SUBJECT: Professional Services Study Session Date:
Agreement with Parametrix Inc., for the COUNCIL MEETING Date:
Kitsap Lake Stormwater Treatment Retrofit Department:
Project Presenter:
Phone:
December 8, 2021
December 15, 2021
Public Works & Utilities
Gunnar Fridriksson
3601473-5758
SUMMARY: The project will design stormwater treatment vaults at four stormwater outfalls that
currently discharge to Kitsap Lake untreated. The vaults will treat stormwater discharging from the
outfalls to a level that meets Washington State Department of Ecology (Ecology) standards for new
development. Parametrix will develop plans, specifications, and estimates (PS&E) to a 90 percent
complete level as required by the City's Water Quality Assistance Grant from Ecology (WQC-2020-
BremPW-00047). The grant amount is $93,750, with remaining project costs the City's responsibility.
ATTACHMENTS: 1. Professional Services Agreement with Parametrix, Inc.
FISCAL IMPACTS (Include Budgeted Amount): This project is included in the 2021 and 2022
Stormwater Capital Budget.
STUDY SESSION AGENDA: 0 Limited Presentation ❑Full Presentation
STUDY SESSION ACTION: M Consent Agenda ❑ General Business ❑ Public Hearing
RECOMMENDED MOTION: Move to approve the Professional Services Agreement for design of
the Kitsap Lake Stormwater Treatment Retrofit in the amount of $153,234.00; and authorize the
Mayor to finalize and execute the agreement with substantially the same terms and conditions as
presented.
COUNCIL ACTION: � Approve
Form Updated 01/02/2018