Contract Modification No. 4
Oyster Bay Beach Sewer Upgrades
CONTRACT MODIFICATION AGREEMENT NO. 4
BETWEEN THE CITY OF BREMERTON AND PARAMETRIX, INC.
PROJECT: Oyster Bay Beach Sewer Upgrades
CONSULTANT: Parametrix, Inc.
DATE: April 5, 2022
THIS CONTRACT MODIFICATION AGREEMENT SPECIFICALLY AMENDS THE
Oyster Bay Beach Sewer Upgrades AGREEMENT (the "Contract") entered into between
the City of Bremerton and Parametrix, Inc. on August 13, 2019).
All provisions in the Contract shall remain in full force and effect except as expressly modified
by this document.
For valuable consideration and by mutual consent of the parties, the modifications to the
Contract are as follows:
I.
Section I. Scope , is modified as follows: See Amendment 4 Scope of Work attached
as Exhibit A.
Section II. Term , is modified as follows:
The term of the contract is not changed.
Section III. Compensation , is modified as follows:
The original contract amount was $437,006. Contract Modification No. 1 increased the contract
amount by $164,490.96, resulting in an amended contract amount of $601,496.96. Contract
Modification No. 2 increased the contract amount by $71,210, resulting in a revised contract
amount of $672,706.96. Contract Modification No. 3 increased the contract amount by
$49,711.71, resulting in a revised contract amount of $722,418.67. This current Contract
Modification No. 4 increases the contract amount by $22,862.90, resulting in a revised contract
amount of $745,281.57.
Exhibit B shows the increased fees for the respective tasks.
II.
Consultant accepts all requirements of this Contract Modification by endorsing below.
Consultant further agrees that this Contract Modification constitutes full and final
settlement of all of the Consultant’s claims for contract time and for all costs of any kind,
including without limitation, costs of delays related to any work either covered or affected
by this Contract Modification, claims related to on-site or home office overhead, or lost
profits. This Contract Modification does not limit the City’s right to bring a claim for past
performance.
DocuSign Envelope ID: 918F7787-3146-4C37-8E5E-51A308854626
Page 2 of 2
Contract Modification No. 4
Oyster Bay Beach Sewer Upgrades
The undersigned consultant approves the foregoing Contract Modification as to the changes,
if any, in the contract price specified for each item, including any and all supervision costs
and other miscellaneous costs relating to the change in work, and as to the extension of time
allowed, if any, for completion of the entire work due to said Contract Modification.
This document will become a supplement of the contract and all provisions will apply hereto.
It is understood that this Contract Modification shall be effective when approved by the City
of Bremerton.
The parties whose names appear below warrant that they are authorized to enter into a
contract modification that is binding on the parties of this contract. In addition, Consultant
warrants that it has or will inform the surety of this change, and shall take appropriate action
to modify any bonds required under the contract to address this change.
IN WITNESS WHEREOF, the parties have executed this Contract Modification on the day
and year first written above.
City Engineer / Public Works Director approved to process _________________________ (Initials and Date)
PARAMETRIX, INC, THE CITY OF BREMERTON
By: By:
Print Name: ____________________ Print Name: Greg Wheeler
Its ___________________________ Its: Mayor
Date: Date:
APPROVED AS TO FORM: ATTEST:
By: By:
KYLIE FINNELL, Bremerton City Attorney ANGELA HOOVER, City Clerk
NOTICES TO BE SENT TO: NOTICES TO BE SENT TO:
Parametrix, Inc Attn: Angela Hoover
Attn: Cedar Simmons City of Bremerton
60 Washington Ave, Suite 390 345 6th Street, Suite 100
Bremerton, WA 98337 Bremerton, WA 98337-1891
Ned Lever
Digitally signed by Ned LeverDN: C=US,
E=ned.lever@ci.bremerton.wa.us, O=City of Bremerton, OU=Engineering, CN=Ned LeverDate: 2022.05.18 13:11:23-07'00'
DocuSign Envelope ID: 918F7787-3146-4C37-8E5E-51A308854626
EP&C Division Manager
5/26/2022
Jenifer Young
5/26/2022
City of Bremerton 233-1896-162
Oyster Bay Beach Sewer Upgrades 1 February 1, 2022
Amendment 4
SCOPE OF WORK
City of Bremerton
Oyster Bay Beach Sewer Upgrades
Amendment 4 – Supplement to Services During Construction
PROJECT BACKGROUND
This project includes the design and installation of grinder pump stations to approximately 53 properties as well
as upland gravity and low-pressure collection system improvements to eliminate sewage backups into Oyster Bay
from failed backflow prevention devices and broken laterals. The overall goal of the project is to reduce the fecal
coliform bacteria pollution and other pollution associated with sewage in Oyster Bay by moving the wastewater
collection system out of marine waters and into an upland system. This project is funded by an SRF loan for
$3,800,000 from the Department of Ecology that expires on December 31, 2022. The City is anticipated to
receive additional funding from Department of Ecology once bids are received.
This amendment is a supplement to existing Task 8, Services During Construction. The scope of work (SOW)
includes services to be executed during the construction phase of this project and outlines additional task
objectives, activities, assumptions, and exclusions. The complete project SOW includes the following tasks, with
additional budget and scope added to Task 8 as presented in this Amendment:
Task 1: Alternatives Analysis
Task 2: Survey
Task 3: Preliminary Design
Task 4: Detailed Design
Task 5: Outreach
Task 6: Environmental Analysis and Permitting
Task 7: Bidding Assistance
Task 8: Services During Construction
Task 9: Project Management
Task 10: Management Reserve
Task 11: Geotechnical Support
Task 12: Electrical Support
Task 13: Force Main Design and Support
AMENDMENT 4 - DETAILED WORK BREAKDOWN
Task 8: Services During Construction
Subtask 8.1: Services During Construction
Provide support to the City’s Project Manager and staff during the construction phase of the project. This is a
supplement to the original contract. All Activities, Assumptions, and Deliverables for this subtask remain the
EXHIBIT A (2 pages)DocuSign Envelope ID: 918F7787-3146-4C37-8E5E-51A308854626
SCOPE OF WORK (continued)
City of Bremerton 233-1896-162
Oyster Bay Beach Sewer Upgrades 2 January 2022
Amendment 4
same except that this supplement provides approximately110 hours of services for approximately a 9-month
duration to be used at the City’s direction on an as-needed basis.
Subtask 8.2: Record Documents Preparation
Objective
Provide project drawings to conform with the Contractor’s construction records.
Activities
• Revise CADD drawings to conform with markups kept by the Contractor during construction.
Assumptions
• Parametrix will not verify completeness and accuracy of the Contractor’s marked up drawing set.
• This task will be started after Contractor has provided a complete marked up drawing set.
• No other record documents besides the Record Drawings will be provided.
Deliverables
• One 22”x34” mylar and two 11”x17” bond hardcopy sets of the Record Drawings.
• CADD files for the project, including sheets and base files (x references), submitted via cloud-based file
transfer site of City’s choice.
• PDF copies of the Record Drawings submitted via cloud-based file transfer site of City’s choice.
DocuSign Envelope ID: 918F7787-3146-4C37-8E5E-51A308854626
Parametrix
Oyster Bay Beach Sewer Upgrades
Contract Modification #4, amount estimated to complete remaining work
Cedar Simmons Joel Linke Jacob Stolle Conner
Whitman TOTAL
PM Sr. Engr Engineer II EE
Rate $230.24 $203.01 $111.27 $227.33
Task 8 - Services During Construction 11 40 75 17 $22,862.90
Item Date Executed Amount Revised
Contract Amt.
Council
Approval
Required?
Original Contract 8/13/2019 437,006.00$ --Yes
Contract Modification #1 12/28/2020 164,490.96$ 601,496.96$ Yes
Contract Modification #2 1/26/2021 71,210.00$ 672,706.96$ No
Contract Modification #3 7/13/2021 49,711.71$ 722,418.67$ Yes
Contract Modification #4 May 2022 22,862.90$ 745,281.57$ No
Summary of Contract Modifications
*Includes hours for field and office support for construction and record drawings
** Management Reserve task is replenished due to additional cost that may be required to complete beach permitting or other
tasks identified