HomeMy WebLinkAbout12/21/2022 6A
AGENDA BILL
CITY OF BREMERTON
6A
CITY COUNCIL
SUBJECT:Study SessionDate: December 14, 2022
Final Public Hearing on the Property Use COUNCIL MEETING Date: December 21, 2022
Agreement with Active Construction Inc.for
Department: Parks & Recreation
the Pine Road Stormwater Basin
Presenter: Jeff Elevado
Improvement Project
Phone: (360) 473-5428
SUMMARY:
Active Construction Inc. is the contractor for the Public Works & Utilities Pine Road Stormwater Basin
Improvement Project currently underway. The contractor has proposed use of an area of Stephenson
Canyon to place ajob trailer and temporary storage of associated project materials and equipment.
This area of Stephenson Canyon is an old roadway and cul-de-sac that contains wood, concrete, and
angular rock debris. In consideration for allowing the contractor to use the area, Parks and Recreation
staff have coordinated the removal and disposal of all existing debris and clearing the area of
unwanted vegetation. The proposed use is anticipated to last through March of 2023.
The Bremerton Parks and Recreation Commission has reviewed the request and recommended
approval by City Council at their September 27, 2022 public meeting.
ATTACHMENTS:
1)Property Use Agreement
2)Bremerton Parks & Recreation Commission Advisory Report (9/30/2022)
3)Stephenson Canyon Current Site Condition Photos
FISCAL IMPACTS(Include Budgeted Amount): None
STUDY SESSION AGENDA: LimitedPresentationFull Presentation
STUDY SESSION ACTION:Consent AgendaGeneral BusinessPublic Hearing
RECOMMENDED MOTION:
Move to approve the Property Use Agreement with Active Construction, Inc. for use of a portion of
Stephenson Canyon and authorize the Mayor to finalize and execute the agreement with
substantially the same terms and conditions as presented.
COUNCIL ACTION:xApprove Deny Table Continue No Action
Form Updated 11/09/2021