk of loss or damage to the public. DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 City of Bremerton 233-1896-178 Downtown Bicycle Pedestrian Circulation Improvements II-18 May 2021 Contract Documents Division 1 Direct or indirect costs incurred by the Contracting Agency attributable to correcting and remedying defective or unauthorized work, or work the Contractor failed or refused to perform, shall be paid by the Contractor. Payment will be deducted by the Engineer from monies due, or to become due, the Contractor. Such direct and indirect costs shall include in particular, but without limitation, compensation for additional professional services required, and costs for repair and replacement of work of others destroyed or damaged by correction, removal, or replacement of the Contractor’s unauthorized work. No adjustment in contract time or compensation will be allowed because of the delay in the performance of the work attributable to the exercise of the Contracting Agency’s rights provided by this Section. The rights exercised under the provisions of this section shall not diminish the Contracting Agency’s right to pursue any other avenue for additional remedy or damages with respect to the Contractor’s failure to perform the work as required. 1-05.11 Final Inspection Delete this section and replace it with the following: 1-05.11 Final Inspections and Operational Testing (October 1, 2005 APWA GSP) 1-05.11(1) Substantial Completion Date When the Contractor considers the work to be substantially complete, the Contractor shall so notify the Engineer and request the Engineer establish the Substantial Completion Date. The Contractor’s request shall list the specific items of work that remain to be completed in order to reach physical completion. The Engineer will schedule an inspection of the work with the Contractor to determine the status of completion. The Engineer may also establish the Substantial Completion Date unilaterally. If, after this inspection, the Engineer concurs with the Contractor that the work is substantially complete and ready for its intended use, the Engineer, by written notice to the Contractor, will set the Substantial Completion Date. If, after this inspection the Engineer does not consider the work substantially complete and ready for its intended use, the Engineer will, by written notice, so notify the Contractor giving the reasons therefore. Upon receipt of written notice concurring in or denying substantial completion, whichever is applicable, the Contractor shall pursue vigorously, diligently and without unauthorized interruption, the work necessary to reach Substantial and Physical Completion. The Contractor shall provide the Engineer with a revised schedule indicating when the Contractor expects to reach substantial and physical completion of the work. The above process shall be repeated until the Engineer establishes the Substantial Completion Date and the Contractor considers the work physically complete and ready for final inspection. DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 City of Bremerton 233-1896-178 Downtown Bicycle Pedestrian Circulation Improvements II-19 May 2021 Contract Documents Division 1 1-05.11(2) Final Inspection and Physical Completion Date When the Contractor considers the work physically complete and ready for final inspection, the Contractor by written notice, shall request the Engineer to schedule a final inspection. The Engineer will set a date for final inspection. The Engineer and the Contractor will then make a final inspection and the Engineer will notify the Contractor in writing of all particulars in which the final inspection reveals the work incomplete or unacceptable. The Contractor shall immediately take such corrective measures as are necessary to remedy the listed deficiencies. Corrective work shall be pursued vigorously, diligently, and without interruption until physical completion of the listed deficiencies. This process will continue until the Engineer is satisfied the listed deficiencies have been corrected. If action to correct the listed deficiencies is not initiated within 7 days after receipt of the written notice listing the deficiencies, the Engineer may, upon written notice to the Contractor, take whatever steps are necessary to correct those deficiencies pursuant to Section 1-05.7. The Contractor will not be allowed an extension of contract time because of a delay in the performance of the work attributable to the exercise of the Engineer’s right hereunder. Upon correction of all deficiencies, the Engineer will notify the Contractor and the Contracting Agency, in writing, of the date upon which the work was considered physically complete. That date shall constitute the Physical Completion Date of the contract, but shall not imply acceptance of the work or that all the obligations of the Contractor under the contract have been fulfilled. 1-05.11(3) Operational Testing It is the intent of the Contracting Agency to have at the Physical Completion Date a complete and operable system. Therefore when the work involves the installation of machinery or other mechanical equipment; street lighting, electrical distribution or signal systems; irrigation systems; buildings; or other similar work it may be desirable for the Engineer to have the Contractor operate and test the work for a period of time after final inspection but prior to the physical completion date. Whenever items of work are listed in the Contract Provisions for operational testing they shall be fully tested under operating conditions for the time period specified to ensure their acceptability prior to the Physical Completion Date. During and following the test period, the Contractor shall correct any items of workmanship, materials, or equipment which prove faulty, or that are not in first class operating condition. Equipment, electrical controls, meters, or other devices and equipment to be tested during this period shall be tested under the observation of the Engineer, so that the Engineer may determine their suitability for the purpose for which they were installed. The Physical Completion Date cannot be established until testing and corrections have been completed to the satisfaction of the Engineer. The costs for power, gas, labor, material, supplies, and everything else needed to successfully complete operational testing, shall be included in the unit contract prices related to the system being tested, unless specifically set forth otherwise in the proposal. Operational and test periods, when required by the Engineer, shall not affect a manufacturer’s guaranties or warranties furnished under the terms of the contract. DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 City of Bremerton 233-1896-178 Downtown Bicycle Pedestrian Circulation Improvements II-20 May 2021 Contract Documents Division 1 1-05.13 Superintendents, Labor, and Equipment of Contractor (August 14, 2013 APWA GSP) Delete the sixth and seventh paragraphs of this section. 1-05.14 Cooperation With Other Contractors Section 1-05.14 is supplemented with the following: It is anticipated that the following work adjacent to or within the limits of this project will be performed by others during the course of this project and will require coordination of the work: 1. Private development at 205 6th Street, Bremerton, WA 98337 1-05.15 Method of Serving Notices (March 25, 2009 APWA GSP) Revise the second paragraph to read: All correspondence from the Contractor shall be directed to the Project Engineer. All correspondence from the Contractor constituting any notification, notice of protest, notice of dispute, or other correspondence constituting notification required to be furnished under the Contract, must be in paper format, hand delivered or sent via mail delivery service to the Project Engineer’s office. Electronic copies such as e-mails or electronically delivered copies of correspondence will not constitute such notice and will not comply with the requirements of the Contract. Add the following new section: 1-05.16 Water and Power (New Section) (October 1, 2005 APWA GSP) The Contractor shall make necessary arrangements, and shall bear the costs for power and water necessary for the performance of the work, unless the contract includes power and water as a pay item. 1-07 LEGAL RELATIONS AND RESPONSIBILITIES TO THE PUBLIC 1-07.1 Laws to be Observed (October 1, 2005 APWA GSP) Supplement this section with the following: In cases of conflict between different safety regulations, the more stringent regulation shall apply. The Washington State Department of Labor and Industries shall be the sole and paramount administrative agency responsible for the administration of the provisions of the Washington Industrial Safety and Health Act of 1973 (WISHA). DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 City of Bremerton 233-1896-178 Downtown Bicycle Pedestrian Circulation Improvements II-21 May 2021 Contract Documents Division 1 The Contractor shall maintain at the project site office, or other well known place at the project site, all articles necessary for providing first aid to the injured. The Contractor shall establish, publish, and make known to all employees, procedures for ensuring immediate removal to a hospital, or doctor’s care, persons, including employees, who may have been injured on the project site. Employees should not be permitted to work on the project site before the Contractor has established and made known procedures for removal of injured persons to a hospital or a doctor’s care. The Contractor shall have sole responsibility for the safety, efficiency, and adequacy of the Contractor’s plant, appliances, and methods, and for any damage or injury resulting from their failure, or improper maintenance, use, or operation. The Contractor shall be solely and completely responsible for the conditions of the project site, including safety for all persons and property in the performance of the work. This requirement shall apply continuously, and not be limited to normal working hours. The required or implied duty of the Engineer to conduct construction review of the Contractor’s performance does not, and shall not, be intended to include review and adequacy of the Contractor’s safety measures in, on, or near the project site. (May 13, 2020 WSDOT GSP, Option 4) COVID-19 Health and Safety Plan In response to COVID-19, the Contractor shall prepare a project specific COVID-19 health and safety plan (CHSP) in conformance with Section 1-07.4(2) as supplemented in these specifications, COVID-19 Health and Safety Plan (CHSP). 1-07.2 State Taxes Delete this section, including its sub-sections, in its entirety and replace it with the following: 1-07.2 Sales Tax (June 27, 2011 APWA GSP) The Washington State Department of Revenue has issued special rules on the State sales tax. Sections 1-07.2(1) through 1-07.2(3) are meant to clarify those rules. The Contractor should contact the Washington State Department of Revenue for answers to questions in this area. The Contracting Agency will not adjust its payment if the Contractor bases a bid on a misunderstood tax liability. The Contractor shall include all Contractor-paid taxes in the unit bid prices or other contract amounts. In some cases, however, state retail sales tax will not be included. Section 1-07.2(2) describes this exception. The Contracting Agency will pay the retained percentage (or release the Contract Bond if a FHWA-funded Project) only if the Contractor has obtained from the Washington State Department of Revenue a certificate showing that all contract-related taxes have been paid (RCW 60.28.051). The Contracting Agency may deduct from its payments to the Contractor any amount the Contractor may owe the Washington State Department of Revenue, whether the amount owed relates to this contract or not. Any amount so deducted will be paid into the proper State fund. DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 City of Bremerton 233-1896-178 Downtown Bicycle Pedestrian Circulation Improvements II-22 May 2021 Contract Documents Division 1 1-07.2(1) State Sales Tax — Rule 171 WAC 458-20-171, and its related rules, apply to building, repairing, or improving streets, roads, etc., which are owned by a municipal corporation, or political subdivision of the state, or by the United States, and which are used primarily for foot or vehicular traffic. This includes storm or combined sewer systems within and included as a part of the street or road drainage system and power lines when such are part of the roadway lighting system. For work performed in such cases, the Contractor shall include Washington State Retail Sales Taxes in the various unit bid item prices, or other contract amounts, including those that the Contractor pays on the purchase of the materials, equipment, or supplies used or consumed in doing the work. 1-07.2(2) State Sales Tax — Rule 170 WAC 458-20-170, and its related rules, apply to the constructing and repairing of new or existing buildings, or other structures, upon real property. This includes, but is not limited to, the construction of streets, roads, highways, etc., owned by the state of Washington; water mains and their appurtenances; sanitary sewers and sewage disposal systems unless such sewers and disposal systems are within, and a part of, a street or road drainage system; telephone, telegraph, electrical power distribution lines, or other conduits or lines in or above streets or roads, unless such power lines become a part of a street or road lighting system; and installing or attaching of any article of tangible personal property in or to real property, whether or not such personal property becomes a part of the realty by virtue of installation. For work performed in such cases, the Contractor shall collect from the Contracting Agency, retail sales tax on the full contract price. The Contracting Agency will automatically add this sales tax to each payment to the Contractor. For this reason, the Contractor shall not include the retail sales tax in the unit bid item prices, or in any other contract amount subject to Rule 170, with the following exception. Exception: The Contracting Agency will not add in sales tax for a payment the Contractor or a subcontractor makes on the purchase or rental of tools, machinery, equipment, or consumable supplies not integrated into the project. Such sales taxes shall be included in the unit bid item prices or in any other contract amount. 1-07.2(3) Services The Contractor shall not collect retail sales tax from the Contracting Agency on any contract wholly for professional or other services (as defined in Washington State Department of Revenue Rules 138 and 244). DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 City of Bremerton 233-1896-178 Downtown Bicycle Pedestrian Circulation Improvements II-23 May 2021 Contract Documents Division 1 1-07.4 Sanitation 1-07.4(2) Health Hazards Section 1-07.4(2) is supplemented with the following: (May 13 , 2020 WSDOT GSP, Option 2) COVID-19 Health and Safety Plan (CHSP) The Contractor shall prepare a project specific COVID-19 health and safety plan (CHSP). The CHSP shall be prepared and submitted as a Type 2 Working Drawing prior to beginning physical Work. The CHSP shall be based on the most current State and Federal requirements. If the State or Federal requirements are revised, the CHSP shall be updated as necessary to conform to the current requirements. The Contractor shall update and resubmit the CHSP as the work progresses and new activities appear on the look ahead schedule required under Section 1-08.3(2)D. If the conditions change on the project, or a particular activity, the Contractor shall update and resubmit the CHSP. Work on any activity shall cease if conditions prevent full compliance with the CHSP. The CHSP shall address the health and safety of all people associated with the project including State workers in the field, Contractor personnel, consultants, project staff, subcontractors, suppliers and anyone on the project site, staging areas, or yards. COVID-19 Health and Safety Plan (CHSP) Inspection The Contractor shall grant full and unrestricted access to the Engineer for CHSP Inspections. The Engineer (or designee) will conduct periodic compliance inspections on the project site, staging areas, or yards to verify that any ongoing work activity is following the CHSP. If the Engineer becomes aware of a noncompliance incident either through a site inspection or other means, the Contractor will be notified immediately (within 1 hour). The Contractor shall immediately remedy the noncompliance incident or suspend all or part of the associated work activity. The Contractor shall satisfy the Engineer that the noncompliance incident has been corrected before the suspension will end. 1-07.9 Wages 1-07.9(5) Required Documents (January 3, 2020 APWA GSP) Delete this section and replace it with the following: General All “Statements of Intent to Pay Prevailing Wages”, “Affidavits of Wages Paid” and Certified Payrolls, including a signed Statement of Compliance for Federal-aid projects, shall be submitted to the Engineer and the State L&I online Prevailing Wage Intent & Affidavit (PWIA) system. DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 City of Bremerton 233-1896-178 Downtown Bicycle Pedestrian Circulation Improvements II-24 May 2021 Contract Documents Division 1 Intents and Affidavits On forms provided by the Industrial Statistician of State L&I, the Contractor shall submit to the Engineer the following for themselves and for each firm covered under RCW 39.12 that will or has provided Work and materials for the Contract: 1. The approved “Statement of Intent to Pay Prevailing Wages” State L&I’s form number F700-029-000. The Contracting Agency will make no payment under this Contract until this statement has been approved by State L&I and reviewed by the Engineer. 2. The approved “Affidavit of Prevailing Wages Paid”, State L&I’s form number F700-007-000. The Contracting Agency will not grant Completion until all approved Affidavit of Wages paid for the Contractor and all Subcontractors have been received by the Engineer. The Contracting Agency will not release to the Contractor any funds retained under RCW 60.28.011 until “Affidavit of Prevailing Wages Paid” forms have been approved by State L&I and all of the approved forms have been submitted to the Engineer for every firm that worked on the Contract. The Contractor is responsible for requesting these forms from State L&I and for paying any fees required by State L&I. Certified Payrolls Certified payrolls are required to be submitted by the Contractor for themselves, all Subcontractors and all lower tier subcontractors. The payrolls shall be submitted weekly on all Federal-aid projects and no less than monthly on State funded projects. Penalties for Noncompliance The Contractor is advised, if these payrolls are not supplied within the prescribed deadlines, any or all payments may be withheld until compliance is achieved. In addition, failure to provide these payrolls may result in other sanctions as provided by State laws (RCW 39.12.050) and/or Federal regulations (29 CFR 5.12). 1-07.13 Contractor’s Responsibility for Work 1-07.13(4) Repair of Damage Section 1-07.13(4) is revised to read: (August 6, 2001 WSDOT GSP) The Contractor shall promptly repair all damage to either temporary or permanent work as directed by the Engineer. For damage qualifying for relief under Sections 1-07.13(1), 1-07.13(2) or 1-07.13(3), payment will be made in accordance with Section 1-04.4. Payment will be limited to repair of damaged work only. No payment will be made for delay or disruption of work. 1-07.15 Temporary Water Pollution Prevention Section 1-07.15 is supplemented with the following: Protection of the Environment: No construction related activity shall contribute to the degradation of the environment, allow material to enter surface or ground waters, or allow DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 City of Bremerton 233-1896-178 Downtown Bicycle Pedestrian Circulation Improvements II-25 May 2021 Contract Documents Division 1 particulate emissions to the atmosphere, which exceed state or federal standards. Any actions that potentially allow a discharge to state waters must have prior approval of the Washington State Department of Ecology. 1-07.16 Protection and Restoration of Property 1-07.16(4) Archaeological and Historical Objects Section 1-07.16(4) is supplemented with the following: The project area has a low potential for containing archaeological or historical objects that may have significance from a historical or scientific standpoint. In the event these objects are inadvertently discovered, the Inadvertent Discovery Plan contained in Standard Specifications Section 1-07.16(4)A shall be implemented. The Contracting Agency, at its discretion and expense, may monitor the Contractor’s operations, conduct various site testing, and perform recovery and removal of such objects when necessary. The Contractor may be required to conduct its operations in a manner that will accommodate such activities, including the reserving of portions of the work area for site testing, exploratory operations and recovery as directed by the Engineer. If such activities are performed by consultants retained by the Contracting Agency, the Contractor shall provide them adequate access to the project site. 1-07.16(5) Payment Section 1-07.16(5) is supplemented with the following: All costs to comply with this special provision, unless otherwise stated, are incidental to the Contract and are the responsibility of the Contractor. The Contractor shall include all related costs in the unit Bid process of the Contract. Added work necessary to uncover, fence, dewater, salvage, or otherwise protect the archaeological or historical objects as ordered by the Engineer shall be paid for in accordance with Standard Specification Section 1-04.4 Changes and 1-08.8 Extensions of Time. 1-07.17 Utilities and Similar Facilities Section 1-07.17 is supplemented with the following: (April 2, 2007 WSDOT GSP, Option 2) Locations and dimensions shown in the Plans for existing facilities are in accordance with available information obtained without uncovering, measuring, or other verification. Public and private utilities, or their Contractors, will furnish all work necessary to adjust, relocate, replace, or construct their facilities unless otherwise provided for in the Plans or these Special Provisions. Such adjustment, relocation, replacement, or construction will be done during the prosecution of the work for this project. It is anticipated that utility adjustment, relocation, replacement, or construction within the project limits will be completed as follows: *** As described in the Contract Plans and Division 8 of these Special Provisions. *** DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 City of Bremerton 233-1896-178 Downtown Bicycle Pedestrian Circulation Improvements II-26 May 2021 Contract Documents Division 1 The Contractor shall attend a mandatory utility preconstruction meeting with the Engineer, all affected Subcontractors, and all utility owners and their Contractors prior to beginning onsite work. The following addresses and telephone numbers of utility companies or their Contractors that will be adjusting, relocating, replacing or constructing utilities within the project limits are supplied for the Contractor’s use: *** Storm Drainage Telephone City of Bremerton CenturyLink (Lumen) Contact: Gunnar Fridriksson, P.E. Contact: Dioni Caiaga 345 6th Street Ste. 500 411 S. Kaiser Road Bremerton, WA 98337 Olympia, WA 98502 (360) 473-5758 (206) 733-5261 Gunnar.Fridriksson@ci.bremerton.wa.us (360) 250-2596 (cell) Dioni.Cariaga@Lumen.com Water/Sanitary Power City of Bremerton Puget Sound Energy Contact: William Davis, P.E. Contact: Errol Burgos 345 6th Street Ste. 500 6522 Kitsap Way Bremerton, WA 98337 Bremerton, WA 98312 (360) 473-2312 (425) 234-5341 william.davis@ci.bremerton.wa.us Errol.burgos@pse.com Gas Cable Cascade Natural Gas Co. Comcast Contact: Shawn O’Neill Contact: Jim LeCompte 6313 Kitsap Way 1225 Sylvan Way Bremerton, WA 98310 Bremerton, WA 98310 (360) 328-6845 (360) 340-1288 shawn.oneill@cngc.com jim_lecompte@cable.comcast.com Fiber Optic Cable Fiber Optic Cable Convergence Technologies Kitsap Co. PUD Contact: John Stockwell Contact: Matt Hensen 900 Sheridan Road 1431 Finn Hill Road Bremerton, WA 98310 Poulsbo, WA 98370 (360) 405-1231 (360) 509-8925 john@nw-commnet.com matt@kpud.org The Contractor shall notify all utility offices which are affected by the construction operation at least two (2) working days in advance. Under no circumstances expose any utility without first obtaining permission from the appropriate agency. Once permission has been granted, locate, expose, and provide temporary support for all existing underground utilities. *** DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 City of Bremerton 233-1896-178 Downtown Bicycle Pedestrian Circulation Improvements II-27 May 2021 Contract Documents Division 1 Add the following new section: 1-07.17(3) Protection and Support of Existing Utilities (New Section) Description The Contractor shall provide protection of all existing utility facilities crossing the work area during construction. All utilities shall remain fully operational throughout the life of this contract unless otherwise stated in these provisions. The Contractor shall be responsible for locating all underground utilities prior to starting excavation work. The Contractor shall note that utilities such as power conduit are anticipated to be located near the RRFB and pedestrian push button foundations. These foundations may need to be adjusted to provide clearance from the conduit. The Contractor shall locate, “pot hole,” and expose all existing underground utilities at the site prior to starting excavation in order to verify utility locations. Excavation immediately adjacent to existing utilities including conduits shall be by hand methods in compliance with Washington State requirements. Payment Costs for utility locates and potholing shall be incidental to the other pay items in the Contract. 1-07.18 Public Liability and Property Damage Insurance Delete this section in its entirety, and replace it with the following: 1-07.18 Insurance (January 4, 2016 APWA GSP) 1-07.18(1) General Requirements A. The Contractor shall procure and maintain the insurance described in all subsections of section 1-07.18 of these Special Provisions, from insurers with a current A. M. Best rating of not less than A-: VII and licensed to do business in the State of Washington. The Contracting Agency reserves the right to approve or reject the insurance provided, based on the insurer’s financial condition. B. The Contractor shall keep this insurance in force without interruption from the commencement of the Contractor’s Work through the term of the Contract and for thirty (30) days after the Physical Completion date, unless otherwise indicated below. C. If any insurance policy is written on a claims made form, its retroactive date, and that of all subsequent renewals, shall be no later than the effective date of this Contract. The policy shall state that coverage is claims made, and state the retroactive date. Claims-made form coverage shall be maintained by the Contractor for a minimum of 36 months following the Completion Date or earlier termination of this Contract, and the Contractor shall annually provide the Contracting Agency with proof of renewal. If renewal of the claims made form of coverage becomes unavailable, or economically prohibitive, the Contractor shall purchase an extended reporting period (“tail”) or execute another form DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 City of Bremerton 233-1896-178 Downtown Bicycle Pedestrian Circulation Improvements II-28 May 2021 Contract Documents Division 1 of guarantee acceptable to the Contracting Agency to assure financial responsibility for liability for services performed. D. The Contractor’s Automobile Liability, Commercial General Liability and Excess or Umbrella Liability insurance policies shall be primary and non-contributory insurance as respects the Contracting Agency’s insurance, self-insurance, or self-insured pool coverage. Any insurance, self-insurance, or self-insured pool coverage maintained by the Contracting Agency shall be excess of the Contractor’s insurance and shall not contribute with it. E. The Contractor shall provide the Contracting Agency and all additional insureds with written notice of any policy cancellation, within two business days of their receipt of such notice. F. The Contractor shall not begin work under the Contract until the required insurance has been obtained and approved by the Contracting Agency. G. Failure on the part of the Contractor to maintain the insurance as required shall constitute a material breach of contract, upon which the Contracting Agency may, after giving five business days’ notice to the Contractor to correct the breach, immediately terminate the Contract or, at its discretion, procure or renew such insurance and pay any and all premiums in connection therewith, with any sums so expended to be repaid to the Contracting Agency on demand, or at the sole discretion of the Contracting Agency, offset against funds due the Contractor from the Contracting Agency. H. All costs for insurance shall be incidental to and included in the unit or lump sum prices of the Contract and no additional payment will be made. 1-07.18(2) Additional Insured All insurance policies, with the exception of Workers Compensation, and of Professional Liability and Builder’s Risk (if required by this Contract) shall name the following listed entities as additional insured(s) using the forms or endorsements required herein: • the Contracting Agency and its officers, elected officials, employees, agents, and volunteers The above-listed entities shall be additional insured(s) for the full available limits of liability maintained by the Contractor, irrespective of whether such limits maintained by the Contractor are greater than those required by this Contract, and irrespective of whether the Certificate of Insurance provided by the Contractor pursuant to 1-07.18(4) describes limits lower than those maintained by the Contractor. For Commercial General Liability insurance coverage, the required additional insured endorsements shall be at least as broad as ISO forms CG 20 10 10 01 for ongoing operations and CG 20 37 10 01 for completed operations. 1-07.18(3) Subcontractors The Contractor shall cause each Subcontractor of every tier to provide insurance coverage that complies with all applicable requirements of the Contractor-provided insurance as set DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 City of Bremerton 233-1896-178 Downtown Bicycle Pedestrian Circulation Improvements II-29 May 2021 Contract Documents Division 1 forth herein, except the Contractor shall have sole responsibility for determining the limits of coverage required to be obtained by Subcontractors. The Contractor shall ensure that all Subcontractors of every tier add all entities listed in 1-07.18(2) as additional insureds, and provide proof of such on the policies as required by that section as detailed in 1-07.18(2) using an endorsement as least as broad as ISO CG 20 10 10 01 for ongoing operations and CG 20 37 10 01 for completed operations. Upon request by the Contracting Agency, the Contractor shall forward to the Contracting Agency evidence of insurance and copies of the additional insured endorsements of each Subcontractor of every tier as required in 1-07.18(4) Verification of Coverage. 1-07.18(4) Verification of Coverage The Contractor shall deliver to the Contracting Agency a Certificate(s) of Insurance and endorsements for each policy of insurance meeting the requirements set forth herein when the Contractor delivers the signed Contract for the work. Failure of Contracting Agency to demand such verification of coverage with these insurance requirements or failure of Contracting Agency to identify a deficiency from the insurance documentation provided shall not be construed as a waiver of Contractor’s obligation to maintain such insurance. Verification of coverage shall include: 1. An ACORD certificate or a form determined by the Contracting Agency to be equivalent. 2. Copies of all endorsements naming Contracting Agency and all other entities listed in 1-07.18(2) as additional insured(s), showing the policy number. The Contractor may submit a copy of any blanket additional insured clause from its policies instead of a separate endorsement. 3. Any other amendatory endorsements to show the coverage required herein. 4. A notation of coverage enhancements on the Certificate of Insurance shall not satisfy these requirements – actual endorsements must be submitted. Upon request by the Contracting Agency, the Contractor shall forward to the Contracting Agency a full and certified copy of the insurance policy(s). If Builders Risk insurance is required on this Project, a full and certified copy of that policy is required when the Contractor delivers the signed Contract for the work. 1-07.18(5) Coverages and Limits The insurance shall provide the minimum coverages and limits set forth below. Contractor’s maintenance of insurance, its scope of coverage, and limits as required herein shall not be construed to limit the liability of the Contractor to the coverage provided by such insurance, or otherwise limit the Contracting Agency’s recourse to any remedy available at law or in equity. All deductibles and self-insured retentions must be disclosed and are subject to approval by the Contracting Agency. The cost of any claim payments falling within the deductible or DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 City of Bremerton 233-1896-178 Downtown Bicycle Pedestrian Circulation Improvements II-30 May 2021 Contract Documents Division 1 self-insured retention shall be the responsibility of the Contractor. In the event an additional insured incurs a liability subject to any policy’s deductibles or self-insured retention, said deductibles or self-insured retention shall be the responsibility of the Contractor. 1-07.18(5)A Commercial General Liability Commercial General Liability insurance shall be written on coverage forms at least as broad as ISO occurrence form CG 00 01, including but not limited to liability arising from premises, operations, stop gap liability, independent contractors, products-completed operations, personal and advertising injury, and liability assumed under an insured contract. There shall be no exclusion for liability arising from explosion, collapse or underground property damage. The Commercial General Liability insurance shall be endorsed to provide a per project general aggregate limit, using ISO form CG 25 03 05 09 or an equivalent endorsement. Contractor shall maintain Commercial General Liability Insurance arising out of the Contractor’s completed operations for at least three years following Substantial Completion of the Work. Such policy must provide the following minimum limits: $1,000,000 Each Occurrence $2,000,000 General Aggregate $2,000,000 Products & Completed Operations Aggregate $1,000,000 Personal & Advertising Injury each offence $1,000,000 Stop Gap / Employers’ Liability each accident 1-07.18(5)B Automobile Liability Automobile Liability shall cover owned, non-owned, hired, and leased vehicles; and shall be written on a coverage form at least as broad as ISO form CA 00 01. If the work involves the transport of pollutants, the automobile liability policy shall include MCS 90 and CA 99 48 endorsements. Such policy must provide the following minimum limit: $1,000,000 Combined single limit each accident 1-07.18(5)C Workers’ Compensation The Contractor shall comply with Workers’ Compensation coverage as required by the Industrial Insurance laws of the State of Washington. DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 City of Bremerton 233-1896-178 Downtown Bicycle Pedestrian Circulation Improvements II-31 May 2021 Contract Documents Division 1 1-07.23 Public Convenience and Safety 1-07.23(1) Construction Under Traffic Section 1-07.23(1) is supplemented with the following: (February 3, 2020 WSDOT GSP, Option 2) Work Zone Clear Zone The Work Zone Clear Zone (WZCZ) applies during working and nonworking hours. The WZCZ applies only to temporary roadside objects introduced by the Contractor’s operations and does not apply to preexisting conditions or permanent Work. Those work operations that are actively in progress shall be in accordance with adopted and approved Traffic Control Plans, and other contract requirements. During nonworking hours equipment or materials shall not be within the WZCZ unless they are protected by permanent guardrail or temporary concrete barrier. The use of temporary concrete barrier shall be permitted only if the Engineer approves the installation and location. During actual hours of work, unless protected as described above, only materials absolutely necessary to construction shall be within the WZCZ and only construction vehicles absolutely necessary to construction shall be allowed within the WZCZ or allowed to stop or park on the shoulder of the roadway. The Contractor's nonessential vehicles and employees private vehicles shall not be permitted to park within the WZCZ at any time unless protected as described above. Deviation from the above requirements shall not occur unless the Contractor has requested the deviation in writing and the Engineer has provided written approval. Minimum WZCZ distances are measured from the edge of traveled way and will be determined as follows: Regulatory Posted Speed Distance From Traveled Way (Feet) 35 mph or less 10 40 mph 15 45 to 50 mph 20 55 to 60 mph 30 65 mph or greater 35 Minimum Work Zone Clear Zone Distance (January 5, 2015 WSDOT GSP, Option 5) Lane closures are subject to the following restrictions: ***Lane restrictions shall be held to a minimum time and length needed for each operation. If the Engineer determines that the lane restrictions are causing congestion, the Contractor will be required to open all lanes to traffic until congestion is eliminated. DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 City of Bremerton 233-1896-178 Downtown Bicycle Pedestrian Circulation Improvements II-32 May 2021 Contract Documents Division 1 Full roadway closures are not allowed. Single-lane closures will be permitted during the following hours: All Downtown Streets (Pacific Avenue, Burwell Street, 1st Street, and Washington Avenue): Sunday: 6:00 PM to 11:59 PM Monday: 12:00 AM to 5:00 AM, 8:00 AM to 3:00 PM and 6:00 PM to 11:59 PM Tuesday: 12:00 AM to 5:00 AM, 8:00 AM to 3:00 PM and 6:00 PM to 11:59 PM Wednesday: 12:00 AM to 5:00 AM, 8:00 AM to 3:00 PM and 6:00 PM to 11:59 PM Thursday: 12:00 AM to 5:00 AM, 8:00 AM to 3:00 PM and 6:00 PM to 11:59 PM Friday: 12:00 AM to 5:00 AM and 8:00 AM to 3:00 PM Saturday: no closures allowed. Austin Drive: Sunday: 6:00 PM to 11:59 PM Monday: 12:00 AM to 6:00 AM, 9:00 AM to 4:00 PM and 6:00 PM to 11:59 PM Tuesday: 12:00 AM to 6:00 AM, 9:00 AM to 4:00 PM and 6:00 PM to 11:59 PM Wednesday: 12:00 AM to 6:00 AM, 9:00 AM to 4:00 PM and 6:00 PM to 11:59 PM Thursday: 12:00 AM to 6:00 AM, 9:00 AM to 4:00 PM and 6:00 PM to 11:59 PM Friday: 12:00 AM to 6:00 AM and 9:00 AM to 4:00 PM Saturday: no closures allowed.*** If the Engineer determines the permitted closure hours adversely affect traffic, the Engineer may adjust the hours accordingly. The Engineer will notify the Contractor in writing of any change in the closure hours. Lane closures are not allowed on any of the following: 1. A holiday, 2. A holiday weekend; holidays that occur on Friday, Saturday, Sunday or Monday are considered a holiday weekend. A holiday weekend includes Saturday, Sunday, and the holiday. 3. After *** 9 pm *** on the day prior to a holiday or holiday weekend, and 4. Before *** 7 am *** on the day after the holiday or holiday weekend. Temporary Parking Restriction Notification Where the Engineer determines that parking is a hazard to through traffic, or to the construction work, parking may be restricted either entirely or during the time when it creates a hazard. Parking signs shall be placed at least 72 hours in advance of parking removal, with the start date of the “no parking” clearly shown. The area to be restricted shall be clearly marked with Type 1 barricades carrying signs that give the specific period (dates and times) that the area is to be free of vehicles. Signs shall be large enough to be easily read from a distance of 50 feet and shall advise where impounded vehicles will be stored or indicate a 24-hour telephone number for obtaining that information. DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 City of Bremerton 233-1896-178 Downtown Bicycle Pedestrian Circulation Improvements II-33 May 2021 Contract Documents Division 1 The Contractor shall be responsible for placement and maintenance of the signs. Placement of the signs will be as approved by the Engineer. The Contractor shall notify the Engineer by telephone or otherwise when the signs are placed. No towing of vehicles shall occur unless signs are placed at least 72 hours prior to the beginning of the restricted parking. All signs must be approved by the Engineer prior to placement and shall generally include the following: WARNING! TOW AWAY ZONE NO PARKING FROM: DATE AND TIME TO: DATE AND TIME FOR CONSTRUCTION WORK ALL VEHICLES REMAINING WILL BE TOWED (IMPOUND INFORMATION) 1-08 PROSECUTION AND PROGRESS Add the following new section: 1-08.0 Preliminary Matters (New Section) (May 25, 2006 APWA GSP) Add the following new section: 1-08.0(1) Preconstruction Conference (New Section) (October 10, 2008 APWA GSP) Prior to the Contractor beginning the work, a preconstruction conference will be held between the Contractor, the Engineer and such other interested parties as may be invited. The purpose of the preconstruction conference will be: 1. To review the initial progress schedule; 2. To establish a working understanding among the various parties associated or affected by the work; 3. To establish and review procedures for progress payment, notifications, approvals, submittals, etc.; 4. To establish normal working hours for the work; 5. To review safety standards and traffic control; and 6. To discuss such other related items as may be pertinent to the work. The Contractor shall prepare and submit at the preconstruction conference the following: 1. A breakdown of all lump sum items; 2. A preliminary schedule of working drawing submittals, if applicable; and 3. A list of material sources for approval, if applicable. DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 City of Bremerton 233-1896-178 Downtown Bicycle Pedestrian Circulation Improvements II-34 May 2021 Contract Documents Division 1 Add the following new section: 1-08.0(2) Hours of Work (New Section) Hours of work for improvements located on Kitsap Transit property shall be limited to 12AM to 5AM. These improvements include 22LF of bike lane pavement markings and 1 sign. The City expects this work to take less than 3 days. A 10-day notice shall be provided to the City before work starts. See Appendix E for delineation of the work area and a letter from the City of Bremerton outlining the requirements. For all other work the following requirements apply: Except in the case of emergency or unless otherwise approved by the Engineer, the normal working hours for the Contract shall be any consecutive 8-hour period between 7:00 a.m. and 6:00 p.m. Monday through Friday, exclusive of a lunch break. If the Contractor desires different than the normal working hours stated above, the request must be submitted in writing prior to the preconstruction conference, subject to the provisions below. The working hours for the Contract shall be established at or prior to the preconstruction conference. All working hours and days are also subject to local permit and ordinance conditions (such as noise ordinances). If the Contractor wishes to deviate from the established working hours, the Contractor shall submit a written request to the Engineer for consideration. This request shall state what hours are being requested, and why. Requests shall be submitted for review no later than 5 days prior to the day(s) the Contractor is requesting to change the hours. If the Contracting Agency approves such a deviation, such approval may be subject to certain other conditions, which will be detailed in writing. For example: 1. On non-Federal aid projects, requiring the Contractor to reimburse the Contracting Agency for the costs in excess of straight-time costs for Contracting Agency representatives who worked during such times. (The Engineer may require designated representatives to be present during the work. Representatives who may be deemed necessary by the Engineer include, but are not limited to: survey crews; personnel from the Contracting Agency’s material testing lab; inspectors; and other Contracting Agency employees or third party consultants when, in the opinion of the Engineer, such work necessitates their presence.) 2. Considering the work performed on Saturdays, Sundays, and holidays as working days with regard to the contract time. 3. Considering multiple work shifts as multiple working days with respect to contract time even though the multiple shifts occur in a single 24-hour period. 4. If a 4-10 work schedule is requested and approved the non working day for the week will be charged as a working day. 5. If Davis Bacon wage rates apply to this Contract, all requirements must be met and recorded properly on certified payroll. DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 City of Bremerton 233-1896-178 Downtown Bicycle Pedestrian Circulation Improvements II-35 May 2021 Contract Documents Division 1 1-08.3 Progress Schedule 1-08.3(2) Progress Schedule Types 1-08.3(2)A Type A Progress Schedule (March 13, 2012 APWA GSP) Revise this section to read: The Contractor shall submit three copies of a Type A Progress Schedule no later than at the preconstruction conference, or some other mutually agreed upon submittal time. The schedule may be a critical path method (CPM) schedule, bar chart, or other standard schedule format. Regardless of which format used, the schedule shall identify the critical path. The Engineer will evaluate the Type A Progress Schedule and approve or return the schedule for corrections within 15 calendar days of receiving the submittal. 1-08.4 Prosecution of Work Delete Section 1-08.4 in its entirety, and replace it with the following: 1-08.4 Notice to Proceed and Prosecution of Work Notice to Proceed will be given after the contract has been executed and the contract bond and evidence of insurance have been approved and filed by the Contracting Agency. The Contractor shall not commence with the work until the Notice to Proceed has been given by the Engineer. The Contractor shall commence construction activities on the project site within ten days of the Notice to Proceed Date, unless otherwise approved in writing. The Contractor shall diligently pursue the work to the physical completion date within the time specified in the contract. Voluntary shutdown or slowing of operations by the Contractor shall not relieve the Contractor of the responsibility to complete the work within the time(s) specified in the contract. No other work shall be performed on the site until a COVID-19 Health and Safety Plan (CHSP) has been prepared in accordance with Section 1-07.4(2) as supplemented in these specifications, COVID-19 Health and Safety Plan (CHSP). 1-08.5 Time for Completion Section 1-08.5 is supplemented with the following: (March 13, 1995 WSDOT GSP, Option 7) This project shall be physically completed within *** 35 *** working days. Revise the third paragraph to read: Contract time shall begin on the first working day that construction activities commence on the project site but no later than 5 days following the Notice to Proceed Date. 1-08.6 Suspension of Work Section 1-08.6 is supplemented with the following: DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 City of Bremerton 233-1896-178 Downtown Bicycle Pedestrian Circulation Improvements II-36 May 2021 Contract Documents Division 1 Contract time may be suspended for procurement of critical materials (Procurement Suspension). In order to receive a Procurement Suspension, the Contractor shall within 21 calendar days after execution by the Contracting Agency, place purchase orders for all materials deemed critical by the Contracting Agency for physical completion of the contract. The Contractor shall provide copies of purchase orders for the critical materials. Such purchase orders shall disclose the purchase order date and estimated delivery dates for such critical material. The Contractor shall show procurement of the materials listed below as activities in the Progress Schedule. If the approved Progress Schedule indicates that the materials procurement are critical activities, and if the Contractor has provided documentation that purchase orders are placed for the critical materials within the prescribed 21 calendar days, then contract time will be suspended upon physical completion of all critical work except that work dependent upon the below listed critical materials: *** signal equipment including radar detection and pole fabrication *** Charging of contract time will resume upon delivery of the critical materials to the Contractor or 120 calendar days after execution by the Contracting Agency, whichever occurs first. 1-08.9 Liquidated Damages (March 3, 2021 APWA GSP, Option B) Revise the second and third paragraphs to read: Accordingly, the Contractor agrees: 1. To pay (according to the following formula) liquidated damages for each working day beyond the number of working days established for Physical Completion, and 2. To authorize the Engineer to deduct these liquidated damages from any money due or coming due to the Contractor. Liquidated Damages Formula LD=0.15C/T Where: LD = liquidated damages per working day (rounded to the nearest dollar) C = original Contract amount T = original time for Physical Completion When the Contract Work has progressed to Substantial Completion as defined in the Contract, the Engineer may determine the Contract Work is Substantially Complete. The Engineer will notify the Contractor in writing of the Substantial Completion Date. For overruns in Contract time occurring after the date so established, the formula for liquidated damages shown above will not apply. For overruns in Contract time occurring after the Substantial Completion Date, liquidated damages shall be assessed on the basis of direct engineering and related costs assignable to the project until the actual Physical Completion Date of all the Contract Work. The Contractor shall complete the remaining Work as promptly as possible. Upon request by DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 City of Bremerton 233-1896-178 Downtown Bicycle Pedestrian Circulation Improvements II-37 May 2021 Contract Documents Division 1 the Project Engineer, the Contractor shall furnish a written schedule for completing the physical Work on the Contract. 1-09 MEASUREMENT AND PAYMENT 1-09.6 Force Account (October 10, 2008 APWA GSP) Supplement this section with the following: The Contracting Agency has estimated and included in the Proposal, dollar amounts for all items to be paid per force account, only to provide a common proposal for Bidders. All such dollar amounts are to become a part of Contractor’s total bid. However, the Contracting Agency does not warrant expressly or by implication, that the actual amount of work will correspond with those estimates. Payment will be made on the basis of the amount of work actually authorized by Engineer. 1-09.9 Payments (March 13, 2012 APWA GSP) Delete the first four paragraphs and replace them with the following: The basis of payment will be the actual quantities of Work performed according to the Contract and as specified for payment. The Contractor shall submit a breakdown of the cost of lump sum bid items at the Preconstruction Conference, to enable the Project Engineer to determine the Work performed on a monthly basis. A breakdown is not required for lump sum items that include a basis for incremental payments as part of the respective Specification. Absent a lump sum breakdown, the Project Engineer will make a determination based on information available. The Project Engineer’s determination of the cost of work shall be final. Progress payments for completed work and material on hand will be based upon progress estimates prepared by the Engineer. A progress estimate cutoff date will be established at the preconstruction conference. The initial progress estimate will be made not later than 30 days after the Contractor commences the work, and successive progress estimates will be made every month thereafter until the Completion Date. Progress estimates made during progress of the work are tentative, and made only for the purpose of determining progress payments. The progress estimates are subject to change at any time prior to the calculation of the final payment. The value of the progress estimate will be the sum of the following: 1. Unit Price Items in the Bid Form—the approximate quantity of acceptable units of work completed multiplied by the unit price. 2. Lump Sum Items in the Bid Form—based on the approved Contractor’s lump sum breakdown for that item, or absent such a breakdown, based on the Engineer’s determination. DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 City of Bremerton 233-1896-178 Downtown Bicycle Pedestrian Circulation Improvements II-38 May 2021 Contract Documents Division 1 3. Materials on Hand—100 percent of invoiced cost of material delivered to Job site or other storage area approved by the Engineer. 4. Change Orders—entitlement for approved extra cost or completed extra work as determined by the Engineer. Progress payments will be made in accordance with the progress estimate less: 1. Retainage per Section 1-09.9(1), on non FHWA-funded projects; 2. The amount of progress payments previously made; and 3. Funds withheld by the Contracting Agency for disbursement in accordance with the Contract Documents. Progress payments for work performed shall not be evidence of acceptable performance or an admission by the Contracting Agency that any work has been satisfactorily completed. The determination of payments under the contract will be final in accordance with Section 1-05.1. 1-09.9(1) Retainage Section 1-09.9(1) content and title is deleted and replaced with the following: (June 27, 2011 WSDOT GSP) 1-09.9(1) Vacant 1-09.11 Disputes and Claims 1-09.11(3) Time Limitation and Jurisdiction (November 30, 2018 APWA GSP) Revise this section to read: For the convenience of the parties to the Contract it is mutually agreed by the parties that any claims or causes of action which the Contractor has against the Contracting Agency arising from the Contract shall be brought within 180 calendar days from the date of final acceptance (Section 1-05.12) of the Contract by the Contracting Agency; and it is further agreed that any such claims or causes of action shall be brought only in the Superior Court of the county where the Contracting Agency headquarters is located, provided that where an action is asserted against a county, RCW 36.01.050 shall control venue and jurisdiction. The parties understand and agree that the Contractor’s failure to bring suit within the time period provided, shall be a complete bar to any such claims or causes of action. It is further mutually agreed by the parties that when any claims or causes of action which the Contractor asserts against the Contracting Agency arising from the Contract are filed with the Contracting Agency or initiated in court, the Contractor shall permit the Contracting Agency to have timely access to any records deemed necessary by the Contracting Agency to assist in evaluating the claims or action. DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 City of Bremerton 233-1896-178 Downtown Bicycle Pedestrian Circulation Improvements II-39 May 2021 Contract Documents Division 1 1-09.13 Claims Resolution 1-09.13(3) Claims $250,000 or Less (October 1, 2005 APWA GSP) Delete this section and replace it with the following: The Contractor and the Contracting Agency mutually agree that those claims that total $250,000 or less, submitted in accordance with Section 1-09.11 and not resolved by nonbinding ADR processes, shall be resolved through litigation unless the parties mutually agree in writing to resolve the claim through binding arbitration. 1-09.13(3)A Administration of Arbitration (November 30, 2018 APWA GSP) Revise the third paragraph to read: The Contracting Agency and the Contractor mutually agree to be bound by the decision of the arbitrator, and judgment upon the award rendered by the arbitrator may be entered in the Superior Court of the county in which the Contracting Agency’s headquarters is located, provided that where claims subject to arbitration are asserted against a county, RCW 36.01.050 shall control venue and jurisdiction of the Superior Court. The decision of the arbitrator and the specific basis for the decision shall be in writing. The arbitrator shall use the Contract as a basis for decisions. 1-10 TEMPORARY TRAFFIC CONTROL 1-10.2 Traffic Control Management 1-10.2(1) General Section 1-10.2(1) is supplemented with the following: (January 3, 2017 WSDOT GSP, Option 1) Only training with WSDOT TCS card and WSDOT training curriculum is recognized in the State of Washington. The Traffic Control Supervisor shall be certified by one of the following: The Northwest Laborers-Employers Training Trust 27055 Ohio Ave. Kingston, WA 98346 (360) 297-3035 Evergreen Safety Council 12545 135th Ave. NE Kirkland, WA 98034-8709 1-800-521-0778 The American Traffic Safety Services Association 15 Riverside Parkway, Suite 100 Fredericksburg, Virginia 22406-1022 DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 City of Bremerton 233-1896-178 Downtown Bicycle Pedestrian Circulation Improvements II-40 May 2021 Contract Documents Division 1 Training Dept. Toll Free (877) 642-4637 Phone: (540) 368-1701 1-10.2(2) Traffic Control Plans Section 1-10.2(2) is supplemented with the following: Development of Temporary Traffic Control Plan Development of a Temporary Traffic Control Plan shall be the responsibility of the Contractor. Costs for the Temporary Traffic Control Plan shall be included in the lump sum costs for “Project Temporary Traffic Control”. Applicable WSDOT Standard Plans are acceptable for the Contractors use in developing this Plan. The Contractor shall submit his Temporary Traffic Control Plan for the Engineer’s review five working days prior to the Preconstruction Meeting. The Engineer shall review the Plan and at the Preconstruction Meeting give written approval or discuss the revisions required. Subsequent reviews or revisions, if required, shall be accomplished by the Engineer within 5 working days after submittal. No work shall be undertaken until the Contractor has written approval of the Temporary Traffic Control Plan. Single lane closures are allowed using one lane, two-way traffic control with flaggers per WSDOT standard Plan TC1. Where two travel lanes in the same direction or a center turn lane exist, single lane closure may be performed per WSDOT Standard Plan TC3 Single-Lane Closure for Multi-Lane Roadways. Lane closures are not allowed weekdays between the hours of 6:30 AM and 7:30 AM and 3:30 PM to 5:00 PM. 1-10.4 Measurement 1-10.4(1) Lump Sum Bid for Project (No Unit Items) Section 1-10.4(1) is supplemented with the following: (August 2, 2004 WSDOT GSP) The proposal contains the item “Project Temporary Traffic Control,” lump sum. The provisions of Section 1-10.4(1) shall apply. END OF DIVISION 1 DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 City of Bremerton 233-1896-178 Downtown Bicycle Pedestrian Circulation Improvements II-41 May 2021 Contract Documents Division 2 DIVISION 2 EARTHWORK 2-02 REMOVAL OF STRUCTURES AND OBSTRUCTIONS 2-02.1 Description Section 2-02.1 is supplemented with the following: Removal shall include but not be limited to all items indicated on the Plans including removal of signs, signposts, sign foundations, concrete sidewalk, and brick pavers. 2-02.3 Construction Requirements Section 2-02.3 is supplemented with the following: Removed signposts in cement concrete pavement shall be cut flush with the pavement surface and ground smooth. All voids shall be patched with grout. Signposts and foundations located in brick paver locations shall be removed entirely. Brick pavers shall be salvaged and reinstalled. Voids resulting from the foundation removal shall be filled backfilled with cement concrete. Removed signs and uncut signposts shall be salvaged to the City. Cut signposts shall be disposed of by the Contractor. 2-02.3(3) Removal of Pavement, Sidewalks, Curbs, and Gutters Section 2-02.3(3) is supplemented with the following: The approximate thickness of the brick pavers is 3 inches. The thickness of the cement concrete slab under the brick pavers is approximately 12 inches. Saw cutting of existing Portland cement concrete or Portland cement concrete pavement shall occur prior to the removal of the existing paved surfaces to assure even edges. To expedite construction, the Contractor may break pavement with a backhoe, jack hammer, or similar piece of equipment provided the width is less than the final paving limits. Removal of pavement in this manner is for the Contractor’s convenience and is considered incidental to removal. Before the pavement restoration, the Contractor shall perform a final (second) saw cut. Any pavement that is damaged by breaking the concrete shall be removed by saw cutting and replacing the damaged portions. Contractor shall exercise care in removal of existing improvements to prevent damage from construction activities or equipment. This shall include damage from vibration equipment such as jack hammers. In particular, the Contractor shall protect existing sidewalks, curbs, gutters, and utility pole foundations due to construction activities in the roadway. DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 City of Bremerton 233-1896-178 Downtown Bicycle Pedestrian Circulation Improvements II-42 May 2021 Contract Documents Division 2 2-02.4 Vacant Section 2-02.4 is deleted in its entirety and replaced with the following: 2-02.4 Measurement “Sign Removal and Pavement Restoration” shall be measured per lump sum. 2-02.5 Payment Section 2-02.5 is replaced with the following: “Sign Removal and Pavement Restoration”, per lump sum. The lump sum Contract price for “Sign Removal and Pavement Restoration” shall be full compensation for the work including saw-cutting, excavation, haul, concrete, grout, mortar, reinstalling salvaged brick pavers, and furnishing and installing new brick pavers. END OF DIVISION 2 DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 City of Bremerton 233-1896-178 Downtown Bicycle Pedestrian Circulation Improvements II-43 May 2021 Contract Documents Division 8 DIVISION 8 MISCELLANEOUS CONSTRUCTION 8-02 ROADSIDE RESTORATION 8-02.1 Description Section 8-02.1 is supplemented with the following: This Work shall consist of backfilling and grading restoration areas in the existing planted medians, application of bark mulch, reinstalling landscaping features and raking to provide a smooth transition to surrounding areas. 8-02.4 Measurement Supplement Section 8-02.4 with the following: “Landscape Restoration” shall be measured per lump sum. 8-02.5 Payment Supplement Section 8-02.4 with the following: “Landscape Restoration”, per lump sum. The lump sum contract price for “Landscape Restoration” shall include all costs for restoration of the work areas to a neat and tidy condition that matches the original condition to the greatest extent practicable as determined by the Engineer. 8-04 CURBS, GUTTERS, AND SPILLWAYS 8-04.3 Construction Requirements 8-04.3(1) Cement Concrete Curbs, Gutters, and Spillways Add the following new section: 8-04.3(1)C Painted Curb (New Section) As described on the plans, the Contractor shall apply curb paint to existing concrete Traffic Curb as indicated on the Plans. The curb is to be painted with two full coats of paint in the color specified on the Plans. The red color shall match Federal Standard 595, color number 11136, and the tolerance of variation shall match that shown in the FHWA “Highway Red Color Tolerance Chart”. When paint is required to match a Federal Standard 595 color, the paint manufacturer or the Contractor may obtain a sample of the required color through the following internet link: www.colorserver.net. Minimum standards for painting of curbs shall conform to Section 8-07.3(2). The work shall include preparation for painting such as removing organics, removing peeling, loose, or chipping existing paint, and ensuring a clean paintable DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 City of Bremerton 233-1896-178 Downtown Bicycle Pedestrian Circulation Improvements II-44 May 2021 Contract Documents Division 8 surface. Any loose material generated shall be vactored out of the gutter line and disposed of appropriately. At no time shall it be allowed to wash into the stormwater system. 8-04.4 Measurement Section 8-04.4 is supplemented with the following: “Red Painted Curb” will be measured per linear foot. 8-04.5 Payment Section 8-04.5 is supplemented with the following: “Red Painted Curb”, per linear foot. This work includes, but is not limited to, applying two coats of curb paint, removing organics, treating petroleum stains, ensuring a clean paintable surface, applying glass traffic paint beads, and clean-up. 8-09 RAISED PAVEMENT MARKERS 8-09.3 Construction Requirements Section 8-09.3 is supplemented with the following: Install temporary cold-applied pre-formed tape edge line or “stick and stomps” as temporary lane markings as needed at the end of each shift following RPM removal and prior to installation of new RPMs. If the new RPMs are installed before the end of the shift, temporary tape is not required. 8-09.3(2) Surface Preparation Section 8-09.3(2) is supplemented with the following: RPMs to be removed shall be obliterated until blemishes caused by the RPM removal conform to the coloration of the adjacent pavement. Hydro-blasting shall be used to remove the RPMs as the only method allowed. If in the opinion of the Engineer, the pavement is materially damaged by the RPM removal, such damage shall be repaired by the Contractor in accordance with Section 1-07.13(4). All costs associated with the removal of existing RPMs shall be included in the bid item “Hydroblasting Existing Pavement Markings”. DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 City of Bremerton 233-1896-178 Downtown Bicycle Pedestrian Circulation Improvements II-45 May 2021 Contract Documents Division 8 8-14 CEMENT CONCRETE SIDEWALKS 8-14.1 Description Section 8-14.1 is supplemented with the following: This work includes detectable warning surface and restoration of pavement removal areas associated with removed signs and installation of the new signs, RRFBs, pedestrian push button poles, and conduit. Restoration materials include cement concrete, mortar, CSTC, cement concrete sidewalk, curb ramp restoration, and brick pavers as shown on the Plans. 8-14.3 Construction Requirements Section 8-14.3 is supplemented with the following: Brick pavers from removal areas shall be salvaged if possible and reinstalled. New brick pavers matching the existing pavers shall be furnished and installed. Pavers shall be set in a bed of mortar and joints shall be filled in the same manner as existing pavers. Add the following new subsection: 8-14.3(6) Curb Ramps (New Section) In the event that curb ramps or curb ramp wings are disturbed and require restoration, the ramps and/or wings shall be restored so that the completed curb ramps meet all ADA requirements. Curb ramps shall be constructed separately from the adjacent triangular shaped transition areas and sidewalk to produce a definite break line between grade changes. All curb ramps shall have a detectable warning pattern installed in accordance with the manufacturer’s written instructions. The Contractor shall notify the Engineer three (3) working days in advance of placing concrete for each curb ramp for layout and formwork inspection. The Contractor shall not place concrete in a sidewalk ramp until the Engineer has either inspected and accepted the layout or waived the layout inspection. Where existing sidewalk ramp(s) is/are to be replaced, including adjacent sidewalk, the Contractor shall complete the required replacement per intersection corner within one week of beginning concrete demolition and removal. Special care shall be taken to assure that the ramps are constructed to meet the requirements. The following requirements shall apply to all curb ramps: 1. Truncated Domes shall be placed on the bottom two feet of the ramp. 2. The landing length shall be a minimum of 48 inches. 3. The cross slope of the landing or ramp shall not be steeper than 2%. 4. The longitudinal slope (up or down) of the ramps shall not exceed 8%. 5. The Flare Side Slopes shall not exceed 10%. DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 City of Bremerton 233-1896-178 Downtown Bicycle Pedestrian Circulation Improvements II-46 May 2021 Contract Documents Division 8 Compliance with ADA Standards is taken very serious and minor modifications to the dimensions shown on the Plans may be required to meet current standards. Therefore, prior to pouring concrete at the curb ramp locations, the Contractor shall check the forms to verify ADA compliance, have each ramp inspected by the Engineer, and receive written approval from the Engineer that the forms are set in compliance with ADA Standards. Ramps poured without written approval, that do not meet current ADA Standards shall be removed and replaced at the Contractor’s expense, regardless of whether or not they conform to the dimensions shown on the Plans. Concrete which is not placed such that the finished surface is a flat and uniform plane may result in non-compliance to the ADA standards and shall be removed and replaced at the Contractors expense. 8-14.4 Measurement Section 8-14.4 is supplemented with the following “Pavement Restoration” shall be measured per lump sum. 8-14.5 Payment Section 8-14.5 is replaced with the following: “Pavement Restoration”, per lump sum. The lump sum Contract price for “Pavement Restoration” shall be full compensation for the work including excavation, haul, concrete, grout, mortar, cement concrete sidewalk, curb ramp and wing restoration, reinstalling salvaged brick pavers, and furnishing and installing new brick pavers. “Detectable Warning Surface”, per each. The per each Contract price for “Detectable Warning Surface” shall be full compensation for the work including excavation, haul, concrete, grout, mortar, and furnishing and installing detectable warning surface. 8-20 ILLUMINATION, TRAFFIC SIGNAL SYSTEMS, INTELLIGENT TRANSPORTATION SYSTEMS, AND ELECTRICAL 8-20.1 Description Section 8-20.1 is supplemented with the following: Electrical work shall include the following: 1. Relocation of one existing central business district double-fixture light and associated conduit as shown in the Plans. DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 City of Bremerton 233-1896-178 Downtown Bicycle Pedestrian Circulation Improvements II-47 May 2021 Contract Documents Division 8 2. Provision and installation of Wavetronix Bicycle Detection Equipment (including wire) on existing signal poles as shown in the plans, as directed by the Engineer, and in Appendix F. 3. Installation of Rectangular Rapid Flashing Beacons (RRFBs), push buttons, concrete foundations, conduit, solar panels, control cabinets, and j-boxes as shown on the Plans and in Appendix F. Appendix F contains information for Carmanah equipment, which meets the minimum project requirements with the exception of the pedestrian push buttons, which shall be Campbell Guardian as described in Special Provisions Section 9-29.19. Substitutions for the Carmanah equipment are acceptable if they are approved equal. Approved equal means the equipment meets the minimum specifications contained in these Special Provisions including performance, function, and warranty. The locations for these items shown on the Plans are approximate. RRFB poles with pedestrian push buttons and pedestrian push button poles shall be located according to the Manual of Uniform Traffic Control Devices for Streets and Highways (MUTCD; current edition) Figure 4E-4 and WSDOT ADA Field Guide for Accessible Public Rights of Way (current edition). These locations shall meet the reach range requirements from clear space for wheelchair users as described in the WSDOT ADA Field Guide. The Contractor shall mark the pole locations in the field for approval by the Engineer prior to construction. 4. Connections to existing controller and service cabinets for the new equipment as shown on the Plans. 5. Abandoning an existing vehicle detection loop and installation of a new vehicle detection loop. 8-20.1(1) Regulations and Code Section 8-20.1(1) is supplemented with the following: All material and work shall conform to the requirements of: 1. Latest adopted (by Washington State) edition of the National Electrical Code (NEC). 2. Laws, Rules, and Regulations for Installing Electric Wires and Equipment, Department of Labor and Industries, State of Washington (L&I). 3. National Electrical Manufacturers Association (NEMA). 4. American Society for Testing and Materials (ASTM). 5. Illumination Engineering Society (IES). 6. American Standards Association (ASA). 7. American National Standards Institute (ANSI). 8. Washington State Department of Transportation Standard Specifications for Road, Bridge and Municipal Construction 2021 (Standard Specifications). DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 City of Bremerton 233-1896-178 Downtown Bicycle Pedestrian Circulation Improvements II-48 May 2021 Contract Documents Division 8 9. Washington State Department of Transportation Standard Plans for Road, Bridge and Municipal Construction, latest edition (Standard Plans). 10. City of Bremerton Standards for Work in Rights-of-Way, Division 7 – Street Lighting, and Division 8 – Traffic Signalization. 11. All applicable provisions of the Revised Code of Washington (RCW) and the Washington Administrative Code (WAC), particularly those addressing the requirements for excavation and installation of underground utilities. 12. Puget Sound Energy (Puget Power). Prior to start of work, all necessary licenses, permits, and approvals shall be obtained. The Contractor shall comply with all laws, ordinances, rules, orders, and regulations relating to the performance of the work, the protection of adjacent property, and the maintenance of all other facilities. The Contractor will be required to comply with all the provisions of these instruments and shall save and hold the City of Bremerton harmless from any damage which may be incurred as a result of the Contractor’s failure to comply with all the terms of these permits. The Contractor is advised that an Electric Work Permit from the State Department of Labor and Industries shall be required for this project. City of Bremerton Standards In general, all work and materials shall conform to the City of Bremerton Standards, City of Bremerton Standard Drawings, the 2021 WSDOT Standard Specifications, and the WSDOT Standard Plans. Where conflict between these City of Bremerton Standards and Drawings and the WSDOT Standard Specifications or WSDOT Standard Plans occurs, the City of Bremerton Standards shall take precedence. Specific requirements contained in the text of these Special Provisions and on the Plans shall take precedence over both the WSDOT Standard Specifications and the City of Bremerton Standards. 8-20.2 Materials Section 8-20.2 is supplemented with the following: Materials shall be as specified in Section 9-29 of the Standard Specifications and Section 9-29 of these Special Provisions. All materials shall be furnished by the Contractor. Rapid Flashing Beacons Rapid Flashing Beacon (RFB) indications shall comply with the dimensional, operational, and flash pattern requirements of Federal Highway Administration (FHWA) Interim Approval 21 (IA-21, Conditions 4, 5, and 6, excluding Condition 5f; (https://mutcd.fhwa.dot.gov/resources /interim_approval/ia21/index.htm). RFB systems shall be capable of providing, at a minimum, the following two-channel flashing patterns: 1. NEMA Standard 50-50: • Channel one is ON and channel two is OFF for 0.5 seconds. • Channel one is OFF and channel two is ON for 0.5 seconds. DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 City of Bremerton 233-1896-178 Downtown Bicycle Pedestrian Circulation Improvements II-49 May 2021 Contract Documents Division 8 (Cycle repeats; the total flashing pattern cycle length is 1.00 second.) 2. RFB “WW+S” Pattern (IA-21 Condition 5b): • Channel one is ON and channel two is OFF for 0.05 seconds. • Both channels are OFF for 0.05 seconds. • Channel one is OFF and channel two is ON for 0.05 seconds. • Both channels are OFF for 0.05 seconds. • Channel one is ON and channel two is OFF for 0.05 seconds. • Both channels are OFF for 0.05 seconds. • Channel one is OFF and channel two is ON for 0.05 seconds. • Both channels are OFF for 0.05 seconds. • Both channels are ON for 0.05 seconds. • Both channels are OFF for 0.05 seconds. • Both channels are ON for 0.05 seconds. • Both channels are OFF for 0.25 seconds. (Cycle repeats; the total flashing pattern cycle length is 0.80 seconds.) The flashing pattern shall be user-selectable in the field. RFB system pushbuttons shall include a locator tone, tactile arrows, speech messages, and vibrotactile indications. RFB system pushbuttons shall use a 9-inch by 12-inch R10-25 sign. The R10-25 sign may include integral yellow warning lights. 8-20.2(1) Equipment List and Drawings Section 8-20.2(1) is supplemented with the following: The Contractor shall be required to submit product data for the RRFBs, pedestrian push buttons, j-boxes, Wavetronix Equipment, conduit, and other appurtenances. Approval of shop drawings will require up to 14 calendar days from the date the Engineer receives the drawings until they are returned to the Contractor. The actual time required for approval is dependent upon the completeness and appropriateness of the drawings as submitted. Any deficiencies will require additional time for approval based on the degree of the deficiency and the additional review time required. If the shop drawings are returned to the Contractor to correct deficiencies, an additional 30 calendar days may be required for the approval process. If more than 14 calendar days are required for routine approval of shop drawings that are completed and accurate, the Contractor will be granted an extension of time equal to the additional review time. All electrical materials for review shall be included in a single submittal. DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 City of Bremerton 233-1896-178 Downtown Bicycle Pedestrian Circulation Improvements II-50 May 2021 Contract Documents Division 8 Materials not approved by the Engineer will not be permitted on the job site. 8-20.3 Construction Requirements 8-20.3(1) General Section 8-20.3(1) is supplemented with the following: Prior to installation of Wavetronix Bicycle Detection Equipment location must be approved by Engineer. All equipment shall be handled and protected so as to prevent damage. Damaged equipment, if any, shall be repaired or replaced by the Contractor to the satisfaction of the Engineer at no additional cost to the Owner. No new facilities shall be installed as part of this Contract that are in conflict with any existing utilities, or the code required thereby. It shall be the Contractor’s responsibility to locate all utilities whether above, on, or below the ground, and to protect against any and all damages arising from work under this project. At least 48 hours before digging, the Contractor shall call the Utilities Underground Locator Center (telephone: 1-800-424-5555). Contractor must maintain locates during the duration of the project once they have been identified. The Contractor is advised that safe wiring labels required by the State of Washington Department of Labor and Industries shall apply on this project. All manufacturers’ warranties or guarantees on all electrical and mechanical equipment, consistent with those provided as customary trade practice, shall be assigned to the City of Bremerton. 8-20.3(2) Excavating and Backfilling Section 8-20.3(2) is supplemented with the following: Backfill for trenches in paved areas shall consist of controlled density fill (CDF). Backfill in landscape areas may consist of select native backfill from the excavation providing that such material is free of organic material, clay, or other deleterious material. All trenches in landscape areas shall be mechanically compacted by a power operated mechanical tamper or other mechanical compaction device approved by the Engineer. Compaction shall be in conformance with Section 2-30.3(14), Method C of the Standard Specifications. The temporary restoration of conduit trenches shall be as directed by the Engineer. The Contractor warrants and represents awareness of the statutory provisions contained in RCW 19.122.010 through 19.122.900, that the Contractor has read and fully understands the same, and will comply with the requirements of these provisions which are incorporated by reference herein. The Contractor agrees that all trenching as well as excavating for all pole foundations shall be an “excavation” as defined under RCW Chapter 19.122 and that such utilities constitute underground facilities. The parties agree that remedies affected under RCW Chapter 19.122 are also incorporated by reference herein. Any cost to the Contractor as a result of this law shall be at the Contractor’s expense. DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 City of Bremerton 233-1896-178 Downtown Bicycle Pedestrian Circulation Improvements II-51 May 2021 Contract Documents Division 8 8-20.3(4) Foundations Section 8-20.3(4) is supplemented with the following: Each concrete foundation shall be constructed in a single pour. Where the pole is located in the sidewalk area, the foundation shall be poured to the top of the sidewalk subgrade; and the sidewalk shall be installed in a separate pour. Where the pole is not located in the sidewalk area, the foundation shall include a cement concrete pad set flush with adjacent grades per the details on the Plans. Construction of the signal pole foundations may require special procedures due to depth, groundwater, and soil conditions, and proximity of existing underground utilities. The Contractor shall consider this in his lump sum bid price for the installation of the various electrical systems and no additional compensation will be paid if special procedures are necessary to properly construct the foundations. 8-20.3(5) Conduit Section 8-20.3(5) is supplemented with the following: Galvanized rigid steel conduit shall be used at the following locations: 1. All conduit above ground. 2. All conduit between the pole foundation and the adjacent junction box. Schedule 40 rigid PVC conduit shall be used at all other locations except that a run out of a junction box that goes to another junction box, shall be rigid metallic galvanized steel regardless of conduit type used for the remainder of the run. See City of Bremerton standards. Each empty conduit run shall contain a 200-pound breaking strength polyolefin pull cord, which shall be tied off at both ends. The size of conduit shall be as shown on the Plans. All galvanized conduit in contact with concrete shall be wrapped with 2-inch-wide, 10-mil-thick electrical tape, half-lapped. All conduit installed underground shall have polyethylene Underground Hazard Marking Tape, 6 inches wide, red, legend “Caution-Electric Line Buried Below,” placed approximately 12 inches above the conduit. 8-20.3(6) Junction Boxes, Cable Vaults, and Pull Boxes Section 8-20.3(6) is supplemented with the following: Junction box locations shown in the Plans are approximate and shall be adjusted by the Contractor to fit existing conditions. No junction boxes shall be located in pedestrian ramp areas. See City of Bremerton Standards and Standard Drawings. DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 City of Bremerton 233-1896-178 Downtown Bicycle Pedestrian Circulation Improvements II-52 May 2021 Contract Documents Division 8 8-20.3(9) Bonding, Grounding Section 8-20.3(9) is supplemented with the following: The illumination systems shall be bonded and grounded in accordance with City of Bremerton Standard Drawings 7010 and 7012. Grounding bushings, where required, shall be OZ Gedney, Type HLBG or Thomas & Betts, Blackjack Type BG. 8-20.3(11) Testing Section 8-20.3(11) is supplemented with the following: Testing for the new illumination system shall be in accordance with Section 7-20.9 of the City of Bremerton Standards. 8-20.3(14) Signal Systems Section 8-20.3(14) is supplemented with the following: Wavetronix bicycle detection radar equipment for bicycles shall be installed as shown on the Plans in conformance with City of Bremerton standards and the details on the Plans. 8-20.4 Measurement Section 8-20.4 is supplemented with the following: Measurement for the bid item “Wavetronix Bicycle Detection Radar” will be by lump sum. Measurement will include the following: a. Furnishing and installing all new bicycle detection radar equipment as shown on the Plans. Measurement for the bid item “Relocate Luminaire” will be by lump sum. Measurement will include the following: a. Relocating existing luminaire as shown on the Plans. b. Installing wire and conduit including moling beneath crosswalk. c. Demolishing existing light pole foundation. Measurement for the bid item “Rectangular Rapid Flashing Beacon (RRFB) System” will be per lump sum. Measurement will include the following: a. Furnishing and installing RRFBs as shown on the Plans b. Furnishing and installing pedestrian push buttons, conduit, and j-boxes as shown in the Plans. DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 City of Bremerton 233-1896-178 Downtown Bicycle Pedestrian Circulation Improvements II-53 May 2021 Contract Documents Division 8 8-20.5 Payment Section 8-20.5 is supplemented with the following: Payment will be made under the following: “Wavetronix Bicycle Detection Radar”, per lump sum. “Relocate Luminaire”, per lump sum. “Rectangular Rapid Flashing Beacon (RRFB) System”, per lump sum. The unit or lump sum Contract prices for “Wavetronix Bicycle Detection Radar”, “Relocate Luminaire”, and “Rectangular Rapid Flashing Beacon (RRFB) System”, shall be full compensation for the costs of all labor, tools, equipment, and materials necessary and incidental to provide fully functioning systems, including but not limited to utility locates, potholing, abandonment of the vehicle detection loop, excavation, haul, backfill, cement concrete, grout, foundations, conduit, utility connections, CDF, wire, wire splicing, connections at existing panels, installation at the pole mast arms, pole penetrations, and seal-tight connectors. 8-21 PERMANENT SIGNING 8-21.1 Description Section 8-21.1 is supplemented with the following: The Work shall include furnishing and installing new signs, signposts, and foundations, and removal and re-installation of existing signs in accordance with the Plans and as directed by the Engineer. Prior to installation of signs, sign locations to be approved by Engineer. 8-21.5 Payment Section 8-21.5 is supplemented with the following: The lump sum contract price for “Permanent Signing” shall include all costs for furnishing and installing new sign foundations, signposts, and signs, and re-installation of existing signs. 8-22 PAVEMENT MARKING 8-22.2 Materials Section 8-22.2 is supplemented with the following: All pavement markings shall be Type A – liquid hot applied thermoplastic or Type B - Pre- Formed Fused Thermoplastic meeting the requirements of Section 9-34.3(1) or 9-34.3(2). Plastic for Bicycle Boxes shall be green color and shall have a minimum skid resistance value of 60 BPN. The Contractor shall provide a color chip submittal for acceptance prior to ordering the material. DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 City of Bremerton 233-1896-178 Downtown Bicycle Pedestrian Circulation Improvements II-54 May 2021 Contract Documents Division 8 8-22.3 Construction Requirements Section 8-22.3 is supplemented with the following: Install temporary cold-applied pre-formed tape edge line as temporary bicycle lane markings and stop bars as needed at the end of each shift following pavement marking removal and prior to installation of new pavement markings. If the new pavement markings are installed before the end of the shift, temporary tape is not required. Removal of existing curb paint as specified on the Plans shall be completed using hydroblasting. 8-22.3(6) Removal of Pavement Markings Section 8-22.3(6) is replaced with the following: Pavement markings to be removed shall be obliterated until blemishes caused by the pavement marking removal conform to the coloration of the adjacent pavement. Hydro-blasting shall be used to remove the painted markings as the only method allowed. If in the opinion of the Engineer, the pavement is materially damaged by the pavement marking removal, such damage shall be repaired by the Contractor in accordance with Section 1-07.13(4). 8-22.4 Measurement Section 8-22.4 is supplemented with the following: “Hydroblasting Existing Pavement Markings” shall be measured per lump sum. “Green Plastic Bike Box” shall be measured per each. “Green Plastic Left Turn Bike Box” shall be measured per each. “White Plastic Parking Markings” shall be measured per lump sum. “3 In. White Plastic Edge Line” shall be measured per linear foot. “4 In. White Plastic Line” shall be measured per linear foot. “4 In. Yellow Plastic Skip Line” shall be measured per linear foot. “6 In. White Plastic Line” shall be measured per linear foot. “6 In. White Plastic Dashed Line” shall be measured per linear foot. “5 Ft. Wide by 3 Ft. Green Plastic Block” shall be measured per square foot. “4 In. Wide by 3 Ft. White Plastic Block” shall be measured per square foot. “12 In. White Plastic Stop Bar” shall be measured per square foot. “Plastic Bicycle Lane Markings” shall be measured per each. “Plastic Shared Lane Marking” shall be measured per each. “Removing Curb Paint” will be measured per linear foot. DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 City of Bremerton 233-1896-178 Downtown Bicycle Pedestrian Circulation Improvements II-55 May 2021 Contract Documents Division 8 8-22.5 Payment Section 8-22.5 is supplemented with the following: “Hydroblasting Existing Pavement Markings”, per lump sum. “Green Plastic Bike Box”, per each. “Green Plastic Left Turn Bike Box”, per each. “White Plastic Parking Markings”, per lump sum. “3 In. White Plastic Edge Line”, per linear foot. “4 In. White Plastic Line”, per linear foot. “4 In. Yellow Plastic Skip Line”, per linear foot. “6 In. White Plastic Line”, per linear foot. “6 In. White Plastic Dashed Line”, per linear foot. “5 Ft. Wide by 3 Ft. Green Plastic Block”, per square foot. “4 In. Wide by 3 Ft. White Plastic Block”, per square foot. “12 In. White Plastic Stop Bar”, per square foot. “Plastic Bicycle Lane Markings”, per each. “Plastic Shared Lane Marking”, per each. “Removing Curb Paint”, per linear foot. Costs for temporary cold-applied pre-formed tape markings shall be included in the unit costs for new pavement markings. END OF DIVISION 8 DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 City of Bremerton 233-1896-178 Downtown Bicycle Pedestrian Circulation Improvements II-56 May 2021 Contract Documents Division 8 This Page Intentionally Left Blank DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 City of Bremerton 233-1896-178 Downtown Bicycle Pedestrian Circulation Improvements II-57 May 2021 Contract Documents Division 9 DIVISION 9 MATERIALS 9-29 ILLUMINATION, SIGNAL, ELECTRICAL 9-29.5 Vacant Section 9-29.5, including title, is replaced with the following: 9-29.5 Rectangular Rapid Flashing Beacon (RRFB) General The intent of the following specification is to provide a complete, solar powered, Rectangular Rapid Flashing Beacon (RRFB) system. The RRFB system shall be designed to operate twenty-four (24) hours per day, seven (7) days per week with the beacons flashing for an average of three hundred (300) cycles per day at twenty (20) seconds per activation. The RRFB system shall be compatible with and activated by a pedestrian pushbutton. Prior to installation of RRFB system, RRFB post and APS post locations must be approved by Engineer. Description This specification describes the minimum acceptable performance and system design for a pedestrian crossing system. The system will be activated on demand by a pedestrian using a pedestrian push button. The system will operate between dawn and dusk without dimming. 1. Requirements The RRFB system shall be solar powered and include all materials noted on the Plans and meeting the requirements of 9-29.15. Each RRFB system shall be comprised of a minimum of two, LED RRFBs and all required equipment, signage, pole, foundation, and incidentals. Rapid Rectangular Beacon (RRFB) signs shall be solar powered Carmanah Blinker Beacon pedestrian crosswalk, or approved equal. Each RRFB system shall include a minimum of two (2) wirelessly connected poles installed on opposite sides of the roadway, as shown on the plans or directed by the Engineer. Each pole shall include a dual horizontal back-to-back LED light arrangement with two pedestrian indicators per side. The flashing pattern shall be user-selectable in the field. The electrical cabinet shall be top-of-pole self-contained control cabinet mounted with a minimum NEMA 3R aluminum enclosure with stainless-steel hardware. The solar panel shall be a minimum of 20-watt 35-Ah battery, or up to a 44-Ah battery. DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 City of Bremerton 233-1896-178 Downtown Bicycle Pedestrian Circulation Improvements II-58 May 2021 Contract Documents Division 9 Vehicle LED Modules shall be 7 inches wide by 3 inches high, two arrays of eight amber LEDs spaced 7 inches apart, SAE J595 class 1 certified. The Pedestrian LED Modules shall be 0.5 inch wide by 1.75 inches high side-viewed, flashing simultaneously with vehicle LED. The unit shall be able to operate in temperatures of -40 degrees F to 122 degrees F. Pedestrian push buttons shall be mounted on the pole to activate the flashing beacons. Pedestrian push buttons shall be compatible with the RRFB system, Guardian Accessible Pedestrian Signal (APS) manufactured by Campbell Company and meeting all Federal and ADA requirements. Installed RRFBs shall wirelessly communicate with adjacent units and shall activate concurrently when operated. Poles shall be 14 feet tall, 4.5 inches in diameter round, schedule 40 aluminum with galvanized hardware. The pole shall meet AASHTO break-away requirements. The foundation shall be per WSDOT Standard Plan J-21.10-04. Other signing on each pole shall include all signing specified in the plan set. The solar power supply shall be power autonomous without need of an external power supply. The batteries shall be sealed, maintenance free, and field-replaceable independently of other components. The battery pack shall have a minimum rated lifespan of three years. The power supply system shall have the capacity to operate the RRFB for 30 days at a normal use of 400 activations of 30 seconds per day without solar charging. The RRFB shall have an automatic light control to provide useful light during extreme conditions that prevent charging over an extended period of time. The manufacturer shall provide documentation for each installation consisting of solar power calculations to verify load, duty cycle, and battery capacity based on location. The solar panel shall be installed at the highest point on the assembly structure, or as directed by the Engineer, and away from the traveled way. The solar panel shall be installed at an angle specified by the manufacturer facing the equator (due south) with a full unobstructed solar exposure for optimum performance of the system, or as recommended by the manufacturer and directed by the Engineer. If batteries are to be installed in a separate cabinet, the cabinet shall be a minimum of seven feet above the ground and located on the post as to be not over the sidewalk, bike path or trail. 9-29.19 Pedestrian Push Buttons Section 9-29.19 is supplemented with the following: Pedestrian push buttons shall be compatible with the RRFB system, Guardian Accessible Pedestrian Signal (APS) manufactured by Campbell Company and meeting all Federal and DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 City of Bremerton 233-1896-178 Downtown Bicycle Pedestrian Circulation Improvements II-59 May 2021 Contract Documents Division 9 ADA requirements. The units shall be yellow. The sign shall be an R10-25. The unit shall include all accessories necessary for proper functioning meeting the specifications: 1. System Operational Requirements: a. Shall meet the intent of the functionality identified and defined in Manual on Uniform Traffic Control Devices, Section 4E part 8-13 Federal Highway Administration, 2009: http://mutcd.fhwa.dot.gov/htm/2009/part4/part4e.htm b. Shall meet The United States Access Board’s Revised Draft Guidelines For Accessible Public Rights-Of-Way, Chapter R3: Technical Provisions Sub Section: R306 Dated: November 23, 2005: https://www.access-board.gov/prowag/draft-2002.html. c. Shall be independent of a central control with a Pedestrian Display to Pedestrian Station ratio of 1:1. d. Shall have confirmation indications at momentary (< 1 second) button activation (Press) via latching LED, sound or verbal “wait”, and optional Vibrotactile bounce. e. Shall provide a verbal location information message with an extended (>1 second) button activation (Press). (“Wait to cross “Street Name” at “cross Street Name”.) f. Shall have a standard locating tone during pedestrian clearance phase (with options of countdown and beaconing). g. Shall provide a verbal walk indication with installations where there is less than ten feet of separation between stations and a rapid percussive tone where there is greater than ten feet of separation between stations. h. Shall have a Vibrotactile indication that has adjustable intensity via USB interface, at the push button during the WALK cycle. i. Shall support a variety of voice messages, languages, tones, and sounds downloadable from indications database via USB interface. j. Shall have all sounds adjust automatically to ambient noise levels over a 60 dB range. i. Shall have a maximum volume of 100 dBA. k. Shall have min and max levels independently set for locator and non-locator indications. l. Shall provide EPAPS (Extended Press Accessible Pedestrian Signals Only) functionality. m. Shall have fail safe operations leading to constant call and play an error message in a fault condition. n. Shall have fail safe operation that reverts to standard push button operation placing a call. o. Shall have time of day functionality providing different operating characteristics for identified time of day. p. Shall have downloadable pedestrian data utility. 2. Mechanical Requirements of the Push Button Station: a. Shall meet The United States Access Board’s Revised Draft Guidelines For Accessible Public Rights-Of-Way, Chapter R3: Technical Provisions Sub Section: R306 Dated: November 23, 2005: https://www.access-board.gov/prowag/draft-2002.html. DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 City of Bremerton 233-1896-178 Downtown Bicycle Pedestrian Circulation Improvements II-60 May 2021 Contract Documents Division 9 b. Shall have a housing of machined aluminum with full gasket matching surfaces. c. Shall have forward facing speaker. d. Shall have removable inserts for sound directionality control. e. Shall have a raised tactile arrow on the push button. f. Shall have a solid-state switch rated at > 100 by 106 operations. g. Shall have a #6 Barrier Terminal connection on station allowing pedestrian station to connect to existing wiring. h. Shall have a cover plate for the Barrier Terminal connections bay. i. Shall be capable of displaying a 5 by 7-3/4-inch sign directly affixed onto the station using mounting screws, without the use of an adapter plate or sign bracket. j. Shall be capable of displaying a 5 by 9 inches, 9 by 12 inches, and 9 by 15-inches sign with the use of an adapter plate and mounting screws. k. Base Station shall have the capability to accept EDPM mounting buttons to conform to all size of poles and flat surfaces. l. Shall have the ability to be programmed while only connected to a USB power source on a device capable of running the software utility. 3. Environmental Requirements for the Push Button Station: a. Shall be fully operational between temperatures of -34°C to +74°C. b. Shall have a weatherproof speaker. 4. Signal Power Interface (SPI): a. Shall have a Signal Power Interface (SPI) installed in the RRFB Controller Enclosure. b. SPI shall interface with RRFB controller per manufacturers requirements. c. SPI shall interface with Pedestrian station via a 6-wire conductor. d. SPI shall have a 6 position; #8 Barrier Terminal connector for the 6-wire conductor cable to be pulled to the pedestrian station. e. Signal Power Interface (SPI) shall operate properly over power sources ranging from 85 Vac to 220 Vac. 5. Environmental Requirements for the Signal Power Interface: a. Shall be fully operational between -34 degrees C to +74 degrees C. b. Shall be fully enclosed in a weatherproof enclosure. 6. Programming and Configuration: a. The Accessible Pedestrian Signal will be configured at the factory for true “Plug and Play” operations. b. Shall have a configuration utility capable of creating reusable templates, flashing software, uploading audio files, and configuring stations. c. Configuration utility shall provide full display readout with integrated hover help menus. DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 City of Bremerton 233-1896-178 Downtown Bicycle Pedestrian Circulation Improvements II-61 May 2021 Contract Documents Division 9 d. The Accessible Pedestrian Signal will be field upgradeable via USB type B connections with free publicly available firmware operating on Windows 7 and newer revisions. e. The Accessible Pedestrian Signal will allow any audible indication in a .wav mono format to be uploaded via USB type B connections with free publicly available firmware operating on Windows 7 and newer revisions. 7. Warranty: a. APS devices shall have a 3-year warranty. (January 13, 2021 WSDOT GSP) STANDARD PLANS The State of Washington Standard Plans for Road, Bridge and Municipal Construction M21-01, effective September 30, 2020, is made a part of this contract. The Standard Plans are revised as follows: A-50.10 DELETED A-50.20 DELETED A-50.30 DELETED A-50.40 DELETED B-90.40 Valve Detail – DELETED C-1a DELETED C-8 Add new Note 5, “5. Type 2 Barrier and Barrier Terminals are allowed in temporary installations only. New Type 2 Barrier and Barrier Terminals are not allowed to be fabricated after December 31, 2019. The plan is provided as a means to verify that any Type 2 barrier and Barrier Terminals fabricated prior to December 31, 2019 meets the plan requirements and cross-sectional dimensions as specified in Standard Specifications 6-10.3(5).” C-8a Add new Note 2, “2. Type 4 Barrier and Barrier Transition are allowed in temporary installations only. New Type 4 Barrier and Barrier Transition are not allowed to be fabricated after December 31, 2019. The plan is provided as a means to verify that any Type 4 barrier and Barrier Transition fabricated prior to December 31, 2019 meets the plan requirements and cross-sectional dimensions as specified in Standard Specifications 6-10.3(5).” DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 City of Bremerton 233-1896-178 Downtown Bicycle Pedestrian Circulation Improvements II-62 May 2021 Contract Documents Division 9 C-8b DELETED C-8e DELETED C-8f DELETED C-16a DELETED C-20.10 The following table is added: SLOPE \ EMBANKMENT TABLE (FOR 8’, 9’, 11’ LONG POSTS) POST LENGTH SLOPE W (FT) 8-FOOT 1H : 1V OR FLATTER 2.5 MIN. 8-FOOT 2H : 1V OR FLATTER 0 (FACE OF BARRIER AT SLOPE BREAK POINT) 9-FOOT 1.5H : 1V OR FLATTER 0 (FACE OF BARRIER AT SLOPE BREAK POINT) 11-FOOT 1H : 1V OR FLATTER 0 (FACE OF BARRIER AT SLOPE BREAK POINT) C-20.11 DELETED C-20.19 DELETED C-40.16 DELETED C-40.18 DELETED C-80.50 DELETED C-85.14 DELETED C-85.15 SECTION B detail, the callout reading “ANCHOR BOLT (TYP.) ~ SEE DETAIL, STANDARD PLAN C-8b”, is revised to read “ANCHOR BOLT (TYP.) ~ SEE DETAIL IN PLANS”. DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 City of Bremerton 233-1896-178 Downtown Bicycle Pedestrian Circulation Improvements II-63 May 2021 Contract Documents Division 9 SECTION B detail, the callout reading “ANCHOR PLATE (TYP.) ~ SEE STANDARD PLAN J- 8b”, is revised to read “ANCHOR PLATE (TYP.) ~ SEE DETAIL IN PLANS”. D-2.14 DELETED D-2.16 DELETED D-2.18 DELETED D-2.20 DELETED D-2.42 DELETED D-2.44 DELETED D-2.46 DELETED D-2.48 DELETED D-2.82 DELETED D-2.86 DELETED D-10.10 Wall Type 1 may be used if no traffic barrier is attached on top of the wall. Walls with traffic barriers attached on top of the wall are considered non-standard and shall be designed in accordance with the current WSDOT Bridge Design Manual (BDM) and the revisions stated in the 11/3/15 Bridge Design memorandum. D-10.15 Wall Type 2 may be used if no traffic barrier is attached on top of the wall. Walls with traffic barriers attached on top of the wall are considered non-standard and shall be designed in accordance with the current WSDOT BDM and the revisions stated in the 11/3/15 Bridge Design memorandum. D-10.30 Wall Type 5 may be used in all cases. DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 City of Bremerton 233-1896-178 Downtown Bicycle Pedestrian Circulation Improvements II-64 May 2021 Contract Documents Division 9 D-10.35 Wall Type 6 may be used in all cases. D-10.40 Wall Type 7 may be used if no traffic barrier is attached on top of the wall. Walls with traffic barriers attached on top of the wall are considered non-standard and shall be designed in accordance with the current WSDOT BDM and the revisions stated in the 11/3/15 Bridge Design memorandum. D-10.45 Wall Type 8 may be used if no traffic barrier is attached on top of the wall. Walls with traffic barriers attached on top of the wall are considered non-standard and shall be designed in accordance with the current WSDOT BDM and the revisions stated in the revisions stated in the 11/3/15 Bridge Design memorandum. D-15.10 STD Plans D-15 series “Traffic Barrier Details for Reinforced Concrete Retaining Walls” are withdrawn. Special designs in accordance with the current WSDOT BDM are required in place of these STD Plans. D-15.20 STD Plans D-15 series “Traffic Barrier Details for Reinforced Concrete Retaining Walls” are withdrawn. Special designs in accordance with the current WSDOT BDM are required in place of these STD Plans. D-15.30 STD Plans D-15 series “Traffic Barrier Details for Reinforced Concrete Retaining Walls” are withdrawn. Special designs in accordance with the current WSDOT BDM are required in place of these STD Plans. G-20.10 SIGN INSTALLATION BEHIND TRAFFIC BARRIER detail, dimension callout “3’ MIN.”, is revised to read “5’ MIN.”. H-70.20 Sheet 2, Spacing Detail, Mailbox Support Type 1, reference to Standard Plan I-70.10 is revised to H-70.10 H-70.30 DELETED J-10.16 Key Note 14, reads: “Mounting Hole ~ See Standard Plan J-10.30 for mounting Details.” Is revised to read: “Mounting Hole ~ See Standard Plan J-10.14 for mounting Details.” General Note 12, reads: “See Standard Plan J-10.30 for pole installation details.” Is revised to read: “See Standard Plan J-10.14 for pole installation details.” J-10.17 Key Note 16, reads: “Mounting Hole ~ See Standard Plan J-10.?? for mounting Details.” Is revised to read: “Mounting Hole ~ See Standard Plan J-10.14 for mounting Details.” DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 City of Bremerton 233-1896-178 Downtown Bicycle Pedestrian Circulation Improvements II-65 May 2021 Contract Documents Division 9 General Note 12, reads: “See Standard Plan J-10.30 for pole installation details.” Is revised to read: “See Standard Plan J-10.14 for pole installation details.” J-10.18 Key Note 12, reads: “Mounting Hole ~ See Standard Plan J-10.20 for mounting Details.” Is revised to read: “Mounting Hole ~ See Standard Plan J-10.14 for mounting Details.” General Note 12, reads: “See Standard Plan J-10.30 for pole installation details.” Is revised to read: “See Standard Plan J-10.14 for pole installation details.” J-20.26 Add Note 1, “1. One accessible pedestrian pushbutton station per pedestrian pushbutton post.” J-20.16 View A, callout, was – LOCK NIPPLE, is revised to read; CHASE NIPPLE J-21.10 Sheet 1, Elevation View, Round Concrete Foundation Detail, callout – “ANCHOR BOLTS ~ ¾” (IN) x 30” (IN) FULL THREAD ~ THREE REQ’D. PER ASSEMBLY” IS REVISED TO READ: “ANCHOR BOLTS ~ ¾” (IN) x 30” (IN) FULL THREAD ~ FOUR REQ’D. PER ASSEMBLY” Sheet 1 of 2, Elevation view (Round), add dimension depicting the distance from the top of the foundation to find 2 #4 reinforcing bar shown, to read; 3” CLR.. Delete “(TYP.)” from the 2 ½” CLR. dimension, depicting the distance from the bottom of the foundation to find 2 #4 reinf. Bar. Sheet 1 of 2, Elevation view (Square), add dimension depicting the distance from the top of the foundation to find 1 #4 reinforcing bar shown, to read; 3” CLR. Delete “(TYP.)” from the 2 ½” CLR. dimension, depicting the distance from the bottom of the foundation to find 1 #4 reinf. Bar. Sheet 2 of 2, Elevation view (Round), add dimension depicting the distance from the top of the foundation to find 2 #4 reinforcing bar shown, to read; 3” CLR. Delete “(TYP.)” from the 2 ½” CLR. dimension, depicting the distance from the bottom of the foundation to find 2 #4 reinf. Bar. Sheet 2 of 2, Elevation view (Square), add dimension depicting the distance from the top of the foundation to find 1 #4 reinforcing bar shown, to read; 3” CLR. Delete “(TYP.)” from the 2 ½” CLR. dimension, depicting the distance from the bottom of the foundation to find 1 #4 reinf. Bar. Detail F, callout, “Heavy Hex Clamping Bolt (TYP.) ~ 3/4” (IN) Diam. Torque Clamping Bolts (see Note 3)” is revised to read; “Heavy Hex Clamping Bolt (TYP.) ~ 3/4” (IN) Diam. Torque Clamping Bolts (see Note 1)” Detail F, callout, “3/4” (IN) x 2’ – 6” Anchor Bolt (TYP.) ~ Four Required (See Note 4)” is revised to read; “3/4” (IN) x 2’ – 6” Anchor Bolt (TYP.) ~ Three Required (See Note 2)” J-21.15 Partial View, callout, was – LOCK NIPPLE ~ 1 ½” DIAM., is revised to read; CHASE NIPPLE ~ 1 ½” (IN) DIAM. J-21.16 Detail A, callout, was – LOCKNIPPLE, is revised to read; CHASE NIPPLE DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 City of Bremerton 233-1896-178 Downtown Bicycle Pedestrian Circulation Improvements II-66 May 2021 Contract Documents Division 9 J-22.15 Ramp Meter Signal Standard, elevation, dimension 4’ - 6” is revised to read; 6’-0” (2x) Detail A, callout, was – LOCK NIPPLE ~ 1 ½” DIAM. is revised to read; CHASE NIPPLE ~ 1 ½” (IN) DIAM. J-28.60 Note 1 “See Standard Plans C-8b and C-85.14 for foundation and anchor bolt details.” is revised to read “See contract for anchor bolt details. See Standard Plan C-85.15 for foundation details.” J-40.10 Sheet 2 of 2, Detail F, callout, “12 – 13 x 1 ½” S.S. PENTA HEAD BOLT AND 12” S. S. FLAT WASHER” is revised to read; “12 – 13 x 1 ½” S.S. PENTA HEAD BOLT AND 1/2” (IN) S. S. FLAT WASHER” J-40.36 Note 1, second sentence; ”Finish shall be #2B for backbox and #4 for the cover.” Is revised to read; ”Finish shall be #2B for barrier box and HRAP (Hot Rolled Annealed and Pickled) for the cover. J-40.37 Note 1, second sentence; ”Finish shall be #2B for backbox and #4 for the cover.” Is revised to read; ”Finish shall be #2B for barrier box and HRAP (Hot Rolled Annealed and Pickled) for the cover. J-75.20 Key Notes, note 16, second bullet point, was: “1/2” (IN) x 0.45” (IN) Stainless Steel Bands”, add the following to the end of the note: “Alternate: Stainless steel cable with stainless steel ends, nuts, bolts, and washers may be used in place of stainless steel bands and associated hardware.” J-81.10 All references to “Type 170 Controller” are replaced with “Controller”. L-40.10 DELETED The following are the Standard Plan numbers applicable at the time this project was advertised. The date shown with each plan number is the publication approval date shown in the lower right-hand corner of that plan. Standard Plans showing different dates shall not be used in this contract. A-10.10-00........8/7/07 A-30.35-00.......10/12/07 A-60.10-03........12/23/14 A-10.20-00......10/5/07 A-40.00-00.........8/11/09 A-60.20-03.........12/23/14 A-10.30-00......10/5/07 A-40.10-04.........7/31/19 A-60.30-01..........6/28/18 A-20.10-00......8/31/07 A-40.15-00.........8/11/09 A-60.40-00..........8/31/07 A-30.10-00......11/8/07 A-40.20-04.........1/18/17 A-30.30-01......6/16/11 A-40.50-02.........12/23/14 DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 City of Bremerton 233-1896-178 Downtown Bicycle Pedestrian Circulation Improvements II-67 May 2021 Contract Documents Division 9 B-5.20-03........9/9/20 B-30.50-03.........2/27/18 B-75.20-02..........2/27/18 B-5.40-02.........1/26/17 B-30.60-00……..9/9/20 B-75.50-01..........6/10/08 B-5.60-02.........1/26/17 B-30.70-04.........2/27/18 B-75.60-00............6/8/06 B-10.20-02........3/2/18 B-30.80-01..........2/27/18 B-80.20-00.........6/8/06 B-10.40-01........1/26/17 B-30.90-02........1/26/17 B-80.40-00.........6/1/06 B-10.70-01……9/9/20 B-35.20-00..........6/8/06 B-85.10-01.........6/10/08 B-15.20-01........2/7/12 B-35.40-00..........6/8/06 B-85.20-00..........6/1/06 B-15.40-01........2/7/12 B-40.20-00..........6/1/06 B-85.30-00..........6/1/06 B-15.60-02........1/26/17 B-40.40-02........1/26/17 B-85.40-00..........6/8/06 B-20.20-02.......3/16/12 B-45.20-01..........7/11/17 B-85.50-01.........6/10/08 B-20.40-04.......2/27/18 B-45.40-01..........7/21/17 B-90.10-00….......6/8/06 B-20.60-03.......3/15/12 B-50.20-00..........6/1/06 B-90.20-00..........6/8/06 B-25.20-02........2/27/18 B-55.20-02..........2/27/18 B-90.30-00..........6/8/06 B-25.60-02.........2/27/18 B-60.20-02..........9/9/20 B-90.40-01..........1/26/17 B-30.05-00……..9/9/20 B-60.40-01..........2/27/18 B-90.50-00..........6/8/06 B-30.10-03.........2/27/18 B-65.20-01..........4/26/12 B-95.20-01..........2/3/09 B-30.15-00……..2/27/18 B-65.40-00..........6/1/06 B-95.40-01..........6/28/18 B-30.20-04.........2/27/18 B-70.20-00..........6/1/06 B-30.30-03.........2/27/18 B-70.60-01..........1/26/17 B-30.40-03..........2/27/18 C-1....................9/9/20 C-20.42-05..........7/14/15 C-70.10-02........9/16/20 C-1b...................9/9/20 C-20.45.02..........8/12/19 C-75.10-02........9/16/20 C-1d................10/31/03 C-22.16-07........9/16/20 C-75.20-02........9/16/20 C-2c..................8/12/19 C-22.40-08........9/16/20 C-75.30-02........9/16/20 C-4f...................8/12/19 C-22.45-05........9/16/20 C-80.10-02........9/16/20 C-6a................10/14/09 C-23.60-04........7/21/17 C-80.20-01........6/11/14 C-7.....................6/16/11 C.24.10-02........8/12/19 C-80.30-01........6/11/14 C-7a...................6/16/11 C-25.20-06........7/14/15 C-80.40-01........6/11/14 C-8.....................2/10/09 C-25.22-05........7/14/15 C-85.10-00........4/8/12 C-8a...................7/25/97 C-25.26-04........8/12/19 C-85.11-01........9/16/20 C-20.10-06.........9/16/20 C-25.30-00…….6/28/18 C-85.15-01........6/30/14 C-20.14-04..........8/12/19 C-25.80-05........8/12/19 C-85.16-01........6/17/14 C-20.15-02..........6/11/14 C-60.10-01…….9/24/20 C-85-18-01........6/11/14 C-20.18-03..........8/12/19 C-60.20-00……9/24/20 C-85.20-01........6/11/14 C-20.40-07..........8/12/19 C-60.30-00……9/24/20 C-20.41-02..........8/12/19 C-60.70-00……9/24/20 D-2.04-00........11/10/05 D-2.80-00........11/10/05 D-6...................6/19/98 D-2.06-01........1/6/09 D-2.84-00........11/10/05 D-10.10-01......12/2/08 D-2.08-00........11/10/05 D-2.88-00........11/10/05 D-10.15-01......12/2/08 D-2.32-00........11/10/05 D-2.92-00........11/10/05 D-10.20-01.........8/7/19 D-2.34-01........1/6/09 D-3.09-00........5/17/12 D-10.25-01.........8/7/19 D-2.36-03........6/11/14 D-3.10-01……5/29/13 D-10.30-00.........7/8/08 D-2.60-00........11/10/05 D-3.11-03……6/11/14 D-10.35-00.........7/8/08 D-2.62-00........11/10/05 D-3.15-02……6/10/13 D-10.40-01......12/2/08 D-2.64-01........1/6/09 D-3.16-02……5/29/13 D-10.45-01......12/2/08 D-2.66-00........11/10/05 D-3.17-02……5/9/16 D-2.68-00........11/10/05 D-4.................12/11/98 DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 City of Bremerton 233-1896-178 Downtown Bicycle Pedestrian Circulation Improvements II-68 May 2021 Contract Documents Division 9 E-1....................2/21/07 E-4....................8/27/03 E-2....................5/29/98 E-4a..................8/27/03 F-10.12-04.......9/24/20 F-10.62-02........4/22/14 F-40.15-04........9/25/20 F-10.16-00.......12/20/06 F-10.64-03........4/22/14 F-40.16-03........6/29/16 F-10.18-02.........9/24/20 F-30.10-04........9/25/20 F-45.10-02........7/15/16 F-10.40-04...........9/24/20 F-40.12-03........6/29/16 F-80.10-04........7/15/16 F-10.42-00.........1/23/07 F-40.14-03........6/29/16 G-10.10-00........9/20/07 G-25.10-05.......9/16/20 G-95.10-02........6/28/18 G-20.10-02........6/23/15 G-26.10-00……7/31/19 G-95.20-03........6/28/18 G-22.10-04..........6/28/18 G-30.10-04.......6/23/15 G-95.30-03........6/28/18 G-24.10-00......11/8/07 G-50.10-03.......6/28/18 G-24.20-01......2/7/12 G-90.10-03……7/11/17 G-24.30-02......6/28/18 G-90.11-00……4/28/16 G-24.40-07.....6/28/18 G-90.20-05……7/11/17 G-24.50-05.....8/7/19 G-90.30-04……7/11/17 G-24.60-05.....6/28/18 G-90.40-02……4/28/16 H-10.10-00..........7/3/08 H-32.10-00.......9/20/07 H-70.10-01......2/7/12 H-10.15-00..........7/3/08 H-60.10-01.........7/3/08 H-70.20-01......2/16/12 H-30.10-00......10/12/07 H-60.20-01.........7/3/08 I-10.10-01.........8/11/09 I-30.20-00.........9/20/07 I-40.20-00.........9/20/07 I-30.10-02.........3/22/13 I-30.30-02.........6/12/19 I-50.20-01..........6/10/13 I-30.15-02.........3/22/13 I-30.40-02.......6/12/19 I-60.10-01..........6/10/13 I-30.16-01.........7/11/19 I-30.60-02.........6/12/19 I-60.20-01..........6/10/13 I-30.17-01.........6/12/19 I-40.10-00.........9/20/07 I-80.10-02..........7/15/16 J-10..................7/18/97 J-28.40-02......6/11/14 J-60.13-00…....6/16/10 J-10.10-04……9/16/20 J-28.42-01.......6/11/14 J-60.14-01……7/31/19 J-10.12-00……9/16/20 J-28.43-01.......6/28/18 J-75.10-02……7/10/15 J-10.14-00……9/16/20 J-28.45-03.......7/21/16 J-75.20-01……7/10/15 J-10.15-01........6/11/14 J-28.50-03.......7/21/16 J-75.30-02…….7/10/15 J-10.16-01……9/16/20 J-28.60-02.......7/21/16 J-75.40-02……6/1/16 J-10.17-01……9/16/20 J-28.70-03.......7/21/17 J-75.41-01……6/29/16 J-10.18-01……9/16/20 J-29.10-01.......7/21/16 J-75.45-02……6/1/16 J-10.20-03……9/16/20 J-29.15-01.......7/21/16 J-80.10-00……6/28/18 J-10.21-01……9/16/20 J-29.16-02.......7/21/16 J-80.15-00……6/28/18 J-10.22-01........9/16/20 J-30.10-00…...6/18/15 J-81.10-01……9/16/20 J-10.25-00……7/11/17 J-40.05-00……7/21/16 J-86.10-00……6/28/18 J-12.15-00……6/28/18 J-40.10-04…...4/28/16 J-90.10-03…….6/28/18 J-12.16-00……6/28/18 J-40.20-03…...4/28/16 J-90.20-03…….6/28/18 J-15.10-01........6/11/14 J-40.30-04……4/28/16 J-90.21-02……6/28/18 J-15.15-02……7/10/15 J-40.35-01……5/29/13 J-90.50-00……6/28/18 J-20.10-04........7/31/19 J-40.36-02……7/21/17 J-20.11-03........7/31/19 J-40.37-02……7/21/17 J-20.15-03........6/30/14 J-40.38-01.......5/20/13 J-20.16-02........6/30/14 J-40.39-00……5/20/13 J-20.20-02........5/20/13 J-40.40-02……7/31/19 DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 City of Bremerton 233-1896-178 Downtown Bicycle Pedestrian Circulation Improvements II-69 May 2021 Contract Documents Division 9 J-20.26-01........7/12/12 J-45.36-00……7/21/17 J-21.10-04......6/30/14 J-50.05-00……7/21/17 J-21.15-01......6/10/13 J-50.10-01…….7/31/19 J-21.16-01......6/10/13 J-50.11-02…….7/31/19 J-21.17-01......6/10/13 J-50.12-02…….8/7/19 J-21.20-01......6/10/13 J-50.13-00…….8/22/19 J-22.15-02......7/10/15 J-50.15-01…….7/21/17 J-22.16-03......7/10/15 J-50.16-01…….3/22/13 J-26.10-03…..7/21/16 J-50.18-00…….8/7/19 J-26.15-01…..5/17/12 J-50.19-00…….8/7/19 J-26.20-01…..6/28/18 J-50.20-00…….6/3/11 J-27.10-01…..7/21/16 J-50.25-00…….6/3/11 J-27.15-00…..3/15/12 J-50.30-00…….6/3/11 J-28.10-02......8/7/19 J-60.05-01…….7/21/16 J-28.22-00.......8/07/07 J-60.11-00…....5/20/13 J-28.24-02.......9/16/20 J-60.12-00…....5/20/13 J-28.26-01......12/02/08 J-28.30-03......6/11/14 K-70.20-01.......6/1/16 K-80.10-02.......9/25/20 K-80.20-00.....12/20/06 K-80.35-01.......9/16/20 K-80.37-01.......9/16/20 L-10.10-02........6/21/12 L-70.10-01.......5/21/08 L-20.10-03........7/14/15 L-40.15-01........6/16/11 L-70.20-01.......5/21/08 L-30.10-02........6/11/14 L-40.20-02........6/21/12 M-1.20-04.........9/25/20 M-11.10-03........8/7/19 M-40.20-00...10/12/07 M-1.40-03.........9/25/20 M-12.10-02……9/25/20 M-40.30-01......7/11/17 M-1.60-03.........9/25/20 M-15.10-01........2/6/07 M-40.40-00......9/20/07 M-1.80-03.........6/3/11 M-17.10-02........7/3/08 M-40.50-00......9/20/07 M-2.20-03.........7/10/15 M-20.10-03........9/25/20 M-40.60-00......9/20/07 M-2.21-00……7/10/15 M-20.20-02........4/20/15 M-60.10-01......6/3/11 M-3.10-04.........9/25/20 M-20.30-04........2/29/16 M-60.20-02......6/27/11 M-3.20-03.........9/25/20 M-20.40-03........6/24/14 M-65.10-02......5/11/11 M-3.30-04.........9/25/20 M-20.50-02........6/3/11 M-80.10-01......6/3/11 M-3.40-04.........9/25/20 M-24.20-02.......4/20/15 M-80.20-00......6/10/08 M-3.50-03.........9/25/20 M-24.40-02.......4/20/15 M-80.30-00......6/10/08 M-5.10-03.........9/25/20 M-24.60-04.......6/24/14 M-7.50-01.........1/30/07 M-24.65-00……7/11/17 M-9.50-02.........6/24/14 M-24.66-00……7/11/17 M-9.60-00……..2/10/09 M-40.10-03......6/24/14 END OF STANDARD PLANS END OF DIVISION 9 DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 City of Bremerton 233-1896-178 Downtown Bicycle Pedestrian Circulation Improvements II-70 May 2021 Contract Documents Division 9 This Page Intentionally Left Blank DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 PREVAILING WAGES DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 8/2/2021 about:blank about:blank 1/18 State of Washington Department of Labor & Industries Prevailing Wage Section - Telephone 360-902-5335 PO Box 44540, Olympia, WA 98504-4540 Washington State Prevailing Wage The PREVAILING WAGES listed here include both the hourly wage rate and the hourly rate of fringe benefits. On public works projects, worker's wage and benefit rates must add to not less than this total. A brief description of overtime calculation requirements are provided on the Benefit Code Key. Journey Level Prevailing Wage Rates for the Effective Date: 07/14/2021 County Trade Job Classification Wage Holiday Overtime Note *Risk Class Kitsap Asbestos Abatement Workers Journey Level $52.39 5D 1H View Kitsap Boilermakers Journey Level $70.79 5N 1C View Kitsap Brick Mason Journey Level $60.57 7E 1N View Kitsap Brick Mason Pointer-Caulker-Cleaner $60.57 7E 1N View Kitsap Building Service Employees Janitor $13.69  1 View Kitsap Building Service Employees Shampooer $13.69  1 View Kitsap Building Service Employees Waxer $13.69  1 View Kitsap Building Service Employees Window Cleaner $13.69  1 View Kitsap Cabinet Makers (In Shop)Journey Level $23.72  1 View Kitsap Carpenters Acoustical Worker $64.94 7A 4C View Kitsap Carpenters Carpenter $64.94 7A 4C View Kitsap Carpenters Carpenters on Stationary Tools $65.07 7A 4C View Kitsap Carpenters Creosoted Material $65.07 7A 4C View Kitsap Carpenters Floor Finisher $64.94 7A 4C View Kitsap Carpenters Floor Layer $64.94 7A 4C View Kitsap Carpenters Scaffold Erector $64.94 7A 4C View Kitsap Cement Masons Application of all Composition Mastic $64.84 7A 4U View Kitsap Cement Masons Application of all Epoxy Material $64.34 7A 4U View Kitsap Cement Masons Application of all Plastic Material $64.84 7A 4U View Kitsap Cement Masons Application of Sealing Compound $64.34 7A 4U View Kitsap Cement Masons Application of Underlayment $64.84 7A 4U View Kitsap Cement Masons Building General $64.34 7A 4U View Kitsap Cement Masons Composition or Kalman Floors $64.84 7A 4U View Kitsap Cement Masons Concrete Paving $64.34 7A 4U View Kitsap Cement Masons Curb & Gutter Machine $64.84 7A 4U View Kitsap Cement Masons Curb & Gutter, Sidewalks $64.34 7A 4U View Kitsap Cement Masons Curing Concrete $64.34 7A 4U View DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 8/2/2021 about:blank about:blank 2/18 Kitsap Cement Masons Finish Colored Concrete $64.84 7A 4U View Kitsap Cement Masons Floor Grinding $64.84 7A 4U View Kitsap Cement Masons Floor Grinding/Polisher $64.34 7A 4U View Kitsap Cement Masons Green Concrete Saw, self- powered $64.84 7A 4U View Kitsap Cement Masons Grouting of all Plates $64.34 7A 4U View Kitsap Cement Masons Grouting of all Tilt-up Panels $64.34 7A 4U View Kitsap Cement Masons Gunite Nozzleman $64.84 7A 4U View Kitsap Cement Masons Hand Powered Grinder $64.84 7A 4U View Kitsap Cement Masons Journey Level $64.34 7A 4U View Kitsap Cement Masons Patching Concrete $64.34 7A 4U View Kitsap Cement Masons Pneumatic Power Tools $64.84 7A 4U View Kitsap Cement Masons Power Chipping & Brushing $64.84 7A 4U View Kitsap Cement Masons Sand Blasting Architectural Finish $64.84 7A 4U View Kitsap Cement Masons Screed & Rodding Machine $64.84 7A 4U View Kitsap Cement Masons Spackling or Skim Coat Concrete $64.34 7A 4U View Kitsap Cement Masons Troweling Machine Operator $64.84 7A 4U View Kitsap Cement Masons Troweling Machine Operator on Colored Slabs $64.84 7A 4U View Kitsap Cement Masons Tunnel Workers $64.84 7A 4U View Kitsap Divers & Tenders Bell/Vehicle or Submersible Operator (Not Under Pressure) $118.80 7A 4C View Kitsap Divers & Tenders Dive Supervisor/Master $81.98 7A 4C View Kitsap Divers & Tenders Diver $118.80 7A 4C 8V View Kitsap Divers & Tenders Diver On Standby $76.98 7A 4C View Kitsap Divers & Tenders Diver Tender $69.91 7A 4C View Kitsap Divers & Tenders Manifold Operator $69.91 7A 4C View Kitsap Divers & Tenders Manifold Operator Mixed Gas $74.91 7A 4C View Kitsap Divers & Tenders Remote Operated Vehicle Operator/Technician $69.91 7A 4C View Kitsap Divers & Tenders Remote Operated Vehicle Tender $65.19 7A 4C View Kitsap Dredge Workers Assistant Engineer $70.62 5D 3F View Kitsap Dredge Workers Assistant Mate (Deckhand)$70.07 5D 3F View Kitsap Dredge Workers Boatmen $70.62 5D 3F View Kitsap Dredge Workers Engineer Welder $71.97 5D 3F View Kitsap Dredge Workers Leverman, Hydraulic $73.41 5D 3F View Kitsap Dredge Workers Mates $70.62 5D 3F View Kitsap Dredge Workers Oiler $70.07 5D 3F View Kitsap Drywall Applicator Journey Level $64.94 5D 1H View Kitsap Drywall Tapers Journey Level $65.31 5P 1E View Kitsap Electrical Fixture Maintenance Workers Journey Level $31.99 5L 1E View Kitsap Electricians - Inside Cable Splicer $92.57 7C 4E View Kitsap Electricians - Inside Cable Splicer (tunnel)$99.46 7C 4E View Kitsap Electricians - Inside Certified Welder $89.44 7C 4E View DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 8/2/2021 about:blank about:blank 3/18 Kitsap Electricians - Inside Certified Welder (tunnel)$96.02 7C 4E View Kitsap Electricians - Inside Construction Stock Person $44.78 7C 4E View Kitsap Electricians - Inside Journey Level $86.30 7C 4E View Kitsap Electricians - Inside Journey Level (tunnel)$92.57 7C 4E View Kitsap Electricians - Motor Shop Craftsman $15.37  1 View Kitsap Electricians - Motor Shop Journey Level $14.69  1 View Kitsap Electricians - Powerline Construction Cable Splicer $82.39 5A 4D View Kitsap Electricians - Powerline Construction Certified Line Welder $75.64 5A 4D View Kitsap Electricians - Powerline Construction Groundperson $49.17 5A 4D View Kitsap Electricians - Powerline Construction Heavy Line Equipment Operator $75.64 5A 4D View Kitsap Electricians - Powerline Construction Journey Level Lineperson $75.64 5A 4D View Kitsap Electricians - Powerline Construction Line Equipment Operator $64.54 5A 4D View Kitsap Electricians - Powerline Construction Meter Installer $49.17 5A 4D 8W View Kitsap Electricians - Powerline Construction Pole Sprayer $75.64 5A 4D View Kitsap Electricians - Powerline Construction Powderperson $56.49 5A 4D View Kitsap Electronic Technicians Journey Level $53.57 7E 1E View Kitsap Elevator Constructors Mechanic $100.51 7D 4A View Kitsap Elevator Constructors Mechanic In Charge $108.53 7D 4A View Kitsap Fabricated Precast Concrete Products Journey Level $13.69  1 View Kitsap Fabricated Precast Concrete Products Journey Level - In-Factory Work Only $13.69  1 View Kitsap Fence Erectors Fence Erector $44.40 7A 4V 8Y View Kitsap Fence Erectors Fence Laborer $44.40 7A 4V 8Y View Kitsap Flaggers Journey Level $44.40 7A 4V 8Y View Kitsap Glaziers Journey Level $69.26 7L 1Y View Kitsap Heat & Frost Insulators And Asbestos Workers Journey Level $79.43 15H 11C View Kitsap Heating Equipment Mechanics Journey Level $89.61 7F 1E View Kitsap Hod Carriers & Mason Tenders Journey Level $54.01 7A 4V 8Y View Kitsap Industrial Power Vacuum Cleaner Journey Level $29.89  1 View Kitsap Inland Boatmen Boat Operator $61.41 5B 1K View Kitsap Inland Boatmen Cook $56.48 5B 1K View Kitsap Inland Boatmen Deckhand $57.48 5B 1K View Kitsap Inland Boatmen Deckhand Engineer $58.81 5B 1K View Kitsap Inland Boatmen Launch Operator $58.89 5B 1K View Kitsap Inland Boatmen Mate $57.31 5B 1K View Kitsap Inspection/Cleaning/Sealing Of Sewer & Water Systems By Remote Control Cleaner Operator, Foamer Operator $13.69  1 View DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 8/2/2021 about:blank about:blank 4/18 Kitsap Inspection/Cleaning/Sealing Of Sewer & Water Systems By Remote Control Grout Truck Operator $13.69  1 View Kitsap Inspection/Cleaning/Sealing Of Sewer & Water Systems By Remote Control Head Operator $13.69  1 View Kitsap Inspection/Cleaning/Sealing Of Sewer & Water Systems By Remote Control Tv Truck Operator $24.17  1 View Kitsap Insulation Applicators Journey Level $64.94 7A 4C View Kitsap Ironworkers Journeyman $76.78 7N 1O View Kitsap Laborers Air, Gas Or Electric Vibrating Screed $52.39 7A 4V 8Y View Kitsap Laborers Airtrac Drill Operator $54.01 7A 4V 8Y View Kitsap Laborers Ballast Regular Machine $52.39 7A 4V 8Y View Kitsap Laborers Batch Weighman $44.40 7A 4V 8Y View Kitsap Laborers Brick Pavers $52.39 7A 4V 8Y View Kitsap Laborers Brush Cutter $52.39 7A 4V 8Y View Kitsap Laborers Brush Hog Feeder $52.39 7A 4V 8Y View Kitsap Laborers Burner $52.39 7A 4V 8Y View Kitsap Laborers Caisson Worker $54.01 7A 4V 8Y View Kitsap Laborers Carpenter Tender $52.39 7A 4V 8Y View Kitsap Laborers Cement Dumper-paving $53.35 7A 4V 8Y View Kitsap Laborers Cement Finisher Tender $52.39 7A 4V 8Y View Kitsap Laborers Change House Or Dry Shack $52.39 7A 4V 8Y View Kitsap Laborers Chipping Gun (30 Lbs. And Over) $53.35 7A 4V 8Y View Kitsap Laborers Chipping Gun (Under 30 Lbs.)$52.39 7A 4V 8Y View Kitsap Laborers Choker Setter $52.39 7A 4V 8Y View Kitsap Laborers Chuck Tender $52.39 7A 4V 8Y View Kitsap Laborers Clary Power Spreader $53.35 7A 4V 8Y View Kitsap Laborers Clean-up Laborer $52.39 7A 4V 8Y View Kitsap Laborers Concrete Dumper/Chute Operator $53.35 7A 4V 8Y View Kitsap Laborers Concrete Form Stripper $52.39 7A 4V 8Y View Kitsap Laborers Concrete Placement Crew $53.35 7A 4V 8Y View Kitsap Laborers Concrete Saw Operator/Core Driller $53.35 7A 4V 8Y View Kitsap Laborers Crusher Feeder $44.40 7A 4V 8Y View Kitsap Laborers Curing Laborer $52.39 7A 4V 8Y View Kitsap Laborers Demolition: Wrecking & Moving (Incl. Charred Material) $52.39 7A 4V 8Y View Kitsap Laborers Ditch Digger $52.39 7A 4V 8Y View Kitsap Laborers Diver $54.01 7A 4V 8Y View Kitsap Laborers Drill Operator (Hydraulic, Diamond) $53.35 7A 4V 8Y View Kitsap Laborers Dry Stack Walls $52.39 7A 4V 8Y View Kitsap Laborers Dump Person $52.39 7A 4V 8Y View Kitsap Laborers Epoxy Technician $52.39 7A 4V 8Y View DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 8/2/2021 about:blank about:blank 5/18 Kitsap Laborers Erosion Control Worker $52.39 7A 4V 8Y View Kitsap Laborers Faller & Bucker Chain Saw $53.35 7A 4V 8Y View Kitsap Laborers Fine Graders $52.39 7A 4V 8Y View Kitsap Laborers Firewatch $44.40 7A 4V 8Y View Kitsap Laborers Form Setter $52.39 7A 4V 8Y View Kitsap Laborers Gabian Basket Builders $52.39 7A 4V 8Y View Kitsap Laborers General Laborer $52.39 7A 4V 8Y View Kitsap Laborers Grade Checker & Transit Person $54.01 7A 4V 8Y View Kitsap Laborers Grinders $52.39 7A 4V 8Y View Kitsap Laborers Grout Machine Tender $52.39 7A 4V 8Y View Kitsap Laborers Groutmen (Pressure) Including Post Tension Beams $53.35 7A 4V 8Y View Kitsap Laborers Guardrail Erector $52.39 7A 4V 8Y View Kitsap Laborers Hazardous Waste Worker (Level A) $54.01 7A 4V 8Y View Kitsap Laborers Hazardous Waste Worker (Level B) $53.35 7A 4V 8Y View Kitsap Laborers Hazardous Waste Worker (Level C) $52.39 7A 4V 8Y View Kitsap Laborers High Scaler $54.01 7A 4V 8Y View Kitsap Laborers Jackhammer $53.35 7A 4V 8Y View Kitsap Laborers Laserbeam Operator $53.35 7A 4V 8Y View Kitsap Laborers Maintenance Person $52.39 7A 4V 8Y View Kitsap Laborers Manhole Builder-Mudman $53.35 7A 4V 8Y View Kitsap Laborers Material Yard Person $52.39 7A 4V 8Y View Kitsap Laborers Motorman-Dinky Locomotive $53.35 7A 4V 8Y View Kitsap Laborers Nozzleman (Concrete Pump, Green Cutter When Using Combination Of High Pressure Air & Water On Concrete & Rock, Sandblast, Gunite, Shotcrete, Water Blaster, Vacuum Blaster) $53.35 7A 4V 8Y View Kitsap Laborers Pavement Breaker $53.35 7A 4V 8Y View Kitsap Laborers Pilot Car $44.40 7A 4V 8Y View Kitsap Laborers Pipe Layer Lead $54.01 7A 4V 8Y View Kitsap Laborers Pipe Layer/Tailor $53.35 7A 4V 8Y View Kitsap Laborers Pipe Pot Tender $53.35 7A 4V 8Y View Kitsap Laborers Pipe Reliner $53.35 7A 4V 8Y View Kitsap Laborers Pipe Wrapper $53.35 7A 4V 8Y View Kitsap Laborers Pot Tender $52.39 7A 4V 8Y View Kitsap Laborers Powderman $54.01 7A 4V 8Y View Kitsap Laborers Powderman's Helper $52.39 7A 4V 8Y View Kitsap Laborers Power Jacks $53.35 7A 4V 8Y View Kitsap Laborers Railroad Spike Puller - Power $53.35 7A 4V 8Y View Kitsap Laborers Raker - Asphalt $54.01 7A 4V 8Y View Kitsap Laborers Re-timberman $54.01 7A 4V 8Y View Kitsap Laborers Remote Equipment Operator $53.35 7A 4V 8Y View Kitsap Laborers Rigger/Signal Person $53.35 7A 4V 8Y View DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 8/2/2021 about:blank about:blank 6/18 Kitsap Laborers Rip Rap Person $52.39 7A 4V 8Y View Kitsap Laborers Rivet Buster $53.35 7A 4V 8Y View Kitsap Laborers Rodder $53.35 7A 4V 8Y View Kitsap Laborers Scaffold Erector $52.39 7A 4V 8Y View Kitsap Laborers Scale Person $52.39 7A 4V 8Y View Kitsap Laborers Sloper (Over 20")$53.35 7A 4V 8Y View Kitsap Laborers Sloper Sprayer $52.39 7A 4V 8Y View Kitsap Laborers Spreader (Concrete)$53.35 7A 4V 8Y View Kitsap Laborers Stake Hopper $52.39 7A 4V 8Y View Kitsap Laborers Stock Piler $52.39 7A 4V 8Y View Kitsap Laborers Swinging Stage/Boatswain Chair $44.40 7A 4V 8Y View Kitsap Laborers Tamper & Similar Electric, Air & Gas Operated Tools $53.35 7A 4V 8Y View Kitsap Laborers Tamper (Multiple & Self- propelled) $53.35 7A 4V 8Y View Kitsap Laborers Timber Person - Sewer (Lagger, Shorer & Cribber) $53.35 7A 4V 8Y View Kitsap Laborers Toolroom Person (at Jobsite)$52.39 7A 4V 8Y View Kitsap Laborers Topper $52.39 7A 4V 8Y View Kitsap Laborers Track Laborer $52.39 7A 4V 8Y View Kitsap Laborers Track Liner (Power)$53.35 7A 4V 8Y View Kitsap Laborers Traffic Control Laborer $47.48 7A 4V 9C View Kitsap Laborers Traffic Control Supervisor $50.31 7A 4V 9C View Kitsap Laborers Truck Spotter $52.39 7A 4V 8Y View Kitsap Laborers Tugger Operator $53.35 7A 4V 8Y View Kitsap Laborers Tunnel Work-Compressed Air Worker 0-30 psi $129.67 7A 4V 9B View Kitsap Laborers Tunnel Work-Compressed Air Worker 30.01-44.00 psi $134.70 7A 4V 9B View Kitsap Laborers Tunnel Work-Compressed Air Worker 44.01-54.00 psi $138.38 7A 4V 9B View Kitsap Laborers Tunnel Work-Compressed Air Worker 54.01-60.00 psi $144.08 7A 4V 9B View Kitsap Laborers Tunnel Work-Compressed Air Worker 60.01-64.00 psi $146.20 7A 4V 9B View Kitsap Laborers Tunnel Work-Compressed Air Worker 64.01-68.00 psi $151.30 7A 4V 9B View Kitsap Laborers Tunnel Work-Compressed Air Worker 68.01-70.00 psi $153.20 7A 4V 9B View Kitsap Laborers Tunnel Work-Compressed Air Worker 70.01-72.00 psi $155.20 7A 4V 9B View Kitsap Laborers Tunnel Work-Compressed Air Worker 72.01-74.00 psi $157.20 7A 4V 9B View Kitsap Laborers Tunnel Work-Guage and Lock Tender $54.11 7A 4V 8Y View Kitsap Laborers Tunnel Work-Miner $54.11 7A 4V 8Y View Kitsap Laborers Vibrator $53.35 7A 4V 8Y View Kitsap Laborers Vinyl Seamer $52.39 7A 4V 8Y View Kitsap Laborers Watchman $40.36 7A 4V 8Y View DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 8/2/2021 about:blank about:blank 7/18 Kitsap Laborers Welder $53.35 7A 4V 8Y View Kitsap Laborers Well Point Laborer $53.35 7A 4V 8Y View Kitsap Laborers Window Washer/Cleaner $40.36 7A 4V 8Y View Kitsap Laborers - Underground Sewer & Water General Laborer & Topman $52.39 7A 4V 8Y View Kitsap Laborers - Underground Sewer & Water Pipe Layer $53.35 7A 4V 8Y View Kitsap Landscape Construction Landscape Construction/Landscaping Or Planting Laborers $40.36 7A 4V 8Y View Kitsap Landscape Construction Landscape Operator $69.33 7A 3K 8X View Kitsap Landscape Maintenance Groundskeeper $13.69  1 View Kitsap Lathers Journey Level $64.94 5D 1H View Kitsap Marble Setters Journey Level $60.57 7E 1N View Kitsap Metal Fabrication (In Shop)Fitter $26.96  1 View Kitsap Metal Fabrication (In Shop)Laborer $13.69  1 View Kitsap Metal Fabrication (In Shop)Machine Operator $13.83  1 View Kitsap Metal Fabrication (In Shop)Welder $13.83  1 View Kitsap Millwright Journey Level $66.44 7A 4C View Kitsap Modular Buildings Cabinet Assembly $13.69  1 View Kitsap Modular Buildings Electrician $13.69  1 View Kitsap Modular Buildings Equipment Maintenance $13.69  1 View Kitsap Modular Buildings Plumber $13.69  1 View Kitsap Modular Buildings Production Worker $13.69  1 View Kitsap Modular Buildings Tool Maintenance $13.69  1 View Kitsap Modular Buildings Utility Person $13.69  1 View Kitsap Modular Buildings Welder $13.69  1 View Kitsap Painters Journey Level $45.40 6Z 2B View Kitsap Pile Driver Crew Tender $69.91 7A 4C View Kitsap Pile Driver Crew Tender/Technician $69.91 7A 4C View Kitsap Pile Driver Hyperbaric Worker - Compressed Air Worker 0-30.00 PSI $80.76 7A 4C View Kitsap Pile Driver Hyperbaric Worker - Compressed Air Worker 30.01 - 44.00 PSI $85.76 7A 4C View Kitsap Pile Driver Hyperbaric Worker - Compressed Air Worker 44.01 - 54.00 PSI $89.76 7A 4C View Kitsap Pile Driver Hyperbaric Worker - Compressed Air Worker 54.01 - 60.00 PSI $94.76 7A 4C View Kitsap Pile Driver Hyperbaric Worker - Compressed Air Worker 60.01 - 64.00 PSI $97.26 7A 4C View Kitsap Pile Driver Hyperbaric Worker - Compressed Air Worker 64.01 - 68.00 PSI $102.26 7A 4C View Kitsap Pile Driver Hyperbaric Worker - Compressed Air Worker 68.01 - 70.00 PSI $104.26 7A 4C View DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 8/2/2021 about:blank about:blank 8/18 Kitsap Pile Driver Hyperbaric Worker - Compressed Air Worker 70.01 - 72.00 PSI $106.26 7A 4C View Kitsap Pile Driver Hyperbaric Worker - Compressed Air Worker 72.01 - 74.00 PSI $108.26 7A 4C View Kitsap Pile Driver Journey Level $65.19 7A 4C View Kitsap Plasterers Journey Level $61.67 7Q 1R View Kitsap Playground & Park Equipment Installers Journey Level $13.69  1 View Kitsap Plumbers & Pipefitters Journey Level $79.47 5A 1G View Kitsap Power Equipment Operators Asphalt Plant Operators $70.49 7A 3K 8X View Kitsap Power Equipment Operators Assistant Engineer $66.30 7A 3K 8X View Kitsap Power Equipment Operators Barrier Machine (zipper)$69.87 7A 3K 8X View Kitsap Power Equipment Operators Batch Plant Operator: concrete $69.87 7A 3K 8X View Kitsap Power Equipment Operators Bobcat $66.30 7A 3K 8X View Kitsap Power Equipment Operators Brokk - Remote Demolition Equipment $66.30 7A 3K 8X View Kitsap Power Equipment Operators Brooms $66.30 7A 3K 8X View Kitsap Power Equipment Operators Bump Cutter $69.87 7A 3K 8X View Kitsap Power Equipment Operators Cableways $70.49 7A 3K 8X View Kitsap Power Equipment Operators Chipper $69.87 7A 3K 8X View Kitsap Power Equipment Operators Compressor $66.30 7A 3K 8X View Kitsap Power Equipment Operators Concrete Finish Machine - Laser Screed $66.30 7A 3K 8X View Kitsap Power Equipment Operators Concrete Pump - Mounted Or Trailer High Pressure Line Pump, Pump High Pressure $69.33 7A 3K 8X View Kitsap Power Equipment Operators Concrete Pump: Truck Mount With Boom Attachment Over 42 M $70.49 7A 3K 8X View Kitsap Power Equipment Operators Concrete Pump: Truck Mount With Boom Attachment Up To 42m $69.87 7A 3K 8X View Kitsap Power Equipment Operators Conveyors $69.33 7A 3K 8X View Kitsap Power Equipment Operators Cranes friction: 200 tons and over $72.63 7A 3K 8X View Kitsap Power Equipment Operators Cranes: 100 tons through 199 tons, or 150' of boom (including jib with attachments) $71.20 7A 3K 8X View Kitsap Power Equipment Operators Cranes: 20 Tons Through 44 Tons With Attachments $69.87 7A 3K 8X View Kitsap Power Equipment Operators Cranes: 200 tons- 299 tons, or 250' of boom including jib with attachments $71.93 7A 3K 8X View Kitsap Power Equipment Operators Cranes: 300 tons and over or 300' of boom including jib with attachments $72.63 7A 3K 8X View Kitsap Power Equipment Operators Cranes: 45 Tons Through 99 Tons, Under 150' Of Boom $70.49 7A 3K 8X View DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 8/2/2021 about:blank about:blank 9/18 (including Jib With Attachments) Kitsap Power Equipment Operators Cranes: A-frame - 10 Tons And Under $66.30 7A 3K 8X View Kitsap Power Equipment Operators Cranes: Friction cranes through 199 tons $71.93 7A 3K 8X View Kitsap Power Equipment Operators Cranes: through 19 tons with attachments, A-frame over 10 tons $69.33 7A 3K 8X View Kitsap Power Equipment Operators Crusher $69.87 7A 3K 8X View Kitsap Power Equipment Operators Deck Engineer/Deck Winches (power) $69.87 7A 3K 8X View Kitsap Power Equipment Operators Derricks, On Building Work $70.49 7A 3K 8X View Kitsap Power Equipment Operators Dozers D-9 & Under $69.33 7A 3K 8X View Kitsap Power Equipment Operators Drill Oilers: Auger Type, Truck Or Crane Mount $69.33 7A 3K 8X View Kitsap Power Equipment Operators Drilling Machine $71.20 7A 3K 8X View Kitsap Power Equipment Operators Elevator And Man-lift: Permanent And Shaft Type $66.30 7A 3K 8X View Kitsap Power Equipment Operators Finishing Machine, Bidwell And Gamaco & Similar Equipment $69.87 7A 3K 8X View Kitsap Power Equipment Operators Forklift: 3000 Lbs And Over With Attachments $69.33 7A 3K 8X View Kitsap Power Equipment Operators Forklifts: Under 3000 Lbs. With Attachments $66.30 7A 3K 8X View Kitsap Power Equipment Operators Grade Engineer: Using Blue Prints, Cut Sheets, Etc $69.87 7A 3K 8X View Kitsap Power Equipment Operators Gradechecker/Stakeman $66.30 7A 3K 8X View Kitsap Power Equipment Operators Guardrail Punch $69.87 7A 3K 8X View Kitsap Power Equipment Operators Hard Tail End Dump Articulating Off- Road Equipment 45 Yards. & Over $70.49 7A 3K 8X View Kitsap Power Equipment Operators Hard Tail End Dump Articulating Off-road Equipment Under 45 Yards $69.87 7A 3K 8X View Kitsap Power Equipment Operators Horizontal/Directional Drill Locator $69.33 7A 3K 8X View Kitsap Power Equipment Operators Horizontal/Directional Drill Operator $69.87 7A 3K 8X View Kitsap Power Equipment Operators Hydralifts/Boom Trucks Over 10 Tons $69.33 7A 3K 8X View Kitsap Power Equipment Operators Hydralifts/Boom Trucks, 10 Tons And Under $66.30 7A 3K 8X View Kitsap Power Equipment Operators Loader, Overhead 8 Yards. & Over $71.20 7A 3K 8X View Kitsap Power Equipment Operators Loader, Overhead, 6 Yards. But Not Including 8 Yards $70.49 7A 3K 8X View Kitsap Power Equipment Operators Loaders, Overhead Under 6 Yards $69.87 7A 3K 8X View Kitsap Power Equipment Operators Loaders, Plant Feed $69.87 7A 3K 8X View Kitsap Power Equipment Operators Loaders: Elevating Type Belt $69.33 7A 3K 8X View Kitsap Power Equipment Operators Locomotives, All $69.87 7A 3K 8X View DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 8/2/2021 about:blank about:blank 10/18 Kitsap Power Equipment Operators Material Transfer Device $69.87 7A 3K 8X View Kitsap Power Equipment Operators Mechanics, All (leadmen - $0.50 Per Hour Over Mechanic) $71.20 7A 3K 8X View Kitsap Power Equipment Operators Motor Patrol Graders $70.49 7A 3K 8X View Kitsap Power Equipment Operators Mucking Machine, Mole, Tunnel Drill, Boring, Road Header And/or Shield $70.49 7A 3K 8X View Kitsap Power Equipment Operators Oil Distributors, Blower Distribution & Mulch Seeding Operator $66.30 7A 3K 8X View Kitsap Power Equipment Operators Outside Hoists (Elevators And Manlifts), Air Tuggers, Strato $69.33 7A 3K 8X View Kitsap Power Equipment Operators Overhead, Bridge Type Crane: 20 Tons Through 44 Tons $69.87 7A 3K 8X View Kitsap Power Equipment Operators Overhead, Bridge Type: 100 Tons And Over $71.20 7A 3K 8X View Kitsap Power Equipment Operators Overhead, Bridge Type: 45 Tons Through 99 Tons $70.49 7A 3K 8X View Kitsap Power Equipment Operators Pavement Breaker $66.30 7A 3K 8X View Kitsap Power Equipment Operators Pile Driver (other Than Crane Mount) $69.87 7A 3K 8X View Kitsap Power Equipment Operators Plant Oiler - Asphalt, Crusher $69.33 7A 3K 8X View Kitsap Power Equipment Operators Posthole Digger, Mechanical $66.30 7A 3K 8X View Kitsap Power Equipment Operators Power Plant $66.30 7A 3K 8X View Kitsap Power Equipment Operators Pumps - Water $66.30 7A 3K 8X View Kitsap Power Equipment Operators Quad 9, Hd 41, D10 And Over $70.49 7A 3K 8X View Kitsap Power Equipment Operators Quick Tower - No Cab, Under 100 Feet In Height Based To Boom $66.30 7A 3K 8X View Kitsap Power Equipment Operators Remote Control Operator On Rubber Tired Earth Moving Equipment $70.49 7A 3K 8X View Kitsap Power Equipment Operators Rigger and Bellman $66.30 7A 3K 8X View Kitsap Power Equipment Operators Rigger/Signal Person, Bellman (Certified) $69.33 7A 3K 8X View Kitsap Power Equipment Operators Rollagon $70.49 7A 3K 8X View Kitsap Power Equipment Operators Roller, Other Than Plant Mix $66.30 7A 3K 8X View Kitsap Power Equipment Operators Roller, Plant Mix Or Multi-lift Materials $69.33 7A 3K 8X View Kitsap Power Equipment Operators Roto-mill, Roto-grinder $69.87 7A 3K 8X View Kitsap Power Equipment Operators Saws - Concrete $69.33 7A 3K 8X View Kitsap Power Equipment Operators Scraper, Self Propelled Under 45 Yards $69.87 7A 3K 8X View Kitsap Power Equipment Operators Scrapers - Concrete & Carry All $69.33 7A 3K 8X View Kitsap Power Equipment Operators Scrapers, Self-propelled: 45 Yards And Over $70.49 7A 3K 8X View Kitsap Power Equipment Operators Service Engineers - Equipment $69.33 7A 3K 8X View Kitsap Power Equipment Operators Shotcrete/Gunite Equipment $66.30 7A 3K 8X View Kitsap Power Equipment Operators Shovel, Excavator, Backhoe, Tractors Under 15 Metric Tons $69.33 7A 3K 8X View Kitsap Power Equipment Operators Shovel, Excavator, Backhoe:$70.49 7A 3K 8X View DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 8/2/2021 about:blank about:blank 11/18 Over 30 Metric Tons To 50 Metric Tons Kitsap Power Equipment Operators Shovel, Excavator, Backhoes, Tractors: 15 To 30 Metric Tons $69.87 7A 3K 8X View Kitsap Power Equipment Operators Shovel, Excavator, Backhoes: Over 50 Metric Tons To 90 Metric Tons $71.20 7A 3K 8X View Kitsap Power Equipment Operators Shovel, Excavator, Backhoes: Over 90 Metric Tons $71.93 7A 3K 8X View Kitsap Power Equipment Operators Slipform Pavers $70.49 7A 3K 8X View Kitsap Power Equipment Operators Spreader, Topsider & Screedman $70.49 7A 3K 8X View Kitsap Power Equipment Operators Subgrader Trimmer $69.87 7A 3K 8X View Kitsap Power Equipment Operators Tower Bucket Elevators $69.33 7A 3K 8X View Kitsap Power Equipment Operators Tower Crane Up To 175' In Height Base To Boom $71.20 7A 3K 8X View Kitsap Power Equipment Operators Tower Crane: over 175' through 250' in height, base to boom $71.93 7A 3K 8X View Kitsap Power Equipment Operators Tower Cranes: over 250' in height from base to boom $72.63 7A 3K 8X View Kitsap Power Equipment Operators Transporters, All Track Or Truck Type $70.49 7A 3K 8X View Kitsap Power Equipment Operators Trenching Machines $69.33 7A 3K 8X View Kitsap Power Equipment Operators Truck Crane Oiler/driver - 100 Tons And Over $69.87 7A 3K 8X View Kitsap Power Equipment Operators Truck Crane Oiler/Driver Under 100 Tons $69.33 7A 3K 8X View Kitsap Power Equipment Operators Truck Mount Portable Conveyor $69.87 7A 3K 8X View Kitsap Power Equipment Operators Welder $70.49 7A 3K 8X View Kitsap Power Equipment Operators Wheel Tractors, Farmall Type $66.30 7A 3K 8X View Kitsap Power Equipment Operators Yo Yo Pay Dozer $69.87 7A 3K 8X View Kitsap Power Equipment Operators- Underground Sewer & Water Asphalt Plant Operators $70.49 7A 3K 8X View Kitsap Power Equipment Operators- Underground Sewer & Water Assistant Engineer $66.30 7A 3K 8X View Kitsap Power Equipment Operators- Underground Sewer & Water Barrier Machine (zipper)$69.87 7A 3K 8X View Kitsap Power Equipment Operators- Underground Sewer & Water Batch Plant Operator, Concrete $69.87 7A 3K 8X View Kitsap Power Equipment Operators- Underground Sewer & Water Bobcat $66.30 7A 3K 8X View Kitsap Power Equipment Operators- Underground Sewer & Water Brokk - Remote Demolition Equipment $66.30 7A 3K 8X View Kitsap Power Equipment Operators- Underground Sewer & Water Brooms $66.30 7A 3K 8X View Kitsap Power Equipment Operators- Underground Sewer & Water Bump Cutter $69.87 7A 3K 8X View Kitsap Power Equipment Operators- Underground Sewer & Water Cableways $70.49 7A 3K 8X View Kitsap Power Equipment Operators- Underground Sewer & Water Chipper $69.87 7A 3K 8X View Kitsap Power Equipment Operators-Compressor $66.30 7A 3K 8X View DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 8/2/2021 about:blank about:blank 12/18 Underground Sewer & Water Kitsap Power Equipment Operators- Underground Sewer & Water Concrete Finish Machine - Laser Screed $66.30 7A 3K 8X View Kitsap Power Equipment Operators- Underground Sewer & Water Concrete Pump - Mounted Or Trailer High Pressure Line Pump, Pump High Pressure $69.33 7A 3K 8X View Kitsap Power Equipment Operators- Underground Sewer & Water Concrete Pump: Truck Mount With Boom Attachment Over 42 M $70.49 7A 3K 8X View Kitsap Power Equipment Operators- Underground Sewer & Water Concrete Pump: Truck Mount With Boom Attachment Up To 42m $69.87 7A 3K 8X View Kitsap Power Equipment Operators- Underground Sewer & Water Conveyors $69.33 7A 3K 8X View Kitsap Power Equipment Operators- Underground Sewer & Water Cranes friction: 200 tons and over $72.63 7A 3K 8X View Kitsap Power Equipment Operators- Underground Sewer & Water Cranes: 100 tons through 199 tons, or 150' of boom (including jib with attachments) $71.20 7A 3K 8X View Kitsap Power Equipment Operators- Underground Sewer & Water Cranes: 20 Tons Through 44 Tons With Attachments $69.87 7A 3K 8X View Kitsap Power Equipment Operators- Underground Sewer & Water Cranes: 200 tons- 299 tons, or 250' of boom including jib with attachments $71.93 7A 3K 8X View Kitsap Power Equipment Operators- Underground Sewer & Water Cranes: 300 tons and over or 300' of boom including jib with attachments $72.63 7A 3K 8X View Kitsap Power Equipment Operators- Underground Sewer & Water Cranes: 45 Tons Through 99 Tons, Under 150' Of Boom (including Jib With Attachments) $70.49 7A 3K 8X View Kitsap Power Equipment Operators- Underground Sewer & Water Cranes: A-frame - 10 Tons And Under $66.30 7A 3K 8X View Kitsap Power Equipment Operators- Underground Sewer & Water Cranes: Friction cranes through 199 tons $71.93 7A 3K 8X View Kitsap Power Equipment Operators- Underground Sewer & Water Cranes: through 19 tons with attachments, A-frame over 10 tons $69.33 7A 3K 8X View Kitsap Power Equipment Operators- Underground Sewer & Water Crusher $69.87 7A 3K 8X View Kitsap Power Equipment Operators- Underground Sewer & Water Deck Engineer/Deck Winches (power) $69.87 7A 3K 8X View Kitsap Power Equipment Operators- Underground Sewer & Water Derricks, On Building Work $70.49 7A 3K 8X View Kitsap Power Equipment Operators- Underground Sewer & Water Dozers D-9 & Under $69.33 7A 3K 8X View Kitsap Power Equipment Operators- Underground Sewer & Water Drill Oilers: Auger Type, Truck Or Crane Mount $69.33 7A 3K 8X View Kitsap Power Equipment Operators- Underground Sewer & Water Drilling Machine $71.20 7A 3K 8X View Kitsap Power Equipment Operators- Underground Sewer & Water Elevator And Man-lift: Permanent And Shaft Type $66.30 7A 3K 8X View Kitsap Power Equipment Operators-Finishing Machine, Bidwell And $69.87 7A 3K 8X View DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 8/2/2021 about:blank about:blank 13/18 Underground Sewer & Water Gamaco & Similar Equipment Kitsap Power Equipment Operators- Underground Sewer & Water Forklift: 3000 Lbs And Over With Attachments $69.33 7A 3K 8X View Kitsap Power Equipment Operators- Underground Sewer & Water Forklifts: Under 3000 Lbs. With Attachments $66.30 7A 3K 8X View Kitsap Power Equipment Operators- Underground Sewer & Water Grade Engineer: Using Blue Prints, Cut Sheets, Etc $69.87 7A 3K 8X View Kitsap Power Equipment Operators- Underground Sewer & Water Gradechecker/Stakeman $66.30 7A 3K 8X View Kitsap Power Equipment Operators- Underground Sewer & Water Guardrail Punch $69.87 7A 3K 8X View Kitsap Power Equipment Operators- Underground Sewer & Water Hard Tail End Dump Articulating Off- Road Equipment 45 Yards. & Over $70.49 7A 3K 8X View Kitsap Power Equipment Operators- Underground Sewer & Water Hard Tail End Dump Articulating Off-road Equipment Under 45 Yards $69.87 7A 3K 8X View Kitsap Power Equipment Operators- Underground Sewer & Water Horizontal/Directional Drill Locator $69.33 7A 3K 8X View Kitsap Power Equipment Operators- Underground Sewer & Water Horizontal/Directional Drill Operator $69.87 7A 3K 8X View Kitsap Power Equipment Operators- Underground Sewer & Water Hydralifts/Boom Trucks Over 10 Tons $69.33 7A 3K 8X View Kitsap Power Equipment Operators- Underground Sewer & Water Hydralifts/Boom Trucks, 10 Tons And Under $66.30 7A 3K 8X View Kitsap Power Equipment Operators- Underground Sewer & Water Loader, Overhead 8 Yards. & Over $71.20 7A 3K 8X View Kitsap Power Equipment Operators- Underground Sewer & Water Loader, Overhead, 6 Yards. But Not Including 8 Yards $70.49 7A 3K 8X View Kitsap Power Equipment Operators- Underground Sewer & Water Loaders, Overhead Under 6 Yards $69.87 7A 3K 8X View Kitsap Power Equipment Operators- Underground Sewer & Water Loaders, Plant Feed $69.87 7A 3K 8X View Kitsap Power Equipment Operators- Underground Sewer & Water Loaders: Elevating Type Belt $69.33 7A 3K 8X View Kitsap Power Equipment Operators- Underground Sewer & Water Locomotives, All $69.87 7A 3K 8X View Kitsap Power Equipment Operators- Underground Sewer & Water Material Transfer Device $69.87 7A 3K 8X View Kitsap Power Equipment Operators- Underground Sewer & Water Mechanics, All (leadmen - $0.50 Per Hour Over Mechanic) $71.20 7A 3K 8X View Kitsap Power Equipment Operators- Underground Sewer & Water Motor Patrol Graders $70.49 7A 3K 8X View Kitsap Power Equipment Operators- Underground Sewer & Water Mucking Machine, Mole, Tunnel Drill, Boring, Road Header And/or Shield $70.49 7A 3K 8X View Kitsap Power Equipment Operators- Underground Sewer & Water Oil Distributors, Blower Distribution & Mulch Seeding Operator $66.30 7A 3K 8X View Kitsap Power Equipment Operators- Underground Sewer & Water Outside Hoists (Elevators And Manlifts), Air Tuggers, Strato $69.33 7A 3K 8X View Kitsap Power Equipment Operators- Underground Sewer & Water Overhead, Bridge Type Crane: 20 Tons Through 44 Tons $69.87 7A 3K 8X View DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 8/2/2021 about:blank about:blank 14/18 Kitsap Power Equipment Operators- Underground Sewer & Water Overhead, Bridge Type: 100 Tons And Over $71.20 7A 3K 8X View Kitsap Power Equipment Operators- Underground Sewer & Water Overhead, Bridge Type: 45 Tons Through 99 Tons $70.49 7A 3K 8X View Kitsap Power Equipment Operators- Underground Sewer & Water Pavement Breaker $66.30 7A 3K 8X View Kitsap Power Equipment Operators- Underground Sewer & Water Pile Driver (other Than Crane Mount) $69.87 7A 3K 8X View Kitsap Power Equipment Operators- Underground Sewer & Water Plant Oiler - Asphalt, Crusher $69.33 7A 3K 8X View Kitsap Power Equipment Operators- Underground Sewer & Water Posthole Digger, Mechanical $66.30 7A 3K 8X View Kitsap Power Equipment Operators- Underground Sewer & Water Power Plant $66.30 7A 3K 8X View Kitsap Power Equipment Operators- Underground Sewer & Water Pumps - Water $66.30 7A 3K 8X View Kitsap Power Equipment Operators- Underground Sewer & Water Quad 9, Hd 41, D10 And Over $70.49 7A 3K 8X View Kitsap Power Equipment Operators- Underground Sewer & Water Quick Tower - No Cab, Under 100 Feet In Height Based To Boom $66.30 7A 3K 8X View Kitsap Power Equipment Operators- Underground Sewer & Water Remote Control Operator On Rubber Tired Earth Moving Equipment $70.49 7A 3K 8X View Kitsap Power Equipment Operators- Underground Sewer & Water Rigger and Bellman $66.30 7A 3K 8X View Kitsap Power Equipment Operators- Underground Sewer & Water Rigger/Signal Person, Bellman (Certified) $69.33 7A 3K 8X View Kitsap Power Equipment Operators- Underground Sewer & Water Rollagon $70.49 7A 3K 8X View Kitsap Power Equipment Operators- Underground Sewer & Water Roller, Other Than Plant Mix $66.30 7A 3K 8X View Kitsap Power Equipment Operators- Underground Sewer & Water Roller, Plant Mix Or Multi-lift Materials $69.33 7A 3K 8X View Kitsap Power Equipment Operators- Underground Sewer & Water Roto-mill, Roto-grinder $69.87 7A 3K 8X View Kitsap Power Equipment Operators- Underground Sewer & Water Saws - Concrete $69.33 7A 3K 8X View Kitsap Power Equipment Operators- Underground Sewer & Water Scraper, Self Propelled Under 45 Yards $69.87 7A 3K 8X View Kitsap Power Equipment Operators- Underground Sewer & Water Scrapers - Concrete & Carry All $69.33 7A 3K 8X View Kitsap Power Equipment Operators- Underground Sewer & Water Scrapers, Self-propelled: 45 Yards And Over $70.49 7A 3K 8X View Kitsap Power Equipment Operators- Underground Sewer & Water Service Engineers - Equipment $69.33 7A 3K 8X View Kitsap Power Equipment Operators- Underground Sewer & Water Shotcrete/Gunite Equipment $66.30 7A 3K 8X View Kitsap Power Equipment Operators- Underground Sewer & Water Shovel, Excavator, Backhoe, Tractors Under 15 Metric Tons $69.33 7A 3K 8X View Kitsap Power Equipment Operators- Underground Sewer & Water Shovel, Excavator, Backhoe: Over 30 Metric Tons To 50 Metric Tons $70.49 7A 3K 8X View DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 8/2/2021 about:blank about:blank 15/18 Kitsap Power Equipment Operators- Underground Sewer & Water Shovel, Excavator, Backhoes, Tractors: 15 To 30 Metric Tons $69.87 7A 3K 8X View Kitsap Power Equipment Operators- Underground Sewer & Water Shovel, Excavator, Backhoes: Over 50 Metric Tons To 90 Metric Tons $71.20 7A 3K 8X View Kitsap Power Equipment Operators- Underground Sewer & Water Shovel, Excavator, Backhoes: Over 90 Metric Tons $71.93 7A 3K 8X View Kitsap Power Equipment Operators- Underground Sewer & Water Slipform Pavers $70.49 7A 3K 8X View Kitsap Power Equipment Operators- Underground Sewer & Water Spreader, Topsider & Screedman $70.49 7A 3K 8X View Kitsap Power Equipment Operators- Underground Sewer & Water Subgrader Trimmer $69.87 7A 3K 8X View Kitsap Power Equipment Operators- Underground Sewer & Water Tower Bucket Elevators $69.33 7A 3K 8X View Kitsap Power Equipment Operators- Underground Sewer & Water Tower Crane Up To 175' In Height Base To Boom $71.20 7A 3K 8X View Kitsap Power Equipment Operators- Underground Sewer & Water Tower Crane: over 175' through 250' in height, base to boom $71.93 7A 3K 8X View Kitsap Power Equipment Operators- Underground Sewer & Water Tower Cranes: over 250' in height from base to boom $72.63 7A 3K 8X View Kitsap Power Equipment Operators- Underground Sewer & Water Transporters, All Track Or Truck Type $70.49 7A 3K 8X View Kitsap Power Equipment Operators- Underground Sewer & Water Trenching Machines $69.33 7A 3K 8X View Kitsap Power Equipment Operators- Underground Sewer & Water Truck Crane Oiler/driver - 100 Tons And Over $69.87 7A 3K 8X View Kitsap Power Equipment Operators- Underground Sewer & Water Truck Crane Oiler/Driver Under 100 Tons $69.33 7A 3K 8X View Kitsap Power Equipment Operators- Underground Sewer & Water Truck Mount Portable Conveyor $69.87 7A 3K 8X View Kitsap Power Equipment Operators- Underground Sewer & Water Welder $70.49 7A 3K 8X View Kitsap Power Equipment Operators- Underground Sewer & Water Wheel Tractors, Farmall Type $66.30 7A 3K 8X View Kitsap Power Equipment Operators- Underground Sewer & Water Yo Yo Pay Dozer $69.87 7A 3K 8X View Kitsap Power Line Clearance Tree Trimmers Journey Level In Charge $55.03 5A 4A View Kitsap Power Line Clearance Tree Trimmers Spray Person $52.24 5A 4A View Kitsap Power Line Clearance Tree Trimmers Tree Equipment Operator $55.03 5A 4A View Kitsap Power Line Clearance Tree Trimmers Tree Trimmer $49.21 5A 4A View Kitsap Power Line Clearance Tree Trimmers Tree Trimmer Groundperson $37.47 5A 4A View Kitsap Refrigeration & Air Conditioning Mechanics Journey Level $79.46 5A 1G View Kitsap Residential Brick Mason Journey Level $22.01  1 View Kitsap Residential Carpenters Journey Level $26.25  1 View Kitsap Residential Cement Masons Journey Level $39.88  1 View DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 8/2/2021 about:blank about:blank 16/18 Kitsap Residential Drywall Applicators Journey Level $48.17 7A 4C View Kitsap Residential Drywall Tapers Journey Level $25.84  1 View Kitsap Residential Electricians Journey Level $44.11  1 View Kitsap Residential Glaziers Journey Level $47.80 7L 1H View Kitsap Residential Insulation Applicators Journey Level $18.03  1 View Kitsap Residential Laborers Journey Level $14.71  1 View Kitsap Residential Marble Setters Journey Level $22.01  1 View Kitsap Residential Painters Journey Level $20.85  1 View Kitsap Residential Plumbers & Pipefitters Journey Level $35.92  1 View Kitsap Residential Refrigeration & Air Conditioning Mechanics Journey Level $40.21  1 View Kitsap Residential Sheet Metal Workers Journey Level $32.91  1 View Kitsap Residential Soft Floor Layers Journey Level $22.03  1 View Kitsap Residential Sprinkler Fitters (Fire Protection) Journey Level $31.53  1 View Kitsap Residential Stone Masons Journey Level $60.57 7E 1N View Kitsap Residential Terrazzo Workers Journey Level $14.86  1 View Kitsap Residential Terrazzo/Tile Finishers Journey Level $39.09  1 View Kitsap Residential Tile Setters Journey Level $35.40  1 View Kitsap Roofers Journey Level $57.30 5A 3H View Kitsap Roofers Using Irritable Bituminous Materials $60.30 5A 3H View Kitsap Sheet Metal Workers Journey Level (Field or Shop)$89.61 7F 1E View Kitsap Shipbuilding & Ship Repair New Construction Boilermaker $39.58 7V 1 View Kitsap Shipbuilding & Ship Repair New Construction Carpenter $39.58 7V 1 View Kitsap Shipbuilding & Ship Repair New Construction Crane Operator $39.58 7V 1 View Kitsap Shipbuilding & Ship Repair New Construction Electrician $39.58 7V 1 View Kitsap Shipbuilding & Ship Repair New Construction Heat & Frost Insulator $79.43 15H 11C View Kitsap Shipbuilding & Ship Repair New Construction Laborer $39.58 7V 1 View Kitsap Shipbuilding & Ship Repair New Construction Machinist $39.58 7V 1 View Kitsap Shipbuilding & Ship Repair New Construction Operating Engineer $39.58 7V 1 View Kitsap Shipbuilding & Ship Repair New Construction Painter $39.58 7V 1 View Kitsap Shipbuilding & Ship Repair New Construction Pipefitter $39.58 7V 1 View Kitsap Shipbuilding & Ship Repair New Construction Rigger $39.58 7V 1 View Kitsap Shipbuilding & Ship Repair New Construction Sheet Metal $39.58 7V 1 View Kitsap Shipbuilding & Ship Repair New Construction Shipfitter $39.58 7V 1 View Kitsap Shipbuilding & Ship Repair New Construction Warehouse/Teamster $39.58 7V 1 View Kitsap Shipbuilding & Ship Repair New Construction Welder / Burner $39.58 7V 1 View Kitsap Shipbuilding & Ship Repair Ship Repair Boilermaker $47.45 7X 4J View Kitsap Shipbuilding & Ship Repair Ship Repair Carpenter $47.35 7X 4J View DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 8/2/2021 about:blank about:blank 17/18 Kitsap Shipbuilding & Ship Repair Ship Repair Crane Operator $45.06 7Y 4K View Kitsap Shipbuilding & Ship Repair Ship Repair Electrician $47.42 7X 4J View Kitsap Shipbuilding & Ship Repair Ship Repair Heat & Frost Insulator $79.43 15H 11C View Kitsap Shipbuilding & Ship Repair Ship Repair Laborer $47.35 7X 4J View Kitsap Shipbuilding & Ship Repair Ship Repair Machinist $47.35 7X 4J View Kitsap Shipbuilding & Ship Repair Ship Repair Operating Engineer $45.06 7Y 4K View Kitsap Shipbuilding & Ship Repair Ship Repair Painter $47.35 7X 4J View Kitsap Shipbuilding & Ship Repair Ship Repair Pipefitter $47.35 7X 4J View Kitsap Shipbuilding & Ship Repair Ship Repair Rigger $47.45 7X 4J View Kitsap Shipbuilding & Ship Repair Ship Repair Sheet Metal $47.35 7X 4J View Kitsap Shipbuilding & Ship Repair Ship Repair Shipwright $47.35 7X 4J View Kitsap Shipbuilding & Ship Repair Ship Repair Warehouse / Teamster $45.06 7Y 4K View Kitsap Sign Makers & Installers (Electrical) Journey Level $51.56 0 1 View Kitsap Sign Makers & Installers (Non- Electrical) Journey Level $33.20 0 1 View Kitsap Soft Floor Layers Journey Level $51.91 5A 3J View Kitsap Solar Controls For Windows Journey Level $13.69  1 View Kitsap Sprinkler Fitters (Fire Protection) Journey Level $85.89 5C 1X View Kitsap Stage Rigging Mechanics (Non Structural) Journey Level $13.69  1 View Kitsap Stone Masons Journey Level $60.57 7E 1N View Kitsap Street And Parking Lot Sweeper Workers Journey Level $16.00  1 View Kitsap Surveyors Assistant Construction Site Surveyor $69.33 7A 3K 8X View Kitsap Surveyors Chainman $66.30 7A 3K 8X View Kitsap Surveyors Construction Site Surveyor $70.49 7A 3K 8X View Kitsap Telecommunication Technicians Journey Level $53.57 7E 1E View Kitsap Telephone Line Construction - Outside Cable Splicer $37.40 5A 2B View Kitsap Telephone Line Construction - Outside Hole Digger/Ground Person $25.04 5A 2B View Kitsap Telephone Line Construction - Outside Telephone Equipment Operator (Light) $31.22 5A 2B View Kitsap Telephone Line Construction - Outside Telephone Lineperson $35.34 5A 2B View Kitsap Terrazzo Workers Journey Level $55.71 7E 1N View Kitsap Tile Setters Journey Level $55.71 7E 1N View Kitsap Tile, Marble & Terrazzo Finishers Finisher $46.54 7E 1N View Kitsap Traffic Control Stripers Journey Level $49.13 7A 1K View Kitsap Truck Drivers Asphalt Mix Over 16 Yards $63.80 5D 4Y 8L View Kitsap Truck Drivers Asphalt Mix To 16 Yards $62.96 5D 4Y 8L View Kitsap Truck Drivers Dump Truck $62.96 5D 4Y 8L View Kitsap Truck Drivers Dump Truck & Trailer $63.80 5D 4Y 8L View Kitsap Truck Drivers Other Trucks $63.80 5D 4Y 8L View DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62 8/2/2021 about:blank about:blank 18/18 Kitsap Truck Drivers - Ready Mix Transit Mix $63.80 5D 4Y 8L View Kitsap Well Drillers & Irrigation Pump Installers Irrigation Pump Installer $13.69  1 View Kitsap Well Drillers & Irrigation Pump Installers Oiler $14.08  1 View Kitsap Well Drillers & Irrigation Pump Installers Well Driller $14.40  1 View DocuSign Envelope ID: 35E3A1CF-FE1C-453D-9E00-0C7441C83B62