HomeMy WebLinkAbout1 - Original Submission_ 5869_Change Order #1_Signed_NLCITY OF BREMERTON
CHANGE ORDER
CONTRACT CHANGE ORDER NO: 1
PROJECT NAME: 2022 Sewer Rehabilitation
PROJECT NO: 5846 CONTRACTOR: Michels Corporation
ORIGINAL CONTRACT AMOUNT: $1,033,366.87 DAYS: 120
PREVIOUSLY APPROVED CHANGES: N/A DAYS: 0
THIS CHANGE: $62,772.21 DAYS: 59
REVISED CONTRACT AMOUNT: $1,096,139.08 DAYS: 179
This Change Order covers changes to the subject contract as described herein. The Contractor shall construct, furnish equipment and materials, and perform all work as necessary or required to complete the Change Order Items. The increase or decrease in contract price shown below includes
any applicable taxes.
________________________________________________________________________________ Rule 170 Rule 171 DESCRIPTION OF CHANGES INCREASE IN CONTRACT AMOUNT ($)
(DECREASE) IN CONTRACT AMOUNT ($)
X WCD #1: Due to lead times of up to four months for styrene-free resin, 59 additional calendar days will be added to the Contract. These additional days will bring the total up from 120 calendar days to 179 calendar days with an anticipated
substantial completion date of September 9, 2022.
Additionally, approximately 600 LF of 8-inch sanitary sewer pipe located at Shorewood Dr/Madrona Point Dr will be added to the contract to be lined.
57,589.18 N/A
NET CHANGE IN CONTRACT AMOUNT
INCREASE OR (DECREASE)
57,589.18 N/A
ESTIMATED SALES TAX AT 9.0% 5,183.03 N/A
TOTAL INCLUDING SALES TAX 62,772.21 N/A
Contractor acknowledges and accepts that this Change Order constitutes final settlement of all claims of any kind or nature arising from or connected with any work either covered or affected by this Change Order, including, without limitation, claims related to contract time, on-site or home office
DocuSign Envelope ID: FA11C121-E8F0-47E1-AE0B-F2CDDD1B9227
CONTRACT CHANGE ORDER NO: _1_
PROJECT NAME: 2022 Sewer Rehabilitation
Page 2 of 2
overhead, or lost profits. Nothing in this Change Order shall limit the City’s right to bring a claim for
past performance.
The undersigned Contractor approves the foregoing Change Order as to the changes, if any, in the contract price specified for each item, including any and all supervision costs and other miscellaneous
costs relating to the change in work, and as to the extension of time allowed, if any, for completion of
the entire work due to said Change Order.
This document will become a supplement of the contract and all provisions will apply hereto. It is understood that this Change Order shall be effective when approved by the City of Bremerton.
The parties whose names appear below warrant that they are authorized to enter into a change order that is binding on the parties of this contract. In addition, Contractor warrants that it has or will inform the surety of this change, and shall take appropriate action to modify any bonds required under the contract to address this change.
CONTRACTOR
Accepted: DATE:
PROJECT MANAGER
Recommended: DATE: CITY ENGINEER Council action is required as project cost will exceed approved budget. Yes No Council action is required as change exceeds Mayors authority per BMC 2.76.110. Yes No
Recommended: DATE:
DIRECTOR OF PUBLIC WORKS AND UTILITIES
Recommended: DATE: MAYOR
Approved: DATE:
APPROVED AS TO FORM: ATTEST:
Bremerton City Attorney City Clerk
3/15/22
3/17/22
3/15/22Michele M. Filley
Ned Lever
Digitally signed by Ned LeverDN: C=US, E=ned.lever@ci.bremerton.wa.us, O=City of Bremerton, OU=Engineering, CN=Ned LeverReason: I have reviewed this documentDate: 2022.03.17 14:36:03-07'00'
DocuSign Envelope ID: FA11C121-E8F0-47E1-AE0B-F2CDDD1B9227
4/4/2022
4/4/2022
1
3/10/2022
The following changes are requested for
between Michels Pipe Services and
Item #QTY Unit Price Extended
A-2 1 LS 4,699.18$ 4,699.18$
A-3 600 LF 6.75$ 4,050.00$
A-5 6 EA 240.00$ 1,440.00$
A-6 600 LF 79.00$ 47,400.00$
-$
-$
-$
-$
-$
-$
-$
-$
-$
57,589.18$
778,739.00$
-$
57,589.18$
Sales Tax 9%5,183.03$
Total Change Order Amount 62,772.21$
By signing on the line provided,
Contract Change Order No:
Date Initiated:
2022 Sewer Rehabiliation Project
City of Bremerton
Pre-Installation Cleaning and Video Inspection
Side Sewer Reinstatement
CIPP for 8-inch Sanitary Sewer
Schedule A - Sanitary Sewer (ADD 600LF)
(Owner's Name)
Description
Project Temporary Traffic Control
Total This Request
SCH A - Original Contract Amount
Previous Change Orders
This Change Order
DocuSign Envelope ID: FA11C121-E8F0-47E1-AE0B-F2CDDD1B9227
PAGE 1 OF 1
CITY OF BREMERTON
WORK CHANGE DIRECTIVE (WCD)
WCD #: _______ Date: ________
YOU ARE DIRECTED TO PROCEED PROMPTLY WITH THE FOLLOWING CHANGE(S):
ATTACHMENT(S):
If a claim is made that the above change(s) have affected Contract Price or Contract Times any claim for a Change Order
is based thereon will involve one or more of the following methods of determining the effect of the change(s). The
Change Order will be executed in accordance with Section 1-04.4 of the WSDOT Standard Specifications, or Article 10 of
the General Conditions.
Method of determining change in Contract Price: Method of determining change in Contract Times:
Unit Price Contractor’s Records
Lump Sum Engineer’s Records
Time & Materials
Other: Other:
Estimated increase (decrease) in Contract Price: Estimated increase (decrease) in Contract Times:
$ . Substantial Completion: 0 days;
If the change involves an increase, the estimated Ready for final payment: 0 days;
amount is not to be exceeded without further If the change involves an increase, the estimated times
authorization. are not to be exceeded without further authorization.
RECOMMENDED: AUTHORIZED:
CONTRACTOR CITY OF BREMERTON
By: _Ryan McGraw_______________________________ By: _______Michele Filley__________________
Project Name: _______________
Project #: _______________
Contractor: _______________
NTP Date: _______________
Michele M. Filley
2022 Sewer Rehabilitation
5846
Michels Corporation
1
3/14/22
3/14/22
Perform the cleaning, video inspection and CIPP lining of approximately 600 LF of 8-inch sanitary
sewer lines at Shorewood Dr and Madrona Point Dr per the project specifications.
Michels Corporation quote
4
4
62,772.21 59