SUBJECT: Study Session Date: April 10, 2019
Confirmation of Contracts with Pape & Sons COUNCIL MEETING Date: April 17, 2019
Construction, Inc. and Pro-Vac, Inc. for the Department: PW&U
Gorst Sewer Emergency Repair Presenter: Thomas Knuckey
Phone: (360) 473-2376
SUMMARY: On March 29th, 2019 Mayor Wheeler issued an emergency proclamation to enable
appropriate and timely response to the sanitary sewer forcemain break that occurred near the
intersection of Anderson Hill Road. In accordance with procedures outlined in BMC 2.26.210
(Mayor's Proclamation of Emergency), the City entered into two contracts that would otherwise have
required Council approval; a contract with Pro-Vac for sewage tanking services, and a contract with
Pape & Sons Construction Inc., for the construction. All physical construction was completed, and a
Mayor's Declaration ending the emergency was issued on April 11, 2019.
ATTACHMENTS: 1) Proclamation of Emergency 2) Public Works Agreement with Pape & Sons
Construction, Inc. 3) Amendment to Public Works Agreement with Pape & Sons Construction, Inc.
Added 3) Contract with Pro-Vac
FISCAL IMPACTS (Include Budgeted Amount): Total cost of the Pro-Vac work was approximately
$76,725, the estimated cost of the Pape Construction work is $120,000. The total cost of all work
and materials for the emergency repair is anticipated to be $350,000.
STUDY SESSION AGENDA: ❑x Limited Presentation ❑ Full Presentation
STUDY SESSION ACTION: ❑ Consent Agenda ❑x General Business ❑ Public Hearing
RECOMMENDED MOTION:
Move to confirm the contracts executed with Pape & Sons Construction, Inc. and Pro-Vac, Inc. with
substantially the same terms and conditions as presented, to complete the Gorst sewer repairs in
response to the March 29, 2019 Mayor's Proclamation of Emergency.
COUNCIL ACTION: Approve ❑ Deny ❑ Table ❑ Continue ❑ No Action