HomeMy WebLinkAbout1 - Original Submission_ 20220617_5848_Contract Modification No. 1 with PMXCONTRACT MODIFICATION AGREEMENT NO. 1 BETWEEN THE CITY OF BREMERTON AND PARAMETRIX, INC.
PROJECT: Decommission Beach Sewer in Manette (OF-4 to EB-2)
CONSULTANT: Parametrix, Inc.
DATE: May 18, 2022
THIS CONTRACT MODIFICATION AGREEMENT SPECIFICALLY AMENDS THE
PROFESSIONAL SERVICES AGREEMENT (the "Contract") entered into between the City of Bremerton and Parametrix, Inc. on December 30, 2021.
All provisions in the Contract shall remain in full force and effect except as expressly modified by this document.
For valuable consideration and by mutual consent of the parties, the modifications to the Contract are as follows: I.
Section I.Scope , is modified as follows:
See Amended Scope of Work attached as Exhibit A.
Section II. Term, is modified as follows: The term of the contract is not changed for December 31, 2023.
Section III. Compensation, is modified as follows:
The original contract amount was $412,208. Per Exhibit B, the City shall pay the Consultant for the additional work described in Exhibit A, based on time and materials, an amount not to exceed $67,749 for a total amended contract amount of $479,957, including this Contract Modification.
II.
Consultant accepts all requirements of this Contract Modification by endorsing below. Consultant further agrees that this Contract Modification constitutes full and final
settlement of all of the Consultant’s claims for contract time and for all costs of any kind, including without limitation, costs of delays related to any work either covered or affected by this Contract Modification, claims related to on-site or home office overhead, or lost profits. This Contract Modification does not limit the City’s right to bring a claim for past performance.
The undersigned consultant approves the foregoing Contract Modification as to the changes, if any, in the contract price specified for each item, including any and all supervision costs and other miscellaneous costs relating to the change in work, and as to the extension of time allowed, if any, for completion of the entire work due to said Contract
Modification.
Page 1 of 2
Decommission Beach Sewer in Manette (OF-4 to EB-2) Contract Modification No. 1
DocuSign Envelope ID: BAAF135D-DAE4-4F5C-8578-164694236DB2
Page 2 of 2
Decommission Beach Sewer in Manette (OF-4 to EB-2) Contract Modification No. 1
This document will become a supplement of the contract and all provisions will apply hereto. It is understood that this Contract Modification shall be effective when approved by the City
of Bremerton.
The parties whose names appear below warrant that they are authorized to enter into a contract modification that is binding on the parties of this contract. In addition, Consultant warrants that it has or will inform the surety of this change, and shall take appropriate action
to modify any bonds required under the contract to address this change.
IN WITNESS WHEREOF, the parties have executed this Contract Modification on the day and year first written above.
City Engineer / Public Works Director approved to process _________________________ (Initials and Date)
PARAMETRIX, INC. THE CITY OF BREMERTON
By: By:
Print Name: Print Name: Greg Wheeler Its: Its: Mayor Date: Date:
APPROVED AS TO FORM: ATTEST:
By: By:
KYLIE J. FINNELL, Bremerton City Attorney ANGELA HOOVER, City Clerk
NOTICES TO BE SENT TO: NOTICES TO BE SENT TO:
Attn: Cedar Simmons Attn: Angela Hoover
Parametrix, Inc. City of Bremerton 60 Washington Ave, Suite 390 345 6th Street, Suite 100 Bremerton, WA 98337 Bremerton, WA 98337-1891
R:\Legal\Legal\Forms\FORMS ON COBWEB\Contract Modification Rev. 09 2021.docx
Jenifer Young
EP&C Division Manager
Ned Lever
Digitally signed by Ned Lever
DN: C=US,
E=ned.lever@ci.bremerton.wa.us, O=City of Bremerton, OU=Engineering, CN=Ned LeverDate: 2022.06.21 09:11:03-07'00'
DocuSign Envelope ID: BAAF135D-DAE4-4F5C-8578-164694236DB2
6/22/2022 6/22/2022
City of Bremerton 233-1896-8BL
Decommission Beach Sewer OF-4 to EB-2 1 May 2022
Contract Modification 1 – Additional Services
EXHIBIT A - SCOPE OF WORK
City of Bremerton
Decommission Beach Sewer OF-4 to EB-2 | Contract Modification 1 – Additional Services
PROJECT BACKGROUND
This project will protect Sinclair Inlet and the Port Washington Narrows by decommissioning an existing gravity
beach sewer located within the tidelands of the Port Washington Narrows. This project also includes the
installation of small municipal pump stations, individual grinder pump systems, and the low-pressure sewer (LPS)
mains and force mains required to redirect flow from individual waterfront properties away from the beach sewer
to an existing upland sewer system. The proposed project will eliminate approximately 1,900 feet of gravity
sewer, 13 side sewers (laterals), and 5 manholes, all buried along the beach. The section of sewer main to be
decommissioned is located along the shoreline immediately north of the Manette Bridge, starting at Sewage
Pump Station EB-2 and ending at a new City Pump Station to be built near the current location of Combined
Sewer Overflow Structure No. 4 (OF-4). The overall goal of the project is to eliminate gravity sewer infrastructure
in marine tidelands that is difficult to maintain and potentially deleterious to the marine environment. This
project is funded by a Clean Water State Revolving Fund (CWSRF) Loan for $2,300,000 from the Washington State
Department of Ecology (Ecology) that expires on December 31, 2022 (Ecology Agreement).
CONTRACT MODIFICATION FOR ADDITIONAL SERVICES
The original scope included using multiple E-One grinder pumps to collect and pump flow from the apartment
complex and residences that contributed to the gravity sewer at the end of E. 16th. However, due to the
complexity of the electrical upgrades that would be required at the apartment complex, the City has elected to
design and install a single new City pump station at the end of 16th Street and decommission existing Overflow
Structure #4 (OF-4). This City pump station was not included in the original scope of work for the project. The
additional scope included herein is for consulting services to support this effort, as well as additional survey work
for boundary line determination where buildings and residences are located very close to property lines which
may affect siting of grinder pump tanks and discharge lines.
SUMMARY OF WORK BREAKDOWN
The bold tasks below indicate original scope tasks where additional scope is proposed:
Task 1 – Survey
Task 2 – Preliminary Design (30%)
Task 3 – Detailed Design (75%, 100%)
Task 4 – Outreach
Task 5 – Environmental Permitting
Task 6 – Bidding Assistance
Task 7 – Services During Construction
Task 8 – Project Management
DocuSign Envelope ID: BAAF135D-DAE4-4F5C-8578-164694236DB2
SCOPE OF WORK (continued)
City of Bremerton 233-1896-8BL
Decommission Beach Sewer OF-4 to EB-2 2 May 2022
Contract Modification 1 – Additional Services
Task 9 – Geotechnical Support
Task 10 – Electrical Support
Task 11 – Management Reserve
DETAILED WORK BREAKDOWN
Task 3 – Detailed Design
Subtask 3.1: Intermediate Design – 75% (Add-On for City Pump Station)
Objective
Prepare basis of design and 75% design level engineering design documents for a two-pump submersible pump
station in City ROW on E 16th Street, west of the intersection with Parkside Drive, consisting of wet well, valve
vault, generator, and control panel with shelter. Design will also identify demolition of Overflow Vault 4 (OF-4).
Activities
·Determine design capacity of city pump station.
Determine minimum size of station based on current water usage and connected properties.
Identify potential future development and potential increase in flows.
Work with City to determine if potential future flows will be included in station capacity.
·Incorporate into deliverables as established in the original scope of work:
Design and demolition drawings into the drawing set per the attached Sheet List.
Cost items into Engineer’s Opinion of Probable Construction Cost (EOPCC).
Design related information into draft Basis of Design Technical Memorandum.
·Advance 30% City pump station drawings to 75% design level (see Attachment 1: Sheet Index).
·Develop 75% pump station supplementary technical specifications.
·Develop structural design elements for electrical enclosure and equipment housekeeping pads.
·Advance EOPCC for items related to the pump station to 75% design level.
·Add pump station bid item to draft EOPCC.
·Prepare pump station updates to the basis of design technical memorandum.
·Perform internal QA/QC.
Assumptions
·Parametrix and the City will perform a site visit to the proposed pump station site to discuss location and
other station details. Site visit assumes 1 hour onsite for up to 2 Parametrix staff.
·The station will be located more than 50 feet from the steep grade to prevent locating within critical area
or requiring permitting for steep slopes. The 50-foot buffer will be marked on the ground by Parametrix
prior to the site meeting. It is assumed the design will not require any additional permitting.
DocuSign Envelope ID: BAAF135D-DAE4-4F5C-8578-164694236DB2
SCOPE OF WORK (continued)
City of Bremerton 233-1896-8BL
Decommission Beach Sewer OF-4 to EB-2 3 May 2022
Contract Modification 1 – Additional Services
·The forcemain will terminate in the closest sewer manhole in Wheaton Way.
·Deliverables and internal Parametrix QA/QC will be as established in the original scope of work.
·The technical specifications associated with the equipment for this station will be in Construction
Specifications Institute (CSI) format.
·Any significant modifications to siting and layout for this work after 30% comments are provided may
require a contract modification.
·Geotechnical engineering to support this task will be managed under Geotechnical Support task.
·City to provide City pump station standards and list of recommended/preferred products for pumps,
valves, flowmeters, pressure meters, instrumentation, generator, and other equipment items.
·City’s review period and comments for the city pump station will be as established for the original scope.
·Deliverables and internal Parametrix QA/QC will be as established in the original scope of work.
·No other structural design services are included except those specified herein.
Deliverables
·Design and cost items to be incorporated into the deliverables established in the original scope of work.
·CSI specifications related to the pump station.
Subtask 3.2 – Final Design (100%) – (Add-on for City Pump Station)
Objective
Provide services for final (100%) design for the submersible pump station in City ROW in E 16th Street.
Activities
·Advance city pump station drawings to 100% design level.
·Advance city pump station supplementary technical specifications to 100% design level.
·Advance EOPCC for items related to the pump station to 100% design level.
·Perform internal QA/QC.
Assumptions
·No design review meeting will be held with the City.
·Internal QA/QC documentation is excluded as a deliverable.
·No City-comments will be incorporated on the 100% design package.
·Incorporation of any modifications after the 100% design package is submitted may require contract
modification.
·No other submittals are included.
Deliverables
·Design and cost items to be incorporated into the deliverables established in the original scope of work.
DocuSign Envelope ID: BAAF135D-DAE4-4F5C-8578-164694236DB2
SCOPE OF WORK (continued)
City of Bremerton 233-1896-8BL
Decommission Beach Sewer OF-4 to EB-2 4 May 2022
Contract Modification 1 – Additional Services
·CSI specifications related to the pump station.
Task 8 – Project Management
Provide oversight, communications, and management of the additional work. The additional project management
scope required is for the additional management of the tasks requested within this contract modification.
Task 9 – Geotechnical Support
Subtask 9.1 – Geotechnical Support for City Pump Station 30% Design
Objective
HWA GeoSciences Inc. (HWA) will provide geotechnical engineering services in support of the design and analyses
for the City pump station. These services will consist of a field exploration, laboratory testing, evaluation of
subsurface conditions, geotechnical recommendations to support facility design, and incorporation of
recommendations into the geotechnical report for this project.
Activities
·Coordinate site explorations consisting of one boring drilled to a depth of 25 feet for site evaluation for
pump station.
·Conduct a site visit to mark the proposed boring location and call in for utility locates.
·Observe soil borings conducted by drilling subcontractor to collect soils samples. Develop a summary log
of the exploration.
·Provide laboratory testing for select soil samples, including tests for moisture content and grain size
analysis.
·Assess soil profile for seismic design (i.e., determination of Site Class and parameters) to support
structural design.
·Provide design parameters for static and seismic lateral earth pressures and resistance to buoyancy for
the pump station structure, vaults, and manholes.
·Evaluate key geotechnical issues and provide recommendations for excavation and shoring and
dewatering of the excavations.
·Assess impact of generator slab and control panel and address mitigation of placing these project
elements within the 50-foot buffer of the adjacent landslide hazard area.
·Provide recommendations for site preparation, grading, drainage, and wet-weather earthwork
procedures.
·Provide task management and internal QA/QC specific to Pump Station design.
Assumptions
·Pump station will be constructed no deeper than 15 feet and will not be located within the 50-foot buffer
for the adjacent steep slope.
·The exploration proposed herein will not be used to assess site environmental conditions. However, visual
or olfactory observations regarding potential contamination will be noted. Analysis, testing, storage, and
DocuSign Envelope ID: BAAF135D-DAE4-4F5C-8578-164694236DB2
SCOPE OF WORK (continued)
City of Bremerton 233-1896-8BL
Decommission Beach Sewer OF-4 to EB-2 5 May 2022
Contract Modification 1 – Additional Services
handling of potentially contaminated soil and groundwater (either sampled or spoils from drilling) are
beyond this scope of services. If contaminated soils and/or groundwater are encountered, the material
will be properly contained on-site for disposal as mutually agreed upon without additional cost to HWA.
·Boring location will be located using handheld Global Positioning System (GPS) and measurement from
existing known features.
·Following finalization of the geotechnical report, all soil samples will be disposed of. Long-term storage of
soil samples by the Consultant is not included.
Task 10 – Electrical Support
Task 10.1 – Electrical Support (Add-On for City Pump Station)
Objective
Identify electrical utility power upgrade needed or required at the pump station location. Size and locate standby
backup generator and transfer switch. Provide layout for rack-style electrical equipment shelter. Provide custom
control panel with SCADA telemetry.
Activities
·Utilize photographs from site investigation to evaluate and determine the specific required electrical
upgrades.
·Electrical design shall include performing load calculations for new electrical service, sizing of main
disconnect, conductors, and conduit, and locating equipment.
·Provide a layout and assembly detail for an electrical cabinet with an overhang or shelter to provide relief
from heavy weather.
·Size and locate standby backup generator and transfer switch for two-pump City pump station.
·Incorporate City recommendations for design of pump station control panel with SCADA telemetry.
Provide panel layout and wiring diagrams sufficient for an integrator to quote and furnish control
equipment.
Assumptions
·The scope of work includes evaluation of the 16th Street City pump station location.
·Photos from the site investigations will be used for the evaluation. No site visits from the electrical
engineer are included.
·Physical description of the improvements will be used in the specifications for the required upgrades or
photos in a specification appendix will be used to identify specific work needed at the site.
·Pump station design will be a two-pump pump station with custom control panel based on
recommendations from the City operating a maximum of two submersible pumps. Parametrix will
coordinate with the City for preferred controls hardware. No programming, telemetry, or SCADA support
will be provided under the design scope, but can be provided under a separate scope. The station will not
have variable frequency drives (VFDs).
·Backup power will be provided from a permanent standby generator.
DocuSign Envelope ID: BAAF135D-DAE4-4F5C-8578-164694236DB2
SCOPE OF WORK (continued)
City of Bremerton 233-1896-8BL
Decommission Beach Sewer OF-4 to EB-2 6 May 2022
Contract Modification 1 – Additional Services
·Residential pump stations with a total flow of more than 1,500 gallons per day are considered Class I,
Division 1, Group D per NFPA 820.
·Electrical specifications will be in CSI format.
·Drawings developed under this subtask will be limited to four additional electrical drawings, including one
electrical detail sheet and three control panel sheets.
·The City, with help from the electrical contractor, will use electrical calculations provided in the contract
drawings to coordinate with the electrical utility for the new electrical services.
·Engineering support for coordination with the electrical utility is not included in this scope of work.
·Additional CSI specifications will be provided as part of this add-on:
40 70 00 – Instrumentation and Controls General Requirements
40 63 43 – Programmable Logic Controllers
40 67 00 – Control Panels
40 78 00 – Panel Mounted and Miscellaneous Field Devices
Deliverables
·Four additional electrical drawings to be included with other design deliverables under Tasks 3 and 4.
·Four CSI specifications to be included with other design deliverables under Tasks 3 and 4.
Electrical design elements developed under this subtask will be incorporated as appropriate into the other design
deliverables described in Tasks 3 and 4.
DocuSign Envelope ID: BAAF135D-DAE4-4F5C-8578-164694236DB2
2022-05-10
Parametrix
City of Bremerton
Manette Sewer Decom
EXHIBIT B - COMPENSATION
PARAMETRIX - DECOMMISSIONING MANETTE BEACH SEWER
CONTRACT MODIFICATION #1
Task Amount
Not-to-Exceed + / -Credit /
Deduct
Cost /
Adder
Total
Proposed
CM1
Task Amount
Not-to-Exceed
01 Survey $ 31,119 $ 1,764 $ - $ - $ - $32,883
02 Preliminary Design - 30% $ 53,543 $ (1,764) $ - $ - $ - $51,779
03 Detailed Design $ 112,504 $ - $ (30,965) $ 57,501 $ 26,536 $ 139,040
04 Outreach $ 2,014 $2,014
05 Environmental Permitting $ 45,289 $45,289
06 Bidding Assistance $ 4,978 $4,978
07 Services During Construction $ 33,713 $33,713
08 Project Management $ 21,009 $ - $ - $ 1,340 $ 1,340 $22,349
09 Geotechnical Support $ 29,491 $ - $ - $ 14,949 $ 14,949 $44,440
10 Electrical Support $ 28,548 $ - $ (3,944) $ 28,868 $ 24,924 $53,472
11 Management Reserve $ 50,000 $ - $ - $ - $ - $50,000
$ 412,208 $ - $ (34,909) $ 102,658 $ 67,749 $ 479,957
Original
Contract
Amended Contract
Including Proposed
CM 1
Total Tasks Not-to-Exceed Amount
Task No.Description
Previous
Modifications
Proposed Contract Modification
(CM) 1
DocuSign Envelope ID: BAAF135D-DAE4-4F5C-8578-164694236DB2
City of Bremerton Staff Name c. simmons j. linke
Y.
Mahmoodi j. stolle r. nickel s. harris K. Winters c. wittman j. reinmuth d. peterson r. rohler
Decommission Beach Sewer OF-4 to EB-2
Contract Mod 1 - Ad'l Services (City P/S)Title/Category PM PE Spec Support
Eng. and
Design
Support
QC Project Controls
Specialist
Project
Accountant Electrical EOR Electrical
Designer IV CADD Support Sr Electrical
Engineer
233-1896-179 Billing Rate 240.22 211.82 145.76 116.10 269.95 131.38 116.72 237.18 162.38 145.42 226.33
2,883$ 11,438$ 875$ 10,681$ 1,620$ 263$ 117$ 11,859$ 1,624$ 8,725$ 2,716$ 305 52,800$ 14,949$ 14,949$ 67,749$
3.0 Detailed Design (75%, 100%)8 54 6 92 6 166 26,536$ -$ -$ 26,536$
3.1 Intermediate Design (75%) for City Pump Station -$ -$ -$
sha 8 10 18 2,856$ -$ 2,856$
PS Wetwell and Valve Vault Design 12 20 32 4,864$ -$ 4,864$
EOPCC - City Pump Station 4 8 12 1,776$ -$ 1,776$
Final Basis of Design TM 2 4 6 888$ -$ 888$
Specifications - City Pump Station 4 4 10 18 2,591$ -$ 2,591$
QA/QC 4 4 1,080$ -$ 1,080$
Design Coord. (Change/Task/Issues-Decision Log)4 4 2 10 2,040$ -$ 2,040$
3.2 Final Design (100%) for City Pump Station -$ -$ -$
4 8 12 1,776$ -$ 1,776$
2 4 6 888$ -$ 888$
Specifications 2 2 8 12 1,644$ -$ 1,644$
QA/QC 2 2 540$ -$ 540$
PS Wetwell and Valve Vault Design 8 16 24 3,552$ -$ 3,552$
Design Coord. (Change/Task/Issues-Decision Log)4 4 2 10 2,040$ -$ 2,040$
8.0 Project Management 4 2 1 7 1,340$ -$ -$ 1,340$
Project Management 4 2 1 7 1,340$ -$ 1,340$
9.0 Geotechnical Support - HWA -$ 14,949$ 14,949$ 14,949$
9.1 Geotechnical Support - HWA -$ 14,949$ 14,949$ 14,949$
10.0 Electrical Support 50 10 60 12 132 24,924$ -$ -$ 24,924$
10.1 Electrical Support -$ -$ -$
Intermediate Design (75%) for City Pump Station
16 40 56 9,612$ -$ 9,612$
Specifications 16 16 3,795$ -$ 3,795$
EOPCC 8 8 1,299$ -$ 1,299$
QA/QC 8 8 1,811$ -$ 1,811$
Submittal -$ -$ -$
Design Review Meetings 1 1 237$ -$ 237$
Response to Comments 1 1 237$ -$ 237$
Final Design (100%) for City Pump Station
8 20 28 4,806$ -$ 4,806$
Specifications 8 8 1,897$ -$ 1,897$
EOPCC 2 2 325$ -$ 325$
QA/QC 4 4 905$ -$ 905$
Submittal -$ -$ -$
12 54 6 92 6 2 1 50 10 60 12 305
2,883$ 11,438$ 875$ 10,681$ 1,620$ 263$ 117$ 11,859$ 1,624$ 8,725$ 2,716$ 305 52,800$ 14,949$ 14,949$ 67,749$
TOTAL
Labor Summary Sub
Total
HWA
(Geotech)
Dollars
Subs
TOTALS
Total Hours
(4) Additional Plan Sheets - (1) Details, (3) Controls
Hours
TOTAL FEE ESTIMATE
(4) Additional Plan Sheets - (1) Details, (3) Controls
Civil - (sheets; site plan, section, details, FM)
EOPCC
Civil - (sheets; site plan, section, details, FM)