CHANGE ORDER
CONTRACT CHANGE ORDER NO: 3
PROJECT NAME: 6th Street Sewer Replacement
PROJECT NO: 5859 CONTRACTOR: Pape & Sons
ORIGINAL CONTRACT AMOUNT: 271,944.10 DAYS: 50
PREVIOUSLY APPROVED CHANGES: 33,062.49 DAYS: 154
THIS CHANGE: 20,937.48 DAYS: 243
REVISED CONTRACT AMOUNT: 325,944.07 DAYS: 397
This Change Order covers changes to the subject contract as described herein. The Contractor shall construct, furnish equipment and materials, and perform all work as necessary or required to complete the Change Order Items. The increase or decrease in contract price shown below includes any
applicable taxes. Rule 170 Rule 171 DESCRIPTION OF CHANGES INCREASE IN CONTRACT
AMOUNT ($)
(DECREASE) IN CONTRACT
AMOUNT ($)
CONTRACT TIME
EXTENSION (DAYS:)
X WCD #7 – Complete surface restoration at three intersections and reinstall survey monument. This also adds additional calendar days to allow the contractor to complete the work during dry weather. The completion of this work was delayed due to winter weather.
19,208.70 243
NET CHANGE IN CONTRACT AMOUNT INCREASE OR (DECREASE) 19,208.70
ESTIMATED SALES TAX AT 9.0% 1,728.78
TOTAL INCLUDING SALES TAX 20,937.48 243
Contractor acknowledges and accepts that this Change Order constitutes final settlement of all claims of any kind or nature arising from or connected with any work either covered or affected by this Change Order, including, without limitation, claims related to contract time, on-site or home office overhead, or lost profits. Nothing in this Change Order shall limit the City’s right to bring a claim for past performance.
The undersigned Contractor approves the foregoing Change Order as to the changes, if any, in the contract price specified for each item, including any and all supervision costs and other miscellaneous
DocuSign Envelope ID: D0210641-BFBC-4FF8-BE8E-CCD80BB3CB05
2/22/22
DocuSign Envelope ID: D0210641-BFBC-4FF8-BE8E-CCD80BB3CB05
3/1/2022
3/1/2022
6th Street Sewer Replacement wjd 1/26/2022
Change Order #3 Summary
Item Description Amt Sales Tax TOTAL
WCD #7 for surface restoration at 3 locations
and survey monument installation 19,208.70$ 1,728.78$ 20,937.48$
Original Contract Amount 271,944.10$
Change Order #1 27,308.70$
Change Order #2 5,753.79$ 305,006.59$
$ 20,937.48
325,944.07$
Maximum contract amount that can be approved by the Mayor $ 326,332.92
Therefore change order #3 can be approved by the Mayor
Current Contract Amount (includes COs # 1 and 2)
Change Order #3
TOTAL REVISED CONTRACT AMT w/ CO #3
DocuSign Envelope ID: D0210641-BFBC-4FF8-BE8E-CCD80BB3CB05
Bill Davis
DocuSign Envelope ID: D0210641-BFBC-4FF8-BE8E-CCD80BB3CB05
6th Street Sewer Replacement wjd, 1/26/22
WCD #7 COST ESTIMATE
Reg Rate Hours Amt
Foreman 79.52$ 24 1,908.48$
Laborer 58.26$ 24 1,398.24$
Laborer 58.26$ 20 1,165.20$
Operator 77.30$ 20 1,546.00$
Truck Driver 69.89$ 10 698.90$
TCS 49.38$ 20 987.60$
SUBTOTAL 7,704.42$
Reg Rate Hours Amt `
Backhoe 50.00$ 10 500.00$
Excavator 80.00$ 0 -$
Dump Truck 80.00$ 10 800.00$
Service Truck 40.00$ 10 400.00$
SUBTOTAL 1,700.00$
Unit Cost Units # of Units TOTAL
CSTC 20.00$ LF 10.00 200.00$
Asphalt 100.00$ Tn 10.00 1,000.00$
Misc Survey Materials 100.00$ Est 1.00 100.00$
SUBTOTAL 1,300.00$
Core Driller $750 Hr 1 750.00$
Surveying (3 trips)2,500.00$ LS 1 2,500.00$
SUBTOTAL 3,250.00$
Base Total Markup Markup Amt TOTAL
LABOR 7,704.42$ 29%2,234.28$ 9,938.70$
EQUIPMENT 1,700.00$ 21%357.00$ 2,057.00$
MATERIALS 1,300.00$ 21%273.00$ 1,573.00$
SUBCONTRACTOR 3,250.00$ 12%390.00$ 3,640.00$
SUBTOTAL 1 (PRE-TAX)17,208.70$
This is an estimate, payment to be based on actual work performed
CONTINGENCY, ONLY TO BE USED UPON WRITTEN AUTHORIZATION 2,000.00$
TOTAL, WCD #7 (pre-tax)19,208.70$
SUBCONTRACTOR
MARKUPS
Description: The City repaired pipe at 3 locations in order to perform cure-in-place pipe lining at these
locations. Currently these locations are covered with cold mix asphalt. These will be replaced with 8" thick
HMA as approved by WSDOT. Additionally, Pape will reset a disturbed survey monument which will be
surveyed and recorded by a licensed surveyor.
LABOR
EQUIPMENT
MATERIALS
DocuSign Envelope ID: D0210641-BFBC-4FF8-BE8E-CCD80BB3CB05
6th Street Sewer Replacement
Surface Restoration Locations
February 2022
Change Order #3
SURFACE RESTORATION AT INTERSECTION OF BURWELL STREET
AND CHESTER AVENUE
DocuSign Envelope ID: D0210641-BFBC-4FF8-BE8E-CCD80BB3CB05
6th Street Sewer Replacement
Surface Restoration Locations
February 2022
Change Order #3
SURFACE RESTORATION AT INTERSECTION OF 11TH STREET
AND WARREN AVENUE
DocuSign Envelope ID: D0210641-BFBC-4FF8-BE8E-CCD80BB3CB05
6th Street Sewer Replacement
Surface Restoration Locations
February 2022
Change Order #3