HomeMy WebLinkAbout2 - Contract Administrator Submission_ 210430_Contract Modification003 (2)Page 1 of 2
Contract Modification
Rev. 10/2019
CONTRACT MODIFICATION AGREEMENT NO. 003
To City Contract # 6020
BETWEEN THE CITY OF BREMERTON AND PARAMETRIX, INC.
PROJECT: Downtown Bremerton Bicycle/Pedestrian Circulation Improvements
CONSULTANT: Parametrix, Inc.
DATE: April 30, 2021
THIS CONTRACT MODIFICATION AGREEMENT SPECIFICALLY AMENDS THE
PROFESSIONAL SERVICES AGREEMENT (the "Contract") entered into between the
City of Bremerton and Parametrix, Inc. on August 28, 2019, and modified on CM#001 on
April 24, 2020 and again modified on CM #002 on January 25, 2021.
All provisions in the Contract shall remain in full force and effect except as expressly modified
by this document.
For valuable consideration and by mutual consent of the parties, the modifications to the
Contract are as follows:
I.
Section I. Scope , is modified as follows:
Work attached as Exhibit A
Section II. Term , is modified as follows:
The Consultant shall complete the work described in this Contract Modification Agreement by
October 30, 2021, attached as Exhibit B.
Section III. Compensation , is modified as follows:
The original contract amount was $ 30,622.51. The current contract amount, including all
previous amendments is $58,864.58 The City shall pay the Consultant for the additional work
described above, based on time and materials, an amount not to exceed $ 14,471.91 for a total
amended contract amount of $ 73,336.49, including this Contract Modification.
II.
Consultant accepts all requirements of this Contract Modification by endorsing below.
Consultant further agrees that this Contract Modification constitutes full and final
settlement of all of the Consultant’s claims for contract time and for all costs of any kind,
including without limitation, costs of delays related to any work either covered or affected
by this Contract Modification, claims related to on-site or home office overhead, or lost
profits. This Contract Modification does not limit the City’s right to bring a claim for past
performance.
DocuSign Envelope ID: B87F1DE6-337A-405E-AFE1-75C60E09A173
Page 2 of 2
Contract Modification
Rev. 10/2019
The undersigned consultant approves the foregoing Contract Modification as to the changes,
if any, in the contract price specified for each item, including any and all supervision costs
and other miscellaneous costs relating to the change in work, and as to the extension of time
allowed, if any, for completion of the entire work due to said Contract Modification.
This document will become a supplement of the contract and all provisions will apply hereto.
It is understood that this Contract Modification shall be effective when approved by the City
of Bremerton.
The parties whose names appear below warrant that they are authorized to enter into a
contract modification that is binding on the parties of this contract. In addition, Consultant
warrants that it has or will inform the surety of this change, and shall take appropriate action
to modify any bonds required under the contract to address this change.
IN WITNESS WHEREOF, the parties have executed this Contract Modification on the day
and year first written above.
City Engineer / Public Works Director approved to process _________________________ (Initials and Date)
CONSULTANT
By:
Print Name:
Its:
Date:
APPROVED AS TO FORM:
By:
ROGER A. LUBOVICH, Bremerton City Attorney
NOTICES TO BE SENT TO:
Parametrix, Inc.
Attn: David Dinkuhn
60 Washington Avenue
Suite #390
Bremerton, WA 98337-1891
THE CITY OF BREMERTON
By:
Print Name: Greg Wheeler____
ATTEST:
By:
ANGELA HOOVER, City Clerk
NOTICES TO BE SENT TO:
City of Bremerton
Attn: Chris Dimmitt
345 6th Street
Suite #100
Bremerton, WA 98337
R:\Legal\Legal\Forms\FORMS ON COBWEB\Contract Modification Rev. 10 2019.docx
Its: Mayor
Date: _________________
DocuSign Envelope ID: B87F1DE6-337A-405E-AFE1-75C60E09A173
5/8/2021
5/10/2021
Principal Consultant
John Perlic
5/10/2021
City of Bremerton 233-1896-178
Downtown Bremerton Bicycle Pedestrian Circulation Improvements 1 April 2021
Amendment 3 - Engineering Services During Bidding and
Construction
SCOPE OF WORK
City of Bremerton
Downtown Bremerton Bicycle Pedestrian Circulation Improvements
Amendment 3 - Engineering Services During Bidding and Construction
Introduction
This document describes Parametrix’s proposed scope of work (SOW) for providing civil engineering services for
the project under Amendment 3 to our existing contract. A proposed schedule is included in this scope and our
proposed budget is attached as Exhibit C. Main elements of the work consist of providing engineering services
during construction.
Task 6 – Engineering Services During Bidding and Construction
Objective
Provide engineering support during the bidding and construction phase of the project.
Activities
The following activities are associated with this task:
·Prepare up to two addenda during bidding.
·Attend construction meetings as requested.
·Review Contractor’s submittals for compliance with the specifications.
·Revise design documents in response to changes encountered during construction.
·Provide on-call field observation services.
Deliverables
The following deliverables are associated with this task:
·Bid addenda.
·Hard copies and electronic copies of responses to material submittals, cut sheets, and shop drawing
review, revised design documents.
·Daily reports.
Assumptions
The following assumptions apply to this task:
EXHIBIT ADocuSign Envelope ID: B87F1DE6-337A-405E-AFE1-75C60E09A173
SCOPE OF WORK (continued)
City of Bremerton 233-1896-178
Downtown Bremerton Bicycle Pedestrian Circulation Improvements 2 April 2021
Amendment 3 - Engineering Services During Bidding and
Construction
·Bid addenda will include a word document describing changes/additions to the bid documents and plans.
Addendum document format will be provided by the City. Revised plans and/or additional information
sheets will be attached to each addendum as needed. Up to two revised plans sheets will be prepared per
addendum (6 hours).
·The Parametrix PM and/or lead engineer will attend up to 2 site meetings at 2 hours each (4 hours total)
·Parametrix will review and respond to shop drawing submittals at an estimated 1.5 hours each and material
submittals at an estimated 1 hour each. It is assumed that a total of 2 shop drawings submittals, and 5
materials submittals will be reviewed (3 hours for shop drawings and 5 hours for submittals).
·4 plan sheets will be revised in response to unanticipated conditions at 2 hours each (8 hours).
·Engineer IV will provide up to 40 hours of field observation.
·Assumed hours for support are: Project Manager – 6 hours, Engineer IV – 44 hours (50 engineer hours
total).
DocuSign Envelope ID: B87F1DE6-337A-405E-AFE1-75C60E09A173
SCOPE OF WORK (continued)
City of Bremerton 233-1896-178
Downtown Bremerton Bicycle Pedestrian Circulation Improvements 3 April 2021
Amendment 3 - Engineering Services During Bidding and
Construction
Exhibit B - Schedule
Work Element Completed By
Notice to Proceed May 17, 2021
Engineering Services During Construction September 1, 2021
Project Complete October 30, 2021
EXHIBIT B
DocuSign Envelope ID: B87F1DE6-337A-405E-AFE1-75C60E09A173
Project: Amendment 3 - Downtown Bremerton Bicycle Pedestrian Circulation Improvements
Direct Salary Cost (DSC):
Classification Man Hours =Rate =Cost
Sr. Consultant 6 X $77.19 $463.14
Engineer IV 60 X $49.07 $2,944.20
Project Controls Specialist 4 X $39.37 $157.48
Sr. Project Accountant 4 X $41.41 $165.64
X $0.00
X $0.00
X $0.00
X $0.00
X $0.00
X $0.00
X $0.00
X $0.00
X $0.00
Total DSC =$3,730.46
Overhead (OH Cost -- including Salary Additives):
OH Rate x DSC of 179.52 % x $$3,730.46 $6,696.92
Fixed Fee (FF):
FF Rate x DSC of 28 % x $$3,730.46 $1,044.53
Management Reserve $3,000.00
Grand Total $14,471.91
Cost Estimate
Parametrix
4/28/2021 Amendment 3 Budget.xls
EXHIBIT CDocuSign Envelope ID: B87F1DE6-337A-405E-AFE1-75C60E09A173