SUMMARY: This Agreement with the Washington State Department of Transportation provides the
foundation for the City to take lead on the SR -303 Corridor Planning Study, which was funded by the
Legislature in April of this year.
ATTACHMENTS:
1) Planning Study Agreement; 2) Exhibit A
FISCAL IMPACTS (Include Budgeted Amount): The study was funded by the State at $450,000,
with the city contributing $50,000. Part of this grant match will be provided through necessary City
investment of staff time and fund balance in the Transportation Capital Projects Fund.
STUDY SESSION AGENDA: x Limited Presentation Full Presentation
STUDY SESSION ACTION: Consent Agenda M General Business Public Hearing
RECOMMENDED MOTION:
Move to authorize approval of a Special Transportation Study Agreement with the Washington State
Department of Transportation, and authorize the Mayor to finalize and execute the agreement with
substantially the same terms and conditions as presented; and further authorize a budget adjustment
of $500,000 in expenditures and $450,000 in grant revenue in the Transportation Capital Projects
Fund.
COUNCIL ACTION: I Approve Deny Table Continue No Action
Form Updated 01/02/2018
Ron Landon for JoAnn Schueler
Project Development Engineer
8/21/2020
AM
Washington State
Department of Transportation
June 18, 2018
City of Bremerton
100 Oyster Bay Avenue N.
Bremerton, WA 98312
Olympic Region
5720 Capitol Boulevard, Tumwater
P.O. Box 47440
Olympia, WA 98504-7440
360-357-2600 / FAX: 360-357-2601
TTY: 1-800-833-6388
www.wsdot.wa.gov
SR 303 — Corridor Study — Special Transportation Planning Study
GCB 2932
Attn.: Katie Ketterer
Project Manager
Dear Ms. Ketterer:
Attached for use is an original of the above -mentioned agreement for your records.
If you have any questions, please call Dennis Engel (360) 357-2651 me at (360) 704-
3263.
Sincerely,
Wr�_
Roscoe Ames
Olympic Region Plans Office
Agreements Liaison
RDA:rda
Enclosures:
GCB 3000 original
cc:
Dennis Engel
■lam► _
'/A - - - — T"nsp'ortatlkm
Special Transportation
Planning Study Agreement
Work by Planning Organization - Actual Cost
Agreement Number I Total Amount Authorized
GCB3000 .$450,000
Project Manager
I Agreement Expiration Date
Dennis Engel June 30, 2020
Organization and Address
City of Bremerton
345 6th Street, Suite 100
Bremerton, WA 98337
Project Title and Description
SR-303 Corridor Study
This study will identify safe, reliable and cost effective
transportation options which will improve livability,
attract investment, and increase economic vitality for
people and businesses using practical solutions.
This AGREEMENT, made and entered into this _ /Y _ day of J ciao
2018
between the STATE OF WASHINGTON, Department of Transportation, acting by and through the Secretary of Transportation,
hereinafter called the "STATE," and the above named organization
hereinafter called the "PLANNING AGENCY."
WHEREAS, the STATE and the PLANNING AGENCY recognize the need for the transportation planning project, described above,
and
WHEREAS, it is deemed in the best interest of the STATE to participate in funding said project for the mutual benefit of local and
state roadway planning in the area of the project, and
WHEREAS, the STATE and the PLANNING AGENCY now wish to define responsibility for preparation of the transportation planning
project.
NOW THEREFORE, it is mutually agreed as follows:
Scope of Work
The PLANNING AGENCY shall undertake the Transportation Planning
Project described above, which shall include the tasks set forth in Exhibit
"A," attached hereto.
Schedule
The project period shall commence upon execution of this agreement and
shall last until the expiration date listed above.
III
Payment
The STATE agrees to reimburse the PLANNING AGENCY's actual direct
and related indirect costs of the project. The maximum amount that the
STATE shall reimburse the PLANNING AGENCY shall not exceed the
"Total Amount Authorized" listed above. Payment by task shall be made
as set forth in Exhibit "A." All costs must be consistent with the Federal
cost principles contained in OMB Circular A-87.
The PLANNING AGENCY shall submit to the STATE requests for funds
as they are expended on the project, but not to exceed one such request
every month. Such requests for reimbursement shall document the
amount of funds that have been expended during the period for the total
project, as well as for the current billing period. The STATE shall review
and approve each request for payment in an expeditious manner and
shall make payment within 30 days after approval of the payment request.
DOT Re F sed 3/2008
IV
Reports
The PLANNING AGENCY shall, from time to time during the progress of
the work, confer with the STATE. The PLANNING AGENCY shall prepare
and present to the STATE an annual progress report. The report shall be
completed and submitted to the STATE within 30 calendar days following
the end of each fiscal year. The STATE however, reserves the right to
request an interim report(s) during the fiscal year. The interim report(s) is
due to the STATE within 21 calendar days of being notified in writing by
the STATE. The interim report(s) shall include a summary of work
progress during the course of the fiscal year, costs incurred in accordance
with the approved scope of work and budget, and progress to date,
including any problems or work delays. The STATE may delay
reimbursement of billings if the requested interim report(s) is not
submitted in a timely manner.
Within 30 days after the conclusion of each fiscal year, the PLANNING
AGENCY shall prepare and submit to the STATE an annual progress
report. This annual report shall summarize work accomplished under the
scope of work, costs incurred by work element, and shall identify any
carryover of funds.
A final report documenting the planning project, including interim and task
reports which provide documentation of all technical data and their
analysis, shall be prepared by the PLANNING AGENCY. The PLANNING
AGENCY shall submit five copies of the final report to the STATE for
acceptance. This requirement for a final report may be waived in writing
by the STATE.
V
Modifications
Either party may request changes in these provisions. Such changes
which are mutually agreed upon shall be incorporated as written
amendments to this Agreement. No variation or alteration of the terms of
this Agreement shall be valid unless made in writing and signed by
authorized representatives of the parties hereto.
VI
Audits, Inspection, and Retention of Records
All project records in support of all costs incurred and actual expenditures
kept by the PLANNING AGENCY are to be maintained in accordance with
procedures prescribed by the Division of Municipal Corporations of the
State Auditor's Office, the U.S. Department of Transportation, and the
STATE.
The STATE, and any of its representatives, shall have full access to and
the right to examine, during normal business hours and as often as they
deem necessary, all of the PLANNING AGENCY's records with respect to
all matters covered by this contract. Such representatives shall be
permitted to audit, examine, and make excerpts or transcripts from such
records and to make audits of all contracts, invoices, materials, payrolls,
and other matters covered by this contract. All documents, papers
accounting records, and other material pertaining to costs incurred in
connection with the project shall be retained by the PLANNING AGENCY
for three years after the STATE's written notice that the project is
complete and the Agreement is terminated. Copies thereof shall be
furnished if requested.
In accordance with OMB Circular A-128 regulations, the PLANNING
AGENCY is required to arrange for audit of funds expended.
VII
Termination
If it is considered in the best interests of the STATE, the STATE may
terminate this Agreement upon giving ten (10) days notice in writing to the
PLANNING AGENCY. If this Agreement is so terminated prior to
fulfillment of the terms stated herein, the PLANNING AGENCY shall be
reimbursed only for actual expenses and noncancelable obligations, both
direct and indirect. incurred to the date of termination.
VIII
Legal Relations
The PLANNING AGENCY shall comply with all Federal, State and Local
Laws and Ordinances applicable to the work to be done under this
Agreement.
Each party to this Agreement shall be responsible for damage to persons
or property resulting from the negligence on the part of itself, its
employees, its agents, or its officers. Neither party assumes any
responsibility to the other party for the consequences of any act or
omission of any person, firm, or corporation not a party to this Agreement.
IX
Subcontracting
The services of the PLANNING AGENCY are to be directed by the Project
Manager identified above. The PLANNING AGENCY shall not assign,
sublet, or transfer any of the work provided for under this Agreement
without prior written approval from the STATE, and the STATE shall
review and approve the PLANNING AGENCY's consultant agreement
prior to execution. The PLANNING AGENCY shall comply with all Federal
and State laws and regulations governing the selection and employment
of consultants. The State reserves the right to appoint a representative to
serve on the Consultant Selection Committee. Subcontracts greater than
$10,000 must contain all the required provisions of this contract.
DOT '.,,,.,, 22a_�R� EF
Revs ed•t;?C^B
X
Travel
Any out-of-state travel must have prior written approval of the STATE to
be eligible for reimbursement. Current STATE travel regulations and rates
shall apply to all in -state and out-of-state travel for which reimbursement
is claimed during the term of this Agreement.
XI
Liability
No liability shall attach to the STATE or the PLANNING AGENCY by
reason of entering into this Agreement except as expressly provided
herein.
XII
Independent Contractor
The PLANNING AGENCY shall be deemed an independent contractor for
all purposes and the employees of the PLANNING AGENCY or any of its
contractors, subcontractors, and the employees thereof, shall not in any
manner be deemed to be employees of the STATE.
XIII
Equal Employment Opportunity
The PLANNING AGENCY agrees to abide by all State and Federal
regulations with respect to employment. This includes, but is not limited
to, equal opportunity employment, nondiscrimination assurances, project
record keeping, audits, inspection, and retention of records and will
adhere to all of the nondiscrimination provisions set forth in Exhibit "C"
attached hereto.
XIV
Severability
If any covenant or provision in this Agreement shall be adjudged void,
such adjudication shall not affect the validity, obligation, or performance of
any other covenant or provision which in itself is valid, if such remainder
would then continue to conform to the terms and requirements of
applicable law and the intent of this contract.
XV
Equipment
All equipment to be purchased under this Agreement shall be listed in the
scope of work. All equipment must be purchased, managed, and disposed
of in accordance with OMB Circular A-102 Attachment N
Exhibit C
Title 6, Civil Rights Act of 1964
During the performance of this Agreement, the Planning Agency, for itself,
its assignees, and successors in interest, hereinafter referred to as the
"Consultant," agree as follows:
1. Compliance With Regulations: The Consultant will comply with
the Regulations of the Department of Transportation relative to
nondiscrimination in Federally -assisted programs of the Department
of Transportation Title 49, Code of Federal Regulations, Part 21,
hereinafter referred and made a part of this Agreement.
2. Nondiscrimination: The Consultant, with regard to the work
performed by it after award and prior to completion of the contract
work, will not discriminate on the grounds of race, color, or national
origin in the selection and retention of subcontractors, including
procurements of materials and leases of equipment. The Consultant
will not participate either directly or indirectly in the discrimination
prohibited by Section 8.4 of the Regulations, including employment
practices when the contract covers a program set forth in Appendix
A-11 of the Regulations.
3.
Solicitations for Subcontracts, Including Procurements of
Materials and Equipment: In all solicitations either by competitive
bidding or negotiation made by the Consultant for work to be
performed under a subcontract, including procurements of materials
or equipment, each potential subcontractor or supplier shall be
notified by the Consultant of the Consultant's obligations under this
contract and the Regulations relative to nondiscrimination on the
grounds of race, color, or national origin.
Information and Reports: The Consultant will provide all
information and reports required by the Regulations, or orders and
instructions issued pursuant thereto, and will permit access to its
books, records, accounts, other sources of information, and its
facilities as may be determined by the State Transportation
Department or the Federal Highway Administration to be pertinent to
ascertain compliance with such regulations, orders, and instructions.
Where any information required of the Consultant is in the exclusive
possession of another who fails or refuses to furnish this information,
the Consultant shall so certify to the State Transportation
Department, or the Federal Highway Administration as appropriate,
and shall set forth what efforts it has made to obtain the information.
5. Sanctions for Noncompliance: In the event of the Consultant's
noncompliance with the nondiscrimination provisions of this contract,
the State Transportation Department shall impose such contract
sanctions as it or the Federal Highway Administration may determine
to be appropriate, including, but not limited to:
a. Withholding of payment to the Consultant under the
contract until the consultant complies, and/or
b. Cancellation, termination, or suspension of the contract, in
whole or in part.
6. Incorporation of Provisions: The Consultant will include the
provisions of paragraphs (1) through (6) in every subcontract,
including procurements of materials and leases of equipment, unless
exempt by the Regulations, order, or instructions issued pursuant
thereto. The consultant will take such action with respect to any
subcontract or procurements as the State Transportation Department
or the Federal Highway Administration may direct as a means of
enforcing such provisions including sanctions for noncompliance.
Provided, however, that in the event the consultant becomes
involved in, or is threatened with litigation with a subcontractor or
supplier as a result of such direction, the consultant may request the
State to enter into such litigation to protect the interest of the United
States.
IN WITNESS WHEREOF, the parties hereto have executed this AGREEMENT on the day and year last written below.
PLANNING AGENCY STATE
By "�J By.
Assistant Secretary/Regional Administrator
Title: Mayor
Date: �, ot:-),�
DOT Form 224-080 EF
Revised 312008
Exhibit A
SR-303 Corridor Study
Program: T - Legislative Appropriation 2018
Date: 5/21/18
Agency: City of Bremerton
Project Title: SR 303 Corridor Study
Project Description: SR 303 is a major transportation corridor that bisects Bremerton and is essential to
the economic vitality of the City. The corridor requires modernization; a comprehensive effort is needed
to identify safe, reliable and cost effective transportation options, contextualized to the corridor, which
will improve livability, attract investment, and increase economic vitality for people and businesses.
Project Budget: $450,000 State
$ 50,000 City
Study Management
Estimated Task Budget - $50,000
• Consistent with a Practical Solutions approach to project development, manage overall Study
scope and milestones, including schedule, budget and deliverables.
• WSDOT's endorsement process will be followed throughout the study, this will assist in receiving
acceptance from WSDOT.
• Select and manage consultants to deliver study elements as described in the scope of work.
• Develop the Needs Statement
o In coordination with key stakeholders, develop the vision and goals for the study.
o In coordination with key stakeholders, develop a project charter.
o In coordination with key stakeholders, develop the problem statement. The problem
statement will address barriers and constraints to corridor investment, livability, and
economic vitality. The problem statement will be used to guide the direction of the
study process and also form the basis for measurement to ensure proposed alternatives
are improving the problem.
o In coordination with key stakeholders, identify initial performance measures, targets
and evaluation criteria. Criteria may include effects on mobility; cost/benefit;
environmental concerns; maintenance expense; constructability; partnerships; impact
on livability; attracting new investment, and impact on economic vitality for people and
businesses.
Develop a detailed study scope, including processes and milestones consistent with the Needs
statement.
o Within the scope, where feasible integrate this SR-303 corridor study effort with
adjacent studies impacting the community, including the Harrison/East Side
Employment Center study and the Olympic College Frontage Improvements study.
Develop a Communication Plan describing how meaningful community engagement, including
with stakeholders and the general public, will be accomplished.
o Identify and contact a list of stakeholders that will be needed to complete the study.
Develop a study steering committee or other communication mechanism to ensure
robust and continuous information exchange and feedback.
Page 1 of 4
In addition to the Washington State Department of Transportation and the City
of Bremerton, a partial list of stakeholders includes Kitsap Transit; Olympic
College; the Bremerton School District; the U.S. Navy; Kitsap County: the Port of
Bremerton: the Bremerton Chamber of Commerce: the Downtown Bremerton
Association: the Manette Business Association: the Bremerton ADA Committee:
the West Sound Cycling Club: the Kitsap Economic Development Alliance; the
Suquamish Tribe; offices of State and Federal Senators and Representatives; the
Bremerton Housing Authority; Kitsap Mental Health Services; the Illahee
Preserve; the Central Kitsap School District; property owners along the corridor;
and interested residents.
o Schedule and facilitate community engagement meetings, stakeholder meetings, and
public outreach.
o Develop project email lists to efficiently communicate with, provide information to, and
gain feedback from all stakeholders, experts, and the general public.
® Environmental evaluation: identify the key environmental features along the corridor study
segment and potential environmental issues that might affect or result from various corridor
improvement options.
w Safety: Conduct and document a "Basic Analysis Level" study of the corridor following the
Safety Guidance for Corridor Planning Studies (June 2015). This analysis will be based on a 5-
year crash history.
Data Collection and modeling
Estimated Task Budget: $100,000
Review previous corridor study efforts, including the June 2002 study and the recent Corridor
Sketch initiative. Collect, analyze and summarize existing relevant data along the corridor,
including traffic information, comprehensive plans, land use information, property use and
property valuation. Relate this information to future corridor investment. Incorporate this
information into the development of improvement strategies and projects.
Collect and review the Puget Sound Regional Council (PSRC) demand models. Use the existing
year model and refine the future baseline travel demand model using information from existing
and/or programmed WSDOT or improvement projects in the vicinity, as well as adjacent and
connecting major arterials. Consult recent studies and local comp plans. Traffic volume
forecasts previously developed by WSDOT along this corridor will be compared to forecasted
volumes from this updated model and adjusted as needed.
Collect corridor traffic data as appropriate to create an adequate present -year baseline.
Develop future year baseline traffic volume forecasts for the near -term year 2024, mid-term
year 2030 and the horizon year 2040 for the AM, PM and weekend peak periods. The PSRC
travel demand model does not contain a weekend forecast. Local growth rates from the AM and
PM peak periods will be calculated and applied to the weekend turning movement counts to
develop a weekend peak period forecast
Model existing and future traffic as appropriate to identify existing and future performance
gaps.
Develop and Assess Alternative Strategies
Estimated Task Budget: $125,000
Page 2 of 4
Compile a list of potential corridor strategies developed by the study team, stakeholders, public
input, and other ideas. Include multi -modal strategies such as Transportation Demand
Management, transit improvements and bike/pedestrian improvements in the analysis, relating
all strategies to the needs statement and the requirement for corridor investment.
Refine the evaluation criteria developed in the Needs Statement.
Implement a screening process that includes stakeholder and public outreach. Using qualitative
and quantitative screening criteria, develop recommended strategies to be carried forward for
the next phase of the study. Gain WSDOT concurrence of the screened strategies.
m Present these screened ideas to stakeholders and the community. Document the decision
process and select strategies to be moved forward into the final screening phase and project
development phase.
Refine Solutions
Estimated Task Budget $50,000
• Perform additional analysis on the strategies that pass the preliminary screening to gather more
detailed information about the impact to traffic operations, environmental elements,
multimodal improvements, livability, safety, and economic vitality.
■ Consult with WSDOT to discuss the results and gain concurrence.
■ Rank refined strategies based on performance and how well they meet the performance targets.
Sequence the strategies into short-term, mid-term and long-term timeframes that address low,
medium and high cost options.
• Present the ranked list of strategies to the stakeholders for concurrence. Results and
recommendations will be presented to the public in an open house.
Projects Identification and Planning Level Cost Estimates
Estimated Task Budget $125,000
• Develop planning level cost estimates for each project in the recommended improvement
strategies. Cost estimates will include probable costs attributable to engineering,
environmental, construction and related costs and expressed in today's dollars.
Prepare a draft report documenting the background, assumptions, process and outcome of the
study. The draft report will be submitted to WSDOT for review and comment. The draft report
will be revised based on WSDOT's comments and submitted the stakeholders for review.
• The draft report will contain a matrix of implementable project and/or process improvements to
the corridor, as identified in the previous section. The matrix will include an implementation
plan for each identified project, including timelines and funding sources. Information will also
be communicated with a graphic of the corridor showing the geographic location of projects.
0 Present matrix of projects and draft to the Public in an open house.
Finalize Study Report Including Implementation Plan
Estimated Task Budget: $50,000
■ Update the draft report based on WSDOT, stakeholder, and public comments.
Page 3 of 4
Include a section in the final report listing implementation projects or processes for each
identified strategy.
Submit to WSDOT for review and comment. Update the report based on comments from
WSDOT and submit a final report for endorsement.