HomeMy WebLinkAbout1 - Original Submission_ 211005_4555_Change Order 1_MDWM_for signature TKCITY OF BREMERTON
CHANGE ORDER
CONTRACT CHANGE ORDER NO: 1
PROJECT NAME: Marine Drive Water Main Replacement
PROJECT NO: CONTRACTOR: Pape & Sons
ORIGINAL CONTRACT AMOUNT: 2,018,002.35 DAYS: 100
PREVIOUSLY APPROVED CHANGES: 0.00 DAYS: 0
THIS CHANGE: 0.00 DAYS: 0
REVISED CONTRACT AMOUNT: 2,018,002.35 DAYS: 100
This Change Order covers changes to the subject contract as described herein. The Contractor shall construct, furnish equipment and materials, and perform all work as necessary or required to complete
the Change Order Items. The increase or decrease in contract price shown below includes any
applicable taxes. Rule 170 Rule 171 DESCRIPTION OF CHANGES INCREASE IN CONTRACT AMOUNT ($)
(DECREASE) IN CONTRACT AMOUNT ($)
CONTRACT TIME EXTENSION (DAYS:)
X Article 3 of the Agreement, which states that: “All project HMA
paving shall be completed by October 15, 2021 or Contractor shall pay liquidated damages in the amount of $1500 per
calendar day to the City after this date.” The date is changed to October 28, 2021, which is the same date as Substantial
Completion. Overall contract time is not increased. Letter from Pape & Sons is attached.
0
NET CHANGE IN CONTRACT AMOUNT INCREASE OR (DECREASE) 0
ESTIMATED SALES TAX AT 9.0% 0
TOTAL INCLUDING SALES TAX 0
Contractor acknowledges and accepts that this Change Order constitutes final settlement of all claims
of any kind or nature arising from or connected with any work either covered or affected by this Change
Order, including, without limitation, claims related to contract time, on-site or home office overhead, or lost profits. Nothing in this Change Order shall limit the City’s right to bring a claim for past performance.
The undersigned Contractor approves the foregoing Change Order as to the changes, if any, in the
contract price specified for each item, including any and all supervision costs and other miscellaneous
costs relating to the change in work, and as to the extension of time allowed, if any, for completion of the entire work due to said Change Order.
DocuSign Envelope ID: 62208C2F-4724-47B4-8C12-036ED920D814
10/14/21
Ned Lever
Digitally signed by Ned LeverDN: C=US, E=ned.lever@ci.bremerton.wa.us,
O=City of Bremerton, OU=Engineering,
CN=Ned Lever
Date: 2021.10.15 08:44:52-07'00'
Thomas Knuckey Digitally signed by Thomas Knuckey
Date: 2021.10.20 07:41:05 -07'00'
DocuSign Envelope ID: 62208C2F-4724-47B4-8C12-036ED920D814
10/21/2021
September 29th, 2021
Mr. Davis
City of Bremerton
RE: Marine Drive Paving Deadline
Mr. Davis:
Despite our best efforts, it has come to our attention that we will not meet the Oct 15th
Deadline within the contract for completing all pavement on the Marine Drive Watermain Replacement
Project. This project experienced a minor delay being awarded and has experienced a slight delay
obtaining right-of-way agreements, which has prevented us to complete that portion on time. As of
today, we have used 71 of the 100 calendar days granted within the contract and see no issue
completing the remaining substantial work within this time restraint.
Pape & Sons is requesting an extension on this deadline to complete the HMA restoration
requirements, including the overlay portion of the project. This work will be completed in coordination
with the city as appropriate weather conditions allow.
Pape & Sons will continue working diligently to complete this project. We appreciate the help
and cooperation we have received working with the city and look forward to working together.
Bradley Appleman
Bradley Appleman
Project Manager
Pape and Sons Construction
DocuSign Envelope ID: 62208C2F-4724-47B4-8C12-036ED920D814
IDTask NameDurationStartFinishPredecessors1Crew #1 Jeff33 daysThu 7/15/21Thu 9/9/212Mobilization - Pipe Delivery2 daysThu 7/15/21Mon 7/19/213Shut Down Tie in 52+47 and Hydrant1 dayTue 7/20/21Tue 7/20/2124Water Main 52+47 to 56+303 daysWed 7/21/21Mon 7/26/2135Pressure and Purities2 daysTue 7/27/21Wed 7/28/2146Water Main 56+30 to 72+003 daysTue 7/27/21Thu 7/29/2147Pressure and Purities2 daysMon 8/2/21Tue 8/3/21688" Water Main 72+00 to 84+004 daysMon 8/2/21Thu 8/5/2169Pressure and Purities2 daysMon 8/9/21Tue 8/10/218108" Water Main 84+00 to 96+93 4 daysMon 8/9/21Thu 8/12/21811Pressure and Purities2 daysMon 8/16/21Tue 8/17/2110128" & 4" Water Main103+55 to 300+702 daysMon 8/16/21Tue 8/17/211013Pressure and Purities2 daysWed 8/18/21Thu 8/19/2112144" Water Main 96+52 to 200+002 daysWed 8/18/21Thu 8/19/211215Pressure and Purities2 daysMon 8/23/21Tue 8/24/21141617Services8 daysMon 8/30/21Thu 9/9/211819Crew #2 Eric49 daysMon 7/26/21Mon 10/18/2120Mob1 dayMon 7/26/21Mon 7/26/2121Water Main3 daysTue 7/27/21Thu 7/29/212022Pressure Test0 daysThu 7/29/21Thu 7/29/212123Tie In at 52+47 and Hydrant 59+951 dayTue 8/3/21Tue 8/3/2124Services 1-336 daysMon 8/16/21Tue 8/24/2125Tie in at 17+28 and 21+921 dayTue 8/10/21Tue 8/10/2121FS+2 days26Concrete and HMA5 daysMon 9/6/21Mon 9/13/2127Services 34-55 4 daysWed 8/25/21Tue 8/31/212428Services 56-13113 daysWed 9/1/21Wed 9/22/212729Tie In at 56+30 and 62+351 dayThu 9/23/21Thu 9/23/212830Tie In 69+90 and 77+851 dayMon 9/27/21Mon 9/27/212931Tie In 93+601 dayTue 9/28/21Tue 9/28/213032HMA Patching4 daysWed 9/29/21Tue 10/5/213133HMA Overlay2 daysWed 10/6/21Thu 10/7/213234Clean up and Demob5 daysMon 10/11/21Mon 10/18/2133WTFSSMTWTFSSMTWTJul 18, '21Jul 25, '21TaskSplitProgressMilestoneSummaryProject SummaryExternal TasksExternal MilestoneDeadlinePape and Sons ConstructionCity of BremertonMarine Drive Water Main 2021Page 1Project: Schedule with 2 crews 8-9-21Date: Mon 8/9/21Prepared by Brad ApplemanHMA Patching delayed pending 4" and service transfersTie ins are delayed pending 4" water main completion/acceptance/service transfers10 Services and one air vac were delayed due to the 4" water main easement. Originally scheduled to be completed 9/21/21 and 9/22/21 are now scheduled to be completed 10/11/21 and 10/12/214" Water main scheduled to be completed 8/17/21 Had easement delays that were approved 10/1/21 and water main completed 10/5/21Schedule as of 8/9/21DocuSign Envelope ID: 62208C2F-4724-47B4-8C12-036ED920D814
IDTask NameDurationStartFinishPredecessors1Crew #1 Jeff52 daysThu 7/15/21Wed 10/13/212Mobilization - Pipe Delivery2 daysThu 7/15/21Mon 7/19/213Shut Down Tie in 52+47 and Hydrant1 dayTue 7/20/21Tue 7/20/2124Water Main 52+47 to 56+303 daysWed 7/21/21Mon 7/26/2135Pressure and Purities2 daysTue 7/27/21Wed 7/28/2146Water Main 56+30 to 72+003 daysTue 7/27/21Thu 7/29/2147Pressure and Purities2 daysMon 8/2/21Tue 8/3/21688" Water Main 72+00 to 84+004 daysMon 8/2/21Thu 8/5/2169Pressure and Purities2 daysTue 8/17/21Wed 8/18/21108" Water Main 84+00 to 96+93 5 daysMon 8/9/21Mon 8/16/218118" & 4" Water Main103+55 to 300+702 daysTue 8/17/21Wed 8/18/211012Pressure and Purities3 daysThu 9/9/21Mon 9/13/21134" Water Main 96+52 to 97+202 daysTue 9/7/21Wed 9/8/2114Pressure and Purities2 daysThu 9/9/21Fri 9/10/2113154" Water 200+00 to 203+002 daysMon 10/4/21Tue 10/5/2116Services on 4" (8 services)2 daysMon 10/11/21Tue 10/12/2115FS+2 days17Tie In1 dayWed 10/13/21Wed 10/13/21161819Services14 daysThu 8/26/21Mon 9/20/2120Services10 daysTue 9/21/21Wed 10/6/21192122Crew #2 Eric43 daysMon 7/26/21Wed 10/6/2123Mob1 dayMon 7/26/21Mon 7/26/2124Water Main3 daysTue 7/27/21Thu 7/29/212325Pressure Test0 daysThu 7/29/21Thu 7/29/212426Tie In at 52+47 and Hydrant 59+951 dayTue 8/3/21Tue 8/3/2127Services 21 daysMon 8/16/21Mon 9/20/2128Services10 daysTue 9/21/21Wed 10/6/212729Tie in at 17+28 and 21+921 dayTue 8/10/21Tue 8/10/2124FS+2 days3031Tie Ins2 daysThu 10/7/21Mon 10/11/2132Tie In at 56+30 and 77+85 1 dayThu 10/7/21Thu 10/7/212033Tie In 69+90 and 62+351 dayMon 10/11/21Mon 10/11/21323435Restoration40 daysMon 8/23/21Thu 10/28/217/WTFSSMTWTFSSMTWTFJul 18, '21Jul 25, '21TaskSplitProgressMilestoneSummaryProject SummaryExternal TasksExternal MilestoneDeadlinePape and Sons ConstructionCity of BremertonMarine Drive Water Main 2021Page 1Project: 9-28-21 ScheduleDate: Tue 9/28/21Prepared by Brad ApplemanSchedule as of 10/4/21DocuSign Envelope ID: 62208C2F-4724-47B4-8C12-036ED920D814
IDTask NameDurationStartFinishPredecessors36Remove 2 Big Trees2 daysWed 8/25/21Thu 8/26/2137Concrete C&G1 dayMon 8/23/21Mon 8/23/2138HMA Rocky Point Crossings1 dayWed 9/8/21Wed 9/8/2139HMA Patching2 daysWed 9/22/21Thu 9/23/2140HMA Patching3 daysWed 10/13/21Mon 10/18/211641HMA Overlay2 daysTue 10/19/21Wed 10/20/214042Clean up and Demob5 daysThu 10/21/21Thu 10/28/2141WTFSSMTWTFSSMTWTFJul 18, '21Jul 25, '21TaskSplitProgressMilestoneSummaryProject SummaryExternal TasksExternal MilestoneDeadlinePape and Sons ConstructionCity of BremertonMarine Drive Water Main 2021Page 2Project: 9-28-21 ScheduleDate: Tue 9/28/21Current Final HMA Scheduled to be completed 10/20/21 Pending WeatherDocuSign Envelope ID: 62208C2F-4724-47B4-8C12-036ED920D814