CONTRACT MODIFICATION AGREEMENT NO. 004
To City Contract # 6020
BETWEEN THE CITY OF BREMERTON AND PARAMETRIX
PROJECT Downtown Bremerton Bicycle/Pedestrian Circulation Improvements
CONSULTANT Parametrix, Inc
DATE October 27, 2021
THIS CONTRACT MODIFICATION AGREEMENT SPECIFICALLY AMENDS THE
PROFESSIONAL SERVICES AGREEMENT (the "Contract") entered into between the
City of Bremerton and Parametrix, Inc. on August 28, 2019, and modified on CM#001 on
April 24, 2020 and again modified on CM #002 on January 25, 2021 and again modified on CM #003 on April 30, 2021.
All provisions in the Contract shall remain in full force and effect except as expressly modified
by this document.
For valuable consideration and by mutual consent of the parties, the modifications to the
Contract are as follows:
I.
Section I. Scope , is modified as follows:
NO CHANGE
Section II. Term , is modified as follows:
The Consultant shall complete the work described in this Contract Modification Agreement by
June 30, 2022.
Section III. Compensation , is modified as follows:
NO CHANGE:The original contract amount was $ 30,622.51. The current contract amount,
including all previous amendments is $73,336.49.
II.
Consultant accepts all requirements of this Contract Modification by endorsing below.
Consultant further agrees that this Contract Modification constitutes full and final
settlement of all of the Consultant’s claims for contract time and for all costs of any kind,
including without limitation, costs of delays related to any work either covered or affected
by this Contract Modification, claims related to on-site or home office overhead, or lost
profits. This Contract Modification does not limit the City’s right to bring a claim for past
performance.
The undersigned consultant approves the foregoing Contract Modification as to the changes,
if any, in the contract price specified for each item, including any and all supervision costs
DocuSign Envelope ID: 04BAFE06-D549-40E6-9FE7-C576A9F7ED6F
Page 2 of 2
Contract Modification
Rev. 09/2021
and other miscellaneous costs relating to the change in work, and as to the extension of time
allowed, if any, for completion of the entire work due to said Contract Modification.
This document will become a supplement of the contract and all provisions will apply hereto.
It is understood that this Contract Modification shall be effective when approved by the City
of Bremerton.
The parties whose names appear below warrant that they are authorized to enter into a
contract modification that is binding on the parties of this contract. In addition, Consultant
warrants that it has or will inform the surety of this change, and shall take appropriate action
to modify any bonds required under the contract to address this change.
IN WITNESS WHEREOF, the parties have executed this Contract Modification on the day
and year first written above.
City Engineer / Public Works Director approved to process _________________________ (Initials and Date)
PARAMETRIX, INC. THE CITY OF BREMERTON
By:By:
Print Name:Print Name:
Its:Its:
Date:Date:
APPROVED AS TO FORM: ATTEST:
By:By:
KYLIE J. FINNELL, Bremerton City Attorney ANGELA HOOVER, City Clerk
NOTICES TO BE SENT TO: NOTICES TO BE SENT TO:
Parametrix, Inc.City of Bremerton
Attn: David Dinkuhn Attn: Shane Weber
60 Washington Avenue 345 6
th Street
Suite #390 Suite #100
Bremerton, WA 98337-1891 Bremerton, WA 98337
R:\Legal\Legal\Forms\FORMS ON COBWEB\Contract Modification Rev. 09 2021.docx
Ned Lever
Digitally signed by Ned Lever
DN: C=US, E=ned.lever@ci.bremerton.wa.us,O=City of Bremerton, OU=Engineering, CN=Ned Lever
Date: 2021.10.29 07:51:12-07'00'
DocuSign Envelope ID: 04BAFE06-D549-40E6-9FE7-C576A9F7ED6F
EP&C Division Manager
Jenifer Young
11/1/2021 11/1/2021
Greg Wheeler
Mayor