HomeMy WebLinkAbout1 - Original Submission_ 20211227_877_Contract Modification No. 1_StantecPage 1 of 2 Contract Modification Rev. 09/2021
CONTRACT MODIFICATION AGREEMENT NO. 1 BETWEEN THE CITY OF BREMERTON AND STANTEC CONSULTING SERVICES, INC. PROJECT: McDougal Creek/Wheaton Way Culvert Repair Permit Support CONSULTANT: Stantec Consulting Services, Inc. DATE: December 27, 2021 THIS CONTRACT MODIFICATION AGREEMENT SPECIFICALLY AMENDS THE McDougal Creek/Wheaton Way Culvert Repair Permit Support AGREEMENT (the "Contract") entered into between the City of Bremerton and Stantec Consulting Services, Inc. on April 19, 2021. All provisions in the Contract shall remain in full force and effect except as expressly modified by this document.
For valuable consideration and by mutual consent of the parties, the modifications to the Contract are as follows: I.
Section I. Scope , is modified as follows:
The scope of the contract is not changed. Section II. Term , is modified as follows:
The contract end date is extended to July 31, 2022.
Section III. Compensation , is modified as follows: No change to the contract compensation. II. Consultant accepts all requirements of this Contract Modification by endorsing below. Consultant further agrees that this Contract Modification constitutes full and final settlement of all of the Consultant’s claims for contract time and for all costs of any kind, including without limitation, costs of delays related to any work either covered or affected by this Contract Modification, claims related to on-site or home office overhead, or lost profits. This Contract Modification does not limit the City’s right to bring a claim for past performance. The undersigned consultant approves the foregoing Contract Modification as to the changes, if any, in the contract price specified for each item, including any and all supervision costs and other miscellaneous costs relating to the change in work, and as to the extension of time allowed, if any, for completion of the entire work due to said Contract Modification.
DocuSign Envelope ID: 11D1387E-0E3D-448F-839F-FA1472AA1677
Page 2 of 2 Contract Modification Rev. 09/2021
This document will become a supplement of the contract and all provisions will apply hereto. It is understood that this Contract Modification shall be effective when approved by the City of
Bremerton. The parties whose names appear below warrant that they are authorized to enter into a contract modification that is binding on the parties of this contract. In addition, Consultant warrants that it has or will inform the surety of this change, and shall take appropriate action to modify any
bonds required under the contract to address this change. IN WITNESS WHEREOF, the parties have executed this Contract Modification on the day and year first written above.
City Engineer / Public Works Director approved to process _________________________ (Initials and Date) CONSULTANT THE CITY OF BREMERTON
By: By:
Print Name: Print Name: Thomas Knuckey_____ Its: Its: Director of Public Works & Utilities Date: Date:
APPROVED AS TO FORM: ATTEST: By: By:
KYLIE J. FINNELL, Bremerton City Attorney ANGELA HOOVER, City Clerk NOTICES TO BE SENT TO: NOTICES TO BE SENT TO: Joe Richards Gunnar Fridriksson
Stantec Consulting Services, Inc. City of Bremerton-Engineering Dept. 1687 114th Avenue SE Suite 100 345 6th Street, Suite 100 Bellevue, WA 98004-6964 Bremerton, WA 98337-1891
R:\Legal\Legal\Forms\FORMS ON COBWEB\Contract Modification Rev. 09 2021.docx
DocuSign Envelope ID: 11D1387E-0E3D-448F-839F-FA1472AA1677
1/19/2022
Joe Richards
Principal Engineer
1/19/2022
1/19/2022