HomeMy WebLinkAboutPacific Avenue 6th Street to 11th Street ProjectGary W. Nystul CPA CFE
City Auditor
345 Sixth Street Suite 600
Bremerton, WA 98337-1873
360.473.5369
gary.nystul@ci.bremerton.wa.us
CITY AUDITOR
February 27, 2015
Members of the Bremerton City Council
Mayor Patty Lent
The City Auditor has prepared the attached report reviewing the Pacific Avenue 6th Street
to 11th Street Project. This review was performed due to the length of time from the
award of the grant to the completion of the project. The review was scheduled on the
2014 work plan and is presented for informational purposes.
The report discusses the several causes of delay including staff changes. The report also
discusses issues raised by citizens.
The assistance of city engineers Thomas Knuckey, Gunnar Fridriksson, and Ned Lever is
greatly appreciated.
Sincerely,
Gary W. Nystul
cc: Director of Public Works
City Attorney
Director of Financial Services
PACIFIC AVENUE 6th STREET to 11th STREET
PURPOSE
This is a special report reviewing the public works project to reconstruct Pacific
Avenue from 6th Street to 11th Street that took an extended amount of time to
complete.
SCOPE
Administrative actions, contracts for the performance of this project including
design and construction, are included.
OBJECTIVE
Present an analysis of the process and the time required to reconstruct Pacific
Avenue from 6th Street to 11th Street.
BACKGROUND
This project was selected for a detailed review due to the extended amount of time
to complete. In October 2009 the Puget Sound Regional Council announced that
Bremerton had been awarded federal funding of $3 million to construct the
project. The federal funding became available on July 1, 2010. The project was
substantially complete in April 2014 (46 months after funding authorization).
The Pacific Avenue Improvements were described in the grant agreement as
follows: "Streetscape improvements including new curb, gutter and sidewalk, low
impact development provisions, and pavement restoration to create a "complete
street" in Bremerton's redevelopment of its downtown urban center."
The funding was provided by the federal grant, moneys from the city's General
Fund, Water Capital and Wastewater Capital Funds. The water department and
wastewater department paid their respective shares to upgrade their facilities in
the project area.
THE PROJECT PROCESS
Through the Puget Sound Regional Council the city applied for federal funding to
rebuild Pacific Avenue. Notification of funding in the amount of $3 million was
received in September 2009 for the 2011 to 2012 funding years through the
Federal Highway Administration Surface Transportation Program. The Local
Agency Agreement (contract) with the Washington State Department of
Transportation was approved for preliminary engineering with the federal share of
$391,326 effective July 1, 2010.
The city then began the process of engaging engineering firms to design the
project as required by federal and state regulations. A Statement of Qualifications
was advertised in October 2010. Interviews were conducted in November 2010.
In February 2011 the city council approved the selection of Parametrix to do the
work activities associated with obtaining final permits and approvals, and
preparation of plans, specifications and cost estimates necessary to bid and
construct the proposed improvements. SvR Design Company was selected to do
the work activities associated with low impact and green stormwater
infrastructure techniques including landscaping and irrigation to manage, treat and
infiltrate stormwater, preparation of plans, specifications and cost estimates
necessary to bid and construct the proposed improvements.
In April 2011 the city council approved a project agreement for design services
with Puget Sound Energy for underground conversion of their overhead lines.
In June 2011 final plans for construction were received from the engineers. A
supplement to the Local Agency Agreement with the Washington State
Department of Transportation was received authorizing the balance of the federal
funds for construction ($2,563,175).
By July 2011, the city engineer, two project engineers and a project manager had
been dismissed from city employment. On July 11, 2011 the Director of Public
Works was dismissed. These personnel actions substantially reduced the ability
of the Department of Public Works to manage major construction projects. In
addition, the estimated costs of the project exceeded funding, including the
amount for pervious surfaces. There were also significant challenges with the
design, cost allocation and residential costs for undergrounding of the electrical
system. As a result, the project was placed on hold.
In January 2013 the project was revived. A contract was awarded to Parametrix
in February to modify the final plans and specifications that were previously
submitted to meet available funding. In June 2013 a contract was awarded to RV
Associates, Inc. for construction. An agreement was also approved with Puget
Sound Energy for undergrounding of their electrical facilities.
2
CAUSE OF DELAYS
The length of time to complete this project was a result of the following:
o Changes in Director of Public Works. There have been four Directors
of Public Works and one interim director since the project was awarded
funding by the Puget Sound Regional Council through its completion.
o Changes in managing engineers/project managers. Managing
engineers and project engineers coordinate with the consultants as well as
assisting in the design. The project manager responsible for this project
was dismissed in 2011, prior to design completion. This coupled with the
departure of several other engineering staff left fewer project managers to
manage a number of projects. Therefore, it was necessary to delay some
projects until there was sufficient staff to manage them.
o Procurement of consulting engineers. There is a procedure established
by law for the procurement of engineers for large projects and those
funded by federal grants. In general this involves drafting a request for
qualifications, publication, selection of a group of firms to interview, the
actual interview, selection of the firm, acceptance by the State Department
of Transportation, followed by city council committee approval and finally
city council approval. All of which takes time.
o Schedule 74 undergrounding by PSE. The process to underground the
electrical distribution system started with the signing of a design
agreement with the electric utility company, where they provided a
ballpark cost estimate of $250,000. With completion of the detailed plans,
the cost for completion was projected to be $425,000, substantially more
than initially estimated. This estimate resulted in a revision to meet
budget causing further delays as the scope of work and the design were
updated.
o Re -design required to reduce construction cost. The project design
completed under the first project manager included a significant amount of
low impact development features beyond the work scope identified in the
grant documents, which were high cost with questionable reliability. The
construction cost estimate completed for this design exceeded the
available funding by 30%. When the project was re-initiated in 2013, staff
worked with the consultant to implement several design revisions to
reduce cost.
CONSTRUCTION CONTRACT
A contract with RV Associates, Inc. was signed June 14, 2013, for $3,131,378
with 138 days to complete the project. The contract was divided into four work
schedules: Roadway, water, sanitary sewer, and vehicle charging station. Each
schedule contained numerous items or quantities of work and the estimated cost.
Public work contracts have a long list of individual tasks and pay items with
estimated quantities. The standard specifications clause regarding estimated
quantities in the contract can be summarized as follows:
The quantities shown on the proposal form and contract are estimates and
are stated only for bid comparison purposes. The city does not warrant
expressly or by implication that the actual quantities of work will
correspond with those estimates. Payment will be made on the basis of
actual quantities of each item of work completed in accordance with the
contract requirements.
As is normal, quantities and conditions varied and were addressed in change
orders. Four Change Orders were approved by the city council. These increased
the total cost by $ 349,851.96 or 11.2% of the original contract. Five days were
also added to the completion time. The following is a summary schedule of the
change orders.
Change Orders
1. Install crosswalks and temporary signs
Additional demolition work
Total
2. Removal and replacement of unsuitable material
Additional backfill
Removal, splicing, restoration of utility conduits
Delete electric car charging stations
Total
3. Adjust for actual vs. estimated quantities
Water
Sewer
Total
4. Incentive for early substantial completion
Paving on Saturday
Quantity Variation
Total
Total Increase
35,612.68
76,854.92
19,878.04
42,488.80
112,467.59
18,000.00
5,420.00
151,597.53
175,017.53
349,851.96
0
CONSTRUCTION OBSERVATIONS/CITIZEN ISSUES
A punch list was prepared by the Department of Public Works staff when the
construction was completed. This standard procedure, at the completion of a
construction project, prepares a listing of all things that need to be completed,
repaired, or replaced for final acceptance by the owner. The Public Works staff
reviewed the items and worked with the contractor to address them.
In addition, some design issues have been noted and reported by citizens. The
following items were observed and a discussion of the item and its disposition
follows the summary remarks.
1. A handicapped compliant ramp was not installed at the front door entrance of a
commercial building at the corner of Pacific and 71' Street.
Prior to the project, there was a non-compliant ramp that sloped up to the door
which included some of the sloping ramp in the city sidewalk. The Building
Official reviewed the situation and outlined the requirements for a handicapped
compliant ramp. There was not enough space to comply with the design
requirements. The building official advised staff on the best solution, which was
a step, which has been installed.
2. A new fire hydrant was installed in the sidewalk near the Red Cross building.
The hydrant is in the sidewalk and located towards the outside edge. The
remaining clear width of the sidewalk meets ADA requirements. Other new fire
hydrants installed on Pacific Avenue and elsewhere in the downtown from recent
projects are not in the far side of the sidewalks and are closer to the curb. While
this may meet ADA standards, it is not a logical placement.
3. The front steps of several residences encroach upon the city street right of way.
The steps from the sidewalk to the front door or porch of several residences are in
the city street right-of-way. These steps most likely do not have a right-of-way
permit but have been there since they were constructed many years ago. The
width of the new city sidewalk meets ADA requirements. Elimination of the
steps in the right-of-way would have required reconstruction on private property.
There were not sufficient funds in the budget to assist with any change. It would
be the responsibility of the homeowner to remove and replace the steps.
4. The undergrounding of the electrical distribution system was done for the
commercial area, but not for the residential area.
Puget Sound Energy has a tariff outlining cost sharing when placing their
electrical distribution system underground. The cost is shared between the city,
the customer and the electric utility. The cost in the street right of way is shared
between PSE and the city. The cost from the edge of the city right of way to the
electrical customer's connection point must be paid for by the customer. Placing
the electric services underground for the residences would place a financial
burden on them. In some cases the houses do not have electrical panels or
services that meet current codes. The residences would have an additional burden
if they had to upgrade their residential wiring. For these reasons the
undergrounding was done only in the commercial area.
5. Sidewalks near some retaining walls did not extend all the way to the wall.
New sidewalks were installed for the length of the project. In some areas where
there was a retaining wall or a concrete stairway, the new sidewalk extended only
to the edge of the retaining wall footing. The footing or bottom step was not
removed therefore does not "appear" complete. It was neither practical nor
economical to remove these footings or bottom step solely for the appearance of a
new sidewalk. There was also risk to the integrity of the wall if the footing were
changed. This base of the footings adjacent to the sidewalk is only a few inches
wide. The new sidewalks meet ADA requirements.
31
6. Pervious pavement was installed on the "uphill" side of the street.
Pervious pavement is intended to direct rain water runoff into the ground under
the street rather than going into the storm sewer. However, the soils under the
street must be appropriate to allow the water to infiltrate. The soils analysis
identified only a limited area that was conducive to absorbing runoff. In addition,
there was concern in some areas of where water could collect. Some older
buildings with basements have benefited from rain water running into the curb
and gutter system and the storm drains. Adding water to the soils near these
buildings may result in water in existing basements. The amount of pervious
surface met the grant requirements and was placed where it would allow
infiltration without jeopardizing adjacent buildings.
7. The bioretention swales appear to be uphill of the street runoff.
Two bioretention swales were installed at the edge of the street. Their surface is
at the curb and sidewalk elevation. The swales are intended for run off from the
sidewalk and nearby concrete surfaces and not from the street. They are at the
proper grade.
8. Electrical boxes in the sidewalk on the side of the street in front of the bank are
not in a straight line.
There are several electrical boxes in the sidewalk that are for servicing street
lights, and other uses. They are not in a single straight line because the conduit
connecting them is not able to be bent around them. It is an aesthetics issue and
not a safety or quality issue.
9. The location of the electrical meter cabinet by the post office at 6th street.
7
The electrical services for lights and other uses require a cabinet to house the
electrical meter. The housing serving the post office area of the project was
installed at the edge of the sidewalk near 6th Street. Visually, it appears out of
place. The sidewalk in the area meets ADA requirements. Access to the panel is
required from the back so it could not be located at the edge of the right of way.
Other panels installed for this project are in less obstructive locations.
WARRANTY
There is not a written warranty clause in the standard contract for the work
performed. The state contract regulations prohibit the city including a clause in
the contract stating, for example, that the contractor shall return to the project to
repair or replace all defects in workmanship and material discovered within one
year after Final Acceptance of the Work. The city has relied on a more general
clause referencing guarantees or warranties for purchased materials.
CONTRACT DOCUMENT ERROR
The contract documents used for these public works projects are forms required
by the Washington State Department of Transportation. The state provides two
versions in their forms library. One form is for constructing buildings and one is
for road construction. The contract executed for this project was actually the form
for buildings. In addition, three places in the contract in which wording should
have been inserted were left blank. The city staff needs to take better care in
properly completing the standard contract forms. The state is working on
addressing IT needs in the use of these forms.
CONCLUDING OBSERVATIONS
The time required to complete this project is not normal for public works. The
start with the grant award, selection of the engineer and completion of plans and
specifications was typical. Problems contributing to the delay were the estimated
costs compared to the available grant and other funds. The problems with
undergrounding the electrical utilities added design time and required cost
revisions. In addition, changes in the director of public works and elimination of
some engineering staff caused the project to be put on the shelf.
SUMMARY OF OBSERVATIONS
Changing the Director of Public Works can have an effect on management of
public works projects.
2. Reduction of engineering staff can have a direct effect on the ability of the
department to design, manage, and maintain required schedules of major projects.
3. A poorly placed fire hydrant or an electrical panel, detract from public confidence
in the finished project although they comply with all construction standards and
are only a small portion of the total cost.
4. It is difficult to understand why the Washington Department of Transportation
prohibits modifications to its bid forms. This inability to modify bid forms
precludes municipalities from including a provision in the construction contracts
for the contractor to warranty their work for one year.
5. There are times that complying with federal regulations result in a solution that
does not appear logical. (Such as a step rather than a ramp.) In cases where
compliance with building standards cannot be achieved, staff appropriately relied
on the building official's direction to minimize the City's risk.
I