HomeMy WebLinkAbout1 - Original Submission_ 20220126_5859_Change Order #3_PapeCITY OF BREMERTON CHANGE ORDER CONTRACT CHANGE ORDER NO: 3 PROJECT NAME: 6th Street Sewer Replacement PROJECT NO: 5859 CONTRACTOR: Pape & Sons ORIGINAL CONTRACT AMOUNT: 271,944.10 DAYS: 50 PREVIOUSLY APPROVED CHANGES: 33,062.49 DAYS: 154 THIS CHANGE: 20,937.48 DAYS: 243 REVISED CONTRACT AMOUNT: 325,944.07 DAYS: 397 This Change Order covers changes to the subject contract as described herein. The Contractor shall construct, furnish equipment and materials, and perform all work as necessary or required to complete the Change Order Items. The increase or decrease in contract price shown below includes any applicable taxes. Rule 170 Rule 171 DESCRIPTION OF CHANGES INCREASE IN CONTRACT AMOUNT ($) (DECREASE) IN CONTRACT AMOUNT ($) CONTRACT TIME EXTENSION (DAYS:) X WCD #7 – Complete surface restoration at three intersections and reinstall survey monument. This also adds additional calendar days to allow the contractor to complete the work during dry weather. The completion of this work was delayed due to winter weather. 19,208.70 243 NET CHANGE IN CONTRACT AMOUNT INCREASE OR (DECREASE) 19,208.70 ESTIMATED SALES TAX AT 9.0% 1,728.78 TOTAL INCLUDING SALES TAX 20,937.48 243 Contractor acknowledges and accepts that this Change Order constitutes final settlement of all claims of any kind or nature arising from or connected with any work either covered or affected by this Change Order, including, without limitation, claims related to contract time, on-site or home office overhead, or lost profits. Nothing in this Change Order shall limit the City’s right to bring a claim for past performance. The undersigned Contractor approves the foregoing Change Order as to the changes, if any, in the contract price specified for each item, including any and all supervision costs and other miscellaneous DocuSign Envelope ID: D0210641-BFBC-4FF8-BE8E-CCD80BB3CB05 2/22/22 DocuSign Envelope ID: D0210641-BFBC-4FF8-BE8E-CCD80BB3CB05 3/1/2022 3/1/2022 6th Street Sewer Replacement wjd 1/26/2022 Change Order #3 Summary Item Description Amt Sales Tax TOTAL WCD #7 for surface restoration at 3 locations and survey monument installation 19,208.70$ 1,728.78$ 20,937.48$ Original Contract Amount 271,944.10$ Change Order #1 27,308.70$ Change Order #2 5,753.79$ 305,006.59$ $ 20,937.48 325,944.07$ Maximum contract amount that can be approved by the Mayor $ 326,332.92 Therefore change order #3 can be approved by the Mayor Current Contract Amount (includes COs # 1 and 2) Change Order #3 TOTAL REVISED CONTRACT AMT w/ CO #3 DocuSign Envelope ID: D0210641-BFBC-4FF8-BE8E-CCD80BB3CB05 Bill Davis DocuSign Envelope ID: D0210641-BFBC-4FF8-BE8E-CCD80BB3CB05 6th Street Sewer Replacement wjd, 1/26/22 WCD #7 COST ESTIMATE Reg Rate Hours Amt Foreman 79.52$ 24 1,908.48$ Laborer 58.26$ 24 1,398.24$ Laborer 58.26$ 20 1,165.20$ Operator 77.30$ 20 1,546.00$ Truck Driver 69.89$ 10 698.90$ TCS 49.38$ 20 987.60$ SUBTOTAL 7,704.42$ Reg Rate Hours Amt ` Backhoe 50.00$ 10 500.00$ Excavator 80.00$ 0 -$ Dump Truck 80.00$ 10 800.00$ Service Truck 40.00$ 10 400.00$ SUBTOTAL 1,700.00$ Unit Cost Units # of Units TOTAL CSTC 20.00$ LF 10.00 200.00$ Asphalt 100.00$ Tn 10.00 1,000.00$ Misc Survey Materials 100.00$ Est 1.00 100.00$ SUBTOTAL 1,300.00$ Core Driller $750 Hr 1 750.00$ Surveying (3 trips)2,500.00$ LS 1 2,500.00$ SUBTOTAL 3,250.00$ Base Total Markup Markup Amt TOTAL LABOR 7,704.42$ 29%2,234.28$ 9,938.70$ EQUIPMENT 1,700.00$ 21%357.00$ 2,057.00$ MATERIALS 1,300.00$ 21%273.00$ 1,573.00$ SUBCONTRACTOR 3,250.00$ 12%390.00$ 3,640.00$ SUBTOTAL 1 (PRE-TAX)17,208.70$ This is an estimate, payment to be based on actual work performed CONTINGENCY, ONLY TO BE USED UPON WRITTEN AUTHORIZATION 2,000.00$ TOTAL, WCD #7 (pre-tax)19,208.70$ SUBCONTRACTOR MARKUPS Description: The City repaired pipe at 3 locations in order to perform cure-in-place pipe lining at these locations. Currently these locations are covered with cold mix asphalt. These will be replaced with 8" thick HMA as approved by WSDOT. Additionally, Pape will reset a disturbed survey monument which will be surveyed and recorded by a licensed surveyor. LABOR EQUIPMENT MATERIALS DocuSign Envelope ID: D0210641-BFBC-4FF8-BE8E-CCD80BB3CB05 6th Street Sewer Replacement Surface Restoration Locations February 2022 Change Order #3 SURFACE RESTORATION AT INTERSECTION OF BURWELL STREET AND CHESTER AVENUE DocuSign Envelope ID: D0210641-BFBC-4FF8-BE8E-CCD80BB3CB05 6th Street Sewer Replacement Surface Restoration Locations February 2022 Change Order #3 SURFACE RESTORATION AT INTERSECTION OF 11TH STREET AND WARREN AVENUE DocuSign Envelope ID: D0210641-BFBC-4FF8-BE8E-CCD80BB3CB05 6th Street Sewer Replacement Surface Restoration Locations February 2022 Change Order #3 SURFACE RESTORATION AT INTERSECTION 16TH STREET AND WARREN AVENUE DocuSign Envelope ID: D0210641-BFBC-4FF8-BE8E-CCD80BB3CB05