HomeMy WebLinkAbout4508 1
Contract Number: 4508
Vendor: PARAMETRIX INC
Subject: Pre-Design - Beach Sewer Replacement
Department: Engineering
File Class: LEG 12-1
Begin Date: 09/16/2005
End Date: 12/31/2006
Review Date: 02/15/2010
Vault Date: Ol/O1/2010 1
Comments :
! \ '
PROFESSIONAL SERVICES AGREEMENT
Beach Sewer Replacement Pre-Design
The City of Bremerton ("City") and Parametrix, Inc., ("Consultant"), referred to
collectively as the "Parties," enter into the following Agreement for professional services:
I. Scope: The Consultant agrees to perform the services more specifically described in the
Scope of Work, dated July, 2005, including any attachments thereto, attached hereto as Exhibit
A, which is incorporated by reference herein. The Scope of Work may be modified only
pursuant to Section VII.G. of this Agreement. If the Scope of Work provides for unspecified
additional services such services shall only be performed upon the express written request of the
City. Consultant further represents that the services furnished under this Agreement will be
performed in accordance with generally accepted professional practices in effect at the time such
services are performed.
II. Term: The City and the Consultant agree that work will begin on the tasks described in
Exhibit A immediately upon execution of this Agreement. The parties agree that the work
described in Exhibit A is to be completed as provided for in the scope of work, on a task by task
basis as approved by the City; provided however, that additional time shall be granted by the
City for excusable delays or extra work as provided for in section IX (A) of this agreement.
III. Compensation: In consideration ofthe services provided pursuant to this Agreement, the
City shall pay Consultant in an amount not to exceed $75,000.00. Consultant's charges and bills
shall conform to the fee schedule attached hereto as Exhibit C and incorporated herein by this
reference.
The Consultant shall submit regular billing statements detailing work performed and
amount charged on each task or portion thereof. The descriptions shall conform to and fall
within the categories set out in the Scope of Work and/or Fee Schedule. Upon receipt of a
conforming billing statement, the City shall promptly process payment. PROVIDED,
HOWEVER, the City reserves the right to prioritize scoped work and accelerate and/or delay
work tasks under the time frame set forth in Section IT herein. The Consultant's labor rates and
billing fees shall be as delineated in Exhibit C.
Consultant shall not perform work beyond the Scope of Work, nor shall be compensated
for such work, unless the Scope of Work or amount of compensation is modified pursuant to this
Agreement. Consultant shall only be compensated for additional services if requested pursuant
to Section I and, if not otherwise provided, such compensation shall be in accordance with
Exhibit C.
If a billing statement does not conform to this Agreement, the City may withhold
payment until the statement is brought into compliance. Such withholding does not relieve
Consultant of its obligations under this Agreement.
BremertonlParametrix, Inc.
Beach Sewer Replacement Pre-Design
Page 1 of6
- -- ----
IV. Relationship of Parties: Consultant represents that it is skilled in the matters addressed
in the Scope of W otk and is performing independent functions and responsibilities within its
field of expertise. Consultant and its personnel are independent Consultants and not employees
of the City. Consultant and its personnel have no authority to bind the City or to control the
City's employees and other Consultants. None of the benefits provided by the City to its
employees, including, but not limited to, compensation, insurance, and unemployment insurance
are available from the City to the employees, agents, representatives, or sub-Consultants of the
Consultant. Consultant will be solely and entirely responsible for its acts and for the acts of
Consultant's agents, employees, representatives and sub-Consultants during the performance of
this Agreement. The City may, during the term of this Agreement, engage other independent
Consultants to perform the same or similar work.
As an independent Consultant, Consultant is responsible for its own management. The
City's administration and enforcement of this Agreement shall not be deemed an exercise of
managerial control over Consultant or its personnel.
As an independent Consultant, Consultant is responsible for payment of all taxes and
licensing fees necessary to perform its obligations under this Agreement. These taxes and fees
include but are not limited to State industrial insurance, Business & Occupation, State
professional licensing, and City business licensing. If any taxes or fees due the City have been
declared delinquent, the City may withhold the delinquent amount, plus any additional charges
arising from the delinquency, from any payments due Consultant.
V. Indemnification: Consultant shall defend, indemnify and hold the City, its officers,
officials, employees, agents and volunteers harmless from any and all claims, injuries, damages,
losses or suits, including all legal costs and attorney fees, arising out of or in connection with the
performance of this Agreement, except for that portion of the injuries and damages caused by the
City's sole negligence.
The City's review or acceptance of any of the work when completed shall not be grounds
to avoid any of these covenants of indemnification.
Should a court of competent jurisdiction determine that this Agreement is subject to
RCW 4.24.115, then, in the event ofliability for damages arising out of bodily injury to persons
or damages to property caused by or resulting from the concurrent negligence of the Consultant
and the City, its officers, officials, employees, agents and volunteers, the Consultant's liability
hereunder shall be only to the extent ofthe Consultant's negligence.
IT IS FURTHER SPECIFICALLY AND EXPRESSLY UNDERSTOOD THAT THE
INDEMNIFICATION PROVIDED HEREIN CONSTITUTES THE CONSULTANT'S
WAIVER OF IMMUNITY UNDER INDUSTRIAL INSURANCE, TITLE 51 RCW, SOLELY
FOR THE PURPOSES OF THIS INDEMNIFICATION. THE PARTIES FURTHER
ACKNOWLEDGE THAT THEY HAVE MUTUALLY NEGOTIATED THIS WAIVER.
The provisions of this section shall survive the expiration or termination of this Agreement.
BremertonlParametrix, Inc.
Beach Sewer Replacement Pre-Design
Page 2 of6
VI. Insurance: The Consultant shall procure and maintain for the duration of the Agreement,
insurance against claims for injuries to persons or damage to property which may arise from or in
connection with the performance of the work hereunder by the Consultant, its agents,
representatives, employees, sub-consultants or sub-Consultants.
Before beginning work on the project described in this Agreement, the Consultant shall
provide a Certificate of Insurance evidencing:
1. Automobile Liability insurance with limits no less than $1,000,000 combined single
limit per accident for bodily injury and property damage; and
2. Commercial General Liabilitv insurance written on an occurrence basis with limits no
less than $1,000,000 combined single limit per occurrence and general aggregate for
personal injury, bodily injury and property damage. Coverage shall include but not be
limited to: blanket contractual; products/completed operations/broad form property
damage; explosion, collapse and underground (XCV) if applicable; and employer's
liability; and
3. Excess Liabilitv insurance with limits not less than 1,000,000 limit per occurrence and
aggregate.
4. Professional Liabilitv insurance with limits no less than $1,000,000 limit per
occurrence/claim.
Any payment of deductible or self insured retention shall be the sole responsibility of the
Consultant.
All required policies shall be provided on an "occurrence" basis except professional
liability insurance (if required), which may be provided on a "claims-made" basis.
The City shall be named as an additional insured on the Commercial General Liability
insurance policy, as respects work performed by or on behalf of the Consultant and a copy of an
endorsement that is acceptable to the City, which names the City as an additional insured shall be
attached to the Certificate of Insurance. The City reserves the right to receive a certified copy of
all the required insurance policies and endorsements. The City further reserves the right to reject
any unacceptable policies and/or endorsements.
The Consultant's Commercial General Liability insurance shall contain a clause stating
that coverage shall apply separately to each insured against whom claim is made or suit is
brought, except with respects to the limits of the insurer's liability.
The Consultant's insurance shall be primary insurance as respects the City and the City
shall be given thirty (30) days prior written notice by certified mail, return receipt requested, of
any cancellation, suspension or material change in coverage.
The City also reserves its unqualified right to require at any time and for any reason,
proof of coverage in the form of a duplicate of the insurance policy with all endorsements as
evidence of coverage.
BremertonlParametrix, Inc.
Beach Sewer Replacement Pre-Design
Page 3 of6
VII. General Conditions:
A. Reports and Information: When requested by the City, Consultant shall furnish
periodic reports and documents on matters covered by this Agreement. The reports and
documents shall be furnished in the time and form requested. Consultant shall maintain
accounting records in accordance with Generally Accepted Accounting Principles (GAAP) to
substantiate all billed amounts.
B. Ownership and Use of Records and Documents: Original documents, drawings,
designs and reports, including those in electronic format, developed under this Agreement are the
property of the City. All written information submitted by the City to the Consultant in
connection with the services performed by the Consultant under this Agreement will be
safeguarded by the Consultant to at least the same extent as the Consultant safeguards like
information relating to its own business. If such information is publicly available or is already in
Consultant's possession or known to it, or is rightfully obtained by the Consultant from third
parties, Consultant shall bear no responsibility for its disclosure, inadvertent or otherwise.
All data, documents and files created by Consultant under this Agreement may be stored
at Consultant's office in Bremerton, Washington. Consultant shall make such data, documents,
and files available to the City upon its request at all reasonable times for the purpose of editing,
modifying and updating as necessary until such time as the City is capable of storing such
information in the City's offices. Duplicate copies of this information shall be provided to the
City upon its request, and at reasonable cost.
All documents, including all reports, drawings, specifications, computer softwareor other
items prepared or furnished by Consultant pursuant to this Agreement, are instruments of service
with respect to the project and are the property of the City. Any reuse by the City for other than
the specific purpose intended will be at City's sole risk.
c. Work Performed at Consultant's Risk: Consultant shall take all precautions necessary
and shall be responsible for the safety of its employees, agents, and sub-consultants in the
performance of the work hereunder and shall utilize all protection necessary for that purpose.
All work shall be done at Consultant's own risk, and Consultant shall be responsible for any loss
of or damage to materials, tools, or other articles used or held for use in connection with the
work.
D. Place of Work: The Consultant shall perform the work authorized under this
Agreement at its offices in Bremerton, Washington. Meetings with the City staff as described in
Exhibit A, Scope of Work, shall take place at the City's offices, or at locations mutually agreed
upon by the parties.
E. Entire Agreement: This Agreement and its Exhibits constitutes the entire agreement
between the Parties, and the Parties acknowledge that there are no other agreements, written or
oral, that have not been set forth in the text of this Agreement.
Bremerton/Parametrix, Inc.
Beach Sewer Replacement Pre-Design
Page 4 of6
F. Severability: Should any part of this Agreement be found void, the balance of the
Agreement shall remain in full force and effect.
G. Modification: This Agreement may only be modified by written instrument signed by
both Parties.
H. Written Notices: All communications regarding this Agreement shall be sent to the
parties at the addresses listed below by registered or 1 st class mail, or by personal service, and
shall be deemed sufficiently given if sent to the addressee at the address stated in this Agreement
or such other address as may be hereafter specified in writing.
City Address
Department of Public Works and Utilities
3027 Olympus Drive
Bremerton, W A 98310
Consultant Address
Parametrix, Inc.
5700 Kitsap Way, Suite 202
Bremerton, W A 98312
I. Waiver: Failure to enforce any provision of this Agreement shall not be deemed a
waiver of that provision. Waiver of any right or power arising out of this Agreement shall not be
deemed waiver of any other right or power.
J. Non- Waiver of Breach: The failure of the City to insist upon strict performance of any
of the covenants and agreements contained herein, or to exercise any option herein conferred in
one or more instances shall not be construed to be a waiver or relinquishment of said covenants,
agreements or options, and the same shall be and remain in full force and effect.
K. Compliance with Laws: Consultant shall comply with all applicable Federal, State,
and local laws in performing its obligations under this Agreement.
L. Choice of Law and Venue: This Agreement shall be interpreted according to the laws
of the State of Washington. Any judicial action to resolve disputes arising out of this Agreement
shall be brought in Kitsap County Superior Court.
M. Attorneys' Fees: In the event of litigation to enforce any of the terms or provisions
herein, each party shall pay all its own costs and attorney's fees.
N. Assignment: Any assignment of this agreement by the Contractor without the written
consent of the City shall be void.
VIII. Nondiscrimination: Consultant shall not discriminate in employment or services to the
public on the basis of race, color, national origin, sex, religion, age, marital status, or disability,
except for employment actions based on bona fide occupational qualification.
IX. Termination: This Agreement shall remain in force until completion and acceptance of
the services, terminated by written instrument upon mutual consent, or by the City of Bremerton
for convenience. This Agreement may be immediately terminated for cause by a Party if the
other Party substantially fails to perform through no fault of the terminating Party, and the non.
Bremerton/Parametrix, Inc.
Beach Sewer Replacement Pre-Design
Page 5 of6
performing Party does not commence correction of the failure of performance within thirty (30)
days of the terminating Party's sending notice to the non-performing Party. Any Notice by
Consultant shall include a report showing the status of all items listed in the Scope of Work
current through the termination date.
If the City receives reimbursement by any federal, state, or other source for work described in
Section I herein, and that funding is withdrawn, reduced or limited in any way, or the project is
cancelled or substantially reduced after the execution date of this Agreement and prior to the
completion of the work, the City may summarily terminate this Agreement.
A. Excusable Delays: The right of Consultant to proceed shall not be terminated nor shall
Consultant be charged with liquidated damages for any delays in the completion of the work due
to: I) any acts of the federal government in controlling, restricting, or requisitioning materials,
equipment, tools, or labor by reason of war, national defense, or other national emergency; 2)
any acts of the City, its consultants, or other public agencies causing such delay; and 3) causes
not reasonably foreseeable by the parties at the time of the execution of the Agreement that are
beyond the control and without the fault or negligence of the Consultant, including, but not
restricted to, acts of God, fires, floods, strikes, or weather of unusual severity. PROVIDED,
HOWEVER, that the Consultant must promptly notify the City within ten (10) calendar days in
writing of the cause of the delay. If, on the basis of the facts and the terms of this Agreement,
the delay is properly excusable, the City shall, in writing, extend the time for completing the
work for a period of time commensurate with the period of excusable delay.
B. Rights Upon Termination: In the event of termination, the City shall pay for all
services performed by the Consultant to the effective date oftermination, as described on a final
invoice submitted to the City. After termination, the City may take possession of all records and
data within the Consultant's possession pertaining to this project which may be used by the City
without restriction. Any such use not related to the project which Consultant was contracted to
perform shall be without liability or legal exposure to the Consultant.
CONSULTANT
By: Cary ozeman
its: Mayor
Date: 9. /1. .nS
~w.~~ _
BY:~ ~
its: ~ ~~
Date:~ (( 2M'
)
Att
Approved as 0 form:
R:\LEGAL\Contracts\FORMS\Professional Services Agreement Form (2003).doc
Bremerton/Parametrix, Inc.
Beach Sewer Replacement Pre-Design
Page 6 of6
SCOPE OF WORK
City of Bremerton
Beach Sewer Replacement Predesign
BACKGROUND
This Scope of Work identifies engineering services for the City of Bremerton (City) for the period of July
I, 2005 through December 31, 2006. This work is being performed in accordance with the scope of work
described in the request for qualifications dated November 30, 2004, as well as subsequent discussions
with City staff. This scope of work represents a best estimate of level of effort required to obtain funding,
and begin agency negotiations for the expansion of Evergreen Park at the Chevron Property and to
develop preliminary designs for an approximate 3,200-foot sewer line replacement along the Port
Washington Narrows between Evergreen Park and the Louis Mentor Boardwalk. This scope of work will
be executed on a time and materials basis with authorization on a task by task basis, further limited to an
annual maximum expenditure. Specific work elements are defined by the following tasks:
. Task 03
Project Management
Preliminary Sewer Design Services
Evergreen Park Expansion
e Task 01
. Task 02
A list of anticipated deliverables for this project is included as Exhibit D.
TASK 01
PROJECT MANAGEMENT
This task consists of coordination and management reserve.
Task 1.1
Coordination (Parametrix)
Objective:
This task will consist of project management, coordination of subcontractors, project
team meetings, coordination d11d meetings with City staff, financial management,
reporting, and scheduling.
.s.4pproach:
The Parametrix team will use a combination of in-house review, routine client meetings,
and monthly progress reports to deliver elements of work described in this task. The team
will provide for the overview, direction, monitoring, and reporting of task activities in a
manner that allows for the delivery of the project in accordance with the negotiated
scope, budget, and schedule. This will include all day-to-day interaction with the City,
attendance at meetings, routine correspondence, scheduling, budget management, etc.
DeJiverabJes: The following will be delivered:
.. The team will prepare and deliver routine correspondence, schedule and budget
updates, status reports on progress of work, and summary reports on meetings with
agencies, property owners and City personnel.
Assumptions: The following assumptions are made about this task:
City of Bremer/on
Beach Sewer Replacemellt alld Predesign
Scope of Work
255-1896-808
July 2005
e Project duration for this phase of work is through December 31, 2006.
e One (1) report detailing progress, budget status, and projected work for the following
month will be provided each month. Weekly progress will be discussed as part of
ordinary correspondence.
. Provide meeting minutes and records of all significant conversations.
. An amount will be added to each invoice to cover direct expenses such as in-house
duplicating and blue printing, local mileage, telephone calls, messaging, and postage.
Administrative time related to the project will be billed hourly. Allocated expenses
will be billed at 6 percent of billable labor. This amount is added to Task 1, but
covers all tasks. This excludes per diem and major outside printing efforts but
includes all minor day-to-day costs.
City
RespoflsibjJity: None
Task 1.2
Management Reserve (Parametrix)
This task consists of a reserve fund to cover unanticipated scope items. No billing to this
task will be allowed without prior written approval by the City.
TASK 02
PRELIMiNARY SEWER DESiGN SERVICES
Task 2.1
Documentation and As-built Review (KPFF/Parametrix)
Objective:
Review available City provided documents that address existing conditions within the
study area, to develop an understanding of the following:
$ Existing sanitary sewer operational characteristics
. Records of sewer lateral and main plugging or failure.
. Proposed WSDOT Manette bridge.
. Natura! environ..!TIent.
. Kitsap County Consolidated Housing Authority's (KCCHA) Condominium project.
. Downtown Revitalization Plan.
Approach:
Review existing City-provided GIS information and as-built drawings. The consultant
team will also review any other existing reports and studies that are on file with the City
that affect this area (that are provided by the City). This may include geotechnical
reports, the City's Comprehensive Plan, and drainage or sanitary sewer studies.
DeliverabJes: The following will be delivered:
.. List of all information collected and reviewed, and one (1) memorandum
summarizing findings.
City of Bremer/on
Beach Sewer Replacement and Predesign
Scope of Work
2
255-1896-808
July 2005
Assumptions: No geotechnical evaluation will be required beyond what already exists from other
sources.
City
Responsibility:The city will be responsible for the following:
~ The City will provide requested existing plans in an AutoCAD compatible format, if
available.
Task 2.2
Objective:
Approach:
. The City will prepare base maps of the project area in AutoCAD compatible format
for use by the Consultant.
Sewer Design Criteria (KPFF/Parametrix)
Develop goals and objectives and purpose and need statement for the sanitary sewer
including operational and maintenance requirements.
The consultant team will work together with the City to develop preliminary design
criteria and to prepare a Design Criteria Memorandum, including a purpose and need
statement. The design criteria will establish any requirements imposed by environmental,
technical, and operational consideration and confirm sewer flows, pipe materials,
connection points, cleaning methodology and access, and other issues that will serve as
the basis of the sewer main and lateral design.
Deliverables: The following will be delivered:
. Six (6) copies of the draft Design Criteria Memorandum.
. Six (6) copies of the final Design Criteria Memorandum.
Assumptions: The following assumptions are made about this task.
e One (1) meeting with City staff will be held to review the Draft Design Criteria
Memorandum and provide additional input on design criteria and purpose and need.
. The Final Design Criteria Memorandum will incorporate comments from City Staff.
City
Responsibjlity:The city will be responsible for the following:
. The City will approve the design criteria and purpose and need statement.
Task 2.3
Objective:
Approach:
Sewer Replacement Alternatives Analysis and Pre-design
(KPFF/Parametrix)
Develop up to seven (7) preliminary sewer replacement alternatives at a conceptual level.
Based on the design criteria and purpose and need statement approved by the City under
Task 2.2, the consultant team will identify up to seven (7) alternatives for a beach sewer
replacement option. The process to complete this task is as follows:
3
255-1896.808
July 2005
City of Bremer/on
Beach Sewer Replacement and Predesign
Scope of Work
e The consultant team will identifY up to seven (7) sewer replacement alternatives to be
screened by the City. These alternatives will evaluate order of magnitude costs,
maintenance, community benefits, aesthetics, and other criteria developed by the
consultant team and City.
II Alternatives for the beach sewer replacement option are likely to include a shallow
trench option, a deep gravity trench option, pressure and gravity mains supported by
a vehicle maintenance structure; a vacuum sewer alternative, and/or a combination of
these systems, various solutions for connecting the laterals, connecting the laterals to
the existing laterals at the toe of the slope on the beach, and alternatively at the top of
the slope directly to residences and businesses. This analysis will also include
options for pump station modifications.
. Based on the purpose and need statement for the project, a ranking system will be
developed for screening of alternatives.
Deliverables: The following will be delivered:
& Six (6) copies of the Alternatives Report and ranking system.
Assumptions: The following assumptions apply to this scope:
. Alternatives vvi!1 be developed based on the design criteria identified under Task 2.2
.. The consultant team will develop seven (7) beach sewer replacement alternatives to
the conceptual level.
. Evaluation of additional alternatives would be justification for a change in project
scope and budget.
f'"1:;..u
L.IL.!'
ResponsibjJity:The City will be responsible for the following:
. The City will develop the "Washington Avenue Grinder Pump" alternative to the 15
percent design completion level.
. The "Washington Avenue Grinder Pump" alternative will be carried forward to the
preliminmy design level by the City.
T^CV n'2
II""\",""I'\. VV
EVERGREEt--J PARK EXPAt--JS!ON
This Task consists of initiating negotiations with Ecology to address contamination issues
at the Chevron Property, submittal of a Brownfields grant application, and preliminary
community relations to build support for the park expansion.
Task 3.1
Negotiations with Regulatory Agencies (Parametrix)
Objective:
To initiate negotiations with Ecology in an effort to establish a path forward under an
agreed order or independent cleanup action at the Chevron Property.
Approach:
Specific work elements required to complete the task goal will include:
City oj Bremer/all
Beach Sewer Replacement alld Predesigll
Scape oj Work
4
255-1896-808
July 2005
@ Attend up to three (3) meetings with City and Ecology staff to negotiate remedial
solutions for the site.
. Using previous work as a guide, refine and select a remedial alternative for use in a
corrective action plan for the property.
. Develop a position paper and technical memorandum documenting the path forward
for the City to remediate the property in preparation for expansion of Evergreen Park.
Deliverables: The following deliverables are included under .this task:
. Six (6) copies of a Technical Memorandum detailing the selected path forward and
selected remedial alternative.
Assumptions: Work will be completed under the following assumptions:
. No sampling is included in this effort.
. This effort does not include writing a cleanup action plan or an agreed order.
. The City will acquire the Chevron property,
. The City will utilize an agreed order or independent cleanup action mechanism for
remediation of the property.
City
Responsibility:The city will be responsible for the following:
. Attending negotiations and approving the recommended solution.
Task 3.2
Brownfields Grants (Parametrix)
Objective:
To complete the final Brownfields Assessment Grant proposal for the Chevron property
for submittal to the United States Envirormlental Protection Agency (EPA).
Approach:
Specific work elements required to complete the task goal will include:
.. Completing one (1) Assessment Grant proposal for the Chevron property.
.. The proposal will be completed following guidelines outlined in Proposal Guidelines
for Brownfields Assessment, Revolving Loan Fund, and Cleanup Grants (EP A 2002).
. Developing budget estimates for conducting the assessment activities.
. Submitting all proposals to the City for final review and signature, as needed.
De/iverables: The following deliverables are included under this task:
. One (1) final Brownfields Assessment Grant Proposal for the Chevron property.
Assumptions: Work will be completed under the following assumptions:
. Only one (1) proposal will be required for assessment of the Chevron property.
Ciry of Bremer/on
Beach Sewer Replaceme11l and Predesign
Scope of Work
5
255-1896-808
July 2005
City
Respomibiiity:The city will be responsible for the following:
. The City will provide review of the proposal and final signature.
Task 3.3
Community Relations (Parametrix)
This program \NiB be intended to build broad based community v/ide support for the park
expanSIOn.
Approach:
The foilowing tasks wiil be performed:
. Facilitate one (1) Community meeting
. Meet with City staff to prepare for the first Public Meeting. Discuss issues and
confirm the City's position on expected concerns.
. Prepare meeting agenda, take and distribute meeting minutes.
o Compile the comment forms and provide a written summary of the comments.
. Meeting announcements, comment forms, directional signs, and sign-in sheets
Assumptions: The following assumptions apply:
. Illustrative figures and hand-drawn illustrations will be prepared under additional
scope.
. Meetings may be held in the evening.
. The design team will provide basic supplies needed for the meeting (easels, paper,
pens, refreshments, etc.).
DeliverabJes: The following will be delivered:
. Meeting minutes.
City
RespoHsibjJjty. The city will be responsible for the following:
.. City will contact property owners to set up meetings.
. Design Team and City staff will both be present at the meetings. Two (2)
representatives from Parametrix, will attend.
. The City will mail anrlOuncements to adjacent property owners and other interested
parties
City of Bremertol1
Beach Sewer Replacement and Predesign
Scape of Work
6
255.1896-808
July 2005
EXHIB!T C
D....J~~4.
DUU!dt:L
Parametrix ........................................................................................................................................ .. $40,500
Subconsultants
KPFF ... ........ ......... ..... ............ ... .............. ... ......... ............ .......... .... ...... ...... ............. ... $34,500
TOT A L ....... ............... ...... ..,...... ..... ... ............. .......... ............ ...... .... ............ $75,000
City of Bremer/on
Beach Sewer Replacement and Predesign
Scope of Work
8
255-1896-808
July 2005
E~hibit C
--------
€.~?(l1\se
illS\{ lO'(N.
"[MIC.
'5\jll~iJ$'I.
ORu c.oof..
1\ ClBI\c.aI!NiIl1Il\
. ~-' -'" ",,- ,- ,,,.
\ \ ,,,,",,"'" ... VI"'.' ,,,,",,,-
vm~cl M'"'''' ^",. ~m'" ISO"'"' VR ,,,,",, I \ Sc\t1"ll,is\ \ S6S.OQ 'rIQl.JRS
- "" -,,,," - - .. ",. ~.,.. -
<'9 II"'''' \"'""
MClClIVLlER . \ "" ,," \ "~ "" . .., . . .' /'
"om ,., . ....--" ........ ~ '0 "11.,,
,,,,;;''''''' ". .~ / //" /.. /'::~' ~~ ~:/ \
",,_ ..' --C . .--...... .' / . .... . ....... "'"~
.' ...\ /."-- .' ..... . . ,.
,__.... ...." .d' .d" _' . ... .d_ /' ...., . . .' ..' Om'
",.';";;';;"" .' ;:~~:..'-~' . _ :::::::::.:-:=:1. /~ '.;.~~-'-'; ..,
\)QCIl",.n\a\IOn"ano,~.:eUI\\ 1'\"-",,,,, ."" - \ ~ \1 ____ ___" - -\' - " -,," \--- I",
\::~;;,;;,;,,,,:;,.~~~~~::::::::: :~; /.z-~..~.:.:--:-,; :.'.~:.~~' d
'€.'ierIJ.............."",. .d' d' . " / /' '" ./..,. . .: "",
.' . /. d' / / .. . .' .
'l'\.gUI.a.\.o.r.i.l\~ga\I~\\O.".'.-/-- -- - -=;--~... ,.///./. . . ,.~
, ..,-. ./.--- '" '"
_,0'.... /./"" " "
fub\IC In,al,,,,.n\ M lB \14 4
Labor Su'o\ola\ \ ~ni\ CO" \ ~n~ Oil.c' CO"
-= \\el~ ~Ulll"'l~
In.t\oUSe E.~pense ~ \ .----l
S\lC"(\I$1I
"[OUll\;l\i>
B,UBO'
B,UB'.
d 1) bUC p'ccess phaSe 'l
YROJEC1': Bea~ u
~t)' of Bretnerton
$B ,OGO
\,,100\
,1:..\fjJ
5,1\10\
6.0401
15,2Gj
,6!<)fJ)1
5.01,
~
,G,d
-
~
15;' \ B96-%OB
\__\~.
1
1500
\1, \;~O
'1.500
1500
\
1
1~ \151)0
1,1)0
-~j\i\;:~o
~,'\151)O
~.<.i<llI.nl
--
-\
1
\ ..'l".\l~O
1.1 1,00
\
1,\9\.
--"...
r.. _"
-- \.--.
,
:J\'>.21~'
~~U~ '{~
--~~.-
O\tet\ cos\
t=-
---
OUlSi~~
Other Expan.a'
_ oe!:s~~ \f'lt2.0
~""''''r\I3_ e\C. . L--- $2, "':-----
-MisCC<ljli~"'~~--_.._-~
-~.--,,--
----
.,--"
-
14,9B~1
------.
. --~
PROJECTTOTAL
\---------~-
-------~
---~
=-----------
A\l?la,"oBY'~)
F\" Na<'" 8"'" '",'" 6Ud6:',;P;'i~'~~O.",~;;~~
'?le?a1er:\. ~y. ---
\?loiec\ Manageli
PAGE ~ Of'
PO f OR~ 00_6003-04
RPfF consulting Engineers
"'.\G,.....,.G cOSr ..-0'" rE' Clt'! o' ."",,^"
",\~ \~ Beach sewer
Civil oesign
'{ear 200S
---------------
~..t
scope;gfWO~~ ..i/..... .......J
fee EstiO"late
?ro\.
prlnc.
~
,?ro\.
Manag
~
\ten\OO.
~I
.---
-
2.
~
"()
't.'t/>.
1,W.
-
2.'17"
21\3
2,~C
Subtotals'.
...-
2.2 ~es\go-crlter\a :..----:
~Wil\l~~--
~tiOn~:ation~1 cnt~na \lniCal Meri'\orandUO"l
prepare orat\. oes\gn cntena eC
~esp~o\"callo D;~;ie9~t~riter~ri'\
r rep~ ----.:':. Suplotals'.
,.,:;;1'''''''''''' ,,,,,,,.,. ",d ,.. ...g'
0"""" s.w" ~::.~~~:~ 5ow" """'''''' E""''"''
Meet Wlt\l CIW to, 017 proposed f>.lternat\\Ies
,r',;';:::::;,~::::"~", E,iI",a" 7 >",'OS''''
0".'00 .""", 5;'"'''' ,< 2
"0'" .",,"g 5;'''''' 0" OW Co"'''',, . ,
""'0'" O"ft "",OS"," >OS"'''' "-'o~it it 2
cC "-"lOW O"ft >,,"os'''' >,al"" -00 '
"", wiln CII; S",,, aid'" ,,,, "ooit 1
""OO"d~~ ---- '
~,"a,,~~OOit--- soo\O"" "
-----------~
------~
2."2./'.
2,2\3
2.2C
2.20
2.2S
'2..3F>.
2.3\3
2.3C
2.30
2.3S
2.3r
2.38
2.3\-\
2.3\
2.3.\
2.3.\
-
city of aremerton
Beacn se~er and public ACcesS
,...,,,Aaet
.\J~'
S r. 'Stf'UC\.
Sngr.
~
'16
-e
"if
B
'2
'8
18
A
A
'8
~
~
-
fa
'4
2.0
'{2
2.0
'4
2A
'2
;;;
'8
%
;3Z
-
\ -r9f':!
1)
'0 \l
.0
'0 ~
------
-cO::> \ "
Cl'-i)DI
jec\l.
""fi5
Nlmin,
'165
Relrr\P
"()
$200
::---
~
1)
"2-
"'1f'
1)
1)
1)
32
~
4 24
16
-----
1
1
4~ A
4 -
-4
Fee
1>D
~ '\,960
$666
~O
"'$0
--sD
$880
=-no
~O
i@
~~DD
~540
~
~
$nO
~
~
~W(l
-:\ -$'1;9&0
1440
$4:'760
~
~
$1 ,060
~
~
$100 \ ~
_~1,71S
~
~~
T"$4~
104469
Juoe 2005
EXHIBIT D
List of Deliverables
1. Technical Memorandum summarizing documentation and As-Built review
2. Final Sewer Design Criteria Memorandum
3. Preliminary Alternatives and Ranking System Report
4. Technical Memorandum on Approach for Evergreen Park Remediation
S. Brownfields Assessment Grant Application
6. Meeting Minutes from Community Meetings
City of Bremer/on
Beach Sewer Replacemen/ and Predesign
Scope of Work
9
255-1896-808
July 2005