HomeMy WebLinkAbout5776AGENDA BILL
CITY OF BREMERTON
CITY COUNCIL
SUBJECT: Illumination Upgrades by Puget Study Session Date:
Sound'Energyon SR303 (Wheaton Way) COUNCIL MEETING Date:
from Sheridan Road to NE Riddell Road Department:
Presenter:
Phone:
January 10, 2018
January 17, 2018
PW&U
Tom Knuckey
360.473.2376
SUMMARY: At the City's request, Puget Sound Energy completed an evaluation of lighting on
Wheaton Way between Sheridan Road and Riddell Road. Recommended improvements would
convert all existing high pressure sodium fixtures to LED and increase the total number of fixtures
along the corridor from 19 to 40. The lighting upgrade will improve illumination along the corridor to
meet roadway lighting standards at all intersections, and nearly everywhere else throughout the
corridor. Installation of the lighting will cost $26,691.76, plus traffic control for.the upgrade of existing
lights which is estimated to be less than $1,.000. These lighting upgrades will increase annual
energy/maintenance charge to PSE by approximately $6,000.
ATTACHMENTS: PSE Proposal Letters (2 letters)
FISCAL IMPACTS (Include Budgeted Amount): Funding is included in the Transportation Projects .
Fund (315) under City Safety Improvement Annual Program
STUDY SESSION AGENDA: ® Limited Presentation ❑ Full Presentation
STUDY SESSION ACTION: ® Consent Agenda ❑ General Business ❑ Public Hearing
RECOMMENDED MOTION:
Move to approve the Puget Sound Energy illumination upgrades on Wheaton Way with costs not to
exceed $28,000; and authorize the Mayor to finalize and execute the agreements with substantially
the same terms and conditions as presented.
COUNCIL ACTION: j-�Approve
Forth Updated 01/07/15
❑ Deny ❑ Table ❑ Continue ❑ No Action
PUGET SOUND ENERGY
January 11, 2018
City of Bremerton
Attn: John Butler
345 6"' St, Suite 100
Bremerton, Wa 98337
Project Name: Wheaton Way Change Out
Project locations: SR 303 from Sheridan to Riddell
Dear John,
Thank you for your street lighting request to service the above location. With your authorization, we will proceed
with the conversion existing 17) HPS Cobraheads to 15)-203W LED Type 2 and 2)- 285W LED Type 2 Cobraheads
on existing PSE poles. 2 HPS lums SL37 and SL38 will be completely removed. The cost for this construction is
$10,148.04. Traffic control costs have been included. Payment for installation will be requested after
installation is completed. This estimate is valid for 90 days.
The monthly energy/maintenance charge of $21.78, and $17.80 respectively, as per our Schedule 53 Electric Tariff
G, will start once the lights are energized
The responsible billing party will be: City of Bremerton
By signing this letter and returning it, you are stating that you authorize us to do the work and this order will be
released to constriction for scheduling. Upon receipt of the signed agreement, we will order materials and schedule
the construction. Please provide date installation should take place: February 2018
If you have any questions, please call me at 425-516-5432
Sincerely,
L4wTC%vwlp�r
Lisa Kinney
Account Sales Manager, PSE Pole Services
The above is accepted and authorization is given
By: lei Date: I
Print: Title:
PUGET SOUND ENERGY
January 11, 2018
City of Bremerton
Attn: John Butler
345 6"' St, Suite 100
Bremerton, Wa 98337
Project Name: Wheaton Way
Project locations: SR 303 from Sheridan to Riddell
Dear John,
Thank you for your street lighting request to service the above location. With your authorization, we will proceed
with the installation of 22- new LED Cobraheads on the existing PSE poles. 3) 138W, 10) 203W, 6) 285W, 1) 54W
and 2) 102W.LED's. The cost for this construction is $16,069.70. This includes two day of flagging. Payment for
installation will be requested after installation is completed. This estimate is valid for 90 days.
The monthly energy/maintenance charge of $9.70, $12.33, $13.99, $17.80, $21.78 respectively as per our
Schedule 53 Electric Tariff G, will start once the lights are energized
The responsible billing party will be: City of Bremerton
By signing this letter and returning it, you are stating that you authorize us to do the work and this order will be
released to construction for scheduling. Upon receipt of the signed agreement, we will order materials and schedule
the construction. Please provide date installation should take place: February 2018
If you have any questions, please call me at 425-516-5432
Sincerely,
L 6salKW' *WY
Lisa Kinney
Account Sales Manager; PSE Pole Services
The above is accepted and authorization is given:
By: Date: 1 %
Print: 4-49A t0KtILW Title: