HomeMy WebLinkAbout03/03/2021 4DAGENDA BILL
CITY OF BREMERTON
CITY COUNCIL
SUBJECT: Accept Highway Safety
Improvement Project Grant; and Approve
Local Agency Agreement with the
Washington State Department of
Transportation (WSDOT) for the Systemic
Pedestrian Treatment Project
Study Session Date: February 24, 2021
COUNCIL MEETING Date: March 3. 2021
Department: Engineering
Presenter: Andrea Archer -Parsons
Phone: (360) 473-2317
SUMMARY: The City has been offered a Highway Safety Improvement Program (HSIP) grant to
design and construct rectangular rapid flashing beacons (RRFB) with associated ADA ramp
upgrades at select locations city wide. The project cost is $864,500. The grant requires a 10%
match; however, the construction phase is eligible for 100% funding if the obligation is authorized by
April 30, 2023. The offered grant will be in WSDOT Standard Forms, with their standard terms and
conditions.
ATTACHMENTS: 1) Grant Award Letter, 2) Site Plan, 3) Local Agency Agreement
FISCAL IMPACTS (Include Budgeted Amount): The total project budget is $864,500. The grant
award amount is $848,500. The 10% match for the design and right of way phases is $16,000,
which will be funded by REST. The construction match is identified as $70,450 and will be waived
assuming construction obligation is received by April 30,2023. The grant award amount assumes
the construction match has been waived.
STUDY SESSION AGENDA: � Limited Presentation ❑Full Presentation
STUDY SESSION ACTION: ❑ Consent Agenda ® General Business ❑ Public Hearing
RECOMMENDED MOTION:
Move to accept grant and approve Local Agency Agreement for the Systemic Pedestrian Treatment
Project, and authorize the Mayor to finalize and execute the agreement with substantially the same
terms and conditions as presented.
COUNCIL ACTION: Approve
Form Updated 01/02/2018
❑ Deny ❑Table ❑Continue ❑ No Action