HomeMy WebLinkAbout02/06/2019 5FAGENDA BILL CITY OF BREMERTON CITY COUNCIL 5F SUBJECT: Budget Adjustment to Close Out Study Session Date: January 23, 2019 Lebo Boulevard Construction Fund COUNCIL MEETING Date: February 6. 2019 Department: Financial Services Presenter: Mike Riley Phone: (360) 473-5303 SUMMARY: The Lebo Boulevard Reconstruction Project was completed in 2018. The City created a separate fund to track the street work, while the utility work was reported in the applicable utility capital funds. The project was funded, in part, by a Transportation Improvement Board (TIB) Grant. The street and stormwater work was grant eligible, and the City elected to use the stormwater work to meet its match requirement. At completion, the City received $5,241,025 from TIB. The street costs totaled $5,008,522. The excess funds (including interest earned) will be transferred to the Stormwater Capital Fund and the Lebo Boulevard Construction Fund will be closed. ATTACHMENTS: FISCAL IMPACTS (Include Budgeted Amount): Authorize a budget adjustment to transfer -out remaining cash and interest earnings in Fund 317 to Fund 484. The transfer amount is estimated to be between $233,000 and $238,000. STUDY SESSION AGENDA: ❑x Limited Presentation ❑ Full Presentation STUDY SESSION ACTION: o Consent Agenda ❑ General Business ❑ Public Hearing RECOMMENDED MOTION: Move authorize the transfer -out of remaining excess funds (cash and interest earnings) from the Lebo Boulevard Construction Fund 317 to the Stormwater Capital Fund 484 and close the Lebo Boulevard Construction Fund. 1 COUNCIL ACTION: ❑ Approve Form Updated 01/02/2018 ❑ Deny ❑ Table ❑ Continue ❑ No Action