SUBJECT: Resolution No. 3298 Declaring Study Session Date: N/A Emergency -Item
an Emergency to stabilize the East Park COUNCIL MEETING Date: November 15, 2017
Storm Water Outfall Department: PW&U
Presenter: Ned Lever
Phone: (360) 473-2398
SUMMARY: The East Park Outfall reconstruction project was completed in September of 2017. The
work included removing beach armoring and placement of beach gravels to restore the beach.
Recent rains have caused significant erosion which is jeopardizing an existing sewer main and the
storm water outfall itself. Public Works has applied for emergency permits from the Army Corps of
Engineers, WDFW, and the DNR. This Resolution declares the emergency conditions, and
authorizes the Mayor and the Mayor's designee to execute the necessary contracts to expedite the
stabilization of the beach and protect the sewer main and storm water outfall.
ATTACHMENTS: 1) Resolution No. 3298 2) Photos
FISCAL IMPACTS (Include Budgeted Amount): The East Park Storm Water Outfall Project is
included in the 2017 Capital Budget and sufficient budget is available to fund this emergency work.
Future reimbursement of costs associated with continuing work at this outfall will be considered.
STUDY SESSION AGENDA: ® No Presentation ❑ Full Presentation
STUDY SESSION ACTION: ® Consent Agenda ❑ General Business ❑ Public Hearing
RECOMMENDED MOTION:
Move to approve Resolution No. 3298 declaring an Emergency to stabilize the East Park Storm
Water Outfall.
COUNCIL ACTION: [�/Approve
Form Updated 01/07/15
❑ Deny ❑ Table ❑ Continue , ❑ No Action