HomeMy WebLinkAbout1 - Original Submission_ 315026 Supplement no. 03
Supplemental Agreement Number
Organization and Address
Phone:
Original Agreement Number
Project Number Execution Date Completion Date
Project Title New Maximum Amount Payable
Description of Work
The Local Agency of
desires to supplement the agreement entered in to with
and executed on and identified as Agreement No.
All provisions in the basic agreement remain in effect except as expressly modified by this supplement.
The changes to the agreement are described as follows:
I
Section 1, SCOPE OF WORK, is hereby changed to read:
II
Section IV, TIME FOR BEGINNING AND COMPLETION, is amended to change the number of calendar days
for completion of the work to read:
III
Section V, PAYMENT, shall be amended as follows:
as set forth in the attached Exhibit A, and by this reference made a part of this supplement.
If you concur with this supplement and agree to the changes as stated above, please sign in the Appropriate
spaces below and return to this office for final action.
By: By:
Consultant Signature Approving Authority Signature
Date
DOT Form 140-063 Revised 09/2005
City of Bremerton
Skillings, Inc.
11/26/2019 315026
See Exhibit A attached.
contract extended thru December 31, 2024
See Exhibit B-2, attached.
03
LA 9630
Skillings, Inc.
5016 Lacey Boulevard SE
Lacey, WA 98503
360-491-3399
STPUL-9918 (017)November 26, 2019 December 31, 2024
Washington & 11th Improvements Project $ 756,241.27
This project will design and construct a roundabout in the intersection of Washington Avenue and the
Manette Bridge, and will include full street reconstruction (including sidewalks and bike lanes) on 11th Street
and Washington Avenue between the new roundabout and Pacific Avenue.
Thomas Skillings, P.E., Skillings Inc.Greg Wheeler, Mayor
DocuSign Envelope ID: A6A79D2F-08F8-4BAD-8C16-8E0222062D51
4/1/2022
Skillings, Inc. Page 1 of 10 Project No. 19149‐Supp No 3
City of Bremerton
Design Modifications, Bid, & Construction Support
EXHIBIT A
SCOPE OF WORK
Prepared for:
CITY OF BREMERTON
WASHINGTON & 11TH IMPROVEMENTS
SUPPLEMENT NO. 3 DESIGN MODIFICATIONS, BID & CONSTRUCTION SUPPORT
CITY PROJECT NO. 315026
FEDERAL AID NO. STPUL‐9918(017)
March 17, 2022
Introduction:
The following Scope of Work delineates supplemental tasks to be performed in addition to the original
agreement between Skillings, Inc. (Consultant) and the City of Bremerton (City).
Skillings, Inc. has been selected by the City of Bremerton to provide design engineering, environmental, and
right‐of‐way acquisition services for the reconstruction of Washington / 11th from the Manette Bridge to
Pacific. In addition to that project, the City previously added work to improve the existing sidewalk adjacent
to the lower portion of Washington Avenue (Lower Sidewalk). Northbound Washington Avenue splits into
an upper and lower section after the Washington Avenue/Manette Bridge intersection. The City also
intends to upgrade the water mains within the vicinity of the two intersections of 11th Street at Pleasant
Avenue and Highland Avenue.
Based on comments from residents adjacent to the project, the City intends to revise the previously
completed alignment of the Washington / 11th Street, redesign of the roadway, and replacement of the
existing rockery wall on the west side of Washington Avenue with a new CIP or soldier pile wall. Work along
the lower portion of Washington Avenue will consist of redesign to reflect the parallel parking option
presented to the community which includes improvements to curbs, road surface, a 4‐ft sidewalk with ADA
turnouts, and storm drainage.
Project Assumptions:
This scope of work is based on the following general assumptions:
The project will be developed as a single package. Bid alternates, bid additives, or subsequent
repackaging of the project into separate phases is not included.
Landscaping and irrigation design are not included in this scope of work or fee.
It is assumed that there are no contaminated soils within the project limits.
WORK ELEMENTS
Task 301 – Geotechnical Investigations for Wall
Consultant will contract with HWA GeoSciences, Inc. (HWA), Subconsultant, to provide supplemental
geotechnical investigation and design parameters for the new wall replacing the existing rockery wall along
the west side of Washington Avenue.
PROJECT BACKGROUND
At this time HWA has submitted a draft report for which most of our scope was completed, except for the
design of the wall that was proposed along the eastern side of the roadway alignment. At this time, we
understand that the wall along the east side will be instead consist of widening the sidewalk and
DocuSign Envelope ID: A6A79D2F-08F8-4BAD-8C16-8E0222062D51
Skillings, Inc. Page 2 of 10 Project No. 19149‐Supp No 3
City of Bremerton
Design Modifications, Bid, & Construction Support
reconstructing retaining walls along the west side of the sidewalk. Walls are anticipated to have exposed
wall heights between 4 to 7.5 feet. Geotechnical services associated with evaluating suitable wall types for
wall construction are desired to complete the design for the sidewalk. To provide these support services,
we propose the following tasks:
HWA Internal QA/QC for Geotechnical and Pavement Tasks: HWA will have all design calculations
and recommendations reviewed by a senior principal prior to distribution to the design team.
Task Coordination and Management: HWA will provide geotechnical task management to all
geotechnical related aspects of the project and will correspond with Skillings and the design team
in the form of emails, fax, and telephone calls, as necessary. HWA will also prepare monthly
invoices, and progress reports for the duration of the design phase of the project.
Site Reconnaissance: HWA will make one site visit to observe the existing site conditions along the
sidewalk alignment where the proposed walls will be installed.
Review Proposed Wall Cross‐Sections and Evaluate Constructability of Wall Alternatives: Based
on data supplied to HWA for proposed wall locations, heights, and roadway proximity, HWA will
evaluate the suitability of using either cantilever walls or soldier pile walls. Recommendations for
each suitable option will be provided to be incorporated into design of the proposed
improvements.
Wall Alternative 1, Cantilever Wall Design Parameters: For walls determined to be constructed as
cantilever walls, HWA will develop design active and seismic earth pressures, nominal and service‐
level bearing capacities, sliding resistances, and perform global stability checks.
Wall Alternative 2, Soldier Pile Design Parameters: For walls determined to be constructed as
soldier pile walls, HWA will develop design earth pressure diagrams and minimum
recommendations for pile spacing and widths for passive pressures.
Provide Recommendations for Temporary Excavations and Shoring: HWA will provide input for
temporary excavations and shoring, as they relate to wall construction.
Provide Earthwork Considerations for Construction: HWA will provide input for earthwork
considerations as it relates to subgrade preparation and type and placement of backfill behind
walls.
Provide Miscellaneous Consultation for Implementing Geotechnical Recommendations: HWA will
provide additional support as needed for the implementation of geotechnical recommendations
during design and construction.
Update Existing Geotechnical Report for Wall Alternatives: HWA will update the existing draft
geotechnical report with proposed recommendations for the wall alternative described. Once we
receive comments, we will incorporate them into a Final Geotechnical Report for the Project.
Review PS&E Documents: HWA will review PS&E documents for design consistency with our
geotechnical recommendations.
DELIVERABLES
One deliverable is anticipated for the new scope of work:
Revised Draft and Final versions of the Geotechnical Report
DocuSign Envelope ID: A6A79D2F-08F8-4BAD-8C16-8E0222062D51
Skillings, Inc. Page 3 of 10 Project No. 19149‐Supp No 3
City of Bremerton
Design Modifications, Bid, & Construction Support
ASSUMPTIONS
No explorations will be performed in the project area for retaining wall evaluation as the data from
the previous borings performed for the project will provide design information.
HWA will respond to one (1) round of comments on the revisions to the draft geotechnical report.
The scope of work is related solely to geotechnical engineering evaluation of site soil and ground
water, as they relate to geotechnical design for the project improvements. Neither identification
nor evaluation of contaminants that may be present in the soil or ground water is included in this
scope of work.
CONSULTANT will complete the following tasks in support of the geotechnical investigation task:
Tasks:
1. Consultant will review the Draft Geotechnical Report and provide one set of comments to HWA.
Deliverables (Consultant):
Comments on Draft Geotechnical Report.
Task 302 – Structural Wall Design
Consultant will contract with Sargent Engineers, Inc. (Sargent), Subconsultant, to provide typical
wall sections, pile spacing, and other structural details needed for the wall along the west side of
Washington Avenue.
Sargent will provide the structural design of the new retaining wall as a subconsultant to Skillings.
The retaining wall is anticipated to be a soldier‐pile wall with concrete fascia, with height ranging
from 4‐8ft.
Sargent will perform the structural design of the soldier pile wall per the requirements of the
project geotechnical report, AASHTO LRFD Specification for Bridge Design, the WSDOT Bridge
Design Manual, and the WSDOT Geotechnical Design Manual.
Sargent will prepare the retaining wall elevation sheet and structural detail sheets needed to
construct the wall, including up to two typical wall sections. The typical wall sections will show the
maximum retained soil height, pile size and spacing, and concrete fascia thickness and reinforcing.
Skillings will prepare the wall plan sheets and will provide the surface profile for finish grade at the
back of wall, which Sargent will use to prepare the wall elevation sheets.
Sargent will prepare the quantities, cost estimate, and technical special provisions for the structural
items in WSDOT format. Sargent will also respond to Skillings, City of Bremerton, and WSDOT
review comments.
CONSULTANT will complete the following tasks in support of the structural wall design task:
Tasks:
1. Consultant will provide coordination with Sargent.
Task 303 – Redesign and 100% PS&E
This task consists of revising the previously completed alignment of the Washington / 11th Street, redesign
of the roadway, storm drainage, illumination, channelization, signage, and replacement of the existing
DocuSign Envelope ID: A6A79D2F-08F8-4BAD-8C16-8E0222062D51
Skillings, Inc. Page 4 of 10 Project No. 19149‐Supp No 3
City of Bremerton
Design Modifications, Bid, & Construction Support
rockery wall on the west side of Washington Avenue with a new CIP or soldier pile wall. Work along the
lower portion of Washington Avenue will consist of redesign to reflect the parallel parking option presented
to the community which includes improvements to curbs, road surface, a 4‐ft sidewalk with ADA turnouts,
and storm drainage.
Assumptions:
Engineer’s Estimate of Probable Costs to Construct will be prepared using WSDOT Unit Bid Price
format.
Special provisions will be prepared utilizing WSDOT specifications format.
City will provide their “boiler plate” format for contract bid package.
Draft Contract Bid Package to contain placeholder items. Depending on when the project is
advertised for construction, the documents may require updating to include the latest information
just prior to advertising.
Tasks:
1. Revise alignment of Washington / 11th Street. The following plan sheets will require revisions:
a. Cover Sheet
b. Horizontal Control Plan Sheet
c. Demo & TESC Plans
d. Typical Roadway Sections
e. Roadway Plan & Profile Sheets
f. Storm Plan & Profile Sheets
g. Roundabout Layout Sheets
h. Curb Ramp Sheets
i. Illumination Plan and Detail Sheets
j. Signing Plan Sheets
k. Channelization Sheets
l. All Lower Sidewalk Sheets
m. Traffic Control Plan Sheets
2. Prepare wall plan, profile, and detail sheets.
3. Update Quantities Notebook.
4. Prepare 100% Engineer’s Estimate of Probable Costs to Construct.
5. Prepare Draft Contract Bid Package:
a. Front end documents, draft invitation to bid, proposal sheets.
b. Required Federal‐aid documents.
c. GSPs and Special Provisions.
d. State and Federal prevailing wage documents.
6. Complete Basis of Design Notebook.
7. Provide internal QA and QC and project coordination.
Deliverables:
Final Basis of Design Memo
Draft Contract Bid Package
One (1) electronic set of 100% PS&E to City and WSDOT for review.
Final Quantity calculation notebook
DocuSign Envelope ID: A6A79D2F-08F8-4BAD-8C16-8E0222062D51
Skillings, Inc. Page 5 of 10 Project No. 19149‐Supp No 3
City of Bremerton
Design Modifications, Bid, & Construction Support
Task 304 – Complete Bid Set
This task consists of addressing City and WSDOT’s 100% comments and preparing a Complete Bid Set.
Assumptions:
WSDOT will provide comments on the 100% PS&E.
City will provide one set of comments on the 100% PS&E.
ROW lines will be delineated on the construction drawings.
Consultant will supply the bid proposal form for the bid package.
Consultant will provide only one update to any portion of the Complete Bid Set.
An Engineer’s Estimate for the Probable Cost to Construct will be prepared that lists all of the
project bid items, showing contract item number, unit of measurement, estimated unit price,
estimated quantity, and total estimated cost for each.
o The total project cost will be shown on this estimate.
o This estimate will be used as the basis of review for the lowest responsive responsible bidder.
Tasks:
1. Phone conference with City to discuss 100% PS&E comments from City and WSDOT.
2. Incorporate 100% PS&E comments.
3. Prepare Complete Bid Set.
4. Complete Contract Bid Package:
a. WSDOT Amendments and GSP “run list” and fill‐ins.
b. Special Provisions.
c. Required Federal‐aid documents.
d. State and Federal prevailing wage documents.
5. Update Engineer’s Estimate of Probable Costs to Construct.
6. Submit Complete Bid Set package to City and WSDOT for their review and approval as necessary.
7. Review City comments on Complete Bid Set.
8. Make minor adjustments to Complete Bid Set as reviewed by the City up to one time.
Deliverables:
Final Basis of Design Notebook
Final Contract Bid Package
Final and signed 100% PS&E
1. One (1) electronic set of 100% PS&E to City.
2. All documents will be submitted as pdf’s, Cad Files, Word Files (.docx), and Estimate in Excel.
Final Quantity calculation notebook
Task 305 – Bid Support Services
Consultant will assist the City through the bidding and award process.
Assumptions:
The City will:
Prepare Advertisement for Bids.
Advertise the project.
Provide Bid Documents and addenda to Builders Exchange for distribution
DocuSign Envelope ID: A6A79D2F-08F8-4BAD-8C16-8E0222062D51
Skillings, Inc. Page 6 of 10 Project No. 19149‐Supp No 3
City of Bremerton
Design Modifications, Bid, & Construction Support
Host the bid opening.
Prepare bid tabulation.
Prepare notice of award.
The Consultant will:
Provide support to City in responding to bidder’s questions.
Prepare up to four (4) addenda.
Attend Bid Opening
Review Bid Tabulation.
Tasks:
1. Consultant will provide assistance through bidding and award. This work is expected to include:
a. Responding to bidder’s questions.
b. Prepare up to four (4) addenda.
c. Attend Bid Opening.
d. Review Bid Tabulation.
Task 306 – Construction Support Services
Consultant will provide construction support consisting of attending the pre‐construction meeting,
reviewing Contractor’s submittals, responding to RFIs, preparing change orders, attending construction
meetings when attendance is requested by City, site visits, reviewing the punch list items.
Assumptions:
City will provide overall construction administration, inspection, and management.
Consultant will attend one pre‐construction meeting (estimated at 2 hours per attendee).
Consultant will review Contractor’s submittals and provide recommendations/comments
(estimated level of effort to not exceed 16 hours).
Consultant will review and respond to Contractor’s RFIs (estimated level of effort to not exceed 24
hours).
Consultant will assist with the drafting, review, and responses to Change Orders (estimated level of
effort to not exceed 32 hours).
Consultant will attend construction meetings at the request of the City (estimated level of effort to
not exceed 40 hours).
Consultant will conduct field visits at the request of the City (estimated level of effort to not exceed
45 hours).
Consultant will participate in the final project walkthrough, review the punch list, and review work
to ensure punch list items are completed (estimated level of effort to not exceed 16 hours).
Compaction testing is not included in the scope of work.
Construction inspection services are not included in this scope of work.
Construction surveying and staking are not included in this scope of work.
Task Description:
1. Attend pre‐construction meeting.
2. Review Contractor’s submittals.
3. Review and respond to Contractor’s RFIs.
4. Prepare Change Orders.
5. Attend construction meetings at the request of the Client or City.
DocuSign Envelope ID: A6A79D2F-08F8-4BAD-8C16-8E0222062D51
Skillings, Inc. Page 7 of 10 Project No. 19149‐Supp No 3
City of Bremerton
Design Modifications, Bid, & Construction Support
6. Conduct field visits at the request of the Client or City.
7. Participate in final project walkthrough, develop punch list, review work for punch list completion.
Deliverables:
Pre‐construction meeting notes.
Contractor submittal reviews responses.
Contractor RFI reviews and responses.
Change Orders.
Construction meeting notes.
Field visit notes.
Punch list.
Verified punch list completion.
END SCOPE OF WORK
DocuSign Envelope ID: A6A79D2F-08F8-4BAD-8C16-8E0222062D51
Skillings, Inc. Page 8 of 10 Project No. 19149‐Supp No 3
City of Bremerton
Design Modifications, Bid, & Construction Support
EXHIBIT B‐1
CONSULTANT COMPUTATION – MAN‐HOURS
PROJECT NO. 19149 PROJECT MANAGER PROJECT ENGINEER ENGINEER TECHNICIAN PROJECT ADMINISTRATOR CITY OF BREMERTON
WASHINGTON & 11TH IMPROVEMENTS
CITY PROJECT NO. 315026
FEDERAL AID NO. STPUL‐9918(017)
SUPPLEMENT NO. 3
DESIGN MODIFICATIONS, BID, AND CONSTRUCTION SUPPORT
TASK # TASK DESCRIPTION
301 GEOTECHNICAL INVESTIGATIONS FOR WALL
1 Consultant will review the wall design letter and provide one
set of comments to HWA. 4
302 STRUCTURAL WALL DESIGN
1 Consultant will provide coordination with Sargent Engineers. 4
303 REDESIGN AND 100% PS&E
1 Revise alignment of Washington / 11th Street. The following
plans sheets will require revisions.
a Cover 2 2
b Horizontal Control Plan Sheet. 2 2
c Demo & TESC Plans. 4 12 12
d Typical Roadway Sections. 2 8 8
e Roadway Plan & Profile Sheets. 8 12 12
f Storm Plan & Profile Sheets. 8 12 12
g Roundabout Layout Sheets. 4 8 8
h Curb Ramp Sheets. 4 8 8
i Illumination Plan & Detail Sheets. 4 8 8
j Signing Plan Sheets. 4 8 8
k Channelization Sheets. 4 8 8
l All Lower Sidewalk Sheets. 24 40 40
m Traffic Control Plan Sheets. 4 8 8
2 Prepare wall plan, profile, and detail sheets. 4 24 24
3 Update Quantities Notebook. 4 8
4 Prepare 100% Engineer's Estimate of Probable Costs to
Construct. 4
5 Prepare Draft Contract Bid Package;
a Front end documents, draft invitation to bid, proposal
sheets. 2 4
b Required Federal‐aid documents. 2
c GSPs and Special Provisions. 4 16
d State and Federal prevailing wage documents. 2
6 Complete Basis of Design Notebook. 2 2
8 Provide internal QA and QC and project coordination. 12 4
304 COMPLETE BID SET
1 Phone conference with City to discuss 100% PS&E comments
from City and WSDOT. 2 2
2 Incorporate 100% PS&E comments. 4 8 8
3 Prepare Complete Bid Set. 4 16 16
DocuSign Envelope ID: A6A79D2F-08F8-4BAD-8C16-8E0222062D51
Skillings, Inc. Page 9 of 10 Project No. 19149‐Supp No 3
City of Bremerton
Design Modifications, Bid, & Construction Support
PROJECT NO. 19149 PROJECT MANAGER PROJECT ENGINEER ENGINEER TECHNICIAN PROJECT ADMINISTRATOR CITY OF BREMERTON
WASHINGTON & 11TH IMPROVEMENTS
CITY PROJECT NO. 315026
FEDERAL AID NO. STPUL‐9918(017)
SUPPLEMENT NO. 3
DESIGN MODIFICATIONS, BID, AND CONSTRUCTION SUPPORT
TASK # TASK DESCRIPTION
4 Complete Control Bid Package:
a WSDOT Amendments and GSP "run list" and fill‐ins. 2
b Special Provisions. 2
c Required Federal‐aid documents. 2
d State and Federal prevailing wage documents. 2
5 Update Engineer's Estimate of Probable Costs to Construct. 2
6 Submit Complete Bid Set package to City and WSDOT for
their review and approval as necessary. 1 2 2
7 Review City comments on Complete Bid Set. 1 1 4 4
8 Make minor adjustments to Complete Bid Set as reviewed by
the City up to one time. 1 4 4
305 BID SUPPORT SERVICES
1 Consultant will provide assistance through bidding and
award. this work is expected to include:
a Responding to bidder's questions. 4 8
b Prepare up to four (4) addenda. 2 8 16
c Attend Bid Opening. 2
d Review Bid Tabulation. 2
HOURS PER DISCIPLINE 40 116 250 194 4
DocuSign Envelope ID: A6A79D2F-08F8-4BAD-8C16-8E0222062D51
Skillings, Inc. Page 10 of 10 Project No. 19149‐Supp No 3
City of Bremerton
Design Modifications, Bid, & Construction Support
EXHIBIT B‐2
CONSULTANT COMPUTATION – SUMMARY
NEGOTIATED HOURLY RATE (NHR):
Classification
Man
Hours x Rate = Cost
PROJECT MANAGER 40 x $198.65 = $7,945.82
PROJECT ENGINEER 116 x $130.76 = $15,168.16
ENGINEER 250 x $98.07 = $24,517.50
TECHNICIAN 194 x $96.72 = $18,763.64
PROJECT ADMINISTRATOR 4 x $122.32 = $489.29
Total Hours = 604 Total NHR = $66,884.41
REIMBURSABLES:
Mileage 0 x $0.585 = $0.00
Miscellaneous Expenses $0.00 x 0% = $0.00
SUB
TOTAL Reimbursables = $0.00
SUBCONSULTANT COST (See Exhibit E):
HWA GeoSciences, Inc. $9,175.00 x 0% = $9,175.00
Sargent Engineers, Inc. $14,758.00 x 0% = $14,758.00
SUB
TOTAL Subconsultants = $23,933.00
MANAGEMENT RESERVE FUND
SUB TOTAL $90,817.41 x 5% = $4,540.87
GRAND TOTAL
GRAND TOTAL = $95,358.28
PREPARED BY: Ian Lee, PE DATE: 3/17/2022
REVIEWED BY: Patrick E. Skillings, PMP DATE: 3/17/2022
DocuSign Envelope ID: A6A79D2F-08F8-4BAD-8C16-8E0222062D51
21312 30th Dr. SE, STE. 110, Bothell, WA 98021 | 425.774.0106 | hwageo.com
March 7, 2022
Skillings, Inc.
5016 Lacey Boulevard SE
Lacey, WA 98503
Attention: Ian Lee, P.E.
Subject: SUPPLEMENTAL SCOPE OF WORK
GEOTECHNICAL ENGINEERING SERVICES
Bremerton Roundabout at Washington and Manette with
Improvements on 11th Street
Bremerton, Washington
Dear Mr. Lee,
Thank you for the opportunity to present this proposal for HWA GeoSciences Inc. (HWA)
consulting services. As requested, HWA has prepared the following supplemental scope of work
and associated cost estimate for geotechnical engineering services in support of the Bremerton
Roundabout and 11th Street Improvements project in Bremerton, Washington. The work scope
and cost estimate are based on our present understanding of the work to be accomplished,
established in our prior correspondence regarding the project.
PROJECT BACKGROUND
At this time HWA has submitted a draft report for which most of our scope was completed,
except for the design of the wall that was proposed along the eastern side of the roadway
alignment. At this time, we understand that the wall along the east side will be instead consist of
widening the sidewalk and reconstructing retaining walls along the west side of the sidewalk.
Walls are anticipated to have exposed wall heights between 4 to 7.5 feet. Geotechnical services
associated with evaluating suitable walls types for wall construction are desired to complete the
design for the sidewalk. To provide these support services, we propose the following tasks:
• HWA Internal QA/QC for Geotechnical and Pavement Tasks: HWA will have all
design calculations and recommendations reviewed by a senior principal prior to
distribution to the design team.
• Task Coordination and Management: HWA will provide geotechnical task
management to all geotechnical related aspects of the project and will correspond with
Skillings and the design team in the form of emails, fax, and telephone calls, as
DocuSign Envelope ID: A6A79D2F-08F8-4BAD-8C16-8E0222062D51
March 7, 2022
HWA Proposal No. 2019-149-21
2019-149-21 Bremerton Roundabot Supp Scope Western Wall 2 HWA GEOSCIENCES INC.
necessary. HWA will also prepare monthly invoices, and progress reports for the duration
of the design phase of the project.
• Site Reconnaissance: HWA will make one site visit to observe the existing site
conditions along the sidewalk alignment where the proposed walls will be installed.
• Review Proposed Wall Cross-Sections and Evaluate Constructability of Wall
Alternatives: Based on data supplied to HWA for proposed wall locations, heights, and
roadway proximity, HWA will evaluate the suitability of using either cantilever walls or
soldier pile walls. Recommendations for each suitable option will be provided to be
incorporated into design of the proposed improvements.
• Wall Alternative 1, Cantilever Wall Design Parameters: For walls determined to be
constructed as cantilever walls, HWA will develop design active and seismic earth
pressures, nominal and service-level bearing capacities, sliding resistances, and perform
global stability checks.
• Wall Alternative 2, Soldier Pile Design Parameters: For walls determined to be
constructed as soldier pile walls, HWA will develop design earth pressure diagrams and
minimum recommendations for pile spacing and widths for passive pressures.
• Provide Recommendations for Temporary Excavations and Shoring: HWA will
provide input for temporary excavations and shoring, as they relate to wall construction.
• Provide Earthwork Considerations for Construction: HWA will provide input for
earthwork considerations as it relates to subgrade preparation and type and placement of
backfill behind walls.
• Provide Miscellaneous Consultation for Implementing Geotechnical
Recommendations: HWA will provide additional support as needed for the
implementation of geotechnical recommendations during design and construction.
• Update Existing Geotechnical Report for Wall Alternatives: HWA will update the
existing draft geotechnical report with proposed recommendations for the wall alternative
described. Once we receive comments, we will incorporate them into a Final
Geotechnical Report for the Project.
• Review PS&E Documents: HWA will review PS&E documents for design consistency
with our geotechnical recommendations.
DELIVERABLES
One deliverable is anticipated for the new scope of work:
• Revised Draft and Final versions of the Geotechnical Report
DocuSign Envelope ID: A6A79D2F-08F8-4BAD-8C16-8E0222062D51
March 7, 2022
HWA Proposal No. 2019-149-21
2019-149-21 Bremerton Roundabot Supp Scope Western Wall 3 HWA GEOSCIENCES INC.
ASSUMPTIONS
• No explorations will be performed in the project area for retaining wall evaluation as the
data from the previous borings performed for the project will provide design information.
• HWA will respond to one (1) round of comments on the revisions to the draft
geotechnical report.
• The scope of work is related solely to geotechnical engineering evaluation of site soil and
ground water, as they relate to geotechnical design for the project improvements. Neither
identification nor evaluation of contaminants that may be present in the soil or ground
water is included in this scope of work.
PROJECT COST ESTIMATE
We estimate that the scope of the new services proposed herein will require a budget of $22,705
to accomplish, as detailed on the attached project cost estimate spreadsheet. HWA currently has
a remaining budget of $13,530. Subtracting the remaining budget from the budget of new and
remaining work, we get a total supplement request of $9,175. We will not exceed the above cost
estimate without your prior authorization. However, if during the evaluation of the available
data or during our field reconnaissance unanticipated subsurface conditions are revealed which
would require a level of effort beyond the scope of our study, we will contact you immediately to
discuss any necessary modifications to our scope of services and/or budget estimate.
The budget presented in this proposal reflects an estimate based on our current understanding of
the project requirements for a scope of work developed from information provided. HWA
reserves the right to transfer hours and budget dollars between tasks to satisfy project
requirements. HWA may also transfer funds allocated for direct costs to professional/technical
hours or vice versa, to satisfy project requirements.
DocuSign Envelope ID: A6A79D2F-08F8-4BAD-8C16-8E0222062D51
March 7, 2022
HWA Proposal No. 2019-149-21
2019-149-21 Bremerton Roundabot Supp Scope Western Wall 4 HWA GEOSCIENCES INC.
Thank you again for the opportunity to provide this proposal for geotechnical and pavement
design services. Should you have any questions regarding this proposal, or require additional
services, please contact us at your convenience. If you agree with the scope of services, budget,
and general conditions described herein, please indicate your concurrence by returning one
signed copy of this letter.
Sincerely,
HWA GeoSciences, Inc.
JoLyn Gillie, P.E.
Geotechnical Engineer, Principal
Enclosures: Project Cost Estimate (1 sheet)
DocuSign Envelope ID: A6A79D2F-08F8-4BAD-8C16-8E0222062D51
Project Cost Estimate - Supplemental Work for Wall Design HWA Ref: 2019-149-21
Bremerton Roundabout at Washington and Manette with Improvements on 11th Street Date: 25-Feb-22
Geotechnical Engineering Services
Bremerton, Washington Prepared By: JLG
PROPOSED WORK SCOPE:
ESTIMATED HWA LABOR:
Principal IX Geotechnical
Engineer VIII
Geotechnical
Engineer I Geologist III Controller/Admin CAD TOTAL
DESCRIPTION $315.00 $265.00 $120.00 $130.00 $133.00 $100.00 HOURS AMOUNT
Geotechnical and Pavement Evaluation and Reporting 2 10 0 0 6 0 18 $4,078
HWA Internal QA/QC for Geotechnical and Pavement Tasks 2 4 6 $1,690
Task Coordination and Management 6 6 12 $2,388
Geotech Support for Wall Design 2 38 58 0 2 6 106 $18,526
Site Reconnaissance 6 6 $1,590
Review Proposed Wall Cross-Sections and Evaluate Constructability of Wall Alternatives 2 4 6 $1,010
Wall Alternative 1: Cantilever Wall Design Parameters
Alt 1: Active and Seismic Earth Pressures 2 6 8 $1,250
Alt 1: Develop Bearing Capacities (Nominal and Service-Level) and Sliding Resistance 2 4 6 $1,010
Alt 1: Global Stability Checks 2 8 10 $1,490
Wall Alternative 2: Soldier Pile Design Parameters
Alt 2: Develop Earth Pressure Diagrams 2 8 2 12 $1,690
Alt 2: Develop Minimum Recommended Pile Spacings and Width of Passive Pressure 2 2 $530
Provide Recommendations for Temporary Excavation and Shoring 2 4 6 12 $2,410
Miscellaneous Consultation for Implementing Geotechnical Recommendations 6 6 $1,590
Provide Earthwork Considerations for Construction 2 4 6 $1,010
Review of Plans and Specifications regarding geotechnical aspects of the design.2 6 8 $1,250
Update Existing Geotechnical Report for Wall Alternatives (Revised Draft and Final)6 12 2 4 24 $3,696
TOTAL LABOR:4 48 58 0 8 6 124 $22,604
DIRECT EXPENSES
Mileage @ 0.56/mile; 1 visit @180 miles $101
TOTAL DIRECT EXPENSES:$101
ESTIMATED TOTALS FOR REMAINING AND NEW WORK:
$22,604
$101
ESTIMATED PROJECT TOTAL:$22,705
ESTIMATED SUPPLEMENT REQUEST:
Total Remaining + New Work $22,705
Remaining Approved Budget ($13,530)
Assumed Conditions:ESTIMATED TOTAL SUPPLEMENT:$9,175 1. All costs are estimated, and may be increased or decreased within the limits of the total budget at the discretion of HWA's project manager.
Provide geotechnical design parameters for walls proposed along west side of Washington and 11th Street. Design to include consideration of two wall alternatives including a CIP wall option and a Soldier Pile option. Includes consideration of wall
types based on excavation needed to install the proposed new wall. Includes update of the geotechnical report, review of the plans and Specs and miscellaneous consulting associated with implementing the geotechnical design recommendations into the
project documents.
2. The scope of work is related solely to geotechnical engineering evaluation of site soil and ground water, as they relate to geotechnical design for the project improvements. Neither identification nor evaluation of contaminants that may be present in the
soil or ground water is included in this scope of work.
Direct Expenses
TOTAL
Total Labor Cost
2022 PERSONNEL & HOURLY BILLING RATES
Budget 1 of 1 HWA GeoSciences Inc.
DocuSign Envelope ID: A6A79D2F-08F8-4BAD-8C16-8E0222062D51
JSS/encl.
\\192.168.0.204\Files\22Files\Proposals\Skillings - Washington Ave Wall\Prop-Washington Ave Wall.doc
Sargent Engineers, Inc.
320 Ronlee Lane NW
Olympia, Washington 98502
Tel 360 867-9284
Fax 360 867-9318
www.sargentengineers.com
March 7, 2022
Mr. Ian Lee, PE
Skillings, Inc.
Via Email to: ilee@skillings.com
RE: Washington Avenue Retaining Wall - Structural Engineering Services Proposal
Project No.: A22100.00
Dear Ian:
On behalf of Sargent Engineers, I am pleased to present to you our proposal for providing structural engineering services for
the retaining wall that will be part of the Washington Ave & 11th Street Intersection Improvements that Skillings is designing for
the City of Bremerton. As part of the improvements, the City would like to replace a rockery wall that currently runs along the
east edge of the corridor. Sargent will provide the structural design of the new retaining wall as a subconsultant to Skillings.
The retaining wall is anticipated to be a soldier-pile wall with concrete fascia, with height ranging from 4-8ft.
We will perform the structural design of the soldier pile wall per the requirements of the project geotechnical report, AASHTO
LRFD Specification for Bridge Design, the WSDOT Bridge Design Manual, and the WSDOT Geotechnical Design Manual.
We will prepare the retaining wall elevation sheet and structural detail sheets needed to construct the wall, including up to two
typical wall sections. The typical wall sections will show the maximum retained soil height, pile size and spacing, and concrete
fascia thickness and reinforcing. Skillings will prepare the wall plan sheets and will provide the surface profile for finish grade
at the back of wall, which Sargent will use to prepare the wall elevation sheets. We will prepare the quantities, cost estimate,
and technical special provisions for the structural items in WSDOT format. We will also respond to Skillings, City of
Bremerton, and WSDOT review comments.
To complete the scope of work described above, I propose a maximum fee of $14,758 to be billed at our approved hourly
rates.
If the scope and fee are acceptable, we can begin working on the design as soon as we receive the geotechnical information
and wall profile from Skillings. Assuming we receive this information by March 18, 2022, we anticipate being able to provide
the completed wall plans, specifications, and cost estimate for you to include in your April submittal to WSDOT. Thank you for
this opportunity to be of assistance to you, and we look forward to another successful project working with Skillings.
Respectfully,
Sargent Engineers, Inc.
Jessica Soward, PE, SE
Principal
DocuSign Envelope ID: A6A79D2F-08F8-4BAD-8C16-8E0222062D51
Mr. Lee
Page 2
March 7, 2022
Principal
Senior
Project
Engineer
Project
Engineer
Design
Engineer Task Cost
Rate: $184.40 $144.45 $132.15 $95.27
Plans, Specifications and Estimate
1. Project Coordination 4 $738
2. Wall Layout (based on Skillings profiles) 2 8 $1,346
3. Soldier Pile Wall Design 2 4 12 $2,532
4. Plan Preparation 4 8 32 $4,684
5. Cost Estimate & Technical GSP's 4 8 $1,635
6.Review Comments & Minor Revisions 2 4 16 8 $3,823
Subtotal 8 18 52 40 $14,758
Direct Costs
Mileage $0.00 $0
Subconsultants $0.00 $0
$0
Total for Plans, Specifications and Estimate $14,758
Structural Engineering Services Proposal
Washington Ave. Retaining Wall
DocuSign Envelope ID: A6A79D2F-08F8-4BAD-8C16-8E0222062D51
Overhead NTE* Fixed Fee NTE152.47% 30.00%PRINCIPAL-IN-CHARGE $84.25 $128.46 $25.28 $237.98SENIOR PROJECT MANAGER $79.80 $121.67 $23.94 $225.41PROJECT MANAGER $69.73 $106.32 $20.92 $196.97SENIOR PROJECT ENGINEER $69.73 $106.32 $20.92 $196.97PROJECT ENGINEER $54.60 $83.25 $16.38 $154.23ENGINEER$46.50 $70.90 $13.95 $131.35ENVIRONMENTAL MANAGER $47.25 $72.04 $14.18 $133.47SENIOR PROJECT SCIENTIST $40.00 $60.99 $12.00 $112.99PROJECT SCIENTIST $36.75 $56.03 $11.03 $103.81STAFF SCIENTIST$28.00 $42.69 $8.40 $79.09STRUCTURAL ENGINEER $44.00 $67.09 $13.20 $124.29TRAFFIC ENGINEER - II $39.00 $59.46 $11.70 $110.16TECHNICIAN$44.50 $67.85 $13.35 $125.70ENGINEERING INTERN $22.00 $33.54 $6.60 $62.14COMMUNICATIONS SPECIALIST $55.29 $84.30 $16.59 $156.18RIGHT OF WAY NEGOTIATOR $45.15 $68.84 $13.55 $127.54SURVEY MANAGER$63.53 $96.86 $19.06 $179.45SURVEY PARTY CHIEF $43.05 $65.64 $12.92 $121.60SURVEYOR$43.05 $65.64 $12.92 $121.60CHAINMAN$24.00 $36.59 $7.20 $67.79INSPECTOR$51.00 $77.76 $15.30 $144.06PROJECT ADMINISTRATOR $47.25 $72.04 $14.18 $133.47ADMINISTRATIVE ASSISTANT $47.25 $72.04 $14.18 $133.47Job ClassificationsDirect Labor Rate NTE*All Inclusive Hourly Billng Rate NTEActuals Not To Exceed Table (ANTE)SKILLINGS CONNOLLY, INC.5016 LACEY BLVD. SELACEY, WA 98503CITY OF BREMERTON MARCH 17, 2022DocuSign Envelope ID: A6A79D2F-08F8-4BAD-8C16-8E0222062D51
July 16, 2021
Skillings, Inc.
5016 Lacey Blvd SE
Lacey, WA 98503
Subject: Acceptance FYE 2020 ICR Risk Assessment Review
Dear Alysa Cushman:
Assessment review of your Indirect Cost Rate (ICR), we have accepted your proposed
FYE 2020 ICR of 152.47% of direct labor (rate includes 0.12% Facilities Capital Cost
of Money). This rate will be applicable for WSDOT Agreements and Local Agency
Contracts in Washington only. This rate may be subject to additional review if
considered necessary by WSDOT. Your ICR must be updated on an annual basis.
Costs billed to agreements/contracts will still be subject to audit of actual costs, based
on the terms and conditions of the respective agreement/contract.
This was not a cognizant review. Any other entity contracting with your firm is
responsible for determining the acceptability of the ICR.
If you have any questions, feel free to contact our office at (360) 705-7019 or via email
consultantrates@wsdot.wa.gov.
Regards;
ERIK K. JONSON
Contract Services Manager
EKJ:ah