Contract Modification No. 1
Rev. 09/2021
CONTRACT MODIFICATION AGREEMENT NO. 1
BETWEEN THE CITY OF BREMERTON AND PARAMETRIX, INC.
PROJECT: 2022 On Call Development Engineering Services
CONSULTANT: Parametrix, Inc.
DATE: October 18, 2022
THIS CONTRACT MODIFICATION AGREEMENT SPECIFICALLY AMENDS THE
PROFESSIONAL SERVICES AGREEMENT (the "Contract") entered into between the
City of Bremerton and Parametrix, Inc. on January 5, 2022.
All provisions in the Contract shall remain in full force and effect except as expressly modified
by this document.
For valuable consideration and by mutual consent of the parties, the modifications to the
Contract are as follows:
I.
Section I. Scope , is modified as follows:
No change to the contract scope, continued on-call review services.
Section II. Term , is modified as follows:
The contract end date is extended to December 31, 2023.
Section III. Compensation , is modified as follows:
The original contract amount was “not to exceed” $24,500. The contract is reduced by $12,000
for a total amended contract amount not to exceed $12,500, including this Contract Modification.
II.
Consultant accepts all requirements of this Contract Modification by endorsing below.
Consultant further agrees that this Contract Modification constitutes full and final
settlement of all of the Consultant’s claims for contract time and for all costs of any kind,
including without limitation, costs of delays related to any work either covered or affected
by this Contract Modification, claims related to on-site or home office overhead, or lost
profits. This Contract Modification does not limit the City’s right to bring a claim for past
performance.
The undersigned consultant approves the foregoing Contract Modification as to the changes,
if any, in the contract price specified for each item, including any and all supervision costs
and other miscellaneous costs relating to the change in work, and as to the extension of time
allowed, if any, for completion of the entire work due to said Contract Modification.
DocuSign Envelope ID: 992950E1-51B5-4ABE-A829-26CBC7A864BB
Page 2 of 2
Contract Modification No. 1
Rev. 09/2021
This document will become a supplement of the contract and all provisions will apply hereto.
It is understood that this Contract Modification shall be effective when approved by the City
of Bremerton.
The parties whose names appear below warrant that they are authorized to enter into a
contract modification that is binding on the parties of this contract. In addition, Consultant
warrants that it has or will inform the surety of this change, and shall take appropriate action
to modify any bonds required under the contract to address this change.
IN WITNESS WHEREOF, the parties have executed this Contract Modification on the day
and year first written above.
City Engineer / Public Works Director approved to process _________________________ (Initials and Date)
PARAMETRIX, INC. THE CITY OF BREMERTON
By:By:
Print Name: Print Name:
Its:Its:
Date:Date:
APPROVED AS TO FORM: ATTEST:
By: By:
KYLIE J. FINNELL, Bremerton City Attorney ANGELA HOOVER, City Clerk
NOTICES TO BE SENT TO: NOTICES TO BE SENT TO:
Rhiannon Sayles Janelle Hitch
Parametrix, Inc. City of Bremerton
60 Washington Avenue, Suite 390 345 6th Street, Suite 100
Bremerton, WA 98337 Bremerton, WA 98337-1891
R:\Legal\Legal\Forms\FORMS ON COBWEB\Contract Modification Rev. 09 2021.docx
Ned Lever Digitally signed by Ned LeverDN: C=US, E=ned.lever@ci.bremerton.wa.us, O=City of Bremerton, OU=Engineering, CN=Ned LeverReason: I have reviewed this documentDate: 2022.10.25 11:58:45-07'00'
Thomas Knuckey
Public Works Director
Jenifer YoungEP&C Division Manager
DocuSign Envelope ID: 992950E1-51B5-4ABE-A829-26CBC7A864BB
11/10/2022 11/14/2022