HomeMy WebLinkAbout1 - Original Submission_ 210211_Change Order # 01CITY OF BREMERTON
CHANGE ORDER
CONTRACT CHANGE ORDER NO:#001
PROJECT NAME: 2020 Pavement Markings (City Contract # 6164)
PROJECT NO: 315040-42223 CONTRACTOR:
ORIGINAL CONTRACT AMOUNT: 113,700.00 DAYS: 28
PREVIOUSLY APPROVED
CHANGES:
0.00 DAYS: 0
THIS CHANGE: 29,737.50 DAYS: 0
REVISED CONTRACT AMOUNT: 143,437.50 DAYS: 28
This Change Order covers changes to the subject contract as described herein. The Contractor shall
construct, furnish equipment and materials, and perform all work as necessary or required to complete
the Change Order Items. The increase or decrease in contract price shown below includes any
applicable taxes. Rule 170 Rule 171 DESCRIPTION OF CHANGES
INCREASE IN
CONTRACT
AMOUNT
($)
(DECREASE) IN
CONTRACT
AMOUNT
($)
CONTRACT
TIME
EXTENSION
(DAYS:)
X
X
X
X
X
X
X
X
X
X
X
X
Corbet Drive- Kitsap Way to E Phinney Bay Drive
E Phinney Bay Dr- Corbet Drive to 26th Street
Wycoff Avenue- 6th Street to 25th Street
Lafayette Avenue- 15th Street to 19th Street
Lafayette Avenue- 24th Street to 26th Street
15th Street- Corbet Drive to High Avenue
13th Street- Callow Avenue to Kitsap Way
Callow Avenue- 6th Street to 15th Street
High Avenue- 11th Street to 15th Street
High Avenue- 6th Street to 11th Street
Veneta Avenue- 6th Street to 11th Street; 5thStreet to 6th Street
Almira Drive- Sheridan Road to Riddell Road
See Attachment #1 for additional scope detail
1,837.50
2,775.00
3,010.00
1,182.50
1,182.50
3,240.00
1,435.00
4,925.00
1,725.00
1,725.00
1,725.00
4,975.00
NET CHANGE IN CONTRACT AMOUNT
INCREASE OR (DECREASE)
29,737.50
ESTIMATED SALES TAX AT 9.0% 0
TOTAL INCLUDING SALES TAX $ 143,437.50
Contractor acknowledges and accepts that this Change Order constitutes final settlement of all claims
of any kind or nature arising from or connected with any work either covered or affected by this Change
Order, including, without limitation, claims related to contract time, on-site or home office overhead, or
lost profits. Nothing in this Change Order shall limit the City’s right to bring a claim for past performance.
113A6165
DocuSign Envelope ID: 96B8DEDA-054E-438E-979B-08428698DDFB
Ned Lever
Digitally signed by Ned Lever
DN: C=US, E=ned.lever@ci.bremerton.wa.us,
O=City of Bremerton, OU=Engineering, CN=Ned
Lever
Date: 2021.02.03 16:00:01-08'00'
Thomas Knuckey Digitally signed by Thomas
Knuckey
Date: 2021.02.11 10:56:40 -08'00'
DocuSign Envelope ID: 96B8DEDA-054E-438E-979B-08428698DDFB
3/1/2021
DocuSign Envelope ID: 96B8DEDA-054E-438E-979B-08428698DDFB
Change Order No. 1 – Bid Item Descriptions
2020 Pavement Marking Project
Bid Item Road Limits Description of Work
13 Corbet Drive Kitsap Way to E Phinney Bay Drive From Kitsap Way to 15th: Centerline skip stripe. This
segment has existing RPM’s. Replace missing Type 1
RPM’s and replace all Type 2 RPM’s with new. Does
NOT Include intersection island at 15th.
From 15th to E Phinney Bay Drive: Centerline DY
line. Convert existing paint double yellow centerline
to RPM’s by installing new RPM’s.
14 E. Phinney Bay
Drive
Corbett to 26th Street/E Phinney
Bay Drive
Centerline skip stripe. This segment has existing
RPM’s. Replace missing Type 1 RPM’s and replace
all Type 2 RPM’s with new.
15 N Wycoff Ave 6th Street to 25th Street Centerline skip stripe. This segment has existing
RPM’s. Replace missing Type 1 RPM’s and replace
all Type 2 RPM’s with new.
16 N Lafayette Ave 15th Street to 19th Street Centerline skip stripe. This segment has existing
RPM’s. Replace missing Type 1 RPM’s and replace
all Type 2 RPM’s with new.
17 N Lafayette Ave 24th Street to 26th Street Centerline skip stripe. This segment has existing
RPM’s. Replace missing Type 1 RPM’s and replace
all Type 2 RPM’s with new.
18 15th Street Corbett Drive to High Ave Centerline skip stripe. This segment has existing
RPM’s. Replace missing Type 1 RPM’s and replace
all Type 2 RPM’s with new.
19 13th Street Kitsap Way to Callow Ave DY Centerline and centerline skip stripe. This
segment has existing RPM’s. Replace missing Type 1
RPM’s and replace all Type 2 RPM’s with new. There
is a segment of paint DY centerline around
horizontal curve just north of Kitsap Way; convert
this paint segment to new RPM’s.
20 Callow Avenue 6th Street to 15th Street All longitudinal lines. This segment has existing
RPM’s. Replace missing Type 1 RPM’s and replace
all Type 2 RPM’s with new.
21 High Avenue 11th Street to 15th Street Centerline skip stripe. This segment has existing
RPM’s. Replace missing Type 1 RPM’s and replace
all Type 2 RPM’s with new.
22 High Avenue 6th Street to 11th Street Centerline skip stripe. This segment has existing
RPM’s. Replace missing Type 1 RPM’s and replace
all Type 2 RPM’s with new.
23 Veneta Avenue 6th Street to 11th Street & 5th
Street to 6th Street
Centerline skip stripe. This segment has existing
RPM’s. Replace missing Type 1 RPM’s and replace
all Type 2 RPM’s with new.
24 Almira Drive Sheridan Road to Riddell Road Centerline skip stripe. This segment has existing
RPM’s. Replace missing Type 1 RPM’s and replace
all Type 2 RPM’s with new.
DocuSign Envelope ID: 96B8DEDA-054E-438E-979B-08428698DDFB