HomeMy WebLinkAbout05/03/2023 4HAGENDA BILL
CITY OF BREMERTON
4H
CITY COUNCIL
SUBJECT:Study SessionDate: April 26, 2023
Agreement w/Southern Road & Bridge, LLC COUNCIL MEETING Date: May 3, 2023
for Reservoir 8Interior Coating
Department: Engineering
Replacement Project
Presenter: Bill Davis
Phone: (360) 473-2312
SUMMARY:Reservoir 8 is a 2.54-million-gallonsteel water reservoir located at 7300 Werner Road.
The scope of work includesabrasive blasting and recoating the entire interiorwith a 3-coat epoxy
coating system. The interior was last coated in 2005.
Bids were opened on April 12, 2023.Seven (7) bids were received. Southern Road and Bridge, LLC
was the lowest responsible, responsive bidder in the amount of $495,768(which includes sales tax).
ATTACHMENTS:1. Agreement; 2. Location Map; 3. Bid Tabulation
FISCAL IMPACTS(Include Budgeted Amount): This project is included in the 2023 Water Capital
Budget.
STUDY SESSION AGENDA: LimitedPresentation Full Presentation
STUDY SESSION ACTION:Consent Agenda General Business Public Hearing
RECOMMENDED MOTION:Move to award the contract for the Reservoir 8 Interior Coating
Replacement project toSouthern Road and Bridge, LLCin the amount of $495,768, including sales
tax, and authorize the Mayor to finalize and execute the agreement with substantially the same terms
and conditions as presented.
COUNCIL ACTION: Approve Deny Table Continue No Action
Form Updated 01/02/2018