HomeMy WebLinkAbout1 - Original Submission_ 20211216_869_CTL Contract Modification #1Page 1 of 2 Contract Modification Rev. 09/2021
CONTRACT MODIFICATION AGREEMENT NO. 001 To City Contract # 6275 BETWEEN THE CITY OF BREMERTON and CONSTRUCTION TESTING LABORATORIES PROJECT Kitsap Way Culvert Replacement VENDOR: Construction Testing Laboratories (CTL)
DATE: December 16, 2021 THIS CONTRACT MODIFICATION AGREEMENT SPECIFICALLY AMENDS THE
AGREEMENT (the "Contract") entered into between the City of Bremerton and CTL on
September 1, 2021. All provisions in the Contract shall remain in full force and effect except as expressly modified by this document.
For valuable consideration and by mutual consent of the parties, the modifications to the Contract are as follows: I.
Section I. Scope , is modified as follows: NO CHANGE Section II. Term , is modified as follows: The term of the Goods and Services Agreement is extended to July 1, 2022.
Section III. Compensation , is modified as follows: NO CHANGE II.
Vendor accepts all requirements of this Contract Modification by endorsing below. Vendor further agrees that this Contract Modification constitutes full and final settlement of all of the Vendor’s claims for contract time and for all costs of any kind, including without limitation, costs of delays related to any work either covered or affected by this Contract
Modification, claims related to on-site or home office overhead, or lost profits. This Contract Modification does not limit the City’s right to bring a claim for past performance. The undersigned Vendor approves the foregoing Contract Modification as to the changes, if any, in the contract price specified for each item, including any and all supervision costs and
other miscellaneous costs relating to the change in work, and as to the extension of time allowed, if any, for completion of the entire work due to said Contract Modification.
DocuSign Envelope ID: 7038AF7B-38DB-48F5-9831-9AA6C22EDDA8
Page 2 of 2 Contract Modification Rev. 09/2021
This document will become a supplement of the contract and all provisions will apply hereto. It is understood that this Contract Modification shall be effective when approved by the City
of Bremerton. The parties whose names appear below warrant that they are authorized to enter into a contract modification that is binding on the parties of this contract. In addition, Vendor warrants that it has or will inform the surety of this change and shall take appropriate action
to modify any bonds required under the contract to address this change. IN WITNESS WHEREOF, the parties have executed this Contract Modification on the day and year first written above.
City Engineer / Public Works Director approved to process _________________________ (Initials and Date) VENDOR THE CITY OF BREMERTON
By: By:
Print Name: Print Name: Greg Wheeler Its: Its: Mayor_____________________ Date: Date:
APPROVED AS TO FORM: ATTEST: By: By:
KYLIE J. FINNELL, Bremerton City Attorney ANGELA HOOVER, City Clerk NOTICES TO BE SENT TO: NOTICES TO BE SENT TO: Chris Pedersen Gunnar Fridriksson
Construction Testing Laboratories Project Manager 400 Valley Avenue NE, Suite 102 City of Bremerton Engineering Dept. Puyallup, WA 98372 345 6th Street, Suite 100 Bremerton, WA 98337
R:\Legal\Legal\Forms\FORMS ON COBWEB\Contract Modification Rev. 09 2021.docx
DocuSign Envelope ID: 7038AF7B-38DB-48F5-9831-9AA6C22EDDA8
1/13/2022
Chris Pedersen
1/13/2022
Operations Manager
1/13/2022