HomeMy WebLinkAbout5554AGENDA BILL
CITY OF BREMERTON
CITY COUNCIL
SUBJECT: Amendment No. 1 to the Study Session Date:
Consultant Supplemental Agreement with COUNCIL MEETING Date:
SCJ Alliance for the Lebo Boulevard Department:
Roadway Improvement Project Presenter:
Phone:
7F
April 12, 2017
_April 19, 2017
Public Works
Chal Martin
(360) 473-5758
SUMMARY: This no -cost amendment to SCJ Alliance's design services contract for the Lebo
Boulevard Roadway Improvement Project will extend construction administration services into the
construction phase. This contract is for $54,397 plus a management reserve component of $36,176,
for a'total of $90,573. SCJ Alliance's original design services contract was $591,984. The Lebo
project was designed and bid for $501,411; therefore this amendment changes the scope (as
envisioned in the original contract) to carry SCJ Alliance's services through construction.
ATTACHMENTS:
1. Amendment #1 to SCJ Alliance Consultant Supplemental Agreement
2. Original Agreement
FISCAL IMPACTS (Include Budgeted Amount): The Lebo Boulevard Road Improvement Project is
funded with a Transportation Improvement Board grant of $4,942,722; City Stormwater Utility funding
of $913,514, and City Water Utility funding of approximately $113,000.
STUDY SESSION AGENDA: N No Presentation ❑ Full Presentation
STUDY SESSION ACTION: o Consent Agenda ❑ General Business ❑ Public Hearing
RECOMMENDED MOTION:
Move to approve Amendment No. 1 to SCJ Alliance's consultant services agreement in the amount
of $90,573 for the Lebo Boulevard Roadway Improvement Project; and authorize the Mayor to
finalize and execute the agreement with substantially the same terms and conditions as presented.
COUNCIL ACTION:, [Approve
Form Updated 01/07/15
❑ Deny ❑ Table ❑ Continue ❑ No Action
Transportation Improvement Board
49),Consultant Supplemental Agreement
Agency City of Bremerton Project Number 8-2-152
Project Name Lebo Boulevard Roadway Improvement Project
Consulting Firm Shea, Carr & Jewell, Inc. (dba SCJ Alliance)
Supplement Phase Supplement for Construction Phase
The Local Agency of the City of Bremerton desires to supplement the agreement entered into with and
executed on April 6th, 20116.
All provisions in the basic, agreement remain in effect except as expressly modified by this supplement.
The changes to the agreement are described as follows:
Section II, SCOPE OF WORK, is hereby amended to include
1. Add Construction Administration Services as outlined in the attached Exhibit A
Section IV, TIME FOR BEGINNING AND COMPLETION, is amended to change the Completion Date
SUPPLEMENTAL COMPLETION DATE IJune 30, 2018
Section V, PAYMENT, shall be amended as follows as set forth in Exhibit A
MAXIMUM AMOUNT PAYABLE $591,984
EXHIBIT A
Date
04117117
Original Agreement
Supplement
Total
Direct Salary Cost
Overhead
(including Payroll Additives)
Direct Non -salary Costs
Fixed Fee
Total
$591,984
0
$591,984
If you concur with this supplement and agree to the changes as stated above, please sign and date in the
appropriate spaces below.
Agency Signature
��-
Date
04117117
Consu� Sign tur
Date
o-
s 7
CONSULTANT SUPPLEMENTAL AGE EMENT.DOC
Transportation Improvement Board
Consultant Supplemental Agreement
Exhibit A
Lebo. Boulevard Roadway Improvement Project
Supplemental Agreement for Construction Administration Services
Consultant shall provide Construction Administration Services for the Lebo Boulevard Roadway
Improvement Project as further outlined in this exhibit. Summary:
Estimated staff hours: 272
Estimated subconsultant support: $11,000
Maximum payable for this phase: $54,397
Management reserve: $36,176
CONSULTANT SUPPLEMENTAL AGREEEMENT.DOC
C..
SCOPE OF WORK
AMENDMENT 1
LEBO BOULEVARD ROADWAY IMPROVEMENT PROJECT
BREMERTON, WASHINGTON
Prepared for: Chal Martin, PE, Public Works & Utilities Director
City of Bremerton
Prepared by: Josh Brannin, PE, Project Engineer
Scott Sawyer, PE, Principal
Date prepared: March 31, 2017
Overview
In April 2016, SCJ Alliance (SCJ) contracted with the City of Bremerton (City) to prepare PS&E
documents for the Lebo Boulevard Roadway Improvement Project. The final PS&E package was
submitted on March 7, 2017. The City has requested that SCJ amend the contract and prepare a
scope and fee for construction administration support. The construction services will be led by
the City with SCJ providing support as described in this scope of work.
The original contract budget was $591,984 including a management reserve fund (MRF) of
$53,817. The scope of work under the contract ended on -3/28/17 with a remaining budget of
$90,573 ($53,817 MRF and $36,756 in budget underrun). The remaining budget will fund the
construction administration services scoped below. The fee is estimated at $54,397 with $36,156
in the MRF for a total of $90,573.
The following scope of work is an amendment to the original PS&E and scope for construction
services:
Phase 13 Construction Administration
This phase includes tasks to administer the construction phase in coordination with the City.
Task 1 Management
1) Management: Manage the project by directing and supervising staff and reviewing work
for the duration of the project. This management is for the overall work rather than
specific tasks.
2) Administration: Provide up to six (6) monthly billing statements to the City including
overall budget and schedule confirmation and review for each progress billing period.
Lebo Boulevard Roadway Improvement Project March 30, 2017
City of Bremerton Page 1
SCJ Alliance
Exhibit A - Scope of Work
Task 2 Construction Administration
1) Plan Submittal Reviews: Review and take action on work plans submitted by the
contractor. The City will provide the submittals to SCJ and SCJ will respond back directly
to the City.
2) RFI/RFC: Review and respond to Requests for Information (RFI) submitted by the
Contractor and developing Requests for Change (RFC) exhibits. All responses will be
submitted through the City for final approval. The City will provide responses to the
Contractor.
3) Change Order: SCJ will provide an independent CO estimate when directed by the City.
All documentation will be submitted through the City for final approval. The City will
provide the Contractor with the CO documentation.
4) Field Changes: SCJ will provide up to 48 hours of support to the City for field changes.
Task 3 Meetings
1) Construction Meetings: SCJ will attend up to eight (8) construction meetings/site visits at
the project site or City Public Works.
Understanding
• The City will be the final approving authority.,
• Project management will be provided over a 10 -month timeframe.
• The hours estimated above are for budgeting purposes. The City may request additional
services in total by amendment.
• Progress billings will be submitted monthly to the City.
• The City will process change order payment.
• The City will coordinate all meeting times, locations and invitations.
• Design changes initiated by the City during the construction phase that require additional
design work and drafting are not covered with this task and will be addressed individually
if an amendment is necessary.
• The City will process all pay requests.
Phase 14 Geotechnical Engineering Inspections (GeoEngineers)
Task 1 Geotechnical Engineering Inspections
1) Supplemental Inspection: Provide construction inspection as directed by the City to
supplement the City inspection. Inspection duties include field soil tests and
investigations and monitoring structural excavation.
Understanding
• The City will provide three days' notice when inspection is requested.
• The budgeted estimated is for budgeting purposes. The City may request additional
services in total by amendment.
• SCJ and the subconsultants are not responsible for directing the contractor, nor have any
authority to give verbal and/or written direction to the contractor.
Lebo Boulevard Roadway Improvement Project March 30, 2017
City of Bremerton Page 2
SCJ Alliance
Exhibit A - Scope of Work
• SCJ and the subconsultant are not responsible for job site safety or contractor
compliance with safety regulations.
END OF SCOPE OF WORK
N:\Projects\0753 City of Gig Harbor\0753.01 Harborview Drive Sidewalk I m prove me nt\Contract\Ame nd me nts\Amend
1- Construction Support Services\2017-0122_scope_harborview sidewalks—CM services.doc
Lebo Boulevard Roadway Improvement Project March 30, 2017
City of Bremerton Page 3
Phase 13 (Construction Adminstration
Task 01
Management
Consultant Labor Hour Estimate
1
SG Alliance
16.0
16.0
32.0
2
e
16.0 8.0 24.0
Subtotal Hours:
r
Client:
City of Bremerton
Task 02
Construction Adminstration
SCJ ALLIANCE
Project:
Lebo Boulevard Roadway Improvement Project
Plan Submittal Reviews
4.0
32.0
CON5O11NO6C"°""
Job #:
702.03
4.0
32.0
36.0
3
File #:
2017-0330_ construction support fee estimate_Lebo elvd_.xlsm
40.0
48.0
4
Field Changes
8.0
40.0
Perry
Scott Josh Gary
Dan Miranda Alyse Alissa
Maddie
Task No.
Task Description
Principal
Principal
Project
Senior
Designer
Project LA
Landscap
Project
Project
Total
Subtotal Hours:
Engineer
24.0
Engineer 11
Planner
a Designer
Coord I
Acct
Phase 13 (Construction Adminstration
Task 01
Management
1
Management
16.0
16.0
32.0
2
Administration
16.0 8.0 24.0
Subtotal Hours:
16.0
16.0
16.0 8.0 56.0
Task 02
Construction Adminstration
1
Plan Submittal Reviews
4.0
32.0
36.0
2
RFI/RFC
4.0
32.0
36.0
3
Change Orders
e0
40.0
48.0
4
Field Changes
8.0
40.0
48.0
Subtotal Hogs:
24.0
144.0
168.0
Task 03
Construction Meetings
1
Construction Meetings
zac
za.0
48,0
Subtotal Hours:
24.0
24.0
48.0
Phase 14 Geotechnical Engineering Support (GeoEngineers)
Total Hours All Phases
Total Cost All Phases
272.0
$40,920.00
3/31/2017 Page 1
Consultant Fee Determination
SCJ Alliance
Client: City of Bremerton
Project: Lebo Boulevard Roadway Improvement Project
Job #: 702
Amount
File #: 2017-0330—construction support fee estimate_Lebo Blvd_.xlsm
Consultant Fee Determination
$130.00
SALARY COST
$90.00
Discipline
Hours
Principal
64.0
Project Engineer II
184.0
Project Coord 1
16.0
Project Acct
8.0
Subtotal: 272.0
SUBCONSULTANTS
REIMBURSABLES
a v
"► i
SCJ ALLIANCE
CONSULTING 3EiiVICE9
Rate
Amount
$230.00
$14,720
$130.00
$23,920
$90.00
$1,440
$105.00
$840
Phase 14 Geotechnical Engineering Support
Subconsultant Fee
Subconsultant Markup: 10%
Copies, Reproductions, e; 4.0%
Mileage: 1,500 miles at
SUBTOTAL (SALARY, SUBCONSULTANTS AND EXPENSES)
Subtotal (Salary, Subconsultants and Expenses)
MANAGEMENT RESERVE FUND (MRF)
Total Salary Cost $40,920
GeoEngineers $10,000.00
$10,000
$1,000
Total Subconsultants $11,000
$1,637
$0.560 $840
Total Expenses: $2,477
$54,397
Management Reserve $36,176
Total Estimated Budget: $90,573
3/31/2017 Page 2
AGENDA BILL
CITY OF BREMERTON
CITY COUNCIL
SUBJECT: Establish Lebo Boulevard Road
Improvement Fund; and Award Consultant
Agreement to SCJ Alliance for the Lebo
Boulevard Road Improvement Project
Study Session Date:
COUNCIL MEETING Date:
Department:
Presenter:
Phone:
�vnlraa- w�
March 23, 2016
April 6, 2016
PW&U
Tom Knuckey
(360) 473-2376
SUMMARY: In December, 2016, the City accepted grant funding from the Transportation
Improvement Board (TIB) to make bicycle and pedestrian improvements on Lebo Boulevard from
Lower Wheaton Way to the City Limits. The work will include revising the roadway section to include
bike facilities, wider sidewalks, landscaping, street lighting, stormwater and minor water
improvements. On February 11th three consultants were interviewed, and SCJ Alliance was selected
to perform the design. Since the grant award was received after the Capital Improvement Funds
were established, the Lebo Boulevard Improvement Fund must be established for the work to
proceed.
ATTACHMENTS: 1) Council Summary; and 2) TIB Consultant Agreement with SCJ Alliance
FISCAL IMPACTS (Include Budgeted Amount): A new capital improvement fund, The Lebo
Boulevard Road Improvement Fund, will be created with an expenditure budget of $750,000.
Funding resources are: Transportation Improvement Board grant $595,000, Water fund $35,000,
Wastewater fund $15,000 and Stormwater fund $105,000.
STUDY SESSION AGENDA: ® No Presentation ❑ Full Presentation
STUDY SESSION ACTION: ® Consent Agenda ❑ General Business ❑ Public Hearing
RECOMMENDED MOTION:
Move to establish the Lebo Boulevard Road Improvement Fund; authorize an appropriation
of $750,000 for project design from the identified sources and further, to approve the
Transportation Improvement Board Consultant Agreement with SCJ Alliance; and authorize
the Mayor to finalize and execute the agreement with substantially the same terms and
conditions as presented.
COUNCIL ACTION: d Approve ❑ Deny ❑ Table ❑ Continue ❑ No Action
Form Updated 01/07/15
Transportation Improvement Board (TIB)
Consultant Agreement
TIB PROJECT NUMBER
PROJECT PHASE (check one) Design ❑ Construction
8-2-152(026)-1
PROJECT TITLE & WORK DESCRIPTION
Lebo Boulevard Roadway Improvement Project
This project will demolish and reclaim the existing cement concrete and use it as base material for the new roadway and sidewalk system.
The new roadway will consist of HMA travel lanes and bicycle lanes on both sides, and concrete sidewalks for the pedestrians. Along
Juniper Street, new sidewalks and ADA ramps will be installed leading up to the Warren Avenue Bridge.
CONSULTANT NAME&ADDRESS Shea, Carr & Jewell, Inc. (dba SCJ Alliance)
8730 Tallon Lane NE, Suite 200
Lacey, WA 98516
AGREEMENT TYPE (checkone)
❑ LUMP SUM $
❑ COST PLUS FIXED FEE OVERHEAD PROGRESS PAYMENT RATE %
OVERHEAD COST METHOD
❑ Actual Cost
❑ Actual Cost Not To Exceed %
❑ Fixed Rate %
FIXED FEE $
SPECIFIC RATES OF PAY Negotiated Houdy Rate
❑ Provisional Houdy Rate
❑ COST PER UNIT WORK
DBE PARTICIPATION
WBE PARTICIPATION
❑ Yes CK No %
❑ Yes No
COMPLETION DATE
MAXIMUM AMOUNT PAYABLE
December 31, 2017
$591,984
THIS AGREEMENT, made and entered into this day of kPrirl V� between
the City/County of Bremerton , Washington, hereinafter called the AGENCY, and the
above organization hereinafter called the CONSULTANT. The Transportation Improvement Board hereinafter called the TIB, administers the following accounts: Urban
Arterial Trust Account funds, Transportation Improvement Account funds, Small City Account funds, and City Hardship Assistance Account funds.
WITNESSETH THAT:
WHEREAS, the AGENCY desires to accomplish the above referenced project, with the aid of TIB funds in conformance with the rules and regulations promulgated by the
TIB; and
WHEREAS, the AGENCY does not have sufficient staff to meet the required commitment and therefore deems it advisable and desirable to engage the assistance of a
CONSULTANT to provide the necessary services for the PROJECT; and
WHEREAS, the CONSULTANT represents that he/she is in compliance with the Washington State Statutes relating to professional registration, it applicable, and has
signified a willingness to furnish Consulting services to the AGENCY,
NOW THEREFORE, in consideration of the terms, conditions, covenants and performance contained herein, or attached and incorporated and made a part hereof, the
parties hereto agree as follows:
I II
GENERAL DESCRIPTION OF WORK SCOPE OF WORK
The work under this AGREEMENT shall consist of the above descdbed work and The Scope of Work and project level of effort for this project is detailed in Exhibit B
services as herein defined and necessary to accomplish the completed work for attached hereto, and by this reference made a part of this AGREEMENT.
this PROJECT The CONSULTANT shall furnish all services, labor and related
equipment necessary to conduct and complete the work as designated elsewhere
in this AGREEMENT.
TIB Form 190-016
Revised Oct 2001 Page 1 of 22
III
GENERAL REQUIREMENTS
All aspects of coordination of the work of this AGREEMENT, with outside
agencies, groups or individuals shall receive advance approval by the AGENCY.
Necessary contacts and meetings with agencies, groups or individuals shall be
coordinated through the AGENCY.
The CONSULTANT shall attend coordination, progress and presentation
meetings with the AGENCY or such Federal, Community, State, City or County
officials, groups or individuals as may be requested by the AGENCY. The
AGENCY will provide the CONSULTANT sufficient notice prior to meetings
requiring CONSULTANT participation. The minimum number of hours or days
notice required shall be agreed to between ttie AGENCY and the CONSULTANT
and shown in Exhibit B attached hereto and made part of this AGREEMENT. The
CONSULTANT shall prepare a monthly progress report, in a form approved by
the AGENCY, that will outline in written and graphical form the various phases and
the order of performance of the work in sufficient detail so that the progress of the
work can easily be evaluated. Goals for Disadvantaged Business Enterprises
(DBE), Minority Business Enterprises (MBE), and Women -owned Business
Enterprises (WBE) if required shall be shown in the heading of this Agreement.
The original copies of all reports, PS&E, and other data furnished to the
CONSULTANT by the AGENCY shall be returned. All designs, drawings,
specifications, documents, and other work products prepared by the
CONSULTANT prior to completion or termination of this AGREEMENT are
instruments of service for the PROJECT and are property of the AGENCY. Reuse
by the AGENCY or by others acting through or on behalf of the AGENCY of any
such instruments of service, not occurring as a part of this PROJECT, shall be
without liability of legal exposure to the CONSULTANT.
IV
TIME FOR BEGINNING AND COMPLETION
The CONSULTANT shall not begin any work under the terms of this
AGREEMENT until authorized in writing by the AGENCY All work under this
AGREEMENT shall be completed by the date shown in the heading of this
AGREEMENT under completion date.
The established completion time shall not be extended because of any delays
attributable to the CONSULTANT, but may be extended by the AGENCY, in the
event of a delay attributable to the AGENCY, or because of unavoidable delays
caused by an act of GOD or governmental actions or other conditions beyond the
control of the CONSULTANT. A prior supplemental agreement issued by the
AGENCY is required to extend the established completion time.
V
PAYMENT
The CONSULTANT shall be paid by the AGENCY for completed work and
services rendered under this AGREEMENT as provided in Exhibit C attached
hereto, and by this reference made part of this AGREEMENT Such payment shall
be full compensation for work performed or services rendered and for all labor,
materials, supplies, equipment, and incidentals necessary to complete the work
specified in Section II, Scope of Work
VI
SUBCONTRACTING
The AGENCY permits subcontracts for those items of work as shown in Exhibit G
to this Agreement. Compensation for this subconsultant work shall be based on
the cost factors shown on Exhibit G, attached hereto and by this reference made a
part of this AGREEMENT
•, Transportation Improvement Board (TIB)
Consultant Agreement
The work of the subconsultant shall not exceed its maximum amount payable
unless a prior written approval has been issued by the AGENCY.
All reimbursable direct labor, overhead, direct non -salary costs and fixed fee costs
for the subconsultant shall be substantiated in the same manner as outlined in
Section V. All subcontracts exceeding $10,000 in cost shall contain all applicable
provisions of this AGREEMENT.
The CONSULTANT shall not subcontract for the performance of any work under
this AGREEMENT without prior written permission of the AGENCY. No
permission for subcontracting shall create, between the AGENCY and
subcontractor, any contract or any other relationship.
VII
EMPLOYMENT
The CONSULTANT warrants that helshe has not employed or retained any
company or person, other than a bona fide employee working solely for the
CONSULTANT, to solicit or secure this contract, and that it has not paid or agreed
to pay any company or person, other than a bona fide employee working solely for
the CONSULTANT, any fee, commission, percentage, brokerage fee, gift, or any
other consideration, contingent upon or resulting from the award or making of this
contract. For breach or violation of this warrant, the AGENCY shall have the right
to annul this AGREEMENT without liability, or in its discretion, to deduct from the
AGREEMENT price or consideration or otherwise recover the full amount of such
fee, commission, percentage, brokerage fee, gift, or contingent fee.
Any and all employees of the CONSULTANT or other persons while engaged in
the performance of any work or services required of the CONSULTANT under this
AGREEMENT, shall be considered employees of the CONSULTANT only and not
of the AGENCY, and any and all claims that may or might arise under any
Worker's Compensation Act on behalf of said employees or other persons while
so engaged, and any and all claims made by a third party as a consequence of
any act or omission on the part of the CONSULTANTs employees or other
persons while so engaged on any of the work or services provided to be rendered
herein, shall be the sole obligation and responsibility of the CONSULTANT.
The CONSULTANT shall not engage, on a full or part time basis, or other basis,
during the period of the contract, any professional or technical personnel who are,
or have been, at any time during the period of the contract, in the employ of the
STATE, or the AGENCY, except regularly retired employees, without written
consent of the public employer of such person.
VIII
NONDISCRIMINATION
The CONSULTANT agrees not to discriminate against any client, employee or
applicant for employment or for services because of race, creed, color, national
origin, marital status, sex, age or handicap except for a bona fide occupational
qualification with regard to, but not limited to the following: employment upgrading,
demotion or transfer, recruitment or any recruitment advertising, layoffs or
terminations, rates of pay or other forms of compensation, selection for training,
rendition of services. The CONSULTANT understands and agrees that if it
violates this provision, this AGREEMENT may be terminated by the AGENCY and
further that the CONSULTANT shall be barred from performing any services for
the AGENCY now or in the future unless a showing is made satisfactory to the
AGENCY that discriminatory practices have terminated and that recurrence of
such action is unlikely.
During the performance of this AGREEMENT, the CONSULTANT, for itself, its
assignees, and successors in interest agrees as follows:
A. COMPLIANCE WITH REGULATIONS: The CONSULTANT shall comply
with the Regulations relative to nondiscrimination in the same manner as in
TIB Form 190-016
Revised Oct 2001 Page 2 of 22
B.
C.
0
E.
Federally -assisted programs of the Department of Transportation, Title 49,
Code of Federal Regulations, Part 21, as they may be amended from time
to time, (hereinafter referred to as the Regulations), which are herein
incorporated by reference and made a part of this AGREEMENT
NONDISCRIMINATION: The CONSULTANT, with regard to the work
performed by it during the AGREEMENT, shall not discriminate on the
grounds of race, creed, color, sex, age, marital status, national origin or
handicap except for a bona fide occupational qualification in the selection
and retention of subconsultants, including procurements of materials and
leases of equipment. The CONSULTANT shall not participate either directly
or indirectly in the discrimination prohibited by Section 21.5 of the
Regulations, including employment practices when the contract covers a
program set forth in Appendix II of the Regulations
SOLICITATIONS FOR SUBCONSULTANTS, INCLUDING
PROCUREMENTS OF MATERIALS AND EQUIPMENT: In all solicitations
either by competitive bidding or negotiation made by the CONSULTANT for
work to be performed under a subcontract, including procurements of
materials or leases of equipment, each potential subconsultant or supplier
shall be notified by the CONSULTANT of the CONSULTANTS obligations
under this AGREEMENT and the Regulations relative to nondiscrimination
on the grounds of race, creed, color, sex, age, marital status, national origin
and handicap
INFORMATION AND REPORTS: The CONSULTANT shall provide all
information and reports required by the Regulations, or directives issued
pursuant thereto, and shall permit access to its books, records, accounts,
other sources of information, and its facilities as may be determined by the
AGENCY or TIB to be pertinent to ascertain compliance with such
Regulations or directives. Where any information required of the
CONSULTANT is in the exclusive possession of another who fails or
refuses to furnish this information the CONSULTANT shall so certify to the
AGENCY, or the TIB as appropriate, and shall set forth what efforts it has
made to obtain the information.
SANCTIONS FOR NONCOMPLIANCE- In the event of the
CONSULTANTS noncompliance with the nondiscrimination provisions of
this AGREEMENT, the AGENCY shall impose such sanctions as it or the
Transportation Improvement Board may determine to be appropriate,
including, but not limited to:
1. Withholding of payments to the CONSULTANT under the
AGREEMENT until the CONSULTANT complies, and/or
2. Cancellation, termination or suspension of the AGREEMENT, in
whole or in part
INCORPORATION OF PROVISIONS: The CONSULTANT shall include
the provisions of paragraphs (A) through (G) in every subcontract, including
procurements of materials and leases of equipment, unless exempt by the
Regulations or directives issued pursuant thereto. The CONSULTANT shall
take such action with respect to any subconsultant or procurement as the
AGENCY or the Transportation Improvement Board may direct as a means
of enforcing such provisions including sanctions for noncompliance;
provided, however, that, in the event a CONSULTANT becomes involved in,
or is threatened with, litigation with a subconsultant or supplier as a result of
such direction, the CONSULTANT may request the AGENCY to enter into
such litigation to protect the interests of the AGENCY, and in addition, the
CONSULTANT may request the TIB to enter into such litigation to protect
the interests of the TIB.
G. UNFAIR EMPLOYMENT PRACTICES: The CONSULTANT shall comply
with RCW 49.60.180 prohibiting unfair employment practices and the
TIB Form 190-016
Revised Oct 2001
•Transportation Improvement Board (TIB)
�fi
Consultant Agreement
Executive Orders numbered E.0.70-01 and E.0 66-03 of the Governor of
the State of Washington.
IX
TERMINATION OF AGREEMENT
The right is reserved by the AGENCY to terminate this AGREEMENT at any time
upon ten days written notice to the CONSULTANT.
In the event this AGREEMENT is terminated by the AGENCY other than for fault
on the part of the CONSULTANT, a final payment shall be made to the
CONSULTANT as shown in Exhibit F for the type of AGREEMENT used.
No payment shall be made for any work completed after ten days following receipt
by the CONSULTANT of the Notice of Termination. If the accumulated payment
made to the CONSULTANT prior to Notice of Termination exceeds the total
amount that would be due computed as set forth herein above, then no final
payment shall be due and the CONSULTANT shall immediately reimburse the
AGENCY for any excess paid.
In the event the services of the CONSULTANT are terminated by the AGENCY
for fault on the part of the CONSULTANT, the above formula for payment shall not
apply. In such an event, the amount to be paid shall be determined by the
AGENCY with consideration given to the actual costs incurred by the
CONSULTANT in performing the work to the date of termination, the amount of
work originally required which was satisfactorily completed to date of termination,
whether that work is in a form or a type which is usable to the AGENCY at the
time of termination; the cost to the AGENCY of employing another firm to
complete the work required and the time which maybe required to do so, and
other factors which affect the value to the AGENCY of the work performed at the
time of termination. Under no circumstances shall payment made under this
subsection exceed the amount which would have been made using the formula
set forth in the previous paragraph
If it is determined for any reason that the CONSULTANT was not in default or that
the CONSULTANTs failure to perform is without it or its employees fault or
negligence, the termination shall be deemed to be a termination for the
convenience of the AGENCY in accordance with the provision of this
AGREEMENT.
In the event of the death of any member, partner or officer of the CONSULTANT
or any of its supervisory personnel assigned to the project, or, dissolution of the
partnership, termination of the corporation, or disaffiliation of the principally
involved employee, the surviving members of the CONSULTANT hereby agree to
complete the work under the terms of this AGREEMENT, if requested to do so by
the AGENCY The subsection shall not be a bar to renegotiation of the
AGREEMENT between the surviving members of the CONSULTANT and the
AGENCY, if the AGENCY so chooses.
In the event of the death of any of the parties listed in the previous paragraph,
should the surviving members of the CONSULTANT, with the AGENCYs
concurrence, desire to terminate this AGREEMENT, payment shall be made as
set forth in the second paragraph of this section.
In the event this AGREEMENT is terminated prior to completion, the onginal
copies of all reports and other data, PS&E materials furnished to the
CONSULTANT by the AGENCY and documents prepared by the CONSULTANT
prior to said termination, shall become and remain the property of the AGENCY
and may be used by it without restriction. Such unrestricted use, not occurring as
a part of this PROJECT, shall be without liability or legal exposure to the
CONSULTANT.
Payment for any part of the work by the AGENCY shall not constitute a waiver by
the AGENCY of any remedies of any type it may have against the CONSULTANT
Page 3 of 22
for any breach of this AGREEMENT by the CONSULTANT, or for failure of the
CONSULTANT to perform work required of it by the AGENCY Forbearance of
any rights under the AGREEMENT will not constitute waiver of entitlement to
exercise those rights with respect to any future act or omission by the
CONSULTANT.
X
CHANGES OF WORK
The CONSULTANT shall make such changes and revisions in the complete work
of this AGREEMENT as necessary to correct errors appearing therein, when
required to do so by the AGENCY, without additional compensation thereof.
Should the AGENCY find it desirable for its own purposes to have previously
satisfactorily completed work or parts thereof changed or revised, the
CONSULTANT shall make such revisions as directed by the AGENCY. This work
shall be considered as Extra Work and will be paid for as herein provided under
Section XIV.
XI
DISPUTES
Any dispute concerning questions of fact in connection with the work not disposed
of by AGREEMENT between the CONSULTANT and the AGENCY shall be
referred for determination to the Director of Public Works or AGENCY Engineer,
whose decision in the matter shall be final and binding on the parties of this
AGREEMENT, provided however, that if an action is brought challenging the
Director of Public Works or AGENCY Engineers decision, that decision shall be
subject to the scope of judicial review provided under Washington Case Law
XII
VENUE, APPLICABLE LAW AND
PERSONAL JURISDICTION
In the event that either party deems it necessary to institute legal action or
proceedings to enforce any right or obligation under this AGREEMENT, the
parties hereto agree that any such action shall be initiated in the Superior Court of
the State of Washington, situated in the county the AGENCY is located in. The
parties hereto agree that all questions shall be resolved by application of
Washington law and that the parties to such action shall have the right of appeal
from such decisions of the Superior court in accordance with the laws of the State
of Washington. The CONSULTANT hereby consents to the personal jurisdiction of
the Superior Court of the State of Washington, situated in the county the AGENCY
is located in.
XIII
LEGAL RELATIONS AND INSURANCE
The CONSULTANT shall comply with all Federal, State, and local laws and
ordinances applicable to the work to be done under this AGREEMENT. This
AGREEMENT shall be interpreted and construed in accord with the laws of
Washington.
The CONSULTANT shall indemnify and hold the AGENCY and the STATE of
Washington, and their officers and employees harmless from and shall process
and defend at its own expense all claims, demands, or suits at law or equity
arising in whole or in part from the CONSULTANT's negligence or breach of any
of its obligations under this AGREEMENT; provided that nothing herein shall
require a CONSULTANT to indemnify the AGENCY and the STATE against and
hold harmless the AGENCY and the STATE from claims, demands or suits based
solely upon the conduct of the AGENCY and the STATE, their agents, officers and
employees and provided further that If the claims or suits are caused by or result
from the concurrent negligence of (a) the CONSULTANT's agents or employees
and (b) the AGENCY and the STATE, their agents, officers and employees, this
indemnity provision with respect to (1) claims or suits based upon such
negligence, (2) the costs to the AGENCY and the STATE of defending such
claims and suits, etc. shall be valid and enforceable only to the extent of the
CONSULTANT's negligence or the negligence of the CONSULTANT's agents or
employees.
Transportation Improvement Board (TIB)
Consultant Agreement
The CONSULTANT's relation to the AGENCY shall be at all times as an
independent contractor.
The CONSULTANT specifically assumes potential liability for actions brought by
the CONSULTANT's own employees against the AGENCY and, solely for the
purpose of this indemnification and defense, the CONSULTANT specifically
waives any immunity under the state industrial insurance law, Tale 51 RCW. The
CONSULTANT recognizes that this waiver was specifically entered into pursuant
to the provisions of RCW 4.24.115 and was the subject of mutual negotiation.
Unless otherwise specified in the AGREEMENT, the AGENCY shall be
responsible for administration of construction contracts, if any, on the project.
Subject to the processing of an acceptable, supplemental agreement, the
CONSULTANT shall provide on-call assistance to the AGENCY during contract
administration. By providing such assistance, the CONSULTANT shall assume no
responsibility for: proper construction techniques, job site safety, or any
construction contractor's failure to perform Its work in accordance with the contract
documents.
The CONSULTANT shall obtain and keep in force during the terms of the
AGREEMENT, or as otherwise required, the following insurance with companies
or through sources approved by the State Insurance Commissioner pursuant to
RCW 48.
Insurance Coverage
A. Workers compensation and employers liability insurance as required by the
STATE
B. General commercial liability insurance in an amount not less than a single limit
of one million and 001100 Dollars ($1,000,000.00) for bodily injury, including death
and property damage per occurrence.
Excepting the Workers Compensation insurance and any professional liability
insurance secured by the CONSULTANT, the AGENCY will be named on all
certificates of insurance as an additional insured. The CONSULTANT shall fumish
the AGENCY with verification of insurance and endorsements required by this
AGREEMENT. The AGENCY reserves the right to require complete, certified
copies of all required insurance policies at any time.
All insurance shall be obtained from an insurance company authorized to do
business in the State of Washington. The CONSULTANT shall submit a
verification of insurance as outlined above within 14 days of the execution of this
AGREEMENT to the AGENCY. No cancellation of the foregoing policies shall be
effective without thirty (30) days prior notice to the AGENCY.
The CONSULTANT's professional liability to the AGENCY shall be limited to the
amount payable under this AGREEMENT or one million dollars, whichever is the
greater unless modified by Exhibit H. In no case shall the CONSULTANT's
professional liability to third parties be limited in any way.
The AGENCY will pay no progress payments under Section V until the
CONSULTANT has fully complied with this section. This remedy is not exclusive;
and the AGENCY and the STATE may take such other action as is available to
them under other provisions of this AGREEMENT, or otherwise in law.
XIV
EXTRA WORK
A. The AGENCY may at any time, by written order, make changes within the
general scope of the AGREEMENT in the services to be performed.
TIB Form 190-016
Revised Oct 2001 Page 4 of 22
B. If any such change causes an increase or decrease in the estimated cost of,
or the time required for, performance of any part of the work under this
AGREEMENT, whether or not changed by the order, or otherwise affects
any other terms and conditions of the AGREEMENT, the AGENCY shall
make an equitable adjustment in the (1) maximum amount payable; (2)
delivery or completion schedule, or both; and (3) other affected terms and
shall modify the AGREEMENT accordingly.
C. The CONSULTANT must submit any proposal for adjustment (hereafter
referred to as proposal) under this clause within 30 days from the date of
receipt of the written order. However, if the AGENCY decides that the facts
justify it, the AGENCY may receive and act upon a proposal submitted
before final payment of the AGREEMENT.
D. Failure to agree to any adjustment shall be a dispute under the disputes
clause. However nothing in this clause shall excuse the CONSULTANT
from proceeding with the AGREEMENT as changed.
E. Notwithstanding the terms and condition of paragraphs (a) and (b) above,
the maximum amount payable for this AGREEMENT, shall not be increased
or considered to be increased except by specific written supplement to this
AGREEMENT.
XV
ENDORSEMENT OF PLANS
The CONSULTANT shall place his endorsement on all plans, estimates or any
other engineering data furnished by him.
XVI
TIB AND AGENCY REVIEW
The AGENCY and TIB shall have the right to participate in the review or
examination of the work in progress.
'Q . Transportation Improvement Board (TIB)
IN Consultant Agreement
XVII
CERTIFICATION OF THE
CONSULTANT AND THE AGENCY
Attached hereto as Exhibit A-1, are the Certifications of the Consultant and the
Agency
XVIII
COMPLETE AGREEMENT
This document and referenced attachments contains all covenants, stipulations
and provisions agreed upon by the parties No agent, or representative of either
party has authority to make, and the parties shall not be bound by or be liable for,
any statement, representation, promise or agreement not set forth herein. No
changes, amendments, or modifications of the terms hereof shall be valid unless
reduced to writing and signed by the parties as an amendment to this
AGREEMENT.
XIX
EXECUTION AND ACCEPTANCE
This AGREEMENT may be simultaneously executed in several counterparts,
each of which shall be deemed to be an original having identical legal effect. The
CONSULTANT does hereby ratify and adopt all statements, representations,
warranties, covenants, and agreements contained in the proposal, and the
supporting materials submitted by the CONSULTANT, and does hereby accept
the AGREEMENT and agrees to all of the terms and conditions thereof.
In witness whereof the parties hereto have executed this AGREEMENT as of the day and year first above written.
B By
hrAyo��
Consultant / iradjy City/County of
C%n iW Ka) #6&- e
TIB Form 190-016
Revised Oct 2001 Page 5 of 22
`• Transportation Improvement Board (TIB)
Consultant Agreement
EXHIBIT A-1
Certification of Consultant
Project No. City/County
,)YtW AM4
I hereby certify that I am \ / AI.I'l �.Q.�l� a duly authorized
representative of the firm of 'he Q C a' -r b Tewe& &pa- SCJNjj�wep) whose address is
X -13o ralla-y? Loo Nf,,, Sw'fe 2e0 LaCN, WH . 1 and that
neither I nor the above firm I here represent has:
(a) Employed or retained for a commission, percentage, brokerage, contingent fee or other consideration, any firm or person (other than a
bona fide employee working solely for me or the above CONSULTANT) to solicit or secure this contract.
(b) Agreed, as an express or implied condition for obtaining this contract, to employ or retain the services of a firm or person in connection
with carrying out the contract.
(c) Paid, or agreed to pay, to any firm, organization or person (other than a bona fide employee working solely for me or the above
CONSULTANT) any fee, contribution, donation or consideration of any kind for, or in connection with procuring or carrying out the contract;
except as here expressly stated (if any):
I further certify that the firm I hereby represent is authorized to do business in the State of Washington and that the firm is in full compliance with
requirements of the Board of Professional Registration.
I acknowledge that this certificate is to be available to the Transportation Improvement Board (TIB), in connection with this contract involving
participation of TIB funds and is subject to applicable State and Federal laws, both criminal and civil/,
Date Signature
Certification of Agency Official
I hereby certify that I am the AGENCY Official of the Ciy6enflfp of IB✓Q My,{ c w.
Washington and that the above consulting firm or his/her representative has not been required, directly or indirectly as an express or implied
condition in connection with obtaining or carrying out this contract to:
(a) Employ or retain, or agree to employ or retain, any firm or person, or
(b) Pay or agree to pay to any firm, person or organization, any fee, contribution, donation or consideration of any kind, except as here
expressly stated (if any).
I acknowledge that this certificate is to be available to the TIB, in connection with this contract involving participation of TIB funds and is subject
to applicable State and Federal laws, both criminal and civil.
0410b !6
Date
Signature
TO Form 190-016
Revised Oct 2001 Page 7 of 22
EXHIBIT B-1
Scope of Work
Protect No.
Describe the Scope of Work
See attached.
Documents to be Fumished by the Consultant
,. Transportation Improvement Board (TIB)
Consultant Agreement
TO Form 190-016
Revised Oct 2001 Page 8 of 22
EXHIBIT B-1
SCOPE OF WORK
LEBO BOULEVARD ROADWAY IMPROVEMENT PROJECT
BREMERTON, WASHINGTON
Prepared for: Jerry Hauth, PE, Managing Engineer
City of Bremerton
Prepared by: Scott Sawyer, PE, Associate Principal
Josh Brannin, PE, Project Engineer
Date prepared: March 11, 2016
Overview
The objective of this project is to reconstruct Lebo Boulevard from Sheridan Road to Lower
Wheaton Way and build a sidewalk along Juniper Street from the Warren Avenue Bridge to Lebo
Boulevard. The existing pavement section for Lebo Boulevard is concrete pavement varying in
thickness from four inches to 9 inches. The intent of the project is to rubbelize or crack and seat
the concrete pavement and overlay with asphalt pavement. The methods used to build the
pavement section will be determined as part of the Geotechnical Design.
The City has engaged the public in two outreach meetings to determine the concept layout and
cross-section of Lebo Boulevard. The City provided the concept layout to SCJ Alliance in PDF
format via SO Files on March 7, 2016. The concept shows two travel lanes, parking lane, angled
parking, bicycle lanes, shared use path, sidewalks. The project includes urban design features,
retaining walls, and stormwater facilities (collection/conveyance and treatment).
The design and construction is funded by Transportation Improvement Board Urban Arterial
Program (UAP) Grant with City local match. The intent is to design the project without the need
for right-of-way acquisition, though some City property (south side, east of Warren Avenue
Bridge) may be needed for widening to accommodate angled parking.
The work will consist of the following phases:
1. Project Management
2. Survey and Right of Way Delineation (by MTN2COAST)
3. Alternatives and Concept Design
4. Preliminary Design
5. Geotechnical Design (by GeoEngineers)
6. Urban Design (by HBB Landscape Architecture)
7. SEPA and Permitting
8. Public Involvement
Lebo Boulevard Roadway Improvement Project March 11, 2016
City of Bremerton Page 1
SCJ Alliance
Exhibit A - Scope of Work
9. Final Design
10. Bidding Services
Phases for Additional Waterline Design and Construction Engineering may be added by
amendment.
Assumptions
1. The project may require right of way or easement acquisition from one City owned
property.
2. The limits of road improvements along Lebo Boulevard extend from Sheridan Road to
Lower Wheaton Way (approximately 1.0 miles). It is anticipated improvements will
extend to the end of curb returns for side streets connecting to Lebo Boulevard.
3. The layout of Lebo Boulevard will generally conform to the concept provided by the City,
dated March 7, 2016.
4. Sidewalk will be built to connect Warren Avenue Bridge to Lebo Boulevard. SCJ will
determine the alignment and cross-section for the sidewalk as part of Phase 3 -
Alternatives and Concept Design.
5. Stormwater improvements will include (1) collection and conveyance for the improved -
roadways, and (2) treatment facilities. Flow control is not required because stormwater
is discharged directly,to Port Washington Narrows (exempt water body).
6. SCJ will evaluate the capacity of existing outfalls to Port Washington Narrows, but
modifications to the outfalls are not included in the scope of this project.
7. Sewer improvements are not included.
8. Water improvements are limited to relocation of meters to proposed back of walk and
the upgrade described in Phase 10.
9. The project will construct pedestrian illumination.
10. The project will not underground power and/or communication utilities.
11. The project will not build within the Ordinary High Water Mark (OHWM).
12. The City will be responsible for any pre -condition surveys of buildings adjacent to Lebo
Boulevard prior to rubblizing the existing concrete pavement.
13. Kitsap Transit buses will not require bus pull-outs (extra pavement width) at bus stops.
Information Provided by the City
1. Concept layout and cross-sections for Lebo Boulevard via SCJ Files on March 7, 2016.
2. Pavement cores for Lebo Boulevard.
3. All available as -built drawings for roadway, water, sewer, and stormwater.
4. Potholes of utilities as determined mutually between SCJ and the City.
Phase 1 Project Management
This phase includes tasks to plan, manage, and administer the work; attend project meetings;
and provide quality assurance/quality control.
Lebo Boulevard Roadway Improvement Project March 11, 2016
City of Bremerton Page 2
SCJ Alliance
Exhibit A - Scope of Work
Task 1 Management
1) Management: Manage the project by directing and supervising staff and reviewing
work for the duration of the project. This management is for the overall work rather
than specific tasks.
1) Schedule and Budget: Develop a critical path project schedule to match the scope of
work. Identify task durations, predecessors, City reviews, deliverables, and milestones.
Review and update the schedule on a monthly basis. Monitor project budget on a
biweekly basis. Provide monthly billing statements to the City including overall budget
and schedule confirmation and review for each progress billing period.
Task 2 Administration
1) Progress Reports: Prepare and submit a bi-weekly progress report. Progress reports will
show: (1) prior work performed, (2) current work planned, (3) schedule and budget
status, (4) a summary of scope changes/added value, and (5) items needed from the City
and/or others.
2) Progress Billings: Prepare a monthly progress bill with weekly progress reports
attached. Bills will show staff hours for each phase (i.e., Phase 1: Project Management).
Include a Budget Remaining Report with each invoice.
3) Filing: Develop a project filing system and maintain project files in one centralized
location. Periodically purge draft and redundant documents.
4) Subconsultant Administration: Execute and administer sub agreements. Review and
approve monthly invoices.
Task 3 Quality Assurance/Quality Control
1) Quality Control: Provide senior level review of task deliverables before submittal to the
City.
2) Quality Assurance: Audit quality check activities and documentation on a periodic basis.
Understanding
• Project management will be provided over a 12 -month timeframe.
• Progress billings will be submitted monthly to the City.
• Timelines and milestones will be outlined in a master schedule using Microsoft Project
and will be updated for each progress billing.
• Budget for peer checks for quality control is included within budget for design tasks.
Deliverables
• Bi -weekly Progress Report submitted via email in PDF format.
• Progress billings submitted monthly submitted via email in PDF format.
• MS Project schedule updates submitted via email in PDF format.
Lebo Boulevard Roadway Improvement Project March 11, 2016
City of Bremerton Page 3
SCJ Alliance
Exhibit A - Scope of Work
Phase 2 Survey and Right of Way Delineation (by
MTN2COAST)
Task 1 Survey and Right of Way Delineation
1) Topographic Survey: Perform topographic survey for the Lebo Boulevard corridor from
Sheridan Road to Lower Wheaton Way. Topography will also extend up each side street
for 100 feet. Collect pavement edges, curbs, sidewalks, utilities appurtenances, utility
markings, trees, fences, driveways, mailboxes, road signs, and breaks in topography.
Arrange for utility locate marks (provided by a locater service included in the fee).
Mapping will generally extend to existing rights of way. Include Juniper Street from Lebc
Boulevard to Warren Avenue Bridge (15 feet beyond the existing curb lines or 10 feet
beyond the toe of slope on the inside of the loop ramp area). Survey the shoreline and
OHWM where proposed sidewalks are located within 200 feet of the Port Washington
Narrows shoreline.
2) Right of Way Mapping: Locate monuments and use record right of way maps to
establish existing rights of way for Lebo Boulevard and Juniper Street. Establish rights of
way on side streets for 100 feet from Lebo Boulevard.
3) Base Map: Prepare a topographic base map in AutoCAD, including existing rights of
way. Provide a surface model for the existing ground surface in Civil 3D.
4) Legal Description and Exhibit: Prepare up to one legal description and exhibit for right-
of-way or easement acquisition.
Understanding
• MTN2COAST will prioritize establishment to centerline alignment and stationing for
Lebo Boulevard for the City's use in developing and implementing a pavement coring
plan.
• Field data will be collected on NAD83/91 Washington State Plane Coordinates, North
Zone, Geoid 12A, and NAVD88 Elevation datum.
• Existing side parcel lot lines will not be mapped.
• Base mapping will conform to City Bremerton and APWA standards.
Deliverables
• Topographic base map in AutoCAD format and existing surface in Civil 3D format.
Phase 3 Alternatives and Concept Design
Task 1 Alternatives and Concept Design
1) Lebo Boulevard Cross -Section — Crown vs Shed: Generally the topography transverse to
Lebo Boulevard falls from the north to the south. Raising Lebo Boulevard as part of the
pavement work and widening the sidewalks will create elevation differences between
existing ground and the proposed back of walk. Evaluate the pros and cons for building
the Lebo Boulevard as a crowned pavement section or a shed pavement section
(draining to the south curb). The intent of the shed cross-section is to lessen the
elevation differences. Develop preliminary roadway model assemblies to determine
proposed back of walk elevations. Compare to existing elevations at 25 -foot intervals.
Lebo Boulevard Roadway Improvement Project March 11, 2016
City of Bremerton Page 4
SO Alliance
Exhibit A - Scope of Work
Summarize elevation differences in a tabular format and present in cross-section view.
Coordinate with Phase 5 — Geotechical Design to assess the constructability and cost of
pavement construction for the alternative sections. Prepare a technical memorandum
describing the alternative sections, constructability, concept cost estimates, and relative
elevation differences at the back of walk.
2) Power Pole Relocation: Develop an exhibit showing centerline alignment and stationing
for Lebo Boulevard with existing and recommended locations for power poles. Meet
once with the City and Puget Sound Energy to finalize the alignment for pole
relocations. Prepare a technical memorandum documenting the basis for the proposed
pole locations.
3) Juniper Street Sidewalk: Develop up to two alternative layouts for sidewalk along
Juniper Street from Warren Avenue Bridge to Lebo Boulevard. It is anticipated the
sidewalk will be located along the east side of Juniper Street. The alternatives will
include embankment widening and retaining wall for the sidewalk near the bridge
connection. Develop concept cost estimates for the alternatives. Prepare a technical
memorandum describing the concepts and recommending the preferred alternative.
Analysis will consider functionality/directness for pedestrians, constructability, WSDOT
involvement, and cost.
4) Oak Street/Boat Ramp Access Driveway: Develop a concept layout for the Oak Street
intersection and the Lion's Park boat ramp access driveway. The intent of the layout is
to reduce the amount of impervious surface and shorten crossing distances for
pedestrians. Meet with City staff to review the concept and revise the concept once per
City feedback. Cost estimating for the final layout will be included in Phase 4 —
Preliminary Design. Prepare a technical memorandum describing the basis for the
layout.
Understanding
• None.
Deliverables
• Technical memorandums submitted in PDF via email.
Phase 4 Preliminary Design
Task 1 Data Collection
1) Data Collection: Gather and review available background data and as-builts from the
City. Gather and review system maps from dry utility providers (power and
communication).
2) Photographs: Walk the site and provide photo documentation.
Task 2 Roadway
1) Horizontal Layout
Establish a final design level centerline for Lebo Boulevard, Juniper Street from Lebo
Boulevard to Warren Avenue Bridge, and side streets for approximately 100 feet
from Lebo Boulevard.
Lebo Boulevard Roadway Improvement Project March 11, 2016
City of Bremerton Page 5
SCJ Alliance
Exhibit A - Scope of Work
• Develop preliminary engineering level detail for the roadway layout. Show travel
lanes, turn lanes, on -street parking, bike lanes, curb/gutter, shared use path,
sidewalks, and driveways. Curb returns at side streets will match existing street
width for side streets.
• Define alignment data (bearing and curve data) for the centerline and define
alignment data (station/offset and curve data) for curbs, and edges of pavement.
• Develop up to four typical sections for Lebo Boulevard based on the cross sections
prepared by the City and presented to the public open house on February 22"d
Develop two typical sections for the Juniper Street sidewalk.
• Coordinate with Kitsap Transit to locate bus stops and bus shelters. Consider ADA
accessibility for sidewalk widths at bus stops and shelters.
2) Vertical Layout
• Develop centerline profile for Lebo Boulevard.
Develop curb return profiles, intersection grading for the intersection, and driveway
grades.
• Design ADA ramps (type selection and preliminary grades) at intersections.
3) Frontage Design
• Profile proposed back of sidewalk or edge of pavement for each parcel abutting the
project. Design each site to integrate proposed improvements with the existing
conditions.
Create a frontage conformance exhibit for some abutting parcels (up to 15 parcels
as directed by the City). Each exhibit will include sufficient plan view detail to show
the general public what the site will look like. The exhibits will include a plan view
site plan showing the roadway, pedestrian facilities, existing structures, parking, and
landscaping. The exhibits may include cross sections and profiles as necessary to
demonstrate how the site will be graded. Each exhibit will be at a scale to fit legibly
on 11x17 paper.
Submit frontage conformance exhibits to the City for review. Incorporate revisions
from one City review.
4) Pavement Underdrains: Coordinate with GeoEngineers on design of pavement
underdrains. Develop cross section details to show perforated pipe size and gravel layer
sizing. Layout piping and design connections to stormwater conveyance system.
5) Review Workshop with City: Conduct one (1) design review workshop in Bremerton to
review roadway work in progress. Revise work according to the design review workshop
comments. Provide workshop minutes to the City in PDF via email.
6) Technical Memorandum: Prepare a draft technical memorandum for inclusion in the
Basis for Design Report described under Phase 4. The memorandum will describe
roadway design including standards used to layout the roadway.
Task 3 Stormwater
1) Field Analysis: Meet on site with City staff to walk the site and review existing basin
boundaries and runoff patterns.
Lebo Boulevard Roadway Improvement Project March 11, 2016
City of Bremerton Page 6
SCJ Alliance
Exhibit A - Scope of Work
2) Modeling: Prepare a hydrologic model of the existing and proposed land use conditions
for the limits of disturbance to determine the treatment requirements. Determine
preliminary footprint size of water quality facilities.
3) Downstream Analysis: Calculate pre- and post -project runoff volumes tributary to the
existing storm pipe discharging to Port Washington Narrows and evaluate the hydraulic
capacity of the existing outfalls. Identify potential capacity issues of existing outfalls.
4) Layout: Develop collection and conveyance model based on the hydrodynamic analysis
method (Storm and Sanitary Analysis 2015). Meet with the City to discuss the City's
Eagle Avenue Stormwater Project and consider this project when developing the
collection and conveyance layout. Prepare plan and profile sheets to a preliminary
design level for the stormwater improvements. Show the plan view footprint of water
quality facilities.
5) Draft Stormwater Site Plan: Prepare a draft Stormwater Site Plan (drainage report) for
inclusion in the Basis for Design Report described under Phase 4.
Task 4 Retaining Walls
1) Layout: Prepare horizontal and vertical layout of approximately 300 linear feet of fill
retaining wall to accommodate the proposed angled parking near Warren Avenue
Bridge and approximately 300 linear feet of fill retaining wall for the Juniper Street
sidewalk. Identify horizontal limits of small walls (cut or fill walls 4 feet high or less) to
minimize impacts to front yards at the back of proposed sidewalk.
2) Type Selection: Evaluate fill wall type considering cost and constructability. Discuss
findings/recommendations with the City and select final wall types.
3) Technical Memorandum: Prepare a draft technical memorandum for inclusion in the
Basis for Design Report described under Phase 4. The technical memorandum will
summarize cost, constructability and aesthetic considerations for identifying preferred
wall types.
Task 5 Traffic and Lighting
1) Channelization: Layout striping for Lebo Boulevard. Include lane striping, intersection
markings, and traffic symbols.
2) Stop Warrant: Prepare a stop warrant analysis per the MUTCD to evaluate the need for
4 -way stop control at Cherry Street, Juniper Street, and Sheridan Street.
3) Lighting: Layout spacing and analyze lighting levels for pedestrian scale lighting along
Lebo Boulevard. Base the spacing of lights on City input and representative lighting
calculations for 300 feet of roadway and sidewalk. Perform lighting calculations using
AG132 software. Coordinate light pole style and height with Phase 6 — Urban Design.
4) Construction Sequencing: Develop a strategy for construction of the improvements
describing sequencing, geometric standards during construction, and traffic control
methods. Include exhibits (up to four phases) depicting the sequence of construction.
Meet with City staff to review the strategy. Include the memorandum in the Basis for
Design Report described under Phase 4.
Lebo Boulevard Roadway Improvement Project March 11, 2016
City of Bremerton Page 7
SCJ Alliance
Exhibit A - Scope of Work
5) Technical Memorandum: Prepare a traffic technical memorandum for inclusion in the
Basis for Design Report described under Phase 4. Describe the basis for design for
striping, lighting, and traffic signals.
Task 6 Preliminary Landscape Design
1) Data Collection: Review the project site, collect background information, and research
zoning requirements.
2) Meetings: Attend up to two meetings at the City of Bremerton and one meeting at SCJ
Alliance's Olympia office.
3) Landscape Plan: Prepare preliminary landscape plan including planting palette, tree
locations, and outline of new shrub and lawn areas.
Task 7 Utility Mapping
1) Utility Mapping:
• Obtain system maps and as -built drawings from utility providers. Compare to
survey mapping to verify mapping completeness.
• Field -verify the utility mapping against visible appurtenances and available system
maps.
• Reconcile mapping discrepancies with the City and utility providers.
2) Utility Conflict Technical Memorandum: Prepare a utility conflict technical
memorandum and submit for City review. Evaluate available data to identify utility
conflicts and make recommendations for final resolution. Coordinate with utility
providers to determine cost responsibility for relocations. Identify special construction -
related requirements for each utility. Revise the memorandum once per City
comments. Include the final memorandum in the Basis for Design Report described
under Phase 4.
3) Utility Coordination: Coordinate with Puget Sound Energy on the relocation of power
poles based on the pole alignment identified in Phase 3, Task 1.2. Track progress by
Puget Sound Energy on development of plans and relocation of poles.
Task 8 Preliminary Plans
1) Preliminary Plans: Prepare the following plan types at V=20' scale (unless noted
otherwise). The number of plan sheets per plan type is shown in parentheses.
• Cover (1 sheet)
• Typical Sections (2 sheets)
• Plan and Profile (12 sheets)
• Underdrains (6 sheets)
• Utility Relocation (6 sheets)
• Channelization (6 sheets)
• Illumination (6 sheets)
• Landscape (6 sheets)
Lebo Boulevard Roadway Improvement Project March 11, 2016
City of Bremerton Page 8
SCJ Alliance
Exhibit A - Scope of Work
Task 9 Preliminary Cost Estimate
1) Cost Estimate
• Develop quantities based on the preliminary plans from Phase 4.
• Assign unit costs for quantified items and assign lump sum costs to other items
based on professional judgment.
• Develop a planning level construction estimate that includes a 30% contingency.
Task 10 Basis for Design Report
1) Draft Basis for Design Report: Prepare an executive summary to describe work
completed and decisions made in Phase 4. Include technical memorandums prepared
separately for roadway design, stormwater design, traffic design, traffic control strategy,
and utility conflict. Include preliminary plans and cost estimates. Submit to the City for
review.
2) Final Basis for Design Report: Revise the report once per City comments.
Understanding
• Roadway design is based on City of Bremerton Engineering and Construction Standards.
• Power pole relocations will be shown on the Roadway Plan & Profile sheets.
• Drainage design is based on Department of Ecology, Stormwater Management Manual
for Western Washington, 2012.
• Lebo Boulevard is a minor arterial per the City of Bremerton Engineering and
Construction Standards.
• For budget purposes, it is assumed the larger fill retaining walls will be either structural
earth wall (SEW) or WSDOT Standard Plan cast -in-place concrete wall. Structural design
for custom retaining walls is not included. The fill walls are assumed to be less than 10
feet in retained height.
• Embankment widening will be selected as the preferred alternative for the Juniper
Street Sidewalk. Therefore, retaining wall design is not included for this location.
• Small walls (less than 4 feet high) to minimize impacts to front yards will be used at up
to 15 parcels.
• Roadway and/or intersection lighting is not included.
• Planting areas include the following:
o The area north of Lebo Boulevard between Sheridan Street and Oak Street.
o The frontage to Lebo Boulevard at the Lion's Park parking lot (replacing cherry
trees).
o The frontage of Lebo Boulevard at the on -street angled parking (south side of
Lebo, east of Warren Avenue Bridge).
o The frontage of Lebo Boulevard at the Parks & Recreation building.
o Gateway entry treatments —Sheridan and Wheaton Way.
Deliverables
• Meeting summaries submitted in PDF via email.
• Utility Conflict technical memorandum submitted in PDF via email.
• Preliminary Plans (11"x17") submitted in PDF via email.
Lebo Boulevard Roadway Improvement Project March 11, 2016
City of Bremerton Page 9
SCJ Alliance
Exhibit A'- Scope of Work
• Basis for Design Report submitted in PDF via email.
Phase 5 Geotechnical Design (by GeoEngineers)
Task 1 Site Investigation and Feasibility Evaluation
1) Visual Condition: Perform a visual condition survey of the existing pavement. Use the
American Association of State Highway and Transportation Officials (AASHTO)/Federal
Highway Administration (FHWA) Pavement Moisture Accelerated Distress Identification
System in our evaluation.
2) Traffic Control: Prepare traffic control plans and provide traffic control to include
signage and flaggers during Falling Weight Deflectometer (FWD) testing and auger
drilling described below.
3) Street Use Permit: Obtain a street use permit to perform site exploration activities
described below. The City will pay the permit fee.
4) Falling Weight Deflectometer: Perform a FWD survey to assess PCC and subgrade
strength. Select existing PCC panels will be tested at about 500 -foot intervals along each
travel lane to establish a general support profile along the alignment. FWD tests will not
be taken at the panel edges because rubblization or crack and seat methods are to be
used as opposed to leaving the existing PCC intact.
5) One -call Notification: Contact the One Call Utility Notification system to clear proposed
exploration locations for presence of underground utilities as required by Washington
State law.
6) Borings: Perform up to 10 hollow -stem auger borings at select locations along the
alignment to further assess subgrade conditions and at planned retaining wall locations.
We understand retaining walls are anticipated at two locations (south side of Lebo
Boulevard east of Warren Avenue Bridge and Juniper Street near the Warren Avenue
Bridge connection). For budgeting purposes we have assumed each boring will typically
be drilled to a depth of 10 feet below existing grade or less (budget estimate is for 110
linear feet of drilling) and that the existing PCC pavement will be cored and patched at
each boring location (assumed slab thickness up to 8 inches). We will perform insitu
sampling at 2.5 -foot depth intervals in each boring in accordance with ASTM
International (ASTM) D 1586 (Standard Penetration Test) procedures.
7) Test Pits: Perform up to six backhoe test pits in the existing unimproved grass and shrub
covered area along the toe of the current embankment on the Warren Avenue Bridge
on-ramp to evaluate conditions for the proposed enlarged fill prism or fill retaining wall.
8) Laboratory Testing: Perform laboratory testing including moisture content and
gradation analysis on select samples obtained from the explorations.
9) Pavement Design: Evaluate feasibility and constraints for accomplishing pavement
reconstruction by rubblizing or cracking and seating the PCC. We anticipate discussing
each of these potential options with specialty contractors to identify critical design and
construction considerations. Develop recommendations for pavement underdrains.
Lebo Boulevard Roadway Improvement Project March 11, 2016
City of Bremerton Page 10
SCJ Alliance
Exhibit A - Scope of Work
10) Asphalt Overlay: Develop preliminary pavement design sections for new hot mix asphalt
(HMA) overlays for the reconstructed pavement.
11) Draft Report: Present the preliminary study results in a draft geotechnical report for
review by the project team.
Task 2 Consultation and Final Design
1) Team Meeting: Meet with the design team to discuss our findings and preliminary
conclusions and obtain consensus on a preferred option to advance to final design.
2) Final Report: Prepare final geotechnical recommendations for the selected
reconstruction option. We anticipate addressing the following:
• General earthwork recommendations including subgrade preparation, criteria for
imported structural fill, fill placement and compaction criteria, and utility trench
backfilling.
• Subdrainage measures appropriate to the selected pavement reconstruction option.
• Recommendations for overlay and base course layer thickness as appropriate for
the selected option. We will require performance criteria such as Equivalent Single
Axle Loads (ESALs) or anticipated average daily traffic counts and projected growth
rates to complete our analysis.
• Lateral earth pressure criteria for design of conventional retaining walls, including
seismic and traffic surcharge values, and a recommended allowable soil bearing
pressure. We will provide geotechnical recommendations for cast -in-place or
contractor -designed structural earth walls and discuss wall drainage.
• Construction considerations specific to the selected pavement reconstruction
option.
Understanding
• The City will pay Street Use Permit fees.
• The planned explorations do not include an environmental site assessment -and the site
is assumed to be "clean" regarding hazardous or contaminated materials.
Deliverables
• Traffic Control Plan submitted in PDF via email.
• Geotechnical Design Report in PDF via email.
Phase 6 Urban Design (by HBB Landscape Architecture)
Task 1 Concept Design
1) Urban Design Alternatives:
• Field walk the site.
• Develop alternatives for finish treatments at entryway sidewalks, mid -block
crossings, and bus stops (plan view layout).
• Develop alternatives for site furnishing for benches and trash receptacles (one
presentation board).
• Subcontract and coordinate with a sign design company to develop entry sign
concepts (billed as expense).
Lebo Boulevard Roadway Improvement Project March 11, 2016
City of Bremerton Page 11
SCJ Alliance
Exhibit A - Scope of Work
• Develop alternatives for lighting options and column treatments for the Warren
Avenue Bridge Portal (one presentation board).
• Photoshop Renderings: Develop one presentation board depicting alternatives for
entry areas, mid -block pedestrian crossings, bus stops, and the Warren Avenue
Bridge portal.
• Concepts Cost Estimate: Develop a concept cost estimates for alternatives for site
furnishings and portal column treatments.
2) Preferred Urban Design Features:
• Coordinate with the City to select and refine the preferred urban design features;
street furnishings, pedestrian light poles and fixtures, and paving finishes (1
materials and finishes board).
• Coordinate with the City to select and refine the preferred portal concept (1
materials/concept rendering board).
• Prepare a preferred concept cost estimate for Urban Design features.
• Subcontract and coordinate with a sign design company to prepare a preferred sign
concept (1 presentation board with materials and cost estimate) (billed as expense).
3) Proprietary Materials Justification:
• Prepare a justification letter for proprietary materials for pedestrian light
pole/fixtures and entry sign.
Task 2 Community Outreach
1) Open House: Attend one Open House meeting. Budget for presentation boards is
included in Task 1 above.
Task 3 90% Plans and Specifications
1) Urban Design Elements:
• Prepare details for urban design elements (1 plan).
• Prepare paving pattern enlargement with key map (1 plan).
• Prepare special provisions for the urban design elements.
• Prepare cost estimates for the urban design elements.
2) Entry Sign: Coordinate and subcontract with a sign design company to prepare the
design intent (materials, dimensions, and costs) (billed as expense)
Task 4 Bid Support
1) Bid Support: Provide up to 4 hours of bidding support as directed by the City.
Understanding
• Urban Design features will be shown on the Plan and Profile and/or Paving sheets.
• Site furnishings will be off the shelf products, custom design furnishings are not
included.
• Sidewalk paving materials and finishes are based on cast -in-place concrete material and
textures.
Lebo Boulevard Roadway Improvement Project March 11, 2016
City of Bremerton Page 12
SCJ Alliance
Exhibit A - Scope of Work
Deliverables
• Urban design concept alternatives (4 sheets)
• Urban design preferred alternative (3 sheets)
• Urban design details (1 sheet)
• Paving pattern enlargement plan (1 sheet)
• Urban design special provisions
• Urban design cost estimate
• Justification letter for proprietary products
• Entry sign design, specifications and cost estimate (by Tube Art)
Phase 7 SEPA/NEPA and Permitting
Task 1 SEPA/NEPA and Permitting
1) SEPA Checklist: Prepare a SEPA Checklist.
2) Ordinary High Water Mark Mapping:
• Conduct research to create base maps and review local codes.
• Flag the OHWM in the field and coordinate with the project surveyor.
• Prepare a technical memorandum describing the mapping methodology and results.
3) Shoreline Substantial Development Permit: Prepare JARPA application and submit to
City. Coordinate with City planning staff during review of permit. Develop required
mitigation plan for any identified impacts.
4) NPDES Permit: Prepare a notice of intent for a Construction Stormwater General Permit
from the Department of Ecology.
5) Critical Areas Ordinance: Prepare documentation that project complies with the City's
Critical Areas Ordinance.
Understanding
• Federal funds will not be used for the project.
• State funds (TIB grant) will be used for the project.
• There are no wetland impacts.
• There is no work within the OHWM.
• There are no discipline reports required for the SEPA Checklist, except the Stormwater
Report prepared under Phase 9.
• WDFW Hydraulic Project Approval and US Army Corps Section 10 permits are not
required for changes in runoff volume to the existing close conduit discharges to Port
Washington Narrows.
• The SEPA determination will be Determination of Non -Significance.
Deliverables
• SEPA Checklist submitted in PDF via email.
• Shoreline Substantial Development Permit submitted in PDF via email.
• Mitigation Plan submitted to City to address impacts to shoreline and critical area
buffers.
Lebo Boulevard Roadway Improvement Project March 11, 2016
City of Bremerton Page 13
SCJ Alliance
Exhibit A - Scope of Work
Phase 8 Public Involvement
Task 1 Public Involvement
1) Focus Meetings: Support the City in meeting with individual property owners and/or
business owners to discuss the project and gather input.
2) Council Briefings: Provide up to two Council briefings to report on project progress and
gather Council input and/or endorsement. Prepare notes from the meetings to
document key decisions and/or action items.
3) Public Meetings: Hold up to two public information meetings to report on project
progress and gather public feedback. The meetings generally will be timed to occur one
to two weeks after the Council briefings. Prepare graphic materials for discussion
purposes. Prepare notes from the meetings to document key decisions and/or action
items.
4) Project Website: Provide graphic and written materials to the City for posting on the
City's project website.
Understanding
• The City Council will endorse major project decisions based on information provided at
the Council Briefings.
• Support for Focus Meetings is budgeted at 32 hours.
• Website support is budgeted for 16 hours.
Deliverables
• Meetings summaries for focus meetings, public information meetings, and Council
briefings submitted in PDF via email.
• Graphics and written materials for the City to post to the project website.
Phase 9 Final Design
Task 1 Utility Coordination
1) Identify Potholing Locations: Based on potential utility conflicts identified under Phase
4, identify requested potholing locations and submit to the City.
2) Potholing: Oversee potholing activities. Up to twelve (12) hours of project engineer
time and two trips to the project have been included. It is anticipated this work will
occur after identifying conflicts in Phase 4, Task 7.2 and prior to beginning Final Design
work.
3) Incorporate Potholing Data: Incorporate potholing data into Civil3D model and review
for potential conflicts.
4) Identify Conflicts: Identify utilities requiring relocation and notify utility providers by
phone, email, and US mail. Determine if providers will relocate conflicting utilities prior
to or during construction. Prepare a relocation tracking matrix and monitor progress by
providers to relocate utilities.
Lebo Boulevard Roadway Improvement Project March 11, 2016
City of Bremerton Page 14
SCJ Alliance
Exhibit A - Scope of Work
Task 2 Roadway
1) Horizontal Layout: Finalize the horizontal layout.
2) Vertical Layout: Determine final centerline grade; develop final curb return profiles and
intersection grading (16 intersections); develop final driveway profiles for up to 55
driveways; and detail ADA ramps, roadway intersections, and driveways. Develop final
back of sidewalk grades and design conformance to existing front yards.
Task 3 Drainage
1) Collection and Conveyance: Update collection and conveyance system to address
previous comments. Verify gutter spread calculations at catch basins.
2) Treatment Facilities: Finalize the design of water quality facilities.
3) Stormwater Site Plan: Prepare a Stormwater Site Plan (drainage report) per the Ecology
Stormwater Management Manual for Western Washington (2012).
4) SWPPP: Prepare a Stormwater Pollution Prevention Plan per the Ecology Stormwater
Management Manual for Western Washington (2012).
Task 4 Channelization and Signing
1) Striping: Revise pavement marking plans to incorporate any horizontal design changes.
2) Signing: Develop a signing plan to meet the requirements of the MUTCD. Identify sign
type, size and location. Identify existing signs to be relocated or removed.
Task 5 Illumination
1) Lighting Layout: Finalize lighting layout based on any horizontal/vertical changes.
2) Electrical Connection: Coordinate power sources with Puget Sound Energy.
3) Line Loss: Perform line loss calculations.
Task 6 Landscape Design
1) Comment Resolution: Address City review comments of the preliminary landscape
plans.
2) Landscape Plan: Provide a complete landscape plan with planting layout, plant schedule,
installation details and installation notes for up to six planting areas.
3) Irrigation System Design and Repair: Provide performance specifications for irrigation
system design for planting areas identified in the landscape plans and performance
specifications for repair of impacts to existing irrigation systems.
4) Temporary Irrigation Systems: Provide performance specifications for temporary
irrigation systems or performance requirements for truck watering.
Lebo Boulevard Roadway Improvement Project March 11, 2016
City of Bremerton Page 15
SCJ Alliance
Exhibit A - Scope of Work
Task 7 Design Documentation
1) Final Design Report: Prepare a memorandum in addendum to the Basis of Design Report
prepared during Phase 4 - Preliminary Design. Explain changes to the design and attach
supporting documentation and/or calculations.
Task 8 60% Progress Meetings:
1) 60% Progress Meetings: Attend up to six meetings in Bremerton to review design and
plan progress with the City between Preliminary Design and 90% PS&E.
Task 9 90% Plan Sheets
1) The following 60% plans will be updated according the 60% review comments:
• Cover Sheet (1 sheet)
• Summary of Quantities (1 sheet)
• Horizontal Alignment Plan (6 sheets @ 20 scale double stacked full size)
• Roadway Sections (3 sheets)
• Temporary Erosion and Sediment Control Plans (6 sheets @ 20 scale double stacked
full size)
• TESC Details and Notes (1 sheet)
• Removal and Excavation Plans (6 sheets @ 20 scale double stacked full size)
• Roadway/Stormwater Plan and Profiles (12 sheets @ 20 scale full size)
• Roadway/Stormwater Details (2 sheets)
• Underdrain Plans (6 sheets)
• Underdrain Details (1 sheet)
• ADA Grading Details (20 sheets)
• Paving Plans (6 sheets @ 20 scale double stacked full size)
• Pavement Marking and Signing Plan (6 sheets @ 20 scale double stacked full size)
• Sign Specification Sheet (1 sheet)
• Illumination Plans (6 sheets @ 20 scale double stacked full size)
• Retaining Walls (2 sheets @ 20 scale full size)
• Landscape Plans (6 sheets @ 20 scale full size)
• Landscape Details (2 sheets)
• Traffic Control Plans (6 sheets @ 20 scale full size)
Task 10 90% Engineer's Estimate
1) 90% Engineer's Estimate: Develop quantities based on the 90% plans. Assign unit costs
for quantified item and assign lump sum costs to other items based on professional
judgment. Develop a 90% construction cost estimate that includes a 10% contingency.
Task 11 90% Contract Documents
1) 90% Contract Documents: Write specifications for all non-standard items. Compile the
special provisions into one Project Manual document.
Lebo Boulevard Roadway Improvement Project March 11, 2016
City of Bremerton Page 16
SCJ Alliance
Exhibit A - Scope of Work
Task 12 Final Comment Resolution
1) Final Comment Resolution: Respond to 90% review comments in a matrix format.
Attend one meeting with the City to resolve comments from the 90% review.
Task 13 Final PS&E Package
1) Final Plans: Update the plans per the 90% review comments.
2) Final Engineer's Estimate: Update the quantities to reflect the plan updates. Prepare
Unit Price Worksheet including item descriptions, unit, quantity and cost. Update the
engineer's estimate with revised quantities.
3) Final Contract Documents: Assemble the General Provisions, Special Provisions, and Unit
Price Worksheet into one Project Manual document.
Understanding
• For budget purposes it is assumed flow control requirements will be addressed by direct
discharge to Port Washington Narrows using existing closed conveyance systems.
• Coordination with utility providers will require up to 60 hours of effort.
• Landscape designs will not require an irrigation design. SG will prepare performance
specifications for irrigation design by the contractor.
• The City will provide SG with approved contract documents and boilerplate Division 1
special provisions.
• The 90% and Final reviews will not result in material changes to the design of
improvements.
Deliverables
• Final Basis of Design Report submitted in PDF via email.
• Stormwater Site Plan submitted in PDF via email.
• PS&E Package (90%) including half-size plans, special provisions, and engineer's
estimate submitted via courier to the City (5 copies) and PDF and AutoCAD via email.
• PS&E Approval Package (Final) including half-size plans, special provisions, and
engineer's estimate submitted via courier to the City (5 copies) and PDF and AutoCAD
via email.
Phase 10 City Funded Utilities (Water and Stormwater)
The design work in this phase covers work to be funded by City utility funds for water and
stormwater. The scope of the improvements is shown on Attachment A.
Task 1 Water Design
1) Preliminary Design: Provide preliminary plans for replacing one (1) 4" water main
crossing at Apple St with a new 8" water main. Plans will show plan and profile for the
replaced pipe. Show existing utilities in plan view only to identify pipe crossings for
potholing. Prepare an engineer's estimate with a 30% contingency.
2) Final Design: Based on potential utility conflicts identified under Task 10.1.14, identify
requested potholing locations and submit to the City. Prepare final plans. Plans will
Lebo Boulevard Roadway Improvement Project March 11, 2016
City of Bremerton Page 17
SO Alliance
Exhibit A — Scope of Work
show plan and profile for the replaced pipe. Show existing utilities in plan and profile
with assumed elevations or pothole elevations where applicable. Prepare an engineer's
estimate with a 5% contingency.
3) PS&E Documents: Prepare final documents — plans, specifications and engineer's
estimate.
Task 2 Storm water Design
1) Preliminary Design: Provide preliminary stormwater modeling, conveyance design, and
plans showing plan and profile for 2,350 linear feet of stormwater main along Lebo
Boulevard. Identify the basins tributary to the stormwater improvements. Show existing
utilities in plan view only to identify pipe crossings for potholing during final design.
Prepare an engineer's estimate with a 30% contingency.
2) Final Design: Based on potential utility conflicts identified under Task 10.1.14, identify
requested potholing locations and submit to the City. Provide final stormwater
modeling, conveyance design, and plans showing plan and profile. Show existing utilities
in plan and profile view with assumed elevations or pothole elevations where
applicable. Prepare an engineer's estimate with a 5% contingency.
3) PS&E Documents: Prepare final documents — plans, specifications and engineer's
estimate.
Phase 11 Bidding Services
Task 1 Bidding Services
1) Bidding Services: Support City staff during the bidding period as directed. For budget
purposes, 24 hours of support are assumed.
Phase 12 Additional Waterline Design (Optional Phase)
The City is considering replacement of the lead jointed water main in Lebo Boulevard.
Phase 13 Construction Engineering (Future Phase)
END OF SCOPE OF SERVICE
N:\Marketing\Proposals\Proposal Numbers\131889.01 Bremerton Lebo Boulevard Lower Wheaton Way\Scope and
Budget\2016-0306_scope of work_Lebo Blvd.doc
Lebo Boulevard Roadway Improvement Project March 11, 2016
City of Bremerton Page 18
M 8 °q
2101 `�❑ b
1714
o - o
-o
0 21008 Replace 4" crossing
12 n,°pipe 60 LF of 6" DI
° 2700A �o
mr
p� 2100
El El
El 7
19
o
c
o ��y o .
0
o � ,
i
0
,El
0
Lebo Boulevard Roadway Improvement Project
Scope of Work - Attachment A: City Funded Utilities
til - 200 feet
3
N C
W °
�:
m
C
water cathodic
0 04 Cast
water fittings
El
W
°
water reducer
Iron
0
Type_Valve
0 20 6 Cast Iron
00 2705
6
•
Butterfly
•
y cSH
b
V
O
GV
•
GVC
O
Ps
PumpStation
8�25t .0
2055 0
❑--_.
water service line
-.
water structure
o tron
water mains
6C ast Iron
•o
D
El El
O
068
Q
0% 109
2054.
�y
V
b 20678
6 C7
EL 6
o
t o
17
'
o
0
El 2067
.D-
..
8
-
oCd
°
Gast
est
❑
,•.:
.
$
`t
❑ o
s.,
�sF
2102 ❑
SM a
19 El
o o
_
M 8 °q
2101 `�❑ b
1714
o - o
-o
0 21008 Replace 4" crossing
12 n,°pipe 60 LF of 6" DI
° 2700A �o
mr
p� 2100
El El
El 7
19
o
c
o ��y o .
0
o � ,
i
0
,El
0
Lebo Boulevard Roadway Improvement Project
Scope of Work - Attachment A: City Funded Utilities
til - 200 feet
3
water blowoff
O
water cathodic
O
water fittings
El
water meters
0
water reducer
•
<all other values>
Type_Valve
•
air relief
•
Butterfly
•
BFVC
•
GV
•
GVC
BoosterStation
Ps
PumpStation
Wells
- -
water service line
water structure
water mains
LEBO BLVD
ERIDAN RD; (i x
.1714
lot tiF�
'Of ST
ACORN ST
IPA
ten,.
........... ........ ......
1000 LF 12" SD
Lebo Boulevard Roadway Improvement Project
Scope of Work - Attachment A: City Funded Utilities
1 inch = 200 feet
SHE,RIDAN RD
w = AK ST
\A0 CT
12" SD
�s
Lebo Boulevard Roadway Improvement Project
Scope of Work - Attachment A: City Funded Utilities
1814
1 inch = 200 feet
0
•
O
Q
O �
LEBO BLVo
•
•
12" SD no current
SD in this area
Separate from the
sewer? 800 If 12"
Lebo Boulevard Roadway Improvement Project
Scope of Work - Attachment A: City Funded Utilities
1815
1 inch = 200 feet
•, Transportation Improvement Board (TIB)
Consultant Agreement
EXHIBIT C-3
Payment
(Negotiated Hourly Rate)
The CONSULTANT shall be paid by the AGENCY for completed work and services under this AGREEMENT as provided hereinafter. Such
payment shall be full compensation for work performed or services rendered and for all labor, materials, supplies, equipment, and incidentals
necessary to complete the work.
1. Hourly Rates
The CONSULTANT shall be paid by the AGENCY for work done, based upon the negotiated hourly rates shown in Exhibits D and E attached hereto and
by this reference made part of this AGREEMENT. The rates listed shall be applicable for the first 12 -month period and shall be subject to negotiation for
the following 12 -month period upon request of the CONSULTANT or the AGENCY. The rates are inclusive of direct salaries, payroll additives, overhead,
and fee
In the event renegotiation of the hourly rates is conducted, the AGENCY reserves the right to audit for any change in the overhead rate currently in use by
the CONSULTANT and modify the hourly rates to be paid to the CONSULTANT subsequent to the renegotiation accordingly Any changes in the
CONSULTANT's fixed hourly rates may include salary or overhead adjustments
2. Direct Nonsalary Costs
Direct nonsalary costs will be reimbursed at the actual cost to the CONSULTANT. These charges may include, but are not limited to the following items.
travel, printing, long distance telephone, supplies, computer charges, and fees of subconsultants. Air or train travel will only be reimbursed to economy
class levels unless otherwise approved by the AGENCY. The billing for nonsalary cost, directly identifiable with the PROJECT, shall be an itemized listing
of the charges supported by the original bills, invoices, expense accounts, and miscellaneous supporting data retained by the CONSULTANT. Copies of
the original supporting documents shall be supplied to the AGENCY upon request. All above charges must be necessary for the services provided under
this AGREEMENT.
3. Maximum Amount
The maximum amount payable for completion of work under this AGREEMENT shall not exceed the amount shown in the heading of this AGREEMENT.
No minimum amount payable is guaranteed under this AGREEMENT. This does not include payment for extra work as stipulated in Section XIV, Extra
Work.
4. Monthly Progress Payments
Progress payments may be claimed on a monthly basis for all costs authorized in 1 and 2 above. The monthly invoices shall be supported by detailed
statements for hours expended at the rates established in Exhibits D and E, including names and classifications of all employees, and invoices for all direct
expenses.
5. Inspection of Cost Records
The CONSULTANT and his/her subconsultants shall keep available for inspection by representatives of the AGENCY, and/or TIB, for a period of three
years after final payment, the cost records and accounts pertaining to this AGREEMENT, and all items related to or bearing upon these records with the
following exception: if any litigation, claim, or audit is started before the three-year period, the records shall be retained until all litigation, claims, or audit
findings involving the records have been resolved. The three-year period begins when the CONSULTANT receives final payment.
6. Final Payment
Final payment of any balance due the CONSULTANT of the gross earned will be made promptly upon its verification by the AGENCY after the completion
of the work under this AGREEMENT, contingent upon receipt of all PS&E, plans, maps, notes, reports, and other related documents which are required to
be fumished under this AGREEMENT Acceptance of such final payment by the CONSULTANT shall constitute a release of claims of any nature which
the CONSULTANT may have against the AGENCY, unless such claims are specifically reserved in writing and transmitted to the AGENCY by the
CONSULTANT prior to its acceptance. Said final payment shall not, however, be a bar to any claims that the AGENCY may have against the
CONSULTANT or to any remedies the AGENCY may pursue with respect to such claims.
The rates and total price of the original contract and any additions or changes thereto shall be adjusted to exclude any significant sums by which the
AGENCY determines the contract price was increased due to inaccurate, incomplete, or noncurrent wage rates or overhead rates, supplied to the
AGENCY by the CONSULTANT.
TIB Form 190-016 Pae 14 of 22
Revised Oct 2001 9
Phase 01 Project Management
Task 01 Project Management
1 Management
90,0
Consultant labor Hour Estimate
900
24.0
SG Alliance
Subtotal Hours
240
760
e
204 0
12 0
2 'Photographs
Client- City of Bremerton
Total Phase Hours
I 240
760
SCJ ALLIANCE
Project: Lebo Boulevard Roadway Improvement Project
Total Phase Cost
$4,92000
$8,96800
$9,880 00
Job P188901
160
Task 02 Roadway7:4
1Horizontal Layout
File 8. 2016-0311 fee estimate Lebo Blvd xlsm
2.0 16.0
40.0
580
Perry
Scott Josh Gary
Dan Miranda Alyse Alissa
Meddle
Task No
Task Description
Principal
Associate
I
Project
Senior
Designer
I Project LA
Landscape
I
Project
I
Project
I
Total
6 Technical Memorandum
2.0 200
Engineer
Principal
Engineer 1
Planner
zz 0
Designer
Coord I
Acc(
Phase 01 Project Management
Task 01 Project Management
1 Management
90,0
680 -
320
600
900
7�t
OU V 1G V aicv
3 Quality Assurance/Quality Control 40.0 400
Subtotal Hours 400 1300 600 600 120 3020
Total Phase Hours 400 1300 i 600 I I 600 l 120 3020
Total Phase Cost • $9,80000 $26,65000 $7,08000 $4,80000 $1,260.00 1 $49,59000
Survey and Rights of Way Delineation (by
Phase 02
MTN2C0ZT)
Phase 03 Alternatives and Concept Design
Task 01 Alternatives and Concept Design
1 Lebo Boulevard Cross -Section - Crown vs Shed 24.0
2 Power Pole Relocation 8.0 16.0
3 Juniper Street Sidewalk 20.0
40.0
8.0
32.0
680 -
320
600
4
1 Oak Street/BOat Ramp Access Driveway
4.0
16.01
24.0
440
Subtotal Hours
240
760
1040
204 0
12 0
2 'Photographs
4.0
Total Phase Hours
I 240
760
1040
204 0
Total Phase Cost
$4,92000
$8,96800
$9,880 00
$23,76800
Phase 04 Preliminary Design
Task 01 Data Collection
1 Data Collection
12.0
12 0
2 'Photographs
4.0
40
Subtotal Hours
160
160
Task 02 Roadway7:4
1Horizontal Layout
�2
2.0 16.0
40.0
580
Vertical Layout
16.0
40.0
60.0
�
4-
580
860
420
3 JFrontage Design 2.0 24�
4 Pavement Underdrains 2.0 24 0
5 Review Workshop with CITY
4.0 4.0
�L
�
80
6 Technical Memorandum
2.0 200
zz 0
Subtotal Hours 14,0 1040
1560
2740
Task 03 Stormwater
1 Field Analysis
16.0
t
160
2 Modeling
64.0
16.0
--II--
800
3 Downstream Analysis
32.0
320 -
20 28.0
24.0
540
=4Layout
al Memorandum
20.0
8.0
ego
Subtotal Hours 20 1600
480
2100
1 of 6 3/14/2016
Consultant labor Hour Estimate
SO Alliance 0
Client. City ofBremerton SCJ ALLIANCE
Prosed Lebo Boulevard Roadway Improvement Project
Job #- P1889.01
File a. 2016-0311 fee estimate Lebo Blvd_ :Ism
Perry Scott Josh Gary Dan Miranda Alyse Alissa Maddie
Tosk No
Task Description
Principal
Engrrleer
Associate
Principal
Project
I Engineer 1
Senior
Planner
Designer
Project LA Landscape
Designer
Project Project
Coord I Acct
rota!
Task 04 Retaining Walls
1 Layout
-t
12.0 16.0 .. -
10.0
280
120
2 :Type Selection 2.0
L
10.0
11 0
_
3 Technical Memorandum 1.0
Subtotal Hours 30 320
160
510
Task 05 Traffic and Lighting
1 Channellzation 2.0
2 Stop Warrant 8.0
3 Lighting 2.0 8.0
12 0
16.0
140
80
260
4 'Construction Sequencing 4.0 24.0
16.0
440
5 Technical Memorandum 1.0 8.0
i 16.0
250
Subtotal Hours, 70 500
600
1170
Task 06 Preliminary Landscape Design
1 Data Collection
2 Meetings
4,0
8.0 2.0
_
4 0
- 10.0
- -
3 : Landscape Plan
4.0 16.0
200
Subtotal Hours
120 220
I
340
Task 07 Utility Mapping
-
1 Utility Mapping 12 0
12.0
240
2 Utility Conflict Technical Memorandum 2.0 20.0
40
��
260
3 Utility Coordination 2.0 20.0
22.0
Subtotal Hours 40 520
160
72.0
Task 08 Preliminary Plans
1 CoverSheet(1)
6.0
..-
60
2 'Typical Sections (2)
2.0 4-.O
12.0
�
180
3 Plan and Profile (12)
4.0 24.0
96.0
1240
4 Underdrain Plans (6)
5 Channellzation (6)
2 0 160
12.0
32.0
36.0
I
500
480
6 Illumina[lon (6)
12.0
36.0
480
7 Landscape (6)
10.0 360
460
Subtotal Hours
80 680
2180 100 360
3400
Task 09 Project Cost Estimate
I
1 Cost Estimate
1.0 4.0
24.0
290
Subtotal Hours
10 1 4.0
240
290
Task 30 Basis for Design Report
1 Draft Basis for Design Report
2.0 16.0
180
2
Final Basis for Design Report
1.0 4.0
so
Subtotal Hours
30 200
230
Total Phase Hours 420 5060 5380 220 580 1,166 0
Total Phase Cost $8,610.00 $59,70800 $51,110 00 $2,530 00$4,640 00 $126,598 00
2 of 6 3/14/2016
Consultant labor Hour Estimate
SCJ Alliance �a
Client City of Bremerton SCJ At_LIANCE
Protect Lebo Boulevard Roadway Improvement Project
lob# P1889.01
File #• 2016-0311 fee estimate Lebo Blvd_.xlsm
Perry Scott Josh Gary Dan Miranda Alyse Alissa Maddie
Task No Task Description Principal Associate Project Senior Designer Project LA Landscape Pro/act Project Total
Engineer Principal Engineer 1 Planner Designer Coord I Acct
Phase 05 Geotechnical Design (by GeoEngineers)
Phase 06 Urban Design (by HBB landscape Architecture)
Phase 07 SEPA and Permitting
Task 01
SEPA and Permitting
1 Focus Meetings 32.0
Identify Potholing Locations
320
2 Council Briefings 8.0
1
SEPA Checklist
240
2.02.0—T16.0
12.0 4.0
-
3
240
4 Project Website 8.0
180
2
;Ordinary High Water Mark Mapping
160
Subtotal Hours 560
24.0
80
240
3
Shoreline Substantial Development Permit
920
Task 02 Roadway
1 Horizontal Layout
2 Vertical Layout
80.0
800
4
NDPES Permit
4.0
720
40
5
;Critical Areas Ordinance
20.0
200
Subtotal Hours
I 6.0
1400
1
1460
Total Phase Hours 60 14001410
Total Phase Cost $70800 $16,80000 $17,508 00
Phase 08 Public Involvement
Task 01 Public Involvement
i
1 Focus Meetings 32.0
Identify Potholing Locations
320
2 Council Briefings 8.0
12.0 4.0
2 Potholing
240
3 Public Meetings 8.0
12.0 4.0
-
3
240
4 Project Website 8.0
8.0
—
100
a
160
Subtotal Hours 560
320
80
800
960
Total Phase Hours 560 320 80 160
Total Phase Cost $11,480 00 $3,77600 $760.00 I I $16,01600
Phase 09 Final Design
Task 01 Utility Coordination
i
Identify Potholing Locations
2.0 4.0
60
2 Potholing
16.0
' 160
-
3
Incorporate Potholing Data
—
2.0 8.0
—
100
a
Identify Conflicts
60.0
600
Subtotal Hours
800
120
920
Task 02 Roadway
1 Horizontal Layout
2 Vertical Layout
4.0 16.0
1 12.0 40.0
200
520
Subtotal Hours
160 560
720
3 of 6 3/14/2016
Consultant Labor Hour Estimate
SG Alliance
Client. City of Bremerton SCJ At.l_IANCE
Project Lebo Boulevard Roadway Improvement Project
Job# P11889.01
File #. 2016-0311 fee estimate Lebo Blvd_ xlsm
Perry Scott Josh Gary Dan Miranda Alyse Alissa Maddie
Task No Task Description Principal Associate Project Senior Designer Project LA Landscape Project Project Total
Engineer Principal Engineer 1 Planner Designer Coad l Acct
Task 03 Drainage
1 Collection and Conveyance 8.0 so
2 Treatment Facilities 8.0 8.0 160_
3 Stormwater Site Plan 24.0 16.0 400
4 SWPPP - 24.0 8.0 320
Subtotal Hours 640 320 960
Task 04 Channelixation and Signing
1 Striping 2.0 8.0 100
2 Signing 2.0 12.0 140
Subtotal Hours 40 I 200 240
Task 05 Illumination
11 g Layout 2.0 16.0 180
2 ctrical Connection 8.0 s o
Ele
3 Line Loss 2.0 8.0 100
Subtotal Hours 120 240 360
Task 06 Landscape Design i
1 Comment Resolution4.0 40
2 Landscape Plan 4.0 20.0 240
3 Irrigation System Repairg,0 s0
4 Temporary Irrigation Systems I 8.0 80
Subtotal Hours 240 200 440
I
Task 07 Design Documentation
1 Final Design Report 1.0 4.0 so
Subtotal Hours 1 0 40 50
Task 08 6D% Progress Meetings
1 60% Progress Meetings 18.0 24.0 8.0 500
Subtotal Hours 180 240 80 50.0
Task 09 90% Plan Sheets
1 Cover Sheet (1) 2.0 2 0
2 Summary of Quantities (1) � 1.0 4.0 50
3 Horizontal Alignment Plan (6) 2.0 1 12.0 140
4 Roadway Sections (3) 2.0 8.0 I 100
5 Temporary Erosion and Sediment Control (6) 8.0 32.0 400
6 TESC Details and Notes (1) 2.0 6.0 so
7 Removal and Excavation Plans (6) 4.0 32.0 36.0
8 Roadway/Stormwater Plan and Profile (12) 24.0 72.0 960
9 Roadway/Stormwater Details (2) 2.0 8.0 100
to Underdraln Plans (6) 16.0 24.0 400
11 Underdraln Details (1) � 8.0 12 0 � zoo
1z ADA Grading Details (20) 24.0 80.0 1040
13 Paving Plans (6) 1 I 16.0 j 48.0 I 640
4 of 6 3/14/2016
Consultant labor Hour Estimate
SG Alliance o
Client- City of Bremerton SCJ ALLIANCE
Protect Lebo Boulevard Roadway Improvement Project
lob p- P1889.01
File 0: 2016-0311 fee estimate Lebo Blvd xism
Perry Scott Josh Gary Dan Miranda Alyse Alissa Maddie
task No
Task Description
Principal Associate
Project
Senior
Designer
Project LA
Landscape
Project Project
Totol
- -
Engineer Principal
Engineer 1
Planner
3 PS&E Documents
1.0
Designer
Coad I Acct
14
Pavement Marking and Signing Plan (6)
8.0
36.0
350
Task 02 Stormwater Design
440
15
16
Sign Specification Sheet (1)
Illumination Plans (6)
2.0
8.0
80
36.0
100
440
1Preliminary Design
16.0
32.0
480
17
Retaining Walls (2)
20.0
4.0
16.0
200
18
Landscape Plans (6)
4.0
4.0
4.0 20.0
24.0
19
Landscape Details (3)
40.0
760
16.0
F=
180
20
Traffic Control Plans (6)
4.0
24.0
280
Subtotal Hours
1350
4600 6,0
360
6370
Task 10
90% Engineer's Estimate
190%Engineer's
Estimate
1.012.0
1-4 200+1.0 6.0
400
Subtotal Hours. 10
120
200 30 60
400
Task 11
90% Contract Documents
1
90% Contract Documents
2.0
24.0
4.0
300
Subtotal Hours20 24.0 40 300
Task 12 Final Comment Resolution I
1 Final Comment Resolution 2,0 8,0 4,0 140
Subtotal Hours 20 1 80 40 140
Task 12
Final PS&E Package
6.
12.0 �
180
2 Final Design
1
Final Plans
4.0 16.0 60.0 40 24.0
1080
2 Final Engineers Estimate 1 1.0 4.0 8.0 2_0 4.0 190
3 iFinal Contract Documents 12.0 4.0 160
Subtotal Hours 50 320 660 100 28.0 1430
Total Phase Hours 290 4150 I 7000 490 900 1,283 0
Total Phase Cost $5,945 00 $48,97000 I $66,500 00 I $5,635 00 $7,20000 1 $134,25000
Phase 10 City Funded Utilities (Water and Stormwater)
Task 01 Water Design
1 Preliminary Design
6.
12.0 �
180
2 Final Design
4.0
-
8.0
.120
- -
-
so
3 PS&E Documents
1.0
20
2.0
Subtotal Hours 10
120
220
350
Task 02 Stormwater Design
1Preliminary Design
16.0
32.0
480
2 Final Design
20.0
40.0
600
3 PS&E Documents
2.0
4.0
4.0
100
Subtotal Hours 20
40.0
760
1180
Total Please Hours. 3.0 520 i 980 i I53 0
Total Phase Cost I $61500 $6,13600 $9,310 00 i$9,31p 00 _ l�$16,063 0000
5 o16 3/14/2016
Phase 11 Bidding Services
Task 01 Bidding Services
1 (Bidding Services 6.0 12.0 6.0��— 240
Subtotal Hours 60 120 60 240
Total Phase Hours 60 120 60 240
Total Phase Cost, $1,23000 $1,41600: $72000 $3,36600
Total Hours All Phases 400 2900 1,159.0 1460 1,448 0 710 1480 600 120 3,3740
Total Cost All Phases 1 $9,80000 1$59,45000 $136,762 00'. $17,520 00 $137,560 00 $8,16500 $11,84000 $4,80000: $1,26000 $387,157 00
6 or 6 3/14/2016
Consultant labor Hour Estimate
SO Alliance
o
Client: City of Bremerton
SCJ ALLIANCE
pnoj c Lebo Boulevard Roadway improvement Project
lob# P189901
File # 2016-0311 fee estimate Lebo Blvd xlsm
Perry
Scott losh Gary
Dan Miranda Alyse Alissa
Maddie
Task No
Task Description
Principe/
Associate Project Senior
Designer
Project LA Landscape
Project
Prgect
Total
Engineer
Principal Engineer 1 Planner
Designer
Coord l
Accl
Phase 11 Bidding Services
Task 01 Bidding Services
1 (Bidding Services 6.0 12.0 6.0��— 240
Subtotal Hours 60 120 60 240
Total Phase Hours 60 120 60 240
Total Phase Cost, $1,23000 $1,41600: $72000 $3,36600
Total Hours All Phases 400 2900 1,159.0 1460 1,448 0 710 1480 600 120 3,3740
Total Cost All Phases 1 $9,80000 1$59,45000 $136,762 00'. $17,520 00 $137,560 00 $8,16500 $11,84000 $4,80000: $1,26000 $387,157 00
6 or 6 3/14/2016
Consultant Fee Determination
SO Alliance
Client: City of Bremerton
Project: Lebo Boulevard Roadway Improvement Project
Job #: P1889.01
File #: 2016-0311 fee estimate Lebo Blvd .xism
Consultant Fee Determination
SALARYCOST
Discipline
- Hours
Principal Engineer
40.0
Associate Principal
290.0
Project Engineer 1
1,159.0
Senior Planner
146.0
Designer
1,448.0
Project LA
71.0
Landscape Designer
148.0
Project Coord 1
60.0
Project Acct
12.0
SUBCONSULTANTS
REIMBURSABLES
Subtotal: 3,374.0
Rate
$245.00
$205.00
$118.00
$120.00
$95.00
$115.00
$80.00
$8000
$105.00
Phase 2 Survey and Rights of Way Delineation
Phase 7 Geotechnical Design
Phase 30 Urban Design
Subconsultant Fee
Subconsultant Markup: 10%
fi �p�A
SCJ ALLIANCE
Amount
$9,800
$59,450
$136,762
$17,520
$137,560
$8,165
$11,840
$4,800
$1,260
Total Salary Cost $387,157
MTN2COAST $47,300.00
GeoEngineers $46,50000
HBB Landscape Architecture $33,900.00
$127,700
$12,770
Total Subconsultants $140,470
Copies, Reproductions, et 2.5% of Total Salary Cost $9,700
Mileage: 1,500 miles at $0.560 $840
Total Expenses: $10,540
SUBTOTAL (SALARY, SUBCONSULTANTS AND EXPENSES)
Subtotal (Salary, Subconsultants and Expenses) $538,167
MANAGEMENT RESERVE FUND (MRF)
Management Reserve 10.0% of Subtotal $53,817
Total Estimated Budget: $591,984
3/14/2016 Page 1
Phase Summary Table Summary - Cost by Fund
Phase # Phase Title SCJ Hours Total Cost Road Stormwater Water Sewer
SG Labor SG Labor
Phase 01
Project Management
Phase 03
Alternatives and Concept Design
Phase 04
Preliminary Design
Phase 07
SEPA and Permitting
Phase 08
Public Involvement
Phase 09
Final Design
302.0
204.0
1166.0
146.0
96.0
1283.0
$49,590
$23,768
$126,598
$17,508
$16,016
$134,250
Phase 10 City Funded Utilities (Water and Stormwater) 153.0 $16,061
Phase 11 Bidding Services 24.0 $3,366
Subtotal 3374.0 $387,157
Subconsultants
Phase 02
Phase 07
Phase 10
Survey and Rights of Way Delineation
Geotechnical Design
Archeological and Architectural Inventory
$52,030
$51,150
$37,290
Subtotal
Survey and Rights of Way Delineation
$140,470
$0
Reimbursable Expenses
$87,912
Phase 99
Reimbursable Expenses
$10,540
$12,643
Management Reserve Fund (MRF)
$487
Phase 98
Management Reserve Fund (MRF)
$53,817
Total
$0
$591,984
$35,809
$12,400
$1,381
$0
$23,768
$0
$0
$0
$87,912
$35,212
$3,468
$0
$12,643
$4,378
$487
$0
$11,565
$4,005
$446
$0
$105,442
$27,622
$1,192
$0
$0
$12,350
$3,711
$0
$2,431
$842
$94
$0
$279,570
$96,808
$10,779
$0
Subconsultants
$37,586
$36,951
$26,939
$12,985
$12,763
$9,305
$1,459
$1,436
$1,047
$0
$0
$0
$101,476
$35,053
$3,941
$0
Reimbursable Expenses
$7,620
$2,610
$310
$0
Management Reserve Fund (MRF)
$39,014
$13,202
$1,601
$0
$427,680
$147,673
$16,632
$0
72%
25%
3%
Transportation Improvement Board (TIB)
,!,J'Consultant Agreement
EXHIBIT F-1
Payment Upon Termination of Agreement
by the Agency Other than for Fault of the Consultant
(Refer to Agreement, Section IX)
Lump Sum Contracts
A final payment shall be made to the CONSULTANT which when added to any payments previously made
shall total the same percentage of the Lump Sum Amount as the work completed at the time of termination is
to the total work required for the PROJECT. In addition, the CONSULTANT shall be paid for any authorized
extra work completed.
Cost Plus Fixed Fee Contracts
A final payment shall be made to the CONSULTANT which when added to any payments previously made,
shall total the actual costs plus the same percentage of the fixed fee as the work completed at the time of
termination is to the total work required for the PROJECT. In addition, the CONSULTANT shall be paid for any
authorized extra work completed.
Specific Rates of Pay Contracts
A final payment shall be made to the CONSULTANT for actual hours charged at the time of termination of this
AGREEMENT plus and direct nonsalary costs incurred at the time of termination of this AGREEMENT.
Cost Per Unit of Work Contracts
A final payment shall be made to the CONSULTANT for actual units of work completed at the time of
termination of this AGREEMENT.
TIB Form 190-016
Revised Oct 2001 Page 20 of 22
w Transportation Improvement Board TIB
Consultant Agreement
EXHIBIT G-1
Subcontracted Work
The AGENCY permits subcontracts for the following portions of the work of this AGREEMENT:
Phase 2 - Survey and Right of Way Delineation - MTN2COAST
Phase 7 - Geotechnical Design - GeoEngineers
Phase 10 - Urban Design - HBB Landscape Architecture
TIB Form 190-016
Revised Oct 2001 Page 21 of 22