CITY OF BREMERTON 5K
CITY COUNCIL
SUBJECT: Study Session Date: May 8, 2019
Budget Amendments to the 2019 REET and COUNCIL MEETING Date: May 15, 2019
Transportation Capital Funds; and Local Department: PW&U
Agency Professional Services Cost Plus Presenter: Shane Weber
Fixed Fee Consultant Agreement with KPFF Phone: (360) 473-2354
for Design of the 6th Street Preservation
Phase 1 and 2 Projects
SUMMARY: On October 17, 2018, the City accepted the PSRC grant funding for the 6th Street
Preservation Phase 1 project, which will grind and overlay 6th between Callow and Naval Avenues
and reconstruct non-compliant curb ramps. On February 6, 2019, the City accepted PSRC grant
funding for the 6th Street Preservation Phase 2 project, which will construct similar improvements
between Warren and Pacific Avenues, including curb ramp and traffic signal reconstruction at Park
Avenue. Four consultants were interviewed to design the improvements and KPFF was selected.
Phase 1 is budgeted for design in 2019 and construction in 2020. Phase 2 was budgeted for design
in 2020 and construction in 2021; however PSRC has approved an acceleration of the design to
match the Phase 1 schedule for efficiency. While the Phase 2 project is not included in the 2019
REET or Capital budgets, it was included in the 5-year REET projection and the CIP.
ATTACHMENTS: 1) Fiscal Summary; 2) Local Agency Agreement for 6th St. Phase 1 Project;
3) Local Agency Agreement for 6th Street Phase 2 Project
FISCAL IMPACTS (Include Budgeted Amount): The consultant fee for design is estimated at
342,727; see attached fiscal summary for detail. The 2019 REET and Transportation Capital Fund
budgets will be amended to add the Phase 2 project.
STUDY SESSION AGENDA: x Limited Presentation Full Presentation
STUDY SESSION ACTION: Z Consent Agenda General Business Public Hearing
RECOMMENDED MOTION:
Move to amend the 2019 REET and Transportation Capital Fund budgets per the attached fiscal
summary; approve the Local Agency Professional Services Cost Plus Fixed Fee Consultant
Agreements with KPFF for design of the 6th Street Preservation Phase 1 and Phase 2 projects; and
authorize the Mayor to finalize and execute the agreements with substantially the same terms and
conditions as presented.
COUNCIL ACTION: 119Approve Deny Table Continue No Action
Form Updated 01/02/2018
DocuSign Envelope ID: 351ACF5B-BE51-4212-A0C5-3532251D0FFA
DocuSign Envelope ID: 351ACF5B-BE51-4212-A0C5-3532251D0FFA
6/25/2020
6/25/2020
Supplemental Agreement
Number
Organization and Address
Phone:
Original Agreement Number
Project Number Execution Date Completion Date
Project Title New Maximum Amount Payable
Description of Work
The Local Agency of
desires to supplement the agreement entered in to with
and executed on and identified as Agreement No.
All provisions in the basic agreement remain in effect except as expressly modified by this supplement.
The changes to the agreement are described as follows:
I
Section 1, SCOPE OF WORK, is hereby changed to read:
II
Section IV, TIME FOR BEGINNING AND COMPLETION, is amended to change the number of calendar days
for completion of the work to read:
III
Section V, PAYMENT, shall be amended as follows:
as set forth in the attached Exhibit A, and by this reference made a part of this supplement.
If you concur with this supplement and agree to the changes as stated above, please sign in the Appropriate
spaces below and return to this office for final action.
By: By:
Consultant Signature Approving Authority Signature
Date
DOT Form 140-063
Revised 09/2005
City of Bremerton
KPFF Consulting Engineers
May 30, 2019 STPUS-6522(012)
This supplement will provide ongoing project coordination and administration support through construction
completion of the 6th Street Preservation Phase I (Callow Avenue to Naval Avenue) Project. See Attachment
Exhibit A.
September 1, 2021
Additional $ 11,114.37 See Attachment Exhibit B.
1
LA 9543
KPFF Consulting Engineers
1601 Fifth Avenue, Suite 1600
Seattle, WA 98101
206-622-5822
STPUS-6522(012)June 12, 2020 September 1, 2021
6th Street Preservation Phase 1 $ 135,944.85
6th Street Preservation Phase I (Callow Avenue to Naval Avenue) consists of asphalt pavement planning and
overlay, pavement markings, evaluation of existing ADA ramps, reconstruction of non-compliance ADA
ramps within the limits of the project, radar vehicle detection systems at existing signals, utility adjustments,
and other related street improvements. The length of this project is approximately 1,700 feet.
Patrick Sloan
DocuSign Envelope ID: 351ACF5B-BE51-4212-A0C5-3532251D0FFA
Greg Wheeler
6/25/2020
Page 1
City of Bremerton
6th Street Preservation Phase I
Scope of Services
AMENDMENT 1
REVISED 20 MAY 2020
Description
The City of Bremerton (CITY) plans to perform a pavement preservation project along
6th Street between Callow Avenue and Naval Avenue. 6th Street Preservation Phase I
consists of asphalt pavement planning and overlay, pavement markings, traffic signal
improvements, reconstruction of non-compliant ADA ramps within the limits of the
project, utility adjustments, and other related street improvements
Schedule
The construction schedule anticipates a notice to proceed in late-August with substantial
completion within 45 days of that.
The contract Scope of Services is amended as follows:
Task 1 – Project Management
Provide ongoing project coordination and administration through completion of
construction or through the duration of the services described herein.
Deliverables:
• Invoices and Monthly progress statements
Task 6 – Bid Support
CONSULTANT will provide support services to the CITY to respond to Contractor
questions and Requests for Information (RFIs), preparation of Addenda.
Assumptions:
• These services do not include bid reviews, reference checks or preparation of a
recommendation.
Deliverables:
• Responses to bidder questions
• Addenda up to a maximum of two.
Task 7 – Construction Management
CONSULTANT will provide support services to the CITY during construction to include
the following services on an as-needed basis to a maximum of 40 hours.
• Producing an Inspector Daily Report (IDR)
• Providing any photos taken during inspections
DocuSign Envelope ID: 351ACF5B-BE51-4212-A0C5-3532251D0FFA
Page 2
• Verifying that traffic control and materials being used have been approved via the
submittal process
• Filling out Field Acceptance Reports (FAR’s) should material be delivered to the
site.
• Gathering delivery documents for materials arriving on-site
• Quantifying daily bid item work completed
• Tracking equipment and personnel during the inspection period
Assumptions:
• Support services to be provided up to a maximum of 40 hours.
DocuSign Envelope ID: 351ACF5B-BE51-4212-A0C5-3532251D0FFA
Fee Proposal6th Street Preservation Phase IKPFF Consulting Engineers and SubconsultantsDescriptionKPFF(Civil)Concord EngineeringLin & AssociatesHWA GeoSciencesRES Group NWCultural Resources Total CostTask 1 Project Management $ 2,465.49 $ - $ - $ - $ - $ - 2,465.49$ 1.1Preparation of Invoices, Progress Reports and Risk Registry $ 1,391.75 -$ -$ -$ -$ -$ 1,391.75$ 1.2Team Management & QA/QC $ 1,073.74 -$ -$ -$ -$ -$ 1,073.74$ Task 6 Bid Support $ 4,280.58 $ - $ - $ - $ - $ - 4,280.58$ 6.1Respond to Bidder Questions $ 972.03 -$ -$ -$ -$ -$ 972.03$ 6.2Prepare Addenda $ 3,308.55 -$ -$ -$ -$ -$ 3,308.55$ Task 7 Construction Management $ 4,234.00 $ - $ - $ - $ - $ - 4,234.00$ 7.1Construction Support $ 4,234.00 -$ -$ -$ -$ -$ 4,234.00$ $ - -$ -$ -$ -$ -$ -$ 10,980.07$ -$ -$ -$ -$ -$ 10,980.07$ Reimbursable Costs by Firm134.30$ -$ -$ -$ -$ -$ 134.30$ Subtotal11,114.37$ -$ -$ -$ -$ -$ 11,114.37$ Management Reserve-$ (*To be used only with City approval)Total Estimated Budget11,114.37$ 5/20/2020Total Labor Cost by FirmPage 1 of 2DocuSign Envelope ID: 351ACF5B-BE51-4212-A0C5-3532251D0FFA
Fee Proposal6th Street Preservation Phase IKPFF Consulting Engineers (Prime)DescriptionNotes PrincipalProject ManagerSenior Engineer IIISenior Engineer IIDesign Engineer IDesign Engineer I CAD LeadProject Coordinator Total HoursTotal Direct Salary CostTask 1 Project Management0 10 0 0 0 0 0 81.1Preparation of Invoices, Progress Reports and Risk Registry48 12 1,391.75$ 1.2Team Management & QA/QC66 1,073.74$ Task 6 Bid Support0 0 0 4 26 0 12 06.1Respond to Bidder Questions1010 972.03$ 6.2Prepare Addenda4 16 12 32 3,308.55$ Task 7 Construction Management0 0 0 20 207.1Construction Support20 2040 4,234.00$ 0 10 0 24 46 0 12 8 100 10,980.07$ 183.51$ 178.96$ 153.98$ 114.50$ 97.20$ 75.94$ 107.94$ 84.49$ Sub-Totals-$ 1,789.56$ -$ 2,747.91$ 4,471.36$ -$ 1,295.31$ 675.92$ 10,980.07$ Hourly Rate69.72$ 67.99$ 58.50$ 43.50$ 36.93$ 28.85$ 41.01$ 32.10$ Overhead Rate133% 92.87$ 90.57$ 77.93$ 57.95$ 49.19$ 38.43$ 54.63$ 42.76$ Profit30% 20.92$ 20.40$ 17.55$ 13.05$ 11.08$ 8.66$ 12.30$ 9.63$ Full Loaded Rate183.51$ 178.96$ 153.98$ 114.50$ 97.20$ 75.94$ 107.94$ 84.49$ REIMBURSABLESItemQuantity Unit Unit CostSub-Totals TotalsVehicle and Ferry Reimbursables4 EA 15.75$ 63.00$ 63.00$ Mileage124 MILE 0.58$ 71.30$ 71.30$ Miscellaneous Minor Reimbursables0 LS-$ -$ -$ -$ -$ -$ -$ -$ -$ -$ Total 134.30$ KPFF Consulting Engineers (Prime) Total Project Costs11,114$ Total Fee5/20/2020Total Hours per personFully Loaded RatesPage 2 of 2DocuSign Envelope ID: 351ACF5B-BE51-4212-A0C5-3532251D0FFA