HomeMy WebLinkAbout04/04/2018 5ESUBJECT: Change Order No. 2 to the
Professional Services Agreement with
Cosmopolitan Marine Engineering for
Sediment Sampling & Analysis and
Combined Sewer Overflow Post -
Construction Monitoring Report
AGENDA BILL
CITY OF BREMERTON 5 E
CITY COUNCIL
Study Session Date:
COUNCIL MEETING Date:
Department:
Presenter:
Phone:
March 28, 2018
April 4, 2018
PW&U / WWTP
Rick Zimburean
(360) 473-5449
SUMMARY: In February 2015, the City entered into a professional services agreement with
Cosmopolitan Marine Engineering for sediment sampling & analysis and a CSO Post Construction
Monitoring Report in the amount of $113, 778. In June 2015, the first change order in the amount of
$4,780 was executed.
The CSO Post Construction Monitoring Report has been completed. There is still supplemental
engineering services needed to work through the critical issues with the sediment sampling and
analysis with WA Dept. of Ecology ("DOE"). Cosmopolitan Marine Engineering will also review the
upcoming draft NPDES Permit in regards to the proposed supplemental sediment sampling
requirements.
The proposed Change Order No. 2 to this PSA would be in the amount of $27,770.
ATTACHMENTS: 1) Current PSA, 2) Change Order No. 2, 3) Proposal from Cosmopolitan Marine
Engineering
FISCAL IMPACTS (Include Budgeted Amount): This is budgeted through the WWTP Professional
Services budget of $200,000.
STUDY SESSION AGENDA: ® Limited Presentation ❑ Full Presentation
STUDY SESSION ACTION: ® Consent Agenda ❑ General Business ❑ Public Hearing
RECOMMENDED MOTION: Move to approve Change Order No. 2 to the Professional Services
Agreement with Cosmopolitan Marine Engineering in the amount of $27,770; and authorize the
Mayor to finalize and execute the Change Order as presented.
COUNCIL ACTION: Q'Approve ❑ Deny ❑ Table ❑ Continue ❑ No Action