HomeMy WebLinkAbout1 - Original Submission_ Parametrix PSA (Modification No. 1)
City of Bremerton 233-1896-8BB
Kitsap Lake Park Improvements 1 December 2020
Modification No. 1
EXHIBIT A
SCOPE OF WORK
MODIFICATION NO. 01
City of Bremerton
Kitsap Lake Park Improvements
INTRODUCTION
This exhibit presents Parametrix’s proposed scope of work (SOW) for work to be performed under Modification
No. 01 under our current contract for the Kitsap Lake Park Renovation project. The work consists of the following:
1. Incorporating the Play Area (shown in the attached conceptual plan) into the project’s plans,
specifications, and estimate (PS&E) deliverables package.
2. Preparing and recording a record of survey for the property’s northern boundary line.
An updated schedule for the project is provided in Exhibit B and our proposed budget is attached as Exhibit C.
The following tasks are associated with this SOW.
Task 02 – Permitting
Objective
Update permit applications to include the new work.
Activities
The following activities would be performed as part of this task:
• Update biological evaluation and permit applications.
Deliverables
The following updated permit applications are deliverables associated with this task.
• Shoreline Substantial Development application with critical area memorandum
• Joint Aquatic Resource Permit Application (JARPA) for USACE Nationwide 3 Permit (maintenance)
• Biological evaluation for informal consultation (to USACE for ESA compliance)
• Hydraulic Project Approval (HPA) application to WDFW
DocuSign Envelope ID: 68764DF5-97F4-4174-AD3C-67471A576768
SCOPE OF WORK (continued)
City of Bremerton 233-1896-8BB
Kitsap Lake Park Improvements 2 December 2020
Modification No. 1
Assumptions
The following assumptions apply to this task:
• Updated drawings, such as a site plan to support the permit applications, will be prepared under the
preliminary design task.
Task 3 – Preliminary Design (30%)
Objective
Prepare 30% plans and engineer’s opinion of probable cost for the play area.
Activities
The following activities would be performed as part of this task:
• Perform a kickoff site walk with City staff.
• Procure a geotechnical subconsultant to perform cone penetrometer test at the Play Area location and
assess the site slopes for suitability for dispersion of drainage from the Play Area.
• Expand drainage requirement evaluation to include Play Area and update drainage technical
memorandum.
• Prepare 30% complete design plans based on City-provided schematics.
• Update 30% engineer’s opinion of probable cost.
Deliverables
The following deliverables will be prepared:
• Plan sheets as follows
Play Area Grading and Drainage Plan 1 sheet at 1-inch = 20-feet scale
1 Sheet Total
• Revised 30% engineer’s opinion of probable cost
• Revised drainage technical memorandum
• Revised draft and final geotechnical report
Assumptions
The following assumptions apply to this task:
• The addition of the Play Area will not trigger treatment or flow control requirements.
DocuSign Envelope ID: 68764DF5-97F4-4174-AD3C-67471A576768
SCOPE OF WORK (continued)
City of Bremerton 233-1896-8BB
Kitsap Lake Park Improvements 3 December 2020
Modification No. 1
Task 4 – 90%, 100%, and Final Plans, Specifications, and Estimates (PS&E)
Objective
Revise 90%, 100%, and final PS&E for the project to include the Play Area.
Activities
The following activities would be performed as part of this task:
• Develop final engineering plans from the 30% plans.
• Prepare an engineer’s opinion of probable cost at each deliverable stage.
• Prepare special provisions at each deliverable stage.
• Prepare contract documents for the 90%, 100%, and final deliverables packages.
Deliverables
The following deliverables will be prepared:
• Plan sheets as follows:
Play Area Grading and Drainage Plan 1 sheet at 1-inch = 20-feet scale
Play Area Grading and Drainage Details 1 sheet
Total Sheets 2
• Revised 60%, 90%, and final engineer’s opinion of probable cost.
• Revised 60%, 90%, and final contract documents.
Assumptions
The following assumptions apply to this task (in addition to the same assumptions as under Task 2):
• Runoff from the Play Area subdrains will be conveyed by buried pipe to the adjacent slope to the west
where it will be dispersed into the established vegetation on the slope.
Task 05 – Survey
Objective
Record a record of survey for the northern boundary of the park property.
Activities
The following activities are associated with this task:
• Calculate boundaries and prepare record of survey exhibit.
• Stake property corners.
• Record exhibit with the Kitsap County Assessor’s office.
DocuSign Envelope ID: 68764DF5-97F4-4174-AD3C-67471A576768
SCOPE OF WORK (continued)
City of Bremerton 233-1896-8BB
Kitsap Lake Park Improvements 4 December 2020
Modification No. 1
Deliverables
The following deliverables are associated with this task:
• Record of survey drawing sealed by a professional surveyor licensed to practice in the state of
Washington.
DocuSign Envelope ID: 68764DF5-97F4-4174-AD3C-67471A576768
SCOPE OF WORK (continued)
City of Bremerton 233-1896-8BB
Kitsap Lake Park Improvements 5 December 2020
Modification No. 1
EXHIBIT B – SCHEDULE
Work Element Completed By
Notice to Proceed October 13, 2020 (actual date)
Survey (complete) November 10, 2020 (actual date)
USACE Permit Application/SEPA December 21, 2020
30% Plans and Cost Estimate January 22, 2021
WDFW Permit Application January 30, 2021
60% PS&E (4 weeks from 30%) February 19, 2021
90% PS&E (5 weeks from 60%) March 26, 2021
Final PS&E (4 weeks from 90%) April 23, 2021
Construction July – October, 2021
Project Closeout September 30, 2021
NOTE: The dates shown have been revised from those shown in the original contract to reflect the actual
notice to proceed date of October 13, 2020.
DocuSign Envelope ID: 68764DF5-97F4-4174-AD3C-67471A576768
PARAMETRIX EXHIBIT C - BUDGET
TOTAL TOTAL
PHASE TASK 3.00 Burdened Labor Rate $231.57 $108.06 $111.03 $151.86 $207.96 $89.58 $128.61 $77.79 $121.74 HOURS COST
1 2 Permitting
Update Biological Evaluation and Permit Applications 8 8 $1,215
Subtotal 8 8 $1,215
1 3 Preliminary Design
Kickoff Site Walk wih City 2 2 4 $679
Update Drainage TM 2 4 6 $907
SHEETS
Play Area Grading and Drainage Plan (1 sheet @ 20 scale)8 16 24 $2,641
SHEET TOTAL - 1
JARPA Figure Update 1 4 5 $676
QC 2 2 $463
Update 30% Engineer's Opinion of Probable Cost 2 4 6 $907
Geotechnical (Shannon & Wilson), incl. 5% markup $840
Subtotal 9 10 28 47 $7,114
1 4 Final Design
SHEETS
Play Area Grading and Drainage Plan (1 sheet @ 20 scale)4 20 24 $2,653
Play Area Grading and Drainage Details (1 sheet)2 8 10 $1,104
SHEET TOTAL - 2
60% Specials 1 2 3 $330
60% Engineer's Opinion of Probable Cost 1 2 3 $330
90% Contract Docs 1 2 3 $330
90% Engineer's Opinion of Probable Cost 1 2 3 $330
Bid Documents and Engineer's Opinion of Probable Cost 1 2 3 $330
QC 2 2 $463
Subtotal 2 11 38 51 $5,871
1 5 Survey
23318968BT
Designer
J. Cerald
Project:
City of Bremerton
STAFFPMX #
Kitsap Lake Park Improvements - Modification 01
BILLING
MULT.:
PM
D. Dinkuhn
Client:
PLS
B. Pusey
Jr. Survey
A. Desplanche
Survey Tech.
S. Sharpe
Survey I
J. Austin
Survey II
K. Allinson
Eng. II
C. Odegard
Sr. Sci.
A. Merrill
Page 1
DocuSign Envelope ID: 68764DF5-97F4-4174-AD3C-67471A576768
PARAMETRIX EXHIBIT C - BUDGET
TOTAL TOTAL
PHASE TASK 3.00 Burdened Labor Rate $231.57 $108.06 $111.03 $151.86 $207.96 $89.58 $128.61 $77.79 $121.74 HOURS COST
23318968BT
Designer
J. Cerald
Project:
City of Bremerton
STAFFPMX #
Kitsap Lake Park Improvements - Modification 01
BILLING
MULT.:
PM
D. Dinkuhn
Client:
PLS
B. Pusey
Jr. Survey
A. Desplanche
Survey Tech.
S. Sharpe
Survey I
J. Austin
Survey II
K. Allinson
Eng. II
C. Odegard
Sr. Sci.
A. Merrill
Stake Corners, Prepare and Record Exhibit 2 4 3 4 8 21 $2,445
Expenses Incl. Recording Fees $400
Subtotal 2 4 3 4 8 21 $2,845
11 21 66 8 2 4 3 4 8 127
PROJECT TOTAL $17,045
D. Dinkuhn, P.E.D. Miller, PE
(Project Manager)(Div. Manager)
Prepared By:
Labor Hours Total
Reviewed By:
Page 2
DocuSign Envelope ID: 68764DF5-97F4-4174-AD3C-67471A576768