AGENDA BILL
CITY OF BREMERTON
3 I
CITY COUNCIL
SUBJECT:Study SessionDate: July 27, 2022
Supplemental AgreementNo. 4with COUNCIL MEETING Date: August 3, 2022
Skillings, Inc. forthe Design of the
Department: PW&U Engineering
th
Washington &11Street Roundabout
Presenter: Shane Weber
Project
Phone: (360) 473-2354
SUMMARY:
In November 2019, the City executed a contract with Skillings, Inc. to design the Washingtonand
th
11Street Roundabout projectfor $530,000.00. Three supplement agreements have been
executed: Supplement No. 1 was a no cost change to remove a survey subconsultant from the
design contract. Supplement No. 2 was in the amount of $130,882.99 and addedadditional design
work to replace sidewalks on lower Washington Avenue and replace two water main crossings on
th
11Street. SupplementNo. 3 was in the amount of $95,358.28 and addedscope to redesign the
mainline alignment and replace anexisting wallto address neighborhood concerns. Supplement No.
3 also added time by extendingthe contract through December 21, 2024.
The proposed Supplement No. 4 increases the contract value by $167,369.09 to a new total of
$923,610.36; the work includes landscaping design, ad-bid support services and construction
engineering support services.
ATTACHMENTS:
1)Local Agency Supplemental AgreementNo. 4with Skillings, Inc.
FISCAL IMPACTS(Include Budgeted Amount):
This project is in the Transportation Capital Fund, no budget adjustment is required.
STUDY SESSION AGENDA: LimitedPresentationFull Presentation
STUDY SESSION ACTION:Consent AgendaGeneral BusinessPublic Hearing
RECOMMENDED MOTION:
th
Move to approve SupplementalAgreementNo. 4 with Skillings, Inc. for the Washington& 11Street
Roundabout Project; and authorize the Mayor to finalize and execute the agreement with
substantially the same terms and conditions as presented.
COUNCIL ACTION:Approve Deny Table Continue No Action