Loading...
HomeMy WebLinkAbout5591AW TV state Washington nt of TnnsporWtion Change order Contract Number Contract Title Federal Aid Number 42105 Crosswalk Improvements 9918(015) Change Order Number Change Description Date 2 Add Luminaire 2/3/17 Prime Contractor / Design -Builder Massana Construction, Inc. ✓ Ordered by Engineer under the terms of Section 1-04.4 of the Standard Specifications ❑ Change proposed by Contractor / Design -Builder Change Description Description: This change order compensates the contractor for all labor, materials and equipment required to furnish and install a luminaire at the intersection of 6th Street and High Ave., and other work shown in the Plans. Material Requirements: Materials shall be in accordance with the plans and City of Bremerton standards (Plan Revision #1). Construction: Work shall be completed in accordance with the plans and specifications. Measurement: Measurement for this change order will be made as "Illumination System" and shall be by lump sum. veroai Hpprovai Uiven t3y Verbal Approval Date Working Days Shane Weber Jan 30; 2017 +2 Original Contract Amount Current Contract Amount Est. Net Change This C.O, Est. Contract Amount $688,455.00 $688,455.00 $10,734.23 $699,189.23 V Approval Recommende, Approved Approved 45:�7�/ gineer_ :ApprcvnlngAuthori a .A. Agreement l �" Date Date ,q 7 �3 Approval Recommended Other Approval As Required 'Birim%e -Contract6r Signature . Date Date Representing WSDOT Form 140-005 Page 1 Revised 04/2015 Contract Number Contract Title Change Order Number 42105 Crosswalk Improvements 2 Change Description Cont. Payment: Payment for Illumination System shall be paid for by lump sum and shall be full pay for the construction of the complete illumination system as described in this change order and as shown -in the Plans, and herein specified, including excavation, backfilling, concrete foundations, conduit, wiring, restoring facilities destroyed or damaged during construction, salvaging existing materials, traffic control, submittal review and for making all required tests. All additional materials and labor, not shown in the Plans or called for herein and which are required to complete the illumination system, shall be included int he lump sum Contract price. Working Days: Add two additional working days to the contract working days. w.l, +V'VVJ Page t Revised 0412015 October 28, 2016 Dana Marie Smith Puget Sound Energy 22884 Ryan Drive NW Poulsbo, WA 98370 Re: Memorandum of Agreement — Design Revision at 6t' and High Ave. Dear Ms. Smith: The City of Bremerton agrees to revise the location of the street light at 6th Street and High Avenue to avoid a conflict with PSE's overhead utilities. This relocation will require: Estimated Cost ® Design and PS&E $5,850 ® Special Foundation Design (for utility conflict, if needed) $2,350 ® Construction Engineering / Administration $5,450 • Installing light pole and foundation, including sitework $15,000 Total cost for the relocation is approximately $28,650 which PSE agrees to pay in full at final/actual cost. The City will invoice PSE with actual costs once the work is completed, which should be by late February 2017. If PSE agrees to these costs, please sign below and return this letter. If you have. any questions or wish to meet to discuss, please feel free to call me at 360.473.2354 or via email at shane.weberci.bremerton.wa.us. Sincerely, Shane JJ Weber, P.E. , Managing Engineer Cc: Thomas Knuckey P.E., City Engineer Project file 1610-07 Dana Marie Smith V Public Works & Utilities 1 3027 Olympus Drive, Bremerton, WA 98312 * Phone (360) 473-5270 * Fax (360) 473-5398 Working for and with our citizens to establish Bremerton as Puget Sound's most beautiful and livable waterfront city! SUBJECT: Contract Award to Massana Construction, Inc. for the Bremerton Crosswalks Improvement Project AGENDA BILL CITY OF BREMERTON CITY COUNCIL &�' 0- -O�Tq I 8A Study Session Date: June 8, 2016 COUNCIL MEETING Date: June 15, 2016 Department: PW&U Presenter: Phone: Knuckey (360) 473-2376 SUMMARY: The City received a $692,000 grant through KRCC for the Bremerton Crosswalks Improvement Project, which improves pedestrian crossings at Kitsap Way at Harlow Drive, and the intersections of Kitsap Way & 11th Street, High Avenue & 11"' Street, High Avenue & 6th Street, and SR304 & 1St Street. Bids were opened on June 10, 2016, with 2 bids received. Massana Construction Inc. was the lowest responsive, responsible bidder at $ 688,455.00, including sales tax. ATTACHMENTS: 1) Site Plan; 2) Contract; and 3) Bid Tab FISCAL IMPACTS (Include Budgeted Amount): The project is included in the 2015 and 2016 CIP at $800,000. To award the bid, additional funding of approximately $65,000 is needed. We recommend the project budget be adjusted to $900,000. Funding is available from the Transportation Capital Improvement Fund. STUDY SESSION AGENDA: o No Presentation ❑ Full Presentation STUDY SESSION ACTION: ❑ Consent Agenda o General Business ❑ Public Hearing RECOMMENDED MOTION: ° Move to award the contract to Massana Construction Inc. in the amount of $688,455.00 for the Bremerton Crosswalks Improvement Project; and authorize the Mayor to finalize and execute the agreement with substantially the same terms and conditions as presented. COUNCIL ACTION: [� Approve ❑ Deny ❑ Table ❑ Continue ❑ No Action Form Updated 01/07/15 Clerk Cody CONTRACT PROVISIONS FOR CONSTRUCTION OF.- CROSSWALK F: CROSSWALK IMPROVEMENTS Federal Aid Project # STPUS-9918(015) March 2016 CITY OF BREMERTON 3456 1h Street, Suite 600 Bremerton, WA 98337 Prepared By: C SKILLINGS CONNOLLY y A. PROJECT ENGINEER CERTIFICATION For Construction of: Crosswalk improvements Federal Aid Project 9 STPUS-8918(0'5) The technical material and data contained in ..this document were prepared under the supervision and direction of the undersigned, whose seal, as a professional engineer licensed to practice as such, is affixed below. Tien Horton, PE Project Manager Date: t-4-1(0 Approved by: To nuckey, PE City Engineer Date: 5 / 1 ,6 TABLE OF CONTENTS I. CONTRACT DOCUMENTS ADVERTISEMENT FOR BIDS....................................................................................... 5 BIDDER'S CHECKLIST................................................................................................ 7 PROPOSALFORM........................................................................................................ 8 PROPOSALBOND........................................................................................................13 STATEMENT OF BIDDER'S QUALIFICATIONS.........................................................14 NON -COLLUSION DECLARATION.............................................................................16 CERTIFICATION FOR FEDERAL -AID CONTRACTS.................................................17 DBE UTILIZATION CERTIFICATION.........................................................................18 DBE UTILIZATION WRITTEN CONFIRMATION.......................................................19 CITY OF BREMERTON - PUBLIC WORKS CONTRACT............................................20 PERFORMANCEBOND...............................................................................................24 PAYMENTBOND..........................................................................................................25 II. GENERAL PROVISIONS III. AMENDMENTS TO THE STANDARD SPECIFICATIONS IV. SPECIAL PROVISIONS V. CONSTRUCTION PLANS (BOUND SEPARATELY) APPENDICES A - FEDERAL AID PROVISIONS FHWA-1273 B -WASHINGTON STATE PREVAILING WAGES C - FEDERAL DAVIS-BACON WAGE DETERMINATION I. CONTRACT DOCUMENTS ADVERTISEMENT FOR BIDS City of Bremerton Crosswalk Improvements RECEIPT OF BIDS: Sealed Bids will be received at the office of the City Clerk of the City of Bremerton, located at 345 6th Street, Bremerton, Washington 98337 until 2:00 p.m. Pacific Time as shown on the wall clock inside the City Clerk's office on June 101, 2016 for the project Bremerton Crosswalk Improvements Project. Bids received after the specified time and date will not be considered. OPENING OF BIDS: The bids will be publicly opened and read after 2:00 p.m. on June 10tH 2016 in the office of the City Clerk at 345 6th Street, Bremerton, Washington 98337. All bid proposals shall be accompanied by a bid proposal deposit in cash, certified check, cashier's check, or surety bond in an amount equal to five percent (5%) of the amount of such bid proposal. Should the successful bidder fail to enter into such contract and furnish satisfactory performance bond .within the time stated in the specifications, the bid proposal deposit shall be forfeited to the City of Bremerton. The following is applicable to federal aid projects: The City of Bremerton in accordance with Title VI of the Civil Rights Act of 1964, 78 Stat. 252, 42 U.S.C. 2000d to 2000d-4 and Title 49, Code of Federal Regulations, Department of Transportation, Subtitle A, Office of the Secretary, Part 21, Nondiscrimination in Federally Assisted Programs of the Department of Transportation issued pursuant to such Act, hereby notifies all bidders that it will affirmatively ensure that in any contract entered into pursuant to this advertisement, disadvantaged business enterprises as defined at 49 CFR Part 26 will be afforded full opportunity to submit bids in response to this invitation and will not be discriminated against on the grounds of race, color, national origin, or sex in consideration for an award. PROJECT DESCRIPTION: This project consists of safety improvements and bringing each intersection into compliance with current ADA standards for five intersections at Kitsap Way & Harlow Drive, Kitsap Way & 11 th Street, 11 th Street & High Avenue, SR 304 & 1St Street, and 6th Avenue & High Avenue. The work includes, but is not limited to: pavement and sidewalk removal, cement concrete curb, gutter and sidewalk, curb ramps, pedestrian signal systems, a HAWK signal system, a rectangular rapid flashing beacon (RRFB) system, traffic control, and all other work all in accordance with the Contract Plans, Provisions, and the 2016 WSDOT Standard Specifications for Road, Bridge, and Municipal Construction. Time for completion of this project is 60 Working Days. The Engineer's base estimate is approximately $550,000 to $610,000. A Disadvantaged Business Enterprise (DBE) mandatory goal of 14% has been established for this project. The 14% mandatory goal applies to all work on the project. Crosswalk Improvements Contract Uocwnents City of Bremerton, Washingion 5 Skillings Connolly, lac Federal Aid # STPUS-9918(1115) March 2016 PREVIEWING CONTRACT DOCUMENTS: Contract Documents may be previewed on printer ARC (formerly known as Reprographics Northwest) website (www.e-arc.com). Go to http://www.e-arc.com/wa/seattle, click on the `Public Planroom' tab and scroll down to find the project. PURCHASING CONTRACT DOCUMENTS: The Contract Documents may be ordered from ARC. Payment is typically cost of reproduction (non-refundable). Contact ARC Bid Services: 1(206) 622-6000; FAX (206) 622-6712; E-mail: seattle.bid.servicesCaD-e-arc.com. Bid documents will be available beginning May 2011, 2016. PROPOSALS: All bid proposals must be made on the blank forms furnished in the Contract Documents. Sealed envelopes containing bids shall be entitled: Bremerton Crosswalk Improvements Project. PRE-BID CONFERENCE: Prospective bidders are strongly encouraged to attend the pre-bid conference conducted by the City which will include a walk-through of the project site. The objective of the pre-bid conference is to acquaint bidders with the work and conditions of the site. The pre-bid conference will begin at 9:00 a.m. on Tuesday, June 7th, 2016, at City of Bremerton Public Works and Utilities offices located at 3027 Olympus Drive, Bremerton, WA 98310. The meeting will be in the large conference room on the 2nd floor, followed by a walk-through. PROJECT COMMUNICATION: All communications related to the project shall be directed to the City prior to opening of Bids: Communication byphone/fax: Gus Garcia Telephone: (360) 473-2317 Fax: (360) 473-5398 E-mail: gus.garcia@ci.bremerton.wa.us Communication by mail: Department of Public Works and Utilities Engineering Division 3027 Olympus Drive Bremerton, WA 98310 ATTN: Gus Garcia CITY'S RIGHTS RESERVED: The City of Bremerton reserves the right to reject any and all bids on any or all schedules or alternates or to waive any informalities in the bidding and shall determine which bid or bidders is the most satisfactory and responsible bidder and shall be the sole judge thereof. No plea of mistake in the bid shall be available to the bidder for the recovery of his/her deposit or as a defense to any action based upon the neglect or refusal to execute a contract. The City of Bremerton is an Equal Opportunity Employer and hereby notifies all bidders that it will affirmatively ensure that in any contract entered into pursuant to this advertisement, disadvantaged business enterprises will be afforded full opportunity to submit bids in response to this invitation and will not be discriminated against on the grounds of race, color, sex, or national origin in consideration for an award. Crosswalk Improvements Contract Documents City of Bremerton, Washington 6 Skillings Connolly, Inc Federal Aid # STPUS-9918(015) March 2016 BIDDER'S CHECKLIST Bidder must execute and return with submittal: PROPOSAL FORM -The unit prices bid must be shown in the space provided. The proposal shall be filled in and signed by the bidder. All addenda must be acknowledaed. J2. BID PROPOSAL BOND 113. STATEMENT OF BIDDERS QUALIFICATIONS v 4. NON -COLLUSION DECLARATION 5. CERTIFICATION FOR FEDERAL AID CONTRACTS 46. DISADVANTAGED BUSINESS ENTERPRISE UTILIZATION CERTIFICATION AND J INSTRUCTIONS DISADVANTAGED BUSINESS ENTERPRISE UTILIZATION WRITTEN CONFIRMATION After the Contract is awarded, execute: 1. CITY OF BREMERTON — PUBLIC WORKS CONTRACT 2. PERFORMANCE BOND 3. PAYMENT BOND Crosswalk Improvements Contract Documents CitygfBremerton, Washington 7 Skillings Connolly, Inc. Federal Aid #STPUS.9918(015) March 2016 PROPOSAL FORM Bidder: Massana Construction Inc. Address: 4810 Pt. Fosdick Dr. SIE 237 Gig Harbor, WA 98335 Date: 6/10/16 TO: CITY OF BREMERTON ADDRESS: 345 Wh Street, Suite 600 Bremerton, WA 98337 PROJECT, Crosswalk Improvements The undersigned hereby certiy(iss) that he/they have personally examined the location and construction details of work as outlined on the plans and specifications for Crosswalk Improvements and have read and thoroughly understand the plans and specifications and contract governing the work embraced in this improvement and the method by which payment will be made for said work and hereby propose to undertake and complete the work embraced in this Improvement in accordance with said plans, specifications, and contract at the attached schedule of rates and unit prices. Unit prices for all items. all extension and total amount of bid must be shown in ink or typed ADDENDA Receipt of Addenda numbers 1 through 1 is hereby acknowledged. Cromwalklmprowmenu Contract Docements City of Brememn. Washington 8 Afflings Connolly, Inc. Federal Aid 0STPUS-4918(OIS) March 2016 Proposal form per Addendum #I, onJinal proposal f6mi was deleted. PROPOSAL FORM (Continued) NOTE: Unit prices for all Items. all extensions and total amount of bid must be shown. Show unit prices in both words and figures and where conflict occurs the written or typed words shall prevail. Include sales tax an d appropriate bid Items. DOR Rule 171 applies. . lE�iil vpbl�t! Pilad, � . PREPARATION 100 MOBILIZATION 1 LS. 3z, (p El 2 te00 WATER LINES 1.00 RESETTING EXISTING HYDRANTS EAdi--._.._...._._......___..-._.._.... __......._ _ _ t5C) 15od o0 EROSION CONTROL AW PLANTING 11.00 INLET PROTECTION 3 EACH So, o0 750 ov 1. EROSIONANATER POLLUTION CONTROL ti 1,250 00 i 1,360 00 �� 620.00 CEMENT CONC. TRAFFIC CURB AND GUTTER 100 TRAFFIC SIGNAL SYSTEM MODIFICATIONS. KITSAP WAY 111TH lei Ls. Ell] El 1.00 TRAFFIC SIGNAL SYSTEM MODIFICATIONS. I1TH ST I HIGH AVE � Z o0o O o 0 1.00 RRFB SIGNAL SYSTEM COMPLETE, SR304 I 119 ST s Ell Zq�O H Croavc/k &vMvfMXnU Cmmoa Dwwwo aygrBM r1ft Wvarl►lV- P sun rm- dr. FftWd A1d t SIPM1V18IO/J) MANN 2016 PROPOSAL FORM (Continued) E1.00 RRFB SIGNAL SYSTEM COMPLETE, KITSAP WAY / HARLOW c LS. 38, o00 �ooa 100.00 CEMENT CONC. TRAFFIC CURB 11 LF. "75. oo ryeo El a1a00 12 CEMENTCONC PEDESTRUWCURB Fo-1E a. ..... .. ......... ._._ 88.00 PAINT LINE 380.00 PLASTIC CROSSWALK LINE H is, IE 5 100 40.00 PLASTIC STOP LINE Fqo I H I El El 0.40 RAISED PAVEMENT MARKER TYPE 1 Fal1 000. $OO, 0.10 RAISED PAVEMENT MARKER TYPE 2 17 HUND 5000, 1.00 PERMANENT SIGNING 18 �Op El 1.00 PROJECT TEMPORARY TRAFFIC CONTROL 18 oe o Qcoo 90000 40.00 PLASTIC YIELD LINE SYMBOL � eAc�•I 5 5 , o o � ,ZOO OTHER REUS 1.00 FIELD ADJUST RAMPS $2,500 .DO 12,800 .00 EST. _.........---...._..... _...._ .__..._... ____._._ ___.�_...._..----• --- cmnwnithop vwmm u C Doctmrm� CAW 9I&eBarnon. Wmhlvron • 10 SIdQh�gt Cwvial0t, /aa Fc&ndAld#W A4-9918(0/5) Advch70/6 PROPOSAL FORM 8. CEMENT CONIC. CURB RAMP TYPE PARALLEL A 9000 °O 2aa0 °O 5.00 CEMENT CONC. CURB RAMP TYPE PERPENDICULAR oey 29 ��, _...- ._...._...----...__...._..._____-_____.�____._..___._ 9�• °D 45000 400 CEMENT OONC. CURB RAMP TYPE COMBINATION 24 EACH 9000. O° 000 � , 7.00 RESOLUTION OF UTILITY CONFLICTS � EST. 52,600 AO 52,600 .00 6.00 ADJUST CATCH BASIN EACH 500 t.00 ADJUST VALVE BOX n PJLCH 250 °� 250 `� 1.00 ROADWAY SURVEYING � ao ee 298.00 CEMENT CONIC. SIDEWALK [Ell S.Y. --------.... _.--_____ �_._.___ _ ___ _..80 18880 1.Q0 ROADSIDE CLEANUP � EST. • - - --.---.. _. __--- 56,000 .00 Sa,000 .00 i. MINOR CHANGE 97 EST. [;;Goo ,o0 513,000 .00 1. SPCC PLAN 00 93 L.S. ?j000, s0 80, cea f#r s ware+�o+aao�, 9enism� aoee+�eer m�o� c�rro � Gmnara.L -.... �g� _ y55. g CmmmfklnWmmmu CwWwDwommu City ofB_nvn. WarNWM 17 su tv CWWRK Im. fedwalAddBSTPiL 491givii) tdmL*201d PROPOSAL FORM (Continued) IF SOLE PROPRIETOR OR PARTNERSHIP IN WITNESS hereto, the undersigned has set his (its) hand this day of . 2016. Signature of Bidder Title IF CORPORATION IN WITNESS WHEREOF, the undersigned corporation has caused this instrument to be executed and its seal affixed by its duly authorized officers this 10 day of 'June . 2016. Massana Construction Inc. �mwt Name of Corporation . �5 Ul By Michael Keyser RA Secretary Sworn to before me this day of _� 1 C A N e 2016. 011111100 VAL l Jul t iJ S pNN P �.0 ��`�V •essichi •••.` ��, Notary Public id and for the State of Washington residing -I 0 Oar boo W A = * = PUBLIC dw NOTE: > .moves NA *-N 1. If the Bidder is a co -partnership, so state, giving the name under which business is transacted. 2. If the Bidder is a corporation, this proposal must be executed by the duly authorized officials and notarized. Crosswalk Improvements Contract Documents Chy of Bremerton. Washington 12 Skulings Connolly, Inc. Federal Aid # STPUS-9918(013) March 2016 STATEMENT OF BIDDER'S QUALIFICATIONS Name of Contractor Massana Construction Inc. Address 4810 Pt. Fosdick Dr. PMB 237. Gig Harbor, WA 98335 Telephone and Contact Person for this Bid Michael Keyser - 253-250-9832 Number of years the contractor has been engaged in the construction business under the present firm name indicated: 15 Gross dollar amount bf work under contract: $ 65,000,000.00 Gross dollar amount of contracts not completed: $ 34,000,000.00 Type of work generally performed by Contractor. Heavy Civil Work List of five projects of a similar size and nature that have been completed by the contractor within the last ten years including the project name, year of construction, contracting agency, contract phone number and the gross dollar amount of each project: Project Name Construction Agency Name Contact Name DollarAmount Year Owned by contra= and Number Olympic Drive NW Bridge 2014-2015 WSDOT Kim Mueller 870,304 special Repair 253-365-6752 Swantown Marina ABC Docks 2015 Port of Olympia William Helbig 887,106 Rehabilitation 360-528-8000 SR 410/Scatter Creek Seismic 2014.2015 WSDOT Aleta Borscbowa 513,469 Bridge 206-768-5860 AV A 320th Vicinity Noise Wall 2014 WSDOT Aleta Borschowa 16864 Replacement 206-768-5860 West Tiger 8t Granite Creek Trail 2013 WSDNR JefrJohnstone334,000 360.902-1203 List of five major pieces of equipment which are anticipated to be used on this project by the contractor and note which items are owned by the contractor and which are to be leased or rented from others: Dump Truck Owned by contractor Ev avator Owned by contractor Pick up Tracks Owned by contra= Crosswalk Improvement Contract Documents City ofBremerton. Washington 14 Skillings Connolly. Inc. Federal Aid # STPUS-9918(01 J) March 2016 STATEMENT OF )BIDDER'S QUALIFICATIONS (continued) Air Compressor Owned by contractor Small Toole Owned by contractor Bank References: PNC BANK How many general superintendents or other responsible employees in a supervisory position do you have at this time and how long have they been with this contractor? 20 employees - since 2001 Have you changed bonding companies within the last three years? No If so, why? (optional) 4 /A Have you ever been sued by the client on any public works contract for a special district, municipality, county, or state government? No For what reason? t,1 1A Disposition of case, if settled: hl /A Washington State: Department of Labor and Industries Workmen's Compensation Account No.: 020,407-01 Department of Licenses Contractor's Registration No.: MASSACI920RW Employment Security Department Number. 553934-00-0 Excise Tax Registration Number: 602-868-553 IRS Employer Number. 22-3849249 Percentage of work to be performed by General Contractor. 65%. 1UssA-.lA CPassauc.T�a.a �r�c.. BIDER Q. By (signed) INC a geo�arE °ti= ._ AA TITLE .� g A. K) . Crosswalklixpravemenrs Contact Docununts City of areneerton, Washington 15 SkItangs Connolly, Inc. Federal AW # STPUS9918(OM) March 2016 NON -COLLUSION DECLARATION Failure to return this Declaration as part of the bid proposal package will make the bid nonresponsive and Ineligible for award. I, by signing the proposal, hereby declare, under penalty of perjury under the laws of the United States that the following statements are true and correct: 1. That the undersigned person(s), firm, association or corporation has (have) not, either directly or indirectly, entered Into any agreement, participated in any collusion, or otherwise taken any action in restraint of free competitive bidding In connection with the project for which this proposal is submitted. 2. That by signing the signature page of this proposal, I am deemed to have signed . and to have agreed to the provisions of this declaration. To report rigging activities call: NOTICE TO ALL BIDDERS 1-800424.9071 The U.S. Department of Transportation (USDOT) operates the above toll-free °hotline° Monday through Friday, 8:00 a.m. to 5:00 p.m., Eastern Time. Anyone with knowledge of possible bid rigging, bidder collusion, or other fraudulent activities should use the "hotline" to report such activities. The "hotline° is part of USDOT's continuing effort to Identify construction contract fraud and abuse and is operated under the Inspector General. All Information will be treated confidentially and respected. and investigate highway direction of the USDOT caller anonymity will be DOT Form 272 -ORI Rev6ad 0712011 Crosswalk Improvements Contract Doenments Cly of Bremerion. Washington 18 Skulings Connolly, Inc. Federal Aid 0 STPUS 9918(01 S) March 2016 CERTIFICATION FOR FEDERAL -AID CONTRACTS The prospective participant certifies by signing and submitting this bid or proposal, to the best of his or her knowledge and belief, that: (1) No Federal appropriated funds have been paid or will be paid, by or on behalf of the undersigned, to any person for Influencing or attempting to Influence an officer or employee of any Federal agency, a Member of Congress, an officer or employee of Congress, or an employee of a Member of Congress in connection with the awarding of any Federal contract, the making of any Federal grant, the making of any Federal loan, the entering into of any cooperative agreement, and the extension, continuation, renewal, amendment, or modification of any Federal contract, grant, loan or cooperative agreement. ' (2) If any funds other than Federal appropriated funds have been paid or will be paid to any person for influencing or attempting to influence an officer or employee of any Federal agency, a Member of Congress, an officer or employee of Congress, or an employee of a Member of Congress in connection with this Federal contract, grant, loan, or cooperative agreement, the undersigned shall complete and submit Standard Form -LLL, "Disclosure Form to Report Lobbying," in accordance with its instructions. This certification is material representation of the fact upon which reliance was placed when this transaction was made or entered into. Submission of this certification is a arereauisite for makino or enterina into this transaction imposed by Section 1352, Title 31, U.S. Code. Any person who fails to file the required certification shall be subject to a civil penalty of not less than $10,000 and not more than $100,000 for each failure. which exceed $100,000 and that all subreclpients shall certify and disclose accordingly. DOT Form 272.04M RoWnd 071211 Crowvalk Improvements Contact Documents City of Dremerton, Washington 17 SiiliingsConnolly, Inc. Federal Aid # STPUS9918(01 S) March 2016 DBE UTILIZATION CERTIFICATION Local Agency Disadvantaged Business Enterprise Utilization Certification To be eligible for award of this contract the bidder must fill out and submit, as part of Its bid proposal, the following Disadvantaged Business Enterprise Utillzellon Certification relating to Dleadvardaged Business Enterprise (DBE) requirements. The Contracting Agency shall consider as non-responsive and shell reject any bid proposal that does not contain a DBE Cwtification which properly demonstrates that the bidder will meet the DBE participation requirements in one of the manners provided for in the proposed control The Bidder must submit good faith effort documentation gots In rho went the bidder's efforts to solicit sufficient DBE participation has been unsuccessful. The successful bidders Disadvantage Business Enterprise Utilization Certification shall be deemed a part of the resulting contract. Information on certified firms is available from OMWBE online at: hNp://omwba.vm.gov/alrectory-dcoMed•fimm/ ML145 A>~��► wnlST�ucslo �.( 1n1C . certifies that the Disadvantaged Business Enterprise (DBE) r Firtne listed below have been contacted regarding participation on this project. If this bidder Is successful on this project and Is awarded the contract, it shall assure that subcontracts or supply agreements are executed with those firms where an 'Amount to be Applied Towards Goal' Is Usted. (If necessary, use additional sheet) • i rCelAl 010 Witter ---- r - .. .: _. Yf11WIN1 �Ap_ r4raci ... Wrrahearre►:�e�;:' ,�,� irrrrrr ._ CalV ptlon ;Dsoal :o! Worric� - Calrann.4, � . ., ITIC be Applied:: _ Toiil"rardb'Gt�al. t D E eA t, 5 WS eoJr4-"-T E l.ICtWtkl Coo l� .5NRL:S nrd%.S !02 , stns, — 40 2.1 Z1 -2,� 2. 3. 4. 6. 7. 8. 9. 10. Disadvantaged Business Enterprise Subcontracting Goal: `t `/p DBE Total $ 25(p, 5(p,$. •~ Box 2 eox 3 Regular Dealer status must be approved prior to bid submittal by the Ofike of Equal Opportunity, Wash. State Dept. of Transportation, on each emnreat. See the sedlon'Cradhing DBE PaMc4mtlon Toward Meattng the host• In the Contract Documem. The Contracting Agency will ullilze this amount to determine whether or not the bidder has met the goal. In the event of an wflhmetk dlBereme between this total and the sum of the Individual amounts Usted above, than the sum of the amounts noted shall prevell end the total will be revised accordingly. Perk p lion In excess of the goal amount will be considered volurdwy or reos•neutrai portico n. SR 00T Farm 2724MA 1aRD16 Crosswalk hnnprovemencr Contract Document CityojBremerron, Washington 1s SkilABs Connolly. Federal Aid 0 STPUS-9918(015) March 2016 er: Jun. 10. 2016 11:35AM DBE ELECTRIC No. 1804 P. 2 DBE UTILIZATION WRITTEN CONFIRMATION Local Agency Disadvantaged Business Enterprise (DBE) Written Confirmation Document Man au on representative of the Disadvantaged Butiness Enterp se (DBE), I confirm that we have been contacted by the referenced bidder with regarflo the referenced project and 0 the bidder is awarded the contract we will enter Into an agreement with the bidder to participate In the project consistent with the information provided in the bidders DIsadvantaofid Contmet Title. CROSSWALK IMPROVEMENTS - CITY OF BREMI;RTON Sidder's Business Name: A55A+JA ( CjSTi2:v tjnoa %&X-. DBE's Business Name: DBE ELECTRIC DBE's Busurass,Addrese: PO BOX 9169, COVINGTON, WA 98042 DBE Signature; - 090's Title: PREIDENT Date: 6/10/16 The enlAes must be consistent with what is shown on the bk*es Dleedventaged Business Enlerpriee UtNization CerURcatlon. Fal= to do so wig result In bid rejection. See contract provision: Disadvantaged &mutes Enterprise Conditton of Award PartUpagon. Desatptlon of Work; ELWMCAL - TRAFFIC SIGNAL, W-8. & HAWK SIGNAL MMWS Amount to be Applied Towards Goat: $256,565.62 SR DOT t4=0eZW1A t.'nu � /nryurivenranp Cn dAwl Dawmaea t'Iry q(Rkniri�o+a rs'a+hr�ghHr to skumv canaoQr. Inc Fdddrol dht �Sri'US�OO/hlU/fi Aforch Aid CITY OF BREMERTON — PUBLIC WORKS CONTRACT ��} w THIS AGREEMENT is made and entered into this �— day of "e -" O (� by and between the CITY OF BREMERTON ( "the City"), and Massana Construction INC. ("the Contractor"). WITNESS: THEREFORE, in consideration of the terms and conditions in this agreement, the parties covenant and agree as follows: 1. The Contractor shall do all work and furnish all tools, materials, and equipment for construction and completion of the Bremerton Crosswalks Improvements project, located at various locations , Bremerton, Washington, as set forth in the plans and specifications on file in the Public Works Director's office, 345 6th Street, Suite 600, Bremerton, WA, 98337, which are hereby incorporated into this contract by reference, and the Contractor shall further perform any alterations in or additions to the work in accordance with the contract documents. The Contractor shall provide and bear the expense of all equipment, work and labor that may be required for the transferring of materials, construction, and completion of the work provided for in this contract, except as expressly provided in the specifications to be furnished by the City. 2. The Contractor agrees to secure all necessary City and State permits, and a City of Bremerton business license. The Contractor further agrees to file with the City Finance Director a performance bond in the amount of $ 688,455.00 , that shall provide for the completion of this Contract pursuant to the following specified conditions in addition to the plans and specifications above-mentioned: a. The Contractor shall commence construction of the project on or before , and shall complete construction of the project within 60 working days from the date of execution of the contract. The Contractor agrees to pay the City liquidated damages Of $ 1,721.14 per day for each day the work is not completed beyond the date set forth in this contract. It is further agreed that the City shall deduct the amount of any applicable liquidated damages from the final payment to the Contractor. b. The construction shall be completed in accordance with the provisions of all applicable ordinances, statutes, and regulations of the City, State, and Federal Governments, including the payment of "prevailing wage." The Contractor and all Sub -Contractors who work on the project shall provide to the City forms approved by the State Department of Labor and Industries certifying that prevailing wages have been paid to Contractor's and Sub -Contractor's employees as required. Crosswalk Improvements Contract Documents Citv of Bremerton. Washington 20 Skillings Connollv, Inc. Federal Ail # STPUS-9918/015% Afarch 2016 c. The job site shall be posted at all times "DO NOT ENTER," and at no time shall material or equipment�be allowed to block a public right-of-way. The work area shall be cleaned at the end of each work day, with no material stored or left in the way of City work crews. The City will agree to coordinate with the Contractor the moving of City vehicles so as not to be in the way of the Contractor. d. The Contractor shall not discriminate against any employee or applicant for employment because of race, creed, national origin, gender, physical or mental handicap, or age. The Contractor shall, in all solicitations for employees, or job orders for employees placed with any employment agency, union, or other firm or agency, state that all qualified applicants will receive consideration for employment without regard to race, creed, national origin, gender, physical or mental handicap, or age. The Contractor shall include the provisions of this section in every sub -contract or purchase order for goods or services which are the subject matter of this contract. If the Contractor fails to comply with any non-discrimination provision of this contract, the City has the right to cancel the contract in whole or in part. If the contract is canceled after partial performance, the City shall pay fair market value or the contract price, whichever is lower, for goods and services which have been received and accepted. e. For contracts of twenty-five thousand dollars or less, at the option of the contractor the City shall, in lieu of bond, retain fifty percent of the contract amount for a period of thirty days after the date of final acceptance, or until receipt of all necessary releases from the department of revenue and the department of labor and industries and settlement of any liens filed against the project. f. If work to be performed is within a public right-of-way, the Contractor shall be required to notify all adjacent property owners of the project prior to the beginning of construction of the project. g. The Contractor shall utilize the Federal E -Verify program to verify that each employee of the Contractor and any Sub -Contractor who works on this project is legally authorized to be employed in the United States. Before a notice to proceed shall be issued by the City, the Contractor shall provide the City with a certification that the Contractor has enrolled in and implemented the E -Verify program to determine the employment eligibility of the employees who will perform work on behalf of the Contractor. Any Sub -Contractor must also provide a certification that the Contractor has enrolled in and implemented the E -Verify program to determine the employment eligibility of the employees who will perform work on behalf of the Contractor. 3. A. No liability shall attach to the City by reason of entering into this contract, except as expressly provided in the contract. The Contractor shall defend, indemnify and hold the City, its officers, officials, employees and volunteers harmless from any and all claims, injuries, damages, losses or suits including attorney fees, arising out of or in connection with the performance of this Agreement, except for injuries and damages arising out of or in connection with the performance of this Agreement, except for injuries and damages caused by the sole negligence of the City. B. Should a court of competent jurisdiction determine that this Agreement is subject to RCW 4.24.115, then, in the event of liability for damages arising out of bodily injury to persons or damages to property caused by or resulting from the concurrent negligence of the Contractor and the City, its officers, officials, employees, and volunteers, the Contractor's liability hereunder Crosswalk Improvements Contract Documents Citv of Bremerton, Washington 21 Skillings COnn)n011V, hu•. Fez oral Aid 4 STPUS-9918('015) tifarcln 2016 shall be only to the extent of the Contractor's negligence. It is further specifically and expressly understood that the indemnification provided herein constitutes the Contractor's waiver of immunity under Industrial Insurance, Title 51 RCW, solely for the purposes of this indemnification. This waiver has been mutually negotiated by the parties. The provisions of this section shall survive the expiration or termination of this Agreement. 4. A. Contractor shall maintain the following insurance limits: 1. Automobile Liability insurance with a minimum combined single limit for bodily injury and property damage of $1,000,000 per accident; 2. Commercial General Liability insurance shall be written with limits no less than $1,000,000 each occurrence, $2,000,000 general aggregate and a $2,000,000 products -completed operations aggregate limit. 3. Worker's Compensation coverage as required by the Industrial Insurance Laws of the State of Washington. B. The Contractor's insurance coverage shall be primary insurance as respect the City. Any Insurance, self-insurance, or insurance pool coverage maintained by the City shall be excess of the Contractor's insurance and shall not contribute with it. C. The Contractor's insurance shall be endorsed tostate that coverage shall not be canceled by either party, except"'after thirty (30) days ,prior written notice by certified mail, return receipt requested, has been given to the City. D. Contractor shall furnish the City with original certificates and a copy of the amendatory endorsements, including but not necessarily limited to the additional insured endorsement, evidencing the insurance requirements of the Contractor before the commencement of the work. E. All of the provisions set forth in Section 4,. Subsections A— D, shall also apply to any and all Sub -Contractors who work on the project. 5. The parties agree that the Contractor engages in said work as an independent contractor. Nothing contained in this agreement shall be construed as making the Contractor the agent to the City for any purpose or as authorizing or empowering the Contractor to obligate or bind the City in any manner. 6. The Contractor for itself and for its heirs, executors, administrators, successors, or assignees, does agree to fully perform all the Contractor's covenants contained in this agreement. 7. The City agrees that upon completion of the terms and conditions of this Contract by the Contractor, and acceptance of the completed project by the City Council, the City will pay to the Contractor the sum of $ 6Rg,455_oo (six hundred eighty-eight thousand four hundred fifty-five Dollars), which amount shall not include sales tax. The City further agrees to release the Contractor's performance bond upon acceptance of the completed project by the City Council, on the day following the Crosswalk Improvements Contract Documents City of Bremerton, Washtttgton 22 Skillings Connolly, Inc Federal Aid # STPUS-9913(015) Alarclt 2016 next regularly scheduled City Council meeting following the completion of the project and submission of all necessary documents required by law and this Contract. r�bkSSCon,;_ Contractor By: M 0--5-, V—\ Title:re.s;�e,.�'� CITY OF BREMERTON ByAr/Z'7/,?,09Z 1,6 (J*afty ent — Mayor ATTEST: By -C�ehffisen Piireetoof Financial s aArtn4vi (err, Crosswalk Improvements Contract Documents Citv of Bremerton, Washington 23 Skillings Connolly, Inc. Federal And # STPUS-9918(015) March 2016 II. GENERAL PROVISIONS PURPOSE The purpose of the City of Bremerton Design and Construction Standards is to provide a consistent framework under which physical aspects of design and construction will be implemented. Most of the elements contained in this document are Public Works oriented and are related to the development or platting process; however it is intended that they apply to both public and private work. These standards cannot apply for all situations. They are not intended to substitute for good technical practices and competent design work. It is expected that the design professional will bring the best of skills from their respective disciplines. These standards also include standard plans which are to be used in conjunction with design activities. 1-10 SHORTEN DESIGNATION: These City of Bremerton Design and Construction Standards shall be cited routinely in the text as the "Standards". 1-20 REFERENCES: The Standards are intended to be consistent with the most currently adopted provisions of: 1-20.1 Bremerton Municipal Code (BMC), including all pertinent ordinances 1-20.2 State of Washington Shoreline Management Act 1-20.3 State and National Environmental Policy Acts 1-20.4 City Design Standards 1-20.5 Washington State Department of Transportation 1-20.6 Uniform Building Code 1-20.7 A Policy on Geometric Design of Highways and Streets, AASHTO. 1-30 STANDARD SPECIFICATIONS: Except where the Standards provide otherwise, design detail, workmanship and materials shall be in accordance with the current edition of the "Standard Specifications for Road, Bridge, and Municipal Construction" (APWA Specification) prepared by the Washington State Chapter of the American Public Works Association and the Washington State Department of Transportation. 1-40 OTHER SPECIFICATIONS: The following shall be applicable when pertinent, when specifically cited in the Standards, or when required by higher funding authority: 1-1 1-40.1 U.S. Department of Transportation Manual of Uniform Traffic Control Devices (MUTCD), as amended and approved by Washington State Department of Transportation. 1-40.2 Rules and regulations of the State Board of Health regarding public water systems, as published by the State Department of Social and Health Services. 1-45 PERMITS: Permits and approvals are required prior to any construction or demolition work in the public right-of-way. Much work done under these Standards will require multiple permits such as water, sanitary or storm sewer work in addition to the right- of-way permit. Questions should be directed to the City Engineer's Office. An approved copy of the right-of-way permit together with a set of approved plans and specifications shall be available on the job site whenev er work is being done on any portion of the project. 1-50 MODIFICATIONS AND UTILITIES: Modifications from these Standards may be granted by the Public Works Director upon evidence that such modifications are in the public interest, that they are based upon sound engineering practices, and that requirements for safety, function, appearance, maintainability, and durability are fully met. Desired modifications must be submitted in writing and approved in writing prior to construction. 1-60 GUARANTEES: Performance and Warranty Guarantees will be required for all public works improvements, unless waived by the Director. Acceptable methods of guarantees will be as follows: 1. Cash deposit 2. Assignment of Savings Account 3. Letter of credit 4. Bond Standard documents as approved by the City for the above items are available from the City Engineer. 1-60.1.1 Performance Guarantees will be required for all public works improvements as detailed on the approved plans, unless conditions are met as noted below: STREET/ALLEY, SIDEWALK: Estimated cost plus 20% QB for a plat, construct all improvements prior to final plat approval. UTILITIES: Estimated cost plus 20% OR construct improvements prior to occupancy QB for a plat, construct prior to final plat approval. 1-2 1-60.1.2 The initial guarantee and subsequent extensions as approved will be limited to one (1) year increments. If time extensions are approved, the guarantee amount shall be revised to reflect inflation and/or other cost impacts. 1-60.1.3 The developer shall provide an estimate of the improvements based on the approved plans, prepared by an Engineer licensed in Washington. 1-60.1.4 The estimate shall be itemized by description, quantities and costs. The submitted data will be reviewed by City Engineer for adequacy of quantities and comprehensiveness of estimates. The estimate shall be reviewed to reflect the City's cost to complete the improvements. 1-60.2.1 Warranty guarantees will be required at the time of final acceptance of the improvements. The Warranty Guarantee amount will be ten percent (10%) of the Performance Guarantee amount or of the documented final cost of the improvements. The Warranty Guarantee is required prior to release of the Performance Guarantee. 1-60.2.2 Methods of posting Warranty Guarantee shall be the same as for Performance Guarantee and shall be for a period of one year. 1-70 AS-RUILTS: Upon completion of work on all projects the "Original" approved plan shall be revised to reflect as -built conditions by the developer's or contractor's engineer and submitted to the City Engineer for permanent records. The "as-builts" shall be submitted in an electronic form and on 24" x 36". The submission of "as-builts" shall be considered part of the performance required to complete a project. The Certificate of Occupancy and the Performance Guarantee as noted in Section 1.60.1 will be retained by the City until this requirement is met. 1-80 PLANS: Work involving the design of street improvements, drainage, water and sewer improvements must be stamped by a registered Civil Engineer licensed in the State of Washington. Any structural work must be stamped by a structural engineer licensed in the State of Washington. The Engineering Division has established these basic standards so plan checking can be processed efficiently. Plans must meet the following standards before they will be accepted. 1-80.1 Type and Size of Paper for Plans: The minimum acceptable size is to be 24" X 36". Plans submitted must be drawn on polyester drafting film or vellum. 90000pren. - . a.I 1-3 1-80.2(1) All plans are to be drawn utilizing an engineer's scale. 1-80.2(2) The minimum acceptable scale for public works improvement plans shall be 1" = 40' for plan view (horizontal) and 1" = 5' for profile view (vertical). In cases when the horizontal scale is enlarged, the vertical scale shall also be enlarged. A larger scale may be required if the plans are crowded, cluttered or hard to read. On small projects, it shall be expected that the scale will be enlarged to adequately utilize the full plan sheet. 1-80.3 Required Plan Sheets: The following plans for public works improvements shall be prepared: 1-80.3(1) Erosion control and grading plan (during and after construction). 1-80.3(2) Street improvements (including frontage improvements & street trees). 1-80.3(3) Storm drain or drainage plan (drainage and street plans may be combined when approved by the City Engineer). 1-80.3(4) Sanitary sewer plan. 1-80.3(5) Water system plan 1-80.3(6) Traffic Control. 1-80.3(7) Street Lights & Traffic Lights. NOTE: Cross-section sheets may be required for plan checking. 1-80.4(1) All public works plans for street improvements and utility systems shall be prepared in a plan/profile format either with sheets printed in half plan and half profile or with separate sheets for plan and profile views. 1-80.4(2) Plans shall be prepared with all utilities, both new and existing, shown on all sets of plans. For example, on the sanitary sewer sets, the water and storm drains shall be shown with the sanitary sewer portions being heavily highlighted. Other utilities are also to be shown in profile views where crossings occur. 1-80.4(3) Whenever possible, use notes specifying City Standards numbers for common items such as catch basins, restrictors, fire hydrant assemblies, etc. 1-80.4(4) Provide signature block on all public works plans for City Engineer's approval. 1-4 1-80.4(5) Show complete data for curb radii, utility locations (new and existing), curb elevations, street stationing, street widths, existing adjacent improvements, elevations of existing street improvements and utilities, etc. 1-80.4(6) All elevations and grades on public works plans shall be to Bremerton City datum available from the Public Works and Utilities Department, Engineering Division. 1-80.4(7) At the back of this Section is a plan preparation checklist which includes many items that are to be noted on all plans as applicable. A copy of the checklist with all applicable items for each plan sheet "checked" as addressed by the designer is to be turned in with all plan submittals for plan checking to Engineering. Additional copies of the checklist are available from Engineering as needed. 1-80.4(8) A summary of quantities for all work within the public right-of-way or in easements granted to the City shall be listed on the title sheet or on the first sheet of all plans or sets of plans. The following list can be used as a guideline for the items to be listed but is to be supplemented as necessary for a particular project: 1-90 TRAFFIC CONTROL PLAN: Traffic control plans shall be submitted with the permit application for all construction projects which impact any public roadway including but not limited to lane closures, detours, slow-moving vehicles or actual construction within the right-of-way such as trenching, paving, etc. 1-5 ITEM ABBREVIATION 1-80.4(8)A Asphalt concrete pavement (roadway) Ton 1-80.4(8)B Cement concrete pavement (roadway) S.Y. 1-80.4(8)C Asphalt concrete pavement (alley) Ton 1-80.4(8)D Cement concrete pavement (alley) S.Y. 1-80.4(8)E Curb and gutter L.F. 1-80.4(8)F Concrete sidewalk S.F. 1-80.4(8)G Concrete driveway approaches S.F. 1-80.4(8)H Water main (size) L.F. 1-80.4(8)1 Gate valves (size) Ea. 1-80.4(8)J Butterfly valves (size) Ea. 1-80.4(8)K Sewer main (size) L.F. 1-80.4(8)L Side sewer (size) L.F. 1-80.4(8)M Sewer manholes (type) Ea. 1-80.4(8)N Drain pipe (size) L.F. 1-80.4(8)0 Catch basins (type) Ea. 1-80.4(8)P Traffic regulatory signs (type) Ea. 1-80.4(8)Q Street name signs Ea. 1-80.4(8)R Fire hydrant assemblies Ea. 1-80.4(8)S Water main blow -offs Ea. 1-80.4(8)T Streetscape Trees (species & sizes) Ea. 1-90 TRAFFIC CONTROL PLAN: Traffic control plans shall be submitted with the permit application for all construction projects which impact any public roadway including but not limited to lane closures, detours, slow-moving vehicles or actual construction within the right-of-way such as trenching, paving, etc. 1-5 1-100 CONSTRUCTION SCHEDULE: A schedule of construction activities shall be submitted prior to issuance of a permit. 1-110 INSPECTION: 1-110.1 Materials - Sampling and Testing: Compaction tests, material sampling and testing shall be required at the discretion of the City Engineer. When required, all testing shall be performed by a testing laboratory certified in the State of Washington. Copies of all test reports shall be furnished to the City Engineer. All costs incurred for testing or sampling as required shall be the responsibility of the contractor or developer. 1-110.2 Materials -Submittals_ Submittals shall be submitted to the City Engineer with substantial proof that all materials used in construction conform to all applicable Standards. 1-110.3 Compaction Tests: Compaction tests will be required at the discretion of the City Engineer on all construction work within the right-of-way. 1-110.4 Line and Grade: Surveying as required to construct a given project per the approved plans shall be furnished by the developer or contractor at no expense to the City. It is required that survey stakes be set for new curb and gutter construction, for both horizontal and vertical control. 1-110.5 Controlled Density Backfill: The City Engineer may require controlled density backfill in lieu of native or granular backfill. Controlled Density Backfill shall meet the WSDOT/AASHTO specifications. 1-120.1 Laws to be Observed: The contractor, applicant and owner, at all times shall comply with all Federal and State laws, local laws and ordinances, and any regulations which in any manner affect the project. The contractor, applicant and owner, shall release, indemnify and promise to defend and save harmless the City, its officers, employees and agents from and against any and all liability, loss, damage, expense, actions, and claims, including costs and reasonable attorneys fees incurred by the City in defense thereof, asserting or arising directly or indirectly on account of any violation of the laws, ordinances or regulations whether such violations are by the contractor, his subcontractors, his employees, or his agents. 1-120.2 Protection and Restoration of PropeU: The contractor shall protect and preserve from damage, interference and destruction all private and public property on or in the vicinity of the work. If such property is damaged or destroyed or its use interfered with by the contractor or his agents, it shall be restored immediately to its former condition by the contractor at his expense and such interference terminated. The contractor shall protect all surveying monuments and property corner markers. 1-120.3 Utilities and Similar Facilities: 1-6 1-120.3(1) The contractor shall protect from damage private and public utilities, including telephone and telegraph lines, power lines, sewer and water lines, railroad tracks and appurtenances, highway lighting and signal systems, and similar facilities. 1-120.3(2) It is the contractor's responsibility to contact the local underground utilities "one -call" number 48 hours in advance of any construction which requires excavation. The one -call number is 1-800-424-5555. RCW Chap. 19.122. 1-120.4 Traffic Control at Construction Site: Approved traffic control shall be established for all construction projects which impact any public roadway including but not limited to lane closures, detours, slow moving vehicles and actual construction within the right-of-way. See Section 1-9. 1-120.5 Detours and Road Closures: Approval must be received from the City Engineer and Police Department for all detours and road closures. See Section 1-90. 1-120.6 Flagmen, Barricades and Signs: Flaggers, barricades, signs and traffic control shall conform to the Standards established in the latest approved edition of the MUTCD. See Sec. 1-90. All equipment and materials required for traffic control shall be furnished, installed 'and maintained by the contractor to the satisfaction of the City Engineer. 1-120.7 Inspection: 1-120.7(1) Work performed within the public right-of-way, whether by or for a private developer, by City forces, or by a City contractor, shall be done to the satisfaction of the City Engineer and in accordance with approved plans and Standards. Unless otherwise approved, any subsequent modifications to approved plans must be approved in writing by the Director before being implemented. 1-120.7(2) It is the responsibility of the developer, contractor or their agents to notify the City in advance of the commencement of any work and to have all work inspected as construction progresses. Advance notification of at least 24 hours is required for scheduling of inspections. Timely notification by the contractor is essential for the City to verify the work meets the standards. Failure to notify the City of construction inspection may result in additional and more complex testing and certification of proper construction standards. The City may prohibit or limit further work until all inspections and corrections have been made to the satisfaction of the City Engineer. All costs associated with additional inspection procedures shall be borne by the contractor. 1-120.7(3) A preconstruction conference and/or field review may be required before the start of any work on major projects as determined by the City Engineer. 1-120.8 Site Maintenance: 1-7 1-120.8(1) The developer and contractor shall schedule and control his work so as to prevent hazards to public safety, health and welfare. 1-120.8(2) Streets shall be kept free of dirt and debris on a continuous basis. 1-120.8(3) Pedestrian facilities shall be kept free of obstructions, and continuity shall be maintained at all times unless otherwise approved by the Engineering Department. 1-120.8(4) On existing streets, two-way traffic shall be maintained at all times unless detour plans have been approved in advance by the City Engineer. 1-120.8(5) Pedestrian and vehicular access to occupied buildings shall be maintained at all times except where approval from the building owner has been obtained. 1-120.9(1) wired Plans and Purim: A temporary erosion/ sedimentation plan is required for the following land alteration activities: on all developments with slopes 15% or greater; or where cut and/or fill slopes 15% or greater will be created by the proposed work. The plan shall clearly indicate the construction sequence for establishment of all erosion control work both temporary and permanent and shall be a separate drawing. The following are the minimum notes required on all temporary erosion/sedimentation control plans: 1-120.9(1)A The temporary erosion control system shall be installed prior to all other construction. 1-120.9(1)B Where possible, maintain natural vegetation for silt control. 1-120.9(1)C As construction progresses and seasonal conditions dictate, the erosion control facilities shall be maintained and/or altered as required by the City Engineer to insure continuing erosion/sedimentation control. 1-120.9(1)D Temporary siltation ponds and all temporary siltation controls shall be maintained in a satisfactory condition until clearing and/or construction is completed, permanent drainage facilities are operational, and the potential for erosion has passed. 1-120.9(1)E All disturbed land areas left for 30 days or more shall be seeded with a mix and by a method approved by the City Engineer and maintained until seed germination is assured. 1-120.9(1)F Approval of this plan does not constitute an approval of design, size, nor 1-8 location of pipes, restrictors, or detention facilities; but is an approval of grading and sedimentation control plan only. 1-120.9(1)G The public right-of-way shall be kept clean. Tracking of mud and debris from the site onto the public right-of-way will not be allowed. Failure to comply with this condition will result in all work on the site being stopped. 1-120.9(1)H Cleanup and Restoration. The following procedures shall be followed in cleaning and restoring the construction site: 1. Street shall be swept each day. 2. Disturbed soils shall be final graded, seeded and mulched; or sodded after the installation of the utility. 3. Ditches shall be seeded, jute matted, netted, sodded, or rock lined to control erosion. 4. Any debris including rocks, cobbles, dirt and silt of downstream drainage facilities, whether ditches or pipe and catch basins, which results from the construction, shall be cleaned out and the work restored to a stable condition as a part of site cleanup each day. 1. Plot Plan Showing: Dimensions North arrow Scale (engineering, not architectural) Street name(s) Right-of-way width(s) (show both sides from centerline) Property lines Building location (distances to lot lines) Driveway location (both proposed and existing and distances from lot lines or corner for each) Easements (type and width) Spot elevations at: Each property corner Finish grade (at building corners) Finish floor Top of curb (at property lines) Each edge of driveway (at property line) Cross-section view (may show some of the above) Parking (proposed traffic flow at entrance and exit) Address and/or assessor's tax lot number Short plat (location of all housing planned) Flood plain data (if applicable) 2. Sanitary Sewer Plan Showing: 1-9 Sewer line locations (show relationship to water lines) Sewer line sizes, material, and class of material Sewer line slopes Building location Elevations at: Building line Changes in line or grade Property line Public Sewer Appurtenances, such as cleanouts and back water valves 3. Storm Sewer Plans Showing: Storm drainage calculation Storm line locations Storm line sizes Storm line slopes Downspout locations Catch basin locations Detention/retention details Elevations at: Catch basins Top of grate Invert elev. Property line Public sewer Area of impervious surface Drainage pattern of impervious surface Oil separators detailed drawing (if required) Connection to public system Location and size of public system Other required best management practices (BMP) 4. Curb, Gutter and Sidewalk Plans Showing: Property lines Street centerline Sidewalk width and location (thickness as per specs.) Driveway width, location and grade (thickness as per specifications) Curb height, slope Gutter width, thickness Wheelchair ramps, location Expansion joints Catch basin locations Spot elevations at: Point of curve (on curb) Point of tangency (on curb) 1-10 Top of curb at property lines Front and back edges of sidewalk at property lines and grade breaks Details on any retaining walls at right-of-way lines Topography of opposite side of roadway 5. Lighting Plan A lighting plan shall be submitted in accordance with City lighting standards. 6. Traffic Plan A traffic plan shall be submitted in accordance with the MUTCD. DIVISION 2. EARTHWORK 2-10 METHODS OF EROSION AND SEDIMENTATION CONTROL: The types of control as noted in this section and the related standard plans for erosion and sedimentation facilities are a minimum requirement, unusual conditions may require more extensive facilities. Erosion control facilities shall be periodically inspected and maintained by the developer or contractor to insure continued operation. 2-10.1 Temporary Siltation/Sedimentation Ponds: Temporary siltation/sedimentation ponds shall be required of all land alteration operations in order to detain runoff waters and trap sediment from erodible areas thus protecting properties, drainage ways, and streams below the installation from damage by excessive sedimentation and debris deposition. The dam or barrier forming the pond shall be located to provide for maximum capacity for trapping sediment behind the structure as well as for greatest ease of cleaning. The temporary pond requirement may be waived, at the discretion of the City Engineer, for small areas of land disturbance where potential damage is minimal and pond construction impractical as long as runoff from all such areas is satisfactorily filtered prior to discharge from the site. 2-10.2 Check Dams and Berms: Check dams and/or berms shall be incorporated into erosion control facilities as needed. 2-10.2(1) Straw bales (staked in place) may be used as energy dissipating drop structures, flow direction control structures and/or dams to create ponding. See Standard Detail No. 2002 and 2003. 2-10.2(2) Rock berms can be used for all uses stated for straw bales and may be used as filtering devices. 2-10.2(3) Earth berms may be used to control flow direction and prevent silt -laden water from discharging into adjacent properties and/or the public rights-of-way. See Standard Detail No. 2004. 2-10.3 Natural/Synthetic Erosion Control: 2-10.3(1) Natural and/or restorative vegetation is encouraged in controlling erosion. 2-10.3(2) Mulches, such as hog fuel or straw may be used as temporary control on exposed areas during inclement weather. It may be necessary to hold mulch in place with utility mesh or netting. 2-10.3(3) Impervious covers such as plastic sheeting may also be used for temporary protection and should be staked to the ground or held in place with tires or rocks. 2-1 2-10.4 Filtering Devices: Filtering devices such as filter fabric fences may be used to filter runoff prior to discharge from site. See Standard Details No. 2005. Approved filter fabrics are celanese fiber, polyvinyl chloride woven cloth, reinforced chlorosulfinated polyethylene cloth, chlorinated polyethylene woven cloth, such as mirafi 100 X, Typar 3401, Stabilenka 100, Amoco Pro Pex Sih Stop or approved equal. 2-10.5 Intercepting Ditches: Intercepting ditches are recommended, whenever possible, to be located across future building sites to preserve natural vegetation. Intercepting ditches outside of future building sites should meander to avoid trees. 2-10.6 Cut-off Trenches: Cut-off trenches are recommended to dissipate drainage into the natural on-site vegetation. 2-10.7 Flexible Down Drains: Flexible down drains may be utilized as temporary structures to protect open slopes and shall be constructed of flared end sections connected by plastic sheet tubing, heavy duty fabric, or nonperforated corrugated plastic pipe. See Standard Detail No. 2006. 2-10.8 Gradient Terraces: A gradient terrace is an earth embankment or ridge designed so that the top of the constructed ridge is no lower at any point than the design elevation of the water surface of the outlet under design flow and is installed so as to intercept surface runoff and convey it to a stable outlet at a non-erosive velocity. Gradient terraces may be useful both as a temporary and/or a permanent erosion control measure. See Standard Detail No. 2007. 2-10.9 Temporary Construction Entrance: A temporary construction entrance is a rock stabilized temporary entrance pad and shall be constructed at points where traffic will be entering or leaving a construction site from or onto public right-of-way. The pad shall be sufficient length and width to eliminate transportation of mud and sediment from the construction area onto the public right-of-way by motor vehicles or by runoff, but under no circumstances shall it be less wide than the ingress/egress at the right-of-way nor less than 50 feet long. The stabilized construction entrance shall be a minimum thickness of eight inches and constructed of material approved by the City Engineer. The entrance shall be maintained to the satisfaction of the City Inspector. See Standard Detail No. 2008. When site conditions are such that the temporary entrance pad fails to perform as required, all vehicles exiting the site shall have their tires and wheels cleaned by sweeping, brushing or washing prior to entering public right-of-way. All washing shall be done on an area draining to an approved erosion control facility. 2-10.10 Erosion Control Practices During Roadway and Parking Lot Construction: In addition to those erosion control methods above, the additional erosion control measures below may be necessary to protect the installed storm drainage system and/or downstream systems and shall be utilized in such combination as is necessary to achieve the requirements of these Standards. Erosion control facilities shall be periodically inspected and maintenance performed in order to insure their proper functioning. 2-2 2-10.10(1) Sediment traps are structures of limited capacity designed to create a temporary siltation pond/filter around storm drain inlets or at points where silt -laden storm water is discharged. Periodic maintenance by the contractor or developer is crucial to the proper functioning of sediment traps. Example of typical sediment trap installations is the gravel filter type, seen on Standard Details No's. 2010 and 2002. 2-10.10(2) Interceptor dikes are temporary berms of compacted soil or gravel constructed across disturbed construction areas. Interceptor dikes shall be designed and constructed so as to reduce erosion by intercepting storm water and diverting it to stabilized outlets such as siltation/sedimentation ponds or areas of well-established vegetation. W DIVISION 3. STREETS AND RELATED WORK 3-10 GENERAL: Design, preparation of plans, and construction of all street improvements and/or appurtenances shall be the responsibility of the developer. All improvements shall be in accordance with current City of Bremerton Design and Construction Standards. All plans shall be approved by the City Engineer prior to issuance of any permits for construction. 3-20 DESIGN: 3-20.1 Roadway Types and Geometrics: 3-20.1(1) City of Bremerton roadways are classified functionally as indicated in Standard Detail No. 3001. Criteria for minimum right-of-way and roadway widths and other geometrics shall be as listed for given classifications. 3-20.1(2) Structural sections and roadway appurtenances shall be as shown on Standard Details Nos... 3002, 3004, 3005, 3006. Where unusual site and use conditions occur the City Engineer may require the designer to perform an engineering analysis on parameters such as soil conditions, ADT and vehicle classifications of traffic proposed on the street. 3-20.1(3) Typical Utility Locations: Typical utility locations for design purposes are shown on Standard Detail No. 3009. 3-20.1(4) Curb and Gutter: Type "A-1" curb and gutter per Standard Detail No. 3131 shall be used on both sides of all roadways. 3-20.1(5) Concrete Sidewalks: Concrete sidewalks shall be required as noted in Standard Detail No. 3101 and shall be constructed per Section 8-14 of the Standard Specifications. 3-20.1(6) Driveways: Driveways shall be per Standard Details Nos. 3121, 3122 as applicable. 3-20.1(6)A General Criteria: 3-20.1(6)A1 New driveways installed in areas where curb and gutter improvements are not existing, and not required, shall be paved from the existing edge of pavement to the property line regardless of whether the remainder of the driveway on the private property is paved. 3-1 3-20.1(6)A2 In areas not fully improved with curbs and sidewalks, the elevation of the driveway at the point where it crosses the property line shall not be more than 3 inches higher than the elevation of the centerline of the existing paved street if the driveway is rising on the private property side and no lower than level with the elevation of the centerline of the existing street if the driveway is falling on the private property side. Provided however, storm runoff shall be maintained off the street. 3-20.1(6)A3 Commercial driveways located closer than 100 feet from the approach to an arterial intersection shall be signed and marked "Right Turn Only" for ingress and egress unless otherwise approved by the City Engineer. Private "Intersection Type" driveway openings may be approved in lieu of conventional driveways in commercial areas where the following criteria are met: 3-20.1(6)A3a Projected driveway usage is greater than 1000 vehicles per day. 3-20.1(6)A3b The opening is at least 200 feet from any other intersection. 3-20.1(6)A3c The opening is at least 200 feet from any other driveway on the property frontage under control of the applicant. 3-20.1(6)A3d A minimum 100 -foot storage area is provided between the curb line on the street and any turning or parking maneuvers within the development. 3-20.2 Local Street Design: The following elements should be incorporated in the design of the local residential street system to discourage and minimize both the volume and impact of through traffic within residential neighborhoods or subdivisions: 1. Use of T -intersections 2. Use of Cul-de-sacs 3. Use of loop streets 4. Use of curvilinear street pattern Employment of the above design elements will provide some degree of travel discontinuity, thus discouraging the use of residential street system and through routes. In addition excessive speed within the neighborhoods may also be minimized. Care should be taken in street design to ensure that connections to collector and arterial streets are adequate, as determined by the City Engineer. 3-20.3 Street Ends: 3-20.3(1) Cul-de-sacs shall be provided at all permanent street ends and on any temporary dead end location when the length of the street is more than 200 feet. Cul-de-sacs shall be per Standard Detail No. 3005. 3-2 3-20.3(2) On temporary dead ends, when the length of the street is less than 200 feet, the required turn -around area may be a hammerhead type of design per Standard Detail No. 3011. 3-20.4 Sight Distance and Stopping Sight Distance: The designer shall use WSDOT " Design Manual and AASHTO " A Policy on Geometric Design of Highways and Streets for determining sight distances. 3-20.5 Intersections: 3-20.5(1) Criteria: Intersections Low Speed Curves Angle of Intersection 801 to 900 Up to 801 Minimum centerline radius N.A. 100 feet Minimum curb radius 25 feet N.A. 3-20.5(2) Minimum Centerline Offset of Adjacent Streets 3-20.5(2)A Local access and collector streets, any combination 160 feet 3-20.5(2)6 Local access or collector streets, crossing or connecting to any arterial; or arterials intersecting arterials 300 feet 3-20.5(3) The design engineer shall field locate and verify the alignment of all existing utilities including depths and manhole inverts. 3-20.6 Radii on Curb Returns: 3-20.6(1) The minimum allowable curb radius shall be 25 feet, which is to be measured from the radius point to the face of curb. The 25 -foot radius curb return may only be used at the intersection of two local access residential streets. 3-20.6(2) On all other street intersections, the minimum allowable radii shall be 30 feet, which shall also be used at the intersection of local access residential street with any collector or arterial. 3-20.6(3) Radii of 40 feet or more, and preferably three -centered compound curves or simple curves with tapers to fit the paths of appropriate design vehicles, should be provided where large truck combinations and buses tum frequently. Larger radii are also desirable where speed reductions would cause traffic problems. 3-3 3-20.7 Curb Ramps (Wheelchair Ramps): In accordance with State Law, curb ramps shall be provided at all pedestrian crossings with curb sections. See Standard Details No. 3111 and 3112 for details. It is required that when a ramp is constructed giving handicap access to the roadway area, the corresponding ramp at the opposite side of the roadway will also be required. Exact locations at each curb return will be approved in the field during construction. 3-20.8 Monumentation: It shall be the developer's responsibility to monument the boundaries of all plats, major street intersections, and street centerline control points. 3-20.8(1) Monuments shall be located at all centerline intersections of intersecting streets. Curve streets shall be monumented at centerline P.I.'s (point of intersection), if it falls within the street driving surface, otherwise both P.C. (point of curvature) and P.T. (point of tangency) of the curve shall be monumented. 3-20.8(2) Monument and monument case and cover shall be supplied and installed per Standard Details No. 3401. Monuments shall be set by a Professional Land Surveyor, licensed in the State of Washington. 3-20.8(3) It shall be the responsibility of the developer to provide longitude and latitude coordinate information of all newly installed monuments to the City Engineer. 3-20.9 Street Illumination: 3-20.9(1) Street lights shall be provided in construction drawings for plats and for commercial developments in accordance with City street light standards. All luminaires maintained by the Puget Sound Energy shall be subject to their approval. All street light wiring, conduit and service connections shall be located underground. 3-20.9(2) Street light locations must be approved by the City Engineer. 3-20.9(3) Coordination for the installation of the street lighting system by Puget Sound Energy (if applicable), shall be the responsibility of the developer. 3-20.10 Traffic Control Signing and Striping: 3-20.10(1) All traffic control devices shall conform to "Manual on Uniform Traffic Control Devices" (MUTCD) as applicable. It shall be the developer's responsibility to pay for all materials and labor as required to install all traffic control devices. All required signing (traffic control and street name signs), striping, and other delineation as required, shall be as shown on the street improvement plans prior to plan approval and shall be installed by City forces. Developer shall reimburse City for installation of traffic control devices. 3-20.10(2) See Section 9.2.1, "Lane Markers", Standard Specifications for Road, Bridge 3-4 and Municipal Construction. 3-20.11 Guardrails: Where required, guardrails shall conform to standards published in Standard Specifications WSDOT and APWD, most recent revision. Type selected shall be approved by the City Engineer. 3-20.12 Safety Railing: 3-20.12(1) Sidewalk Safety Rail: When a sidewalk is to be constructed above a slope, adjacent to a rock wall or retaining wall where, in the opinion of the City Engineer a hazardous condition will exist, a safety rail will be required. 3-20.12(2) Design: Safety railings shall be constructed of 2" galvanized steel pipe with vertical supports at 10 feet on center and horizontal railings 9 inches on center. All joints except expansion joints, shall be welded and the entire safety railing coated to assure corrosion protection. Railings shall be erected to assure a continuous line and grade. Finish height to be 42 inches above pedestrian area. See Standard Detail No. 3301 and 3302 3-20.13 Rock Walls and Retaining Walls: 3-20.13(1) Public Works Permit is required for ALL rock walls/retaining walls within the public right-of-way. Structural calculations and design drawings stamped by a Licensed Engineer are required for all retaining walls greater than 4 feet in height measured from undisturbed grade to top of wall. 3-20.13(2) Removed. 3-20.13(3) Rock Wall Usage: 3-20.13(3)A Rock walls may be used for the containment of cut or fill embankments up to a maximum height of 4 feet in stable soil conditions which will result in no significant foundation settlement or outward thrust upon the walls. 3-20.13(3)6 Rock walls may be used for containment of cut or fill embankments greater than 4' high and up to a maximum height of 12 feet upon approval by the City Engineer of a rock wall design stamped by a Licensed Structural Engineer. In addition to construction monitoring by Public Works, rock walls greater than 8 feet in height require the owner to employ a licensed soils engineer for construction inspection and submit copies of his inspection reports to the City Engineer. 3-20.13(3)C Rock Wall Materials 3-5 3-20.13(3)C1 Size categories shall include: Two-man rocks (300 to 800 pounds), 13" - 18" in least dimensions; and Three-man rocks (800 to 1,500 pounds), 18" - 24" in least dimensions; and Four -man rocks (1,500 to 2,100 pounds), 24" - 32" in least dimension; and Five -man rocks (2,100 to 3,000 pounds), 30" - 38" in least dimension. Five -man rocks shall be used for bottom course rock in all rock retaining walls over 7 feet in height. 3-20.13(3)C2 The rock material shall be fractured and as nearly rectangular as possible. No stone shall be used which does not extend through the wall. The rock material shall be hard, sound, durable and free from weathered portions, seams, cracks and other defects. For all walls higher than 4 feet or with a surcharge, rock density shall be a minimum of 160 pounds per cubic foot. 3-20.13(4) Trench Excavation: The rock wall shall be designed and constructed with an excavated trench having a minimum depth of one-half the base course or one foot (whichever is greater) below the ground level in embankment sections. 3-20.13(5) Rock Selection and Placement: Rock selection and placement shall be such that there will be minimum voids and, in the exposed face of the wall, no open voids over six inches across in any direction. The final course shall have a continuous appearance and be placed to minimize erosion of the backfill material. The larger rocks shall be placed at the base of the rockery so that the wall will be stable and have a stable appearance. The rocks shall be placed in a manner such that the longitudinal axis of the rock shall be at right angles to the rockery face. The rocks shall have all inclining faces sloping to the back of the rockery. Each course shall be seated tightly and evenly on the course beneath. After setting each course, all voids shall be filled from the back with quarry rock to eliminate any void sufficient to pass a 2 -inch square probe. 3-20.13(6) Backfill: The wall backfill shall consist of quarry spalls with a maximum size of 2-1/2 inches and a minimum size of 3/4 inches or as specified by a Licensed Engineer. This material shall be placed to twelve -inch minimum thickness between the entire wall and the cut or fill material. The backfill material shall be placed in lifts to an elevation approximately six inches below the top of each course of rocks as they are placed, until the uppermost course is placed. 3-20.13(7) Filter Fabric: Fabric shall be as specified by a Licensed Engineer See Section 2-1.4. 3-6 3-20.13(8) Location: The location of rock or structural retaining walls shall not restrict drivers' sight distances. 3-20.14 Curb and Gutter: The standard curb and gutter section shall be Type "A" per Standard Detail No. 3131. All new curb and gutter shall be placed over not less than six inches of compacted crushed surfacing top coarse placed over a compacted sub -grade. The minimum acceptable compaction shall be 95% of maximum density. Steel forms shall be used for all tangent sections. Wood forms may be used on curved sections and on curb returns. No new curb and gutter is to be poured until forms have been checked and approved for line, grade and compaction by the City inspector. 3-20.15 Sidewalks: All sidewalks shall be placed over a minimum of three inches of crushed surfacing top coarse compacted to not less than 95% of maximum density placed on compacted sub- grade. In all cases, sub -grade and top of rock grade shall be approved by the City Engineer prior to concrete being placed. Sidewalks shall be a minimum of 4" thick. Generally, score marks are to be placed on five-foot centers, but at the discretion of the inspector this may be changed to make a better match with the surrounding area. Expansion joints shall be placed to match those placed in curbs if new sidewalk is poured adjacent to curb and gutter, in all other cases the maximum spacing on expansion joints shall be thirty feet. 3-20.16 Driveways: 3-20.16(1) The minimum thickness of the driveway apron shall be six inches in residential driveways and eight inches in commercial driveways. The adjacent sidewalk in the driveway area is to have a minimum thickness of six inches in residential areas and eight inches in commercial areas placed over a minimum of four inches of crushed surfacing top coarse compacted to 95% maximum density over a compacted sub -grade. In all cases, sub -grade and top of rock grade shall be approved by the City Engineer prior to concrete being placed. Driveway aprons over fifteen feet wide shall have an expansion joint placed in the center of the apron. 3-20.16(2) In location where a driveway is to be constructed and sidewalk and curb and gutter is already existing, it must be totally removed and replaced to driveway standards. The total curb and gutter section shall be removed, either by saw cutting or to the nearest expansion joint, and replaced to driveway standards. 3-20.16(2)A Abandoned Driveways: Where driveways are to be abandoned the driveway section shall be removed and replaced with a curb and gutter section. 3-20.17 Trench Excavation: Trench excavation under sidewalks or roadways shall comply with all sections of the Standard Specifications. 3-7 All service and utility lines shall be shored, supported and maintained during construction. In the event of damage, breakage or environmental contamination the contractor shall be responsible for all claims and fines which may arise. Open trenches shall be closed by the end of each working day. The City Engineer may require the trench to be plated or covered with cold mix asphalt. 3-20.18 Trench Backfill: Excavated material may be used as trench backfill only when approved by the City Engineer. Otherwise trench backfill shall be select material complying with Section 9-03.9 (3) of the Standard Specifications and shall be installed as per applicable sections of the Standard Specifications. 3-20.18(1) Compaction: Compaction shall be in compliance with applicable sections of Division 7 of the Standard Specifications. 3-20.19 Patching: The edges of all street cuts must be free from loose or broken pieces prior to patching. All existing pavement edges shall be sawcut. See Standard Plan No. 3153. 3-20.19(1) Cement Concrete Patches: Cement concrete patches shall be installed as shown on Standard Detail No. 3154 and shall be given a heavy broom finish. Expansion joints shall be placed as directed by the Engineer. 3-20.19(2) Asphalt Concrete Patches: Asphalt concrete patches shall be installed as shown on Standard Plan No. 3153 and edges sealed with SS -1 or AR 4000. 3-20.20 Earthwork: Earthwork shall comply with applicable sections of Division 2 of the Standard Specifications. 3-20.21 Crushed Rock: Crushed rock material shall comply with section 9-03.9(3) of the Standard Specifications and shall be installed as per applicable sections of Division 4 of the Standard Specifications. Ballast Shoulder Ballast (2 1/2"-0") Crushed Surfacing (1 1/4"-0") Maintenance Rock (1/2"-0") Standard Specification 9-03.9(1) Standard Specification 9-03.9(2) Standard Specification 9-03.9(3) Standard Specification 9-03.9(4) 3-20.22 Recycled Glass Aggregate: Aggregate composed solely of glass may be used as gravel backfill for walls, pipe bedding, and sand drains; sand drainage blanket; and gravel burrow. One hundred percent of the glass shall pass a 3/ -inch square sieve and not more than 5 percent by weight shall pass a U.S. No. 200 sieve. Sieve analysis shall be conducted according to WAQTCFOP for AASHTOT27/11 on at least a quarterly basis by the product 3-8 supplier. All test results shall be kept on file by the product supplier. The maximum debris level shall be 10 percent. Debris is defined as any deleterious material which impacts the performance of the engineered fill and includes all non -glass constituents of the glass feed stock. The percentage of debris in cullet shall be quantified using the following visual method. Approximately 200 grams of processed cullet shall be placed in a flat pan or plate. The percentage of debris shall be estimated using AGI Data Sheets 15.1 and 15.2 "Comparison Charts for Estimating Percentage Composition", by the American Geological Institute, 1982. Total lead content testing shall be performed quarterly by the product supplier. Tests shall include a minimum of 5 samples. Sample collection shall be conducted according to WSDOT FOP for AASHTO T 2. The mean of these tests shall not exceed 80 ppm. Total lead content testing will be conducted according to the EPA Method 3010/6010. All test results shall be kept on file by the product supplier. 3.20.23 Pavement: Pavement materials and construction methods shall comply with applicable sections of Division 5 of the Standard Specifications. 3-9 DIVISION 7. STREET LIGHTING 7-10 GENERAL: This section describes Street Lighting Standards for developments within the City of Bremerton. Street Light(s) or Street Lighting referred to in this standard is defined as that street lighting owned and maintained by the City of Bremerton. Existing lighting on public rights of way that is not currently owned and maintained by the City shall be replaced by new lighting, designed and installed in accordance to City Standards. The owner or developer shall pay for design and installation and deed to the City once the City has approved of such installations. This street lighting standard sets minimum illumination levels and uniformity for various classifications of roadways within the City of Bremerton. Lighting systems are to be designed to meet the desired illumination in accordance with these Standards. 7-10.1 Standards and Regulations: All electrical equipment shall conform to the requirements of these Specifications, the plans and special provisions, all material and work shall conform to the requirements of the following in the order noted: Latest adopted (by Washington State) edition of the National Electrical Code (NEC). Laws, Rules, & Regulations for Installing Electric Wires & Equipment, Department of Labor & Industries, State of Washington (L&I). National Electrical Manufacturers Association (NEMA). American Society for Testing and Materials (ASTM). Illumination Engineering Society (IES). American Standards Association (ASA). Puget Sound Energy (Puget Power). City of Bremerton Street Lighting Design Standard Drawings (City Standard Drawings). American National Standards Institute (ANSI). Washington State Standard Specifications for Road, Bridge and Municipal Construction (Standard Specifications). Washington State Standard Plans for Road, Bridge and Municipal Construction (Standard Plans). Other City ordinances or requirements that may apply. All material must be Underwriters laboratories Listed (UL) Prior to start of work, all necessary licenses, permits and approvals shall be obtained. The Contractor shall comply with all laws, ordinances, rules, orders, and regulations relating to the performance of the work, the protection of adjacent property and the maintenance of all other facilities. The Contractor will be required to comply with all the provisions of these instruments and shall save and hold the City harmless from any 7-1 Revised January 2015 damage which may be incurred as a result of the Contractor's failure to comply with all the terms of these permits. The Contractor is advised that an Electrical Work Permit from the State Department of Labor and Industries shall be required for this project. Street lighting shall be designed in conformance with these specifications, and the most current version of the American National Standard Roadway Lighting except as modified by this standard. Conformance shall be obtained by calculations meeting the requirements of the City Standards. 7-10.2 Roadway Classification: Roadway classifications are based on Bremerton Standard Detail Drawing 3001 for Functional Roadway Classification 7-10.3 Street Lighting Required: Street lighting shall be required for all lots and parcels being developed or constructed upon. Street lighting will also be required for any frontage of existing streets not already illuminated. In addition, street lighting may be required for lots and parcels containing existing structures which are being improved or altered, depending on the nature and extent of the work. Placement of the street lighting will be in accordance to the lighting design. Street lighting will not be required for a single residence. 7-10.4 Developer's Responsibility for Relocation of Existing Street Lights: Existing street lighting that must be relocated or repositioned, as a result of the construction of new streets or driveways into a development shall be the responsibility of the developer. 7-10.5 Utility Company Authorization: A written notice from the serving utility company, stating that line clearances and service have been checked and are adequate, shall be submitted to the Engineer for all developments. 7-10.6 Submittals: A full submittal shall be dropped off to the City of Bremerton Electronics Division personnel. The submittals shall consist of: Catalog cuts that clearly identifies all poles, base type, lighting fixtures, service cabinets, junction boxes, lamps, photoelectric eyes, splice kits, wire, fuse holders and products that are to be used in this project. Completed Bremerton Standard Drawing for Lighting Design Summary. Lighting System Design drawing showing pole locations and conduit runs, per. Bremerton Standard Drawings. 7-2 Revised January 2015 Pole Schedule giving pole heights, base type, pole arm lengths, and luminaire wattages, per Bremerton Standard Drawings. Conduit Wiring Schedule giving conduit run number, conduit size and type, number and size of lighting conductors in each conduit run, number and size of grounding conductors in each conduit run, number and size of service conductors in each conduit run, number and size of photoelectric eye conductors in each conduit run, number and size of any miscellaneous conductors in each conduit run, and any special notes about each conduit run, per Bremerton Standard Detail Drawings. Riser diagram per Bremerton Standard Detail Drawings. Any other information or calculations necessary to verify that the submitted design meets this specification. 7-20 STREET LIGHTING - SPECIFICATIONS 7-20.1 Luminaires Two types of street lighting installations are permitted: Standard - Uses metal galvanized tapered poles and mast arms, referred to as Type 1, ranging in mounting heights from 25 to 40 feet. Decorative - Uses a pole with a design that has been approved for the local area, roadway, trail, or zone. The design of the pole may be found within the sub -area plan or similar document, these standards, or prescriptive by their previous use in an area, roadway, trail, or zone. 7-20.1(A) Lighting Pole Identification: Assignment of the pole numbers shall be by the Electronics Division who will also install the stickers. Nominal Voltage Identification: Labeled over the lighting standard handhole. 1 inch high, black legend on orange background. The top of the legend shall be 4 inches above the top of the handhole. Legend is to be "240 VOLTS". Label needs to be Type 1 or 2 reflective sheeting in accordance with WSDOT Standard Specifications Section 9-28.12. 7-20.1(13) Spare Lighting Poles: Depending on the type of poles and quantity of poles used in this project, spare replacement poles may be required. Confirmation of whether spares are required shall be by the Electronics Division. The spare replacement poles shall be delivered to a site in the City as directed by the Electronics Division. 7-20.2 Luminaires: 7-3 Revised January 2015 The type of street light luminaire and lamp wattage shall be specified on the plans.. All luminaire heads are to be Light Emitting Diode (LED) style as manufactured by Cooper Lighting equipped with Telensa programmable dimmers installed. The light distribution pattern for each luminaire shall be specified on the plans. Luminaries shall have: Corrosion resistant hardware. Multi -tap voltage drivers. Must be UL Listed. A photoelectric control receptacle (7 pin) shall be installed on each fixture Type 1 luminaires are to be a Gray paint finish, decorative to match the color of the pole. Luminaries are to be leveled. Luminaires and poles in the Central Business District shall be in accordance with Bremerton Standard Drawing 7022 and 7023. LED Luminaries shall be Cooper Lighting or Visionaire Lighting New Orleans II Lighting Models to match city existing system. Decorative Luminaires for neighborhoods or areas a choice of the following two fixture styles. The luminaire shall be UL listed as suitable for wet locations at a maximum 60 degree C ambient temperature. Acorn GranVille 7-20.3 Photoelectric Controls: Control of the street lighting is by a master photocell. This photocell controls a lighting relay in a pad mount electrical service cabinet. The photo cell will be mounted atop the nearest light pole to the service cabinet. The photo cell will be a twist lock configure with the window pointing north and instant on operation, designed to turn on at 3 foot- candles, rated to operate over the voltage range of 105 to 305 volts AC, 60 Hz. The seven (7) pin turn lock shall meet the requirements of ANSI. Each fixture head will have a shorting cap installed. Photoelectric control installation shall be per Bremerton Standard Detail Drawing 7017. 7-20.4 Electrical Connections At Light Pole Bases: 7-4 Revised January 2015 Electrical connections at light pole bases shall be per Bremerton Standard Drawings.. Fuse connectors shall be installed at every light pole base. All lighting branch circuit conductors above ground potential shall be served by a fused connector. 7-20.4(A) Luminaire Fusing: Fuse connectors shall be manufactured by SEC (Signal Electric Company). . The fuse holders shall be readily accessible from the Light Pole handhole, and have eighteen inches (18) of slack in the conductors. Luminaire fusing for Lighting Poles shall conform to Bremerton Standard Drawings. Fuses shall be 13/32" x 1 1/2" Dual Element Time Delay Fuse - Bussman Type FNM, Reliance MEN, Gould-Shawmut TRM, or approved equal with the appropriate current rating as per Bremerton Standard Drawings. 7-20.5 Service: The Service Cabinet shall be Underwriter Laboratory listed and labeled for service entrance use. Metering is required on all installations. See City of Bremerton Standard Drawings. Lighting branch circuits are sized to maximum 80% of the branch circuit ampacity. Lighting branch circuits can be 20 or 30 amperes. Available fault current at the service point of the Service Cabinet is assumed to be 10,000 Amperes. Contractor is responsible to determine available fault current. If greater than 10,000 AIC a higher rated AIC main breaker is required, and conformance with NEC Article 110-8 and 110-9 is required. The minimum service size is 200 amp at 240 volt. Service size may be increased to as large as 250 amps at 240 volts based on the engineered approved drawings. 7-20.5(A) Electrical Service: The electrical service shall be obtained from Puget Sound Energy by the Contractor upon the Contractor's request. and full expense. The contractor shall energize the street lighting service in the contractor's name and operate the system trouble free for a period of 90 days. At such time after acceptance testing has been performed, approved and all work has been accepted by the City. The electrical service will then be transferred to the City of Bremerton street lighting account. If any additional questions contact the Public Works Operations at 360-473-5920. The Contractor shall ascertain the requirements of Puget Sound Energy and shall seek approval from Puget Sound Energy and the Engineer as to locations and type of construction for connecting and mounting service hardware. All service cabinet(s) shall be locked at all times that work is not being performed on the equipment. Service conductors shall be as indicated on the wiring schedule and also must be copper type USE, XHHW/RHW/ XLP. All street lighting systems shall have underground service provided. Service points to pole or pad mount transformer shall be provided within a utility easement immediately adjacent to or within the right-of-way and shall be open and easily accessible to the street frontage. 7-5 Revised January 2015 7-20.5(8) Electrical Service Cabinet (General): The length of conductors within the Service Cabinet shall be sufficient to neatly train the conductor to the terminal point with no excess. Multiple conductors shall be neatly bundled, and secured with suitable nylon ties. Terminations shall be made so that there is no bare conductor at the terminal. The conductor insulation shall bear against the terminal or connector shoulder. All galvanized conduit in contact with concrete shall be wrapped with 2" wide, 10 mil thick electrical tape, Scotchrap 50 or approved equal, half lapped. Coat with suitable primer. The base of the service cabinet shall be sealed to the concrete pad with a polyurethane sealant meeting ASTM C-920, Type S, Class 25, Grade NS. The color shall approximately match the color of the Service Cabinet. Grounding of the service cabinet shall be per Bremerton Standard Detail Drawings. Electrical Service fed from Underground Source: Shall meet most current PSE requirements and codes. Verify requirements for connections to pad mount transformer with Puget Sound Energy Engineer. Service entrance conduit can be rigid metallic galvanized or PVC non-metallic schedule 80. End bell for PVC conduit. Phenolic bushing for rigid metallic galvanized. Provide 6" of sand backfill above and below exposed conductors. Continuous conduit from service cabinet to Puget Sound Energy Pole. Extend up pole to height as determined by Puget Sound Energy engineer. Install a PVC weather head. Rigid metallic galvanized conduit. Pole riser per. Bremerton Standard Detail Drawing 7018. 7-20.5(C) Electrical Service Cabinet Service cabinet to be per Bremerton Standard Detail Drawing as manufactured by Rhino Manufacturing Snohomish Washington and have the following: • Cabinet shall be UL labeled. • NEMA 3R construction, pad mount, 25" wide x 30" deep x 60" high. • 12 gage pre -galvanized steel. • Removable equipment mounting pan. • Stainless steel vault handles, 3 point latch. • Best cabinet locks with Blue Construction Cores. • Cabinet doors: Lift off, heavy-duty barrel hinges, closed cell neoprene gasket, hinged on left. 7-6 Revised January 2015 • Cabinet vents: Two screened and gasketed, one near top of cabinet end, other near bottom.(not in meter section). • All internal fasteners to be pan head Phillips SS. • Exterior finish: Polyurethane powder coat, ASA 61 Gray. • Interior finish: white enamel paint. • Internal wireway. Provide 1/2" diameter mounting holes in bottom flange. Wiring: Cabinet wiring to be stranded, type MTW or SIS copper. Panelboard: Minium 120/240 VAC, 1 Phase, 200 amp mains, 16 space, 10KAIC. Provide following branch circuits: (See Bremerton Standard Detail Drawings). 20/4 Illumination, one per each lighting contactor required 20/4 Tree lights 15/1 Control 15/1 Heat 20/1 Signal Branch 20/1 Receptacle Branch Lighting Contactor(s): 30 amp, 2 pole, 600 volt, 120 volt coil, Square D (Number of lighting contactors 6 — 2 pole). Meterbase :200 Amp 5 jaw with bypass block , with 5 jaw at 9:00 position. The base foundation for the service cabinets shall conform to State of Washington Standard Plans and Sections 8-20 and 6-02 of the Standard Specifications. The foundation will include a pad for maintenance of the cabinet of 6 inches on each side, 24 inches on the back (meter base) side, and 24 inches on the door side as per the Bremerton Standard Plans. All foundations shall include a 3/8 inch diameter plastic drain. A minimum of one spare 2 inch conduit will be installed from the panel side of the service to the nearest junction box. 7-20.6 Junction Boxes: All junction boxes, shall be concrete with a galvanized steel lid and shown and identified on the submitted plans. All connections and splices shall be made only within junction boxes. Install junction boxes: All splices made to the illumination circuits in junction boxes will be made in a Polaris insulatated multi -cable connector blocs in accordance with City Standard Drawings. Enter conduit from the direction of the run. Terminating within 3 inches of the box wall nearest entry. Concrete junction boxes with steel lids shall be sized by number of conduits in the box as per the NEC as identified in Standard Plans, galvanized, with grounding strap, and locking lid, bearing the legend "LT", in conformance with Washington State Standard Plans and will be locking with SS penta head bolt. All junction boxes shall have a minimum of 6 inches of crushed gravel underneath. 7-7 Revised January 2015 Concrete junction boxes with steel lids shall be used in all locations including where the junction box will be in the sidewalk. Junction boxes shall be installed at: Locations where more than two conduit runs intersect. Where conduit runs are more than 300 feet long. Where shown on the submitted plans. At critical angle points. Locations as directed by the Engineer. In the sidewalk at the back of the walk whenever possible. Flush with the sidewalk grade, firmly bedded and aligned as directed by the Engineer. 7-20.7 Tree Lighting Where receptacles for tree lights are to be installed, they are to be Gard -N -Post Low Profile Support Model #GP26B. 7-20.8 Conductors: All conductors, including quantity and size, shall be identified on the submitted plans. Voltage drop: Shall be per NEC requirements. Size lighting branch circuits for 5% voltage drop. Size service entrance conductors for 3% voltage drop. Calculations showing voltage drop for lighting branch circuits are required. Wire conductors for underground feeder runs, service entrance and for circuitry from the in-line fuse in the poles to the junction box shall be six hundred (600) volt, single conductor stranded copper type, USE, XHHW/RHW/XLP in accordance with the Insulated Power Cable Engineer's Association Specifications. Conductors used in the service cabinet are per section 3451.7 Wire conductors inside the pole from the luminaire to the in-line fuse shall be per Standard Specification Section 9-23.3 (5); six hundred (600) volt, Pole and Bracket cable. If the luminaire requires fixture wire temperature greater than 75 C, the outer portion of the cable jacket shall be stripped for that portion of the cable inside the luminaire. The single conductors shall be sheathed with braided fiberglass sleeving of the temperature rating recommended by the luminaire manufacturer. Minimum conductor size for lighting branch circuits' is #8 AWG, including equipment ground. Minimum conductor size for photoelectric control is #12 AWG and the same type as mentioned above. 7-8 Revised January 2015 7-20.8(A) Conductor Color Coding: Color coding shall be accomplished by colored thermoplastic electrical tape, if the conductor is not of the required color. Conductors shall be taped for a minimum of 3", lapping each turn 1/2. Equipment grounding conductors and the grounded conductor shall be color coded per the National Electrical Code. At each junction box, light standard handhole,. and service cabinet, street lighting conductors shall be color coded per phase of the 120/240 volt AC service. Remote wiring from the Service Cabinet to the photoelectric control shall be color coded as follows: Black -Line White -Neutral (grounded conductor) Red -Load These conductors shall be USE, XHHW/RHW, or XLP. 7-20.9 Conduit: All conduit runs, including the size, shall be shown and identified on the plans. The minimum conduit for each conduit run shall be determined according to the NEC, with the minimum size between junction boxes being one and one half (1 1/2") diameter conduit for lighting branch circuits. Larger conduit may be required at the discretion of the City. All conduits 90's and risers entering and leaving existing junction boxes shall be rigid metallic galvanized conduit. All conduits from the junction box feeding luminaires, tree well receptacles, and festival receptacles shall be schedule 40 or 80 PVC. A spare 2" conduit shall be installed between each junction box Conduit installed underground across roadways or driveways shall be rigid metallic galvanized or Schedule 80 PVC conforming to NEC. All conduit installed underground shall have Polyethylene Underground Hazard Marking Tape, 6 inches wide, red, legend "Caution -Electric Line Buried below", placed approximately 12" above the conduit. All galvanized conduit in contact with concrete shall be wrapped with 2" wide, 10 mil thick electrical tape, Scotchwrap 50 or approved equal, half lapped. Coat with a suitable primer. All conduits installed under sidewalk shall be Schedule 40 rigid polyvinyl (PVC) unless otherwise noted on the plans. PVC conduit shall conform to the NEC. Conduits terminating in junction boxes shall terminate not less than five inches or more than nine inches below the lid of the box and be a minimum of 2 inches above final 7-9 Revised January 2015 grade in the bottom of the box. Every conduit entering such boxes shall be neatly upswept and contain an equipment ground with a minimum size 8 awg stranded copper, except for spare conduits. The only conduit bends permitted shall be either factory bends or those formed by the use of an approved conduit bending tool employing correctly sized dies. Conduit entering any electrical enclosures shall be positioned to avoid bending or cutting cabinet braces and cross members that are formed as a part of the electrical enclosure or its pedestal. Such bending or cutting is expressly prohibited. All metallic conduits in junction boxes shall have grounding bushings and be bonded to the system ground wire and be attached to the ground strap, lid, and box. Size of all conduits shall be shown on the Plans. A 200 pound breaking strength pull string or true tape with footage measurements shall be pulled into all conduit runs, except the service entrance conduit and conduit for grounding electrode conductor. All empty conduits shall be plugged or capped immediately after pulling through a cleaning mandrel and installation of the pull string. 7-20.9(A) Grounding of Illumination System: The illumination system shall be bonded and grounded in accordance with Bremerton Standard Detail Drawing 7010 & 7012. Grounding bushings, where required, shall be OZ Gedney, type HLBG or Thomas & Betts, Blackjack type BG. 7-20.10 Acceptance Testing: All testing shall be performed in the presence of a representative of the City Electronics Division and recorded on Bremerton Standard Detail Drawing 7009. The project will not be considered acceptable and completed until the completed Bremerton Standard Detail Drawing 7009 is submitted to the City Engineer. Testing may be scheduled through Bremerton One Call at 360.473.5920 with a minimum of three working days notice and ask for Electronics personnel. All measurements will be made with an instrument designed for that purpose and acceptable to the City. The Contractor may use its own instruments to verify readings. If a discrepancy exists, the readings taken with the City's instrument will be considered as the correct readings. If the contractor disputes the City's readings, the City will produce calibration documentation for the instrument or verify the readings with a third instrument. 7-20.10(A) Insulation Testing: To perform this test the Contractor shall disconnect all luminaires at the fuse connector in the hand holes of each pole. Then test the insulation resistance at 500 volts with a suitable testing device. An acceptable reading shall be at least twenty five (25) megaohm at 500 volts for one minute. 7-20.10(8) Operational Testing: 7-10 Revised January 2015 The Contractor shall verify the correct operation of the lighting test switch, the master photocell, and the ground fault circuit interrupter receptacle. 7-20.10(C) Voltage Readings: The Contractor shall take voltage readings at the supply side of the lighting contactor. The voltage readings will be taken with the contactor open (no lights energized) and the contactor closed (all lights on). The readings to be taken are Leg A to ground, Leg B to ground, and Leg A to Leg B. 7-20.10(D) Amperage Readings: The Contractor shall take current readings using a clamp on amp meter with the lighting contactor closed (all lights on). The readings to be taken are Leg A at the output of the lighting contactor and Leg B at the output of the lighting contactor. 7-20.10(E) Record Drawings: The contractor shall provide red lined prints of the plans showing as -built information of the field wiring prior to acceptance of the job by the City. Drawings are to be delivered to the City of Bremerton Public Works 100 Oyster Bay Ave, Bremerton Washington, 98312. 7-11 Revised January 2015 DIVISION 8. TRAFFIC SIGNALIZATION 8-10 GENERA All work to be in conformance with Sections 8-20 and 9-29 of the Standard Specifications for Road, Bridge and Municipal Construction (Current Edition), and to all revision and supplements thereto except as modified herein. References here within this division to Engineer shall be to the City Engineer or their appointed representative. 8-20 OPERATION OF EXISTING SIGNAL SYSTEMS: It shall be the responsibility of the Contractor to assure the continuous operation of any existing signal systems until activation of the new signal system or as required by the Engineer. This shall include but not be limited to any relocation of poles or equipment required by construction. In the event that construction requirements necessitate a period of time when the signal system will be non -operational the "down time" must have prior approval of the Engineer. Contractor shall provide traffic control as required by the Bremerton Police Department at any time the signal system is not functioning. 8-30 APPROVAL OF SHOP DRAWINGS AND MANUFACTURER'S DATA: Within fifteen (15) days following the date of Notice to Proceed, the Contractor shall submit to the Engineer for approval the complete list of material sources for all signal items to be employed on this contract. Manufacturer's technical information shall be submitted to the Engineer for approval of all items to be included in the project. All approvals by the Engineer must be received by the Contractor before materials will be allowed at the job site. Material not approved by the Engineer will not be permitted at the job site. Approval of shop drawings for signal work will require up to thirty (30) calendar days from the date the Engineer receives the drawing until they are returned to the Contractor. The actual time required for approval is dependent upon the completeness and appropriateness of the drawings as submitted. Any deficiencies will require additional time for approval based on the degree of the deficiency and the additional review time required. If the shop drawings are returned to the Contractor to correct deficiencies, an additional 30 calendar days may be required for the approval process. If more than 30 calendar days are required for routine approval of shop drawings that are completed and accurate, the Contractor will be granted an extension of time equal to the additional review time. 8-1 Revision 10/27/2014 8-40 INSPECTION OF MATERIALS: The City reserves the right to inspect the manufacturing process of all materials. Final inspection and acceptance of the installed materials will not be given until final installation and testing has been completed on the system. Approval to install materials and equipment must be obtained from the Engineer at the job site before installation. Appropriate insulation resistance tests shall be performed in accompaniment with the Engineer. All electrical equipment shall conform to the Standards of the National Electrical Manufacturers Association (NEMA). In addition to the requirements of these specifications, all material and work shall conform to the requirements of the National Electric Code: Laws & Regulations for installing electric wires & equipment, of the Department of Labor and Industries, State of Washington; the American Standards Association Materials (ASTM); the American Standards Association (ASA); American National Standards Institute (ANSI); Standard Specifications for Road, Bridge and Municipal Construction (Standard Specifications); Standard Plans for Road, Bridge and Municipal Construction (Standard Plans); and any other City Ordinances or requirements of Puget Power and Light Company which may apply. Prior to start of work, all necessary licenses, permits and approvals shall be obtained. The Contractor shall comply with all laws, ordinances, rules, orders, and regulations relating to the performance of the work, the protection of adjacent property and the maintenance of all other facilities. The Contractor will be required to comply with all the provisions of these instruments and shall save and hold the City harmless from any damage which may be incurred as a result of the Contractor's failure to comply with all the terms of these permits. 8-60 EXISTING UTILITIES: See Section 1-1.01 (8) and Section 1-2.10 (2) of these General Provisions. No new fixture shall be constructed as part of this Contract which is in conflict with any existing Utilities Facility, or the code required thereby, until approved by the Engineer. 8-70 FIELD TESTING 8-70.1 System Activation: Before the signal system is activated for Traffic Control purposes, the Contractor shall perform all field tests specified in Section 8-20.3 (11) of the Standard Specifications. When all tests have been completed to the satisfaction of the Engineer, the Engineer shall direct the authorized representative of the Contractor to activate the traffic signal system. Authorized City personnel shall be present to assure proper functioning. The Contractor shall give the Engineer five (5) days advance notice of the capability of signal system activation. 8-2 Revision 10/27/2014 8-80.1 8 -Phase Signal Controller/Nema: The controller shall be an Econolite Cobalt controller with advanced display, FSK Module , Data Key and TSP Data key. The units shall be constructed and shall operate in accordance with NEMA Publication No. TS1-1976 and Section 9.29 of the Standard Specifications. The supplier shall submit documentation with his bid detailing the brand and model number of the signal controllers proposed to be furnished for this project. The documentation shall include catalog cuts and operation details. The City reserves the right to reject any and all equipment that does not meet these specifications. All controllers shall be compatible with the Econolite Aries software. Controllers and cabinets shall be equipped to operate to the full capacity of eight vehicle phases, four pedestrian phases and four overlaps with no additional equipment or major modifications and shall be capable of operating as a fully actuated, semi -actuated, or pre -timed unit. Each unit shall be delivered pre-set to operate in conformance with the phase diagram, sequence charts, and Table I for each location which are a part of these Specifications. Two sets of controller/board schematics shall be included with the operations and programming documentation. All cabinet and control equipment shall be designed to operate under the following conditions. 1. An ambient temperature range of -30F to +165F. 2. A relative humidity range of 5%-95% (without condensation). 3. A voltage range of 95 to 135 VAC RMS with a corresponding frequency ranges of 57-67 Hz. The design life of all components shall not be less than five years of continuous 24-hour a day operation. All external connections to the signal controller unit shall be made to terminals provided on the back panel. High pressure terminals shall be provided for field signal and primary power connections. Screw terminals shall be provided for all other connections. 8-90.1 General: All necessary equipment for the full capacity of the Controller and all auxiliary control equipment as specified in Section 9-29.13 (7) B of the Standard Specifications shall be furnished and installed in each traffic signal controller, except as modified or amended herein. Also required to provide interconnect capabilities, twisted pair, fiber, radio. All equipment shall employ solid state circuitry including the flash transfer relay assembly and shall be commensurate with the quality of the controller specified herein. 8-90.2 Multifunction Management Unit (MMW: The MMU shall be a self-contained solid state device, external to the control, capable of detecting conflicting signal displays, displaying all field voltages at the same time on an OLED display, improper power supply 8-3 Revision 10/27/2014 voltages from the controller, and lack of any red yellow or green indications. The unit shall meet the current NEMA TS2-2003 and TS1-1989 requirements for a Type 16L conflict monitor and these special provisions. The MMU will have an organic LED display and an SLDC and an Ethernet port on the front panel for connectivity. The unit shall monitor the green, amber, walks, short yellow intervals and the absence of red indications, as well as being programmable to monitor all conflicting phases' overlaps, and disable short yellow with a universal program board. All monitoring shall be on the field wiring terminals of the cabinet. When the monitor is triggered as a result of sensing conflicting displays, it shall place the intersection in emergency flash, stop time the controller, store and display on the front panel. The front panel display shall have separate indicators for red, yellow, green, and walk for each channel. The monitor shall retain this operation until reset by a front panel push-button, at which time the controller shall immediately take command of the signal displays. The MMU shall also record the time and date of any incidents at the intersection. This information shall be viewable by a front panel display. To prevent actuation of MMU due to the removal of electrical loads from monitored circuits, paralleling loads to lamp loads will be required. Those load switches serving single signal heads shall have five watt loads between signal circuit and neutral for the yellow, green, and walk circuit segments only. These loads shall serve to parallel the lamp load and shall prevent the conflict monitor from functioning in the event of a signal lamp burnout. If additional protection is required, either in the form of increased loads (not to exceed 10 watts) per monitored circuit, or through other means, to assure proper function without malfunction of the conflict monitors, such shall be provided. In addition to all other requirements stated herein for conflict monitors, the use of fluorescent signal cabinet lights is prohibited. Signal cabinet lights shall be an approved LED type. 8-90.3 Load Switches: Load switches shall be specified per NEMA TS2 part 5 and these Special Provisions. The load switches shall operate in a temperature range of -20 F to 165 F and have an individual switch capability of 1,000 watts tungsten lamp load. Only optically isolated load switches will be allowed. Each load switch shall be provided with LED indicators on the input and output of each circuit. 8-90.4 Cabinet Fan Assembly: The cabinets shall be equipped with an electric fan assembly with a minimum capacity of 100 cubic feet per minute. The fan shall be mounted on the top of the cabinet in a manner to prevent rain from entering the cabinet. Each cabinet shall be provided with louvered filtered vents in the front door. The fan shall be thermostatically controlled and shall be manually adjustable to turn on between 90 degrees and 150 degrees Fahrenheit. The cabinet fan circuit shall be fused at 125 percent of capacity of the fan motor. 8-90.5 Loa: A load bay and controller interface panel shall be provided with 16 load switch positions. Each load switch output shall be wired to fused field terminals providing for 8 vehicles, 4 pedestrian and 4 overlap movements. Fused terminals shall be provided with 5 amp fuses. Both the front and back of the load bay shall be labeled with all terminal/pin numbers. Four additional fuses shall be provided. The emergency vehicle light circuits shall also be fused independently for 5 amps. 8-4 Revision 10/27/2014 A jumper plug system utilizing Molex connectors shall be installed on the load bay that will facilitate the simple programming of the flashing indications. This shall apply to all vehicle signal indications. Changing the flash from red to yellow shall not require major disassembly or rewiring of the cabinet. Cabinet will be programed for all red flash and 4 spare Molex connectors for yellow flash. The terminal blocks provided shall be two -position, twelve -pole barrier type or single -position, feed -through type. Terminal blocks shall be so arranged that they shall not upset the entrance, routing, and connection of incoming field conductors. All terminals shall be suitably identified and shall be permanently associated with the terminal block. No more than three (3) conductors shall be brought to any one (1) terminal screw. No electrically live parts shall extend beyond the protection afforded by the barrier. Terminal blocks used for field wiring connections (field terminals) shall be capable of securing conductors with 6-32 or larger, nickel, or cadmium -plated brass binder head screws. Terminal blocks used for the applied AC power shall be capable of securing conductors with a 10-32, or larger, nickel or cadmium -plated brass binder head screws. There shall be twelve -position field terminal blocks for the connection of loop detectors. A minimum of 12 spare terminals shall be provided. Two equipment grounding buss shall be provided in each cabinet. The ground buss shall be grounded in the cabinet, and shall provide at least fourteen (14) terminals each. Ground buss will be located one on each side of the cabinet. All number identifications for the terminal blocks shall be silk screened or engraved on the terminal block board. 8-90.6 Power Panel: The cabinets shall have a power distribution panel containing the following elements: a. 50 amp radio interference suppressor b. 40 amp main circuit breaker C. 20 amp auxiliary circuit breaker d. Solid state flash transfer relay e. Neutral buss bar isolated from the cabinet f. Transient voltage protector g. Cover h. 20 amp Video circuit breaker 1 15 amp Equip. circuit breaker The solid state flash transfer relay shall normally be closed and capable of switching 75 amps, 120 volts AC. The two neutral buss terminals shall be easily accessible and provided with at least 14 terminals, and shall not be grounded to the cabinet 1 neutral bus on each side of the cabinet. An additional AC neutral buss with twenty (20) positions shall also be provided. 8-90.7 Transient Protection: The transient voltage protectors shall be installed to protect all electrical components within the cabinet from voltage abnormalities of less than one-half cycle duration. The protectors shall be solid state, high-energy circuit, containing no spark gap, gas tube or bar component. Normal service capacity shall be not less than 15 amperes. 8-5 Revision 10/27/2014 The protection provided shall be a transient suppression of 200 volts peak, a transient response of less than five (5) nanoseconds, a power dissipation of 10,000 watts. The protector shall function with 10 x 1000 microsecond wave from clamping no greater than 200 volt peak. 8-90.8 Police and Auxiliary Panel: The cabinets shall have an auxiliary maintenance panel located inside the door and a panel located outside the door containing the following elements: 1. Police Panel (outside) a. Auto / Flash switch 2. Auxiliary Panel (inside) a. Convenience outlet with ground fault interrupted protection rated at 25 amps b. Auto/Flash switch C. Rest green/red switch d. Stop time switch e. Controller On/Off f. Vehicle detector input switches g. EPV input switches h. Ped detector input switches 8-90.9 Police Flash: Two Flash -Automatic switches shall be supplied. One switch shall be located behind the Police panel door. When this switch is turned to FLASH position, the signals shall immediately revert to flash; and stop -timing will be applied to the Controller. When the switch is placed on AUTOMATIC, the signals shall continue to flash for an additional eight -second flash period. At the completion of the continued eight -second flash period, unless otherwise specified, the Controller shall immediately resume normal cycle operations at the beginning of artery green. 8-90.10 Auxiliary Panels: The second Flash -Automatic switch shall be placed on the Maintenance Panel. When this switch is placed on the FLASH position the signals shall immediately revert to flash; however, the Controller shall continue to function. When the flash automatic switch is placed in the Automatic position, the Controller shall immediately resume normal cyclic operation. The controller on/off switch shall be a two (2) position toggle switch labeled "Controller On/Off." In the ON position, the controller shall run normally. When placed in the OFF position, AC+ power shall be removed from the controller and flash power AC+ shall be applied to the flash transfer relays, causing the signals to go on flash. When placed from the OFF to the ON position, the controller shall sequence through power up. The Controller power switch shall be electrical interconnected with the inside AUTO -FLASH switch such that the Controller power switch will only remove power from the Controller when the inside AUTO -FLASH switch is in the FLASH position. The rest green/red switch shall be labeled "Rest Green/Red." In the rest green position, the controller with a lack of calls shall rest in the last phase green. Within the rest red position and with a lack of call, "Call -A -Way" shall be applied and the signals shall display all red. 8-6 Revision 10/27/2014 The stop time switch shall be a three position switch labeled OFF -AUTOMATIC -ON. When the switch is in the AUTOMATIC position, the controller will sequence automatically; when the switch is in the ON position stop time will be applied; and when in the OFF position stop time shall be removed from the controller. Labels for all switches shall be applied via a silk screen or engraving process. 8-90.11 Detectors: The cabinet mounted equipment shall consist of 2-8 position card racks, 2 channel detector modules, and wired for 2 channel operation. Switches with separate operate, test, and OFF positions shall be provided for each field detector input circuit as a plug in card module in the vehicle detector racks. A display LED indicator lamp will be provided for each switch and will illuminate upon vehicle, pedestrian or test -switch actuation. The test -switch shall provide a spring-loaded momentary contact that will place a call into the controller. When in the OFF position, respective detector circuits will be disconnected. In the operate position, each respective detector circuit shall operate normally. Each detector unit will be model C-1200 series and shall include two complete detector channels, detector switch panels will be model SP301 manufactured by Reno A&E or most current models and 24 -volt power supplies. The detector module shall incorporate LED display, minimum eight sensitivity settings. The system shall be capable of operating in four modes: Presence, Extended Presence, Pulse, and Inhibited Pulse. All such units shall be rack mounted in the controller cabinet. Rack shall be wired to accommodate two (2) channel Detector Units. Each channel shall sequentially energize its loop inputs to eliminate crosstalk (mutual coupling) between large, very closely spaced adjacent loops connected to the same unit. The sequential time sharing and digital processing of loop inductance data shall be accomplished on a single LSI micro -circuit per unit for maximum reliability. The method of measurement shall be crystal reference digital period counting, multi -channel scanning. Only one channel input per unit shall be active at any point in time. 8-90.12 Emergency Vehicle Pre -Em tions: Controller cabinet will be wired for discriminator modules. If the units are not compatible with the optical emitters presently mounted in the Fire Station vehicles and Transit agency vehicles, either the units shall be adequately modified or auxiliary equipment supplied and interconnected such that they are compatible. All such units shall be rack mounted in the controller cabinet. Rack shall be wired to accommodate two (2) two (2) channel units or one (1) channel unit of the newest version manufactured by 3M Opticom. No daughter board units will be allowed. Discriminator modules shall supply power to and received input from the detectors. Each module shall incorporate connections for four optical detectors, one for each channel. Have an auxiliary board to facilitate advance detectors. When valid detector signals are recognized by the module, they shall provide an output to the controller through an optically isolated NPN transistor. 8-7 Revision 10/27/2014 The discriminator module shall incorporate the following features: 1. Four channels 2. Two priority levels. Priority I vehicles shall produce a 6.25 Hz output, while higher Priority II vehicles shall produce a steady ON condition. Priority demand shall be provided on a first come, first served basis. At all times, Priority II vehicles shall have precedence over Priority I vehicles when both are active. 3. Capability for assigning one of the two priority levels to traffic movement on any of the four channels. All pre-emption equipment shall be completely wired together and interfaced with the controller to provide a properly functioning system. 8-90.13 Dis laay Panel: A display panel showing signal indications shall be included. The intersection panel shall depict the general intersection layout, street name, phase and overlap identification, and north arrow. Appropriately colored, LED indicator lamps for each red, amber, flashing amber arrow, green, walk and don't walk, for every phase and overlap, shall be provided. The locations of the display lamps on the panel shall simulate the field locations of associated signal displays. The intersection display LEDs shall be wired to appropriate field wire terminals. The panel shall be located on the inner side of the door. Switches shall be provided on the panel with labels and functions as follows: a. Display On -Signal indicator LEDs will display the exact operation of the intersection. b. Test -All signal indicator LEDs shall be energized. C. Display Off - All signal indicator LEDs shall be de -energized. The display panel shall include an approved means of disconnecting all wiring entering the panel. All display LEDs shall turn off when the cabinet door is closed by a door switch or automatically extinguish after a 15-20 minute period of non-use. 8-90.14 Installation: All wiring harnesses, brackets and other devices necessary to mount the equipment in the controller cabinet and to make all electrical and mechanical connections shall also be supplied, installed and connected. All rack equipment to be installed in the controller cabinet shall be securely mounted and readily accessible. All wiring shall be neatly cabled together and securely fastened to the cabinet or other support structures. 8-90.15 Documentation: Included with the cabinet wiring diagrams shall be schematic diagrams for load switch bay circuit back panel, all detector amplifiers, MMU, flashers, load switches, auxiliary control panels and pre-emption circuits. 8-8 Revision 10/27/2014 All diagrams shall contain a parts listing unless the part number is shown on the parts. Parts that are not common items available in stores shall have the vendor's name and address listed within the parts listing for said part. One reproducible mylar and three sets of blueprints shall be provided. One reproducible on mylar and a compact disk with an AutoCAD compatible drawing file and in a PDF format and DWG(if available) of the as -built cabinet wiring diagram and component wiring diagram shall be furnished with each cabinet. Each cabinet shall be equipped with a plastic envelope to house one or more cabinet wiring diagrams. The cabinet wiring diagram shall indicate and identify all wire terminations; all plug connectors and the locations of all equipment in the cabinet. Included in the diagram shall be an intersection sketch identifying all heads, detectors, and push buttons; and a signal sequence chart. 8-90.16 Communications: The communications ports on the controller will be the controller manufactures FSK telemetry unit, data key, Ethernet port with the most current version of software. The unit shall be configured for four wire, multi drop, operation and lightning arresters shall be provided at the field connection point for the four wire interconnect. 8-90.17 Extra Components: The Supplier shall submit with his bid proposal a list of spare parts he recommends the City stock for maintenance of these intersections. The list shall include a current price list with any discount that may apply. Prices included on this list shall not be used in determining award of the bid. The list shall include, but not be limited to, the following: 1. Module circuit boards 2. Indicator lamps where applicable 3. Solid state flasher 4. Malfunction Management Unit 5. Solid state load switches 6. Four / Two channel loop detector amplifiers No spare parts are to be supplied with this bid proposal. 8-100 TESTING OF TRAFFIC CONTROLLER: The Contractor shall deliver the traffic signal controller mechanism and signal controller cabinets involved in this contract for bench testing to the Electronics Department, City of Bremerton. The Contractor shall totally assemble all control mechanisms and connect signal load terminals to lamps simulating the traffic signal displays to be constructed over the roadways. The Contractor shall then demonstrate the total functions of all equipment required by the contract. The demonstration shall evidence all signal displays, overlapped displays, pre-emption sequences, etc., as required within this contract, flashing displays, other special sequence displays as may be defined within this contract, vehicle detector function and minimum and maximum timing performance of every timing element required by this contract. The test demonstration shall first be conducted at normal design voltage of the equipment and thereafter repeated at +15% and -15% of that design voltage. 8-9 Revision 10/27/2014 Every module or device, i.e., synchronization units, special sequence units, flash relay assembly, special timers, etc., shall have affixed thereto name tags or name plates stating the component's function within the composite signal device. The Contractor shall notify the Engineer five demonstration, and shall make available to demonstration four (4) complete sets of the technical data necessary for use by City demonstration: (5) working days in advance of the functional the Engineer before the start of functional following diagrams, manuals and any other personnel who will witness the functional 1. Wiring diagram for composite system. 2. Service manuals for all composite parts. 3. If electronic logic external to controller mechanisms is used to obtain signal functions, logic diagrams identifying all gating and Switching performed by the logic components shall be provided. Satisfactory performance of all functions required by the foregoing demonstration shall be considered at the start of a ten-day evaluation test period. If malfunction of any component occurs within the ten-day evaluation test period the test shall stop at the time of component malfunction and shall not resume until the Contractor has caused the defective component to be repaired or replaced, as directed by the Engineer. If any component malfunctions or breaks down within the last 72 hours of the test period, the test shall stop until the defective component has been repaired or replaced, and the test shall be resumed for a minimum of 72 hours continuous satisfactory operation. Even though this may extend the ten-day evaluation test period under no condition shall any part of the signal control mechanism be disassembled and/or removed from the demonstration site until the foregoing test has been satisfactorily concluded, and shall include the final 72 hours trouble-free operation of the entire, integrated signal control mechanism. The demonstration by the Contractor of all components functioning properly shall not relieve the Contractor of any responsibilities relative to the proper functioning of signal control equipment when field installed. Upon satisfactory completion of the test, it shall be the Contractor's responsibility to transport all signal control enclosures from the City of Bremerton's Electronics Department to the project. All costs of the functional demonstration and evaluation test shall be included in the lump sum bid. 8-110 TRAINING SESSION: The Contractor shall arrange for the signal manufacturer's local authorized representative to conduct a minimum of 8 hours of training session in the theory of operation and the maintenance of the traffic signal controller equipment. The Contractor shall provide the Engineer no less than five (5) working days advance notice prior to the presentation of the training session. Those personnel in attendance at the training session shall be provided complete manuals and other material necessary for operation and maintenance of this equipment. The training session shall occur during the ten day shakedown period of the control mechanism as discussed elsewhere herein. The training session shall be held at the Electronics Department, City of Bremerton. The above described minimum eight (8) hour training session shall be considered incidental to other bid items on the proposal. 8-10 Revision 10/27/2014 8-110.1 Additional Training: In the event that additional training time is required by the City in the use and operation of intersection controllers including programming, general equipment maintenance and/or diagnostic equipment, the Contractor shall arrange for the signal manufacturer's local authorized representative to provide a minimum of four (4) hours additional training at a location agreeable to the City. Bid price shall be per hour of additional training time. 8-120.1 Pad Mounted Cabinets: The 8 -phase traffic signal controllers and accessories shall be housed in Type P pad mounted, single door, weather-proof, outdoor cabinets manufactured by Cascade Signal Corp. of WA. To the city of Bremerton layout standard with adequate shelf space to accommodate all controllers and auxiliary equipment called for in these provisions and contract plans including a retractable drawer to hold drawing and a laptop computer. Nominal external dimensions shall be: width -44", depth -26", height - 65". The concrete pad shall have 36" of pad on door side of cabinet and a minimum of 12" on all remaining sides. The side walk can be included in the pad size. The door shall not face the street side The outside of the housings shall not be painted. The inside shall be painted white with two coats of factory applied aluminum paint. The cabinets shall be constructed of sheet aluminum at least 0.125 of an inch thick and adequately reinforced. The main cabinet door shall be provided with a BEST blue construction lock. Cast cabinets shall have an approved one point positive latch. Formed cabinets shall have a three point latch. The auxiliary door shall be equipped with a lock for a standard police key. Two (2) keys shall be furnished for each police door lock. When the door is closed and latched, with the key removed, the door shall lock. The Contractor shall furnish two (2) keys for the main cabinet door. Four (4) Best Cores will be ordered with City of Bremerton Specifications for Installation after construction. The cabinets shall be equipped with a door stop assembly to hold the door open at 90 degrees and at 135 degrees. All cabinet wiring harnesses shall be neat, firm and routed to minimize "crosstalk" and electrical interference. Printed circuit mother boards may be used to eliminate or reduce cabinet wiring. All conductors and live terminals, or parts which could be hazardous to maintenance personnel, shall be covered with suitable insulation material. 8-11 Revision 10/27/2014 8-130 VEHICLE DETECTION SYSTEM: The vehicle detection system and equipment shall conform to all criteria contained in Section 9- 29.18 of the Standard Specifications and including the City of Bremerton Design Standard details 8001, 8002, 8003, 8004, 8005 as included herein. Vehicle detection equipment compatible with field installed induction loops and lead-in cables shall be furnished and installed in the controller cabinet. The equipment, when used in conjunction with the field installed loops, shall be capable of detecting the presence or passage of automobiles, trucks, motorcycles, and bicycles. The electronic circuitry shall be self -tuning to compensate for changes in environmental conditions, including temperature, humidity, and stalled vehicles. The system components shall be capable of operating on 120 volt AC+10%, -15% and shall function normally without manual adjustment in a temperature range of -20F to 165F. Detector units shall have optically -isolated transistor outputs. Relays shall be used for interface with electro -mechanical controllers, traffic counters, parking gates, etc. Optically isolated outputs may be specified for interface with existing or new solid state controllers and computer systems. Controls for selection of sensitivity, mode of operation, and reset/circuit breakers shall be front panel accessible. The front panel shall include an erasable, write -on channel identification area and clearly indicated switch operating positions via the LCD display on each unit. Sequential scanning shall fully prevent crosstalk between channels of a detector connected to closely spaced or overlapped loops for directional detection. Sequential scanning shall allow two detection channels to operate with full performance using a common four conductor home -run cable. Sequential scanning shall allow two or more detection channels to be connected to a single detection loop with full operating performance, including separate mode and sensitivity selection capability on each channel. Each channel of the sensor unit shall automatically self tune to any loop and lead-in inductance from 20 to 2000 micro henries within 10 seconds after application or interruption of supply voltage. Units shall also track changes in loop/lead-in electrical characteristics, as might reasonably be expected to occur in undamaged loops, properly installed in sound pavement, without producing false indications or changes in sensitivity. Each channel shall retune and detect properly, immediately following reconnection of the broken (open) circuit. Previous 'open" loop/lead-in connections shall be held in memory for recall and verification via a front panel 'open loop test" switch. 8-12 Revision 10/27/2014 Each detector unit shall be provided with a loop test switch position to verify loop system integrity and reduce maintenance costs. The "open loop test" position shall indicate a previous fault via the front panel indicator. The memory shall remain intact and can be queried repeatedly. Existing detections shall not be reset and the memory shall only be reset by power interruption as by pressing the circuit breaker/reset button on AC powered units, or removing and re-inserting the plug-in detector units. Each channel shall have the capability to allow selection of,8 Pulse sensitivities, 7 Presence levels and an "Off' position. The sensitivity setting shall offer 2:1 steps over a range of 128:1 to enable selection of the proper sensitivity (threshold) to insure detection of all licensed motor vehicles (including 70cc motorcycles) without detecting automobiles in the adjacent lane, moving or stopped, within 36" of the loop(s) described in the following configurations, each with 50', 500', and 1000' of lead-in cable. Three -turn Square loops: Single 6'x6' loop Four 6'x6' loops Four 6'x6' loops Three 6'x6' loops for left turn applications Three -turn Round Loops: Single 5'x5' loop Four 5'x5' loops Four 5'x5' loops Three 5'x5' loops - Series/Parallel connected - Series connected - in series with special bicycle loop Two -turn loops: (note) Long loops require special configuration to insure adjacent lane rejection (i.e., left turn lanes). Single 6'x30' loop Single 6'x30' loop (2-4-2 wire count) 8-140.1 General Operation: The emergency pre-emption equipment shall provide signal operation and display as indicated in these Specifications. Activation of the pre-emption equipment shall cause the signal to sequence as follows: The phase or phases which are in the green interval and are not to be in the green interval during the pre-emption mode shall immediately begin a yellow clearance interval before displaying red. Such pre-emption shall not take place during the timing of initial or yellow clearance. The phase or phases which are in the green interval and are to be in the green interval during the pre-emption mode shall remain in the green interval. The phase or phases which are in the red interval and are to be in the green interval during pre-emption mode shall advance to the green mode immediately following display of the red indication on any conflicting movements. 8-13 Revision 10/27/2014 When the signal display conditions specified for a particular detector actuation have been completed, the indicator light (specified later) associated with that detector shall be activated by a solid state output and indicate a steady light throughout the pre-emption mode. Termination of the pre-emption mode shall cause the controller to immediately provide the normal clearance interval for the pre-emption phase displayed. The controller shall then advance to the next phase to which it would normally proceed following this phase. Manual switches shall be provided in the controller cabinet to simulate remote emergency pre- emption input. The indicator light shall not be activated until immediately after the intersection signals are displaying pre-emption conditions associated with the phase activated by the pre-empt detector. 8-140.2 Detectors: The unit shall be capable of receiving optical pulses from an OPTICOM emitter and converting these signals to electrical impulses compatible with the other control equipment. The unit shall employ solid state circuitry and shall have a detection range adjustable between 1800 feet and a few feet. The detector shall be capable of receiving an impulse from an emitter located within an area approximately 120 feet on each side of the detector centerline at 1800 feet distance from the detector. Detector units will be of the newest version manufactured by Opticom. 8-140.3 Indicators Light: A light shall be provided which will indicate to approaching emergency vehicles that the signal has advanced to the pre-emption mode associated with the corresponding detector. The housing shall be constructed of cast iron or aluminum. All cast iron parts shall be galvanized while all fasteners shall be galvanized or stainless steel. Indicator lamps Use Sylvania LED PAR20 36 120v 8W" A neoprene gasket shall be installed between the lens and housing which will provide a watertight seal when the lens is secured in position. The entire unit shall be weather tight and vibration proof. 8-150 FOUNDATION FOR CONTROLER CABINETS: The base foundation shall conform to State of Washington Standard Plans and Sections 8-20 and Section 6-02 of the Standard Specifications. Except foundation will include a pad for maintenance of the cabinet, minimum size is cabinet depth plus 12" on each side and 36" on door side. All foundations will include a 3/8" diameter plastic drain. 8-160 EQUIPMENT: The equipment comprising a Traffic Controller Assembly shall be identical to that specified in these Specifications and shall include, but not be limited to: 8 -phase controller and all auxiliary equipment described in Section 8-80 of these Specifications. Controller cabinet as described in these Specifications. 8-14 Revision 10/27/2014 Electrical Service as described in Drawing 8007 and in the City of Bremerton Division 7 Street Lighting Specifications. Vehicle detection equipment as described in Section 8-90 & 8-130 of these Specifications. Emergency vehicle pre-emption and transit pre-emption equipment as described in Section 8-90 & 8-140 of these Specifications. All equipment shall be assembled, tested and delivered to the City of Bremerton Electronics Shop in Bremerton ready for operation. All equipment shall be capable of providing full 8 -phase operation as described herein. 8-180.1 Vehicle Detector L000s: 8-180.1(A) Materials: All wiring for loop detectors shall comply with the requirements of Section 9-29.3 (7) and (8) of the Standard Specifications. 8-180.1(8) Installation: All vehicle detection loops shall be completely installed by the Contractor including saw -cutting, laying -wire, testing and sealing. Splices will be allowed only where unshielded loop wire is joined to shielded lead-in wire in the closest junction box. All splices will be made is a ridged 2 piece plastic resin filled tank Proper installation of vehicle detection loops is vital to the performance of the controller and special care shall be used at all times. Special instructions given by the Engineer and these Special Provisions shall be adhered to. Loop installation shall conform to Manufacturer's recommendations. Conductors of lead-in pairs from all loop detectors shall be identified by the following labeling practice. Where the detector loop wires from the clockwise laid loop, by convention, enter the curb side of the junction box and connect to shielded lead-in cable, each twisted pair of loop wires shall be coded with PVC sleeve bearing as its identification the loop number indicated on the wiring schematic drawings. Vehicle loop detector wire shall be placed in the roadway in accordance with the Plans and City of Bremerton Standard Plan 8005. The loop location shall not be altered by the Contractor without the express permission of the Engineer. After the lead-in and loop saw -cuts are completed, the slot shall be thoroughly blown out with 100 PSI air pressure. Any rocks or sharp protrusions shall be removed. If traffic is allowed to travel over the saw cuts, they shall be blown out again before placement of the wire and sealing. The wiring shall be installed with a blunt nosed wooden wedge. Care shall be taken not to pull the wire. There shall be slack at each corner. 8-15 Revision 10/27/2014 All loops shall have the insulation resistance tested at 500 volts D.C., and installation approved by the Engineer before filling the saw -cuts with crack pouring compound. Acceptable tests will measure between 100 megohms and infinity. The Contractor shall furnish the Engineer with three copies of the test results. Proper performance of the loops shall be the responsibility of the Contractor but no additional payment shall be made to the Contractor for additional work required to make the loops operable. Saw cuts shall be filled with crack pouring compound before being exposed to traffic, where possible. The Contractor shall take care to ensure that no air bubbles or foam are entrapped in the saw cut. Crack pouring compound shall be approved by the Engineer. Acceptable crack pouring compounds are: 1. CRAFCO #34271 Loop Sealant or approved equivalent. 8-180.1(C) Tem: All amplifiers shall be tested at the Electronics Department, City of Bremerton, Washington. A test shall be made of the inductance of the loop and recorded in the Electrical Inspector's Handbook upon completion of each amplifier circuit. Testing shall conform to Section 8-20.3 (14) D Standard Specifications. All tests shall be performed by the Contractor in the presence of the Engineer for each loop. The tests shall be performed at the amplifier location after complete installation of the loop. All costs associated with testing shall be incidental to the unit contract prices of the respective bid items. Test A - The DC resistance between the two lead-in cable wires will be measured by a volt ohmmeter. The resistance shall not exceed 10 OHMS. Test B - An insulation resistance test at 500 Volts DC shall be made between the lead-in cable shield and grounding prior to connection to grounding. The resistance shall equal or exceed 100 megohms. Test C - A megger test shall be made between the loop circuit and grounding. The resistance shall equal or exceed 100 megohms. Test D - An inductance test to determine the inductance level of each inductance loop. The Contractor shall record the inductance level of each inductance loop installed on the project and shall furnish the findings to the Engineer. An inductance level below 150 microhenries is considered a failure for a Type 1 loop, any one round loop and an inductance level below 75 microhenries is considered a failure for a Type 2 loop. If any of the installations fails to pass all tests, the loop installation and/or lead-in cable shall be repaired and replaced and then retested. Detection shall be positive for all vehicles passing through the loop from 0 to 80 miles per hour. Detection shall be positive for all classes of vehicles from motor bikes to tractor -trailer combinations. 8-16 Revision 10/27/2014 8-180.2 Conduits: Installation and material shall conform to Sections 8-20 and 9.29 of the Standard Specifications, except as modified herein and to appropriate articles of the latest edition of the National Electrical Code. Conduit to be installed underground across roadways or across driveway shall Schedule 80 PVC conforming to the National Electrical Code. All conduit installed underground shall have Polyethylene Underground Hazard Marking Tape, 6 inches wide, legend "Caution -Electric Line Buried below", placed approximately 12" above the conduit. Conduit to be installed above ground shall be rigid metal type conforming to Article 346 of the National Electrical Code and must contain an equipment ground conductor with a minimum size of 8 awg insulated copper. Conduit installed underground along the edge of the roadway shall be PVC non-metallic conduit Schedule 80 unless otherwise noted in the wiring schedule and must contain a equipment ground conductor with a minimum size 8 awg insulated copper. Conduit installed underground outside the driving area of the roadway shall be PVC rigid non-metallic conduit Schedule No. 40 unless otherwise noted in the wiring schedule and must contain a equipment ground conductor with a minimum size 8 awg insulated copper. P.V.C. conduit shall conform to the National Electric Code. Size of conduit shall be as shown on the Plans, but not less than that required to meet the requirements of the National Electrical Code. A 200 pound minimum breaking strength Pull string with footage measurements shall be installed in each run of conduit between junction boxes. Conduits will have foam plugs installed in all unused conduits and duct seal or foam plugs in all conduits with conductors. 8-180.3 Conductors: All electric cables and conductors used through this project shall conform to the requirements of Section 9-29.3 of the Standard Specifications, except as required elsewhere in these Special Provisions. The conductor insulation shall be of the respective (red, yellow, green) colors as specified in the schematic wiring diagram. Five (5) conductors (IMSA Spec. 19-1 or 20-1) shall be used for signal head circuits. Wiring schedules have been included on the plan sheets to aid the Contractor. If there should be a discrepancy between the wiring schedules and the wiring diagram, the wiring diagram shall govern. Every end of every conductor at each wire termination, connector or device shall have a PVC wire marking sleeve bearing as the legend the circuit number indicated in the wiring schematic drawings. If the Contractor elects to put in additional spares, spare conductors shall be numbered consistent with the approved schematic wiring diagram as described herein. In 8-17 Revision 10/27/2014 addition to the foregoing, where terminal strips also bear the circuit number consistent with the wiring schematic the field wiring terminal in the signal cabinet shall be numbered consistent with the Contract plans. All cabinet wiring harnesses shall be neat, firm and routed to minimize "crosstalk" and electrical interference. All wiring shall be neatly cabled together and securely fastened to the cabinet or other support structures. The Contractor shall provide red -lined print of the wiring diagram showing as -built information of the field wiring prior to the acceptance of the job by the City. 8-180.4 Splicing: No splicing of any traffic signal conductors or detector conductors shall be permitted, including service wires. Only terminal boards with pressure type binding shall be used in any conductor for signal heads or detectors. The only exception shall be the splice in detector loops at the nearest junction box to the buried pavement induction loop. See Standard Plan J-50. 8-180.5 Concrete Junction Boxes: Concrete junction boxes shall conform to the requirements shown on the State of Washington Standard Plans. The cover plates shall have the letters "TS" welded to them and will be locking with a SS penta head bolt. All exposed steel will be galvanized by the manufacturer. Boxes shall be of sufficient size to easily accommodate required conduit or as specified on the plans. All Junction Boxes will have a minimum of 6" pea gravel pad underneath. Conduits terminating in concrete junction boxes shall terminate not less than five inches nor more than nine inches below the lid of the box. Every conduit entering such boxes shall be neatly upswept and contain an equipment ground with a minimum size 8 awg. The only conduit bends permitted shall be either factory bends or those formed by the use of an approved conduit bending tool employing correctly sized dies. Conduit entering any electrical enclosures shall be positioned to avoid bending or cutting cabinet braces and cross members that are formed as a part of the electrical enclosure or its pedestal. Such bending or cutting is expressly prohibited. 8-190 EXISTING PAVEMENT AND PAVED SURFACES: The installation of conduits and associated junction boxes, signal poles, and conductors may require the removal of certain already paved and/or landscaped surfaces. It shall be the responsibility of the Contractor to make such removals as is required for his work and perform temporary patching and maintenance. Permanent repairs will be made by the Contractor in conformance with Section 3-3.5, after all tests have been satisfactorily completed and before acceptance of the work. Removals and repairs performed in the course of signal installation shall be incidental to the lump sum bid for the signal system complete. Where asphalt concrete paving is included in the contract, all installation of conduits, induction loops, etc., requiring pavement sawing or trenching shall be completed prior to the final overlay. Pavement patching shall be scheduled to accommodate the demands of traffic and shall be performed as rapidly as possible to provide maximum safety and convenience to public travel. 8-18 Revision 10/27/2014 8-200 SIGNAL DISPLAY 8-200.1 Traffic Signal Heads: All traffic signal heads employed on this project shall be 12 inch heads and shall be consistent with the requirements of Section 9-29. of the Standard Specifications and the State of Washington Standard Plans and as indicated on the Contract Plans with the exception that all vehicles displays be made up entirely of led and all arrow indications to be 3 row design by the same manufacturer. Each signal head shall have 3/16" drain hole. Polycarbonate traffic signal heads, visors or lenses are not acceptable. Mounting of traffic signal heads shall conform to 9-29 Standard Specifications for mast arm and span wire mounted signals. The heads shall be adjusted in the field, such that a person standing on the pavement, a distance four times the speed limit in feet from the stop bar, shall see the brightest image of the red section. All heads shall be plumbed as viewed from the direction in which they face. Leveling of all signal heads shall be by reference to the red signal sections. 8-200.2 Backlaa tes: Traffic signal heads shall be furnished with back plates as shown on the Plans. Back plates shall conform to Section 9-29 of the Standard Specifications. 8-200.3 Pedestrian Heads: Pedestrian signals shall be LED countdown, modular type, with international symbols and shall conform to the requirements of 9-29 of the Standard Specifications with the exception that aluminum housings shall not be required and the displays are made entirely of LED's. Housings of equal quality shall be considered for approval. Housings shall be mounted such that normal access to the interior is provided. 8-200.4 Pedestrian Push -Button: Where shown on the Plans, pedestrian push-button conforming to Section 9-29 of the Standard Specifications, Current Edition, and State of Washington Standard Plans, and be Campbell Advisor AGPS57YR10-3E shall be furnished and installed. Verify all mounting heights prior to installation with the City of Bremerton Engineering Division. 8-210 TRAFFIC SIGNAL STANDARDS WITH MAST ARMS: All Signal standards with mast arms will have junctions as shown on City Standard Drawing 8006. Signal arm traffic signal supports with signal mast arm lengths less than 45 feet and with projected wind load areas, including future back plates, less than the allowable values indicated in Standard Plans section J may be fabricated in accordance with the methods and materials specified in Standard Plans section J, provided all other requirements, of the Special Provisions are also satisfied, in conformance with the following pre -approved plan: Pre -Approved Plan Drawing No. TB -10164-R Drawing No. 5000-1-R Fabricator Union Metal Manufacturing Co. Valmont 8-19 Revision 10/27/2014 Combination single arm traffic signal pole and luminaire standards with single mast arm lengths of less than 45 feet; with laminar mast arm lengths of less than 16 feet; and with projected wind load areas, including future back plates, less than the allowable values indicated on Standard Plan J, may be fabricated in conformance with the methods and materials specified in the following pre -approved plan, at the specified mounting height, provided all other requirements of the Special Provisions are satisfied: Pre -Approved Plan Fabricator Mounting Height Drawing No. 71026 -F2 -R2 Union Metal Drawing No. 5000-1-R1 Valmont 40 and 50 feet Signal Standards that exceed the previously mentioned limiting values may be fabricated consistent with shop drawings that meet requirements of the latest ASSHTO Standard Specifications for structural supports for highway signs, luminaires and traffic signals, provided the signal mast arm can is 5 degrees, the handhole conforms to the details on Standard Plan section J: and Drawing 8006. The luminaries arm connection, if required, must have special approval; complete calculations for structural design, including foundation and anchor bolt details have been submitted with the shop drawings and other requirements of the Special Provisions have been satisfied. The Contractor shall submit for approval 8 sets of shop drawings to the Engineer for each of the following types of standards proposed for use on this project: (A) Traffic Signal Standards (B) Combination Traffic Signal and Lighting Standard (C) Pedestrian Signal Standards (D) Metal Strain Poles (E) Pedestrian Push Button Posts If traffic signal standards or combination traffic signal and lighting standards are proposed, final verified dimensions including pole base to signal mast arm connection point, pole base light source distances (1-11), mast arm length, offset distances to mast arm mounted appurtenances and orientations of pole mounted appurtenances will be furnished by the Engineer as part of the final approved shop drawings prior to fabrication. The area of the face of each mast arm mounted signal head with back plates shall not exceed the amount for each combination head shown on the plan. The design weight of each signal head and plumb riser shall be the exact per manufacturer's specifications for each combination of sections and appurtenances. Complete calculations for structural design shall be submitted with the shop drawings for approval before fabrication or ordering materials. 8-20 Revision 10/27/2014 These calculations shall include stresses in the pole and cantilever arms, attachment of signals to the structure, connection between cantilever arms and vertical pole, pole session at handhole, base plate anchor plates, and foundation. The submittal shall include material and welding specifications, and details of the foundation and anchor bolts. The traffic signal support structure shall consist of a single vertical pole erected on a concrete foundation, with one cantilever signal arm or one cantilever signal arm and one luminaire arm as shown on the plans. After signals have been installed, the poles shall be plumbed and the cantilever arms shall have an upward slope away from the pole that shall not exceed 0.05 ft/ft except where specified elsewhere in this section. The vertical clearance to any portion of the signal heads nearest the pavement shall be a minimum of 16'6" and a maximum of 18'6". The poles and arms shall be tapered tubes round or octagonal in cross-section. The size of the arm where it connects to the pole shall not be larger than the pole's size at that height. The largest gauge pole thickness shall be chosen such that the pole diameter shall be a minimum. A handhole with cover shall be provided in the pole within 18" of the base, and there shall be approved wire way fixtures installed to facilitate pulling wire from the base of an outlet at each signal after the structure is erected. The finished structure shall be rain tight. Conduit terminating in the pole base shall be aimed toward the handhole opening. The pole base shall accommodate the conduit stubbed up from the foundation. The pole base shall be drained by a 1/2" drain pipe through the grout pad. Leveling nuts on the anchor bolts shall be furnished for use in plumbing the pole. The drain pipe shall be copper. Tamper resistant covers shall be provided for the anchor bolts. All materials and work shall be in accordance with Section 8-20and Section 9-06 of the Standard Specifications. Structural steel having a minimum yield point of 33,000 PSI or more shall be used for all structural parts, and it shall be galvanized after fabrication per ASTM A-123. The foundation concrete shall be Class B mix and shall have reinforcing steel as required by the design loads. The following loads shall be used: dead load shall consist of the weight of the signals, signs, appurtenances and supporting structure, wind load shall be taken as 35 PSF for the signal heads, and 25 PSF for the supporting structures (which valves account for the effects of gust and shape factors) on the greatest area of signals, signs, and structure in any elevated view; live load and ice load may be omitted. . 8-210.1 ! uminaires. Wiring and Photo Electroni Controls: Luminaires, wiring and photo electric controls shall be LED type and conform to all applicable portions of Section 8-20 and Section 9-29 of the State of Washington Standard Specifications except as modified herein. 8-210.2 Foundation for Traffic Signal Standards With Mast Arms: The base foundation shall conform to State of Washington Standard Plans section J and Sections 8-20.3(4)and Section 6-02.3 of the Standard Specifications. 8-21 Revision 10/27/2014 8-210.3 Installation of Signal Standards With Mast Arms: All work shall be in conformance with Section 8-20.1 (1) of the Standard Specifications for the safe installation of signal standards. The Contractor shall take care to handle the material in such a manner that marring, overstressing or soiling of the fixtures does not occur. If it is necessary to inhibit the flow of traffic around the area, or if there is any danger to adjacent traffic, as determined by the Engineer, then proper traffic control procedures shall be utilized as noted elsewhere in these provisions. 8-210.4 Fabrication For all Components: Where bolts, nuts, flat washers, screws and rivets are mixed or used with aluminum, they shall be stainless steel or bronze only, except that anchor bolts shall be in accordance with the Standard Specifications. Galvanized components may be used as part of the slip fitter assembly. All aluminum surfaces in contact with steel or concrete shall be given one coat of zinc chromate primer paint conforming to U. S. Federal Specification TTP -645. 8-210.5 Sianal Pole Attachments: All attachments shall be located in the field and allwire entrances into the pole shall be drilled or punched in the field. All drilled or punched surfaces shall be carefully reamed and/or deburred before application of a coat of galvanic paint. The Engineer shall confirm the location and mounting heights of all pole attachments located in the field prior to installation. 8-220 REMOVAL OF EXISTING SIGNAL EQUIPMENT & STRUCTURES: Existing signal equipment remains the property of the City. No existing signal equipment or structures shall be removed until approved by the Engineer. When so directed, the Contractor shall carefully remove the existing signal equipment and deliver it to the area designated by the Engineer. Removed span cables and signal cables shall be disposed of by the Contractor. When so directed, the Contractor shall remove existing signal structures (pole foundations, controller foundations, j -boxes, conduit, poles, etc.) and dispose of them. The poles and j - boxes shall be delivered to a storage site in the City as directed by the Engineer. All equipment from the existing controller shall be evaluated by Electronics for salvage. 8-22 Revision 10/27/2014 III. AMENDMENTS TO THE STANDARD SPECIFICATIONS 1 INTRODUCTION 2 The following Amendments and Special Provisions shall be used in conjunction with the 3 2016 Standard Specifications for Road, Bridge, and Municipal Construction. 4 . 5 AMENDMENTS TO THE STANDARD SPECIFICATIONS 6 7 The following Amendments to the Standard Specifications are made a part of this contract 8 and supersede any conflicting provisions of the Standard Specifications. For informational 9 purposes, the date following each Amendment title indicates the implementation date of the 10 Amendment or the latest date of revision. 11 12 Each Amendment contains all current revisions to the applicable section of the Standard 13 Specifications and may include references which do not apply to this particular project. 14 15 Section 1-07, Legal Relations and Responsibilities to the Public 16 January 4, 2016 17 1-07.1 Laws to be Observed 18 In the second to last sentence of the third paragraph, "WSDOT" is revised to read 19 "Contracting Agency". 20 21 Section 1-08, Prosecution and Progress 22 January 4, 2016 23 1-08.1(1) Prompt Payment, Subcontract Completion and Return of Retainage 24 Withheld 25 In item number 5 of the first paragraph, "WSDOT" is revised to read "Contracting Agency". 26 27 Section 5-02, Bituminous Surface Treatment 28 January 4, 2016 29 5-02.3(2) Preparation of Roadway Surface 30 This section is supplemented with the following new subsection: 31 32 5-02.3(2)E Crack Sealing 33 Where shown in the Plans, seal cracks and joints in the pavement in accordance with 34 Section 5-04.3(5)C. 35 36 Section 5-04, Hot Mix Asphalt 37 January 4, 2016 38 5-04.2 Materials 39 The first paragraph is supplemented with the following new items: 40 41 Hot Poured Sealant 9-04.2(1)A 42 Sand Slurry 9-04.2(1)B 43 44 This section is supplemented with the following new paragraph: 45 Crosswalk Improvements Standard Amendments City of Bremerton. Washington 1 Skillings Connolly. Inc. rederal Aid # S7PUS-9918(01.1) April 2016 1 The requirements of Section 1-06.6 do not apply to the portland cement and fine 2 aggregate used in sand slurry. 3 4 5-04.3(5)C Crack Sealing 5 This section's content is deleted and replaced with the following new subsections: 6 7 5-04.3(5)C1 General 8 When the Proposal includes a pay item for crack sealing, all cracks and joints '/4 inch in 9 width and greater shall be sealed. Cracks and joints shall be thoroughly clean, dry and 10 free of all loose and foreign material when filled with crack sealant material. Immediately 11 prior to filling a crack or joint with the sealant material a hot air lance shall be used to 12 dry and warm the pavement surfaces within the crack or joint. Pavement shall not be 13 overheated and direct flame dryers shall not be used. Routing cracks and joints is not 14 required. 15 16 Where cracks and joints are to be filled with sand slurry thoroughly mix the components 17 and pour the mixture into the cracks and joints until full. Additional CSS -1 emulsified 18 asphalt may be added to the sand slurry as needed for the mixture to be workable to 19 completely fill the crack or joint. Strike off the sand slurry flush with the existing 20 pavement surface and allow the mixture to cure. Cracks or joints that were not 21 completely filled shall be topped off with additional sand slurry. Do not place the HMA 22 overlay until the slurry has fully cured. 23 24 Where cracks and joints are to be filled with hot poured sealant the material shall be 25 applied in accordance with these requirements and the manufacturer's 26 recommendations. The manufacturer's recommendations shall be furnished to the 27 Engineer prior to the start of work and shall include recommended heating time and 28 temperatures, allowable storage time and temperatures after initial heating, allowable 29 reheating criteria, and application temperature range. 30 31 Crack sealing with hot poured sealants shall be controlled to confine the material within 32 the crack or joint. Any overflow of sealant shall be cleaned from the pavement surface. 33 If, in the opinion of the Engineer, the Contractor's method of sealing the cracks and 34 joints with hot poured sealant results in an excessive amount of material on the 35 pavement surface, the operation shall be stopped and corrected to eliminate the excess 36 material. 37 38 5-04.3(5)C2 Crack Sealing Areas Prior to Paving 39 In areas where HMA will be placed the cracks and joints shall be filled with sand slurry. 40 41 5-04.3(5)C3 Crack Sealing Areas Not to be Paved 42 In areas where HMA will not be placed the cracks and joints shall be filled as follows: 43 44 1. Cracks %4 inch to 1 inch in width shall be filled with hot poured sealant. 45 46 2. Cracks and joints greater than 1 inch in width shall be filled with sand slurry. 47 48 5-04.3(5)C4 Crack Sealing Areas Prior to a Bituminous Surface Treatment 49 In areas where a BST will be placed the cracks and joints shall be filled per Section 5- 50 04.3(5)C3. 51 Crosswalk Improvements Standard Amendments Cin, of Bremerton. Washington 2 Skillings Connolly. Ine Federal Aid # SI PUS -9918(01.1) April 2016 1 5-04.4 Measurement 2 The following new paragraph is inserted after the third paragraph: 3 4 Crack Sealing -LF will be measured by the linear foot along the line of the crack. 5 6 5-04.5 Payment 7 The Bid item "Crack Sealing" is revised to read "Crack Sealing -FA". 8 9 The following is inserted after the paragraph following the Bid item "Crack Sealing -FA", by 10 force account (after the preceding Amendment is applied): 11 12 "Crack Sealing -LF", per linear foot. 13 The unit Contract price per linear foot for "Crack Sealing -LF" shall be full payment for all 14 costs incurred to perform the Work described in Section 5-04.3(5)C. 15 16 Section 6-02, Concrete Structures 17 January 4, 2016 18 6-02.3(2)A1 Contractor Mix Design for Concrete Class 4000D 19 The following new sentence is inserted after the second sentence of the last paragraph: 20 21 Mix designs using shrinkage reducing admixture shall state the specific quantity 22 required. 23 24 The following new sentence is inserted before the last sentence of the last paragraph: 25 26 Testing samples of mixes using shrinkage reducing admixture shall use the admixture 27 amount specified in the mix design submittal. 28 29 6-02.3(26)D2 Test Block Dimensions 30 The first sentence is revised to read: 31 32 The dimensions of the test block perpendicular to the tendon in each direction shall be 33 the smaller of twice the minimum edge distance or the minimum spacing specified by 34 the special anchorage device manufacturer, with the stipulation that the concrete cover 35 over any confining reinforcing steel or supplementary skin reinforcement shall be 36 appropriate for the project -specific application and circumstances. 37 38 Section 6-14, Geosynthetic Retaining Walls 39 January 4, 2016 40 6-14.5 Payment 41 The bid item "Concrete Fascia Panel", per square foot, and the paragraph following this bid 42 item are revised to read: 43 44 "Concrete Fascia Panel For Geosynthetic Wall", per square foot. 45 46 All costs in connection with constructing the concrete fascia panels as specified shall be 47 included in the unit Contract price per square foot for "Concrete Fascia Panel For 48 Geosynthetic Wall", including all steel reinforcing bars, premolded joint filler, 49 polyethylene bond breaker strip, joint sealant, PVC pipe for weep holes, exterior surface Crosswalk Improvements Standard Amendments City of Bremerton. Washington 3 Skillings Colln011y, Inc. rederal Aid # STPUS-9)18(015) April 2016 1 finish, and pigmented sealer (when specified), constructing and placing the concrete 2 footing, edge beam, anchor beam, anchor rod assembly, and backfill. 3 4' Section 6-19, Shafts 5 January 4, 2016 6 6-19.4 Measurement 7 The first paragraph is revised to read: 8 9 Soil excavation for shaft, including haul, will be measured by the cubic yards of shaft 10 excavated. The cubic yards will be computed using the shaft diameter, top of shaft 11 elevation and bottom of shaft elevation shown in the Plans, less all rock excavation 12 measured as specified for rock excavation. Excavation between the existing ground 13 line and the top of shaft elevation is considered incidental to soil excavation for shaft 14 and will not be measured. 15 16 The second paragraph is deleted. 17 18 6-19.5 Payment 19 The paragraph following the bid item "Soil Excavation For Shaft Including Haul", per cubic 20 yard is revised to read: 21 22 The unit Contract price per cubic yard for "Soil Excavation For Shaft Including Haul' 23 shall be full pay for performing the work as specified, including all costs in connection 24 with furnishing, mixing, placing, maintaining, containing, collecting, and disposing of all 25 mineral, synthetic, and water slurry, and disposing of groundwater collected by the shaft 26 excavation, and the incidental excavation of soils between the top of shaft elevation 27 shown in the Plans and the existing ground line. 28 29 Section 8-01, Erosion Control and Water Pollution Control 30 January 4, 2016 31 8-01.2 Materials 32 This section is supplemented with the following new paragraph: 33 34 Recycled concrete, in any form, shall not be used for any Work defined in Section 8-01. 35 36 Section 8-10, Guide Posts 37 January 4, 2016 38 8-10.3 Construction Requirements 39 The last sentence of the second paragraph is deleted. 40 41 Section 8-22, Pavement Marking 42 January 4, 2016 43 8-22.4 Measurement 44 The first two sentences of the fourth paragraph are revised to read: 45 46 The measurement for "Painted Wide Lane Line", "Plastic Wide Lane Line", "Profiled 47 Plastic Wide Lane Line", "Painted Barrier Center Line", "Plastic Barrier Center Line". Crossiralk bnprorements Standard Amendments Cin, ojBremerton, Washington 4 Skrllins Connolly, Inc. Federal Aid # S7PUS-991,4(01.1) April 2016 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 "Painted Stop Line", "Plastic Stop Line", "Painted Wide Dotted Entry Line", or "Plastic Wide Dotted Entry Line" will be based on the total length of each painted, plastic or profiled plastic line installed. No deduction will be made for the unmarked area when the marking includes a broken line such as, wide broken lane line, drop lane line, wide dotted lane line or wide dotted entry line. 8-22.5 Payment The following two new Bid items are inserted after the Bid item "Plastic Crosshatch Marking" per linear foot: "Painted Wide Dotted Entry Line", per linear foot. "Plastic Wide Dotted Entry Line", per linear foot. Section 9-03, Aggregates January 4, 2016 9-03.21(1)B Concrete Rubble This section, including title, is revised to read: 9-03.21(1)B Recycled Concrete Aggregate Recycled concrete aggregates are coarse and fine aggregates manufactured from hardened concrete mixtures. Recycled concrete, in any form, shall not be placed below the ordinary high water mark of any water of the State. Section 9-04, Joint and Crack Sealing Materials January 4, 2016 9-04.2(1) Hot Poured Joint Sealants This section's content is deleted and replaced with the following new subsections: 9-04.2(1)A Hot Poured Sealant Hot poured sealant shall be sampled in accordance with ASTM D5167 and tested in accordance with ASTM D5329. Hot poured sealant shall have a minimum Cleveland Open Cup Flash Point of 205°C in accordance with AASHTO T 48. 9-04.2(1)A1 Hot Poured Sealant for Cement Concrete Pavement Hot poured sealant for cement concrete pavement shall meet the requirements of ASTM D6690 Type IV, except for the following: The Cone Penetration at 25°C shall be 130 maximum. 2. The extension for the Bond, non -immersed, shall be 100 percent. 9-04.2(1)A2 Hot Poured Sealant for Bituminous Pavement Hot poured sealant for bituminous pavement shall meet the requirements of ASTM D6690 Type II. Crosswalk Improvements City of Bremerton. Washington Federal Aid # S 1 PUS -9918(010 Standard Amendments Skdlrngs Connolly, Inc. April 2016 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 9-04.2(1)B Sand Slurry for Bituminous Pavement Sand slurry is mixture consisting of the following components measured by total weight: 1. Twenty percent CSS -1 emulsified asphalt, 2. Two percent portland cement, and 3. Seventy-eight percent fine aggregate meeting the requirements of 9-03.1(2)B Class 2. Fine aggregate may be damp (no free water). Section 9-07, Reinforcing Steel January 4, 2016 9-07.1(1)A Acceptance of Materials The first sentence of the first paragraph is revised to read: Reinforcing steel rebar manufacturers shall comply with the National Transportation Product Evaluation Program (NTPEP) Work Plan for Reinforcing Steel (rebar) Manufacturers. The first sentence of the second paragraph is revised to read: Steel reinforcing bar manufacturers use either English or a Metric size designation while stamping rebar. Crosswalk Improvements Cit vofBremerton, Washington Federal Aid # STPUS-9918(01 j) 6 Standard Amendments Skillings Connollv, Irc. April 201 6 IV. SPECIAL PROVISIONS 1 INTRODUCTION TO THE SPECIAL PROVISIONS 2 3 (August 14, 2013 APWA GSP) 4 5 The work on this project shall be accomplished in accordance with the Standard 6 Specifications for Road, Bridge and Municipal Construction, 2014 edition, as issued by the 7 Washington State Department of Transportation (WSDOT) and the American Public Works 8 Association (APWA), Washington State Chapter (hereafter "Standard Specifications"). The 9 Standard Specifications, as modified or supplemented by the Amendments to the Standard 10 Specifications and these Special Provisions, all of which are made a part of the Contract 11 Documents, shall govern all of the Work. 12 13 These Special Provisions are made up of both General Special Provisions (GSPs) from 14 various sources, which may have project -specific fill-ins; and project -specific Special 15 Provisions. Each Provision either supplements, modifies, or replaces the comparable 16 Standard Specification, or is a new Provision. The deletion, amendment, alteration, or 17 addition to any subsection or portion of the Standard Specifications is meant to pertain only 18 to that particular portion of the section, and in no way should it be interpreted that the 19 balance of the section does not apply. 20 21 The project -specific Special Provisions are not labeled as such. The GSPs are labeled 22 under the headers of each GSP, with the effective date of the GSP and its source. For 23 example: 24 25 (March 8, 2013 APWA GSP) 26 (April 1, 2013 WSDOT GSP) 27 28 Also incorporated into the Contract Documents by reference are: 29 • Manual on Uniform Traffic Control Devices for Streets and Highways, currently 30 adopted edition, with Washington State modifications, if any 31 • Standard Plans for Road, Bridge and Municipal Construction, WSDOT/APWA, 32 current edition 33 • Engineering Design & Construction Standards, City of Bremerton, current edition 34 35 Contractor shall obtain copies of these publications, at Contractor's own expense. 36 37 38 Division 1 39 General Requirements 40 41 1-01 DESCRIPTION OF WORK 42 43 (******) 44 This Contract provides for the improvement of *** five intersections at Kitsap Way & Harlow 45 Drive, Kitsap Way & 11 th Street, 11 th Street & High Avenue, SR 304 & 1s' Street, and 6th 46 Avenue & High Avenue. The work to be performed consists of safety improvements and 47 bringing each intersection into compliance with current ADA standards, and includes, but is 48 not limited to: pavement and sidewalk removal, cement concrete curb, gutter and sidewalk, 49 curb ramps, pedestrian signal systems, a HAWK signal system, a rectangular rapid flashing 50 beacon (RRFB) system, traffic control, *** and other work, all in accordance with the 51 attached Contract Plans, these Contract Provisions, and the Standard Specifications. Crossivalk hnprovements .Special Provisions City of Breinerton, Washiiigton 1 Skillings Connollv. Inc. Federal Aid # STPbS-4918(015) April 2016 1 2 1-01.3 Definitions 3 (January 4, 2016 APWA GSP) 4 5 Delete the heading Completion Dates and the three paragraphs that follow it, and replace 6 them with the following: 7 8 Dates 9 Bid Opening Date 10 The date on which the Contracting Agency publicly opens and reads the Bids. 11 Award Date 12 The date of the formal decision of the Contracting Agency to accept the lowest 13 responsible and responsive Bidder for the Work. 14 Contract Execution Date 15 The date the Contracting Agency officially binds the Agency to the Contract. 16 Notice to Proceed Date 17 The date stated in the Notice to Proceed on which the Contract time begins. 18 Substantial Completion Date 19 The day the Engineer determines the Contracting Agency has full and unrestricted 20 use and benefit of the facilities, both from the operational and safety standpoint, any 21 remaining traffic disruptions will be rare and brief, and only minor incidental work, 22 replacement of temporary substitute facilities, plant establishment periods, or 23 correction or repair remains for the Physical Completion of the total Contract. 24 Physical Completion Date 25 The day all of the Work is physically completed on the project. All documentation 26 required by the Contract and required by law does not necessarily need to be 27 furnished by the Contractor by this date. 28 Completion Date 29 The day all the Work specified in the Contract is completed and all the obligations of 30 the Contractor under the contract are fulfilled by the Contractor. All documentation 31 required by the Contract and required by law must be furnished by the Contractor 32 before establishment of this date. 33 Final Acceptance Date 34 The date on which the Contracting Agency accepts the Work as complete. 35 36 Supplement this Section with the following: 37 38 All references in the Standard Specifications, Amendments, or WSDOT General Special 39 Provisions, to the terms "Department of Transportation", "Washington State 40 Transportation Commission", "Commission", "Secretary of Transportation", "Secretary", 41 "Headquarters", and "State Treasurer" shall be revised to read "Contracting Agency". 42 43 All references to the terms "State" or "state" shall be revised to read "Contracting 44 Agency" unless the reference is to an administrative agency of the State of Washington, 45 a State statute or regulation, or the context reasonably indicates otherwise. 46 47 All references to "State Materials Laboratory" shall be revised to read "Contracting 48 Agency designated location". 49 Crosswalk Improvements Special Provisions Citv of Bremerton, Washington 2 Skillings Connollv. Inc Federal Aid # STPUS-9918(015) April 2016 1 All references to "final contract voucher certification" shall be interpreted to mean the 2 Contracting Agency form(s) by which final payment is authorized, and final completion 3 and acceptance granted. 4 5 Additive 6 A supplemental unit of work or group of bid items, identified separately in the Bid 7 Proposal, which may, at the discretion of the Contracting Agency, be awarded in addition 8 to the base bid. 9 10 Alternate 11 One of two or more units of work or groups of bid items, identified separately in the Bid 12 Proposal, from which the Contracting Agency may make a choice between different 13 methods or material of construction for performing the same work. 14 15 Business Day 16 A business day is any day from Monday through Friday except holidays as listed in 17 Section 1-08.5. 18 19 Contract Bond 20 The definition in the Standard Specifications for "Contract Bond" applies to whatever 21 bond form(s) are required by the Contract Documents, which may be a combination of a 22 Payment Bond and a Performance Bond. 23 24 Contract Documents 25 See definition for "Contract". 26 27 Contract Time 28 The period of time established by the terms and conditions of the Contract within which 29 the Work must be physically completed. 30 31 Notice of Award 32 The written notice from the Contracting Agency to the successful Bidder signifying the 33 Contracting Agency's acceptance of the Bid Proposal. 34 35 Notice to Proceed 36 The written notice from the Contracting Agency or Engineer to the Contractor authorizing 37 and directing the Contractor to proceed with the Work and establishing the date on which 38 the Contract time begins. 39 40 Traffic 41 Both vehicular and non -vehicular traffic, such as pedestrians, bicyclists, wheelchairs, and 42 equestrian traffic. 43 44 1-02 Bid Procedures and Conditions 45 Crosswalk /mprovements Special Provisions 01v of Bremerton, Washington 3 Sk111ings Connotiv. [tic. Federal Air! # STPUS-9913(01.4) April 20l6 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 1-02 BID PROCEDURES AND CONDITIONS 1-02.1 Prequalification of Bidders Delete this section and replace it with the following: 1-02.1 Qualifications of Bidder (January 24, 2011 APWA GSP) Before award of a public works contract, a bidder must meet at least the minimum qualifications of RCW 39.04.350(1) to be considered a responsible bidder and qualified to be awarded a public works project. 1-02.2 Plans and Specifications (June 27, 2011 APWA GSP) Delete this section and replace it with the following: Information as to where Bid Documents can be obtained or reviewed can be found in the Call for Bids (Advertisement for Bids) for the work. After award of the contract, plans and specifications will be issued to the Contractor at no cost as detailed below: To Prime Contractor No. of Sets Basis of Distribution Reduced plans (11" x 17") 3 Furnished automatically upon award. Contract Provisions 3 Furnished automatically upon award. Large plans (e.g., 22" x 0 Furnished only upon 34") request. Additional plans and Contract Provisions may be obtained by the Contractor from the source stated in the Call for Bids, at the Contractor's own expense. 1-02.4(2) Subsurface Information (March 8, 2013 APWA GSP) The second sentence in the first paragraph is revised to read: The Summary of Geotechnical Conditions and the boring logs, if and when included as an appendix to the Special Provisions, shall be considered as part of the Contract. 1-02.5 Proposal Forms (June 27, 2011 APWA GSP) Delete this section and replace it with the following: Crosstivalk Impovemenis Ci(v of Bremerton. Washington Federal Aid # S'1'PC'S-9918(015) Special Provisions Skillings Connolly, Inc. April 2016 1 The Proposal Form will identify the project and its location and describe the work. It will 2 also list estimated quantities, units of measurement, the items of work, and the materials 3 to be furnished at the unit bid prices. The bidder shall complete spaces on the proposal 4 form that call for, but are not limited to, unit prices; extensions; summations; the total bid 5 amount; signatures; date; and, where applicable, retail sales taxes and acknowledgment 6 of addenda; the bidder's name, address, telephone number, and signature; the bidder's 7 D/M/WBE commitment, if applicable; a State of Washington Contractor's Registration 8 Number; and a Business License Number, if applicable. Bids shall be completed by 9 typing or shall be printed in ink by hand, preferably in black ink. The required 10 certifications are included as part of the Proposal Form. 11 12 The Contracting Agency reserves the right to arrange the proposal forms with alternates 13 and additives, if such be to the advantage of the Contracting Agency. The bidder shall 14 bid on all alternates and additives set forth in the Proposal Form unless otherwise 15 specified. 16 17 1-02.6 Preparation of Proposal 18 (June 27, 2011 APWA GSP) 19 20 Supplement the second paragraph with the following: 21 4. If a minimum bid amount has been established for any item, the unit or lump sum 22 price must equal or exceed the minimum amount stated. 23 5. Any correction to a bid made by interlineation, alteration, or erasure, shall be 24 initialed by the signer of the bid. 25 26 Delete the last paragraph, and replace it with the following: 27 28 The Bidder shall make no stipulation on the Bid Form, nor qualify the bid in any manner. 29 30 A bid by a corporation shall be executed in the corporate name, by the president or a 31 vice president (or other corporate officer accompanied by evidence of authority to sign). 32 33 A bid by a partnership shall be executed in the partnership name, and signed by a 34 partner. A copy of the partnership agreement shall be submitted with the Bid Form if any 35 D/M/WBE requirements are to be satisfied through such an agreement. 36 37 A bid by a joint venture shall be executed in the joint venture name and signed by a 38 member of the joint venture. A copy of the joint venture agreement shall be submitted 39 with the Bid Form if any D/W/MBE requirements are to be satisfied through such an 40 agreement. 41 42 Add the following new section: 43 44 1-02.6(1) Recycled Materials Proposal 45 (January 4, 2016 APWA GSP) 46 47 The Bidder shall submit with the Bid, its proposal for incorporating recycled materials into 48 the project, using the form provided in the Contract Provisions. 49 50 (May 7, 2012) Crosswalk Improvements Special Provisions Citv of Bremerton. Washington 5 ShIlings Connollv, Gic Federal Ail # S7TLS-9918(01 5) April 20/6 1 The Bidder shall submit with the Bid a completed Disadvantaged Business Enterprise 2 (DBE) Utilization Certification, when required by the Special Provisions. For each and 3 every DBE firm listed on the Bidder's completed Disadvantaged Business Enterprise 4 Utilization Certification, the Bidder shall submit written confirmation from that DBE firm 5 that the DBE is in agreement with the DBE participation commitment that the Bidder has 6 made in the Bidder's completed Disadvantaged Business Enterprise Utilization 7 Certification. WSDOT Form 422 031 EF (Disadvantaged Business Enterprise Written 8 Confirmation Document) is to be used for this purpose. Bidder must submit good faith 9 effort documentation only in the event the bidder's efforts to solicit sufficient DBE 10 participation have been unsuccessful. Directions for delivery of the Disadvantaged 11 Business Enterprise Written Confirmation Documents and Disadvantaged Business 12 Enterprise Good Faith Effort documentation are included in Sections 1-02.9. 13 14 (August 2, 2004) 15 The fifth and sixth paragraphs of Section 1-02.6 are deleted. 16 17 1-02.7 Bid Deposit 18 (March 8, 2013 APWA GSP) 19 20 Supplement this section with the following: 21 22 Bid bonds shall contain the following: 23 1. Contracting Agency -assigned number for the project; 24 2. Name of the project; 25 3. The Contracting Agency named as obligee; 26 4. The amount of the bid bond stated either as a dollar figure or as a percentage which 27 represents five percent of the maximum bid amount that could be awarded; 28 5. Signature of the bidder's officer empowered to sign official statements. The signature 29 of the person authorized to submit the bid should agree with the signature on the 30 bond, and the title of the person must accompany the said signature; 31 6. The signature of the surety's officer empowered to sign the bond and the power of 32 attorney. 33 34 If so stated in the Contract Provisions, bidder must use the bond form included in the 35 Contract Provisions. 36 37 If so stated in the Contract Provisions, cash will not be accepted for a bid deposit. 38 39 1-02.9 Delivery of Proposal 40 (August 15, 2012 APWA GSP, Option A) 41 42 Delete this section and replace it with the following: 43 44 Each proposal shall be submitted in a sealed envelope, with the Project Name and 45 Project Number as stated in the Call for Bids clearly marked on the outside of the 46 envelope, or as otherwise required in the Bid Documents, to ensure proper handling and 47 delivery. 48 49 If the project has FHWA funding and requires DBE Written Confirmation Documents or 50 Good Faith Effort Documentation, then to be considered responsive, the Bidder shall Crosswalk Improvements Special Provisions Citv of Bremerton, Washington 6 Skillings Connollv, Inc. Federal Aid # STI'US-9918(015) April 2016 1 submit with their Bid Proposal, written Confirmation Documentation from each DBE firm 2 listed on the Bidder's completed DBE Utilization Certification, form 272-056A EF, as 3 required by Section 1-02.6. 4 5 The Contracting Agency will not open or consider any Bid Proposal that is received after 6 the time specified in the Call for Bids for receipt of Bid Proposals, or received in a 7 location other than that specified in the Call for Bids. 8 9 1-02.13 Irregular Proposals 10 (January 4, 2016 APWA GSP) 11 12 Delete this section and replace it with the following: 13 14 1. A proposal will be considered irregular and will be rejected if: 15 a. The Bidder is not prequalified when so required; 16 b. The authorized proposal form furnished by the Contracting Agency is not 17 used or is altered; 18 C. The completed proposal form contains any unauthorized additions, deletions, 19 alternate Bids, or conditions; 20 d. The Bidder adds provisions reserving the right to reject or accept the award, 21 or enter into the Contract; 22 e. A price per unit cannot be determined from the Bid Proposal; 23 f. The Proposal form is not properly executed; 24 g. The Bidder fails to submit or properly complete a Subcontractor list, if 25 applicable, as required in Section 1-02.6; 26 h. The Bidder fails to submit or properly complete a Disadvantaged Business 27 Enterprise Certification, if applicable, as required in Section 1-02.6; 28 i. The Bidder fails to submit written confirmation from each DBE firm listed on 29 the Bidder's completed DBE Utilization Certification that they are in 30 agreement with the bidders DBE participation commitment, if applicable, as 31 required in Section 1-02.6, or if the written confirmation that is submitted fails 32 to meet the requirements of the Special Provisions; 33 j The Bidder fails to submit DBE Good Faith Effort documentation, if applicable, 34 as required in Section 1-02.6, or if the documentation that is submitted fails to 35 demonstrate that a Good Faith Effort to meet the Condition of Award was 36 made; 37 k. The Bid Proposal does not constitute a definite and unqualified offer to meet 38 the material terms of the Bid invitation; or 39 I. More than one proposal is submitted for the same project from a Bidder under 40 the same or different names. 41 42 2. A Proposal may be considered irregular and may be rejected if: 43 a. The Proposal does not include a unit price for every Bid item; 44 b. Any of the unit prices are excessively unbalanced (either above or below the 45 amount of a reasonable Bid) to the potential detriment of the Contracting 46 Agency; 47 C. Receipt of Addenda is not acknowledged; 48 d. A member of a joint venture or partnership and the joint venture or 49 partnership submit Proposals for the same project (in such an instance, both 50 Bids may be rejected); or 51 e. If Proposal form entries are not made in ink. 52 Crosswalk Improvements Special Provisions City of Bremerton, Washington 7 Skillings Connolly. Inc. Federal Aid # STPUS-9918(015) April 20/6 1 1-02.14 Disqualification of Bidders 2 (March 8, 2013 APWA GSP, Option A) 3 4 Delete this section and replace it with the following: 5 6 A Bidder will be deemed not responsible if the Bidder does not meet the mandatory 7 bidder responsibility criteria in RCW 39.04.350(1), as amended. 8 9 As evidence that the Bidder meets the mandatory bidder responsibility criteria, the 10 apparent two lowest Bidders must submit to the Contracting Agency within 24 hours of 11 the bid submittal deadline, documentation (sufficient in the sole judgment of the 12 Contracting Agency) demonstrating compliance with all responsibility criteria. The 13 Contracting Agency reserves the right to request such documentation from other Bidders 14 as well, and to request further documentation as needed to assess bidder responsibility. 15 The Contracting Agency also reserves the right to obtain information from third parties 16 concerning a Bidder's compliance with the mandatory bidder responsibility criteria. 17 18 If the Contracting Agency determines the Bidder does not meet the mandatory bidder 19 responsibility criteria in RCW 39.04.350(1) and is therefore not a responsible Bidder, the 20 Contracting Agency shall notify the Bidder in writing, with the reasons for its 21 determination. If the Bidder disagrees with this determination, it may appeal the 22 determination within two (2) business days of the Contracting Agency's determination by 23 presenting its appeal and any additional information to the Contracting Agency. The 24 Contracting Agency will consider the appeal and any additional information before 25 issuing its final determination. If the final determination affirms that the Bidder is not 26 responsible, the Contracting Agency will not execute a contract with any other Bidder 27 until at least two business days after the Bidder determined to be not responsible has 28 received the Contracting Agency's final determination. 29 30 1-02.15 Pre Award Information 31 (August 14, 2013 APWA GSP) 32 33 Revise this section to read: 34 35 Before awarding any contract, the Contracting Agency may require one or more of these 36 items or actions of the apparent lowest responsible bidder: 37 1. A complete statement of the origin, composition, and manufacture of any or all 38 materials to be used, 39 2. Samples of these materials for quality and fitness tests, 40 3. A progress schedule (in a form the Contracting Agency requires) showing the order 41 of and time required for the various phases of the work, 42 4. A breakdown of costs assigned to any bid item, 43 5. Attendance at a conference with the Engineer or representatives of the Engineer, 44 6. Obtain, and furnish a copy of, a business license to do business in the city or county 45 where the work is located. 46 7. Any other information or action taken that is deemed necessary to ensure that the 47 bidder is the lowest responsible bidder. 48 49 50 1-03 Award and Execution of Contract 51 Crosswalk Improvements Special Provisions Ce(v of Bremerton. Washington 8 Skillings Connollv. Inc Federal Aid # S77'US-9918(015) April 2016 1 1-03.1 Consideration of Bids 2 (January 23, 2006 APWA GSP) 3 4 Revise the first paragraph to read: 5 6 After opening and reading proposals, the Contracting Agency will check them for 7 correctness of extensions of the prices per unit and the total price. If a discrepancy 8 exists between the price per unit and the extended amount of any bid item, the price per 9 unit will control. If a minimum bid amount has been established for any item and the 10 bidder's unit or lump, sum price is less than the minimum specified amount the 11 Contracting Agency will unilaterally revise the unit or lump sum price to the minimum 12 specified amount and recalculate the extension. The total of extensions, corrected 13 where necessary, including sales taxes where applicable and such additives and/or 14 alternates as selected by the Contracting Agency, will be used by the Contracting Agency 15 for award purposes and to fix the Awarded Contract Price amount and the amount of the 16 contract bond. 17 18 1-03.1(1) Identical Bid Totals 19 (January 4, 2016 APWA GSP) 20 21 Revise this section to read: 22 23 After opening Bids, if two or more lowest responsive Bid totals are exactly equal, then 24 the tie-breaker will be the Bidder with an equal lowest bid, that proposed to use the 25 highest percentage of recycled materials in the Project, per the form submitted with the 26 Bid Proposal. If those percentages are also exactly equal, then the tie-breaker will be 27 determined by drawing as follows: Two or more slips of paper will be marked as follows: 28 one marked "Winner" and the other(s) marked "unsuccessful". The slips will be folded to 29 make the marking unseen. The slips will be placed inside a box. One authorized 30 representative of each Bidder shall draw a slip from the box. Bidders shall draw in 31 alphabetic order by the name of the firm as registered with the Washington State 32 Department of Licensing. The slips shall be unfolded and the firm with the slip marked 33 "Winne" will be determined to be the successful Bidder and eligible for Award of the 34 Contract. Only those Bidders who submitted a Bid total that is exactly equal to the lowest 35 responsive Bid, and with a proposed recycled m aterials percentage that is exactly equal 36 to the highest proposed recycled materials amount, are eligible to draw. 37 38 1-03.3 Execution of Contract 39 (October 1, 2005 APWA GSP) 40 41 Revise this section to read: 42 43 Copies of the Contract Provisions, including the unsigned Form of Contract will be 44 available for signature by the successful bidder on the first business day following award 45 The number of copies to be executed by the Contractor will be determined by the 46 Contracting Agency. 47 48 Within 10 calendar days after the award date, the successful bidder shall return the 49 signed Contracting Agency -prepared contract, an insurance certification as required by 50 Section 1-07.18, and a satisfactory bond as required by law and Section 1-03.4. Before 51 execution of the contract by the Contracting Agency, the successful bidder shall provide 52 any pre -award information the Contracting Agency may require under Section 1-02.15. Crosswalk Improvements Special Provisions City of Bremerton, Washington 9 Shllnrgs Connolly, Inc. Federal Aid # STPUS-9918(015) April 2016 1 2 Until the Contracting Agency executes a contract, no proposal shall bind the Contracting 3 Agency nor shall any work begin within the project limits or within Contracting Agency - 4 furnished sites. The Contractor shall bear all risks for any work begun outside such areas 5 and for any materials ordered before the contract is executed by the Contracting Agency. 6 7 If the bidder experiences circumstances beyond their control that prevents return of the 8 contract documents within the 10 calendar days after the award date stated above, the 9 Contracting Agency may grant up to a maximum of 10 additional calendar days for return 10 of the documents, provided the Contracting Agency deems the circumstances warrant it. 11 12 13 1-03.4 Contract Bond 14 (July 23, 2015 APWA GSP) 15 16 Delete the first paragraph and replace it with the following: 17 18 The successful bidder shall provide executed payment and performance bond(s) for the 19 full contract amount. The bond may be a combined payment and performance bond; or 20 be separate payment and performance bonds. In the case of separate payment and 21 performance bonds, each shall be for the full contract amount. The bond(s) shall: 22 1. Be on Contracting Agency -furnished form(s); 23 2. Be signed by an approved surety (or sureties) that: 24 a. Is registered with the Washington State Insurance Commissioner, and 25 b. Appears on the current Authorized Insurance List in the State of Washington 26 published by the Office of the Insurance Commissioner, 27 3. Guarantee that the Contractor will perform and comply with all obligations, duties, 28 and conditions under the Contract, including but not limited to the duty and obligation 29 to indemnify, defend, and protect the Contracting Agency against all losses and 30 claims related directly or indirectly from any failure: 31 a. Of the Contractor (or any of the employees, subcontractors, or lower tier 32 subcontractors of the Contractor) to faithfully perform and comply with all contract 33 obligations, conditions, and duties, or 34 b. Of the Contractor (or the subcontractors or lower tier subcontractors of the 35 Contractor) to pay all laborers, mechanics, subcontractors, lower tier 36 subcontractors, material person, or any other person who provides supplies or 37 provisions for carrying out the work; 38 4. Be conditioned upon the payment of taxes, increases, and penalties incurred on the 39 project under titles 50, 51, and 82 RCW; and 40 5. Be accompanied by a power of attorney for the Surety's officer empowered to sign 41 the bond; and 42 6. Be signed by an officer of the Contractor empowered to sign official statements (sole 43 proprietor or partner). If the Contractor is a corporation, the bond(s) must be signed 44 by the president or vice president, unless accompanied by written proof of the 45 authority of the individual signing the bond(s) to bind the corporation (i.e., corporate 46 resolution, power of attorney, or a letter to such effect signed by the president or vice 47 president). 48 49 1-04 Scope of the Work 50 Crosswalk Improvements Special Provisions City of'Bremerton, Washington 10 Skillings Connolly. hie. Federal Aid # S7PL/S-9918(015) April 2016 1 1-04.2 Coordination of Contract Documents, Plans, Special Provisions, 2 Specifications, and Addenda 3 4 (March 13, 2012 APWA GSP) 5 6 7 Revise the second paragraph to read: 8 9 Any inconsistency in the parts of the contract shall be resolved by following this order of 10 precedence (e.g., 1 presiding over 2, 2 over 3, 3 over 4, and so forth): 11 1. Addenda, 12 2. Proposal Form, 13 3. Special Provisions, 14 4. Contract Plans, 15 5. Amendments to the Standard Specifications, 16 6. Standard Specifications, 17 7. Contractinq Agency's Standard Plans or Details (if any), and 18 8. WSDOT Standard Plans for Road, Bridge, and Municipal Construction. 19 20 1-05 Control of Work 21 22 1-05.4 Conformity With and Deviations From Plans and Stakes 23 - 24 Section 1-05.4 is supplemented with the following: 25 26 (April 1, 2013) 27 Contractor Surveying - Roadway 28 Copies of the Contracting Agency provided primary survey control data are available for 29 the bidder's inspection at the office of the Project Engineer. 30 31 The Contractor shall be responsible for setting, maintaining, and resetting all alignment 32 stakes, slope stakes, and grades necessary for the construction of the roadbed, 33 drainage, surfacing, paving, channelization and pavement marking, illumination and 34 signals, guardrails and barriers, and signing. Except for the survey control data to be 35 furnished by the Contracting Agency, calculations, surveying, and measuring required 36 for setting and maintaining the necessary lines and grades shall be the Contractor's 37 responsibility. 38 39 The Contractor shall inform the Engineer when monuments are discovered that were 40 not identified in the Plans 'and construction activity may disturb or damage the 41 monuments. All monuments noted on the plans "DO NOT DISTURB" shall be protected 42 throughout the length of the project or be replaced at the Contractors expense. 43 44 Detailed survey records shall be maintained, including a description of the work 45 performed on each shift, the methods utilized, and the control points used. The record 46 shall be adequate to allow the survey to be reproduced. A copy of each day's record 47 shall be provided to the Engineer within three working days after the end of the shift. 48 49 The meaning of words and terms used in this provision shall be as listed in "Definitions 50 of Surveying and Associated Terms" current edition, published by the American 51 Congress on Surveying and Mapping and the American Society of Civil Engineers. Crosswalk Improvements Special Provisions City of Bremcrlon, Washington 11 Skillings Connolly, Inc. Federal Aid # STPUS-9918(015) 1 pril 20l6 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 The survey work shall include but not be limited to the following: Verify the primary horizontal and vertical control furnished by the Contracting Agency, and expand into secondary control by adding stakes and hubs as well as additional survey control needed for the project. Provide descriptions of secondary control to the Contracting Agency. The description shall include coordinates and elevations of all secondary control points. 2. Establish, the centerlines of all alignments, by placing hubs, stakes, or marks on centerline or on offsets to centerline at all curve points (PCs, PTs, and PIs) and at points on the alignments spaced no further than 50 feet. 3. Establish clearing limits, placing stakes at all angle points and at intermediate points not more than 50 feet apart. The clearing and grubbing limits shall be 5 feet beyond the toe of a fill and 10 feet beyond the top of a cut unless otherwise shown in the Plans. 4. Establish grading limits, placing slope stakes at centerline increments not more than 50 feet apart. Establish offset reference to all slope stakes. If Global Positioning Satellite (GPS) Machine Controls are used to provide grade control, then slope stakes may be omitted at the discretion of the Contractor 5. Establish the horizontal and vertical location of all drainage features, placing offset stakes to all drainage structures and to pipes at a horizontal interval not greater than 25 feet. 6. Establish roadbed and surfacing elevations by placing stakes at the top of subgrade and at the top of each course of surfacing. Subgrade and surfacing stakes shall be set at horizontal intervals not greater than 50 feet in tangent sections, 25 feet in curve sections with a radius less than 300 feet, and at 10 - foot intervals in intersection radii with a radius less than 10 feet. Transversely, stakes shall be placed at all locations where the roadway slope changes and at additional points such that the transverse spacing of stakes is not more than 12 feet. If GPS Machine Controls are used to provide grade control, then roadbed and surfacing stakes may be omitted at the discretion of the Contractor. 7. Establish intermediate elevation benchmarks as needed to check work throughout the project. 8. Provide references for paving pins at 25 -foot intervals or provide simultaneous surveying to establish location and elevation of paving pins as they are being placed. 9. For all other types of construction included in this provision, (including but not limited to channelization and pavement marking, illumination and signals, guardrails and barriers, and signing) provide staking and layout as necessary to adequately locate, construct, and check the specific construction activity. 10. Contractor shall determine if changes are needed to the profiles or roadway sections shown in the Contract Plans in order to achieve proper smoothness Crosswalk Improvements Special Pro visions Ciro of Bremerton. Washington 12 Skil/rags Connollv. Inc. Federal Aid # STPUS-9918(015) April 2016 1 and drainage where matching into existing features, such as a smooth 2 transition from new pavement to existing pavement. The Contractor shall 3 submit these changes to the Project Engineer for review and approval 10 days 4 prior to the beginning of work. 5 6 The Contractor shall provide the Contracting Agency copies of any calculations and 7 staking data when requested by the Engineer. 8 9 To facilitate the establishment of these lines and elevations, the Contracting Agency will 10 provide the Contractor with primary survey control information consisting of descriptions 11 of two primary control points used for the horizontal and vertical control, and 12 descriptions of two additional primary control points for every additional three miles of 13 project length. Primary control points will be described by reference to the project 14 alignment and the coordinate system and elevation datum utilized by the project. In 15 addition, the Contracting Agency will supply horizontal coordinates for the beginning and 16 ending points and for each Point of Intersection (PI) on each alignment included in the 17 project. 18 19 The Contractor shall ensure a surveying accuracy within the following tolerances: 20 21 Vertical Horizontal 22 Slope stakes ±0.10 feet ±0.10 feet 23 Subgrade grade stakes set 24 0.04 feet below grade ±0.01 feet ±0.5 feet 25 (parallel to alignment) 26 ±0.1 feet 27 (normal to alignment) 28 29 Stationing on roadway N/A ±0.1 feet 30 Alignment on roadway N/A ±0.04 feet 31 Surfacing grade stakes ±0.01 feet ±0.5 feet 32 (parallel to alignment) 33 ±0.1 feet 34 (normal to alignment) 35 36 Roadway paving pins for 37 surfacing or paving ±0.01 feet ±0.2 feet 38 (parallel to alignment) 39 ±0.1 feet 40 (normal to alignment) 41 42 The Contracting Agency may spot-check the Contractor's surveying. These spot - 43 checks will not change the requirements for normal checking by the Contractor. 44 45 When staking roadway alignment and stationing, the Contractor shall perform 46 independent checks from different secondary control to ensure that the points staked 47 are within the specified survey accuracy tolerances. 48 49 The Contractor shall calculate coordinates for the alignment. The Contracting Agency 50 will verify these coordinates prior to issuing approval to the Contractor for commencing 51 with the work. The Contracting Agency will require up to seven calendar days from the 52 date the data is received. Crosswalk Improvements Special Provisions Citv of Bremerton, Washington 13 Skillings Connolly. Inc. Federal Aid # S7PUS-9918(015) April 2016 1 2 Contract work to be performed using contractor -provided stakes shall not begin until the 3 stakes are approved by the Contracting Agency. Such approval shall not relieve the 4 Contractor of responsibility for the accuracy of the stakes. 5 6 Stakes shall be marked in accordance with Standard Plan A10.10. When stakes are 7 needed that are not described in the Plans, then those stakes shall be marked, at no 8 additional cost to the Contracting Agency as ordered by the Engineer. 9 10 Payment 11 Payment will be made in accordance with Section 1-04.1 for the following bid item when 12 included in the proposal: 13 14 "Roadway Surveying", lump sum. 15 16 The lump sum contract price for "Roadway Surveying" shall be full pay for all labor, 17 equipment, materials, and supervision utilized to perform the Work specified, including 18 any resurveying, checking, correction of errors, replacement of missing or damaged 19 stakes, and coordination efforts. 20 21 1-05.7 Removal of Defective and Unauthorized Work 22 (October 1, 2005 APWA GSP) 23 24 Supplement this section with the following: 25 26 If the Contractor fails to remedy defective or unauthorized work within the time specified 27 in a written notice from the Engineer, or fails to perform any part of the work required by 28 the Contract Documents, the Engineer may correct and remedy such work as may be 29 identified in the written notice, with Contracting Agency forces or by such other means as 30 the Contracting Agency may deem necessary. 31 32 If the Contractor fails to comply with a written order to remedy what the Engineer 33 determines to be an emergency situation, the Engineer may have the defective and 34 unauthorized work corrected immediately, have the rejected work removed and replaced, 35 or have work the Contractor refuses to perform completed by using Contracting Agency 36 or other forces. An emergency situation is any situation when, in the opinion of the 37 Engineer, a delay in its remedy could be potentially unsafe, or might cause serious risk 38 of loss or damage to the public. 39 40 Direct or indirect costs incurred by the Contracting Agency attributable to correcting and 41 remedying defective or unauthorized work, or work the Contractor failed or refused to 42 perform, shall be paid by the Contractor. Payment will be deducted by the Engineer from 43 monies due, or to become due, the Contractor. Such direct and indirect costs shall 44 include in particular, but without limitation, compensation for additional professional 45 services required, and costs for repair and replacement of work of others destroyed or 46 damaged by correction, removal, or replacement of the Contractor's unauthorized work. 47 48 No adjustment in contract time or compensation will be allowed because of the delay in 49 the performance of the work attributable to the exercise of the Contracting Agency's 50 rights provided by this Section. 51 Crosswalk Improvements Special Provisions CRY of Bremerton, Washington 14 Skillings Connollv, Inc. Federal Aid #S7PUS-9918(015) April1016 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 The rights exercised under the provisions of this section shall not diminish the Contracting Agency's right to pursue any other avenue for additional remedy or damages with respect to the Contractor's failure to perform the work as required. 1-05.11 Final Inspection Delete this section and replace it with the following: 1-05.11 Final Inspections and Operational Testing (October 1, 2005 APWA GSP) 1-05.11(1) Substantial Completion Date When the Contractor considers the work to be substantially complete, the Contractor shall so notify the Engineer and request the Engineer establish the Substantial Completion Date. The Contractor's request shall list the specific items of work that remain to be completed in order to reach physical completion. The Engineer will schedule an inspection of the work with the Contractor to determine the status of completion. The Engineer may also establish the Substantial Completion Date unilaterally. If, after this inspection, the Engineer concurs with the Contractor that the work is substantially complete and ready for its intended use, the Engineer, by written notice to the Contractor, will set the Substantial Completion Date. If, after this inspection the Engineer does not consider the work substantially complete and ready for its intended use, the Engineer will, by written notice, so notify the Contractor giving the reasons therefor. Upon receipt of written notice concurring in or denying substantial completion, whichever is applicable, the Contractor shall pursue vigorously, diligently and without unauthorized interruption, the work necessary to reach Substantial and Physical Completion. The Contractor shall provide the Engineer with a revised schedule indicating when the Contractor expects to reach substantial and physical completion of the work. The above process shall be repeated until the Engineer establishes the Substantial Completion Date and the Contractor considers the work physically complete and ready for final inspection. 1-05.11(2) Final Inspection and Physical Completion Date When the Contractor considers the work physically complete and ready for final inspection, the Contractor by written notice, shall request the Engineer to schedule a final inspection. The Engineer will set a date for final inspection. The Engineer and the Contractor will then make a final inspection and the Engineer will notify the Contractor in writing of all particulars in which the final inspection reveals the work incomplete or unacceptable. The Contractor shall immediately take such corrective measures as are necessary to remedy the listed deficiencies. Corrective work shall be pursued vigorously, diligently, and without interruption until physical completion of the listed deficiencies. This process will continue until the Engineer is satisfied the listed deficiencies have been corrected. Crosswalk Improvements City of Bremerton, Washington Federal Aid # STPUS-9918(015) 15 Special Provisions Skillings Connollv, Inc. Apri12016 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 If action to correct the listed deficiencies is not initiated within 7 days after receipt of the written notice listing the deficiencies, the Engineer may, upon written notice to the Contractor, take whatever steps are necessary to correct those deficiencies pursuant to Section 1-05.7. The Contractor will not be allowed an extension of contract time because of a delay in the performance of the work attributable to the exercise of the Engineer's right hereunder. Upon correction of all deficiencies, the Engineer will notify the Contractor and the Contracting Agency, in writing, of the date upon which the work was considered physically complete. That date shall constitute the Physical Completion Date of the contract, but shall not imply acceptance of the work or that all the obligations of the Contractor under the contract have been fulfilled. 1-05.11(3) Operational Testing It is the intent of the Contracting Agency to have at the Physical Completion Date a complete and operable system. Therefore when the work involves the installation of machinery or other mechanical equipment; street lighting, electrical distribution or signal systems; irrigation. systems; buildings; or other similar work it may be desirable for the Engineer to have the Contractor operate and test the work for a period of time after final inspection but prior to the physical completion date. Whenever items of work are listed in the Contract Provisions for operational testing they shall be fully tested under operating conditions for the time period specified to ensure their acceptability prior to the Physical Completion Date. During and following the test period, the Contractor shall correct any items of workmanship, materials, or equipment which prove faulty, or that are not in first class operating condition. Equipment, electrical controls, meters, or other devices and equipment to be tested during this period shall be tested under the observation of the Engineer, so that the Engineer may determine their suitability for the purpose for which they were installed. The Physical Completion Date cannot be established until testing and corrections have been completed to the satisfaction of the Engineer. The costs for power, gas, labor, material, supplies, and everything else needed to successfully complete operational testing, shall be included in the unit contract prices related to the system being tested, unless specifically set forth otherwise in the proposal. Operational and test periods, when required by the Engineer, shall not affect a manufacturer's guaranties or warranties furnished under the terms of the contract. 1-05.13 Superintendents, Labor and Equipment of Contractor (August 14, 2013 APWA GSP) Delete the sixth and seventh paragraphs of this section. 1-05.15 Method of Serving Notices (March 25, 2009 APWA GSP) Revise the second paragraph to read: All correspondence from the Contractor shall be directed to the Project Engineer. All correspondence from the Contractor constitutina anv notification, notice of protest, notice Crosswalk Improvements Special Provisions Citv of Bremerton. Washington 16 Skillings Connolly. Inc. Federal Aid # PPUS-9918(015) April 2016 1 of dispute, or other correspondence constituting notification required to be furnished 2 under the Contract, must be in paper format, hand delivered or sent via mail delivery 3 service to the Project Engineer's office. Electronic copies such as e-mails or 4 electronically delivered copies of correspondence will not constitute such notice and will 5 not comply with the requirements of the Contract. 6 7 Add the following new section: 8 9 1-05.16 Water and Power 10 (October 1, 2005 APWA GSP) 11 12 The Contractor shall make necessary arrangements, and shall bear the costs for power 13 and water necessary for the performance of the work, unless the contract includes power 14 and water as a pay item. 15 16 1-06 Control of Material 17 18 Section 1-06 is supplemented with the following: 19 20 Buy America 21 22 (August 6,'2012) 23 In accordance with Buy America requirements contained in 23 CFR 635.410, the major 24 quantities of steel and iron construction material that is permanently incorporated into 25 the project shall consist of American-made materials only. Buy America does not apply 26 to temporary steel items, e.g., temporary sheet piling, temporary bridges, steel 27 scaffolding and falsework. 28 29 Minor amounts of foreign steel and iron may be utilized in this project provided the cost 30 of the foreign material used does not exceed one-tenth of one percent of the total 31 contract cost or $2,500.00, whichever is greater. 32 33 American-made material is defined as material having all manufacturing processes 34 occurring domestically. To further define the coverage, a domestic product is a 35 manufactured steel material that was produced in one of the 50 States, the District of 36 Columbia, Puerto Rico, or in the territories and possessions of the United States. 37 38 If domestically produced steel billets or iron ingots are exported outside of the area of 39 coverage, as defined above, for any manufacturing process then the resulting product 40 does not conform to the Buy America requirements. Additionally, products 41 manufactured domestically from foreign source steel. billets or iron ingots do not 42 conform to the Buy America requirements because the initial melting and mixing of 43 alloys to create the material occurred in a foreign country. 44 45 Manufacturing begins with the initial melting and mixing, and continues through the 46 coating stage. Any process which modifies the chemical content, the physical size or 47 shape, or the final finish is considered a manufacturing process. The processes include 48 rolling, extruding, machining, bending, grinding, drilling, welding, and coating. The action 49 of applying a coating to steel or iron is deemed a manufacturing process. Coating 50 includes epoxy coating, galvanizing, aluminizing, painting, and any other coating that 51 protects or enhances the value of steel or iron. Any process from the original reduction 52 from ore to the finished product constitutes a manufacturing process for iron. Crosswalk Improvements Special Provisions Ciro of'Bremerton, !Washington 17 Skilliurgs Canrolly, Inc. Federal Aid # S'IPUS-9918(0/5) April 2016 1 - 2 Due to a nationwide waiver, Buy America does not apply to raw materials (iron ore and 3 alloys), scrap (recycled steel or iron), and pig iron or processed, pelletized, and reduced 4 iron ore. 5 6 The following are considered to be steel manufacturing processes: 7 8 1. Production of steel by any of the following processes: 9 10 a. Open hearth furnace. 11 12 b. Basic oxygen. 13 14 c. Electric furnace. 15 16 d. Direct reduction. 17 18 2. Rolling, heat treating, and any other similar processing. 19 20 3. Fabrication of the products. 21 22 a. Spinning wire into cable or strand. 23 24 b. Corrugating and rolling into culverts. 25 26 c. Shop fabrication. 27 28 A certification of materials origin will be required for any items comprised of, or 29 containing, steel or iron construction materials prior to such items being incorporated 30 into the permanent work. The certification shall be on DOT Form 350-109EF provided 31 by the Engineer, or such other form the Contractor chooses, provided it contains the 32 same information as DOT Form 350-109EF. 33 34 1-06.6 Recycled Materials 35 (January 4, 2016 APWA GSP) 36 37 Delete this section, including its subsections, and replace it with the following: 38 39 The Contractor shall make their best effort to utilize recycled materials in the construction 40 of the project. Approval of such material use shall be as detailed elsewhere in the 41 Standard Specifications. 42 43 Prior to Physical Completion the Contractor shall report the quantity of recycled materials 44 that were utilized in the construction of the project for each of the items listed in Section 45 9-03.21. The report shall include hot mix asphalt, recycled concrete aggregate, recycled 46 glass, steel furnace slag and other recycled materials (e.g. utilization of on-site material 47 and aggregates from concrete returned to the supplier). The Contractor's report shall be 48 provided on DOT form 350-075 Recycled Materials Reporting. 49 50 1-07 Legal Relations and Responsibilities to the Public 51 Crossivalk hnprovements Special Provisions Ciry of Bremerton, Washington 18 Skillings Connolly, Inc. Federal Aid # STPbS-9918(015) April 2016 1 1-07.1 Laws to be Observed 2 (October 1, 2005 APWA GSP) 3 4 Supplement this section with the following: 5 6 In cases of conflict between different safety regulations, the more stringent regulation 7 shall apply. 8 9 The Washington State Department of Labor and Industries shall be the sole and 10 paramount administrative agency responsible for the administration of the provisions of 11 the Washington Industrial Safety and Health Act of 1973 (WISHA). 12 13 The Contractor shall maintain at the project site office, or other well known place at the 14 project site, all articles necessary for providing first aid to the injured. The Contractor 15 shall establish, publish, and make known to all employees, procedures for ensuring 16 immediate removal to a hospital, or doctor's care, persons, including employees, who 17 may have been injured on the project site. Employees should not be permitted to work 18 on the project site before the Contractor has established and made known procedures 19 for removal of injured persons to a hospital or a doctor's care. 20 21 The Contractor shall have sole responsibility for the safety, efficiency, and adequacy of 22 the Contractor's plant, appliances, and methods, and for any damage or injury resulting 23 from their failure, or improper maintenance, use, or operation. The Contractor shall be 24 solely and completely responsible for the conditions of the project site, including safety 25 for all persons and property in the performance of the work. This requirement shall apply 26 continuously, and not be limited to normal working hours. The required or implied duty of 27 the Engineer to conduct construction review of the Contractor's performance does not, 28 and shall not, be intended to include review and adequacy of the Contractor's safety 29 measures in, on, or near the project site. 30 31 32 1-07.7 Load Limits 33 34 Section 1-07.7 is supplemented with the following: 35 36 (March 13, 1995) 37 If the sources of materials provided by the Contractor necessitates hauling over roads 38 other than State Highways, the Contractor shall, at the Contractor's expense, make all 39 arrangements for the use of the haul routes. 40 41 1-07.9 Wages 42 43 1-07.9(1) General 44 45 Section 1-07.9(1) is supplemented with the following: 46 47 (January 8, 2016) 48 The Federal wage rates incorporated in this contract have been established by the 49 Secretary of Labor under United States Department of Labor General Decision No. 50 WA160001. 51 Crosswalk Improvements Special Provisions Gtv oJHremerton. Washington 19 Skillings ConnoQv. hu. Federal Aid # STPUS-9918(01 ) April 2016 1 The State rates incorporated in this contract are applicable to all construction 2 activities associated with this contract. 3 4 1-07.11 Requirements for Nondiscrimination 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 Section 1-07.11 is supplemented with the following: (August 5, 2013) Requirement for Affirmative Action to Ensure Equal Employment Opportunity (Executive Order 11246) The Contractor's attention is called to the Equal Opportunity Clause and the Standard Federal Equal Employment Opportunity Construction Contract Specifications set forth herein. 2. The goals and timetables for minority and female participation set by the Office of Federal Contract Compliance Programs, expressed in percentage terms for the Contractor's aggregate work force in each construction craft and in each trade on all construction work in the covered area, are as follows: Women - Statewide Timetable Goal Until further notice 6.9% Minorities - by Standard Metropolitan Statistical Area (SMSA) Spokane, WA: SMSA Counties: Spokane, WA WA Spokane. Non -SMSA Counties WA Adams; WA Asotin; Lincoln, WA Pend Oreille 2.8 3.0 WA Columbia; WA Ferry; WA Garfield; WA WA Stevens; WA Whitman. Richland, WA SMSA Counties: Richland Kennewick, WA WA Benton; WA Franklin. Non -SMSA Counties WA Walla Walla. Yakima, WA: SMSA Counties: Yakima, WA WA Yakima. Non -SMSA Counties WA Chelan; WA Douglas; Crosswalk Improvements Citv of Bremerton. Washington Federal Air! # S7PUS-9918(015) 5.4 kV M 7.2 WA Grant; WA Kittitas; WA Okanogan. 20 Special Provisions Skillings Connollv, Inc. April 20l h 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 Seattle, WA: SMSA Counties: Seattle Everett, WA 7.2 WA King; WA Snohomish. Tacoma, WA 6.2 WA Pierce. Non -SMSA Counties 6.1 WA Clallam; WA Grays Harbor; WA Island; WA Jefferson; WA Kitsap; WA Lewis; WA Mason; WA Pacific; WA San Juan; WA Skagit; WA Thurston; WA Whatcom. Portland, OR: SMSA Counties: Portland, OR -WA WA Clark. Non -SMSA Counties WA Cowlitz; 4.5 3.8 WA Klickitat; WA Skamania; WA Wahkiakum. These goals are applicable to each nonexempt Contractor's total on-site construction workforce, regardless of whether or not part of that workforce is performing work on a Federal, or federally assisted project, contract, or subcontract until further notice. Compliance with these goals and time tables is enforced by the Office of Federal Contract compliance Programs. The Contractor's compliance with the Executive Order and the regulations in 41 CFR Part 60-4 shall be based on its implementation of the Equal Opportunity Clause, specific affirmative action obligations required by the specifications set forth in 41 CFR 60-4.3(a), and its efforts to meet the goals. The hours of minority and female employment and training must be substantially uniform throughout the length of the contract, in each construction craft and in each trade, and the Contractor shall make a good faith effort to employ minorities and women evenly on each of its projects. The transfer of minority or female employees or trainees from Contractor to Contractor or from project to project for the sole purpose of meeting the Contractor's goal shall be a violation of the contract, the Executive Order and the regulations in 41 CFR Part 60-4. Compliance with the goals will be measured against the total work hours performed. 3. The Contractor shall provide written notification to the Office of Federal Contract Compliance Programs (OFCCP) within 10 working days of award of any construction subcontract in excess of $10,000 or more that are Federally funded, at any tier for construction work under the contract resulting from this solicitation. The notification shall list the name, address and telephone number of the Subcontractor; employer identification number of the Subcontractor; estimated dollar amount of the subcontract; estimated starting and completion dates of the subcontract; and the geographical area in which the contract is to be performed. The notification shall be sent to: U.S. Department of Labor Office of Federal Contract Compliance Programs Pacific Region Attn: Regional Director San Francisco Federal Building 90-7 1h Street, Suite 18-300 Crosswalk Improvements Special Provisions City of Bremerton. Washington 21 Skillings Connolly, Inc. Federal Anil # S7PUS-9918(015) April 2016 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 San Francisco, CA 94103(415) 625-7800 Phone (415) 625-7799 Fax Additional information may be found at the U.S. Department of Labor website: http://www.dol.gov/ofccp/TAguides/ctaguide.htm 4. As used in this Notice, and in the contract resulting from this solicitation, the Covered Area is as designated herein. Standard Federal Equal Employment Opportunity Construction Contract Specifications (Executive Order 11246) 1. As used in these specifications: a. Covered Area means the geographical area described in the solicitation from which this contract resulted; b. Director means Director, Office of Federal Contract Compliance Programs, United States Department of Labor, or any person to whom the Director delegates authority; c. Employer Identification Number means the Federal Social Security number used on the Employer's Quarterly Federal Tax Return, U. S. Treasury Department Form 941; d. Minority includes: (1) Black, a person having origins in any of the Black Racial Groups of Africa. (2) Hispanic, a fluent Spanish speaking, Spanish surnamed person of Mexican, Puerto Rican, Cuban, Central American, South American, or other Spanish origin. (3) Asian or Pacific Islander, a person having origins in any of the original peoples of the Pacific rim or the Pacific Islands, the Hawaiian Islands and Samoa. (4) American Indian or Alaskan Native, a person having origins in any of the original peoples of North America, and who maintain cultural identification through tribal affiliation or community recognition. 2. Whenever the Contractor, or any Subcontractor at any tier, subcontracts a portion of the work involving any construction trade, it shall physically include in each subcontract in excess of $10,000 the provisions of these specifications and the Notice which contains the applicable goals for minority and female participation and which is set forth in the solicitations from which this contract resulted. 3. If the Contractor is participating (pursuant to 41 CFR 60-4.5) in a Hometown Plan approved by the U.S. Department of Labor in the covered area either individually or through an association, its affirmative action obligations on all work in the Plan Crosswalk Improvements Special Provisions Citv of Bremerton, Washington 22 Skillings Connolly, lac. Federal Aid # STPUS-9918(015) April 2016 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 area (including goals and timetables) shall be in accordance with that Plan for those trades which have unions participating in the Plan. Contractors must be able to demonstrate their participation in and compliance with the provisions of any such Hometown Plan. Each Contractor or Subcontractor participating in an approved Plan is individually required to comply with its obligations under the EEO clause, and to make a good faith effort to achieve each goal under the Plan in each trade in which it has employees. The overall good faith performance by other Contractors or Subcontractors toward a goal in an approved Plan does not excuse any covered Contractor's or Subcontractor's failure to take good faith effort to achieve the Plan goals and timetables. 4. The Contractor shall implement the specific affirmative action standards provided in paragraphs 7a through 7p of this Special Provision. The goals set forth in the solicitation from which this contract resulted are expressed as percentages of the total hours of employment and training of minority and female utilization the Contractor should reasonably be able to achieve in each construction trade in which it has employees in the covered area. Covered construction contractors performing construction work in geographical areas where they do not have a Federal or federally assisted construction contract shall apply the minority and female goals established for the geographical area where the work is being performed. The Contractor is expected to make substantially uniform progress in meeting its goals in each craft during the period specified. 5. Neither the provisions of any collective bargaining agreement, nor the failure by a union with whom the Contractor has a collective bargaining agreement, to refer either minorities or women shall excuse the Contractor's obligations under these specifications, Executive Order 11246, or the regulations promulgated pursuant thereto. 6. In order for the nonworking training hours of apprentices and trainees to be counted in meeting the goals, such apprentices and trainees must be employed by the Contractor during the training period, and the Contractor must have made a commitment to employ the apprentices and trainees at the completion of their training, subject to the availability of employment opportunities. Trainees must be trained pursuant to training programs approved by the U.S. Department of Labor. 7. The Contractor shall take specific affirmative actions to ensure equal employment opportunity. The evaluation of the Contractor's compliance with these specifications shall be based upon its effort to achieve maximum results from its action. The Contractor shall document these efforts fully, and shall implement affirmative action steps at least as extensive as the following: a. Ensure and maintain a working environment free of harassment, intimidation, and coercion at all sites, and in all facilities at which the Contractor's employees are assigned to work. The Contractor, where possible, will assign two or more women to each construction project. The Contractor shall specifically ensure that all foremen, superintendents, and other on-site supervisory personnel are aware of and carry out the Contractor's obligation to maintain such a working environment, with specific attention to minority or female individuals working at such sites or in such facilities. Crosswalk Improvements Ci(v of Bremerton, Washington Federal Aid # STPUS-9918(015) 23 Special Provisions Skillings Connollv. Inc. April 2016 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 b. Establish and maintain a current list of minority and female recruitment sources, provide written notification to minority and female recruitment sources and to community organizations when the Contractor or its unions have employment opportunities available, and maintain a record of the organizations' responses. Maintain a current file of the names, addresses and telephone numbers of each minority and female off -the -street applicant and minority or female referral from a union, a recruitment source or community organization and of what action was taken with respect to each such individual. If such individual was sent to the union hiring hall for referral and was not referred back to the Contractor by the union or, if referred, not employed by the Contractor, this shall be documented in the file with the reason therefor, along with whatever additional actions the Contractor may have taken. d. Provide immediate written notification to the Director when the union or unions with which the Contractor has a collective bargaining agreement has not referred to the Contractor a minority person or woman sent by the Contractor, or when the Contractor has other information that the union referral process has impeded the Contractor's efforts to meet its obligations. e. Develop on-the-job training opportunity and/or participate in training programs for the area which expressly include minorities and women, including upgrading programs and apprenticeship and trainee programs relevant to the Contractor's employment needs, especially those programs funded or approved by the U.S. Department of Labor. The Contractor shall provide notice of these programs to the sources compiled under 7b above. Disseminate the Contractor's EEO policy by providing notice of the policy to unions and training programs and requesting their cooperation in assisting the Contractor in meeting its EEO obligations; by including it in any policy manual and collective bargaining agreement; by publicizing it in the company newspaper, annual report, etc.; by specific review of the policy with all management personnel and with all minority and female employees at least once a year; and by posting the company EEO policy on bulletin boards accessible to all employees at each location where construction work is performed. g. Review, at least annually, the company's EEO policy and affirmative action obligations under these specifications with all employees having any responsibility for hiring, assignment, layoff, termination or other employment decisions including specific review of these items with on-site supervisory personnel such as Superintendents, General Foremen, etc., prior to the initiation of construction work at any job site. A written record shall be made and maintained identifying the time and place of these meetings, persons attending, subject matter discussed, and disposition of the subject matter. h. Disseminate the Contractor's EEO policy externally by including it in any advertising in the news media, specifically including minority and female Crosswalk hnprovements Special Provisions City of Bremerton. Washington 24 Skillings Connollv. Inc. Federal Aid # STPUS-991 8(015) April 20l 6 1 news media, and providing written notification to and discussing the 2 Contractor's EEO policy with other Contractors and Subcontractors with 3 whom the Contractor does or anticipates doing business. 4 5 i. Direct its recruitment efforts, both oral and written to minority, female and 6 community organizations, to schools with minority and female students 7 and to minority and female recruitment and training organizations serving 8 .the Contractor's recruitment area and employment needs. Not later than 9 one month prior to the date for the acceptance of applications for 10 apprenticeship or other training by any recruitment source, the Contractor 11 shall send written notification to organizations such as the above, 12 describing the openings, screening procedures, and tests to be used in 13 the selection process. 14 15 j. Encourage present minority and female employees to recruit other 16 minority persons and women and where reasonable, provide after school, 17 summer and vacation employment to minority and female youth both on 18 the site and in other areas of a Contractor's work force. 19 20 k. Validate all tests and other selection requirements where there is an 21 obligation to do so under 41 CFR Part 60-3. 22 23 I. Conduct, at least annually, an inventory and evaluation of all minority and 24 female personnel for promotional opportunities and encourage these 25 employees to seek or to prepare for, through appropriate training, etc., 26 such opportunities. 27 28 m. Ensure that seniority practices, job classifications, work assignments and 29 other personnel practices, do not have a discriminatory effect by 30 continually monitoring all personnel and employment related activities to 31 ensure that the EEO policy and the Contractor's obligations under these 32 specifications are being carried out. 33 34 • n. Ensure that all facilities and company activities are nonsegregated except 35 that separate or single -user toilet and necessary changing facilities shall 36 be provided to assure privacy between the sexes. 37 38 o. Document and maintain a record of all solicitations of offers for 39 subcontracts from minority and female construction contractors and 40 suppliers, including circulation of solicitations to minority and female 41 contractor associations and other business associations. 42 43 p. Conduct a review, at least annually, of all supervisors' adherence to and 44 performance under the Contractor's EEO policies and affirmative action 45 obligations. 46 47 8. Contractors are encouraged to participate in voluntary associations which assist in 48 fulfilling one or more of their affirmative action obligations (7a through 7p). The 49 efforts of a contractor association, joint contractor -union, contractor -community, or 50 other similar group of which the Contractor is a member and participant, may be 51 asserted as fulfilling any one or more of the obligations under 7a through 7p of this 52 Special Provision provided that the Contractor actively participates in the group, Crosswalk Improvements Special Provisions Citv of Bremerton. Washington 25 Skillings Connolly, Inc. Federal Aid # S'/•PUS-9918(1115) April 2016 1 makes every effort to assure that the group has a positive impact on the 2 employment of minorities and women in the industry, ensure that the concrete 3 benefits of the program are reflected in the Contractor's minority and female work - 4 force participation, makes a good faith effort to meet its individual goals and 5 timetables, and can provide access to documentation which demonstrate the 6 effectiveness of actions taken on behalf of the Contractor. The obligation to 7 comply, however, is the Contractor's and failure of such a group to fulfill an 8 obligation shall not be a defense for the Contractor's noncompliance. 9 10 9. A single goal for minorities and a separate single goal for women have been 11 established. The Contractor, however, is required to provide equal employment 12 opportunity and to take affirmative action for all minority groups, both male and 13 female, and all women, both minority and non -minority. Consequently, the 14 Contractor may be in violation of the Executive Order if a particular group is 15 employed in substantially disparate manner (for example, even though the 16 Contractor has achieved its goals for women generally, the Contractor may be in 17 violation of the Executive Order if a specific minority group of women is 18 underutilized). 19 20 10. The Contractor shall not use the goals and timetables or affirmative action 21 standards to discriminate against any person because of race, color, religion, sex, 22 or national origin. 23 24 11. The Contractor shall not enter into any subcontract with any person or firm 25 debarred from Government contracts pursuant to Executive Order 11246. 26 27 12. The Contractor shall carry out such sanctions and penalties for violation of these 28 specifications and of the Equal Opportunity Clause, including suspensions, 29 terminations and cancellations of existing subcontracts as may be imposed or 30 ordered pursuant to Executive Order 11246, as amended, and its implementing 31 regulations by the Office of Federal Contract Compliance Programs. Any 32 Contractor who fails to carry out such sanctions and penalties shall be in violation 33 of these specifications and Executive Order 11246, as amended. 34 35 13. The Contractor, in fulfilling its obligations under these specifications, shall 36 implement specific affirmative action steps, at least as extensive as those 37 standards prescribed in paragraph 7 of this Special Provision, so as to achieve 38 maximum results from its efforts to ensure equal employment opportunity. If the 39 Contractor fails to comply with the requirements of the Executive Order, the 40 implementing regulations, or these specifications, the Director shall proceed in 41 accordance with 41 CFR 60-4.8. 42 43 14. The Contractor shall designate a responsible official to monitor all employment 44 related activity to ensure that the company EEO policy is being carried out, to 45 submit reports relating to the provisions hereof as may be required by the 46 government and to keep records. Records shall at least include, for each 47 employee, their name, address, telephone numbers, construction trade, union 48 affiliation if any, employee identification number when assigned, social security 49 number, race, sex, status (e.g., mechanic, apprentice, trainee, helper, or laborer), 50 dates of changes in status, hours worked per week in the indicated trade, rate of 51 pay, and locations at which the work was performed. Records shall be maintained 52 in an easily understandable and retrievable form; however, to the degree that Crosswalk Improvements Special Provisions Citv of Bremerton. Washington 26 Skillings Connollv. Inc Federal Aid # STPUS-9918(015) April 2016 1 existing records satisfy this requirement, the Contractors will not be required to 2 maintain separate records. 3 4 15. Nothing herein provided shall be construed as a limitation upon the application of 5 other laws which establish different standards of compliance or upon the 6 application of requirements for the hiring of local or other area residents (e.g., those 7 under the Public Works Employment Act of 1977 and the Community Development 8 Block Grant Program). 9 10 16. Additional assistance for Federal Construction Contractors on contracts 11 administered by Washington State Department of Transportation or by Local 12 Agencies may be found at: 13 14 Washington State Dept. of Transportation 15 Office of Equal Opportunity 16 PO Box 47314 17 310 Maple Park Ave. SE 18 Olympia WA 19 98504-7314 20 Ph: 360-705-7090 21 Fax: 360-705-6801 22 http://www.wsdot.wa.gov/equalopportunity/default.htm 23 24 1-07.11 Requirements for Nondiscrimination 25 (December 8, 2014 APWA GSP, Option B) 26 27 Supplement this section with the following: 28 29 Disadvantaged Business Enterprise Condition of Award Participation 30 The Disadvantaged Business Enterprise (DBE) requirements of 49 CFR Part 26 apply 31 to this Contract. Demonstrating compliance with these specifications is a Condition of 32 Award (COA) of this Contract. Failure to comply with the requirements of this 33 specification may result in your bid being found to be nonresponsive and may be 34 rejected. 35 36 DBE COA Goal 37 The Contracting Agency has established a COA Contract goal in the amount of: 38 14%. 39 40 DBE Eligibility/Selection of DBEs 41 A Directory of Certified DBE Firms denoting the Description of Work the DBE 42 Contractors are certified to perform is available at: 43 44 www.omwbe.wa.gov/certification/index.shtml. 45 46 The directory provides plain language on the Description of Work that the listed 47 DBE's have been certified by the Office of Minority and Women's Business 48 Enterprises (OMWBE) to perform. The Bidder shall use the Directory of 49 Certified DBE Firms to confirm if a DBE is certified for the "Description of 50 Work" the Bidder lists on the DBE Utilization Certification form # 272-056 EF 51 (see form instructions) and therefore qualifies for credit towards the COA goal. 52 Crosswalk Improvements Special Provisions Citv of Bremerton. Washington 27 Skillings Connolly, Inc. Federal Aid # STPUS-9918(015) April 2016 1 Crediting DBE Participation 2 Joint Venture 3 When a DBE performs as a participant in a joint venture, only that portion of 4 the total dollar value of the Contract equal to the distinct, clearly defined 5 portion of the Work that the DBE performs with its own forces shall be credited. 6 7 DBE Prime Contractor 8 A DBE Prime Contractor may only take credit for that portion of the total dollar 9 value of the Contract equal to the distinct, clearly defined portion of the Work 10 that the DBE Prime performs with its own forces. 11 12 DBE Subcontractor 13 When a DBE firm participates as a Subcontractor only that portion of the total 14 dollar value of the Contract equal to the distinct, clearly defined portion of the 15 Work that the DBE performs with its own forces shall be credited. 16 17 • Include the cost of supplies and materials obtained by the DBE for the 18 Work in the Contract including supplies purchased or equipment leased 19 by the DBE. 20 However, you may not take credit for supplies, materials, and 21 equipment the DBE Subcontractor purchases or leases from the 22 Prime Contractor or its affiliate. In addition, Work performed by a 23 DBE, utilizing resources of the Prime Contractor or its affiliates 24 shall not be credited. 25 26 In very rare situations, a DBE firm may utilize equipment and/or 27 personnel from a non -DBE firm other than the Prime Contractor or its 28 affiliates. Should this situation arise the arrangement must be short - 29 term and have prior written approval from the Office of Equal 30 Opportunity (OEO). 31 32 Count the entire value of fees or commissions charged by a DBE firm 33 for providing a bona fide service, such as professional, technical, 34 consultant, managerial services, or for providing bonds or insurance. 35 36 • When a DBE subcontracts to another firm, the value of the 37 subcontracted Work may be counted as participation only if the DBE's 38 lower tier Subcontractor is also a DBE. Work that a DBE subcontracts 39 to a non -DBE firm shall not be credited. 40 41 42 When non -DBE Subcontractor further subcontracts to a lower -tier 43 Subcontractor or supplier who is a certified DBE, then that portion of 44 the Work further subcontracted may be credited as DBE participation, 45 provided it is a distinct clearly defined portion of the Work that the DBE 46 is certified to perform and the DBE Subcontractor performs the Work 47 with its own forces. 48 49 If a firm is not certified as a DBE at the time of the execution of the 50 contract, their participation cannot be counted toward any DBE goals. 51 Crosswalk Improvements Special Provisions Citv of Bremerton, Washington 28 Skillings Connolly, Inc. Federal Aid # STPUS-9918(015) April 2016 1 Trucking 2 Use the following factors in determining DBE credit and whether a DBE 3 trucking company is performing a commercially useful function: 4 5 1. The DBE must be responsible for the management and supervision of 6 the entire trucking operation for which credit is being claimed. 7 8 2. The DBE must itself own and, with its own workforce, operate at least 9 one fully licensed, insured, and operational truck used on the 10 Contract. 11 12 3. The DBE receives credit only for the value of the transportation 13 services it provides on the Contract using trucks it owns or leases, 14 licenses, insures, and operates with drivers it employs. For purposes 15 of this requirement a lease must indicate that the DBE has exclusive 16 use of and control over the truck. This does not preclude the leased 17 truck from working for others provided it is with the consent of the 18 DBE and the lease provides the DBE first priority for use of the leased 19 truck. Leased trucks must display the name and identification number 20 of the DBE. 21 22 4. The DBE may lease trucks from another DBE firm including an 23 owner -operator provided they are certified as a DBE for trucking. The 24 DBE who leases trucks from another DBE may claim participation for 25 the total value of the transportation services the lessee DBE provides 26 on the Contract. 27 28 5. The DBE may also lease trucks from a non -DBE firm and may enter 29 into an agreement with an owner -operator who is a non -DBE. The 30 DBE shall only receive credit for the number of additional non -DBE 31 trucks equal or less than the number of DBE trucks the firms owns or 32 has leased/subcontracted through another DBE trucking company. 33 The DBE must control the work of the non -DBE trucks. If the non - 34 DBE is performing the work without supervision of that work by the 35 DBE, the DBE is not performing a Commercially Useful Function 36 (CUF). 37 38 6. In any lease or owner -operator situation, as described in requirement 39 #4 and #5 above, the following rules shall apply: 40 41 a. A written lease/rental agreement is required for all trucks 42 leased or rented; documenting the ownership and the terms 43 of the agreement. The agreements must be submitted and 44 approved by the Contracting Agency prior to the beginning 45 of the Work. The agreement must show the leaser's name, 46 truck description and agreed upon amount and method of 47 payment (hour, ton, or per load). All lease agreements shall 48 be for a long-term relationship, rather than for the individual 49 project. (This requirement does not apply to owner -operator 50 arrangements.) 51 Crosswalk lmprovemenws Special Provisions City of Bremerton. Washington 29 Skillings Connolly, Inc. Federal Aid # S7PUS-9918(015) April 2016 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 b. Only the vehicle, (not the operator) may be leased or rented. (This requirement does not apply to owner -operator arrangements). 7. Credit may only be claimed for DBE trucking firms operating under a subcontract or a written agreement approved by the Contracting Agency prior to performing Work. Expenditures paid to other DBEs Expenditures paid to other DBEs for materials or supplies may be counted toward DBE goals as provided in the following: Manufacturer You may claim DBE credit for 100 percent of value of the materials or supplies obtained from a DBE manufacturer. A manufacturer is a firm that operates or maintains a factory or establishment that produces, on the premises, the materials, supplies, articles, or equipment required under the contract. A manufacturer shall include firms that produce finished goods or products from raw or unfinished material or that purchases and substantially alters goods and materials to make them suitable for construction use before reselling them. In order to receive credit as a DBE Manufacturer, the firm must be certified by OMWBE as a manufacturer in a NAICS code that falls within the 31XXXX to 33XXXX classification. Regular Dealer You may claim credit for 60 percent of the value of the materials or supplies purchased from a DBE regular dealer. Rules applicable to regular dealer status are contained in 49 CFR Part 26.55.e.2. To be considered a regular dealer you must meet the following criteria: WSDOT considers and recognizes a regular dealer, as a firm that owns, operates, or maintains a store, warehouse, or other establishment in which the materials or supplies required for the performance of the Contract and described by the specifications of the Contract are bought, kept in stock and regularly sold or leased to the public in the usual course of business. • Sixty percent (60%) of the cost of materials or supplies purchased from an approved regular dealer may be credited as DBE participation. Regular dealer status is granted on a contract -by -contract basis. A firm wishing to be approved as a regular dealer for WSDOT contracted projects or Highways & Local Program administered projects must submit a request in writing to OEO for approval, no later than seven days prior to bid opening. Crosswalk Improvements Special Provisions City of Bremerton. Washington 30 Skillings Connollv. Inc. Federal Aid # STPUS-9918(0/5) April 2016 1 Once the OEO has received the request, an onsite review will be set up 2 with the firm and a review conducted to determine the firm's qualifications. 3 If it is determined that the firm qualifies as a regular dealer the OEO will 4 list the firm on an Approved Regular Dealers List. The list may be 5 accessed through the OEO Home website is at: 6 7 www.wsdot.wa.gov/equalopportunity. 8 9 Note: Requests to be listed as a regular dealer will only be processed if 10 the requesting firm is certified by the Office of Minority and 11 Women's Business Enterprises in a NAICS code that fall within 12 the 42XXXX NAICS Wholesale code section. 13 14 Materials or Supplies Purchased from a DBE 15 With regard to materials or supplies purchased from a DBE who is neither 16 a manufacturer nor a regular dealer you may claim credit for the following: 17 18 1. Fees or commissions charged for assistance in the procurement 19 of the materials and supplies. 20 21 2. Fees or transportation charges for the delivery of materials or 22 supplies. 23 24 In either case you may not take credit for any part of the cost of the 25 materials and supplies. 26 27 Commercially Useful Function (CUF) 28 The Prime Contractor has a responsibility and must treat the working 29 relationship with the DBE such that the DBE is performing a commercially 30 useful function. The Prime Contractor may only take credit for Work performed 31 by a DBE that is determined to be performing a commercially useful function. 32 33 • A DBE performs a commercially useful function when it is responsible for 34 execution of a distinct element of Work and is carrying out its 35 responsibilities by performing, managing and supervising the Work 36 involved. The DBE must also be responsible with respect to materials and 37 supplies used on the Contract. For example; negotiating price, 38 determining quality, determining quantities, ordering, installing (if 39 applicable) and paying for the material itself. 40 41 A DBE does not perform a commercially useful function if its role is limited 42 to that of an extra participant in a transaction, Contract, or project through 43 which funds are passed. 44 45 46 Joint Checking Allowance 47 Prime Contractors and DBEs must receive pre-approval by the OEO before 48 using a joint check. Joint check requests shall be submitted by the Prime 49 Contractor to the Contracting Agency for approval. 50 51 When requesting approval for use of a joint checking allowance, the Contractor 52 must distribute a written joint check agreement among the parties (including Crosswalk Improvements Special Provisions City of Bremerton, Washington 31 Skillings Catnolly. Grc. Federal Aid # S7PUS-9918(01.1) Apri12016 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 the suppliers involved) providing full and prompt disclosure of the expected use of the joint checks. The agreement shall contain all the information concerning the parties' obligations and consequences or remedies if the agreement is not fulfilled or a breach occurs. The joint check request shall be submitted to the Contracting Agency for approval prior to signing the contract agreement. The following are some general conditions that must be met by all parties regarding joint check use: a. It is understood that the Prime Contractor acts solely as the guarantor of a joint check. b. The DBE's own funds are used to pay supplier of materials. The Prime Contractor does not make direct payment to supplier. In order to be performing a Commercially Useful Function (CUF), the DBE must release the check to the supplier (paying for the materials it -self and not be an extra participant in a transaction). c. If the Prime Contractor makes joint checks available to one DBE Subcontractor, the service must be made available to all Subcontractors (DBE and non -DBE). d. The relationship between the DBE and its suppliers should be established independently of and without interference by the Prime Contractor. The DBE has final decision-making responsibility concerning the procurement of materials and supplies, including which supplier to use. e. The Prime Contractor and DBE shall be able to provide receipts, invoices, cancelled checks and/or certification statements of payment if requested by the Contracting Agency. f. The DBE remains responsible for all other elements of 49 CFR 26.55(c)(1). Failure by the Prime Contractor to request and receive prior approval of a joint check arrangement will result in the joint check amount not counting towards the Prime Contractor's DBE goal. Disadvantaged Business Enterprise Utilization Certification FORM # 272- 056 EF To be eligible for award of the Contract, the Bidder shall properly complete and submit a Disadvantaged Business Enterprise Utilization Certification with the Bidder's sealed Bid Proposal, as specified Section 1-02.9 Delivery of Proposal. The Bidder's Disadvantaged Business Enterprise Utilization Certification must clearly demonstrate how the Bidder intends to meet the DBE COA goal. A Disadvantaged Business Enterprise Utilization Certification (form # 272-056 EF) is included in your Proposal package for this purpose as well as instructions on how to properly fill out the form. In the event of arithmetic errors in completing the Disadvantaged Business Enterprise Utilization Certification the amount listed to be applied towards the Crosswalk Improvements Special Provisions City of Bremerton, Washington 32 Skillings Connolly, frit Federal Aid # STPUS-9918(015) Apri1201 h 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 goal for each DBE shall govern and the DBE total amount shall be adjusted accordingly. Note: The Contracting Agency shall consider as non-responsive and shall reject any Bid Proposal submitted that does not contain a Disadvantaged Business Enterprise Utilization Certification that accurately demonstrates how the Bidder intends to meet the COA goal. Disadvantaged Business Enterprise (DBE) Written Confirmation Document(s) FORM # 422-031 EF The Bidder shall submit a complete and accurate Disadvantaged Business Enterprise (DBE) Written Confirmation Document for each DBE firm listed in the Bidder's completed Disadvantaged Business Enterprise Utilization Certification as submitted with the bid. Failure to do so will result in the associated participation being disallowed, which may result in bid rejection. A Disadvantaged Business Enterprise (DBE) Written Confirmation Document (form No. 422-031 EF) is included in your Proposal package for this purpose. The form(s) shall be received as specified in the special provisions for Section 1-02.9 Delivery of Proposal. It is prohibited for the Bidder to require a DBE to submit a Written Confirmation Document with any part of the form left blank. Should the Contracting Agency determine that a Written Confirmation Document was signed by a DBE that was not complete; the validity of the document comes into question and the associated DBE Participation may not receive credit. Selection of Successful Bidder/Good Faith Efforts (GFE) The successful Bidder shall be selected on the basis of having submitted the lowest responsive Bid, which demonstrates a good faith effort to achieve the DBE COA goal. Achieving the goal may be accomplished in one of two ways, as follows: By meeting the -goal The best indication of good faith efforts is to document, through submission of the Disadvantaged Business Enterprise Utilization Certification and supporting Disadvantaged Business Enterprise (DBE) Written Confirmation Document(s) that the Bidder has obtained enough DBE participation to meet or exceed the assigned DBE COA contract goal. That being the case no additional GFE documentation is required. Or; 2. By documentation that it made adequate GFE to meet the goal The Bidder may demonstrate a GFE in whole or part through GFE documentation ONLY IN THE EVENT a Bidder's efforts to solicit sufficient DBE participation have been unsuccessful. In this case, the Bidder must supply GFE documentation in addition to the Disadvantaged Business Enterprise Utilization Certification, and supporting Disadvantaged Business Enterprise (DBE) Written Confirmation document(s). Crosswalk Improvements Citv of Bremerton, Washiitgtat Federal Aid # S7PUS-9918(015) 33 Special Provisions Skillings Connolly, Inc. April 2016 1 2 Note: In the case where the Bidder was awarded the contract based on 3 demonstrating adequate GFE the advertised DBE goal will not be 4 reduced to the Bidder's partial commitment. The Bidder shall 5 demonstrate a GFE during the life of the Contract to attain the DBE 6 Condition of Award (COA) Goal as assigned to the project. 7 specific DBEs, identified from the OMWBE Directory of Certified DBE 8 Good Faith Efforts (GFE) Documentation 9 GFE documentation shall be received, as specified in the special provisions for 10 Section 1-02.9 Delivery of Proposal. 11 6. Follow-up by the Bidder of initial solicitations of interest by contacting 12 Based upon all the relevant documentation submitted in Bid or as supplement 13 to Bid, the Contracting Agency shall determine whether the Bidder has 14 demonstrated a sufficient GFE to achieve DBE participation. The Contracting 15 Agency will make a fair and reasonable judgment of whether a Bidder that did 16 not meet the goal through participation, made adequate good faith efforts as 17 demonstrated by the GFE documentation. 18 19 The following is a list of types of actions, which would be considered as part of 20 the Bidder's GFE to achieve DBE participation. It is not intended to be a 21 mandatory checklist, nor is it intended to be exclusive or exhaustive. Other 22 factors or types of efforts may be relevant in appropriate cases: 23 24 1. Attendance by the Bidder at any pre -solicitation or pre -Bid meetings 25 that were scheduled by the Contracting Agency to inform DBEs of 26 contracting and subcontracting or material supply opportunities 27 available on the project; 28 2. Contacting local Tribes, Tribal Employment Rights Offices (TERO) 29 concerning the subcontracting or supply opportunities in sufficient 30 time to allow the enterprises to participate effectively; 31 3. Selection by the Bidder of specific economically feasible units of the 32 project to be performed by DBEs in order to increase the likelihood of 33 participation by DBEs even if the Bidder preferred to perform these 34 Work items as the Prime Contractor; 35 36 4. Advertising by the Bidder in general circulation, trade association 37 minority and trade oriented, women focus publications, concerning 38 the subcontracting or supply opportunities; 39 40 5. Providing written notice from the Bidder to a reasonable number of 41 specific DBEs, identified from the OMWBE Directory of Certified DBE 42 Firms for the selected subcontracting or material supply Work, in 43 sufficient time to allow the enterprises to participate effectively; 44 45 6. Follow-up by the Bidder of initial solicitations of interest by contacting 46 the DBEs to determine with certainty whether they were interested. 47 Documentation of this kind of action shall include the information 48 outlined below: 49 50 a. The names, addresses, telephone numbers of DBEs who were 51 contacted, the dates of initial contact, and whether initial Crosswalk Improvements Special Provisions City of Bremerton, Rashington 34 Skillings Connollv, Inc. Federal Aid # STPUS-9918(015) April 2010 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 solicitations of interest were followed-up by contacting the DBEs to determine with certainty whether the DBEs were interested; b. A description of the information provided to the DBEs regarding the plans, specifications, and estimated quantities for portions of the Work to be performed; Documentation of each DBE contacted but rejected and the reason(s) for that rejection; 7. Providing, to interested DBEs, adequate information about the plans, specifications, and requirements for the selected subcontracting or material supply Work; 8. Negotiating in good faith with the DBE firms, and not, without justifiable reason, rejecting as unsatisfactory, Bids that are prepared by any DBE. The DBE's standing within its industry, membership in specific groups, organizations, or associations and political or social affiliations - union vs. non-union employee status - are not legitimate causes for the rejection or non -solicitation of bids in the Prime Contractor's efforts to meet the project goal; 9. Advertising and making efforts to obtain DBE participation that were reasonably expected to produce a level of participation sufficient to meet the goal or requirements of the Contracting Agency; 10. Making any other efforts to obtain DBE participation that were reasonably expected to produce a level of participation sufficient to meet the goal or requirements of the Contracting Agency; 11. Using the services of minority community organizations, minority contractor groups, local, State, and federal minority business assistance offices and other organizations identified by WSDOT and advocates for disadvantaged, minority, and women businesses that provide assistance in the recruitment and placement of disadvantaged, minority, and women business enterprises; and 12. Using the WSDOT OEO DBE Supportive Services to assist you. For more. information please contact the OEO by calling toll free at (888) 259-9143 or emailing dbess@wsdot.wa.gov. Administrative Reconsideration of GFE Documentation Any Bidder has the right to reconsideration but only for the purpose of reassessing their GFE documentation that was determined to be inadequate. The Bidder must request and schedule a reconsideration hearing within seven calendar days of notification of being nonresponsive or forfeit the right to reconsideration. • The reconsideration decision on the adequacy of the Bidder's GFE documentation shall be made by an official who did not take part in the original determination. Crosswalk Improvements Cy of Bremerton. Washington Federal Aid # S7PUS-9918(01.1) 35 Special Provisions Skillings Connolly, Inc. April 2016 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 • The Bidder shall have the opportunity to meet in person with the official for the purpose of setting forth the Bidder's position as to why the GFE documentation demonstrates a sufficient effort. • The reconsideration official shall provide the Bidder with a written decision on reconsideration within five business days of the hearing explaining the basis for their finding. Procedures between Award and Execution After Award and prior to Execution the Bidder shall provide the additional information described below. Failure to comply shall result in the forfeiture of the Bidder's Proposal bond or deposit. 1. Additional information for all successful DBE's as shown on the Disadvantaged Business Enterprise Utilization Certification: a. Correct business name, federal employee identification number (if available), and mailing address. b. List of all Bid items assigned to each successful DBE firm, including unit prices and extensions. c. Description of partial items (if any) to be sublet to each successful DBE firm specifying the distinct elements of Work under each item to be performed by the DBE and including the dollar value of the DBE portion. Total amounts shown for each DBE shall not be less than the amount shown on the Disadvantaged Business Enterprise Utilization Certification. A breakdown that does not conform to the Disadvantaged Business Enterprise Utilization Certification or that demonstrates a lesser amount of DBE participation than that included in the Disadvantaged Business Enterprise Utilization Certification will be returned for correction. 2. A list of all firms who submitted a Bid or quote in an attempt to participate in this project whether they were successful or not. Include the business name and a mailing address. Note: The firms identified by the Prime Contractor may be contacted by the Contracting Agency to solicit general information as follows: age of the firm and average of its gross annual receipts over the past three - years. Procedures after Execution Crediting DBE Participation toward Meeting the Goal Reporting All DBE work whether COA or race neutral participation is reported. The Prime Contractor shall submit a Quarterly Report of Amounts Credited as DBE Participation form (422-102 EF) on a quarterly basis for any calendar quarter in which DBE has accomplished Work or Crosswalk Improvements City of Bremerton. Washington Federal Aid # STPUS-9918(015) 36 Special Provisions Skillings Coli101iV. Inc April 2016 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 upon completion of the project, as appropriate. The dollars are to be reported as specified herein. In the event that the payments to a DBE have been made by an entity other than the Prime Contractor, as in the case of a lower -tier Subcontractor or supplier, then the Prime Contractor shall obtain the quarterly report, including the signed affidavit, from the paying entity and submit the report to the Contracting Agency. Changes in DBE COA participation Owner initiated Change Orders The Prime Contractor shall demonstrate a GFE to substitute COA DBE participation when the Contracting Agency deletes Work items by change order that impact a COA DBE's Work. When the Contract allows alternate Work methods which serve to delete or create under -runs in COA DBE Work then the Prime Contractor must provide documentation of negotiating the change with the DBE that was to perform the reduced Work and demonstrate a GFE to substitute other DBE COA participation. Original Quantity Under runs In the event that Work committed to a DBE firm as part of the COA under runs the original planned quantities the Prime Contractor shall demonstrate a GFE to substitute other DBE COA participation. Contractor -Initiated Proposals—General The Contractor cannot reduce the amount of work committed to a DBE firm at contract award without good cause and only with written concurrence from the OEO. Reducing a COA DBE's Work is viewed as a partial DBE termination, subject to the procedures below. DBE Termination A COA DBE Subcontractor may only be terminated in whole or part with the approval of the Contracting Agency (in coordination with OEO). Approval will be granted provided the Prime Contractor demonstrates that the termination is based on good cause. Good cause typically includes situations where the DBE Subcontractor is unable or has failed to perform the work of its subcontract in accordance with normal industry standards. While not all inclusive, some examples of good cause include the following circumstances: Good cause may exist if: • The listed DBE Subcontractor fails or refuses to execute a written contract. The listed DBE Subcontractor fails or refuses to perform the work of its subcontract in a way consistent with normal industry standards. Crosswalk Improvements Special Provisions Cin, of Bremerton, Washington 37 Skillings ConnoUv. Inc Federal Aid # STPUS-9918(0/5) April 2016 1 • The listed DBE Subcontractor fails or refuses to meet the 2 Prime Contractor's reasonable, nondiscriminatory bond 3 requirements. 4 5 • The listed DBE Subcontractor becomes bankrupt, insolvent, 6 or exhibits credit unworthiness. 7 8 • The listed DBE Subcontractor is ineligible to work on public 9 works projects because of suspension and debarment 10 proceedings pursuant 2 CFR Parts 180, 215 and 1,200 or 11 applicable state law. 12 13 • The listed DBE Subcontractor voluntarily withdraws from the 14 project and provides to you written notice of its withdrawal. 15 16 • The listed DBE is ineligible to receive DBE credit for the type 17 of work required. 18 19 0 A DBE owner dies or becomes disabled with the result that 20 the listed DBE is unable to complete its work on the contract. 21 22 Good cause does not exist if: 23 24 • The Prime Contractor seeks to terminate a COA DBE so that 25 the Prime can self -perform the Work. 26 27 • The Prime Contractor seeks to terminate a COA DBE so the 28 Prime Contractor can substitute another DBE or non -DBE 29 after contract award. 30' 31 • The failure or refusal of the DBE Subcontractor to perform its 32 work on the subcontract results from the bad faith or 33 discriminatory action of the Prime Contractor (e.g., the failure 34 of the Prime Contractor to make timely payments or the 35 unnecessary placing of obstacles in the path of the DBE's 36 Work). 37 38 Prior to requesting termination, the Prime Contractor must give notice in 39 writing to the DBE Subcontractor with a copy to the Contracting Agency of 40 its intent to request to terminate DBE work and the reasons for doing so. 41 The DBE Subcontractor shall have five (5) days to respond to the prime 42 Contractor's notice. The DBE's response shall either support the 43 termination or advise the Contracting Agency and the Prime Contractor of 44 the reasons it objects to the termination of its subcontract. 45 46 When a COA DBE firm is "terminated" from a Contract (or fails to complete 47 its Subcontract for any reason), the Prime Contractor shall make every 48 good faith effort to substitute another DBE Firm (ref.to 49 CFR 26.53(g)). Crosswalk Improvements Special Provisions Ci(v of Bremerton. Washington 38 Skillings Connollv. Inc. Federal Aid # STPUS-9918(015) April 1016 1 2 Graduation 3 When a DBE firm "graduates" from the DBE program (during the course of 4 an executed subcontract), the DBE participation of that firm "may" 5 continue to count towards the contract DBE goal. 6 7 Decertification 8 When a COA DBE firm who has a signed subcontract in place with a 9 Prime, later becomes "decertified" (during the course of that subcontract) 10 — the DBE participation of that firm "may" continue to count towards the 11 Contract DBE goal. 12 13 Counting payments 14 Payments to a DBE firm will count toward DBE goals only if the 15 participation is in accordance with these specifications. 16 17 Prompt Payment 18 Prompt payment to all Subcontractors shall be in accordance with Section 19 1-08.1(1) of these Contract special provisions. 20 21 Payment 22 Compensation for all costs involved with complying with the conditions of 23 this specification and any other associated DBE requirements is included 24 in payment for the associated Contract items of Work. 25 26 Damages for Noncompliance 27 The Prime Contractor shall not discriminate on the basis of race, color, 28 national origin, or sex in the performance of this Contract. The Prime 29 Contractor shall carry out applicable requirements of 49 CFR Part 26 in 30 the award and administration of Contracts, which contain funding 31 assistance from the United States Department of Transportation. Failure 32 by the Prime Contractor to carry out these requirements is a material 33 breach of this Contract, which may result in the Termination of this 34 Contract or such other remedy as the Contracting Agency deems 35 appropriate. 36 37 If the Prime Contractor does not comply with any part of its Contract as 38 required under 49 CFR part 26, and/or any other applicable law or 39 regulation regarding DBE, the Contracting Agency may withhold payment, 40 suspend the ability of the Prime Contractor to participate in future 41 Contracting Agency contracts, impose sanctions or Terminate the 42 Contract, and subject the Prime Contractor to civil penalties of up to ten 43 percent of the amount of the Contract for each violation. In the case of 44 WSDOT Contracts, prequalification may be suspended pursuant to WAC 45 468-16-180, and continuous violations (exceeding a single violation) may 46 also disqualify the Prime Contractor from further participation in WSDOT 47 Contracts for a period of up to three years. 48 49 An apparent low Bidder must be in compliance with these Contract 50 Provisions as a condition precedent to the granting of a notice of award by 51 the Contracting Agency. The Prime Contractor is entitled to request an 52 adjudicative proceeding with respect to the Contracting Agency's Crosswalk Improvements Special Provisions Gtv of Bremerton, Washington 39 Skillings Corotolly. Inc. Federal Aid # STPUS-9918(01 i) April 2016 1 determination of Contract violation and assessed penalties by filing a 2 written application within thirty days of receipt of notification. The 3 adjudicative proceeding, if requested, will be conducted by an 4 administrative law judge pursuant to the procedures set forth in RCW 5 34.05 and Chapter 10.08 of the Washington Administrative Code. 6 7 1-07.12 Federal Agency Inspection 8 9 Section 1-07.12 is supplemented with the following: 10 11 (January 25, 2016) 12 Required Federal Aid Provisions 13 The Required Contract Provisions Federal Aid Construction Contracts (FHWA 1273) 14 Revised May 1, 2012 and the amendments thereto supersede any conflicting provisions 15 of the Standard Specifications and are made a part of this Contract; provided, however, 16 that if any of the provisions of FHWA 1273, as amended, are less restrictive than 17 Washington State Law, then the Washington State Law shall prevail. 18 19 The provisions of FHWA 1273, as amended, included in this Contract require that the 20 Contractor insert the FHWA 1273 and amendments thereto in each Subcontract, 21 together with the wage rates which are part of the FHWA 1273, as amended. Also, a 22 clause shall be included in each Subcontract requiring the Subcontractors to insert the 23 FHWA 1273 and amendments thereto in any lower tier Subcontracts, together with the 24 wage rates. The Contractor shall also ensure that this section, REQUIRED FEDERAL 25 AID PROVISIONS, is inserted in each Subcontract for Subcontractors and lower tier 26 Subcontractors. For this purpose, upon request to the Project Engineer, the Contractor 27 will be provided with extra copies of the FHWA 1273, the amendments thereto, the 28 applicable wage rates, and this Special Provision. 29 30 Contractor's Responsibility for Work 31 32 Repair of Damage 33 34 Section 1-07.13(4) is revised to read: 35 36 (August 6, 2001) 37 The Contractor shall promptly repair all damage to either temporary or permanent 38 work as directed by the Engineer. For damage qualifying for relief under Sections 39 1-07.13(1), 1-07.13(2) or 1-07.13(3), payment will be made in accordance with 40 Section 1-04.4. Payment will be limited to repair of damaged work only. No 41 payment will be made for delay or disruption of work. 42 43 Utilities and Similar Facilities 44 45 Section 1-07.17 is supplemented with the following: 46 47 (April 2, 2007) 48 Locations and dimensions shown in the Plans for existing facilities are in accordance 49 with available information obtained without uncovering, measuring, or other verification. 50 Crosswalk Improvements Special Provisions City ojBreinerton, Washington 40 Skillings Connolly, Inc. Federal Aid # STPUS-9918(015) April 2016 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 The following addresses and telephone numbers of utility companies known or suspected of having facilities within the project limits are supplied for the Contractor's convenience: *** City of Bremerton (360) 473-5920 Puget Sound Energy (888) 728-9343 Cascade Natural Gas (360) 373-1405 Centurylink (800) 283-4237 1-07.18 Public Liability and Property Damage Insurance Delete this section in its entirety, and replace it with the following: 1-07.18 Insurance (January 4, 2016 APWA GSP) 1-07.18(1) General Requirements A. The Contractor shall procure and maintain the insurance described in all subsections of section 1-07.18 of these Special Provisions, from insurers with a current A. M. Best rating of not less than A-: VII and licensed to do business in the State of Washington. The Contracting Agency reserves the right to approve or reject the insurance provided, .based on the insurer's financial condition. B. The Contractor shall keep this insurance in force without interruption from the commencement of the Contractor's Work through the term of the Contract and for thirty (30) days after the Physical Completion date, unless otherwise indicated below. C. If any insurance policy is written on a claims made form, its retroactive date, and that of all subsequent renewals, shall be no later than the effective date of this Contract. The policy shall state that coverage is claims made, and state the retroactive date. Claims - made form coverage shall be maintained by the Contractor for a minimum of 36 months following the Completion Date or earlier termination of this Contract, and the Contractor shall annually provide the Contracting Agency with proof of renewal. If renewal of the claims made form of coverage becomes unavailable, or economically prohibitive, the Contractor shall purchase an extended reporting period ("tail") or execute another form of guarantee acceptable to the Contracting Agency to assure financial responsibility for liability for services performed. D. The Contractor's Automobile Liability, Commercial General Liability and Excess or Umbrella Liability insurance policies shall be primary and non-contributory insurance as respects the Contracting Agency's insurance, self-insurance, or self-insured pool coverage. Any insurance, self-insurance, or self-insured pool coverage maintained by the Contracting Agency shall be excess of the Contractor's insurance and shall not contribute with it. E. The Contractor shall provide the Contracting Agency and all additional insureds with written notice of any policy cancellation, within two business days of their receipt of such notice. Crosswalk Improvements Special Provisions City of Bremerton. Washington 41 Skillings Connollv, Inc. Federal Aid # STPUS-9918(0/5) April 20lh 1 F. The Contractor shall not begin work under the Contract until the required insurance has 2 been obtained and approved by the Contracting Agency 3 4 G. Failure on the part of the Contractor to maintain the insurance as required shall 5 constitute a material breach of contract, upon which the Contracting Agency may, after 6 giving five business days' notice to the Contractor to correct the breach, immediately 7 terminate the Contract or, at its discretion, procure or renew such insurance and pay any 8 and all premiums in connection therewith, with any sums so expended to be repaid to the 9 Contracting Agency on demand, or at the sole discretion of the Contracting Agency, 10 offset against funds due the Contractor from the Contracting Agency. 11 12 H. All costs for insurance shall be incidental to and included in the unit or lump sum prices 13 of the Contract and no additional payment will be made. 14 15 1-07.18(2) Additional Insured 16 All insurance policies, with the exception of Workers Compensation, and of Professional 17 Liability and Builder's Risk (if required by this Contract) shall name the following listed 18 entities as additional insured(s) using the forms or endorsements required herein: 19 ■ the Contracting Agency and its officers, elected officials, employees, agents, and 20 volunteers 21 ■ $$1$$ 22 ■ $$2$$ 23 ■ $$3$$ 24 The above -listed entities shall be additional insured(s) for the full available limits of liability 25 maintained by the Contractor, irrespective of whether such limits maintained by the 26 Contractor are greater than those required by this Contract, and irrespective of whether the 27 Certificate of Insurance provided by the Contractor pursuant to 1-07.18(4) describes limits 28 lower than those maintained by the Contractor. 29 30 For Commercial General Liability insurance coverage, the required additional insured 31 endorsements shall be at least as broad as ISO forms CG 20 10 10 01 for ongoing 32 operations and CG 20 37 10 01 for completed operations. 33 34 1-07.18(3) Subcontractors 35 The Contractor shall cause each Subcontractor of every tier to provide insurance coverage 36 that complies with all applicable requirements of the Contractor -provided insurance as set 37 forth herein, except the Contractor shall have sole responsibility for determining the limits of 38 coverage required to be obtained by Subcontractors. 39 40 The Contractor shall ensure that all Subcontractors of every tier add all entities listed in 41 1-07.18(2) as additional insureds, and provide proof of such on the policies as required by 42 that section as detailed in 1-07.18(2) using an endorsement as least as broad as ISO CG 20 43 10 10 01 for ongoing operations and CG 20 37 10 01 for completed operations. 44 45 Upon request by the Contracting Agency, the Contractor shall forward to the Contracting 46 Agency evidence of insurance and copies of the additional insured endorsements of each 47 Subcontractor of every tier as required in 1-07.18(4) Verification of Coverage. 48 49 1-07.18(4) Verification of Coverage 50 The Contractor shall deliver to the Contracting Agency a Certificate(s) of Insurance and 51 endorsements for each policy of insurance meeting the requirements set forth herein when 52 the Contractor delivers the signed Contract for the work. Failure of Contracting Agency to Crosswalk Improvements Special Provisions City of Bremerton, Washinglon 42 Skillings Connolly, Inc. F uleral Aid # STPUS-9918(01 i) April 2016 1 demand such verification of coverage with these insurance requirements or failure of 2 Contracting Agency to identify a deficiency from the insurance documentation provided shall 3 not be construed as a waiver of Contractor's obligation to maintain such insurance. 4 5 Verification of coverage shall include: 6 1. An ACORD certificate or a form determined by the Contracting Agency to be equivalent. 7 2. Copies of all endorsements naming Contracting Agency and all other entities listed in 8 1-07.18(2) as additional insured(s), showing the policy number. The Contractor may 9 submit a copy of any blanket additional insured clause from its policies instead of a 10 separate endorsement. 11 3. Any other amendatory endorsements to show the coverage required herein. 12 4. A notation of coverage enhancements on the Certificate of Insurance shall not satisfy 13 these requirements — actual endorsements must be submitted. 14 15 Upon request by the Contracting Agency, the Contractor shall forward to the Contracting 16 Agency a full and certified copy of the insurance policy(s). If Builders Risk insurance is 17 required on this Project, a full and certified copy of that policy is required when the 18 Contractor delivers the signed Contract for the work. 19 20 1-07.18(5) Coverages and Limits 21 The insurance shall provide the minimum coverages and limits set forth below. Contractor's 22 maintenance of insurance, its scope of coverage, and limits as required herein shall not be 23 construed to limit the liability of the Contractor to the coverage provided by such insurance, 24 or otherwise limit the Contracting Agency's recourse to any remedy available at law or in 25 equity. 26 27 All deductibles and self-insured retentions must be disclosed and are subject to approval by 28 the Contracting Agency. The cost of any claim payments falling within the deductible or self - 29 insured retention shall be the responsibility of the Contractor. In the event an additional 30 insured incurs a liability subject to any policy's deductibles or self-insured retention, said 31 deductibles or self-insured retention shall be the responsibility of the Contractor. 32 33 1-07.18(5)A Commercial General Liability 34 Commercial General Liability insurance shall be written on coverage forms at least as broad 35 as ISO occurrence form CG 00 01, including but not limited to liability arising from premises, 36 operations, stop gap liability, independent contractors, products -completed operations, 37 personal and advertising injury, and liability assumed under an insured contract. There shall 38 be no exclusion for liability arising from explosion, collapse or underground property 39 damage. 40 41 The Commercial General Liability insurance shall be endorsed to provide a per project 42 general aggregate limit, using ISO form CG 25 03 05 09 or an equivalent endorsement. 43 44 Contractor shall maintain Commercial General Liability Insurance arising out of the 45 Contractor's completed operations for at least three years following Substantial Completion 46 of the Work. 47 48 Such policy must provide the following minimum limits: 49 $1,000,000 Each Occurrence 50 $2,000,000 General Aggregate Crosswalk Improvements .Special Provisions Cily of Bremerton. Washington 43 Skillings Connolly. Inc. Federal Aid # S7 -PUS -9918(015) April 20/6 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 $2,000,000 Products & Completed Operations Aggregate $1,000,000 Personal & Advertising Injury each offence $1,000,000 Stop Gap / Employers' Liability each accident 1-07.18(5)B Automobile Liability Automobile Liability shall cover owned, non -owned, hired, and leased vehicles; and shall be written on a coverage form at least as broad as ISO form CA 00 01. If the work involves the transport of pollutants, the automobile liability policy shall include MCS 90 and CA 99 48 endorsements. Such policy must provide the following minimum limit: $1,000,000 Combined single limit each accident 1-07.18(5)C Workers' Compensation The Contractor shall comply with Workers' Compensation coverage as required by the Industrial Insurance laws of the State of Washington. Public Convenience and Safety Construction Under Trac Section 1-07.23(1) is supplemented with the following: (January 2, 2012) Work Zone Clear Zone The Work Zone Clear Zone (WZCZ) applies during working and nonworking hours. The WZCZ applies only to temporary roadside objects introduced by the Contractor's operations and does not apply to preexisting conditions or permanent Work. Those work operations that are actively in progress shall be in accordance with adopted and approved Traffic Control Plans, and other contract requirements. During nonworking hours equipment or materials shall not be within the WZCZ unless they are protected by permanent guardrail or temporary concrete barrier. The use of temporary concrete barrier shall be permitted only if the Engineer approves the installation and location. During actual hours of work, unless protected as described above, only materials absolutely necessary to construction shall be within the WZCZ and only construction vehicles absolutely necessary to construction shall be allowed within the WZCZ or allowed to stop or park on the shoulder of the roadway. The Contractor's nonessential vehicles and employees private vehicles shall not be permitted to park within the WZCZ at any time unless protected as described above. Deviation from the above requirements shall not occur unless the Contractor has requested the deviation in writing and the Engineer has provided written approval. Crosswalk Improvements Cin, of Bremerton, Washington rederal Aid 4 STPUS-9918(O15) 44 Special Provisions Skillings Connolly'/tic.April 2016 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 Minimum WZCZ distances are measured from the edge of traveled way and will be determined as follows: Regulatory Posted Speed Distance From Traveled Way Feet 35 mph or less 10* 40 mph 15 45 to 55 mph 20 60 mph or greater 30 ' or 2 -feet beyond the outside edge of sidewalk Minimum Work Zone Clear Zone Distance (January 5, 2015) Lane closures are subject to the following restrictions: *** Lane closures shall be restricted to the hours of 7:00 a.m. and 6:00 p.m. and no less than one vehicular lane in each direction of travel at all times, in conformance with Section 1-08.0(2) of the Special Provisions. Shoulder/bike lane closures related to the curb ramp work may extend outside of working hours as long as: 1. The number of vehicles lanes are not restricted/minimized, and 2. The traffic control devices are approved for night time operation. 3. Pedestrian routing is in conformance with the traffic control plans provided in the Contract Documents. *** If the Engineer determines the permitted closure hours adversely affect traffic, the Engineer may adjust the hours accordingly. The Engineer will notify the Contractor in writing of any change in the closure hours. Lane closures are not allowed on any of the following: 1. A holiday, 2. A holiday weekend; holidays that occur on Friday, Saturday, Sunday or Monday are considered a holiday weekend. A holiday weekend includes Saturday, Sunday, and the holiday. 3. After *** 12:00 p.m. *** on the day prior to a holiday or holiday weekend, and 4. Before' 12:00 p.m.*** on the day after the holiday or holiday weekend. 1-07.24 Rights of Way (July 23, 2015 APWA GSP) Delete this section and replace it with the following: Crosswalk Improvements City of Bremerton, Washington Federal Aid # STPUS-9918(015) 45 Special Provisions Skillings Connollv, Inc. April 2016 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 Street Right of Way lines, limits of easements, and limits of construction permits are indicated in the Plans. The Contractor's construction activities shall be confined within these limits, unless arrangements for use of private property are made. Generally, the Contracting Agency will have obtained, prior to bid opening, all rights of way and easements, both permanent and temporary, necessary for carrying out the work. Exceptions to this are noted in the Bid Documents or will be brought to the Contractor's attention by a duly issued Addendum. Whenever any of the work is accomplished on or through property other than public Right of Way, the Contractor shall meet and fulfill all covenants and stipulations of any easement agreement obtained by the Contracting Agency from the owner of the private property. Copies of the easement agreements may be included in the Contract Provisions or made available to the Contractor as soon as practical after they have been obtained by the Engineer. Whenever easements or rights of entry have not been acquired prior to advertising, these areas are so noted in the Plans. The Contractor shall not proceed with any portion of the work in areas where right of way, easements or rights of entry have not been acquired until the Engineer certifies to the Contractor that the right of way or easement is available or that the right of entry has been received. If the Contractor is delayed due to acts of omission on the part of the Contracting Agency in obtaining easements, rights of entry or right of way, the Contractor will be entitled to an extension of time. The Contractor agrees that such delay shall not be a breach of contract. Each property owner shall be given 48 hours notice prior to entry by the Contractor. This includes entry onto easements and private property where private improvements must be adjusted. The Contractor shall be responsible for providing, without expense or liability to the Contracting Agency, any additional land and access thereto that the Contractor may desire for temporary construction facilities, storage of materials, or other Contractor needs. However, before using any private property, whether adjoining the work or not, the Contractor shall file with the Engineer a written permission of the private property owner, and, upon vacating the premises, a written release from the property owner of each property disturbed or otherwise interfered with by reasons of construction pursued under this contract. The statement shall be signed by the private property owner, or proper authority acting for the owner of the private property affected, stating that permission has been granted to use the property and all necessary permits have been obtained or, in the case of a release, that the restoration of the property has been satisfactorily accomplished. The statement shall include the parcel number, address, and date of signature. Written releases must be filed with the Engineer before the Completion Date will be established. 1-08 PROSECUTION AND PROGRESS Add the following new section: 1-08.0 Preliminary Matters (May 25, 2006 APWA GSP) Crosswalk Improvements Citv of Bremerton, Washington Federal Aid # S7PUS-9918(015) 46 Special Provisions Skillings Connolly. Inc. April 2016 1 2 Add the following new section: 3 4 1-08.0(2) Hours of Work 5 (December 8, 2014 APWA GSP) 6 7 Except in the case of emergency or unless otherwise approved by the Engineer, the 8 normal working hours for the Contract shall be any consecutive 8 -hour period between 9 7:00 a.m. and 6:00 p.m. Monday through Friday, exclusive of a lunch break. If the 10 Contractor desires different than the normal working hours stated above, the request 11 must be submitted in writing prior to the preconstruction conference, subject to the 12 provisions below. The working hours for the Contract shall be established at or prior to 13 the preconstruction conference. 14 15 All working hours and days are also subject to local permit and ordinance conditions 16 (such as noise ordinances). 17 18 If the Contractor wishes to deviate from the established working hours, the Contractor 19 shall submit a written request to the Engineer for consideration. This request shall state 20 what hours are being requested, and why. Requests shall be submitted for review no 21 later than 3 days prior to the day(s) the Contractor is requesting to change the hours. 22 23 If the Contracting Agency approves such a deviation, such approval may be subject to 24 certain other conditions, which will be detailed in writing. For example: 25 1. On non -Federal aid projects, requiring the Contractor to reimburse the 26 Contracting Agency for the costs in excess of straight -time costs for Contracting 27 Agency representatives who worked during such times. (The Engineer may 28 require designated representatives to be present during the work. 29 Representatives who may be deemed necessary by the Engineer include, but are 30 not limited to: survey crews; personnel from the Contracting Agency's material 31 testing lab; inspectors; and other Contracting Agency employees or third party 32 consultants when, in the opinion of the Engineer, such work necessitates their 33 presence.) 34 2. Considering the work performed on Saturdays, Sundays, and holidays as working 35 days with regard to the contract time. 36 3. Considering multiple work shifts as multiple working days with respect to contract 37 time even though the multiple shifts occur in a single 24-hour period. 38 4. If a 4-10 work schedule is requested and approved the non working day for the 39 week will be charged as a working day. 40 5. If Davis Bacon wage rates apply to this Contract, all requirements must be met 41 and recorded properly on certified payroll 42 43 1-08.1 Subcontracting 44 45 Section 1-08.1 is supplemented with the following: 46 47 (October 12, 1998) 48 Prior to any subcontractor or lower tier subcontractor beginning work, the Contractor 49 shall submit to the Engineer a certification (WSDOT Form 420-004 EF) that a written Crosswalk Improvements Special Provisions City of Bremerton, Washington 47 Skillings Connolly, Inc. Federal Aid # S (PUS -9913(015.) April 2016 1 agreement between the Contractor and the subcontractor or between the subcontractor 2 and any lower tier subcontractor has been executed. This certification shall also 3 guarantee that these subcontract agreements include all the documents required by the 4 Special Provision Federal Agency Inspection. 5 6 A Subcontractor or lower tier Subcontractor will not be permitted to perform any work 7 under the contract until the following documents have been completed and submitted to 8 the Engineer: 9 10 1. Request to Sublet Work (Form 421-012 EF), and 11 2. Contractor and Subcontractor or Lower Tier Subcontractor Certification for 12 Federal -aid Projects (Form 420-004 EF). 13 14 The Contractor's records pertaining to the requirements of this Special Provision shall 15 be open to inspection or audit by representatives of the Contracting Agency during the 16 life of the contract and for a period of not less than three years after the date of 17 acceptance of the contract. The Contractor shall retain these records for that period. 18 The Contractor shall also guarantee that these records of all Subcontractors and lower 19 tier Subcontractors shall be available and open to similar inspection or audit for the 20 same time period. 21 22 1-08.4 Prosecution of Work 23 24 Delete this section and replace it with the following: 25 26 1-08.4 Notice to Proceed and Prosecution of Work 27 (July 23, 2015 APWA GSP) 28 29 Notice to Proceed will be given after the contract has been executed and the contract 30 bond and evidence of insurance have been approved and filed by the Contracting 31 Agency. The Contractor shall not commence with the work until the Notice to Proceed 32 has been given by the Engineer. The Contractor shall commence construction activities 33 on the project site within ten days of the Notice to Proceed Date, unless otherwise 34 approved in writing. The Contractor shall diligently pursue the work to the physical 35 completion date within the time specified in the contract. Voluntary shutdown or slowing 36 of operations by the Contractor shall not relieve the Contractor of the responsibility to 37 complete the work within the time(s) specified in the contract. 38 39 When shown in the Plans, the first order of work shall be the installation of high visibility 40 fencing to delineate all areas for protection or restoration, as described in the Contract. 41 Installation of high visibility fencing adjacent to the roadway shall occur after the 42 placement of all necessary signs and traffic control devices in accordance with 1-10.1(2). 43 Upon construction of the fencing, the Contractor shall request the Engineer to inspect the 44 fence. No other work shall be performed on the site until the Contracting Agency has 45 accepted the installation of high visibility fencing, as described in the Contract. 46 47 (****** 48 Order of Work 49 The work shall be completed in accordance with the plans and the following: 50 Crosswalk Improvements Special Provisions Citv of Bremerton. Washington 48 Skillings Connolly. Inc. Federal Aid #STPUS-9918(015) April 2016 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 The contractor shall schedule the work so that the time between removing the existing sidewalk or ramps and placing the new cement concrete sidewalk or curb ramp type shall not exceed one week. The signal pole foundations shall be excavated on the same day. The Contractor shall contact, Kevin Lamb at GeoDesign, Inc. 7 days before beginning the work to coordinate for a representative to be on site during the excavation of the signal pole foundations. Kevin Lamb 10700 Meridian Avenue North #402 Seattle WA 98133 (206) 838-9900 1-08.5 Time for Completion Section 1-08.5 is supplemented with the following: (March 13, 1995) This project shall be physically completed within *** 60 *** working days. 1-08.5 Time for Completion (August 14, 2013 APWA GSP, Option A) Revise the third and fourth paragraphs to read: Contract time shall begin on the first working day following the Notice to Proceed Date. Each working day shall be charged to the contract as it occurs, until the contract work is physically complete. If substantial completion has been granted and all the authorized working days have been used, charging of working days will cease. Each week the Engineer will provide the Contractor a statement that shows the number of working days: (1) charged to the contract the week before; (2) specified for the physical completion of the contract; and (3) remaining for the physical completion of the contract. The statement will also show the nonworking days and any partial or whole day the Engineer declares as unworkable. Within 10 calendar days after the date of each statement, the Contractor shall file a written protest of any alleged discrepancies in it. To be considered by the Engineer, the protest shall be in sufficient detail to enable the Engineer to .ascertain the basis and amount of time disputed. By not filing such detailed protest in that period, the Contractor shall be deemed as having accepted the statement as correct. If the Contractor is approved to work 10 hours a day and 4 days a week (a 4-10 schedule) and the fifth day of the week in which a 4-10 shift is worked would ordinarily be charged as a working day then the fifth day of that week will be charged as a working day whether or not the Contractor works on that day. Revise the sixth paragraph to read: The Engineer will give the Contractor written notice of the completion date of the contract after all the Contractor's obligations under the contract have been performed by the Contractor. The following events must occur before the Completion Date can be established: 1. The physical work on the project must be complete; and Crosswalk Improvements Special Provisions Citv of Bremerton, Washington 49 Skillings Connolly. Inc. Federal Aid 4 SITUS -9918(015) April 2016 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 2. The Contractor must furnish all documentation required by the contract and required by law, to allow the Contracting Agency to process final acceptance of the contract. The following documents must be received by the Project Engineer prior to establishing a completion date: a. Certified Payrolls (per Section 1-07.9(5)). b. Material Acceptance Certification Documents c. Quarterly Reports of Amounts Credited as DBE Participation, as required by the Contract Provisions. d. Final Contract Voucher Certification e. Copies of the approved "Affidavit of Prevailing Wages Paid" for the Contractor and all Subcontractors f. Property owner releases per Section 1-07.24 1-08.6 Suspension of Work Section 1-08.6 is supplemented with the following: (January 5, 2015) Contract time may be suspended for procurement of critical materials (Procurement Suspension). In order to receive a Procurement Suspension, the Contractor shall within 21 calendar days after execution by the Contracting Agency, place purchase orders for all materials deemed critical by the Contracting Agency for physical completion of the contract. The Contractor shall provide copies . of purchase orders for the critical materials. Such purchase orders shall disclose the purchase order date and estimated delivery dates for such critical material. The Contractor shall show procurement of the materials listed below as activities in the Progress Schedule. If the approved Progress Schedule indicates that the materials procurement are critical activities, and if the Contractor has provided documentation that purchase orders are placed for the critical materials within the prescribed 21 calendar days, then contract time shall be suspended upon physical completion of all critical work except that work dependent upon the below listed critical materials: o RRFB Signal System Complete, Kitsap Way / Harlow Dr, o RRFB Signal System Complete, SR304 / 1St St, and o HAWK Signal System Complete, 6th St / High Ave. Charging of contract time will resume upon delivery of the critical materials to the Contractor or 120 calendar days after execution by the Contracting Agency, whichever occurs first. 1-08.9 Liquidated Damages (August 14, 2013 APWA GSP) Revise the fourth paragraph to read: When the Contract Work has progressed to Substantial Completion as defined in the Contract, the Engineer may determine that the work is Substantially Complete. The Engineer will notify the Contractor in writing of the Substantial Completion Date. For Crosswalk Improvements Special Provisions City of Bremerton, Washington 50 Skillings Connolly, Inc. Federal Aid # STPUS-9918(015) April 2016 1 overruns in Contract time occurring after the date so established, the formula for 2 liquidated damages shown above will not apply. For overruns in Contract time occurring 3 after the Substantial Completion Date, liquidated damages shall be assessed on the 4 basis of direct engineering and related costs assignable to the project until the actual 5 Physical Completion Date of all the Contract Work. The Contractor shall complete the 6 remaining Work as promptly as possible. Upon request by the Project Engineer, the 7 Contractor shall furnish a written schedule for completing the physical Work on the 8 Contract. 9 10 1-09 Measurement and Payment 11 12 1-09.6 Force Account 13 (October 10, 2008 APWA GSP) 14 15 Supplement this section with the following: 16 17 The Contracting Agency has estimated and included in the Proposal, dollar amounts for 18 all items to be paid per force account, only to provide a common proposal for Bidders. 19 All such dollar amounts are to become a part of Contractor's total bid. However, the 20 Contracting Agency does not warrant expressly or by implication, that the actual amount 21 of work will correspond with those estimates. Payment will be made on the basis of the 22 amount of work actually authorized by Engineer. 23 24 1-09.9 Payments 25 (March 13, 2012 APWA GSP) 26 27 Supplement this section with the following: 28 29 Lump sum item breakdowns are not required when the bid price for the lump sum item is 30 less than $20,000. 31 32 1-09.9(1) Retainage 33 34 Section 1-09.9(1) content and title is deleted and replaced with the following: 35 36 (June 27, 2011) 37 Vacant 38 39 1-09.13(3) Claims $250,000 or Less 40 (October 1, 2005 APWA GSP) 41 42 Delete this section and replace it with the following: 43 44 The Contractor and the Contracting Agency mutually agree that those claims that total 45 $250,000 or less, submitted in accordance with Section 1-09.11 and not resolved by 46 nonbinding ADR processes, shall be resolved through litigation unless the parties 47 mutually agree in writing to resolve the claim through binding arbitration. 48 49 1-10 Temporary Traffic Control 50 51 1-10.2 Traffic Control Management 52 Crosswalk Improvements Special Provisions City of Bremerton, Washington 51 Skillings Connollv, Inc. Federal Aid # STPUS-991801?) April 2010 1 1-10.2(1) General 2 3 Section 1-10.2(1) is supplemented with the following: 4 5 (January 8, 2016) 6 Only training with WSDOT TCS card and WSDOT training curriculum is recognized 7 in the State of Washington. The Traffic Control Supervisor shall be certified by one 8 of the following: 9 10 The Northwest Laborers -Employers Training Trust 11 27055 Ohio Ave. 12 Kingston, WA 98346 13 (360) 297-3035 14 15 Evergreen Safety Council 16 12545135 1h Ave. NE 17 Kirkland, WA 98034-8709 18 1-800-521-0778 or 19 (425) 814-3930 20 21 The American Traffic Safety Services Association 22 15 Riverside Parkway, Suite 100 23 Fredericksburg, Virginia 22406-1022 24 Training Dept. Toll Free (877) 642-4637 25 Phone: (540) 368-1701 26 27 1-10.4 Measurement 28 29 1-10.4(1).Lump Sum Bid for Project (No Unit'ltems) 30 31 Section 1-10.4(1) is supplemented with the following: 32 33 (August 2, 2004) 34 The proposal contains the item "Project Temporary Traffic Control", lump sum. The 35 provisions of Section 1-10.4(1) shall apply. 36 37 Division 2 38 Earthwork 39 40 2-01 Clearing, Grubbing, and Roadside Cleanup 41 42 2-01.5 Payment 43 44 Section 2-01.5 is supplemented with the following: 45 46 47 If no bid item for "Clearing and Grubbing" is included in the proposal, any work 48 described in this section shall be included in other unit contract prices. 49 Crosswalk Improvements Special Provisions City of Bremerton. Washington 52 Skillings Connolly, Inc. Federal Aid # STPUS-99/8(0/5) April 2016 1 Division 8 2 Miscellaneous Construction 3 4 8-04 Curbs, Gutters, and Spillways 5 6 8-04.3(1) Construction Requirements 7 8 Section 8-04.3(1) is supplemented with the following: 9 10 11 Prior to the placement of any cement concrete, the Contractor shall obtain approval 12 from the Project Inspector. Any minor adjustments to the layout or formwork shall be 13 included in the unit bid price. 14 15 Crushed surfacing base course required for the improvements shall be included as part 16 of the work and no separate measurements will be made. 17 18 8-04.5 Payment 19 20 Section 8-04.5 is supplemented with the following: 21 22 (******) 23 The unit contract price, per linear foot, for curbs and gutters shall be full pay for all costs 24 for equipment, labor and materials, including, but not limited to, saw cutting, pavement 25 and concrete removal, excavation or grading, haul, form work, furnishing and installing 26 crushed surfacing top course (or sand), restoration of the roadway adjacent to the work 27 with HMA or concrete to match existing materials, sealing, compaction, dowels, cement 28 concrete, and. finishing. Locating existing traffic loops and replacing existing crosswalk 29 and stop bar striping affected by the work shall be'made incidental to the work. 30 31 8-14 Cement Concrete Sidewalks 32 33 8-14.1 Description 34 35 Section 8-14.1 is supplemented with the following: 36 37 38 The Work shall also consist of providing miscellaneous construction and documentation 39 as described herein. 40 41 8-14.2 Materials 42 43 Section 8-14.2 is replaced with the following 44 45 (******) 46 Materials shall meet the requirements of the following sections: 47 48 Portland Cement 9-01 49 Aggregates 9-03 50 Premolded Joint Filler 9-04.1 Crossivalk Improvements Citv of Bremerton, Washington 53 Federal Aid # STPUS-99180151 Special Provisions Skillings Connolly. Inc. April 2016 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 Concrete Curing Materials and Admixtures 9-23 The Contractor shall use one of the detectable warning surface products listed in the Qualified Products List or seek approval through the WSDOT Request for Approval of Material process. The detectable warning surface shall have the truncated dome shape shown in the Plans. The minimum 2 -foot -wide detectable warning surface area shall be black and shall match Federal Standard 595, color number 37038. 8-14.3 Construction Requirements 8-14.3(3) Placing and Finishing Concrete Section 8-14.3(3) is supplemented with the following: Prior to the placement of any cement concrete for sidewalks, the Contractor shall obtain approval from the Engineer. Any minor adjustments to the layout or formwork shall be included in the unit bid price. Crushed surfacing top course required per the typical sections shown on the Plans shall be included as part of the work and no separate measurements will be made. Add the following new sub -section: 8-14.3(6) Curb Ramp Curb ramp alignment shall be as indicated on the Plans or as directed by the Engineer in the field. Curb ramps shall be constructed separately from the adjacent triangular shaped transition areas and sidewalk to produce a definite break line between grade changes. All curb ramps shall have a detectable warning pattern installed in accordance with the manufacturer's written instructions. The Contractor shall notify the Engineer three (3) working days in advance of placing concrete for each curb ramp for layout and formwork inspection. The Contractor shall not place concrete in a sidewalk ramp until the Engineer has either inspected and accepted the layout or waived the layout inspection. Where existing sidewalk ramp(s) is/are to be replaced, including adjacent sidewalk, the Contractor shall complete the required replacement per intersection corner within three (3) days of beginning concrete demolition and removal. Crushed surfacing top course required for the improvements shall be included as part of the work and no separate measurements will be made. Add the following new sub -section: 8-14.3(7) Resolution of Utility Conflicts This work involves the identification and resolution of utility conflicts not identified in the plans between proposed improvements and existing utilities. The Contracting Agency Crosswalk Improvements Special provisions City of Bremerton. Washington 54 Skillings Connolly. hie Federal Aid # S7PUS-9918(015) April ?016 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 will pay these costs by force account if the work proves to be acceptable and the Contractor had performed the work with the authority of and due notice to the Engineer. Utility conflicts discovered during construction will typically be addressed by adjusting the location of the proposed improvement that is in conflict with the existing utility. Should existing conditions and/or proposed improvements prohibit relocation of the new improvements, then the existing, conflicting utility will be relocated. In the event that a conflict arises between the proposed improvements and an existing utility, the Resolution of Utility Conflicts item will compensate the Contractor for standby time and additional work in the following manner: 1. Standby time resulting from existing utility conflicts a. Standby time is defined as time the Contractor is unable to proceed with progression of a specific work item (i.e. storm drainage, Water Main etc.) due to conflicts with existing facilities. However, payment for standby time shall be limited to: For each agreed upon conflict, a maximum of four (4) hours of standby time will be paid for actual delay of labor and equipment due to a utility conflict. The Contractor shall be responsible to adjust his work schedule and/or reassign his work forces and equipment to other areas of work to minimize standby time. ii. If the conflict is resolved within one (1) hour of notification to the Engineer, no standby time will be paid. 2. Additional work required to resolve utility conflicts will be paid for at the bid unit prices for the associated work. Work that can be measured and paid for at the unit contract prices shall not be identified as force account work. This work includes but is not limited to: a. Storm drainage manhole, pipe, vault, and conduit realignments of line and/or grade for the storm drain and undergrounding of overhead utilities, to avoid existing utility conflicts. b. Additional storm drainage manholes, pipe, vaults, and conduit required by a change in alignment, and/or grade, not exceeding the limits set in section 1- 04.4 of the Standard Specifications. Add the following new sub -section: 8-14.3(8) Field Adjust Ramp Grades This work involves the field adjustment of the forms prior to concrete pouring at the direction of the Engineer. The Contracting Agency will pay for the costs by force account if the work proves to be acceptable and the Contractor had performed the work with the authority of and due notice to the Engineer. . Crosswalk Improvements Citv of'Bremerton, Washington Federal Aid # S7PUS-9918(0/5) 55 Special Provisions Skillings Connolly. Inc April 2016 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 8-14.4 Measurement Section 8-14.4 is supplemented with the following: Measurement and payment for "Resolution of Utility Conflicts" shall be by force account per 1-09.6 of the Standard Specifications. Measurement and payment for "Field Adjust Ramp Grades" shall be by force account per 1-09.6 of the Standard Specifications. 8-14.5 Payment Section 8-14.5 is supplemented with the following: The unit contract price, per square yard, for all concrete sidewalk shall be full pay for all costs for equipment, labor and materials, including, but not limited to, saw cutting, pavement and concrete removal, excavation or grading, haul, form work, furnishing and installing crushed surfacing top coarse (or sand), restoration of the roadway adjacent to the work with HMA or concrete to match existing materials, sealing, compaction, dowels, cement concrete, and finishing. Locating existing traffic loops and replacing existing crosswalk and stop bar striping affected by the work shall be made incidental to the work. "Cement Conc. Curb Ramp", per each. The unit contract price, per each, for "Cement Conc. Curb Ramp" shall be full pay for all costs for equipment, labor and materials, including, but not limited to, saw cutting, pavement and concrete removal, excavation or grading, haul, form work, furnishing and installing crushed surfacing top coarse (or sand), restoration of the roadway adjacent to the work with HMA or concrete to match existing materials, sealing, compaction, dowels, cement concrete, finishing, and installing detectable warning surface. No extra payment shall be made for forming and finishing curb ramps. Locating existing traffic loops and replacing existing crosswalk and stop bar striping affected by the work shall be made incidental to the work. "Resolution of Utility Conflicts", by force account. "Resolution of Utility Conflicts" shall be full pay for costs incurred as a result of horizontal or vertical realignment of existing utilities as necessary to allow construction of the improvements proposed with this project, as approved by the Engineer, shall be paid by force account under the Bid item "Resolution of Utility Conflicts". This Bid item applies only to costs that would not have been otherwise incurred as a result of per -Plan activities. This option will only be approved by the Engineer if it is determined that utility conflict cannot be resolved by realignment of the new utilities replaced as part of this project alone. Should additional materials become necessary due to realignment of the new utilities, they will be measured and paid for separately according to the pay items to which they apply. Crosswalk Improvements Special Provisions Citv of'Bremerton, Washington 56 Skillings Connoliv, 111c. Federal And # STPUS-9918(015) April 2016 1 For the purposes of bidding equality, the Contracting Agency has furnished an estimated 2 quantity for this item of work. Actual payment for this work, if necessary, will be made 3 only for the actual amount of work performed as authorized and deemed necessary by 4 the Engineer and may differ greatly from the estimated amount provided. 5 6 "Field Adjust Ramp Grades", by force account. 7 8 "Field Adjust Ramp Grades" shall be full pay for costs incurred to field adjust forms prior 9 to concrete pouring, as approved by the Engineer. This Bid item applies only to costs 10 that would not have been otherwise incurred as a result of per -Plan activities. Should 11 additional materials become necessary, they will be measured and paid for separately 12 according to the pay items to which they apply. 13 14 For the purposes of bidding equality, the Contracting Agency has furnished an estimated 15 quantity for this item of work. Actual payment for this work, if necessary, will be made 16 only for the actual amount of work performed as authorized and deemed necessary by 17 the Engineer and may differ greatly from the estimated amount provided. 18 19 20 8-20 Illumination, Traffic Signal Systems, Intelligent Transportation Systems, 21 and Electrical 22 23 8-20.1 Description 24 25 Section 8-20.1 is replaced with the following: 26 27 (Special Provision) 28 29 Work includes furnishing and installing all materials necessary to provide: 30 1. Modification to existing signal systems at the following intersections 31 o Kitsap Way and 11 th Street 32 o High Avenue and 11th Street 33 2. A new HAWK signal system at the intersection of 6th Street and High Avenue 34 3. New Rectangular Rapid Flashing Beacon (RRFB) systems at the following 35 intersections 36 o SR 304 at 15t Street 37 o Kitsap Way at Harlow Drive 38 39 All work shall be performed as shown in the Plans in accordance with applicable 40 Standard Specifications and Standard Plans included herein, the City of Bremerton 41 General Provisions, Division 7 for Illumination and Division 8 for Traffic Signalization, 42 and the following Special Provisions. Work shall include the supply, testing, and 43 installation of all traffic signal hardware including the communication cable and interface 44 system, and when specified, the modification of such an existing system. 45 46 The work involves, but shall not be limited to, the following: 47 1. Signal controllers and equipment 48 2. Signal cabinets and bases 49 3. Signal poles 50 4. Signal and pedestrian heads 51 5. Emergency Pre-emption equipment 52 6. Conduit and wire Crosswalk Improvements Special Provisions City of Bremerton. Washington 57 Skillings Connollv, Inc. Federal Aid # S'IPUS-9918(015) April 2016 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 7. APS push buttons 8. Luminaires Work shall include the supply, testing and installation of all traffic signal hardware including the communication cable and interface system, and when specified, the modification of such an existing system. The existing traffic signal system shall be kept in full operation during construction until the new system is in place and ready for turn -on or switchover. 8-20.2 Materials Junction Boxes, Cable Vaults, and Pull Boxes Standard Duty Junction Boxes Section 9-29.2(1)A is supplemented with the following: (January 7, 2013) Concrete Junction Boxes Both the slip -resistant lid and slip -resistant frame shall be treated with Mebac#1 as manufactured by IKG industries, or SlipNOT Grade 3 -coarse as manufactured by W.S. Molnar Co. Where the exposed portion of the frame is '/2 inch wide or less the slip -resistant treatment may be omitted on that portion of the frame. The slip -resistant lid shall be identified with permanent marking on the underside indicating the type of surface treatment ("MV for Mebac#1; or "SY for SIONOT Grade 3 -coarse) and the year manufactured. The permanent marking shall be 1/8 inch line thickness formed with a stainless steel weld bead. Add the following section: 8-20.3(18) HAWK Signal System (Special Provision) HAWK Signal system shall be furnished and installed by the Contractor and shall comply with all other specifications for signal systems. The system shall include all materials and work needed to provide a complete working system as shown on the plans, including but not limited to pedestrian push buttons, signal heads, poles, foundations, conduit, junction boxes, and controller cabinet and components needed for complete operation. All the components shall be installed per manufacturer's recommendations and per the Plans. The method and locations of installation shall be approved by the Engineer in the field, prior to drilling holes in the supporting poles. The systems shall be powered from the electrical service, per the Plans. Add the following section: 8-20.3(19) Rectangular Rapid Flashing Beacons System (Special Provision) Crosswalk Improvements Citv of Bremerton. Washington Federal Aid # STPUS-9918(015) 58 Special Provisions Skillings Connolly. Inc. April 2016 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 Rectangular Rapid Flashing Beacon (RRFB) system shall be furnished and installed by the Contractor and shall comply with the Federal Highway Administration's (FHWA) approval for the use for pedestrian and school crossings and shall include flashing, rectangular -shaped, high intensity LEDs, associated signs, push buttons, passive detection, and assemblies as shown on the Plans. The lights shall be activated by push button and/or passive detection as shown on the plans. All the components shall be installed per manufacturer's recommendations, per the Plans and the method and locations of installation shall be approved by the Engineer in the field, prior to drilling holes in the supporting poles. The systems shall be powered from the electrical service, per the Plans. Add the following section: 8-20.3(20) Microwave Pedestrian Presence Detection (Special Provision) Microwave Pedestrian Presence Detection shall be furnished and installed by the Contractor and shall comply with section 9-29.28. All components shall be installed per manufacturer's recommendations, per the Plans and the method and location of installation shall be approved by the Engineer in the field, prior to drilling holes in the supporting poles. 8-20.4 Measurement Section 8-20.4 is supplemented as follows: When a bid item is shown as lump sum in the proposal, no specific unit of measurement will apply, but measurement will be for the sum total of all items for a complete system to be furnished and installed. Sawcutting required shall be incidental to lump sum items and no separate measurement will be made. Conduit zone bedding shall be incidental to the lump sum items and no separate measurement will be made. Removal, and salvage where required, of existing traffic signal equipment, including grinding and removal of existing loop detectors, shall be incidental to the lump sum items and no separate measurement will be made. Temporary surface restoration items required for resuming pedestrian and vehicular traffic prior to final surfacing, including steel sheeting, crushed rock, and cold mix asphalt, shall be incidental to the lump sum items and no separate measurement will be made. The cost of conduit trenching or directional boring, backfilling, compaction and landscape restoration outside of paved areas and trenching and backfill for the pipe zone within paved areas shall be included in the listed lump sums. Crosswalk Improvements Special Provisions Citv of Bremerton. Washington 59 Skillings Connollv, Inc. Federal Aid # STPUS-9913(01 S) April 201 6 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 All costs for adjustment of junction boxes, both to the final grade and any grade adjustments required for the various construction stages proposed in the Contract, or for alternative stages proposed by the Contractor, shall be included in the applicable lump sum contract price(s). 8-20.5 Payment Section 8-20.5 is supplemented as follows: Payment will be made for the following bid items: "HAWK Signal System Complete, ", per lump sum; "RRFB Signal System Complete, ", per lump sum; "Traffic Signal System Modifications, ", per lump sum; The lump sum contract prices shall include all incidental work and shall be full compensation for all labor, materials, tools and equipment necessary to satisfactorily complete the work as defined in the Contract Documents. Subsurface explorations to determine the locations of existing utilities in order to install, abandon, and/or remove the associated equipment for the "HAWK Signal System Complete, ", and "RRFP Signal System Complete, " shall be considered incidental to the lump sum bid item. Bidders are cautioned to also include in the lump sum bid items all costs related to protection of items to remain, utility locates, subsurface explorations, dewatering, and costs associated with permits and with obtaining electrical inspection and connection and signal testing as required. 8-21 Permanent Signing 34 8-21.2 Materials 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 8-21.2(9-06.16) Roadside Sign Structures Section 9-06.16 is supplemented with the following: (January 3, 2011) Perforated Steel Square Sign Post System Where noted in the Plans, steel sign post systems galvanized steel tubing, that are NCHRP 350 Test approved. The steel sign post system shall include hardware required for a complete sign installation. shall be square, pre -punched Level 3 Certified and FHWA all anchor sleeves, and other System Acceptance Systems listed in the current QPL will be accepted per the QPL approval code. Systems not listed in the QPL will be accepted based on a Supplier's Certificate of Compliance. The Supplier's Certificate of Compliance will be a contract specific letter from the supplier stating the system is NCHRP 350 Test Level 3 compliant. Crosswalk Improvements Special Provisions Cety of Bremerton, Washington 60 Skillings Connolly, Inc. Federal Aid # STPUS-9918(01 S) April 2016 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 8-21.2(9-28.14) Sign Support Structures Section 9-28.14 is supplemented with the following: (January 3, 2011) Manufacturers for Steel Roadside Sign Supports The Standard Plans lists several steel sign support types. These supports are patented devices and many are sole -source. All of the sign support types listed below are acceptable when shown in the Plans. Steel Siqn Support Type Type TP -A & TP -B Type PL, PL -T & PL -U Type AS Type AP Manufacturer Transpo Industries, Inc. Northwest Pipe Co. Transpo Industries, Inc. Transpo Industries, Inc. Type ST 1, ST 2, ST 3, & ST 4Ultimate Highway Products, Allied Tube & Conduit, Inc., Northwest Pipe, Inc. Type SB -1, SB -2, & SB -3 9-29 Illumination, Signal, Electrical Add the following section: 9-29.26 Wireless Interconnect (Special Provision) Ultimate Highway Products, Xcessories Squared Development and Manufacturing Incorporated, Northwest Pipe, Inc. Division 9 Materials Wireless interconnect shall be ENCOM E -Lite 5GHz, 300 Mbps Wireless Broadband System. Antennas shall be external, mounted on the mastarms as shown on the plans or as directed by the engineer. The radios shall be mounted on the corresponding signal pole. All wiring shall be run internal to the pole and mastarm. Add the following section: 9-29.27 Rectangular Rapid Flashing Beacon (RRFB) System (Special Provision) Crosswalk Improvements City of Bremerton. Washington Federal Aid # S7PUS-9918(01.1) 61 Special Provcsion.s Skillings Connolly, Inc. April 2016 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 Rectangular Rapid Flashing Beacon (RRFB) system shall consist of RRFB LED light bars, controller cabinet, control panel, push button assemblies, and associated warning signs, all mounted on poles (configuration per the Plans). Controller Cabinet The cabinet shall be manufactured of 0.125" sheet aluminum and shall be Type 3X NEMA enclosure. Nominal cabinet dimensions shall be 13.63" H x 15.5" W x 14.75" D. The cabinet shall be a one (1) compartment type with a neoprene gasket seal for a weather seal. The cabinet shall have wire screened insect proof louvers on each side for ventilation. The louvers shall be designed to not allow any rain to enter the cabinet. On the bottom of the cabinet there shall be two screened insect proof drain holes. The door shall be a single unit with a continuous piano hinge riveted to the door and the cabinet. The door shall incorporate a neoprene gasket which, when closed, forms a snug weather tight seal. The door lock shall be a standard police lock, reinforced with a steel plate. Each cabinet shall be equipped with the necessary rigid mounts appropriately sized for a pole as dimensioned on the plans. All necessary hardware for proper mounting shall be included. Control Panel The control panel containing the electronics (circuit breaker, surge arrestor, flasher, countdown timer and a 120VAC to 12VDC power supply) shall be mounted in the cabinet using bolts with wing nuts for quick and easy removal. The back panel and flashing beacons shall be connected through a main wiring harness via a circular pin connector (CPC). All modular components shall be connected in such a manner that they are easily removed for replacement or maintenance. Two control panels will be supplied, one in the upper compartment and one in the lower compartment. Each control panel will control the flashing beacons for one set of lanes. The circuit breaker must be a 1 pole, 20 amp, 120VAC with reversible line or load lugs for line or surface mount wiring. The flasher shall be solid state, 2 circuit device which controls the flashing sequence of the beacon. The flasher will have a selectable flash rate of 35-70 flashes per minute and will flash a duty cycle of 50% on and 50% off. The flasher shall be a separate unit easily removable for maintenance. The flasher will be capable of operating in a temperature range of -40 degrees C and +85 degrees C. The surge arrestor will be capable of protecting up to 120VAC, 60 amp service, will have no follow current, respond in 5 nanoseconds, and will allow automatic recovery. It must be flame retardant epoxy encapsulated. The peak surge current will be 13kA/mode/phase total. The surge arrestor will be approximately 0.5" H x 1.5" W x 2.0" L. It will operate from -40°C to +85° C. The system shall employ countdown timer that allows the end user to adjust the length of time that the RRFBs flash upon activation. The range of time shall be from adjustable from 1 second to a minimum of 1 minute in 1 second intervals. The timer shall operate such that any time the pedestrian pushes the button the timer resets to its preset time to allow the pedestrian the full amount of time to cross the street. The countdown timer will operate from -20 degrees C to + 60 degrees C. RRFB LED Light Bar The RRFB shall comply with the latest FHWA guidelines and the housing shall have a brushed Aluminum finish and shall have rectangular shaped, high intensity LED alternating pattern flashing beacons with number of LEDs and configuration per the Plans. Mounting shall be per manufacturer's recommendation — coordinate work with the Engineer in the field. The RRFBs will wig -wag with a flash pattern of 2 rapid flashes on 1 beacon and then 4 short rapid flashes and 1 longer rapid flash on the other beacon Crosswalk Improvements Citv of Bremerton, Washington Federal Aid # Sl PUS -9918(015) 62 Special provisions Skillings Connollv, Inc April 2016 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 as specified in the latest interpretation letter from the FHWA dated June 13, 2012. The beacons shall flash at a rate between 70 — 80 flashes per minute. The LED light on the end facing the pedestrian crosswalk shall be a Whelen Class 1 light. The LEDs used in the light,bar shall meet the SAE J595 requirement for peak luminous (candelas) for Class 1. The vendor shall submit third party lab certification that the LEDs have been tested and certified for Class 1 intensity. The RRFB light bar will be assembled and wired as a unit. It will consist of a mounting bracket, a bottom shell that attaches to the mounting bracket, and a top shell that attaches to the bottom shell. It shall be mounted to the pole with U -bolts. Pedestrian Push Buttons Pedestrian push buttons shall be per City of Bremerton General Provisions, Section 8- 200. Pedestrian push button mounts shall be Polara Engineering, 5 -inch by 7 -inch frame, part number PBF 5X7 -B. Pedestrian push button plaques text shall be approved by the Engineer. Poles Poles shall be per plan. Signs Signs shall be per the Plans. Add the following section: 9-29.28 Microwave Pedestrian Presence Detection (Special Provision) Pedestrian Microwave Presence Detection shall accomplish automated hands free activation of pedestrian signals via microwave sensor, with microwave reliability up to 22 -feet. Microwave sensor shall minimize false activation from nearby moving traffic, with modes to detect approach -only, depart -only, or bidirectional pedestrian motion. The sensor shall allow for adjustable detection angle and pattern with detection verification time between 0.1 and 5.0 seconds. The sensor shall be enclosed in a powder coated aluminum enclosure. Installation shall be per manufacturer's instructions as shown on the plans. Appendices (January 2, 2012) The following appendix is attached and made a part of this contract: *** APPENDIX A: GeoDesign Inc. Geotechnical Memorandum August 27, 2015 APPENDIX B: SWPPP *** Crosswalk Improvements Ciro of Bremerton, Washington Federal Aid # STPUS4918/015) 63 Special Provisions Skillings Connolly, Inc. April 2016 N 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 (January 4, 2016) Standard Plans The State of Washington Standard Plans for Road, Bridge and Municipal Construction M21- 01 transmitted under Publications Transmittal No. PT 15-048, effective August 3, 2015 is made a part of this contract. The Standard Plans are revised as follows: A-30.15 DELETED A-50.10 Sheet 2 of 2, Plan, with Single Slope Barrier, reference C-1 4a is revised to C-70.10 A-50.20 Sheet 2 of 2, Plan, with Anchored Barrier, reference C-1 4a is revised to C-70.10 A-50.30 Sheet 2 of 2, Plan (top), reference C-1 4a is revised to C-70.10 B-10.20 and B-10.40 Substitute "step" in lieu of "handhold" on plan B-15.60 Table, Maximum Knockout Size column, 120" Diam., 42" is revised to read; 96" B-25.20 Add Note 7. See Standard Specification Section 8-04 for Curb and Gutter requirements B-55.20 Metal Pipe elevation, title is revised to read; "Metal Pipe and Steel Rib Reinforced Polyethylene Pipe" B-90.40 Offset & Bend details, add the subtitle, "Plan View' above titles C -8b Section A, callout, was - "Grout" is revised to read; "Grout - 2" (IN) MAX., callout, was - "Anchor Bolt (TYP.) - See Detail" is revised to read; "Anchor Bolt or Rod (TYP.) - See Detail", Sheet 2, Detail "A", callout, was - "Anchor Bolt (TYP.) - See Detail", is revised to read; "Anchor Bolt or Rod (TYP) - See Detail". Anchor Bolt Detail, DELETED - Headed Bolt DETAIL portion of the ANCHOR BOLT DETAIL. Dimension, "5 1/2" MIN. Threads" is deleted. Add dimension, 1" MAX." from top of barrier to bottom of the nut, Callout, was -.1" Diam. Threaded Rod - ASTM A 419" is revised to read; "1" (IN) Diam. Threaded Full Length Rod or Bolt - ASTM F 1554, Grade 105". Note (Below Title), was - "Galvanize Exposed Anchor Rod End 1' - 9" Min." is revised to read; "Galvanized Anchor Bolt Full Length according to ASTM F 2329". Subtitle - was "Threaded Rod" is revised to read; "Threaded Rod or Bolt", Sheet 2, Anchor Plate detail, callout, was - 1" DIAM. HOLE (TYP.)" IS REVISED TO READ; 1 1/8" (IN) DIAM. HOLE (TYP.)", callout, was - "/2" Plate" is revised to read;" 1/2" (IN) Plate - ASTM A36 Crosswalk Improvements City of Bremerton. Washington Federal Aid # STPUS-9918(015) 64 Special Provisions Skillings Co holly, Inc. April 2016 1 C-1 2 Assembly Detail, Steel Post, (post) callout - was - "W6 x 9 or W6 x 15" is revised to 3 read; "W6 x 8.5 or W6 x 9 or W6 x 15" 4 5 C-10 6 General Note 1, first sentence, was - "Length of W8 x 35 and W6 x 9 shall be 7 determined by measurement from top of ground to top of grout pad." Is revised to read; 8 "Length of W8 x 35 and W6 x 8.5 or W6 x 9 shall be determined by measurement from 9 top of ground to top of grout pad." 10 Sheet 1, Post Base Plate Detail, callout, was - "W6 x 9" is revised to read; "W6 x 8.5 or 11 W6x9" 12 Sheet 1, Box Culvert Guardrail Steel Post Type 2 detail, callout, was - "W6 x 9 Steel 13 Post" is revised to read;" "W6 x 8.5 or W6 x 9 Steel Post" 14 Sheet 1, Post Anchor Attachment Detail, callout, was - "W6 x 9 - See Note 1" is revised 15 to read; "W6 x 8.5 or W6 x 9 - See Note 1" 16 Sheet 1, Detail A, callout, was - "W6 x 9 Steel Post - See Note 1" is revised to read; 17 "W6 x 8.5 or W6 x 9 Steel Post - See Note 1" 18 Sheet 2, Box Culvert Guardrail Steel Post Type 1, callout, was - "W6 x 9 x 27.5" Steel 19 Post" is revised to read; "W6 x 8.5 x 27.5" (IN) or W6 x 9 x 27.5" (IN) Steel Post" 20 Sheet 2, Detail B, callout, was - "W6 x 9 x 27.5" Steel Post" is revised to read; "W6 x 21 8.5 x 27.5" (IN) or W6 x 9 x 27.5" (IN) Steel Post" 22 23 C -16a 24 Note 1, reference C-28.40 is revised to C-20.10 25 26 C -16b 27 Note 3, reference C-28.40 is revised to C-20.10 28 29 C-22.14 30 Plan, callout, was - "Location of Post (Without Block) - W6 x 9 Steel Post Only" is 31 revised to read; "Location of Post (Without Block) - W6 x 8.5 or W6 x 9 Steel Post Only" 32 Elevation, callout, was - "Location of Post (Without Block) - W6 x 9 Steel Post Only" is 33 revised to read; "Location of Post (Without Block) - W6 x 8.5 or W6 x 9 Steel Post Only" 34 35 C-22.45 36 Note 1, was - "This Terminal is FHWA accepted at Test Level Two (TL -2) and may be 37 used in applications with speeds of 40 MPH or less." Is revised to read: "This Terminal is 38 FHWA accepted at Test Level Two (TL -2) and may be used in applications with speeds 39 of 45 MPH or less." Plan Title, was - "Beam Guardrail Type 31 Non - Flared Terminal 40 Steel Posts (Posted Speed - 40. MPH and Below)" is revised to read: "Beam Guardrail 41 Type 31 Non - Flared Terminal Steel Posts (Posted Speed - 45 MPH and Below 42 43 D-10.10 44 Wall Type 1 may be used if no traffic barrier is attached on top of the wall. Walls with 45 traffic barriers attached on top of the wall are considered non-standard and shall be 46 designed in accordance with the current WSDOT Bridge Design Manual (BDM) and the 47 revisions stated in the 11/3/15 Bridge Design memorandum. 48 49 D-10.15 50 Wall Type 2 may be used if no traffic barrier is attached on top of the wall. Walls with 51 traffic barriers attached on top of the wall are considered non-standard and shall be Crosswalk Improvements Special Provisions Civ of Bremerton, Washing/on 65 Skillings Connollv, Inc. Federal Aid # STPUS-9918(015) April 2016 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 designed in accordance with the current WSDOT BDM and the revisions stated in the 11/3/15 Bridge Design memorandum. D-10.20 Wall Type 3 may be used in all cases. The last sentence of Note 6 on Wall Type 3 shall be revised to read: The seismic design of these walls has been completed using a site adjusted (effective) peak ground acceleration of 0.32g. D-10.25 Wall Type 4 may be used in all cases. The last sentence of Note 6 on Wall Type 4 shall be revised to read: The seismic design of these walls has been completed using a site adjusted (effective) peak ground acceleration of 0.32g. D-10.30 Wall Type 5 may be used in all cases. D-10.35 Wall Type 6 may be used in all cases. D-10.40 Wall Type 7 may be used if no traffic barrier is attached on top of the wall. Walls with traffic barriers attached on top of the wall are considered non-standard and shall be designed in accordance with the current WSDOT BDM and the revisions stated in the 11/3/15 Bridge Design memorandum. D-10.45 Wall Type 8 may be used if no traffic barrier is attached on top of the wall. Walls with traffic barriers attached on top of the wall are considered non-standard and shall be designed in accordance with the current WSDOT BDM and the revisions stated in the revisions stated in the 11/3/15 Bridge Design memorandum. D-15.10 STD Plans D-15 series "Traffic Barrier Details for Reinforced Concrete Retaining Walls" are withdrawn. Special designs in accordance with the current WSDOT BDM are required in place of these STD Plans. D-15.20 STD Plans D-15 series "Traffic Barrier Details for Reinforced Concrete Retaining Walls" are withdrawn. Special designs in accordance with the current WSDOT BDM are required in place of these STD Plans. D-15.30 STD Plans D-15 series "Traffic Barrier Details for Reinforced Concrete Retaining Walls" are withdrawn. Special designs in accordance with the current WSDOT BDM are required in place of these STD Plans. F-10.12 Section Title, was — "Depressed Curb Section" is revised to read: "Depressed Curb and Gutter Section" F-10.40 "EXTRUDED CURB AT CUT SLOPE", Section detail - Deleted Crosswalk Improvements City of Bremerton. Washington Federal Aid # STPUS-9918(015) 66 Special Provisions Skillings Connolly. Inc. April 2016 1 2 F-10.42 3 DELETE - "Extruded Curb at Cut Slope" View 4 5 -G-24.40 6 Sheet 1, Elevation (upper left corner), callout, was - "Sign Brace- 36" (IN) or larger in 7 width required (See Standard Plan G-50.10)" is revised to read; "Sign Brace (See 8 Standard Plan G-50.10)" Sheet 3, Elevation (upper left corner), callout, was - "Sign 9 Brace- 36" (IN) or larger in width required (See Standard Plan G-50:10)" is revised to 10 read; "Sign Brace (See Standard Plan G-50.10)" 11 12 H-70.20 13 Sheet 2, Spacing Detail, Mailbox Support Type 1, reference to Standard Plan 1-70.10 is 14 revised to H-70.10 15 16 1-80.10 17 Stabilized Construction Entrance, Isometric View, add Note to read; "Note: At the 18 discretion of the contractor, smaller rock may be used to fill in voids between the quarry 19 spalls to create a walking pathway for crossing the construction entrance." 20 21 J-3 22 DELETED 23 24 J -3b 25 DELETED 26 27 J -3C 28 DELETED 29 30 J-10.21 31 Note 18, was - "When service cabinet is installed within right of way fence, see 32 Standard Plan J-10.22 for details." Is revised to read; "When service cabinet is installed 33 within right of way fence, or the meter base is mounted on the exterior of the cabinet, 34 see Standard Plan J-10.22 for details." 35 36 J-10.22 37 Key Note 1, was - "Meter base per serving utility requirements- as a minimum, the 38 meter base shall be safety socket box with factory -installed test bypass facility that 39 meets the requirements of EUSERC drawing 305." Is revised to read; "Meter base per 40 serving utility requirements- as a minimum, the meter base shall be safety socket box 41 with factory -installed test bypass facility that meets the requirements of EUSERC 42 drawing 305. When the utility requires meter base to be mounted on the side or back of 43 the service cabinet, the meter base enclosure shall be fabricated from type 304 44 stainless steel." 45 Key Note 4, "Test with (SPDT Snap Action, Positive close 15 Amp - 120/277 volt "T" 46 rated). Is revised to read: "Test Switch (SPDT snap action, positive close 15 amp - 47 120/277 volt "T" rated)." 48 Key Note 14, was - "Hinged dead front with % turn fasteners or slide latch." Is revised to 49 read; "Hinged dead front with % turn fasteners or slide latch. - Dead front panel bolts 50 shall not extend into the vertical limits of the breaker array(s)." 51 Key Note 15, was - "Cabinet Main Bonding Jumper. Buss shall be 4 lug tinned copper. 52 See Cabinet Main bonding Jumper detail, Standard Plan J -3b." is revised to read; Crosswalk Improvements Special Provisions City of Bremerton, Washington 67 Skillings Connollv. Inc. Federal Aid # STPUS-9913(01.1) April 2016 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 "Cabinet Main Bonding Jumper Assembly - Buss shall be 4 lug tinned copper - See Standard Plan J-10.20 for Cabinet Main Bonding Jumper Assembly details." J-20.10 Add Note 5, "5. One accessible pedestrian signal assembly per pedestrian pushbutton post." J-20.11 Sheet 2, Foundation Detail, Elevation, callout - "Type 1 Signal Pole" is revised to read: "Type PS or Type 1 Signal Pole" Sheet 2, Foundation Detail, Elevation, add note .below Title, "(Type 1 Signal Pole Shown)" Add Note 6, "6. One accessible pedestrian signal assembly per pedestrian pushbutton post." J-20.26 Add Note 1, 1. One accessible pedestrian pushbutton station per pedestrian pushbutton post." J-20.16 View A, callout, was - LOCK NIPPLE, is revised to read; CHASE NIPPLE J-21.10 Sheet 1 of 2, Elevation view (Round), add dimension depicting the distance from the top of the foundation to find 2 #4 reinforcing bar shown, to read; 3" CLR.. Delete "(TYR)" from the 2'/2" CLR. dimension, depicting the distance from the bottom of the foundation to find 2 # 4 reinf. Bar. Sheet 1 of 2, Elevation view (Square), add dimension depicting the distance from the top of the foundation to find 1 #4 reinforcing bar shown, to read; 3" CLR. Delete "(TYR)" from the 2'/" CLR. dimension, depicting the distance from the bottom of the foundation to find 1 # 4 reinf. Bar. Sheet 2 of 2, Elevation view (Round), add dimension depicting the distance from the top of the foundation to find 2 #4 reinforcing bar shown, to read; 3" CLR. Delete "(TYR)" from the 2'/Z" CLR. dimension, depicting the distance from the bottom of the foundation to find 2 # 4 reinf. Bar. Sheet 2 of 2, Elevation view (Square), add dimension depicting the distance from the top of the foundation to find 1 #4 reinforcing bar shown, to read; 3" CLR. Delete "(TYR)" from the 2'/2° CLR. dimension, depicting the distance from the bottom of the foundation to find 1 # 4 reinf. Bar. J-21.15 Partial View, callout, was - LOCK NIPPLE - 1 '/2' DIAM., is revised to read; CHASE NIPPLE - 1 '/z° (IN) DIAM. J-21.16 Detail A, callout, was - LOCKNIPPLE, is revised to read; CHASE NIPPLE J-22.15 Ramp Meter Signal Standard, elevation, dimension 4'- 6" is revised to read; 6'-0" (2x) Detail A, callout, was - LOCK NIPPLE - 1 '/2" DIAM. is revised to read; CHASE NIPPLE -- 1 '/z' (IN) DIAM. Crosswalk Improvements Special Provisions City of Bremerton, Washington 68 Skillings Connolly. bic. Federal Aid # STPUS-9918(015) April 2016 1 J-28.45- 2 -28.452 Steel Light Standard Elbow Detail, dimension, was - 1-1/2" MAX." is revised to read; 2" 3 MAX.. callout, was - 1.00 - 8 UNC x 8" (IN) long bolt threaded full length (ASTM A325 4 or F1554 GR. 105) with two heavy hex nuts, two plate washers, and a round washer 5 (Typ.) (Galvanized AASHTO M232)"is revised to read; 1.00 - 8 UNC x 8 1/2" (IN) long 6 bolt threaded full length (ASTM A325 or F1554 GR. 105) with two heavy hex nuts, two 7 plate washers, and a round washer (Typ.) (Galvanized per AASHTO F2329)". callout, 8 was - "3/16" (IN) thick preformed "Fabreeka" fabric pad with 5" (IN) diam. hole - cement 9 to flange plate and trim outside edge flush" is revised to read; "3/16" (IN) or 1/4" (IN) 10 thick preformed "Fabreeka" fabric pad with 5" (IN) diam. hole cement to flange plate 11 and trim outside edge flush". Exploded Isometric View, callout, was - 1" (IN) Diam. 12 Heavy Hex Bolt (Typ.)" is revised to read;1" Diam. Bolt (Typ.). Section B, callout, was - 13 "3 1/2" (IN) x 3/16" (IN)(17" (IN)..." is revised to read; "4" (IN) x 3/16" (IN)(17" (IN)...". 14 Typical Sections, two traffic barrier views, add dimension [from the top of the pole base 15 plate to the bottom of the Hand Hole]"6" MIN.". all three views, callout, was - 1" (IN) 16 Diam. H. S. bolt w/ hardened lock washer and nut (Typ.) (ASTM A325 or F1554 GR. 17 105)" is revised to read; 1" (IN) Diam. H. S. bolt w/ hardened lock washer and nut 18 (Typ.) (ASTM A449 or F1554 GR. 105)". 19 20 J-28.50 21 Section D, callout, was - Backup Strip (ref. to key note 3) is revised to read; 22 "Continuous Backup Strip (ref. to key note 3)" 23 Key Note 3, was — %" Thick, or No thinner than pole wall thickness. Tack weld or seal 24 weld to Base plate. Is revised to read; "1/4" Thick, or No thinner than Pole wall 25 thickness. Tack weld in root or continuous seal weld to Base plate or Pole wall." 26 27 J-28.60 28 Section B, callout, was - "Continuous Back-up ring - 1/4" or no thinner than pole wall 29 thickness - tack weld to plate" is revised to read; "Continuous Back-up ring - 1/4" or no 30 thinner than pole wall thickness - tack weld in root or continuous seal weld to base plate 31 or pole wall' 32 33 J-28.70 34 Detail C, dimension, 2" MAX. is revised to read: 1" MAX. 35 Detail D, dimension, 2" MAX. is revised to read: 1" MAX. 36 37 J-29.10 38 Galvanized Welded Wire Mesh detail, callout - "Drill and Tap for Y4' Diam. Cap Screw, 3 39 Places, @ 9" center, all 4 edges S.S. Screw, ASTM F593 and washer" 40 Is revised to read; 41 `Drill and Tap Y4" (IN) Diam. x 1" (IN) Cap Screw with washer - space approx.. 9" o.c. 42 Liberally coat threads with Anti-seize compound (TYR)" 43 44 Add Boxed note: * Bolts, Nuts, and washers -r ASTM F593 or A193 Type 304 or Type 45 316 Stainless Steel (S.S.) 46 47 J-29.15 48 Title, "Camera Pole Standard" is revised to read; "Camera Pole Standard Details" 49 50 J-29-16 51 Title, "Camera Pole Standard Details" is revised to read; "Camera Pole Details" 52 Crosswalk Improvements Special Provisions Citv of Bremerton, Washington 69 Skillings Connolly, lnc. Federal Aid #STPUS-MNOI.i) ApriI20lh 1 J-40.10 2 Sheet 2 of 2, Detail F, callout, 12 - 13 x 1 Y2" S.S. PENTA HEAD BOLT AND 12" S. S. 3 FLAT WASHER" is revised to read; "12 - 13 x 1 1/" S.S. PENTA HEAD BOLT AND 1/2" 4 (IN) S. S. FLAT WASHER" 5 6 J-60.14 7 All references to J -16b (6x) are revised to read; J-60.11 8 9 J-90.10 10 Section B, callout, "Hardware Mounting Rack - S. S. 1-5/8" Slotted Channel" is revised 11 to read: "Hardware Mounting Rack (Typ.) - Type 304 S. S. 1-5/8" Slotted Channel" 12 13 J-90.20 14 Section B, callout, "Hardware Mounting Rack (Typ.) - S. S. 1-5/8" Slotted Channel" is 15 revised to read: "Hardware Mounting Rack (Typ.) - Type 304 S. S. 1-5/8" Slotted 16 Channel" 17 18 K-80.10 19 Sign Installation (Fill Section), dimension, 6' TO 12' MIN. is revised to read: 12' MIN. 20 Sign Installation (Sidewalk and Curb Section), dimension, 6' TO 12' MIN. is revised to 21 read: 12' MIN. 22 Sign Installation (Behind Traffic Barrier Section), Delete dimensions - 6' TO 12' MIN. and 23 6' MIN. 24 Sign with Supplemental Plaque Installation (Fill Section), dimension, 6' TO 12' MIN. is 25 revised to read: 12' MIN. 26 Sign Installation (Ditch Section), dimension, 6' TO 12' MIN. is revised to read: 12' MIN. 27 Delete dimension - 6' MIN. 28 29 K-80.30 30 In the NARROW BASE, END view, the reference to Std. Plan C -8e is revised to Std. 31 Plan K-80.35 32 33 34 M-11.10 35 Layout, dimension (from stop bar to "X"), was - 23' is revised to read; 24' 36 37 M-20.30 38 Sheet 2, Plan View, One -Way Roadway Recessed Pavement Marker Details, ONE-WAY 39 TRAFFIC arrow symbol, is revised to point in the opposite direction (towards the rpm) 40 41 The following are the Standard Plan numbers applicable at the time this project was 42 advertised. The date shown with each plan number is the publication approval date 43 shown in the lower right-hand corner of that plan. Standard Plans showing different 44 dates shall not be used in this contract. 45 A-10.10-00........8/7/07 A-30.35-00.......10/12/07 A-50.20-01.........9/22/09 A-10.20-00......10/5/07 A-40.00-00.........8/11/09 A-50.30-00.......11/17/08 A-10.30-00......10/5/07 A-40.10-03.........12/23/14 A-50.40-00.......11/17/08 A-20.10-00......8/31/07 A-40.15-00.........8/11/09 A-60.10-03........12/23/14 A-30.10-00......11/8/07 A-40.20-03.........12/23/14 A-60.20-03.........12/23/14 A-40.50-02.........12/23/14 A-60.30-00 .......... 11/8/07 A-30.30-01......6/16/11 A-50.10-00.......11/17/08 A-60.40-00 .......... 8/31/07 Crosswalk Improvements Special Provisions City of Bremerton. Washington 70 Skillings Connollv, Inc. Federal Aid # STPUS-9918(015) April 2016 E 3 B-5.20-01........6/16/11 B-5.40-01......... 6/16/11 B-5.60-01 ......... 6/16/11 B-10.20-01........ 2/7/12 B-10.40-00 ........ 6/1 /06 B-10.60-00........6/8/06 ..................6/21 /06 B-15.20-01 ........ 2/7/ 12 B-15.40-01 ........ 2/7/ 12 B-15.60-01 ........ 2/7/ 12 B-20.20-02....... 3/16/12 B-20.40-03....... 3/16/12 B-20.60-03....... 3/15/12 B-25.20-01........ 3/15/12 B-25.60-00 ......... 6/1 /06 B-30.10-01......... 4/26/12 B-30.20-02 ......... 4/26/12 B-30.30-01.........4/26/12 C -2p ................10/31 /03 B-30.40-01.......... 4/26/12 C-1 .................... 6/16/11 C-1 a .................7/14/15 C-1 b ...................7/14/15 C-1 c ..................5/30/97 C-1 d ................10/31 /03 C-2 ....................1 /6/00 C -2a ..................6/21 /06 C -2b ..................6/21 /06 C -2c ..................6/21 /06 C -2d ..................6/21 /06 C -2e ..................6/21 /06 C -2f ................... 3/14/97 C -2g .................. 7/27/01 C -2h ..................3/28/97 C -2i ...................3/28/97 B-65.20-01 .......... 4/26/ 12 C-2 j ................... 6/12/98 C-2 k .................. 7/27/01 C-2 n .................. 7/27/01 C -2o .................. 7/13/01 C -2p ................10/31 /03 C-3 ................... 7/2/12 C- 3 a .................10/4/0 5 C -3b ................6/27/11 C -3c ................6/27/11 C -4b ..................6/8/06 C -4e ..................10/23/ 14 C -4f ...................7/2/12 B-30.50-01.........4/26/12 C-6 a ................10/ B-30.70-03 ......... 4/26/ 12 B-30.80-00 ........... 6/8/06 B-30.90-01........ 9/20/07 B-35.20-00 .......... 6/8/06 B-35.40-00.......... 6/8/06 B-40.20-00 .......... 6/1 /06 B-40.40-01........ 6/16/10 B-45.20-00 .......... 6/1 /06 B-45.40-00 .......... 6/1 /06 B-50.20-00 .......... 6/1 /06 B-55.20-00 .......... 6/1 /06 B-60.20-00 .......... 6/8/06 B-60.40-00 .......... 6/1 /06 B-65.20-01 .......... 4/26/ 12 B-65.40-00 .......... 6/1 /06 B-70.20-00 .......... 6/1 /06 B-70.60-00 .......... 6/1 /06 C-6 .................... 5/30/97 C-6 a ................10/ 14/09 C -6c ....................1 /6/00 C-6 d ................... 5/30/97 C -6f ...................7/25/97 B-80.40-00 C-7 ..................... 6/16/11 C -7a ...................6/16/11 B-85.10-01 C-8 ..................... 2/10/09 C -8a ................... 7/25/97 C -8b ....................6/27/11 B-85.40-00 C -8e ....................2/21 /07 C -8f .....................6/30/04 B-90.10-00.......... C-10 ...................... 6/3/10 C-16 a ................. 6/3/10 C-16 b ................. 6/3/10 C-20.10-03......... 7/14/15 C-20.14-03 .......... 6/11 /14 C-20.15-02 .......... 6/11 /14 C-20.18-02 .......... 6/11 /14 C-20.19-02 .......... 6/11 /14 C-20.40-05.......... 7/14/15 C-20.41-01 .......... 7/14/15 C-20.42-05.......... 7/14/15 C-20.45.01 ........... 7/2/12 C-22.14-03 ........ 6/11 /14 C-22.16-05........ 7/14/15 C-22.40-04........10/23/ 14 C-22.41-01........10/23/14 C-22.45-01........10/23/ 14 B-75.20-01 .......... 6/ 10/08 B-75.50-01.......... 6/10/08 B-75.60-00............ 6/8/06 B-80.20-00 ......... 6/8/06 B-80.40-00 ......... 6/1 /06 B-82.20-00 ......... 6/1 /06 B-85.10-01 ......... 6/ 10/08 B-85.20-00 .......... 6/1 /06 B-85.30-00 .......... 6/1 /06 B-85.40-00 .......... 6/8/06 B-85.50-01.........6/10/08 6/11 /14 B-90.10-00.......... 6/8/06 B-90.20-00 .......... 6/8/06 B-90.30-00 .......... 6/8/06 B-90.40-00 .......... 6/8/06 B-90.50-00 .......... 6/8/06 B-95.20-01 .......... 2/3/09 B-95.40-00.......... 6/8/06 C-23.60-03......6/11 /14 C.24.10-01......6/11 /14 C-25.18-05........ 7/14/15 C-25.20-06........ 7/14/15 C-25.22-05 ........ 7/14/15 C-25.26-03 ........ 7/14/15 C-25.80-03 ........ 6/11 /14 C-40.14-02 ........ 7/2/12 C-40.16-02........ 7/2/12 C-40.18-02........ 7/2/12 C-70.10-01........ 6/17/14 C-75.10-01 ........ 6/11 /14 C-75.20-01 ........ 6/11 /14 C-75.30-01 ........ 6/11/14 C-80.10-01 ........ 6/11 /14 C-80.20-01 ........ 6/11 /14 C-80.30-01 ........ 6/11 /14 C-80.40-01 ........ 6/11 /14 C-80.50-00 ........ 4/8/ 12 C-85.10-00 ........ 4/8/ 12 C-85.11-00........4/8/12 C-85.14-01 ........ 6/11 /14 C-85.15-01 ........ 6/30/ 14 C-85.16-01 ........ 6/17/14 C-85-18-01 ........ 6/11 /14 C-85.20-01 ........ 6/11 /14 C-90.10-00........ 7/3/08 D-2.04-00........11/10/05 D-2.48-00........11/10/05 D-3.17-01......5/17/12 D-2.06-01 ........ 1 /6/09 D-2.64-01 ........ 1 /6/09 D-4 .................12/11 /98 Crosswalk Improvements City of Bremerton, Washington Federal And # SI PUS -9918(01.1) 71 Special Provisions Skillings Connolly, Inc. April 2016 2 3 4 5 0 D-2.08-00 ........ 11 /10/05 D-2.14-00 ........ 11 /10/05 D-2.16-00 ........ 11 /10/05 D-2.18-00 ........ 11 /10/05 D-2.20-00 ........ 11 /10/05 D-2.32-00 ........ 11 /10/05 D-2.34-01 ........ 1 /6/09 D-2.36-03 ........ 6/11 /14 D-2.42-00 ........ 11 /10/05 D-2.44-00 ........ 11 /10/05 D-2.60-00 ........ 11 /10/05 D-2.62-00 ........ 11 /10/05 D-2.46-01 ........ 6/11 /14 D-2.66-00 ........ 11 /10/05 D-2.68-00 ........ 11 /10/05 D-2.80-00 ........ 11 /10/05 D-2.82-00 ........ 11 /10/05 D-2.84-00 ........ 11 /10/05 D-2.86-00 ........ 11 /10/05 D-2.88-00 ........ 11 /10/05 D-2.92-00 ........ 11 /10/05 D-3.09-00........ 5/17/12 D-3.10-01...... 5/29/13 D-3.11-03...... 6/11/14 D-3.15-02...... 6/10/13 D-3.16-02...... 5/29/13 E-1 ....................2/21/07 E-4 ................ :... 8/27/03 E-2 ....................5/29/98 E -4a .................. 8/27/03 F-10.12-03 ....... 6/11 /14 F-10.16-00.......12/20/06 4/22/14 F-10.18-00 ......... 6/27/ 11 F-10.40-02 ........... 6/21 /12 F-10.42-00 ......... 1 /23/07 G-10.10-00........9/20/07 G-20.10-02 ........ 6/23/ 15 G-22.10-03.......... 7/10/15 G-24.10-00 ...... 11 /8/07 G-24.20-01...... 2/7/12 G-24.30-01...... 2/7/12 G-24.40-05.....6/23/15 G-24.50-03.....6/17/14 H-1 0. 10-00 .......... 7/3/08 H-1 0. 15-00 .......... 7/3/08 H-30.10-00 ...... 10/ 12/07 F-10.62-02........ 4/22/14 F-10.64-03........ 4/22/14 F-30.10-03 ........ 6/11 /14 F-40.12-02 ........ 6/20/ 13 F-40.14-02 ........ 6/20/ 13 G-24.60-04.....6/23/15 D-10.10-01......12/2/08 G-25.10-04...... 6/10/13 G-30.10-04..... 6/23/15 G-50.10-02..... 6/23/15 G-60.10-03....... 6/18/15 G-60.20-02....... 6/18/15 G-60.30-02.......6/18/15 D-10.40-01......12/2/08 G-70.10-03 ...... 6/18/15 H-32.10-00.......9/20/07 H-60.10-01......... 7/3/08 H-60.20-01 ......... 7/3/08 D-6 ...................6/ 19/98 D-10.10-01......12/2/08 F-40.16-02 D-10.15-01......12/2/08 F-45.10-01 D-10.20-00 ......... 7/8/08 D-10.25-00 ......... 7/8/08 D-10.30-00......... 7/8/08 D-10.35-00......... 7/8/08 D-10.40-01......12/2/08 1-30.40-01 D-10.45-01......12/2/08 1-60.10-01 D-15.10-01......12/2/08 1-30.16-00......... D-15.20-02........6/2/11 1-30.60-00......... D-15.30-01......12/02/08 1-60.20-01 F-40.15-02 ........ 6/20/ 13 F-40.16-02 ........ 6/20/ 13 F-45.10-01 ........ 6/21 /12 F-80.10-03 ........ 6/11 /14 G-70.20-02....6/10/13 G-70.30-02 ...... 6/10/13 G-90.10-01.....5/11 /11 G-90.20-03..... 7/10/15 G-90.30-02.....3/22/13 G-90.40-01.....10/ 14/09 G-95.10-01.....6/2/ 11 G-95.20-02......6/2/ 11 G-95.30-02......6/2/ 11 H-70.10-01......2/7/ 12 H-70.20-01 ...... 2/16/12 H-70.30-02......2/7/ 12 1-10.10-01 ......... 8/11 /09 1-30.20-00.........9/20/07 J-10.15-01 1-40.20-00.........9/20/07 J-10.16-00 1-30.10-02 ......... 3/22/13 1-30.30-01......... 6/10/13 1-50.20-01 .......... 6/10/13 1-30.15-02......... 3/22/13 1-30.40-01 ....... 6/10/13 1-60.10-01 .......... 6/10/13 1-30.16-00......... 3/22/13 1-30.60-00......... 5/29/13 1-60.20-01 .......... 6/10/13 1-30.17-00.........3/22/13 1-40.10-00.........9/20/07 1-80.10-01 .......... 8/11 /09 J-10 .................. 7/18/97 J-10.10-03...... 6/3/15 J-10.15-01 ........ 6/11 /14 J-10.16-00 .......6/3/ 15 J-10.17-00 .......6/3/ 15 Crosswalk Improvements City of Bremerton. Washington Federal Aid # S7PUS-9918(01.1) J-26.15-01.....5/17/12 J-40.40-00......5/20/13 J-26.20-00.....6/11 /14 J-27.10-00.....3/15/12 J-50.10-00.......6/3/11 J-27.15-00.....3/15/12 J-50.11-00.......6/3/11 J-28.10-01......5/11/11 J-50.12-00.......6/3/11 J-28.22-00.......8/07/07 J-50.15-00.......6/3/11 J-28.24-01.......6/3/15 J-50.16-01.......3/22/13 Special Provisions 72 Skillings Connolly, Inc. April 2016 J-10.18-00....... 6/3/15 J-10.20-00........6/3/15 K-80.20-00..:..12/20/06 J-10.21-00........6/3/15 ...... 6/30/ 14 J-10.22-00........ 5/29/13 J-15.10-01 ........ 6/11 /14 J-15.15-02 ...... 7/10/15 J-20.10-03......6/30/ 14 J-20.11-02......6/30/14 K-80.20-00..:..12/20/06 J-20.15-03 ...... 6/30/ 14 J-20.16-02...... 6/30/14 J-20.20-02......5/20/13 K-80.37-00 ....... J-20.26-01...... 7/12/12 J-21.10-04 ...... 6/30/14 J-21.15-01...... 6/10/13 J-21.16-01 ...... 6/10/13 J-21.17-01...... 6/10/13 J-21.20-01...... 6/10/13 J-22.15-02 ...... 7/10/15 J-22.16-03 ...... 7/10/15 J-26.10-02.....3/15/12 K-70.20-00....... 2/15/07 K-80.10-00 ....... 2/21 /07 K-80.20-00..:..12/20/06 J-28.45-02 K-80.30-00 ....... 2/21 /07 K-80.35-00 ....... 2/21 /07 K-80.37-00 ....... 2/21 /07 J-28.26-01......12/02/08 J-28.30-03......6/11 /14 J-28.40-02......6/11 /14 J-28.42-01 ....... 6/11 /14 J-28.43-00 ....... 6/11 /14 J-28.45-02 ....... 6/11 /14 J-28.50-02 ....... 6/2/ 11 J-28.60-01 ....... 6/2/ 11 J-28.70-01 ....... 5/11 /11 J-29.1 0-00 ........ 6/27/ 11 J-29.15-00 ....... 6/27/ 11 J-29.16-01 ....... 6/20/ 13 J-30.10-00......6/18/15 J-40.10-03...... 5/20/13 J-40.20-02......6/11 /14 J-40.30-03...... 5/20/13 J-40.35-01...... 5/29/13 J-40.36-01...... 5/20/13 J-40.37-01 ...... 5/20/ 13 J-40.38-01....... 5/20/13 J-40.39-00...... 5/20/13 2 L-10.10-02........6/21/12 L-40.10-02........6/21/12 L-20.10-03........7/14/15 L-40.15-01........6/16/11 L-30.10-02........6/11/14 L-40.20-02........6/21/12 3 M-1.20-03 ......... 6/24/ 14 M-1.40-02......... 6/3/11 M-1.60-02 ......... 6/3/ 11 M-1.80-03 ......... 6/3/11 M-2.20-03......... 7/10/15 M-2.21-00...... 7/10/15 M-3.10-03 ......... 6/3/11 M-3.20-02 ......... 6/3/11 M-3.30-03 ......... 6/3/11 Crosswalk Improvements City of Bremerton. Washington Federal Aid # STPUS-9918(01.1) M-9.60-00.......2/10/09 M-11.10-01 ....... 1 /30/07 M-15.10-01....... 2/6/07 M-17.10-02 ......... 7/3/08 M-20.10-02 ......... 6/3/11 M-20.20-02 ....... 4/20/15 M-20.30-03.....4/20/ 15 M-20.40-03.........6/24/14 73 J-50.20-00.......6/3/11 J-50.25-00 ....... 6/3/11 J-50.30-00.......6/3/11 J-60.05-00 ....... 6/16/11 J-60.11-00.......5/20/13 J-60.12-00.......5/20/13 J-60.13-00.......6/16/10 J-75.41-00...... J-60.14-00 ...... 6/16/10 J-75.10-02 ...... 7/10/15 J-75.20-01...... 7/10/15 J-75.30-02 ....... 7/10/15 J-75.40-01......6/11 /14 J-75.41-00...... 6/11/14 J-75.45-01......6/11 /14 J-90.1 0-01 ....... 6/27/11 J-90.20-01.......6/27/11 J-90.21-00...... 6/30/14 L-70.10-01 ....... 5/21 /08 L-70.20-01 ....... 5/21 /08 M-40.10-03......6/24/14 M-40.20-00...10/ 12/07 M-40.30-00...... 9/20/07 M-40.40-00...... 9/20/07 M-40.50-00...... 9/20/07 M-40.60-00...... 9/20/07 M-60.10-01......6/3/ 11 M-60.20-02......6/27/11 Special Provisions Skillings Connolly, Inc. April 2016 1 2 M-3.40-03....... M-3.50-02....... M-5.10-02....... M-7.50-01....... M-9.50-02...... 6/3/11 6/3/11 6/3/11 1/30/07 6/24/14 Crosswalk Improvements Citv of Bremerton. Washington Federal Aid # STPUS-9918(015) M-20.50-02 ......... 6/3/11 M-24.20-02....... 4/20/15 M-24.40-02....... 4/20/15 M-24.50-00 ....... 6/16/11 M-24.60-04.......6/24/ 14 74 M-65.10-02......5/11 /11 M-80.10-01...... 6/3/11 M-80.20-00 ...... 6/ 10/08 M-80.30-00 ...... 6/ 10/08 Special Provisions Skillings Connolly. Inc. April 2016 Special Provisions —Appendix A GeoDesign Inc. Geotechnical Memorandum August 27, 2015 [Insert Geotech Memo] Special Provisions -Appendix B SWPPP March, 2016 [Insert SWPPP] V. CONSTRUCTION PLANS. [Construction Plans Bound Separately] APPENDIX A Federal Aid Provisions FHWA-1273 REQUIRED CONTRACT PROVISIONS FEDERAL -AID CONSTRUCTION CONTRACTS I. General II. Nondiscrimination III. Nonsegregated Facilities IV. Davis -Bacon and Related Act Provisions V. Contract Work Hours and Safety Standards Act Provisions VI. Subletting or Assigning the Contract VII. Safety: Accident Prevention VIII. False Statements Concerning Highway Projects IX. Implementation of Clean Air Act and Federal Water Pollution Control Act X. Compliance with Governmentwide Suspension and Debarment Requirements XI. Certification Regarding Use of Contract Funds for Lobbying ATTACHMENTS A. Employment and Materials Preference for Appalachian Development Highway System or Appalachian Local Access Road Contracts (included in Appalachian contracts only) I. GENERAL 1. Form FHWA-1273 must be physically incorporated in each construction contract funded under Title 23 (excluding emergency contracts solely intended for debris removal). The contractor (or subcontractor) must insert this form in each subcontract and further require its inclusion in all lower tier subcontracts (excluding purchase orders, rental agreements and other agreements for supplies or services). The applicable requirements of Form FHWA-1273 are incorporated by reference for work done under any purchase order, rental agreement or agreement for other services. The prime contractor shall be responsible for compliance by any subcontractor, lower -tier subcontractor or service provider. Form FHWA-1273 must be included in all Federal -aid design - build contracts, in all subcontracts and in lower tier subcontracts (excluding subcontracts for design services, purchase orders, rental agreements and other agreements for supplies or services). The design -builder shall be responsible for compliance by any subcontractor, lower -tier subcontractor or service provider. Contracting agencies may reference Form FHWA-1273 in bid proposal or request for proposal documents, however, the Form FHWA-1273 must be physically incorporated (not referenced) in all contracts, subcontracts and lower -tier subcontracts (excluding purchase orders, rental agreements and other agreements for supplies or services related to a construction contract). 2. Subject to the applicability criteria noted in the following sections, these contract provisions shall apply to all work performed on the contract by the contractor's own organization and with the assistance of workers under the contractor's immediate superintendence and to all work performed on the contract by piecework, station work, or by subcontract. FHWA-1273 -- Revised May 1, 2012 3. A breach of any of the stipulations contained in these Required Contract Provisions may be sufficient grounds for withholding of progress payments, withholding of final payment, termination of the contract, suspension / debarment or any other action determined to be appropriate by the contracting agency and FHWA. 4. Selection of Labor: During the performance of this contract, the contractor shall not use convict labor for any purpose within the limits of a construction project on a Federal -aid highway unless it is labor performed by convicts who are on parole, supervised release, or probation. The term Federal -aid highway does not include roadways functionally classified as local roads or rural minor collectors. II. NONDISCRIMINATION The provisions of this section related to 23 CFR Part 230 are applicable to all Federal -aid construction contracts and to all related construction subcontracts of $10,000 or more. The provisions of 23 CFR Part 230 are not applicable to material supply, engineering, or architectural service contracts. In addition, the contractor and all subcontractors must comply with the following policies: Executive Order 11246, 41 CFR 60, 29 CFR 1625-1627, Title 23 USC Section 140, the Rehabilitation Act of 1973, as amended (29 USC 794), Title VI of the Civil Rights Act of 1964, as amended, and related regulations including 49 CFR Parts 21, 26 and 27; and 23 CFR Parts 200, 230, and 633. The contractor and all subcontractors must comply with: the requirements of the Equal Opportunity Clause in 41 CFR 60- 1.4(b) and, for all construction contracts exceeding $10,000, the Standard Federal Equal Employment Opportunity Construction Contract Specifications in 41 CFR 60-4.3. Note: The U.S. Department of Labor has exclusive authority to determine compliance with Executive Order 11246 and the policies of the Secretary of Labor including 41 CFR 60, and 29 CFR 1625-1627. The contracting agency and the FHWA have the authority and the responsibility to ensure compliance with Title 23 USC Section 140, the Rehabilitation Act of 1973, as amended (29 USC 794), and Title VI of the Civil Rights Act of 1964, as amended, and related regulations including 49 CFR Parts 21, 26 and 27; and 23 CFR Parts 200, 230, and 633. The following provision is adopted from 23 CFR 230, Appendix A, with appropriate revisions to conform to the U.S. Department of Labor (US DOL) and FHWA requirements. 1. Equal Employment Opportunity: Equal employment opportunity (EEO) requirements not to discriminate and to take affirmative action to assure equal opportunity as set forth under laws, executive orders, rules, regulations (28 CFR 35, 29 CFR 1630, 29 CFR 1625-1627, 41 CFR 60 and 49 CFR 27) and orders of the Secretary of Labor as modified by the provisions prescribed herein, and imposed pursuant to 23 U.S.C. 140 shall constitute the EEO and specific affirmative action standards for the contractor's project activities under this contract. The provisions of the Americans with Disabilities Act of 1990 (42 U.S.C. 12101 et seq.) set forth under 28 CFR 35 and 29 CFR 1630 are incorporated by reference in this contract. In the execution of this contract, the contractor agrees to comply with the following minimum specific requirement activities of EEO: a. The contractor will work with the contracting agency and the Federal Government to ensure that it has made every good faith effort to provide equal opportunity with respect to all of its terms and conditions of employment and in their review of activities under the contract. b. The contractor will accept as its operating policy the following statement: "It is the policy of this Company to assure that applicants are employed, and that employees are treated during employment, without regard to their race, religion, sex, color, national origin, age or disability. Such action shall include: employment, upgrading, demotion, or transfer; recruitment or recruitment advertising; layoff or termination; rates of pay or other forms of compensation; and selection for training, including apprenticeship, pre -apprenticeship, and/or on-the- job training." 2. EEO Officer: The contractor will designate and make known to the contracting officers an EEO Officer who will have the responsibility for and must be capable of effectively administering and promoting an active EEO program and who must be assigned adequate authority and responsibility to do SO. 3. Dissemination of Policy: All members of the contractor's staff who are authorized to hire, supervise, promote, and discharge employees, or who recommend such action, or who are substantially involved in such action, will be made fully cognizant of, and will implement, the contractor's EEO policy and contractual responsibilities to provide EEO in each grade and classification of employment. To ensure that the above agreement will be met, the following actions will be taken as a minimum: a. Periodic meetings of supervisory and personnel office employees will be conducted before the start of work and then not less often than once every six months, at which time the contractor's EEO policy and its implementation will be reviewed and explained. The meetings will be conducted by the EEO Officer. b. All new supervisory or personnel office employees will be given a thorough indoctrination by the EEO Officer, covering all major aspects of the contractor's EEO obligations within thirty days following their reporting for duty with the contractor. c. All personnel who are engaged in direct recruitment for the project will be instructed by the EEO Officer in the contractor's procedures for locating and hiring minorities and women. d. Notices and posters setting forth the contractor's EEO policy will be placed in areas readily accessible to employees, applicants for employment and potential employees. e. The contractor's EEO policy and the procedures to implement such policy will be brought to the attention of employees by means of meetings, employee handbooks, or other appropriate means. 4. Recruitment: When advertising for employees, the contractor will include in all advertisements for employees the notation: "An Equal Opportunity Employer." All such advertisements will be placed in publications having a large circulation among minorities and women in the area from which the project work force would normally be derived. a. The contractor will, unless precluded by a valid bargaining agreement, conduct systematic and direct recruitment through public and private employee referral sources likely to yield qualified minorities and women. To meet this requirement, the contractor will identify sources of potential minority group employees, and establish with such identified sources procedures whereby minority and women applicants may be referred to the contractor for employment consideration. b. In the event the contractor has a valid bargaining agreement providing for exclusive hiring hall referrals, the contractor is expected to observe the provisions of that agreement to the extent that the system meets the contractor's compliance with EEO contract provisions. Where implementation of such an agreement has the effect of discriminating against minorities or women, or obligates the contractor to do the same, such implementation violates Federal nondiscrimination provisions. c. The contractor will encourage its present employees to refer minorities and women as applicants for employment. Information and procedures with regard to referring such applicants will be discussed with employees. 5. Personnel Actions: Wages, working conditions, and employee benefits shall be established and administered, and personnel actions of every type, including hiring, upgrading, promotion, transfer, demotion, layoff, and termination, shall be taken without regard to race, color, religion, sex, national origin, age or disability. The following procedures shall be followed: a. The contractor will conduct periodic inspections of project sites to insure that working conditions and employee facilities do not indicate discriminatory treatment of project site personnel. b. The contractor will periodically evaluate the spread of wages paid within each classification to determine any evidence of discriminatory wage practices. c. The contractor will periodically review selected personnel actions in depth to determine whether there is evidence of discrimination. Where evidence is found, the contractor will promptly take corrective action. If the review indicates that the discrimination may extend beyond the actions reviewed, such corrective action shall include all affected persons. d. The contractor will promptly investigate all complaints of alleged discrimination made to the contractor in connection with its obligations under this contract, will attempt to resolve such complaints, and will take appropriate corrective action within a reasonable time. If the investigation indicates that the discrimination may affect persons other than the complainant, such corrective action shall include such other persons. Upon completion of each investigation, the contractor will inform every complainant of all of their avenues of appeal. 6. Training and Promotion: a. The contractor will assist in locating, qualifying, and increasing the skills of minorities and women who are applicants for employment or current employees. Such efforts should be aimed at developing full journey level status employees in the type of trade or job classification involved. b. Consistent with the contractor's work force requirements and as permissible under Federal and State regulations, the contractor shall make full use of training programs, i.e., apprenticeship, and on-the-job training programs for the geographical area of contract performance. In the event a special provision for training is provided under this contract, this subparagraph will be superseded as indicated in the special provision. The contracting agency may reserve training positions for persons who receive welfare assistance in accordance with 23 U.S.C. 140(a). c. The contractor will advise employees and applicants for employment of available training programs and entrance requirements for each. d. The contractor will periodically review the training and promotion potential of employees who are minorities and women and will encourage eligible employees to apply for such training and promotion. 7. Unions: If the contractor relies in whole or in part upon unions as a source of employees, the contractor will use good faith efforts to obtain the cooperation of such unions to increase opportunities for minorities and women. Actions by the contractor, either directly or through a contractor's association acting as agent, will include the procedures set forth below: a. The contractor will use good faith efforts to develop, in cooperation with the unions, joint training programs aimed toward qualifying more minorities and women for membership in the unions and increasing the skills of minorities and women so that they may qualify for higher paying employment. b. The contractor will use good faith efforts to incorporate an EEO clause into each union agreement to the end that such union will be contractually bound to refer applicants without regard to their race, color, religion, sex, national origin, age or disability. c. The contractor is to obtain information as to the referral practices and policies of the labor union except that to the extent such information is within the exclusive possession of the labor union and such labor union refuses to furnish such information to the contractor, the contractor shall so certify to the contracting agency and shall set forth what efforts have been made to obtain such information. d. In the event the union is unable to provide the contractor with a reasonable flow of referrals within the time limit set forth in the collective bargaining agreement, the contractor will, through independent recruitment efforts, fill the employment vacancies without regard to race, color, religion, sex, national origin, age or disability; making full efforts to obtain qualified and/or qualifiable minorities and women. The failure of a union to provide sufficient referrals (even though it is obligated to provide exclusive referrals under the terms of a collective bargaining agreement) does not relieve the contractor from the requirements of this paragraph. In the event the union referral practice prevents the contractor from meeting the obligations pursuant to Executive Order 11246, as amended, and these special provisions, such contractor shall immediately notify the contracting agency. 8. Reasonable Accommodation for Applicants / Employees with Disabilities: The contractor must be familiar with the requirements for and comply with the Americans with Disabilities Act and all rules and regulations established there under. Employers must provide reasonable accommodation in all employment activities unless to do so would cause an undue hardship. 9. Selection of Subcontractors, Procurement of Materials and Leasing of Equipment: The contractor shall not discriminate on the grounds of race, color, religion, sex, national origin, age or disability in the selection and retention of subcontractors, including procurement of materials and leases of equipment. The contractor shall take all necessary and reasonable steps to ensure nondiscrimination in the administration of this contract. a. The contractor shall notify all potential subcontractors and suppliers and lessors of their EEO obligations under this contract. b. The contractor will use good faith efforts to ensure subcontractor compliance with their EEO obligations. 10. Assurance Required by 49 CFR 26.13(b): a. The requirements of 49 CFR Part 26 and the State DOT's U.S. DOT -approved DBE program are incorporated by reference. b. The contractor or subcontractor shall not discriminate on the basis of race, color, national origin, or sex in the performance of this contract. The contractor shall carry out applicable requirements of 49 CFR Part 26 in the award and administration of DOT -assisted contracts. Failure by the contractor to carry out these requirements is a material breach of this contract, which may result in the termination of this contract or such other remedy as the contracting agency deems appropriate. 11. Records and Reports: The contractor shall keep such records as necessary to document compliance with the EEO requirements. Such records shall be retained for a period of three years following the date of the final payment to the contractor for all contract work and shall be available at reasonable times and places for inspection by authorized representatives of the contracting agency and the FHWA. a. The records kept by the contractor shall document the following: (1) The number and work hours of minority and non - minority group members and women employed in each work classification on the project; (2) The progress and efforts being made in cooperation with unions, when applicable, to increase employment opportunities for minorities and women; and (3) The progress and efforts being made in locating, hiring, training, qualifying, and upgrading minorities and women; b. The contractors and subcontractors will submit an annual report to the contracting agency each July for the duration of the project, indicating the number of minority, women, and non -minority group employees currently engaged in each work classification required by the contract work. This information is to be reported on Form FHWA-1391. The staffing data should represent the project work force on board in all or any part of the last payroll period preceding the end of July. If on-the-job training is being required by special provision, the contractor will be required to collect and report training data. The employment data should reflect the work force on board during all or any part of the last payroll period preceding the end of July. III. NONSEGREGATED FACILITIES This provision is applicable to all Federal -aid construction contracts and to all related construction subcontracts of $10,000 or more. The contractor must ensure that facilities provided for employees are provided in such a manner that segregation on the basis of race, color, religion, sex, or national origin cannot result. The contractor may neither require such segregated use by written or oral policies nor tolerate such use by employee custom. The contractor's obligation extends further to ensure that its employees are not assigned to perform their services at any location, under the contractor's control, where the facilities are segregated. The term "facilities" includes waiting rooms, work areas, restaurants and other eating areas, time clocks, restrooms, washrooms, locker rooms, and other storage or dressing areas, parking lots, drinking fountains, recreation or entertainment areas, transportation, and housing provided for employees. The contractor shall provide separate or single -user restrooms and necessary dressing or sleeping areas to assure privacy between sexes. IV. DAVIS-BACON AND RELATED ACT PROVISIONS This section is applicable to all Federal -aid construction projects exceeding $2,000 and to all related subcontracts and lower -tier subcontracts (regardless of subcontract size). The requirements apply to all projects located within the right-of- way of a roadway that is functionally classified as Federal -aid highway. This excludes roadways functionally classified as local roads or rural minor collectors, which are exempt. Contracting agencies may elect to apply these requirements to other projects. The following provisions are from the U.S. Department of Labor regulations in 29 CFR 5.5 "Contract provisions and related matters" with minor revisions to conform to the FHWA- 1273 format and FHWA program requirements. 1. Minimum wages a. All laborers and mechanics employed or working upon the site of the work, will be paid unconditionally and not less often than once a week, and without subsequent deduction or rebate on any account (except such payroll deductions as are permitted by regulations issued by the Secretary of Labor under the Copeland Act (29 CFR part 3)), the full amount of wages and bona fide fringe benefits (or cash equivalents thereof) due at time of payment computed at rates not less than those contained in the wage determination of the Secretary of Labor which is attached hereto and made a part hereof, regardless of any contractual relationship which may be alleged to exist between the contractor and such laborers and mechanics. Contributions made or costs reasonably anticipated for bona fide fringe benefits under section 1(b)(2) of the Davis -Bacon Act on behalf of laborers or mechanics are considered wages paid to such laborers or mechanics, subject to the provisions of paragraph 1.d. of this section; also, regular contributions made or costs incurred for more than a weekly period (but not less often than quarterly) under plans, funds, or programs which cover the particular weekly period, are deemed to be constructively made or incurred during such weekly period. Such laborers and mechanics shall be paid the appropriate wage rate and fringe benefits on the wage determination for the classification of work actually performed, without regard to skill, except as provided in 29 CFR 5.5(a)(4). Laborers or mechanics performing work in more than one classification may be compensated at the rate specified for each classification for the time actually worked therein: Provided, That the employer's payroll records accurately set forth the time spent in each classification in which work is performed. The wage determination (including any additional classification and wage rates conformed under paragraph 1.b. of this section) and the Davis -Bacon poster (WH -1321) shall be posted at all times by the contractor and its subcontractors at the site of the work in a prominent and accessible place where it can be easily seen by the workers. b.(1) The contracting officer shall require that any class of laborers or mechanics, including helpers, which is not listed in the wage determination and which is to be employed under the contract shall be classified in conformance with the wage determination. The contracting officer shall approve an additional classification and wage rate and fringe benefits therefore only when the following criteria have been met: (i) The work to be performed by the classification requested is not performed by a classification in the wage determination; and (ii) The classification is utilized in the area by the construction industry; and (iii) The proposed wage rate, including any bona fide fringe benefits, bears a reasonable relationship to the wage rates contained in the wage determination. (2) If the contractor and the laborers and mechanics to be employed in the classification (if known), or their representatives, and the contracting officer agree on the classification and wage rate (including the amount designated for fringe benefits where appropriate), a report of the action taken shall be sent by the contracting officer to the Administrator of the Wage and Hour Division, Employment Standards Administration, U.S. Department of Labor, Washington, DC 20210. The Administrator, or an authorized representative, will approve, modify, or disapprove every additional classification action within 30 days of receipt and so advise the contracting officer or will notify the contracting officer within the 30 -day period that additional time is necessary. (3) In the event the contractor, the laborers or mechanics to be employed in the classification or their representatives, and the contracting officer do not agree on the proposed classification and wage rate (including the amount designated for fringe benefits, where appropriate), the contracting officer shall refer the questions, including the views of all interested parties and the recommendation of the contracting officer, to the Wage and Hour Administrator for determination. The Wage and Hour Administrator, or an authorized representative, will issue a determination within 30 days of receipt and so advise the contracting officer or will notify the contracting officer within the 30 -day period that additional time is necessary. (4) The wage rate (including fringe benefits where appropriate) determined pursuant to paragraphs 1.b.(2) or 1.b.(3) of this section, shall be paid to all workers performing work in the classification under this contract from the first day on which work is performed in the classification. c. Whenever the minimum wage rate prescribed in the contract for a class of laborers or mechanics includes a fringe benefit which is not expressed as an hourly rate, the contractor shall either pay the benefit as stated in the wage determination or shall pay another bona fide fringe benefit or an hourly cash equivalent thereof. d. If the contractor does not make payments to a trustee or other third person, the contractor may consider as part of the wages of any laborer or mechanic the amount of any costs reasonably anticipated in providing bona fide fringe benefits under a plan or program, Provided, That the Secretary of Labor has found, upon the written request of the contractor, that the applicable standards of the Davis -Bacon Act have been met. The Secretary of Labor may require the contractor to set aside in a separate account assets for the meeting of obligations under the plan or program. 2. Withholding The contracting agency shall upon its own action or upon written request of an authorized representative of the Department of Labor, withhold or cause to be withheld from the contractor under this contract, or any other Federal contract with the same prime contractor, or any other federally - assisted contract subject to Davis -Bacon prevailing wage requirements, which is held by the same prime contractor, so much of the accrued payments or advances as may be considered necessary to pay laborers and mechanics, including apprentices, trainees, and helpers, employed by the contractor or any subcontractor the full amount of wages required by the contract. In the event of failure to pay any laborer or mechanic, including any apprentice, trainee, or helper, employed or working on the site of the work, all or part of the wages required by the contract, the contracting agency may, after written notice to the contractor, take such action as may be necessary to cause the suspension of any further payment, advance, or guarantee of funds until such violations have ceased. 3. Payrolls and basic records a. Payrolls and basic records relating thereto shall be maintained by the contractor during the course of the work and preserved for a period of three years thereafter for all laborers and mechanics working at the site of the work. Such records shall contain the name, address, and social security number of each such worker, his or her correct classification, hourly rates of wages paid (including rates of contributions or costs anticipated for bona fide fringe benefits or cash equivalents thereof of the types described in section 1(b)(2)(B) of the Davis -Bacon Act), daily and weekly number of hours worked, deductions made and actual wages paid. Whenever the Secretary of Labor has found under 29 CFR 5.5(a)(1)(iv) that the wages of any laborer or mechanic include the amount of any costs reasonably anticipated in providing benefits under a plan or program described in section 1(b)(2)(B) of the Davis - Bacon Act, the contractor shall maintain records which show that the commitment to provide such benefits is enforceable, that the plan or program is financially responsible, and that the plan or program has been communicated in writing to the laborers or mechanics affected, and records which show the costs anticipated or the actual cost incurred in providing such benefits. Contractors employing apprentices or trainees under approved programs shall maintain written evidence of the registration of apprenticeship programs and certification of trainee programs, the registration of the apprentices and trainees, and the ratios and wage rates prescribed in the applicable programs. b.(1) The contractor shall submit weekly for each week in which any contract work is performed a copy of all payrolls to the contracting agency. The payrolls submitted shall set out accurately and completely all of the information required to be maintained under 29 CFR 5.5(a)(3)(i), except that full social security numbers and home addresses shall not be included on weekly transmittals. Instead the payrolls shall only need to include an individually identifying number for each employee e.g. , the last four digits of the employee's social security number). The required weekly payroll information may be submitted in any form desired. Optional Form WH -347 is available for this purpose from the Wage and Hour Division Web site at http://www.dol.gov/esa/whd/forms/wh347instr.htm or its successor site. The prime contractor is responsible for the submission of copies of payrolls by all subcontractors. Contractors and subcontractors shall maintain the full social security number and current address of each covered worker, and shall provide them upon request to the contracting agency for transmission to the State DOT, the FHWA or the Wage and Hour Division of the Department of Labor for purposes of an investigation or audit of compliance with prevailing wage requirements. It is not a violation of this section for a prime contractor to require a subcontractor to provide addresses and social security numbers to the prime contractor for its own records, without weekly submission to the contracting agency.. (2) Each payroll submitted shall be accompanied by a "Statement of Compliance," signed by the contractor or subcontractor or his or her agent who pays or supervises the payment of the persons employed under the contract and shall certify the following: (i) That the payroll for the payroll period contains the information required to be provided under §5.5 (a)(3)(ii) of Regulations, 29 CFR part 5, the appropriate information is being maintained under §5.5 (a)(3)(i) of Regulations, 29 CFR part 5, and that such information is correct and complete; (ii) That each laborer or mechanic (including each helper, apprentice, and trainee) employed on the contract during the payroll period has been paid the full weekly wages earned, without rebate, either directly or indirectly, and that no deductions have been made either directly or indirectly from the full wages earned, other than permissible deductions as set forth in Regulations, 29 CFR part 3; (iii) That each laborer or mechanic has been paid not less than the applicable wage rates and fringe benefits or cash equivalents for the classification of work performed, as specified in the applicable wage determination incorporated into the contract. (3) The weekly submission of a properly executed certification set forth on the reverse side of Optional Form WH -347 shall satisfy the requirement for submission of the "Statement of Compliance" required by paragraph 3.b.(2) o' this section. (4) The falsification of any of the above certifications may subject the contractor or subcontractor to civil or criminal prosecution under section 1001 of title 18 and section 231 of title 31 of the United States Code. c. The contractor or subcontractor shall make the records required under paragraph 3.a. of this section available for inspection, copying, or transcription by authorized representatives of the contracting agency, the State DOT, the FHWA, or the Department of Labor, and shall permit such representatives to interview employees during working hours on the job. If the contractor or subcontractor fails to submit the required records or to make them available, the FHWA may, after written notice to the contractor, the contracting agency or the State DOT, take such action as may be necessary to cause the suspension of any further payment, advance, or guarantee of funds. Furthermore, failure to submit the required records upon request or to make such records available may be grounds for debarment action pursuant to 29 CFR 5.12. 4. Apprentices and trainees a. Apprentices (programs of the USDOL). Apprentices will be permitted to work at less than the predetermined rate for the work they performed when they are employed pursuant to and individually registered in a bona fide apprenticeship program registered with the U.S. Department of Labor, Employment and Training Administration, Office of Apprenticeship Training, Employer and Labor Services, or with a State Apprenticeship Agency recognized by the Office, or if a person is employed in his or her first 90 days of probationary employment as an apprentice in such an apprenticeship program, who is not individually registered in the program, but who has been certified by the Office of Apprenticeship Training, Employer and Labor Services or a State Apprenticeship Agency (where appropriate) to be eligible for probationary employment as an apprentice. The allowable ratio of apprentices to journeymen on the job site in any craft classification shall not be greater than the ratio permitted to the contractor as to the entire work force under the registered program. Any worker listed on a payroll at an apprentice wage rate, who is not registered or otherwise employed as stated above, shall be paid not less than the applicable wage rate on the wage determination for the classification of work actually performed. In addition, any apprentice performing work on the job site in excess of the ratio permitted under the registered program shall be paid not less than the applicable wage rate on the wage determination for the work actually performed. Where a contractor is performing construction on a project in a locality other than that in which its program is registered, the ratios and wage rates (expressed in percentages of the journeyman's hourly rate) specified in the contractor's or subcontractor's registered program shall be observed. Every apprentice must be paid at not less than the rate specified in the registered program for the apprentice's level of progress, expressed as a percentage of the journeymen hourly rate specified in the applicable wage determination. Apprentices shall be paid fringe benefits in accordance with the provisions of the apprenticeship program. If the apprenticeship program does not specify fringe benefits, apprentices must be paid the full amount of fringe benefits listed on the wage determination for the applicable classification. If the Administrator determines that a different practice prevails for the applicable apprentice classification, fringes shall be paid in accordance with that determination. In the event the Office of Apprenticeship Training, Employer and Labor Services, or a State Apprenticeship Agency recognized by the Office, withdraws approval of an apprenticeship program, the contractor will no longer be permitted to utilize apprentices at less than the applicable predetermined rate for the work performed until an acceptable program is approved. b. Trainees (programs of the USDOL). Except as provided in 29 CFR 5.16, trainees will not be permitted to work at less than the predetermined rate for the work performed unless they are employed pursuant to and individually registered in a program which has received prior approval, evidenced by formal certification by the U.S. Department of Labor, Employment and Training Administration. The ratio of trainees to journeymen on the job site shall not be greater than permitted under the plan approved by the Employment and Training Administration. Every trainee must be paid at not less than the rate specified in the approved program for the trainee's level of progress, expressed as a percentage of the journeyman hourly rate specified in the applicable wage determination. Trainees shall be paid fringe benefits in accordance with the provisions of the trainee program. If the trainee program does not mention fringe benefits, trainees shall be paid the full amount of fringe benefits listed on the wage determination unless the Administrator of the Wage and Hour Division determines that there is an apprenticeship program associated with the corresponding journeyman wage rate on the wage determination which provides for less than full fringe benefits for apprentices. Any employee listed on the payroll at a trainee rate who is not registered and participating in a training plan approved by the Employment and Training Administration shall be paid not less than the applicable wage rate on the wage determination for the classification of work actually performed. In addition, any trainee performing work on the job site in excess of the ratio permitted under the registered program shall be paid not less than the applicable wage rate on the wage determination for the work actually performed. In the event the Employment and Training Administration withdraws approval of a training program, the contractor will no longer be permitted to utilize trainees at less than the applicable predetermined rate for the work performed until an acceptable program is approved. c. Equal employment opportunity. The utilization of apprentices, trainees and journeymen under this part shall be in conformity with the equal employment opportunity requirements of Executive Order 11246, as amended, and 29 CFR part 30. d. Apprentices and Trainees (programs of the U.S. DOT). Apprentices and trainees working under apprenticeship and skill training programs which have been certified by the Secretary of Transportation as promoting EEO in connection with Federal -aid highway construction programs are not subject to the requirements of paragraph 4 of this Section IV. The straight time hourly wage rates for apprentices and trainees under such programs will be established by the particular programs. The ratio of apprentices and trainees to journeymen shall not be greater than permitted by the terms of the particular program. 5. Compliance with Copeland Act requirements. The contractor shall comply with the requirements of 29 CFR part 3, which are incorporated by reference in this contract. 6. Subcontracts. The contractor or subcontractor shall insert Form FHWA-1273 in any subcontracts and also require the subcontractors to include Form FHWA-1273 in any lower tier subcontracts. The prime contractor shall be responsible for the compliance by any subcontractor or lower tier subcontractor with all the contract clauses in 29 CFR 5.5. 7. Contract termination: debarment. A breach of the contract clauses in 29 CFR 5.5 may be grounds for termination of the contract, and for debarment as a contractor and a subcontractor as provided in 29 CFR 5.12. 8. Compliance with Davis -Bacon and Related Act requirements. All rulings and interpretations of the Davis - Bacon and Related Acts contained in 29 CFR parts 1, 3, and are herein incorporated by reference in this contract. 9. Disputes concerning labor standards. Disputes arising out of the labor standards provisions of this contract shall not be subject to the general disputes clause of this contract. Such disputes shall be resolved in accordance with the procedures of the Department of Labor set forth in 29 CFR parts 5, 6, and 7. Disputes within the meaning of this clause include disputes between the contractor (or any of its subcontractors) and the contracting agency, the U.S. Department of Labor, or the employees or their representatives. 10. Certification of eligibility. a. By entering into this contract, the contractor certifies that neither it (nor he or she) nor any person or firm who has an interest in the contractor's firm is a person or firm ineligible to be awarded Government contracts by virtue of section 3(a) of the Davis -Bacon Act or 29 CFR 5.12(a)(1). b. No part of this contract shall be subcontracted to any person or firm ineligible for award of a Government contract by virtue of section 3(a) of the Davis -Bacon Act or 29 CFR 5.12(a)(1). c. The penalty for making false statements is prescribed in the U.S. Criminal Code, 18 U.S.C. 1001. V. CONTRACT WORK HOURS AND SAFETY STANDARDS ACT The following clauses apply to any Federal -aid construction contract in an amount in excess of $100,000 and subject to the overtime provisions of the Contract Work Hours and Safety Standards Act. These clauses shall be inserted in addition to the clauses required by 29 CFR 5.5(a) or 29 CFR 4.6. As used in this paragraph, the terms laborers and mechanics include watchmen and guards. 1. Overtime requirements. No contractor or subcontractor contracting for any part of the contract work which may require or involve the employment of laborers or mechanics shall require or permit any such laborer or mechanic in any workweek in which he or she is employed on such work to work in excess of forty hours in such workweek unless such laborer or mechanic receives compensation at a rate not less than one and one-half times the basic rate of pay for all hours worked in excess of forty hours in such workweek. 2. Violation; liability for unpaid wages; liquidated damages. In the event of any violation of the clause set forth in paragraph (1.) of this section, the contractor and any subcontractor responsible therefor shall be liable for the unpaid wages. In addition, such contractor and subcontractor shall be liable to the United States (in the case of work done under contract for the District of Columbia or a territory, to such District or to such territory), for liquidated damages. Such liquidated damages shall be computed with respect to each individual laborer or mechanic, including watchmen and guards, employed in violation of the clause set forth in paragraph (1.) of this section, in the sum of $10 for each calendar day on which such individual was required or permitted to work in excess of the standard workweek of forty hours without payment of the overtime wages required by the clause set forth in paragraph (1.) of this section. 3. Withholding for unpaid wages and liquidated damages. The FHWA or the contacting agency shall upon its own action or upon written request of an authorized representative of the Department of Labor withhold or cause to be withheld, from any moneys payable on account of work performed by the contractor or subcontractor under any such contract or any other Federal contract with the same prime contractor, or any other federally -assisted contract subject to the Contract Work Hours and Safety Standards Act, which is held by the same prime contractor, such sums as may be determined to be necessary to satisfy any liabilities of such contractor or subcontractor for unpaid wages and liquidated damages as provided in the clause set forth in paragraph (2.) of this section. 4. Subcontracts. The contractor or subcontractor shall insert in any subcontracts the clauses set forth in paragraph (1.) through (4.) of this section and also a clause requiring the subcontractors to include these clauses in any lower tier subcontracts. The prime contractor shall be responsible for compliance by any subcontractor or lower tier subcontractor with the clauses set forth in paragraphs (1.) through (4.) of this section. VI. SUBLETTING OR ASSIGNING THE CONTRACT This provision is applicable to all Federal -aid construction contracts on the National Highway System. 1. The contractor shall perform with its own organization contract work amounting to not less than 30 percent (or a greater percentage if specified elsewhere in the contract) of the total original contract price, excluding any specialty items designated by the contracting agency. Specialty items may be performed by subcontract and the amount of any such specialty items performed may be deducted from the total original contract price before computing the amount of work required to be performed by the contractor's own organization (23 CFR 635.116). a. The term "perform work with its own organization" refers to workers employed or leased by the prime contractor, and equipment owned or rented by the prime contractor, with or without operators. Such term does not include employees or equipment of a subcontractor or lower tier subcontractor, agents of the prime contractor, or any other assignees. The term may include payments for the costs of hiring leased employees from an employee leasing firm meeting all relevant Federal and State regulatory requirements. Leased employees may only be included in this term if the prime contractor meets all of the following conditions: (1) the prime contractor maintains control over the supervision of the day-to-day activities of the leased employees; (2) the prime contractor remains responsible for the quality of the work of the leased employees; (3) the prime contractor retains all power to accept or exclude individual employees from work on the project; and (4) the prime contractor remains ultimately responsible for the payment of predetermined minimum wages, the submission of payrolls, statements of compliance and all other Federal regulatory requirements. b. "Specialty Items" shall be construed to be limited to work that requires highly specialized knowledge, abilities, or equipment not ordinarily available in the type of contracting organizations qualified and expected to bid or propose on the contract as a whole and in general are to be limited to minor components of the overall contract. 2. The contract amount upon which the requirements set forth in paragraph (1) of Section VI is computed includes the cost of material and manufactured products which are to be purchased or produced by the contractor under the contract provisions. 3. The contractor shall furnish (a) a competent superintendent or supervisor who is employed by the firm, has full authority to direct performance of the work in accordance with the contract requirements, and is in charge of all construction operations (regardless of who performs the work) and (b) such other of its own organizational resources (supervision, management, and engineering services) as the contracting officer determines is necessary to assure the performance of the contract. 4. No portion of the contract shall be sublet, assigned or otherwise disposed of except with the written consent of the contracting officer, or authorized representative, and such consent when given shall not be construed to relieve the contractor of any responsibility for the fulfillment of the contract. Written consent will be given only after the contracting agency has assured that each subcontract is evidenced in writing and that it contains all pertinent provisions and requirements of the prime contract. 5. The 30% self -performance requirement of paragraph (1) is not applicable to design -build contracts; however, contracting agencies may establish their own self -performance requirements. VII. SAFETY: ACCIDENT PREVENTION T h i s p r o v i s i o n i s applicable to all Federal -aid construction contracts and to all related subcontracts. 1. In the performance of this contract the contractor shall comply with all applicable Federal, State, and local laws governing safety, health, and sanitation (23 CFR 635). The contractor shall provide all safeguards, safety devices and protective equipment and take any other needed actions as it determines, or as the contracting officer may determine, to be reasonably necessary to protect the life and health of employees on the job and the safety of the public and to protect property in connection with the performance of the work covered by the contract. 2. It is a condition of this contract, and shall be made a condition of each subcontract, which the contractor enters into pursuant to this contract, that the contractor and any subcontractor shall not permit any employee, in performance of the contract, to work in surroundings or under conditions which are unsanitary, hazardous or dangerous to his/her health or safety, as determined under construction safety and health standards (29 CFR 1926) promulgated by the Secretary of Labor, in accordance with Section 107 of the Contract Work Hours and Safety Standards Act (40 U.S.C. 3704). 3. Pursuant to 29 CFR 1926.3, it is a condition of this contract that the Secretary of Labor or authorized representative thereof, shall have right of entry to any site of contract performance to inspect or investigate the matter of compliance with the construction safety and health standards and to carry out the duties of the Secretary under Section 107 of the Contract Work Hours and Safety Standards Act (40 U.S.C.3704). VIII. FALSE STATEMENTS CONCERNING HIGHWAY PROJECTS T h i s p r o v i s i o n i s applicable to all Federal -aid construction contracts and to all related subcontracts. In order to assure high quality and durable construction in conformity with approved plans and specifications and a high degree of reliability on statements and representations made by engineers, contractors, suppliers, and workers on Federal - aid highway projects, it is essential that all persons concerned with the project perform their functions as carefully, thoroughly, and honestly as possible. Willful falsification, distortion, or misrepresentation with respect to any facts related to the project is a violation of Federal law. To prevent any misunderstanding regarding the seriousness of these and similar acts, Form FHWA-1022 shall be posted on each Federal -aid highway project (23 CFR 635) in one or more places where it is readily available to all persons concerned with the project: 18 U.S.C. 1020 reads as follows: 'Whoever, being an officer, agent, or employee of the United States, or of any State or Territory, or whoever, whether a person, association, firm, or corporation, knowingly makes any false statement, false representation, or false report as to the character, quality, quantity, or cost of the material used or to be used, or the quantity or quality of the work performed or to be performed, or the cost thereof in connection with the submission of plans, maps, specifications, contracts, or costs of construction on any highway or related project submitted for approval to the Secretary of Transportation; or Whoever knowingly makes any false statement, false representation, false report or false claim with respect to the character, quality, quantity, or cost of any work performed or to be performed, or materials furnished or to be furnished, in connection with the construction of any highway or related project approved by the Secretary of Transportation; or Whoever knowingly makes any false statement or false representation as to material fact in any statement, certificate, or report submitted pursuant to provisions of the Federal -aid Roads Act approved July 1, 1916, (39 Stat. 355), as amended and supplemented; Shall be fined under this title or imprisoned not more than 5 years or both." IX. IMPLEMENTATION OF CLEAN AIR ACT AND FEDERAL WATER POLLUTION CONTROL ACT This provision is applicable to all Federal -aid construction contracts and to all related subcontracts. By submission of this bid/proposal or the execution of this contract, or subcontract, as appropriate, the bidder, proposer, Federal -aid construction contractor, or subcontractor, as appropriate, will be deemed to have stipulated as follows: 1. That any person who is or will be utilized in the performance of this contract is not prohibited from receiving an award due to a violation of Section 508 of the Clean Water Act or Section 306 of the Clean Air Act. 2. That the contractor agrees to include or cause to be included the requirements of paragraph (1) of this Section X in every subcontract, and further agrees to take such action as the contracting agency may direct as a means of enforcing such requirements. X. CERTIFICATION REGARDING DEBARMENT, SUSPENSION, INELIGIBILITY AND VOLUNTARY EXCLUSION This provision is applicable to all Federal -aid construction contracts, design -build contracts, subcontracts, lower -tier subcontracts, purchase orders, lease agreements, consultant contracts or any other covered transaction requiring FHWA approval or that is estimated to cost $25,000 or more — as defined in 2 CFR Parts 180 and 1200. 1. Instructions for Certification — First Tier Participants: a. By signing and submitting this proposal, the prospective first tier participant is providing the certification set out below. b. The inability of a person to provide the certification set out below will not necessarily result in denial of participation in this covered transaction. The prospective first tier participant shall submit an explanation of why it cannot provide the certification set out below. The certification or explanation will be considered in connection with the department or agency's determination whether to enter into this transaction. However, failure of the prospective first tier participant to furnish a certification or an explanation shall disqualify such a person from participation in this transaction. c. The certification in this clause is a material representation of fact upon which reliance was placed when the contracting agency determined to enter into this transaction. If it is later determined that the prospective participant knowingly rendered an erroneous certification, in addition to other remedies available to the Federal Government, the contracting agency may terminate this transaction for cause of default. d. The prospective first tier participant shall provide immediate written notice to the contracting agency to whom this proposal is submitted if any time the prospective first tier participant learns that its certification was erroneous when submitted or has become erroneous by reason of changed circumstances. e. The terms "covered transaction," "debarred," "suspended," "ineligible," "participant," "person," "principal," and "voluntarily excluded," as used in this clause, are defined in 2 CFR Parts 180 and 1200. "First Tier Covered Transactions" refers to any covered transaction between a grantee or subgrantee of Federal funds and a participant (such as the prime or general contract). "Lower Tier Covered Transactions" refers to any covered transaction under a First Tier Covered Transaction (such as subcontracts). "First Tier Participant" refers to the participant who has entered into a covered transaction with a grantee or subgrantee of Federal funds (such as the prime or general contractor). "Lower Tier Participant" refers any participant who has entered into a covered transaction with a First Tier Participant or other Lower Tier Participants (such as subcontractors and suppliers). f. The prospective first tier participant agrees by submitting this proposal that, should the proposed covered transaction be entered into, it shall not knowingly enter into any lower tier covered transaction with a person who is debarred, suspended, declared ineligible, or voluntarily excluded from participation in this covered transaction, unless authorized by the department or agency entering into this transaction. g. The prospective first tier participant further agrees by submitting this proposal that it will include the clause titled "Certification Regarding Debarment, Suspension, Ineligibility and Voluntary Exclusion -Lower Tier Covered Transactions," provided by the department or contracting agency, entering into this covered transaction, without modification, in all lower tier covered transactions and in all solicitations for lower tier covered transactions exceeding the $25,000 threshold. h. A participant in a covered transaction may rely upon a certification of a prospective participant in a lower tier covered transaction that is not debarred, suspended, ineligible, or voluntarily excluded from the covered transaction, unless it knows that the certification is erroneous. A participant is responsible for ensuring that its principals are not suspended, debarred, or otherwise ineligible to participate in covered transactions. To verify the eligibility of its principals, as well as the eligibility of any lower tier prospective participants, each participant may, but is not required to, check the Excluded Parties List System website (https://www.epis.ciov/), which is compiled by the General Services Administration. i. Nothing contained in the foregoing shall be construed to require the establishment of a system of records in order to render in good faith the certification required by this clause. The knowledge and information of the prospective participant is not required to exceed that which is normally possessed by a prudent person in the ordinary course of business dealings. j. Except for transactions authorized under paragraph (f) of these instructions, if a participant in a covered transaction knowingly enters into a lower tier covered transaction with a person who is suspended, debarred, ineligible, or voluntarily excluded from participation in this transaction, in addition to other remedies available to the Federal Government, the department or agency may terminate this transaction for cause or default. 2. Certification Regarding Debarment, Suspension, Ineligibility and Voluntary Exclusion — First Tier Participants: a. The prospective first tier participant certifies to the best of its knowledge and belief, that it and its principals: (1) Are not presently debarred,'suspended, proposed for debarment, declared ineligible, or voluntarily excluded from participating in covered transactions by any Federal department or agency; (2) Have not within a three-year period preceding this proposal been convicted of or had a civil judgment rendered against them for commission of fraud or a criminal offense in connection with obtaining, attempting to obtain, or performing a public (Federal, State or local) transaction or contract under a public transaction; violation of Federal or State antitrust statutes or commission of embezzlement, theft, forgery, bribery, falsification or destruction of records, making false statements, or receiving stolen property; (3) Are not presently indicted for or otherwise criminally or civilly charged by a governmental entity (Federal, State or local) with commission of any of the offenses enumerated in paragraph (a)(2) of this certification; and (4) Have not within a three-year period preceding this application/proposal had one or more public transactions (Federal, State or local) terminated for cause or default. b. Where the prospective participant is unable to certify to any of the statements in this certification, such prospective participant shall attach an explanation to this proposal. 2. Instructions for Certification - Lower Tier Participants: (Applicable to all subcontracts, purchase orders and other lower tier transactions requiring prior FHWA approval or estimated to cost $25,000 or more - 2 CFR Parts 180 and 1200) a. By signing and submitting this proposal, the prospective lower tier is providing the certification set out below. b. The certification in this clause is a material representation of fact upon which reliance was placed when this transaction was entered into. If it is later determined that the prospective lower tier participant knowingly rendered an erroneous certification, in addition to other remedies available to the Federal Government, the department, or agency with which 10 this transaction originated may pursue available remedies, including suspension and/or debarment. c. The prospective lower tier participant shall provide immediate written notice to the person to which this proposal is submitted if at any time the prospective lower tier participant learns that its certification was erroneous by reason of changed circumstances. d. The terms "covered transaction," "debarred," "suspended," "ineligible," "participant," "person," "principal," and "voluntarily excluded," as used in this clause, are defined in 2 CFR Parts 180 and 1200. You may contact the person to which this proposal is submitted for assistance in obtaining a copy of those regulations. "First Tier Covered Transactions" refers to any covered transaction between a grantee or subgrantee of Federal funds and a participant (such as the prime or general contract). "Lower Tier Covered Transactions" refers to any covered transaction under a First Tier Covered Transaction (such as subcontracts). "First Tier Participant" refers to the participant who has entered into a covered transaction with a grantee or subgrantee of Federal funds (such as the prime or general contractor). "Lower Tier Participant" refers any participant who has entered into a covered transaction with a First Tier Participant or other Lower Tier Participants (such as subcontractors and suppliers). e. The prospective lower tier participant agrees by submitting this proposal that, should the proposed covered transaction be entered into, it shall not knowingly enter into any lower tier covered transaction with a person who is debarred, suspended, declared ineligible, or voluntarily excluded from participation in this covered transaction, unless authorized by the department or agency with which this transaction originated. f. The prospective lower tier participant further agrees by submitting this proposal that it will include this clause titled "Certification Regarding Debarment, Suspension, Ineligibility and Voluntary Exclusion -Lower Tier Covered Transaction," without modification, in all lower tier covered transactions and in all solicitations for lower tier covered transactions exceeding the $25,000 threshold. g. A participant in a covered transaction may rely upon a certification of a prospective participant in a lower tier covered transaction that is not debarred, suspended, ineligible, or voluntarily excluded from the covered transaction, unless it knows that the certification is erroneous. A participant is responsible for ensuring that its principals are not suspended, debarred, or otherwise ineligible to participate in covered transactions. To verify the eligibility of its principals, as well as the eligibility of any lower tier prospective participants, each participant may, but is not required to, check the Excluded Parties List System website (htti)s://www.epls.gov/), which is compiled by the General Services Administration. h. Nothing contained in the foregoing shall be construed to require establishment of a system of records in order to render in good faith the certification required by this clause. The knowledge and information of participant is not required to exceed that which is normally possessed by a prudent person in the ordinary course of business dealings. i. Except for transactions authorized under paragraph a of these instructions, if a participant in a covered transaction knowingly enters into a lower tier covered transaction with a person who is suspended, debarred, ineligible, or voluntarily excluded from participation in this transaction, in addition to other remedies available to the Federal Government, the department or agency with which this transaction originated may pursue available remedies, including suspension and/or debarment. Certification Regarding Debarment, Suspension, Ineligibility and Voluntary Exclusion --Lower Tier Participants: 1. The prospective lower tier participant certifies, by submission of this proposal, that neither it nor its principals is presently debarred, suspended, proposed for debarment, declared ineligible, or voluntarily excluded from participating in covered transactions by any Federal department or agency. 2. Where the prospective lower tier participant is unable to certify to any of the statements in this certification, such prospective participant shall attach an explanation to this proposal. XI. CERTIFICATION REGARDING USE OF CONTRACT FUNDS FOR LOBBYING This provision is applicable to all Federal -aid construction contracts and to all related subcontracts which exceed $100,000 (49 CFR 20). 1. The prospective participant certifies, by signing and submitting this bid or proposal, to the best of his or her knowledge and belief, that: a. No Federal appropriated funds have been paid or will be paid, by or on behalf of the undersigned, to any person for influencing or attempting to influence an officer or employee of any Federal agency, a Member of Congress, an officer or employee of Congress, or an employee of a Member of Congress in connection with the awarding of any Federal contract, the making of any Federal grant, the making of any Federal loan, the entering into of any cooperative agreement, and the extension, continuation, renewal, amendment, or modification of any Federal contract, grant, loan, or cooperative agreement. b. If any funds other than Federal appropriated funds have been paid or will be paid to any person for influencing or attempting to influence an officer or employee of any Federal agency, a Member of Congress, an officer or employee of Congress, or an employee of a Member of Congress in connection with this Federal contract, grant, loan, or cooperative agreement, the undersigned shall complete and submit Standard Form -LLL, "Disclosure Form to Report Lobbying," in accordance with its instructions. 2. This certification is a material representation of fact upon which reliance was placed when this transaction was made or entered into. Submission of this certification is a prerequisite for making or entering into this transaction imposed by 31 U.S.C. 1352. Any person who fails to file the required certification shall be subject to a civil penalty of not less than $10,000 and not more than $100,000 for each such failure. 3. The prospective participant also agrees by submitting its bid or proposal that the participant shall require that the language of this certification be included in all lower tier subcontracts, which exceed $100,000 and that all such recipients shall certify and disclose accordingly. 11 ATTACHMENT A - EMPLOYMENT AND MATERIALS PREFERENCE FOR APPALACHIAN DEVELOPMENT HIGHWAY SYSTEM OR APPALACHIAN LOCAL ACCESS ROAD CONTRACTS This provision is applicable to all Federal -aid projects funded under the Appalachian Regional Development Act of 1965. 1. During the performance of this contract, the contractor undertaking to do work which is, or reasonably may be, done as on-site work, shall give preference to qualified persons who regularly reside in the labor area as designated by the DOL wherein the contract work is situated, or the subregion, or the Appalachian counties of the State wherein the contract work is situated, except: a. To the extent that qualified persons regularly residing in the area are not available. b. For the reasonable needs of the contractor to employ supervisory or specially experienced personnel necessary to assure an efficient execution of the contract work. c. For the obligation of the contractor to offer employment to present or former employees as the result of a lawful collective bargaining contract, provided that the number of nonresident persons employed under this subparagraph (1c) shall not exceed 20 percent of the total number of employees employed by the contractor on the contract work, except as provided in subparagraph (4) below. 2. The contractor shall place a job order with the State Employment Service indicating (a) the classifications of the laborers, mechanics and other employees required to perform the contract work, (b) the number of employees required in each classification, (c) the date on which the participant estimates such employees will be required, and (d) any other pertinent information required by the State Employment Service to complete the job order form. The job order may be placed with the State Employment Service in writing or by telephone. If during the course of the contract work, the information submitted by the contractor in the original job order is substantially modified, the participant shall promptly notify the State Employment Service. 3. The contractor shall give full consideration to all qualified job applicants referred to him by the State Employment Service. The contractor is not required to grant employment to any job applicants who, in his opinion, are not qualified to perform the classification of work required. 4. If, within one week following the placing of a job order by the contractor with the State Employment Service, the State Employment Service is unable to refer any qualified job applicants to the contractor, or less than the number requested, the State Employment Service will forward a certificate to the contractor indicating the unavailability of applicants. Such certificate shall be made a part of the contractor's permanent project records. Upon receipt of this certificate, the contractor may employ persons who do not normally reside in the labor area to fill positions covered by the certificate, notwithstanding the provisions of subparagraph (1c) above. 5. The provisions of 23 CFR 633.207(e) allow the contracting agency to provide a contractual preference for the use of mineral resource materials native to the Appalachian region. 12 6. The contractor shall include the provisions of Sections 1 through 4 of this Attachment A in every subcontract for work which is, or reasonably may be, done as on-site work. APPENDIX B Washington State Prevailing Wages Benefit Code Key State of Washington Department of Labor & Industries Prevailing Wage Section - Telephone 360-902-5335 PO Box 44540, Olympia, WA 98504-4540 Washington State Prevailing Wage The PREVAILING WAGES listed here include both the hourly wage rate and the hourly rate of fringe benefits. On public works projects, worker's wage and benefit rates must add to not less than this total. A brief description of overtime calculation requirements are provided on the Benefit Code Key. Journey Level Prevailing Wage Rates for the Effective Date: 03/14/2016 cougty. Trade Job Classification Waje HolidayOvertime Notel Kitsap aAsbestos Abatement Workers !Journey Level i $43.951 5D 1H Kitsap Boilermakers y Level Kitsap Kitsap 1Brick Mason Brick Mason ;Journey Level $52.82! 5A j Pointer -Caulker -Cleaner 1 $52.82, 5A j IM 1M Kitsap !Building Service Employees M !Janitor $9.471 Kitsap--i Building Service Employees ;Buildinp, Service Employees— IShampooer $9 * 47 .Kitsap ;Waxer $9.47 , Kitsap Fd -iul ing Service Employees . . . ....... Window Cleaner $13.22, Kitsap lCabinet Makers (in SbQW KitsapAcoustical Journey Level Worker $23.72; $54.02i 5D ---4—C ;Carpenters I Bridge, Dock And Wharf !Carpenters $54.02; 5D Kitsap Car enters Car enter $54.P�2 _Q 4C Kitsap Kitsap !Carpenters lCarpenters ,Carpenters on Stationary Tools Creosoted Material T-- $54.15* 5D $54.12, 5D 44C Kitsap :Carpenters_ p Floor Finisher $54.021 5D j 4C Kitsap .......... !Carpenters Floor Layer AC $54.021 4C Kitsap lCarp enters ......... iScaffold Erector $54.02 5D 1 4C Kitsap [Kitsap lCement Masons Journey Level $53.95. 7A M Divers Et Tenders Diver .$107.221 5D I 4C 8A . .. ........... Kitsap Et Tenders Diver On Standby ----- - i $64.421 5D 4C _jDivers Kitsap !Divers Et Tenders i Diver Tender $58.33 5D AC Kitsap Divers Et Tenders !Surface Rcv Et Rov Operator j $58.33 5D I 4C ... . ........ ..... Kitsap Divers Et Tenders Surface Rcv Et Rov Operator $54.27� 5A 4C Tender Kitsap IDredee Workers Assistant Engineer $56.44 5DT LF I !Kitsap Dredge Workers ;Assistant Mate (Deckhand) $56.00; 5D 3F —Lp— Dredge Workers men $56.�41 5D' LF Kitsap Dredge Workers ;Engineer Kitsap Dredge Workers ,Leverman, KitsapDredQe Workers ,Dredge Welder I - -- - Hydraulic Mates — $57.51; 5D - $58.671t 5D j $56.44; 5D ; 3F 1 3F 3F Kitsap Workers Oiler $56.00= 5D 3F Kitsap =Drywall Applicator _ ,Journey y-- -- _ Level_ —� J $54.02-5D 1H_ Kitsap Arywatt Tapers Kitsap iElectrical Fixture Maintenance Journey Level — Journey Level i $4.07 5P-- $31.74' JE .1 Y Workers Kitsap !Electricians - Inside lJourney Level $51.26 1 Kitsap !Electricians - Motor Shop——iCraftsman KitsapElectricians - Motor Sho� 'Journey _ -- �_^-- i Level —$14.691 $15.37; 1� 1 Kitsap .Electricians - Powerline Cable Splicer $74.921 5A 1 4D :Construction'-- Kitsap Electricians -Powerline ------- --_— '—�_ Certified Line Welder$65.71 1 5A — ' 4D — (Construction j Kitsap Electricians - Powerline Groundperson ; $44.12; 5A� 1 4D Construction - Kitsap Electricians - Powerline —_ ; Heavy Line Equipment i $65.711 5A I 4D—� Construction _ —4 Operator Kitsap Electricians - Powerline :Journey Level Lineperson $65.71; 5A 1 4D lConstruction ( _ Kitsap ;Electricians - Powerline Line Equipment Operator _ $55.34 5A 4D Construction Kitsap Electricians - Powerline ; Pole Sprayer �— $65.71; 5A ; 4D jConstruction Kitsap Electricians - Powerline 1 ---_—Construction-- Kitsap !Electronic Technicians Powderperson jJourney Level $49.16 -- $44.76; 5A — 7E 4D ! 1D i , Kitsap Elevator Constructors Mechanic $85.451 7D 4A Kitsap jElevator Constructors KitsapFabricated Precast Concrete iMechanic In Charge Journey Level - In-Factory ; $92.35, , $13.501 7D 4A 1 — Products _ — —Work Only — ' Kitsap ' Fence Erectors _ — Kitsap ;Fence Erector $13.801 1 Fence Erectors Fence Laborer $11.60—-1 Kitsap Kitsap ___i ._.._.___.._..--__...__..__.__.._______.___ :Flaggers —_-- (Glaziers 'Journey Level$37.26E— Journey Level - 7A , $56.16; 7L 31 1Y V - Kitsap SHeat it Frost Insulators And !Asbestos Workers Journeyman $63.181 5.1 1S Kitsap Heating Equipment Mechanics ---- Level Journey Level y $72.83 7F -- JE -- Kitsap KitsapIndl a_� HodCarriers ft Mason Tenders 'Hod Carriers ustrial Power Vacuum _ _ Journey Level Journey Level — -- '; $45.32; 7A $29.89 ' 31 1 Cleaner _ 3 I I Kitsap Inland Boatmen ;Boat Operator$56.781— 566^1K Kitsap Inland Boatmen Cook _ $53.301 5B 1K `Kitsap Inland Boatmen 1Deckhand 1 $53.30; 5B 1K Kitsap Inland Boatmen Deckhand Engineer 1 $54.32 5B 1K Kitsap- Inland Boatmen-�_ -.--iMate ,Launch Operator,�-$55.57 5B 1K i Kitsap!Inland Boatmen 1 $55 57. 5B 1K -- Kitsap Inspection/Cleaning/Sealing Of Cleaner Operator, Foamer i $9.73 1 k'Sewer Et Water Systems By 1Operator Remote Control Kitsap I n spection/Cleaning/Sealing 0 Grout Truck Operator $11.48; 1 1 Sewer Et Water Systems By Remote Control I I Kitsap ,Inspection/Cleaning/Sealing Of Head Operator--^ —� - ; $12.78; I 1 =Sewer Et Water Systems By i I Remote Control 1 I _ Kitsap Inspection/Cleaning/Sealing Of ITv Truck Operator ---- $24.17'- jSewer Et Water Systems By —� Remote Control Kitsap Applicators Journey Level $54.02; 5D 4C I _!Insulation Kitsap 1ronworkers KitsapjLaborers _^Journeyman $63.53: i ,Air, Gas Or Electric Vibrating $43.95 7N 7A 10 31 ; Kitsap Laborers ;Screed Airtrac Drill Operator j �$45.321 7A 31 Kitsap 1'Laborers - Kitsap- Laborers Ballast Regular Machine Batch Weighman $43.95; -$37.26; 7A - 31 I 7A € 31 € - -�-- -_-- -- KitsapjLaborers Brick Pavers I $43.95 7A 31 Kitsap�__ _ Laborers - - ....._...__. ___..._.._.__...... _._. r......__...____......___.......____-__ Brush CutterM $43.951 7A 31 Kitsap ;LaborersBrushg j er Feeder ed � $43.95; 7A 31 Kitsap Laborers _ _ Burner $43.951 7A Kitsap ,Laborers 'Caisson Kitsap Laborers Worker i $45.32; 7A 31 Carpenter Tender $43.951 7A� 31 l Kitsap ;Laborers !Caulker i $43.951 7A 31 Kitsap Laborers _ Cement Dumper-paving I $44.76 7A 1 ._..._.__....--- 31 ; Kitsap jLaborers _ €Cement Kitsap Laborers —Y ?Change Finisher Tender 1 $43.95: House Or Dry Shack _ $43.95; 7A € 31 7A 31 Kitsap 1 Laborers _ ;Chipping Gun (under 30 Lbs.) $43.951 7A ; 31 I Kitsap Laborers Chipping Gun(30 Lbs. And I $44.761 7A ! 31 Over) I i I Kitsap ,Laborers ____.__......._.___.......... Choker Setter ___ $43.95: 7A I 31 Kitsap Laborers ,Chuck Tender - - ! $43.95; 7A 31 Kitsap ;Laborers ;Clary Power Spreader $44.76; 7A I 31 Kitsap;Laborers ----'Concrete -Clean-up Laborer --� $43.95; 7A 31 [KitsapLaborers Du Dumper/chute Operator $44.76; I 7A € - 31 j KitsapLaborers__ Concrete Form Stripper ��$43 95 7A 31 a Kitsap jLaborers !Concrete Placement Crew i $44.761 7A 31 I I `Kitsap Laborers Concrete Saw Operator/core $44.76` 7A -31 f Dnller Kitsap =Laborers Kitsap I Laborers r Feeder Curing Laborer $37.26; I $43.95' 7A 31 I _ 7A 31 Kitsap ;Laborers !Demolition: Wrecking Et 1 $43.95; 7A i 31 1 Kitsap Laborers - ;Moving (incl. Charred Material), Ditch Digger $43.95 7A 31 -� Kitsap---Laborers_ -- Kitsap Laborers Diver Drill Operator f $45.32; 7A $44.76 7A 31 i 31 t Kitsap Laborers (hydraulic, diamond) Dry Stack• Walls $43.95; 7A 31-� Kitsap Laborers Dump Person -� _ j _ $43.95 7A Kitsap Laborers ;Epoxy Technician $43.951 7A + Kitsap Laborers Erosion Control Worker $43.95 7A - Laborers Et Bucker Chain Saw $44.761 7A 31 1 31 31 31 _ ,Kitsap Kitsap Laborers _.._____.____.-__._..____..-•-Fine ;Faller Graders—�---.�--.---- 1 $43.95! 7A %-�-_- —3i____._ _.._ Kitsap ILaborers �IFirewatch $37.26? 7A 31 } Kitsap 1 Laborers Form Setter $43.95 i -I TTGabian 7A 31 Kitsap Laborers _ Kitsap =rers �- ` Basket Builders -� General Laborer $43.95' 1 $43.95 7A 1 7A 31 31 Kitsap ;Laborers ,Grade Checker Et Transit $45.32 7A 31 1 � Kitsap Laborers Person Grinders - a __ $43.951 4 7A 31 Kitsap Laborers Grout Machine Tender $43.95_ 7A 1 31 i Kitsap Laborers Groutmen (pressure)including Post Tension Beams 1$44.761 ! 7A 31 l Kitsap ,Laborers Kitsap ( Laborers Guardrail Erector ! $43.95 Hazardous) Waste Worker (level $45.321 A 7A 7A 31 31 Kitsap ILaborers W -.'Hazardous Waste Worker (level; $44.764 E B) 7A ! 31 Kitsap Laborers - Hazardous Waste Worker (level ! $43.95 7A C) w 4 31 Kitsap_; Laborers _ Kitsap Laborers ��- _ _ High Scaler Jackhammer _$45.32; 7A �f $44.761 7A� 1 31 31 _ ° Kitsap Laborers Kitsap I Laserbeam Operator -'rMaintenance Person $44.76: 7A $43.A- 1 31 31 _Laborers �- ^-- Kitsap !Laborers Kitsap Laborers Manhole Builder-mudman d Per Material Yard n MaterialPerso $44.761 _ 7A $43.951 7A i - 31 � -' -- Kitsap !Laborers :Motorman-dinky Locomotive f_ $44.76. 7A � 31 Kitsap Laborers Nozzleman (concrete Pump, $44.761 7A 31 ►Green Cutter When Using ; 1 Combination Of High Pressure Air Et Water On Concrete Et 1 Rock, Sandblast, Gunite, 1 Shotcrete, Water Bla Kitsap Kitsap jLaborers� Laborers jPavement,Breaker„ Pilot Car L_-....__________�____ $44.76 7A $37.26 7A ! _ 31 31 1 - Kitsap Kitsap 1 Laborers borers _ ! Pipe Layer Lead Pipe Layer/tailor $45.321 $44.76 7A 7A I� 31 31 Kitsap Kitsap ? Laborers ! Pipe Pot Tender TLaborers Pipe Reliner $44.76; 7A 1 31 — 44.76 7A 31 Kitsap Kitsap Kitsa 11-aborers Laborers Pipe Wrapper $44.76` 7A 31 j �--_—__`---------+— Pot Tender $43.95 7A- 31—� Kitsap ; Laborers Powderman _ _ — i $45.32" 7A 31 i Kitsap Laborers Powderman's Helper $43.95! 7A 31 Kitsap Kitsap 1 Laborers Laborers Power Jacks $44.76 Railroad Spike Puller - Power $44.76 7A 7A ____...._...__..__._-.....__..._..___ 31 Kitsap Kitsap Laborers -- _ Laborers Raker - Asphalt _ Re-timberman — j $45.32 . 321 7A 7A 31-- 31 i 'Kitsap Kitsap 'Laborers Laborers iRemote Equipment Operator $44.76? 7A —31 Rigger/signal Person $44.76 7A 31 l Kitsap Kitsap Kitsap ; Laborers Laborers ! ' Laborers Rip Rap Person` $43.951 7A 31 Rivet Buster $44.761 7A 31 Rodder ; $44.761 7A 31 Kitsap , Laborers Scaffold Erector $43.95 7A I 31 I Kitsap ;Laborers 'Scale Person E $43.951 7A i 31 Kitsap _-...._.__-..__..�.___...._..____._._...--__.___.._._..._...__..._.._....__ Laborers Sloper (over 20") $44.761 _ 7A 31 Kitsap 1 Laborers . Sloper Sprayer = $43.954 7A 31 Kitsap — _ Laborers 'S reader concrete , 44.76 _ 7A �� 31 Kitsap j Laborers !Stake Hopper $43.95 7A i _ 31 —31 Kitsap Laborers ;Stock Piler $43.95 7A r s Kitsap Laborers Tamper Ft Similar Electric, Air $44.76; 7A _ 1 31 1 Gas Operated Tools ' Kitsap .._._TEt TLaborers Tamper (multiple £t Self- $44.76. 7A � propelled) Kitsap Laborers TTimber Person - Sewer (tagger, i $44.76; 7A 1 31 1 Shorer It Cribber) S 3 Kitsap Laborers 'Toolroom Person (at Jobsite) 1 $43.951 7A' ; 31 — KitsapTLaborers _.__. Topper 1 $43.951 _..... _7A — _._. _..... T 31 Kitsap .Laborers ;Track Laborer $43.951 7A i 31 1 Kitsap ;Laborers __._._..._ — Liner (power) _ $44.76' i 7A 31 1 Kitsap _ Laborers — ,!Track Traffic Control Laborer $39.841 7A — 31 1 8R p Kitsap =Laborers KitsapLaborers ........ _._ 'Traffic Control Supervisor ___——_ _.._—._P --_-- $39.84 — ---- 7A 31 _ i 8R i _ _ Truck Spotter $43.95 7A 31 I Kitsap �� Kitsap Laborers _ — _-- Laborers -- Tugger Operator — — — $4476 Tunnel Work -Compressed Air $74.29 7A 7A —_f — 31 — Kitsap Laborers -- 0-30 psi � ITunnet Work -Compressed Air 1 $79.321 'Worker 7A p 31 — 8� .•___._.—_. .._......... .—.---._....._._......._._._..______ 30.01-44.00 psi 1 Kitsap I Laborers Tunnel Work -Compressed Air $83.00 Worker 44.01-54.00 psi 7A ! 31 ' 84 IV LiGtH LQUVI CI Kitsap unnet WOO -Compresses Air )&s. /u /A 31 1 80 Worker 54.01-60.00 psi s T Tunnel Work -Compressed Air 1 $90.821 7A 31 i 3 1 Worker 60.01-64.00 psi Kitsap Laborers Tunnel Work -Compressed Air $95.92 7A 31 Worker 64.01-68.00 psi E Kitsap ;Laborers iTunnel Work -Compressed Air F $97.821 7A 318( Worker 68.01-70.00 psi E j Kitsap Laborers ;Tunnel Work -Compressed Air $99.821 7A 31 8� !Worker 70.01-72.00psi I [Kitsap ;Laborers Tunnel Work -Compressed Air 1$101.821 7A ; 31 8� Worker 72.01-74.00 psi I 1 Kitsap `Laborers 'Tunnel Work-Guage and Lock $45.422 7A �- 31 I Tender _......_... ....... _ KitsapM Laborers ^-_..__Y_...._......._._-_.....__._._..,.....Tunnel Work -Miner ���----!V $45.4214Y� 7A Yui 31 8� I Kitsap 'Laborers Vibrator $44.76; 7A 31 [Kitsap Laborers Vinyl Seamer $43.951 7A i 31 1 I Kitsap`. Laborers lWatchman $33.861 7A 31 Kitsap Laborers ;Welder $44.761 7A i !A 31 Kitsap ;Laborers ;Well Point Laborer $44.761 7A 31 Kitsap Laborers _ 'Window Washer/cleaner $33.861 7A 31 F Kitsap ;Laborers = Underground Sewer jGeneral Laborer Et Topman $43.95€ 7A 31 , 1 Et Water + Kitsap 'Laborers - Underground Sewer Pipe Layer $44.761 7A ; 31 , Et Water Kitsap ;Landscape Construction jIrrigation Or Lawn Sprinkler ; $9.471 1 1 Installers I Kitsap jLandscape Construction 'Landscape Equipment $10.051 1 I Operators Or Truck Drivers 4 + + KitsapSLandscape Construction 'Landscaping Or Planting $12.92; 1 I -, Laborers Kitsap (Lathers iIJOURNEY LEVEL $21 00! 1 ? - Kitsap ::Marble Setters ;Journey Level $52.82: 5A ; 1M Kitsap IMetal Fabrication (In Shop) Fitter $26.961Kitsap 'Metal Fabrication (In ShoplY� 1Laborer ? $9.47+ 1 Kitsap !Metal Fabrication (In Shop} IMachine Operator $13.83; Kitsap Metal Fabrication (In Shop) ;Welder _ $13.83; 1 i Kitsap Millwright __...__._.._....._...._............. _-`Journey Level -$44.89 1..__.__..;.-_---_-----i --�- _ _ ___ ___....__._----...- ..........._. _.-.-.--._..... __..._.._...-......----- ..._......_...-..__._.._......__..._._.._.�..------ ___.._ ._.........__.._. Kitsap !Modular Buildings iCabinet Assembly $11.56! 1 Kitsap Modular Buildings Electrician $11.56 ~�1- jKitsap {Modular BuitdinQs� __........... Equipment Maintenance ........1.- $11.561-�__�---�..�_...--1 ..............i Kitsap Modular Modular Buildings ;Plumber 1 $11.56; + Kitsap ±Modular Buildings ;Production Worker $9.47; 1 Kitsap =Modular Buildings Tool Maintenance $11.561 1 _ =Kitsap ;Modular Buildings Utility Person 1 $11.56 1 Kitsap Modular Buildings Welder $11.56; Kitsap `Painters :Journey Levet $39.35 `6Z 2B i ............... Kitsap ;Pile Driver •Journey Level $54271 5D 4C A Kitsap ;Plasterers Asphalt Plant Operators i $56.94' 7A 3C Journey Level $51.68; 74 1 R Kitsap__......._.._...._ : Playground Et Park Equipment _..._....__._....__._......____._....._._ Journey Level ..._.._._._�...__.___.........................._ ___.._.....__._.._ _ __.__..._._. f $9.47; 1 i ;Power Equipment Operators Power Equipment Operators 'Installers _.----_.----_____.....__._...___.._.._ ....... ...... _..... _;..__...._....._...._......_........ + $56.44;1, 7A ! 3C j 8P IKitsap ;Plumbers Et Pipefitters .... __-_.__.._........___.._ 'Journey Level _._.._.. _._...__.....___..._ ..._.__....._... ............. ............. .... ... __ ` $65.52 5A 1G 'Power Equipment Operators Power Eouipment Operators �Brokk Kitsap . !Power Eouipment Operators Asphalt Plant Operators i $56.94' 7A 3C 8P d IK itsap ; Power Equipment Operators Assistant Engineer $53.57; . 7A 3C 8P Kitsap Kitsap ;Power Equipment Operators Power Equipment Operators ;Barrier Machine (zipper) $56.441 7A 3C Batch Plant Operator, $56.44 7A 3C 8P 8P + $56.44;1, 7A ! 3C j 8P Concrete 'Tons With Attachments Kitsap Kitsap 'Power Equipment Operators Power Eouipment Operators �Brokk 3Bobcat i $53.57; 7A 3C - Remote Demolition $53.57 7A 3C +Equipment 8P 8P Kitsap !Power Eouipment Operators 'Brooms $53.57; 7A i 3C 8P Kitsap _...._._. __......__...._._....._.._...:....._...... _. – ............_-..__...__.. ..._.._._.—........_.....:-......._._...... Cutter I $56.44 7A 3C _.. --.... 8P Power Equipment Operators JBump Kitsap L. .. ;Kitsap Kitsap Power Eguigment Operators , Cableways $56.94! 7A 3C $56.44 7A 3C _..._...._i ;Compressor ' $53 57= 7A 3C 8P t 8P 8P ;Power Equipment Operators ;Chipper Power Equipment Operators Kitsap Power Equipment Operators Concrete Pump: Truck Mount i $56.94 7A 3C 8P With Boom Attachment Over !Attachments)f f �4-2 MM---- Finish Machine -laser $53.57; 7A i 3C 8P Kitsap Power Equipment Operators 3Comcrete ;Screed f Kitsap Power Equipment Operators Concrete Pump - Mounted Or $56.001 7A I 3C 8P Trailer High Pressure Line Pump, Pump High Pressure. Kitsap :Power Equipment Operators Concrete Pump: Truck Mount $56.44, 7A ' 3C ! 8P 'With 142m Boom Attachment Up To ' i p'Kitsap ;Power Equipment Operators ±Conveyors ' $56.00F 7A - 3C = 8P ! I Kitsap Power Equipment Operators !Cranes Friction: 200 tons and $58.67= 7A f 3C 8P (Kitsap ___..._...............__.._... _. ;Power Equipment ;over ___._........._..._..__.._._.-.,__..........,..__.3_.__........_...._......_..._....._...._.__._.._....--'_.-_'-.•-----.__.i..._....__._-----__....:..._..-........._.__......_...y......._.....__....._.__......__�..._._..._.._....._...__.4 Operators !Cranes: 20 Tons Through 44 + $56.44;1, 7A ! 3C j 8P 'Tons With Attachments f _.._..__........._. Kitsap -..__..._._.w_.__..__ ... ........ .._.... ....._..__..... -- 'Power Equipment Operators !Cranes: 100 Tons Through 199 ! $57.51: 7A 3C 8P s 'Tons, Or 150' Of Boom (Including Jib With 3 !Attachments)f f .Kitsap 1Power Equipment Operators Cranes: 200 tons- 299 tons, or ' $58.101 7A 3C 8P 250' of boom including jib ` i.- with attachments Kitsap Power Eouipment Operators (Cranes: 300 tons and over or f $58.67: 7A 3C 8P ;300' of boom including jib I !with attachments Kitsap Power Equipment Operators Cranes: 45 Tons Through 99 i $56.94` 7A 3C 8P Tons, Under 150' Of Boom i i (including Jib With { _ Attachments) I Kitsap 'Power Equipment Operators Cranes: A -frame - 10 Tons And' $53.57; 7A 3C 8P j i Under ' f i ` ; Kitsap ?Power Equipment Operators ithrough Cranes: Friction cranes $58.101 7A 199 tons ! i 3C 8P Kitsap Power Eouipment Operators Cranes: Through 19 Tons With I $56.001 7A Attachments A -frame Over 10 3C 8P - --- --- - —_ Tons Kitsap ;Power Equipment Operators Crusher _ $56.44 7A 3C s 8P Kitsap !Power Equipment Operators Deck Engineer/deck Winches $56.441 7A (Power)__.__--------..__.-----._ �—�___�-------- 3C �� 8P Kitsap iPower V Equipment Operators !Derricks, On Building Work i $56.941 7A 3C 8P Kitsap I Power Equipment Operators Dozers D-9 Et Under ; $56.00 7A 3C 8P Kitsap ;Power Equipment Operators Drill Oilers: Auger Type, Truck$56.00' 7A 3C s 8P Kitsap lOr Power Equipment Operators jDnlling Crane Mount Machine $57.51 7A 3C_ 8P Kitsap Power Equipment Operators Elevator And Man -lift: $53.57; 7A 1 3C 8P Kitsap Power Equipment Operators Permanent And Shaft Type Finishing Machine, Bidwell AndT $56.441 7A Gamaco Et Similar Equipment 3C 8P Kitsap Power Equipment Operators Forklift: 3000 Lbs And Over $56.00t 7A 3C 8P Kitsa-'Power Equipment Operators With Attachments _ Forklifts: Under 3000 Lbs. With $53.571 7A Attachments 3C .8P - Kitsap !Power Equipment Operators Grade Engineer: Using Blue j $56.44; 7A 3C 8P ,Kitsap Power Equipment Operators Prints, Cut Sheets, Etc Gradechecker/stakeman $53.57�i 7A 3C 8P Kitsap Power Equipment Operators :Guardrail Punch _ $56.441 7A — 3C 8P Kitsap Power Equipment Operators Hard Tail End Dump — $56.94 - 7A 3C 8P 'Articulating Off- Road aEquipment 45 Yards. Et Over Kitsap ---- ;Power Equipment Operators !Hard Tail End Dump ; $56.44; 7A 3C - 8P ;Articulating .Off-road ;Equipment Under 45 Yards ? Kitsap !Power Equipment Operators Horizontal/directional Drill $56.0011 7A Locator 3C 1 8P Kitsap Power Equipment Operators — !Horizontal/ directional Drill 1 $56.44` 7A- 3C ! 8P - Kitsap !Power Equipment Operators Operator i ----------__--- --- - Hydralifts/boom Trucks Over $56.00 7A - 3C --- 8P T--�— X10 Tons I Kitsap Power Equipment Operators 1 Hydralifts/ boom Trucks, 10 $53.57 7A 3C 8P #Tons And Under___ Kitsap Power Equipment Operators Loader, Overhead 8 Yards. Et i $57.51 7A Over 3C ~- _8P _ Kitsap 'I iPower Equipment OperatorsLoader, Overhead, 6 Yards. $56.94; 7A i 3C 8P _i Kitsap Power Equipment Operators 'But Not Including 8 Yards Loaders, Overhead Under 6 $56.44 7A 3C ! 8P Yards - — -8P Kitsap Kitsap !Power Equipment Operators Power Equipment Operators Loaders, Plant Feed _ _$56.44; 7A Loaders: Elevating Type Belt $56.00 7A 1 3C 3C - _ 8P Kitsap ;Power Equipment Operators ;Locomotives, All $56.441 7A 3C I 8P Kitsap !Power Equipment Operators Material Transfer Device ! $56.441' 7A 3C 8P Kitsap ! Power Equipment Operators Mechanics, All (leadmen - $57.51' 7A ; 3C ! 8P $0.50 Per Hour Over Mechanic); �+ _.94! Kitsap Power Equipment Operators Motor Patrol Graders $56 7A 3C 8P kKitsap ,Power Equipment Operators ;Mucking Machine, Mole, $56.94E 7A 3C i 8P !Tunnel Drill, Boring, Road r Header And/or Shield ! Kitsap ,Power Eguiqment Operators Oil Distributors, Blower $53.571' 7A ; 3C 8P Distribution Et Mulch Seeding Operator 1 ! kKitsap Power Equipment Operators (Outside Hoists (elevators And j $56.001 7A 3C 8P 3 Manlifts), Air Tuggers,strato Kitsap !Power Equipment i ! Operators Overhead, Bridge Type Crane: 20 Tons Through 44 Tons $56.441 ; 1. 7A 3C 8P I Kitsap ;Power Equipment Operators Overhead, Bridge Type: 100 $57.51: 7A 3C 8P ' ;Tons And Over ! Kitsap Power Equipment Operators :Overhead, Bridge Type: 45C $56.94 7A 3C —l8P i Kitsap 'Tons Through 99 Tons Kitsap !Power Equipment Power Equipment Operators Operators Pavement Breaker $53.57; Pile Driver (other Than Crane$56.441 7A 3C 7A 3C 8P 8P ! Mount) ! € I Kitsap !Power Equipment Operators I Plant Oiler - Asphalt, Crusher ':. $56.00 7A ! 3C 8P Kitsap!Poi wer Equipment Operators Posthole Digger, Mechanical ! $53.57 7A 3C f 8P Kitsap Kitsap ' Power Equipment Operators !Power Equipment Operators ' Power Plant Pumps - $53.57; ; $5_3.57 7A 3C 7A 3C ° 8P L8P 1 Kitsap Kitsap ;Power Equipment (Power Equipment _ Operators Operators _Wa_ter _ Quad 9, Hd 41, D10 And Over Quick Tower - No Cab, Under $56.941 f $53.57 7A 3C 7A ! 3C ( 8P 3 8P 100 Feet In Height Based To 3 I Boom Kitsap !Power Equipment Operators Remote Control Operator On ! $56.94 7A 3C 1 8P jRubber Tired Earth Moving IEquipm_ent Kitsap -Power E ui ment Operators _ q p p Rigger And Bellman gg i $53.57' —~ ��-- 7A i 3C — — 8P !Kitsap !Power Equipment Operators Rigger/Signal Person, Bellman (Certified) $56.00' 7A ! 3C ` 8P Kitsap Power Equipment Operators Rollagon`~ _ ~--'-- ! $56.94; 7A 3C ; 8P ' Kitsap ;Power Equipment !Roller, Other Than Plant Mix $53.57 7A Operators 3C- 4 8P Kitsap !P Eo Power quipment Operators Roller, Plant Mix Or Multi -lift $56.00 7A 3C j 8P Materials i i ! Kitsap ! Power Equipment Operators 1' Roto -mill, Roto -grinder ' $56.441 7A 1' 3C 8P Kitsap !Power Equipment Operators Saws - Concrete 1 $56.00! 7A 3C i 8P Kitsap Power Equipment OperatorsJScraper, Self Propelled Under $56.44 7A i 3C 8P i 145 Yards Kap Power Equipment Operators Scrapers - Concrete Et Carry A11.1' $56.001 7A 3C I 8P Kitsap 'Power Equipment Operators ':Scrapers, IYards.And Self-propelled: 45 ! $56.94; 7A 3C ! 8P Over Kitsap -Power Equipment Operators Service Engineers - Equipment $56.00; 7A 3C 8P Kitsap !Power Equipment Operators Shotcrete/gunite Equipment $53.57; 7A 3C ! 8P Kitsap 'Power Equipment Operators Shovel , Excavator, Backhoe, ! $56.001 7A i Under 15 Metric Tons. 3C 8P ' _Tractors - Kitsap !Power Equipment Operators Shovel, Excavator, Backhoe: $56.94: 7A 3C 8P jOver 30 Metric Tons To 50 F Metric Tons I 4 Kitsap��Poer Equipment Operators �Shovel, Excavator, Backhoes, $56.44 7A 3C i 8P Kitsap Equipment Operators Tractors: 15 To 30 Metric Tons Shovel, Excavator, Backhoes: $57.51 7A 3C 8P ;Power E , ;Over 50 Metric Tons To 90 # Metric Tons _ Kitsap 'Power Equipment Operators _ Shovel, Excavator, Backhoes: ; $58.10 A r 3C 8P ' Over 90 Metric Tons ; ! Kitsap 1Power Equipment Operators Slipform Pavers $56.94 7A 3C , Kitsap --- Power Equipment Operators _ - Spreader, Topsider Et ! $56.94 7A ------ - 3C - 8P -- 8P Screedman Kitsap jPower Equipment Operators FSubgrader Trimmer !__$56.441 7A I 3C 1 8P xKitsap Power Equipment Operators Tower Bucket Elevators $56.00 7A 3C 8P Kitsap Pow Equipment Operators Tower Crane Up To 175' In $57.51 7A 3C 8P Kitsap Power Equipment Operators !Height Base To Boom Tower Crane: over 175' _ $58.10 7A 3C 8P , through 250' in height, base to boom Kitsap 'Power Equipment Operators Tower Cranes: over 250' in $58.671 7A 3C 8P 'height from base to boom Kitsap ;Power Equipment Operators Transporters, All Track Or i $56.94 Truck Type 7A 3C 8P itsap _ !Power Eauipment_O_perators Trenching Machines_ $56.001' 7A — 3C j 8P [Kitsap +Power Equipment Operators Truck Crane Oiler/driver - 100 $56.44 7A 3C — Kitsap __ Power Equipment Operators _ Tons And Over Truck Crane Oiler/driver $56.00 7A 3C I ; Kitsap _!Under Power Equipment Operators- 100 Tons_ Truck Mount Portable $56.44 7A 3C 8P Kitsa!Power Equipment Operators Conveyor j ;'Welder $56 4949 7A i ! 8P Kitsap Power Equipment Operators Wheel Tractors, Farma_ l_l Type $53.57 - — 7A _� - _3C - 3C 8P Kitsap Kitsap Power Equipment Operators Power Equipment Operators- iYo Yo Pay Dozer— $56.44�Y Asphalt Plant Operators $56.947A 7A 3C 3C 8P 8P UnderQround Sewer Et Water i _ Kitsap !Power Equipment Operators- Assistant Engineer 1 $53.571 7A , 3C 8P _ Kitsap ' UnderQround Sewer Et Water jPower Equipment Operators- Underground Sewer Et Water _ Barrier Machine (zipper) $56.44 7A 3 i 3C 8P -- Kitsap 1Power Equipment Operators- IBatch Plant Operator, $56.44 7A i 3C — 8P _Underground Kitsap Sewer Et Water Power Equipment Operators- ;Concrete ---_-__— ; Bobcat $53.57 I 7A ; 3C 8P (Underground Sewer Et Water Kitsap ;Power Equipment Operators- }Brokk - Remote Demolition I $53.57 7A 3C 8P ----Underground Sewer Et Water 1Equipment� j i ,IKitsap 1Power Equipment Operators- ;Underground Sewer Et Water I Kitsap Power Equipment Operators- E 'Underground Sewer Et Water Kitsap !Power Equipment Operators- (Underground Sewer Et Water Kitsap ;Power Equipment Operators- ;Underground Sewer Et Water Kitsap (Power Equipment Operators- Underground Sewer Et Water Kitsap !Power Equipment Operators- !Underground Sewer Et Water Brooms I 'Bump Cutter Cableways ' !Chipper Compressor - _ T Concrete Pump: Truck Mount ! With Boom Attachment Over X42 M Concrete Finish Machine -laser ,Screed $53.571 $56.441; $56.94 1 $56.44 $53.57 i $56.94! i $53.571 7A 7A 7A 7A 7A-3C 7A 7A 3C ! 8P 3C 8P 3C 8P 3C 8P ! 8P 1 3C ! 8P ...______.__.__.._..�._.____._ ..._ ... 3C 8P I....... Kitsap Power Equipment Operators- Underground Sewer Et Water Kitsap SPower Equipment Operators- +Concrete Pump - Mounted Or $56.00; 7A ;— 3C 8P ;Underground Sewer Et Water ITrailer High Pressure Line F Kitsap ;Power Equipment Operators- 'Pump, Pump High Pressure. ! Concrete Pump: Truck Mount56 444 7A - , 3C 8P underground Sewer Et Water j g With B ! t Boom Attachment Up To ------------ ___Kitsap Power Equipment Operators- Kitsap 42m 1Conveyors $56.00; 7A , 3C = 8P Underground Sewer Et Water _.._._. _._.. Kitsap --..x__.._....____..._....__.._.... ..__ ..._._... _ _ ..... ..... !Power Equipment Operators- ;Underground Sewer Et Water -•................. __....... --._..._- ----- - : Cranes Friction: 200 tons and ' over ' - - - -- ---- $58.671 7A ------- ! 3C 8P Kitsap 'Power Equipment Operators- ;Cranes: 20 Tons Through 44 ; $56.44; 7A 3C 8P 1Underground Sewer Et Water Tons With Attachments Kitsap !Power Equipment Operators- Cranes: 100 Tons Through 199 $57.51 7A _ - -- 3C ! 8P Underground Sewer ft Water Tons, Or 150' Of Boom j (Including Jib With Attachments)I 1 Kitsap ;Power Equipment Operators- Cranes: 200 tons- 299 tons, or $58.101 7A ! 3C ¢ 8P !Underground Sewer Et Water ;250' of boom including jib ; ! (with attachments ! Kitsap !Power Equipment Operators. ]Cranes. 300 tons and over or _ -$58.671 7A - i - 3C _ �� -8P 1Undemround Sewer Et Water+300' of boom including jib !with attachments I ! + f Kitsap ;Power Equipment Operators- !Cranes: 45 Tons Through 99 $56.941 7A ! 3C '; 8P a ;Underground Sewer Eat Water jTons, Under 150' Of Boom j (including Jib With ! l d ;Attachments) 1 ;....—._____._._.._---...___._....-...._..._..__.___.._-._.._..r_.._.-_...._._.._..___.....-..___ Kitsap !Power Equipment Operators- ___........ _....... ___._..____,_..._._.._..._._.__.._..._._w.___.._•-_ Cranes: A-frame - 10 Tons And $53.571 7A ! 3C 8P ;Underground Sewer Et Water r Under pK� tsap Power Equipment Operators- Cranes: Friction cranes $58.10: 7A 3C 8P Kitsap Underground Sewer Et Water —+Power Equipment Operators- !through 199 tons Through 19 Tons With $56.00 7A 3C { 8P (Cranes: Underground Sewer Et Water Attachments A-frame Over 10 j (Tons 1 Kitsap Power Equipment Operators- !Crusher ! $56.441. 7A ! 3C ' 8P ;Underground Sewer Et Water , Kitsap 'Power N—� Kitsap ;Power Kitsap Equipment Operators- (Deck Underground Sewer Et Water �(power) Equipment Operators -Dei Underground Sewer Et Water Power Equipment Operators- (Dozers Underground Sewer Et Water Engineer/deck Winches I $56.44 rricks, On Building Work $56.941 D-9 Et Under $56.00 7A i 7A 7A i 3C 3C ! 3C i 8P 8P 8P Kitsap ;Power Equipment Operators- Drill Oilers: Auger Type, Truck $56.00; 7A 3C 8P 'Underground Sewer Et Water Or Crane Mount ! i Kitsap __-_........._.....-._.__...._.__-_ Power Equipment Operators- Drilling Machine $57.51' 7A 3C I 8P Underground Sewer Et Water Kitsap Power Equipment Operators- Elevator And Man -lift: $53.571 7A 3C 8P Underground Sewer Et Water Permanent And Shaft Type KitsapPower Equipment Operators- Finishing Machine, Bidwell And i $56.441 7A I� 3C 8P _ Kitsap Underground Sewer Et Water Power Equipment Operators- Gamaco Et Similar Equipment-� 3000 Lbs And Over $56.001 7A ! 1 3C — 8P Underground Sewer Et Water iForklift: 1 1With Attachments Kitsap Power Equipment Operators- Forklifts: Under 3000 Lbs. Withj $53.57 7A 3C 8P Underground Sewer Et Water Attachments li_T—_�- Kitsap _ jPower Equipment Operators- JGrade Engineer: Using Blue ! $56.441 7A 3C 8P Kitsap jUnderground Sewer Et Water iPower Equipment Operators. !Prints, Cut Sheets,'Etc _ radechecker/stakeman $53.57 7A 3C 8P Underground Sewer Et Water , Kitsap ;Power Equipment Operators- IGuardrail Punch $56.441 7A 3C 8P _ Kitsap 1 Underground Sewer Et Water _ Power _~--� Equipment Operators- }Underground Hard Tail End Dump $56.94 7A 3C 8P Sewer Et Water Articulating Off- Road Equipment 45 Yards. Et Over — Kitsap Power Equipment Operators- Underground Sewer Et Hard Tail End Dump 1 $56.44; 'Articulating 7A4 3C i 8P Water Off-road 1 Kitsap !Power Equipment Operators- (Underground Sewer Et Water Equipment Under 45 Yards Horizontal/directional Drill $56.00 Locator 7A j 3C 8P Kitsap Power Equipment Operators- `Horizontal/directional Drill $56.441 7A 3C 8P U_nderero_und Sewer Et Water !Operator _ -- -- Kitsap Power Equipment Operators-- Underground Sewer Et Water =_..._...._..-.- Hydralifts/boom Trucks Over $56.00 X10 Tons 7A --- 3C --- 8P Kitsap ;Power EquiQment Operators- Hydralifts/boom Trucks, 10 $53.571 7A 3C 8P - - _!Underground Kitsap Sewer Et Water, 1Power Equipment Operators- iTons And Under ^` Loader, Overhead 8 Yards. Et - $57.51 — 7A 3C 8P Kitsap Underground Sewer Et Water 'Power Over� _ ! _ Equipment Operators- (Underground Sewer Et Water Loader, Overhead, 6 Yards. $56.94; ;But Not Including 8 Yards 7A 3C 8P Kitsap Power Equipment Operators- Loaders, Overhead Under ( Underground Sewer Et Water 6 $56.441 Yards 7A 3C 8P Kitsap Kitsap -Power Power Equipment Operators- U nderground Sewer Et Water Equipment Operators- Loaders, Plant Feed $56.441 ! Loaders: Elevating Type Belt $56.00 7A ! 7A 3C 3C 4 8P + 8P Underground Sewer Et Water Kitsap ,Power Equipment Operators- ;Locomotives, All $56.441 7A 3C 8P Underground Sewer Et Water j Kitsap Power Equipment Operators- (Material Transfer Device ; $56.441 7A , --- 3C 8P (Underground Sewer Et Water j •.__...--_.._.—_-....._._....._._..._....._._.._.-_.—.______._..._.._..-....._.._..-. Kitsap I Power Equipment Operators- _._ .. ._..._._..._............._._.._.._.._............ .... -_.._.........--_._._....____..e..___._.._.__...._..J._._.-...,..____._._._..-__I IMechamcs, All (leadmen - I $57.51' 7A I ._._-...__._.._ 3C 8P ;Underground Sewer Et Water Kitsap Power Equipment Operators- —!Motor $0.50 Per Hour Over Mechanic);- Patrol Graders $ 9 A 8P 3C 8P Underground Underground Sewer Et Water Mucking Machine, Mole, $56.94; 7A ; 3C 8P Kitsap ;Power Equipment Operators- (Underground Sewer Et Water Tunnel Drill, Boring, Road i 'Header And/or Shield Kitsap Power Equipment Operators -Oil Underground Sewer Et Water IDistribution Distributors, Blower- Et Mulch Seeding $53.5711 7A i 3C 8P .__--- - -Operator Kitsap Power Equipment Operators- Outside Hoists (elevators And $56.00: 7A 11 3C 8P ;Underground Sewer Et Water 9Manlifts), Air Tuggers,strato Kitsap Power Equipment Operators- Overhead, Bridge Type Crane: $56.441 7A - 3C I 8P Underground Sewer Et Water '20 Tons Through 44 Tons j Kitsap Power Equipment Operators- Overhead, Bridge Type: 100 $57.51; 7A 3C 8P Underground Sewer Et Water iTons And Over 1 Kitsap 'Power Equipment Operators- Overhead, Bridge Type: 45 $56.941 7A 3C �— 8P Underground Sewer Et Water Tons Through 99 Tons i E Kitsap !Power Equipment Operators- 'Pavement Breaker $53.57; 7A 3C 8P IUnderground Sewer Et Water Kitsap ;Power Equipment Operators- Pile Driver (other Than Crane j $56.441 7A 3C 8P _ 'Underground Sewer Et Water Mount) Kitsap ;Power Equipment Operators- Plant Oiler - Asphalt, Crusher $56.00; 7A 3C 8P 1Underground Sewer Et Water Kitsap Power Equipment Operators- Posthole Digger, Mechanical $53.57i 7A 3C 8P 3Underground Sewer Et Water Kitsap 1Power Equipment Operators- Power Plant r $53.57: 7A 3C 8P ;Underground Sewer Et Water Kitsap 'Power Equipment Operators- Pumps - Water I $53.57] 7A i 3C j 8P Underground Sewer Et Water _ _ ' � — ___1 i _---_- Kitsap ;Power Equipment Operators- lQuad 9, Hd 41, D10 And Over $56.94( 7A 3C 8P 1 Underground Sewer Et Water _11 _. Kitsap p Power Eouipment 0 erators- p Quick Tower - No Cab, Under $53.5711- 7A4 3C.._....._._i_.___8P ;Underground Sewer Et Water 100 Feet In Height Based To I j I Boom Kitsap Power Equipment Operators- 'Remote Control Operator On $56.94; 7A ; 3C ` 8P {Underground Sewer Et Water Rubber Tired Earth Moving i s Equipment Kitsap— Power Equipment Operators-- Underground Sewer Et Water iRigger And Bellman �- 1 ! $53.571 7A i 3C ; 8P i EKitsap tPower Equipment Operators- Rigger/Signal Person, Bellman $56.00; 7A 3C 8P (Under round Sewer Et Water g � (Certified) Kitsap (Power Equipment Operators- Rollagon $56.94 7A 3C I 8P 'Underground Sewer Et Water i Kitsap 'Power Equipment Operators- Roller, Other Than Plant Mix i I $53.5717A ; 3C 8P iUnderground Sewer Et Water 'Kitsap 'Power Equipment Q?erators- Roller, Plant Mix Or Multi -lift $56.00; 7A 3C 8P !Underground Sewer Et Water !Materials !Kitsap 'Power Equipment Operators `Roto -mill, Roto -grinder $56.44; .7A i 3C 8P R ;Underground Sewer Et Water Kitsap ;Power Equipment Operators- !!Saws - Concrete ! $56.001 7A ' 3C E 8P i 'Underground Sewer Et Water ( ' Kitsap i Power Equipment Operators- Scraper, Self Propelled Under $56.44 7A 3C 8P Underp-round Sewer Et Water 45 Yards ' Kitsap 'Power Equipment Operators- :Scrapers - Concrete Et Carry Alli $56.001 7A 3C 8P ! Underground Sewer Et Water IKitsapm IPower Equipment Operators- ;Scrapers, Self-propelled: 45 1 $56.94! 7A ' 3C 8P ;Underground Sewer Et Water ;Yards And Over Kitsap !Power Equipment Operators- (Service Engineers - Equipment $56.001 7A 3C 8P i !Underground Sewer Et Water ! ! .- ----------- �_.-._......__. __.1 Kitsap ;Power Equipment Operators- ;Shotcrete/gunite Equipment $53.57; 7A 3C 8P s :Underground Sewer Et Water ! ! 3 � Kitsap _ Power Equipment Operators- Shovel , Excavator, Backhoe, $56.001 7A 3C 8P i Underground Sewer Et Water ;Tractors Under 15 Metric Tons. ! Kitsap Power Equipment Operators- !Shovel, Excavator, Backhoe: $56.94 7A 3C j 8P l Underground Sewer Et Water jOver 30 Metric Tons To 50 i Metnc Tons ------ _...... ._..__..__._.__ Kitsap Power Equipment Operators- §Shovel, Excavator, Backhoes, $56.44; 7A 3C ; 8P !Underground Sewer Et WaterTractors: 15 To 30 Metric Tons ! j Kitsap Power Equipment Operators- IShovel, Excavator, Backhoes: $57.51 7A 3C 8P Underground Sewer Et Water Over 50 Metric Tons To 90 ! _ Metric Tons Kitsap !Power Equipment Operators- IShovel, Excavator, Backhoes: 8 101 7A ` 3C 8P� (Underground Sewer Et Water 'Over 90 Metric Tons ! ' Kitsap Kitsap !Power Equipment Operators- _ !Underground Sewer Et Water Kitsap 'Power Equipment Operators- Kitsap �Slipform Pavers $56.94; 7A } 3C 8P Spreader, Topsider Et i $56.941 7A 1 3C 8P Screedman _ .-._.__...._..._.___......... ..._._�_._;____._ Subgrader Trimmer ' $56.44' 7A 3C 8P Tower Bucket Elevators Kitsap ;Power Equipment Operators - Tower Crane Up To 175' In Underground Sewer Et Water Height Base To Boom Kitsap !Power Equipment Operators- 'Tower Crane: over 175' 'Unde[ground Sewer Et Water !through 250' in height, base to _......... _-_-.___ ! ........ _ _...__.._._...._. ' boom Kitsap 'Power Equipment Operators- !Tower Cranes: over 250' in fUndereround Sewer Et Water !height from base to boom Kitsap !Power Equipment Operators- !Transporters, All Track Or !Truck Underground Sewer Et Water Type Kitsap 'Power Equipment Operators- 'Trenching Machines Kitsap Power Equipment Operators - Underground Sewer Et Water Kitsap 'Power Equipment Operators- ! 3 $56.00! 7A 3C i 8P i $57.51; 7A 3C 8P ! $58.10' 7A 3C ! 8P $58.67° 7A 3C 1 8P $56.941 7A ! 3C 8P $56.00' 7A 3C ! 8P ! Truck Crane Oiler/driver - 100 ! $56.44! 7A J 3C Tons And Over ! j Truck Crane Oiler/driver $56.001 7A 3C 8P 8P I Underground Sewer Et Water lUnder 100 Tons ... . ...... - Kitsap ::Power Equipment Operators- Truck Mount Portable 1 $56.44� 7A 3C f LP jUnderground Sewer Et Water Conveyor Kitsap Power Equipment Operators- Welder $56.94 7A 3C 8P Underground Sewer Et Water ....... .. . .. Kitsap Power Equipment Operators- jWheel Tractors, Farmall Type $53.57£ 7A 3C 8P 'Underground Sewer Et Water Kitsap Power Equipment Ooerators- Yo Yo Pay Dozer ly$56.44j 7A T 3C 8P Underground Sewer Et Water Kitsap ;Power Line Clearance Tree 'Journey Level In Charge $45.75 5A 4A Trimmers Kitsap Power Line Clearance Tree Spray Person i $43.381 5A AA 1 Trimmers ........... Kitsap Power Line Clearance Tree ee Equipment Operator $45.75i 5A 4A -7 i;Trimmers Kitsap Power Line Clearance Tree Tree Trimmer $40.84i 5A AA jTrimmers !Kitsap ;Power Line Clearance Tree !Tree Trimmer Groundperson $30.744 5A 4A !Trimmers ;Kitsap ;Refrigeration Et Air Mechanic $65.524 5A 1G !Conditioning Mechanics Kitsap 'Residential Brick Mason !Journey Level $17.044 Kitsap Residential Carpenters lJourney Level j $40.66' 5D 4C .... ........ . . .... . .... . .... Kitsap Residential Cement Masons �Journey Level $30.87; i 1 !Kitsap 'Residential Drywall Applicators :Journey Level $40.641 5D 4C Kitsap !Residential Drywall Tapers lJourney Level $20.001 ... ....... .. ...... ....... Kitsap �Residential Electricians 'Journey Level $27.00 1 Kitsap t Glaziers liournev Level 556.16; R IY --, en Kitsap Residential Insulation lApplicators Journey Level $13.96 jKitsap ;'Residential Laborers 'Journey Level $16.89f.; . . . .... . ......... ,Kitsap 'Residential Marble Setters `Journey Level $17.04: $19.52 Kitsap ;Residential Painters Journey Level ...... " i -is a'- p "kes'-i. ... .. . ..... -dential :Ki.. Plumbers Et Journey Level $21.11k Pil?efitter . . ........ Kitsap ;Residential Refrigeration Et Air Journey Level $17.64t !Conditioning Mechanics Kitsap 'Residential Sheet Metal Workers Journey Level (Field or Shop) i $28.W , 'Kitsap Residential Soft Floor Layers ;Journey Level $19.38 ;Kitsap Residential Sprinkler Fitters Journey Level $27.74' (Fire Protection ti on) ----- ---------- - ---------------- Kitsap I Residential Stone Masons gurney Level $52.82 5A 1M (Kitsap :'Residential Terrazzo Workers Journey Level $9.47 Kitsap Residential Terrazzo/Tile Journey Level $30.261 Finishers Kitsap !Residential Tile Setters fJourney Level $31.141 ,Kitsap RoofersJourney Level $46.461 5A 3H E .. . ......... .. ....... . ........ . .... . Kitsap =Roofers -µ Kitsap Using Irritable Bituminous i $48.711 1 Materials ! Kitsap =Sheet Metal Workers Journey Level (Field or Shop) i $72.83 Kitsap 'Shipbuilding Et Ship Repair _ _1 ;CARPENTER $19.29; Kitsap _._..,._......._..........._.._........_.._._._................_......_....._...._.._..._._...._..... =Shipbuilding Et Ship Repair {ELECTRICIAN $25.53: _--_..._._._._..._-....—..__._..__......_.__.__._...__.._.... .w._.._.......__......� Kitsap ;Shipbuilding Et Ship Repair ;Heat Et Frost Insulator $6_3.187 Kitsap ;Shipbuilding Et Ship Repair ,Laborer �— _ _ _ Yi $19.64 Kitsap ;Shipbuilding Et Ship Repair ;MACHINIST $19.29; Kitsap 'Shipbuilding Et Ship Repair !OPERATOR$19.441 • Kitsap ;Shipbuilding Et Ship Repair; Painter. $39.35e Kitsap Shipbuilding Et Ship Repair IPIPEFITTER $19.29; Kitsap ;Shipbuilding Et Ship Repair TRIGGER $19.29; _ ..__......_..._. Kitsap ;Stone Masons Journey Level IStreet And Parkinp- Lot ourney Level Sweeper J _....,...._._._..._....._...,..._. ___ [Shipbuilding Et Ship _._.... _, ,..._........_...._..3.._.._..._.. _ _ ..__,__._., ..__ _..__. ....�_. __._._._......Y..._ Repair ;Sheet Metal ...... .... -.._...._..�._ i Kitsap 'Shipbuilding _$22.21 Et Ship Repair S iIPFITTER$19.29 5A 3H 7F1E ' 1 ' 1 ...... 5 J 15 } • 1 ! 1 _6Z 2B _ 1 � 1 1 � ___ Kitsap _ _.._._.____..__.._.._..,.._._.._...__.._..____.._..___._.._...__._._._-._.__.,.—..__.__..._ - ____t _..._._._.._ .:......................_. ....... �...__.____ Shipbuildin Et�Ship Repair WELDER/BURNER $19.29 i 1 -µ Kitsap Sign Makers Et Installers ;Journey Level IE $20.58! 1 (Electrical) ! i Kitsap Sign Makers Et Installers (Non- Journey Level $9.47; i 1 r Electrical) Kitsap `Soft Floor Layers Journey Level .... _.... .... $44.11 I 5A 7 3D_ _ Kitsap Solar Controls For Windows Journey Level ._.I...._...__,__._.__... ; $10.311 Kitsap ;Sprinkler Fitters (Fire 'Journey Level $70.14= 5C 1X ;Protection) _ Kitsap iStage Rigging Mechanics (Non _ Journey Level—�- $13.23 1 Structural) Kitsap Kitsap ;Stone Masons Journey Level IStreet And Parkinp- Lot ourney Level Sweeper J € $52.82': 5A I i $16.00 1M 3 Kitsap ; Workers ;Surveyors Assistant Construction Site $56.00; 7A 3C 8P i Surveyor Kitsap ),Surveyors Chainman $55.471 7A ! 3C i 8P Kitsap YSurveyors ;Construction Site Surveyor $56.94; 7A j 3C 8P $Kitsap (Telecommunication ;Journey Level $43.327 7E 1JE ! 'Technicians 7 _. ~ lCable - "~$37.60; �5A .. µ 2B ..___....___� Kitsap ;Telephone Line Construction - SplicerV Outside E Kitsap !Telephone Line Construction - 'Hole Digger/Ground Person I $20.79; 5A 2B _ Kitsap ;Outside ;Telephone Line Construction - Installer (Repairer) ! Outside t $36.02f { 5A 1 2B s_..__.__..._T.._.i.......___..__-------_..._.._.._._. (Kitsap !Telephone Line Construction - ;Special Aparatus Installer 1 $37.60; 5A _.. 2B !Outside Kitsap Telephone Line Construction - Special Apparatus Installer II $36.82 8 T 5A 2B Outside i Kitsap ;Telephone Line Construction - Telephone Equipment Operator; $37.60; 5A c 2B f i ?Outside (Heavy) ! Kitsap (Telephone Line Construction - Telephone Equipment Operator $34.941 Outside (Light) I 5A 2B Kitsap !Telephone Line Construction - ;Telephone Lineperson $34.93± 5A 2B ; ,Outside Kitsap Telephone Line Construction - Television Groundperson s' $19.73 ! 5A 2B _ Outside Kitsap Line Construction - {Television Lineperson/Installer $26.31 5A 2B 'Outside `Outside Kitsap Telephone Line Construction - Television System Technician f $31.501 5A 2B I Outside Kitsap ;Telephone Line Construction - :Television Technician $28.23: 5A 2B I 'Outside ITelephone Line Construction - Kitsap Tree Trimmer;; $' 34.931 5A 2B Outside s Kitsap :Terrazzo Workers Journe Level y $47.461 5A 5A 1 M 1M , Kitsap 'Tile Setters Journey Level $47.46 (Kitsap Tile. Marble Et Terrazzo 'Finishers Journey Level $12.00= 1 j Kitsap Traffic Control Stri ers JourneyLl _eve$43.731 7A 1K Kitsap ;Truck Drivers :Asphalt u Mix Over 16 Yards (W. $51.251 5D 3A 8L ,WA Kitsap ITruck Drivers -Joint Council 28) Asphalt Mix To 16 Yards (W. $50.41 5D 3A 8L WA -Joint Council 28 Kitsap !Truck Drivers ;Dump :_._...._...__........._� Truck $19.60— i 1 -Kitsap :Truck Drivers Dump Truck And Trailer $19.60 1 Kitsap 1Truck Drivers Other Trucks $18.37! 1 Kitsap Truck Drivers Transit Mixer $20.79. 1 Kitsap Well Drillers Et Irrigation Pump ;Irrigation Pump Installer $13.17; 1 Installers l i Kitsap Well Drillers Et Irrigation Pump Oiler j $14.08 1 Installers ?Kitsap Nell Drillers Et Irrigation Pump ,Well Driller $14.40' 1 t ?Installers : a ._._:.... .....:.,_,:e__:-......���.::a...��.:a.,��.. ,�-,_......,�.... __.-.......< Benefit Code Key — Effective 3/2/2016 thru 8/30/2016 Overtime Codes Overtime calculations are based on the hourly rate actually paid to the worker. On public works projects, the hourly rate must be not less than the prevailing rate of wage minus the hourly rate of the cost of fringe benefits actually provided for the worker. ALL HOURS WORKED IN EXCESS OF EIGHT (8) HOURS PER DAY OR FORTY (40) HOURS PER WEEK SHALL BE PAID AT ONE AND ONE-HALF TIMES THE HOURLY RATE OF WAGE. B. All hours worked on Saturdays shall be paid at one and one-half times the hourly rate of wage. All hours worked on Sundays and holidays shall be paid at double the hourly rate of wage. C. The first two (2) hours after eight (8) regular hours Monday through Friday and the first ten (10) hours on Saturday shall be paid at one and one-half times the hourly rate of wage. All other overtime hours and all hours worked on Sundays and holidays shall be paid at double the hourly rate of wage. D. The first two (2) hours before or after a five -eight (8) hour workweek day or a four -ten (10) hour workweek day and the first eight (8) hours worked the next day after either workweek shall be paid at one and one-half times the hourly rate of wage. All additional hours worked and all worked on Sundays and holidays shall be paid at double the hourly rate of wage. E. The first two (2) hours after eight (8) regular hours Monday through Friday and the first eight (8) hours on Saturday shall be paid at one and one-half times the hourly rate of wage. All other hours worked Monday through Saturday, and all hours worked on Sundays and holidays shall be paid at double the hourly rate of wage. The first two (2) hours after eight (8) regular hours Monday through Friday and the first ten (10) hours on Saturday shall be paid at one and one-half times the hourly rate of wage. All other overtime hours worked, except Labor Day, shall be paid at double the hourly rate of wage. All hours worked on Labor Day shall be paid at three times the hourly rate of wage. G. The first ten (10) hours worked on Saturdays and the first ten (10) hours worked on a fifth calendar weekday in a four -ten hour schedule, shall be paid at one and one-half times the hourly rate of wage. All hours worked in excess of ten (10) hours per day Monday through Saturday and all hours worked on Sundays and holidays shall be paid at double the hourly rate of wage. H. All hours worked on Saturdays (except makeup days if work is lost due to inclement weather conditions or equipment breakdown) shall be paid at one and one-half times the hourly rate of wage. All hours worked Monday through Saturday over twelve (12) hours and all hours worked on Sundays and holidays shall be paid at double the hourly rate of wage. All hours worked on Sundays and holidays shall also be paid at double the hourly rate of wage. The first two (2) hours after eight (8) regular hours Monday through Friday and the first ten (10) hours on Saturday shall be paid at one and one-half times the hourly rate of wage. All hours worked over ten (10) hours Monday through Saturday, Sundays and holidays shall be paid at double the hourly rate of wage. K. All hours worked on Saturdays and Sundays shall be paid at one and one-half times the hourly rate of wage. All hours worked on holidays shall be paid at double the hourly rate of wage. M. All hours worked on Saturdays (except makeup days if work is lost due to inclement weather conditions) shall be paid at one and one-half times the hourly rate of wage. All hours worked on Sundays and holidays shall be paid at double the hourly rate of wage. N. All hours worked on Saturdays (except makeup days) shall be paid at one and one-half times the hourly rate of wage. All hours worked on Sundays and holidays shall be paid at double the hourly rate of wage. Benefit Code Key — Effective 3/2/2016 thru 8/30/2016 Overtime Codes Continued O. The first ten (10) hours worked on Saturday shall be paid at one and one-half times the hourly rate of wage. All hours worked on Sundays, holidays and after twelve (12) hours, Monday through Friday and after ten (10) hours on Saturday shall be paid at double the hourly rate of wage. P. All hours worked on Saturdays (except makeup days if circumstances warrant) and Sundays shall be paid at one and one-half times the hourly rate of wage. All hours worked on holidays shall be paid at double the hourly rate of wage. Q. The first two (2) hours after eight (8) regular hours -Monday through Friday and up to ten (10) hours worked on Saturdays shall be paid at one and one-half times the hourly rate of wage. All hours worked in excess of ten (10) hours per day Monday through Saturday and all hours worked on Sundays and holidays (except Christmas day) shall be paid at double the hourly rate of wage. All hours worked on Christmas day shall be paid at two and one-half times the hourly rate of wage. R. All hours worked on Sundays and holidays shall be paid at two times the hourly rate of wage S. The first two (2) hours after eight (8) regular hours Monday through Friday and the first eight (8) hours on Saturday shall be paid at one and one-half times the hourly rate of wage. All hours worked on holidays and all other overtime hours worked, except Labor Day, shall be paid at double the hourly rate of wage. All hours worked on Labor Day shall be paid at three times the hourly rate of wage. U. All hours worked on Saturdays shall be paid at one and one-half times the hourly rate of wage. All hours worked on Sundays and holidays (except Labor Day) shall be paid at two times the hourly rate of wage. All hours worked on Labor Day shall be paid at three times the hourly rate of wage. V. All hours worked on Sundays and holidays (except Thanksgiving Day and Christmas day) shall be paid at one and one-half times the hourly rate of wage. All hours worked on Thanksgiving Day and Christmas day shall be paid at double the hourly rate of wage. W. All hours worked on Saturdays and Sundays (except make-up days due to conditions beyond the control of the employer)) shall be paid at one and one-half times the hourly rate of wage. All hours worked on holidays shall be paid at double the hourly rate of wage. X. The first four (4) hours after eight (8) regular hours Monday through Friday and the first twelve (12) hours on Saturday shall be paid at one and one-half times the hourly rate of wage. All hours worked over twelve (12) hours Monday through Saturday, Sundays and holidays shall be paid at double the hourly rate of wage. When holiday falls on Saturday or Sunday, the day before Saturday, Friday, and the day after Sunday, Monday, shall be considered the holiday and all work performed shall be paid at double the hourly rate of wage. Y. All hours worked outside the hours of 5:00 am and 5:00 pm (or such other hours as may be agreed upon by any employer and the employee) and all hours worked in excess of eight (8) hours per day (10 hours per day for a 4 x 10 workweek) and on Saturdays and holidays (except labor day) shall be paid at one and one-half times the hourly rate of wage. (except for employees who are absent from work without prior approval on a scheduled workday during the workweek shall be paid at the straight -time rate until they have worked 8 hours in a day (10 in a 4 x 10 workweek) or 40 hours during that workweek.) All hours worked Monday through Saturday over twelve (12) hours and all hours worked on Sundays and Labor Day shall be paid at double the hourly rate of wage. Z. All hours worked on Saturdays and Sundays shall be paid at one and one-half times the hourly rate of wage. All hours worked on holidays shall be paid the straight time rate of pay in addition to holiday pay. Benefit Code Key — Effective 3/2/2016 thru 8/30/2016 Overtime Codes Continued ALL HOURS WORKED IN EXCESS OF EIGHT (8) HOURS PER DAY OR FORTY (40) HOURS PER WEEK SHALL BE PAID AT ONE AND ONE-HALF TIMES THE HOURLY RATE OF WAGE. B. All hours worked on holidays shall be paid at one and one-half times the hourly rate of wage. C. All hours worked on Sundays shall be paid at one and one-half times the hourly rate of wage. All hours worked on holidays shall be paid at two times the hourly rate of wage. F. The first eight (8) hours worked on holidays shall be paid at the straight hourly rate of wage in addition to the holiday pay. All hours worked in excess of eight (8) hours on holidays shall be paid at double the hourly rate of wage. G. All hours worked on Sunday shall be paid at two times the hourly rate of wage. All hours worked on paid holidays shall be paid at two and one-half times the hourly rate of wage including holiday pay. H. All hours worked on Sunday shall be paid at two times the hourly rate of wage. All hours worked on holidays shall be paid at one and one-half times the hourly rate of wage. O. All hours worked on Sundays and holidays shall be paid at one and one-half times the hourly rate of wage. R. All hours worked on Sundays and holidays and all hours worked over sixty (60) in one week shall be paid at double the hourly rate of wage. U. All hours worked on Saturdays shall be paid at one and one-half times the hourly rate of wage. All hours worked over 12 hours in a day or on Sundays and holidays shall be paid at double the hourly rate of wage. W. The first two (2) hours after eight (8) regular hours Monday through Friday and the first eight (8) hours on Saturday shall be paid at one and one-half times the hourly rate of wage. All other hours worked Monday through Saturday, and all hours worked on Sundays and holidays shall be paid at double the hourly rate of wage. On a four-day, ten-hour weekly schedule, either Monday thru Thursday or Tuesday thru Friday schedule, all hours worked after ten shall be paid at double the hourly rate of wage. The first eight (8) hours worked on the fifth day shall be paid at one and one-half times the hourly rate of wage. All other hours worked on the fifth, sixth, and seventh days and on holidays shall be paid at double the hourly rate of wage. ALL HOURS WORKED IN EXCESS OF EIGHT (8) HOURS PER DAY OR FORTY (40) HOURS PER WEEK SHALL BE PAID AT ONE AND ONE-HALF TIMES THE HOURLY RATE OF WAGE. A. Work performed in excess of eight (8) hours of straight time per day, or ten (10) hours of straight time per day when four ten (10) hour shifts are established, or forty (40) hours of straight time per week, Monday through Friday, or outside the normal shift, and all work on Saturdays shall be paid at time and one-half the straight time rate. Hours worked over twelve hours (12) in a single shift and all work performed after 6:00 pm Saturday to 6:00 am Monday and holidays shall be paid at double the straight time rate of pay. Any shift starting between the hours of 6:00 pm and midnight shall receive an additional one dollar ($1.00) per hour for all hours worked that shift. The employer shall have the sole discretion to assign overtime work to employees. Primary consideration for overtime work shall be given to employees regularly assigned to the work to be performed on overtime situations. After an employee has worked eight (8) hours at an applicable overtime rate, all additional hours shall be at the applicable overtime rate until such time as the employee has had a break of eight (8) hours or more. C. Work performed in excess of eight (8) hours of straight time per day, or ten (10) hours of straight time per day when four ten (10) hour shifts are established, or forty (40) hours of straight time per week, Monday through Friday, or outside the normal shift, and all work on Saturdays shall be paid at one and one-half times the hourly rate of wage. All work performed after 6:00 pm Saturday to 5:00 am Monday and Holidays shall be paid at double the hourly rate of wage. After an employee has worked eight (8) hours at an applicable overtime rate, all additional hours shall be at the applicable overtime rate until such time as the employee has had a break of eight (8) hours or more. Benefit Code Key — Effective 3/2/2016 thru 8/30/2016 Overtime Codes Continued D. All hours worked between the hours of 6:00 pm and 6:00 am, Monday through Saturday, shall be paid at a premium rate of 15% over the hourly rate of wage. All other hours worked after 6:00 am on Saturdays, shall be paid at one and one-half times the hourly rate of wage. All hours worked on Sundays and holidays shall be paid at double the hourly rate of wage. E. All hours worked Sundays and holidays shall be paid at double the hourly rate of wage. Each week, once 40 hours of straight time work is achieved, then any hours worked over 10 hours per day Monday through Saturday shall be paid at double the hourly wage rate. F. All hours worked on Saturday shall be paid at one and one-half times the hourly rate of wage. All hours worked on Sunday shall be paid at two times the hourly rate of wage. All hours worked on paid holidays shall be paid at two and one-half times the hourly rate of wage including holiday pay. H. All work performed on Sundays between March 16th and October 14th and all Holidays shall be compensated for at two (2) times the regular rate of pay. Work performed on Sundays between October 15th and March 15th shall be compensated at one and one half (1-1/2) times the regular rate of pay. I. All hours worked on Saturdays shall be paid at one and one-half times the hourly rate of wage. In the event the job is down due to weather conditions during a five day work week (Monday through Friday,) or a four day -ten hour work week (Tuesday through Friday,) then Saturday may be worked as a voluntary make-up day at the straight time rate. However, Saturday shall not be utilized as a make-up day when a holiday falls on Friday. All hours worked Monday through Saturday over twelve (12) hours and all hours worked on Sundays and holidays shall be paid at double the hourly rate of wage. ALL HOURS WORKED IN EXCESS OF EIGHT (8) HOURS PER DAY OR FORTY (40) HOURS PER WEEK SHALL BE PAID AT ONE AND ONE-HALF TIMES THE HOURLY RATE OF WAGE. A. All hours worked in excess of eight (8) hours per day or forty (40) hours per week shall be paid at double the hourly rate of wage. All hours worked on Saturdays, Sundays and holidays shall be paid at double the hourly rate of wage. B. All hours worked over twelve (12) hours per day and all hours worked on holidays shall be paid at double the hourly rate of wage. C. On Monday through Friday, the first four (4) hours of overtime after eight (8) hours of straight time work shall be paid at one and one half (1-1/2) times the straight time rate of pay, unless a four (4) day ten (10) hour workweek has been established. On a four (4) day ten (10) hour workweek scheduled Monday through Thursday, or Tuesday through Friday, the first two (2) hours of overtime after ten (10) hours of straight time work shall be paid at one and one half (1-1/2) times the straight time rate of pay. On Saturday, the first twelve (12) hours of work shall be paid at one and one half (1-1/2) times the straight time rate of pay, except that if the job is down on Monday through Friday due to weather conditions or other conditions outside the control of the employer, the first ten (10) hours on Saturday may be worked at the straight time rate of pay. All hours worked over twelve (12) hours in a day and all hours worked on Sunday and Holidays shall be paid at two (2) times the straight time rate of pay. 4 Benefit Code Key — Effective 3/2/2016 thru 8/30/2016 Overtime Codes Continued D. All hours worked in excess of eight (8) hours per day or forty (40) hours per week shall be paid at double the hourly rate of wage. All hours worked on Saturday, Sundays and holidays shall be paid at double the hourly rate of pay. Rates include all members of the assigned crew. EXCEPTION: On all multipole structures and steel transmission lines, switching stations, regulating, capacitor stations, generating plants, industrial plants, associated installations and substations, except those substations whose primary function is to feed a distribution system, will be paid overtime under the following rates: The first two (2) hours after eight (8) regular hours Monday through Friday of overtime on a regular workday, shall be paid at one and one-half times the hourly rate of wage. All hours in excess of ten (10) hours will be at two (2) times the hourly rate of wage. The first eight (8) hours worked on Saturday will be paid at one and one-half (1-1/2) times the hourly rate of wage. All hours worked in excess of eight (8) hours on Saturday, and all hours worked on Sundays and holidays will be at the double the hourly rate of wage. All overtime eligible hours performed on the above described work that is energized, shall be paid at the double the hourly rate of wage. E. The first two (2) hours after eight (8) regular hours Monday through Friday and the first eight (8) hours on Saturday shall be paid at one and one-half times the hourly rate of wage. All other hours worked Monday through Saturday, and all hours worked on Sundays and holidays shall be paid at double the hourly rate of wage. On a four-day, ten-hour weekly schedule, either Monday thru Thursday or Tuesday thru Friday schedule, all hours worked after ten shall be paid at double the hourly rate of wage. The Monday or Friday not utilized in the normal four-day, ten hour work week, and Saturday shall be paid at one and one half (1 %z) times the regular shift rate for the first eight (8) hours. All other hours worked Monday through Saturday, and all hours worked on Sundays and holidays shall be paid at double the hourly rate of wage. F. All hours worked between the hours of 6:00 pm and 6:00 am, Monday through Saturday, shall be paid at a premium rate of 20% over the hourly rate of wage. All hours worked on Sundays shall be paid at one and one-half times the hourly rate of wage. All hours worked on holidays shall be paid at double the hourly rate of wage. G. All hours worked on Saturdays shall be paid at one and one-half times the hourly rate of wage. All hours worked Monday through Saturday over twelve (12) hours and all hours worked on Sundays and holidays shall be paid at double the hourly rate of wage. Holidav Codes A. Holidays: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, Friday after Thanksgiving Day, and Christmas Day (7). B. Holidays: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, Friday after Thanksgiving Day, the day before Christmas, and Christmas Day (8). C. Holidays: New Year's Day, Presidents' Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, the Friday after Thanksgiving Day, And Christmas Day (8). D. Holidays: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, the Friday and Saturday after Thanksgiving Day, And Christmas Day (8). H. Holidays: New Year's Day, Memorial Day, Independence Day, Thanksgiving Day, the Day after Thanksgiving Day, And Christmas (6). Benefit Code Key — Effective 3/2/2016 thru 8/30/2016 Holiday Codes Continued 5. I. Holidays: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, and Christmas Day (6). J. Holidays: New Year's Day, Memorial Day, Independence Day, Thanksgiving Day, Friday after Thanksgiving Day, Christmas Eve Day, And Christmas Day (7). K. Holidays: New Year's Day, Presidents' Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, Friday After Thanksgiving Day, The Day Before Christmas, And Christmas Day (9). L. Holidays: New Year's Day, Martin Luther King Jr. Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, Friday after Thanksgiving Day, And Christmas Day (8). N. Holidays: New Year's Day, Presidents' Day, Memorial Day, Independence Day, Labor Day, Veterans' Day, Thanksgiving Day, The Friday After Thanksgiving Day, And Christmas Day (9). P. Holidays: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, Friday And Saturday After Thanksgiving Day, The Day Before Christmas, And Christmas Day (9). If A Holiday Falls On Sunday, The Following Monday•Shall Be Considered As A Holiday. Q. Paid Holidays: New Year's Day, Memorial Day; Independence Day, Labor Day, Thanksgiving Day, and Christmas Day (6). R. Paid Holidays: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, Day After Thanksgiving Day, One -Half Day Before Christmas Day, And Christmas Day. (7 1/2). S. Paid Holidays: New Year's Day, Presidents' Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, And Christmas Day (7). T. Paid Holidays: New Year's Day, Washington's Birthday, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, The Friday After Thanksgiving Day, Christmas Day, And The Day Before Or After Christmas (9). Z. Holidays: New Year's Day, Memorial Day, Independence Day, Labor Day, Veterans Day, Thanksgiving Day, the Friday after Thanksgiving Day, And Christmas Day (8). 6. A. Paid Holidays: New Year's Day, Presidents' Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, the Friday after Thanksgiving Day, And Christmas Day (8). E. Paid Holidays: New Year's Day, Day Before Or After New Year's Day, Presidents Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, the Friday after Thanksgiving Day, Christmas Day, and a Half -Day On Christmas Eve Day. (9 1/2). G. Paid Holidays: New Year's Day, Martin Luther King Jr. Day, Presidents' Day, Memorial Day, Independence Day, Labor Day, Veterans' Day, Thanksgiving Day, the Friday after Thanksgiving Day, Christmas Day, and Christmas Eve Day (11). H. Paid Holidays: New Year's Day, New Year's Eve Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, Friday After Thanksgiving Day, Christmas Day, The Day After Christmas, And A Floating Holiday (10). I. Paid Holidays: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, Friday After Thanksgiving Day, And Christmas Day (7). 0 Benefit Code Key — Effective 3/2/2016 thru 8/30/2016 Holiday Codes Continued 6. T. Paid Holidays: New Year's Day, Presidents' Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, The Friday After Thanksgiving Day, The Last Working Day Before Christmas Day, And Christmas Day (9). Z. Holidays: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, Friday after Thanksgiving Day, And Christmas Day (7). If a holiday falls on Saturday, the preceding Friday shall be considered as the holiday. If a holiday falls on Sunday, the following Monday shall be considered as the holiday. A. Holidays: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, the Friday and Saturday after Thanksgiving Day, And Christmas Day (8). Any Holiday Which Falls On A Sunday Shall Be Observed As A Holiday On The Following Monday. If any of the listed holidays falls on a Saturday, the preceding Friday shall be a regular work day. B. Holidays: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, the Friday and Saturday after Thanksgiving Day, And Christmas Day (8). Any holiday which falls on a Sunday shall be observed as a holiday on the following Monday. Any holiday which falls on a Saturday shall be observed as a holiday on the preceding Friday. C. Holidays: New Year's Day, Martin Luther King Jr. Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, the Friday after Thanksgiving Day, And Christmas Day (8). Any holiday which falls on a Sunday shall be observed as a holiday on the following Monday. Any holiday which falls on a Saturday shall be observed as a holiday on the preceding Friday. D. Paid Holidays: New Year's Day, Memorial Day, Independence Day, Labor Day, Veteran's Day, Thanksgiving Day, the Friday after Thanksgiving Day, And Christmas Day (8). Unpaid Holidays: President's Day. Any paid holiday which falls on a Sunday shall be observed as a holiday on the following Monday. Any paid holiday which falls on a Saturday shall be observed as a holiday on the preceding Friday. E. Holidays: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, the Friday after Thanksgiving Day, And Christmas Day (7). Any holiday which falls on a Sunday shall be observed as a holiday on the following Monday. Any holiday which falls on a Saturday shall be observed as a holiday on the preceding Friday. Holidays: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, the Friday after Thanksgiving Day, the last working day before Christmas day and Christmas day (8). Any holiday which falls on a Sunday shall be observed as a holiday on the following Monday. Any holiday which falls on a Saturday shall be observed as a holiday on the preceding Friday. G. Holidays: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, and Christmas Day (6). Any holiday which falls on a Sunday shall be observed as a holiday on the following Monday. H. Holidays: New Year's Day, Martin Luther King Jr. Day, Independence Day, Memorial Day, Labor Day, Thanksgiving Day, the Friday after Thanksgiving Day, the Last Working Day before Christmas Day and Christmas Day (9). Any holiday which falls on a Sunday shall be observed as a holiday on the following Monday. Any holiday which falls on a Saturday shall be observed as a holiday on the preceding Friday. I. Holidays: New Year's Day, President's Day, Independence Day, Memorial Day, Labor Day, Thanksgiving Day, The Friday After Thanksgiving Day, The Day Before Christmas Day And Christmas Day (9). Any holiday which falls on a Sunday shall be observed as a holiday on the following Monday. Any holiday which falls on a Saturday shall be observed as a holiday on the preceding Friday. Holidays: New Year's Day, Independence Day, Memorial Day, Labor Day, Thanksgiving Day and Christmas Day (6). Any holiday which falls on a Sunday shall be observed as a holiday on the following Monday. Any holiday which falls on a Saturday shall be observed as a holiday on the preceding Friday. 7 Benefit Code Key — Effective 3/2/2016 thru 8/30/2016 Holiday Codes Continued K. Holidays: New Year's Day, Memorial Day, Independence Day, Thanksgiving Day, the Friday and Saturday after Thanksgiving Day, And Christmas Day (8). Any holiday which falls on a Sunday shall be observed as a holiday on the following Monday. Any holiday which falls on a Saturday shall be observed as a holiday on the preceding Friday. L. Holidays: New Year's Day, Memorial Day, Labor Day, Independence Day, Thanksgiving Day, the Last Work Day before Christmas Day, And Christmas Day (7). Any holiday which falls on a Sunday shall be observed as a holiday on the following Monday. Any holiday which falls on a Saturday shall be observed as a holiday on the preceding Friday. M. Paid Holidays: New Year's Day, The Day after or before New Year's Day, President's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, the Friday after Thanksgiving Day, Christmas Day, And the Day after or before Christmas Day (10). Any holiday which falls on a Sunday shall be observed as a holiday on the following Monday. Any holiday which falls on a Saturday shall be observed as a holiday on the preceding Friday. N. Holidays: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, the Friday after Thanksgiving Day, And Christmas Day (7). Any holiday which falls on a Sunday shall be observed as a holiday on the following Monday. When Christmas falls on a Saturday, the preceding Friday shall be observed as a holiday. Holidays: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, Friday after Thanksgiving Day, And Christmas Day (7). Any holiday which falls on a Sunday shall be observed as a holiday on the following Monday. Q. Holidays: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, the Friday after Thanksgiving Day, the Last Working Day before Christmas Day and Christmas Day (8). Any holiday which falls on a Sunday shall be observed as a holiday on the following Monday. If any of the listed holidays falls on a Saturday, the preceding Friday shall be a regular work day. R. Paid Holidays: New Year's Day, the day after or before New Year's Day, President's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, the Friday after Thanksgiving Day, Christmas Day, and the day after or before Christmas Day (10). If any of the listed holidays fall on Saturday, the preceding Friday shall be observed as the holiday. If any of the listed holidays falls on a Sunday, the day observed by the Nation shall be considered a holiday and compensated accordingly. Paid Holidays: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, Friday after Thanksgiving Day, Christmas Day, the Day after Christmas, and A Floating Holiday (9). If any of the listed holidays falls on a Sunday, the day observed by the Nation shall be considered a holiday and compensated accordingly. T. Paid Holidays: New Year's Day, the Day after or before New Year's Day, President's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, the Friday after Thanksgiving Day, Christmas Day, and The Day after or before Christmas Day. (10). If any of the listed holidays falls on a Sunday, the day observed by the Nation shall be considered a holiday and compensated accordingly. Any holiday which falls on a Saturday shall be observed as a holiday on the preceding Friday. Note Codes A. In addition to the hourly wage and fringe benefits, the following depth premiums apply to depths of fifty feet or more: Over 50' To 100' -$2.00 per Foot for Each Foot Over 50 Feet Over 100' To 150' 43.00 per Foot for Each Foot Over 100 Feet Over 150' To 220'-$4.00 per Foot for Each Foot Over 150 Feet Over 220'-$5.00 per Foot for Each Foot Over 220 Feet Benefit Code Key — Effective 3/2/2016 thru 8/30/2016 Note Codes Continued C. In addition to the hourly wage and fringe benefits, the following depth premiums apply to depths of fifty feet or more: Over 50' To 100'-$ 1.00 per Foot for Each Foot Over 50 Feet Over 100' To 150'-$1.50 per Foot for Each Foot Over 100 Feet Over 150' To 200' -$2.00 per Foot for Each Foot Over 150 Feet Over 200' -Divers May Name Their Own Price D. Workers working with supplied air on hazmat projects receive an additional $1.00 per hour. L. Workers on hazmat projects receive additional hourly premiums as follows -Level A: $0.75, Level B: $0.50, And Level C: $0.25. M. Workers on hazmat projects receive additional hourly premiums as follows: Levels A & B: $1.00, Levels C & D: $0.50. N. Workers on hazmat projects receive additional hourly premiums as follows -Level A: $1.00, Level B: $0.75, Level C: $0.50, And Level D: $0.25. Workers on hazmat projects receive additional hourly premiums as follows -Class A Suit: $2.00, Class B Suit: $1.50, Class C Suit: $1.00, And Class D Suit $0.50. Q. The highest pressure registered on the gauge for an accumulated time of more than fifteen (15) minutes during the shift shall be used in determining the scale paid. R. Effective August 31, 2012 — A Traffic Control Supervisor shall be present on the project whenever flagging or spotting or other traffic control labor is being utilized. A Traffic Control Laborer performs the setup, maintenance and removal of all temporary traffic control devices and construction signs necessary to control vehicular, bicycle, and pedestrian traffic during construction operations. Flaggers and Spotters shall be posted where shown on approved Traffic Control Plans or where directed by the Engineer. All flaggers and spotters shall possess a current flagging card issued by the State of Washington, Oregon, Montana, or Idaho. These classifications are only effective on or after August 31, 2012. Effective August 31, 2012 — A Traffic Control Supervisor shall be present on the project whenever flagging or spotting or other traffic control labor is being utilized. Flaggers and Spotters shall be posted where shown on approved Traffic Control Plans or where directed by the Engineer. All flaggers and spotters shall possess a current flagging card issued by the State of Washington, Oregon, Montana, or Idaho. This classification is only effective on or after August 31, 2012. T. Effective August 31, 2012 — A Traffic Control Laborer performs the setup, maintenance and removal of all temporary traffic control devices and construction signs necessary to control vehicular, bicycle, and pedestrian traffic during construction operations. Flaggers and Spotters shall be posted where shown on approved Traffic Control Plans or where directed by the Engineer. All flaggers and spotters shall possess a current flagging card issued by the State of Washington, Oregon, Montana, or Idaho. This classification is only effective on or after August 31, 2012. U. Workers on hazmat projects receive additional hourly premiums as follows — Class A Suit: $2.00, Class B Suit: $1.50, And Class C Suit: $1.00. Workers performing underground work receive an additional $0.40 per hour for any and all work performed underground, including operating, servicing and repairing of equipment. The premium for underground work shall be paid for the entire shift worked. Workers who work suspended by a rope or cable receive an additional $0.50 per hour. The premium for work suspended shall be paid for the entire shift worked. Workers who do "pioneer" work (break open a cut, build road, etc.) more than one hundred fifty (150) feet above grade elevation receive an additional $0.50 per hour. 0 Washington State Department of Labor and Industries Policy Statement (Regarding the Production of "Standard" or "Non-standard" Items) Below is the department's (State L&I's) list of criteria to be used in determining whether a prefabricated item is "standard" or "non-standard". For items not appearing on WSDOT's predetermined list, these criteria shall be used by the Contractor (and the Contractor's subcontractors, agents to subcontractors, suppliers, manufacturers, and fabricators) to determine coverage under RCW 39.12. The production, in the State of Washington, of non-standard items is covered by RCW 39.12, and the production of standard items is not. The production of any item outside the State of Washington is not covered by RCW 39.12. 1. Is the item fabricated for a public works project? If not, it is not subject to RCW 39.12. If it is, go to question 2. 2. Is the item fabricated on the public works jobsite? If it is, the work is covered under RCW 39.12. If not, go to question 3. 3. Is the item fabricated in an assembly/fabrication plant set up for, and dedicated primarily to, the public works project? If it is, the work is covered by RCW 39.12. If not, go to question 4. 4. Does the item require any assembly, cutting, modification or other fabrication by the supplier? If not, the work is not covered by RCW 39.12. If yes, go to question 5. 5. Is the prefabricated item intended for the public works project typically an inventory item which could reasonably be sold on the general market? If not, the work is covered by RCW 39.12. If yes, go to question 6. 6. Does the specific prefabricated item, generally defined as standard, have any unusual characteristics such as shape, type of material, strength requirements, finish, etc? If yes, the work is covered under RCW 39.12. Any firm with questions regarding the policy, WSDOT's Predetermined List, or for determinations of covered and non -covered workers shall be directed to State L&I at (360) 902-5330. Supplemental to Wage Rates 03/02/2016 Edition, Published February 1s', 2016 WSDOT's Predetermined List for Suppliers - Manufactures - Fabricator Below is a list of potentially prefabricated items, originally furnished by WSDOT to Washington State Department of Labor and Industries, that may be considered non- standard and therefore covered by the prevailing wage law, RCW 39.12. Items marked with an X in the "YES" column should be considered to be non-standard and therefore covered by RCW 39.12. Items marked with an X in the "NO" column should be considered to be standard and therefore not covered. Of course, exceptions to this general list may occur, and in that case shall be evaluated according to the criteria described in State and L&I's policy statement. ITEM DESCRIPTION YES NO 1. Metal rectangular frames, solid metal covers, herringbone grates, and bi-directional vaned grates for Catch Basin I X Types 1, 1 L, 1 P, and 2 and Concrete Inlets. See Std. Plans I j 2. Metal circular frames (rings) and covers, circular grates, and prefabricated ladders for Manhole Types 1, 2, and 3, X Drywell Types 1, 2, and 3 and Catch Basin Type 2. See Std. Plans 3. -Prefabricated steel grate supports and welded grates, metal frames and dual vaned grates, and Type 1, 2, and X. 3 structural tubing grates for Drop Inlets. See Std. Plans. 4. Concrete Pipe - Plain Concrete pipe and reinforced concrete pipe Class 2 to 5 sizes smaller than 60 inch diameter. - - P _ - - —' - �- 5. Concrete ipe -Plain Concrete pi-pe and reinforced - concrete pipe Class 2 to 5 sizes larger than 60 inch diameter. X 6. Corrugated Steel Pipe - Steel lock seam corrugated pipe for culverts and storm sewers, sizes 30 inch to 120 inches in diameter. May also be treated, 1 thru 5. 7. Corrugated Aluminum Pipe - Aluminum lock seam corrugated pipe for culverts and storm sewers, sizes 30 inch to 120 inches in diameter. May also be treated, #5. X Supplemental to Wage Rates 2 03/02/2016 Edition, Published February 1s', 2016 ITEM DESCRIPTION YES NO 8. Anchor Bolts & Nuts - Anchor Bolts and Nuts, for mounting sign structures, luminaries and other items, shall be . made from commercial bolt stock. See Contract Plans and Std. Plans for size and material type. 9. Aluminum Pedestrian Handrail - Pedestrian handrail conforming to the type and material specifications set forth in the contract plans. Welding of aluminum shall be in accordance with Section 9-28.14(3). 10. Major Structural Steel Fabrication - Fabrication of major steel items such as trusses, beams, girders, etc., for bridges. ' i 11. Minor Structural Steel Fabrication -Fabrication of minor steel Items such as special hangers, brackets, access doors for structures, access ladders for irrigation boxes, bridge expansion joint systems, etc., involving welding, cutting, punching and/or boring of holes. See Contact Plans for item description and shop drawings. i 12. Aluminum Bridge Railing Type BP - Metal bridge railing conforming to the type and material specifications set forth in the Contract Plans. Welding of aluminum shall be in accordance with Section 9-28.14(3). 13 Concrete Piling--Precast-Prestressed concrete piling for use as 55 and 70 ton concrete piling. Concrete to conform to Section 9-19.1 of Std. Spec.. 14. Precast Manhole Types 1, 2,—an--d3 with cones, adjustment sections and flat top slabs. See Std. Plans. 15. Precast Drywell Types 1, 2, and with cones and adjustment Sections. See Std. Plans. 16. Precast Catch Basin ---C- atch Basin type 1,--l- L, 1 P, and 2 With adjustment sections. See Std. Plans.( Supplemental to Wage Rates 3 03/02/2016 Edition, Published February 1s', 2016 ITEM DESCRIPTION YES NO 17. Precast Concrete Inlet - with adjustment sections, See Std. Plans I X 18. Precast Drop Inlet Type 1 and 2 with metal grate supports. See Std. Plans., 19. Precast Grate Inlet Type 2 with extension and top units. See Std. Plans 20. Metal frames, vaned grates, and hoods for Combination Inlets. See Std. Plans 21. Precast Concrete Utility Vaults - Precast Concrete utility vaults of various sizes. Used for in ground storage of utility facilities and controls. See Contract Plans for size and construction requirements. Shop drawings are to be provided for approval prior to casting 22. Vault Risers - For use with Valve Vaults and Utilities Vaults. 23. Valve Vault - For use with underground utilities. See Contract Plans for details. 24. Precast Concrete Barrier - Precast Concrete Barrier for use as new barrier or may also be used as Temporary Concrete j Barrier. Only new state approved barrier may be used as permanent barrier. 25. Reinforced Earth Wall Panels — Reinforced Earth Wall Panels in f size and shape as shown in the Plans. Fabrication plant has annual approval for methods and materials to be used. See Shop Drawing. Fabrication at other locations may be approved, after facilities inspection, contact HQ. Lab. 26. Precast Concrete Walls - Precast Concrete Walls - tilt -up wall panel in size and shape as shown in Plans. Fabrication plant has annual approval for methods and materials x to be used Supplemental to Wage Rates 4 03/02/2016 Edition, Published February 151, 2016 ITEM DESCRIPTION YES NO 27. Precast Railroad Crossings - Concrete Crossing Structure _ _Slabs.__ _ _ 28. 12, 18 and 26 inch Standa_rd Precast Prestre_ _ss_ed Girder - Standard Precast Prestressed Girder for use in structures. i Fabricator plant has annual approval of methods and materials to be used. Shop Drawing to be provided for approval prior to I x( casting girders. See Std. Spec. Section 6-02.3(25)A 29. Prestressed Concrete Girder Series 4-14 - Prestressed Concrete Girders for use in structures. Fabricator plant has annual approval of methods and materials to be used. Shop Drawing to be j provided for approval prior to casting girders. ' See Std. Spec. Section 6-02.3(25)A 30. Prestressed T ri-Beam Girder --P r -es fr-e s -s e dTri-Beam Girders for Ti - use use in structures. Fabricator plant has annual approval'of methods and materials to be used. Shop Drawing to be provided for approval prior to casting girders. x See Std. Spec. Section 6-02.3(25)A 31. Prestressed Precast Hollow -Core Slab - Precast Prestressed Hollow -core slab for use in structures. Fabricator plant has annual approval of methods and materials to be used. Shop Drawing to be provided for approval prior to casting girders. See Std. Spec. Section 6-02.3(25)A. 32. Prestressed -Bulb Tee Girder -Bulb Tee Prestressed Girder for use in structures. Fabricator plant has annual approval of methods and materials to be used. Shop Drawing to be provided for approval prior to casting girders. See Std. Spec. Section 6-02.3(25)A 33. Monument Case and Cover See Std. Plan. Supplemental to Wage Rates 5 03/02/2016 Edition, Published February 15', 2016 ITEM DESCRIPTION YES NO 34. Cantilever Sign Structure - Cantilever Sign Structure I ' fabricated from steel tubing meeting AASHTO-M-183. See Std. Plans, and Contract Plans for details. The steel structure shall be galvanized after fabrication in accordance with AASHTO-M-111. 35. Mono -tube Sign Structures - Mono -tube Sign Bridge fabricated to details shown in the Plans. Shop drawings for approval are required prior to fabrication. 36. Steel Sign Bridges - Steel Sign Bridges fabricated from steel tubing meeting AASHTO-M-138 for Aluminum Alloys. See Std. Plans, and Contract Plans for details. The steel structure shall be galvanized after fabrication in accordance with AASHTO-M-111. I 37. Steel Sign Post - Fabricated Steel Sign Posts as detailed in Std Plans. Shop drawings for approval are to be provided prior to X fabrication _ 38. Light Standard -Prestressed - Spun, prestressed, holiow concrete poles. 39. Light Standards - Lighting Standards for use on highway illumination systems, poles to be fabricated to conform with methods and materials as specified on Std. Plans. See Specia l Provisions for pre -approved drawings. 40. Traffic Signal Standards -Traffic Signal Standards for use on highway and/or street signal systems. Standards to be fabricated I X to conform with methods and material as specified on Std. Plans. See Special Provisions for pre -approved drawings 41. Precast Concrete Sloped Mountable Curb (Single and DualFaced) See Std. Plans. ------ -- — - — - - - -- - — - --- — - -- Supplemental to Wage Rates 03/02/2016 Edition, Published February 1St, 2016 Supplemental to Wage Rates 7 03/02/2016 Edition, Published February 1s', 2016 ITEM DESCRIPTION YES NO 42. Traffic Signs - Prior to approval of a Fabricator of Traffic Signs, the sources of the following materials must be submitted and approved for reflective sheeting, legend material, and aluminum sheeting. I X NOTE: *** Fabrication inspection required. Only signs tagged "Fabrication Approved" by WSDOT Sign Fabrication Inspector to be installed— — _- — — — — Custom Message � Std Signing - i Messes 43. Cutting & bending reinforcing steel I 44. Guardrail components x Custom;Standard End Sec I.—Se J 45. Aggregates/Concrete mixes Covered by WAC 296-127-018 46. Asphalt covered by WAC 296-127-018 47. Fiber fabrics 48. Electrical wiring/components 49. treated or untreated timber pile 50. Girder pads (elastomeric bearing) — --tan --dard —b--- - I 51. SDimension lum- e—r---- I ------ I i 52. -- — Irrigation compents on — Supplemental to Wage Rates 7 03/02/2016 Edition, Published February 1s', 2016 ITEM DESCRIPTION 53. Fencing materials 54. Guide Posts 55. Traffic Buttons 56. Epoxy --57. Cribbing — --- ------ 58. Water distribution materials 59. Steel "H" piles 60. Steel pipe for concrete pile casings 61. Steel pile tips, standard 62. Steel pile tips, custom YES NO X X� X X X Prefabricated items specifically produced for public works projects that are prefabricated in a county other than the county wherein the public works project is to be completed, the wage for the offsite prefabrication shall be the applicable prevailing wage for the county in which the actual prefabrication takes place. It is the manufacturer of the prefabricated product to verify that the correct county wage rates are applied to work they perform. See RCW 39.12.010 (The definition of 'locality" in RCW 39.12.010 2) contains the phrase "wherein the physical work is being performed." The department interprets this phrase to mean the actual work site. Supplemental to Wage Rates 8 03/02/2016 Edition, Published February 1St, 2016 WSDOT's List of State Occupations not applicable to Heavy and Highway Construction Projects This project is subject to the state hourly minimum rates for wages and fringe benefits in the contract provisions, as provided by the state Department of Labor and Industries. The following list of occupations, is comprised of those occupations that are not normally used in the construction of heavy and highway projects. When considering job classifications for use and / or payment when bidding on, or building heavy and highway construction projects for, or administered by WSDOT, these Occupations will be excepted from the included "Washington State Prevailing Wage Rates For Public Work Contracts" documents. • Building Service Employees • Electrical Fixture Maintenance Workers • Electricians - Motor Shop • Heating Equipment Mechanics • Industrial Engine and Machine Mechanics • Industrial Power Vacuum Cleaners • Inspection, Cleaning, Sealing of Water Systems by Remote Control • Laborers - Underground Sewer & Water • Machinists (Hydroelectric Site Work) • Modular Buildings • Playground & Park Equipment Installers • Power Equipment Operators - Underground Sewer & Water • Residential *** ALL ASSOCIATED RATES *** • Sign Makers and Installers (Non -Electrical) • Sign Makers and Installers (Electrical) • Stage Rigging Mechanics (Non Structural) The following occupations may be used only as outlined in the preceding text concerning "WSDOT's list for Suppliers - Manufacturers - Fabricators" • Fabricated Precast Concrete,Products • Metal Fabrication (In Shop) Definitions for the Scope of Work for prevailing wages may be found at the Washington State Department of Labor and Industries web site and in WAC Chapter 296-127. Supplemental to Wage Rates g 03/02/2016 Edition, Published February 1",.2016 Washington State Department of Labor and Industries Policy Statements (Regarding Production and Delivery of Gravel, Concrete, Asphalt, etc.) WAC 296-127-018 Agency filings affecting this section Coverage and exemptions of workers involved in the production and delivery of gravel, concrete, asphalt, or similar materials. (1) The materials covered under this section include but are not limited to: Sand, gravel, crushed rock, concrete, asphalt, or other similar materials. (2) All workers, regardless of by whom employed, are subject to the provisions of chapter 39.12 RCW when they perform any or all of the following functions: (a) They deliver or discharge any of the above -listed materials to a public works project site: (i) At one or more point(s) directly upon the location where the material will be incorporated into the project; or - (ii) At multiple points at the project; or (iii) Adjacent to the location and coordinated with the incorporation of those materials. (b) They wait at or near a public works project site to perform any tasks subject to this section of the rule. (c) They remove any materials from a public works construction site pursuant to contract requirements or specifications (e.g., excavated materials, materials from demolished structures, clean-up materials, etc.). (d) They work in a materials production facility (e.g., batch plant, borrow pit, rock quarry, etc.,) which is established for a public works project for the specific, but not necessarily exclusive, purpose of supplying materials for the project. (e) They deliver concrete to a public works site regardless of the method of incorporation. (f) They assist or participate in the incorporation of any materials into the public works project. Supplemental to Wage Rates 10 03/02/2016 Edition, Published February 1St, 2016 (3) All travel time that relates to the work covered under subsection (2) of this section requires the payment of prevailing wages. Travel time includes time spent waiting to load, loading, transporting, waiting to unload, and delivering materials. Travel time would include all time spent in travel in support of a public works project whether the vehicle is empty or full. For example, travel time spent returning to a supply source to obtain another load of material for use on a public works site or returning to the public works site to obtain another load of excavated material is time spent in travel that is subject to prevailing wage. Travel to a supply source, including travel from a public works site, to obtain materials for use on a private project would not be travel subject to the prevailing wage. (4) Workers are not subject to the provisions of chapter 39.12 RCW when they deliver materials to a stockpile. (a) A "stockpile" is defined as materials delivered to a pile located away from the site of incorporation such that the stockpiled materials must be physically moved from the stockpile and transported to another location on the project site in order to be incorporated into the project. (b) A stockpile does not include any of the functions described in subsection (2)(a) through (f) of this section; nor does a stockpile include materials delivered or distributed to multiple locations upon the project site; nor does a stockpile include materials dumped at the place of incorporation, or adjacent to the location and coordinated with the incorporation. (5) The applicable prevailing wage rate shall be determined by the locality in which the work is performed. Workers subject to subsection (2)(d) of this section, who produce such materials at an off-site facility shall be paid the applicable prevailing wage rates for the county in which the off-site facility is located. Workers subject to subsection (2) of this section, who deliver such materials to a public works project site shall be paid the applicable prevailing wage rates for the county in which the public works project is located. [Statutory Authority: Chapter 39.12 RCW, RCW 43.22.051 and 43.22.270. 08-24-101, § 296-127-018, filed 12/2/08, effective 1/2/09. Statutory Authority: Chapters 39.04 and 39.12 RCW and RCW 43.22.270. 92-01-104 and 92-08-101, § 296-127-018, filed 12/18/91 and 4/1/92, effective 8/31/92.] Supplemental to Wage Rates 11 03/02/2016 Edition, Published February 1s', 2016 APPENDIX C Federal Davis -Bacon Wage Determination General Decision Number: WA160001 04/22/2016 WAl Superseded General Decision Number: WA20150001 State: Washington Construction Type: Highway Counties: Washington Statewide. HIGHWAY (Excludes D.O.E. Hanford Site in Benton and Franklin Counties) Note: Under Executive Order (EO) 13658, an hourly minimum wage of $10.15 for calendar year 2016 applies to all contracts subject to the Davis -Bacon Act for which the solicitation was issued on or after January 1, 2015. If this contract is covered by the E0, the contractor must pay all workers in any classification listed on this wage determination at least $10.15 (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on the contract in calendar year 2016. The EO minimum wage rate will be adjusted annually. Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts. Modification Number 0 1 2 3 4 CARP0001-008 06/01/2015 Publication Date 01/08/2016 02/19/2016 02/26/2016 03/04/2016 04/22/2016 Rates CARPENTER GROUP 1 .....................$ 27.61 GROUP 2 .....................$ 41.86 GROUP 3 .....................$ 32.97 GROUP 4 .....................$ 31.94 GROUP 5 .....................$ 73.44 GROUP 6 .....................$ 35.02 GROUP 7 .....................$ 36.72 GROUP 8 .....................$ 33.27 GROUP 9 .....................$ 35.02 WA160001 Modification 4 Federal Wage Determinations for Highway Construction Fringes 14.00 14.49 14.00 14.00 14.00 14.00 14.00 14.00 14.00 Page 1 Page 12 CARPENTER & DIVER CLASSIFICATIONS: GROUP l: Carpenter GROUP 2: Millwright, machine erector GROUP 3: Piledriver - includes driving, pulling, cutting, placing collars, setting, welding, or creosote treated material, on all piling GROUP 4: Bridge carpenters GROUP 5: Diver Wet GROUP 6: Diver Tender, Manifold Operator, ROV Operator GROUP 7: Diver Standby, Bell/Vehicle or Submersible operator Not Under Pressure GROUP 8: Assistant Tender, ROV Tender/Technician GROUP 9: Manifold Operator -Mixed Gas ZONE PAY: ZONE 1 0-40 MILES FREE ZONE 2 41-65 MILES $2.25/PER HOUR ZONE 3 66-100 MILES $3.25/PER HOUR ZONE 4 OVER 100 MILES $4.75/PER HOUR DISPATCH POINTS: CARPENTERS/MILLWRIGHTS: PASCO (515 N Neel Street) or Main Post Office of established residence of employee (Whichever is closest to the worksite). CARPENTERS/PILEDRIVER: SPOKANE (127 E. AUGUSTA AVE.) or Main Post Office of established residence of employee (Whichever is closest to the worksite). CARPENTERS: WENATCHEE (27 N. CHELAN) or Main Post Office of established residence of employee (Whichever is closest to the worksite). CARPENTERS: COEUR D' ALENE (1839 N. GOVERNMENT WAY) or Main Post Office of established residence of employee (Whichever is closest to the worksite). CARPENTERS: MOSCOW (302 N. JACKSON) or Main Post Office of established residence of employee (Whichever is closest to the worksite). WA160001 Modification 4 Federal Wage Determinations for Highway Construction Page 3 DEPTH PAY FOR DIVERS BELOW WATER SURFACE: 50-100 feet $2.00 per foot 101-150 feet $3.00 per foot 151-220 feet $4.00 per foot 221 feet and deeper $5.00 per foot PREMIUM PAY FOR DIVING IN ENCLOSURES WITH NO VERTICAL ASCENT: 0-25 feet Free 26-300 feet $1.00 per Foot SATURATION DIVING: The standby rate applies until saturation starts. The saturation diving rate applies when divers are under pressure continuously until work task and decompression are complete. the diver rate shall be paid for all saturation hours. WORK IN COMBINATION OF CLASSIFICATIONS: Employees working in any combination of classifications within the diving crew (except dive supervisor) in a shift are paid in the classification with the highest rate for that shift. HAZMAT PROJECTS: Anyone working on a HAZMAT job (task), where HAZMAT certification is required, shall be compensated at a premium, in addition to the classification working in as follows: LEVEL D + $.25 per hour - This is the lowest level of protection. No respirator is used and skin protection is minimal. LEVEL C + $.50 per hour - This level uses an air purifying respirator or additional protective clothing. LEVEL B + $.75 per hour - Uses same respirator protection as Level A. Supplied air line is provided in conjunction with a chemical "splash suit". LEVEL A +$1.00 per hour - This level utilizes a fully encapsulated suit with a self-contained breathing apparatus or a supplied air line. WA160001 Modification 4 Federal Wage Determinations for Highway Construction Page 14 CARP0003-006 10/01/2011 SOUTHWEST WASHINGTON: CLARK, COWLITZ, KLICKITAT, LEWIS(Piledriver only), PACIFIC (South of a straight line made by extending the north boundary line of Wahkiakum County west to Willapa Bay to the Pacific Ocean), SKAMANIA AND WAHKIAKUM COUNTIES and INCLUDES THE ENTIRE PENINSULA WEST OF WILLAPA BAY SEE ZONE DESCRIPTION FOR CITIES BASE POINTS ZONE 1: Rates Carpenters: CARPENTERS ..................$ 32.04 DIVERS TENDERS ..............$ 36.34 DIVERS ......................$ 77.08 DRYWALL .....................$ 27.56 MILLWRIGHTS .................$ 32.19 PILEDRIVERS .................$ 33.04 DEPTH PAY: 50 TO 100 FEET $1.00 PER FOOT OVER 50 FEET 101 TO 150 FEET $1.50 PER FOOT OVER 101 FEET 151 TO 200 FEET $2.00 PER FOOT OVER 151 FEET Zone Differential (Add up Zone 1 rates): Zone 2 - $0.85 Zone 3 - 1.25 Zone 4 - 1.70 Zone 5 - 2.00 Zone 6 - 3.00 Fringes 14.18 14.18 14.18 14.18 14.18 14.18 BASEPOINTS: ASTORIA, LONGVIEW, PORTLAND, THE DALLES, AND VANCOUVER, (NOTE: All dispatches for Washington State Counties: Cowlitz, Wahkiakum and Pacific shall be from Longview Local #1707 and mileage shall be computed from that point.) ZONE 1: Projects located within 30 miles of the respective city hall of the above mentioned cities ZONE 2: Projects located more than 30 miles and less than 40 miles of the respective city of the above mentioned cities ZONE 3: Projects located more than 40 miles and less than 50 miles of the respective city of the above mentioned cities ZONE 4: Projects located more than 50 miles and less than 60 miles of the respective city of the above mentioned cities. ZONE 5: Projects located more than 60 miles and less than 70 miles of the respective city of the above mentioned cities ZONE 6: Projects located more than 70 miles of the respected city of the above mentioned cities WA160001 Modification 4 Federal Wage Determinations for Highway Construction Page I5 CARP0770-003 06/01/2015 (HOURLY ZONE PAY: WESTERN AND CENTRAL WASHINGTON - ALL CLASSIFICATIONS EXCEPT MILLWRIGHTS AND PILEDRIVERS Hourly Zone Pay shall be paid on jobs located outside of the free zone computed from the city center of the following listed cities: Seattle Auburn Renton Aberdeen-Hoquiam Ellensburg Centralia Chelan Zone Pay: Olympia Bremerton Shelton Tacoma Everett Mount Vernon Pt. Townsend 0 -25 Rates Fringes CARPENTER 26-35 radius CENTRAL WASHINGTON: $1.00/hour 36-45 CHELAN, DOUGLAS (WEST OF miles $1.15/hour THE 120TH MERIDIAN), radius miles KITTITAS, OKANOGAN (WEST Over 55 radius miles OF THE 120TH MERIDIAN) AND YAKIMA COUNTIES CARPENTERS ON CREOSOTE MATERIAL ...................$ 40.46 13.66 CARPENTERS .................$ 40.36 13.66 DIVERS TENDER ..............$ 35.02 14.00 DIVERS .....................$ 73.44 14.00 MILLWRIGHT AND MACHINE ERECTORS ...................$ 41.86 13.66 PILEDRIVER, DRIVING, PULLING, CUTTING, PLACING COLLARS, SETTING, WELDING OR CRESOTE TREATED MATERIAL, ALL PILING ....... $ 40.61 13.66 (HOURLY ZONE PAY: WESTERN AND CENTRAL WASHINGTON - ALL CLASSIFICATIONS EXCEPT MILLWRIGHTS AND PILEDRIVERS Hourly Zone Pay shall be paid on jobs located outside of the free zone computed from the city center of the following listed cities: Seattle Auburn Renton Aberdeen-Hoquiam Ellensburg Centralia Chelan Zone Pay: Olympia Bremerton Shelton Tacoma Everett Mount Vernon Pt. Townsend 0 -25 radius miles Free 26-35 radius miles $1.00/hour 36-45 radius miles $1.15/hour 46-55 radius miles $1.35/hour Over 55 radius miles $1.55/hour Bellingham Anacortes Yakima Wenatchee Port Angeles Sunnyside (HOURLY ZONE PAY: WESTERN AND CENTRAL WASHINGTON - MILLWRIGHT AND PILEDRIVER ONLY) Hourly Zone Pay shall be computed from Seattle Union Hall, Tacoma City center, and Everett City center Zone Pay: 0 -25 radius miles Free 26-45 radius miles $ .70/hour Over 45 radius miles $1.50/hour WA160001 Modification 4 Federal Wage Determinations for Highway Construction Page 6 ---------------------------------------------------------------- CARP0770-006 06/01/2015 Rates Fringes CARPENTER WESTERN WASHINGTON: CLALLAM, GRAYS HARBOR, ISLAND, JEFFERSON, KING, KITSAP, LEWIS (excludes piledrivers only), MASON, PACIFIC (North of a straight line made by extending the north boundary line of Wahkiakum County west to the Pacific Ocean), PIERCE, SAN JUAN, SKAGIT, SNOHOMISH, THURSTON AND WHATCOM COUNTIES BRIDGE CARPENTERS .......... $ 40.36 13.66 CARPENTERS ON CREOSOTE 26-35 radius MATERIAL ...................$ 40.46 13.66 CARPENTERS .................$ 40.36 13.66 DIVERS TENDER ..............$ 44.67 13.66 DIVERS .....................$ 93.56 13.66 MILLWRIGHT AND MACHINE $1.55/hour ERECTORS ...................$ 41.86 13.66 PILEDRIVER, DRIVING, PULLING, CUTTING, PLACING COLLARS, SETTING, WELDING OR CRESOTE TREATED MATERIAL, ALL PILING ....... $ 40.61 13.66 (HOURLY ZONE PAY: WESTERN AND CENTRAL WASHINGTON - ALL CLASSIFICATIONS EXCEPT MILLWRIGHTS AND PILEDRIVERS Hourly Zone Pay shall be paid on jobs located outside of the free zone computed from the city center of the following listed cities: Seattle Auburn Renton Aberdeen-Hoquiam Ellensburg Centralia Chelan Zone Pay: Olympia Bremerton Shelton Tacoma Everett Mount Vernon Pt. Townsend 0 -25 radius miles Free 26-35 radius miles $1.00/hour 36-45 radius miles $1.15/hour 46-55 radius miles $1.35/hour Over 55 radius miles $1.55/hour Bellingham Anacortes Yakima Wenatchee Port Angeles Sunnyside (HOURLY ZONE PAY: WESTERN AND CENTRAL WASHINGTON - MILLWRIGHT AND PILEDRIVER ONLY) Hourly Zone Pay shall be computed from Seattle Union Hall, Tacoma City center, and Everett City center Zone Pay: 0 -25 radius miles Free 26-45 radius miles $ .70/hour Over 45 radius miles $1.50/hour WA160001 Modification 4 Federal Wage Determinations for Highway Construction Page 17 ---------------------------------------------------------------- ELEC0046-001 02/01/2016 CALLAM, JEFFERSON, KING AND KITSAP COUNTIES Rates Fringes CABLE SPLICER ....................$ 46.87 30+15.96 ELECTRICIAN ......................$ 45.77 3%+17.91 ---------------------------------------------------------------- ELEC0048-003 01/01/2016 CLARK, KLICKITAT AND SKAMANIA COUNTIES Rates Fringes CABLE SPLICER ....................$ 44.22 21.50 ELECTRICIAN ......................$ 40.20 21.11 HOURLY ZONE PAY: Hourly Zone Pay shall be paid on jobs located outside of the free zone computed from the city center of the following listed cities: Portland, The Dalles, Hood River, Tillamook, Seaside and Astoria Zone Pay: Zone 1: 31-50 miles $1.50/hour Zone 2: 51-70 miles $3.50/hour Zone 3: 71-90 miles $5.50/hour Zone 4: Beyond 90 miles $9.00/hour *These are not miles driven. Zones are based on Delorrne Street Atlas USA 2006 plus. ---------------------------------------------------------------- ELEC0048-029 01/01/2016 COWLITZ AND WAHKIAKUM COUNTY Rates Fringes CABLE SPLICER ....................$ 44.22 21.50 ELECTRICIAN ......................$ 40.20 21.11 ---------------------------------------------------------------- WA160001 Modification 4 Federal Wage Determinations for Highway Construction Page 18 ELECO073-001 07/01/2015 ADAMS, FERRY, LINCOLN, PEND OREILLE, SPOKANE, STEVENS, WHITMAN COUNTIES Rates Fringes CABLE SPLICER ....................$ 34.10 16.68 ELECTRICIAN ......................$ 31.00 16.68 ---------------------------------------------------------------- ELEC0076-002 09/01/2014 GRAYS HARBOR, LEWIS, MASON, PACIFIC, PIERCE, AND THURSTON COUNTIES Rates Fringes CABLE SPLICER ....................$ 37.94 23.36 ELECTRICIAN ......................$ 34.49 23.36 ---------------------------------------------------------------- ELEC0112-005 06/01/2015 ASOTIN, BENTON, COLUMBIA, FRANKLIN, GARFIELD, KITTITAS, WALLA WALLA, YAKIMA COUNTIES Rates Fringes CABLE SPLICER ....................$ 40.74 18.65 ELECTRICIAN ......................$ 38.80 18.59 ---------------------------------------------------------------- ELEC0191-003 06/01/2014 ISLAND, SAN JUAN, SNOHOMISH, SKAGIT AND WHATCOM COUNTIES Rates Fringes CABLE SPLICER ....................$ 44.23 17.73 ELECTRICIAN ......................$ 40.21 17.73 ---------------------------------------------------------------- ELEC0191-004 06/01/2014 CHELAN, DOUGLAS, GRANT AND OKANOGAN COUNTIES Rates Fringes CABLE SPLICER ....................$ 40.82 17.63 ELECTRICIAN ......................$ 37.11 17.63 ---------------------------------------------------------------- WA160001 Modification 4 Federal Wage Determinations for Highway Construction Page 9 ENGI0302-003 06/01/2014 CHELAN (WEST OF THE 120TH MERIDIAN), CLALLAM, DOUGLAS (WEST OF THE 120TH MERIDIAN), GRAYS HARBOR, ISLAND, JEFFERSON, KING, KITSAP, KITTITAS, MASON, OKANOGAN (WEST OF THE 120TH MERIDIAN), SAN JUNA, SKAGIT, SNOHOMISH, WHATCOM AND YAKIMA (WEST OF THE 120TH MERIDIAN) COUNTIES PROJECTS: CATEGORY A PROJECTS (EXCLUDES CATEGORY B PROJECTS, AS SHOWN BELOW) Zone 1 (0-25 radius miles): Rates Fringes Power equipment operators: Group 1A ...................$ 38.39 17.39 Group 1AA..................$ 38.96 17.39 Group 1AAA.................$ 39.52 17.39 Group 1 .....................$ 37.84 17.39 Group 2 .....................$ 37.35 17.39 Group 3 .....................$ 36.93 17.39 Group 4 .....................$ 34.57 17.39 Zone Differential (Add to Zone 1 rates): Zone 2 (26-45 radius miles) - $1.00 Zone 3 (Over 45 radius miles) - $1.30 BASEPOINTS: Aberdeen, Bellingham, Bremerton, Everett, Kent, Mount Vernon, Port Angeles, Port Townsend, Seattle, Shelton, Wenatchee, Yakima POWER EQUIPMENT OPERATORS CLASSIFICATIONS GROUP 1AAA - Cranes -over 300 tons, or 300 ft of boom (including jib with attachments) GROUP 1AA - Cranes 200 to 300 tons, or 250 ft of boom (including jib with attachments); Tower crane over 175 ft in height, base to boom GROUP lA - Cranes, 100 tons thru 199 tons, or 150 ft of boom (including jib with attachments); Crane -overhead, bridge type, 100 tons and over; Tower crane up to 175 ft in height base to boom; Loaders -overhead, 8 yards and over; Shovels, excavator, backhoes-6 yards and over with attachments GROUP 1 - Cableway; Cranes 45 tons thru 99 tons, under 150 ft of boom (including jib with attachments); Crane -overhead, bridge type, 45 tons thru 99 tons; Derricks on building work; Excavator, shovel, backhoes over 3 yards and under 6 yards; Hard tail end dump articulating off-road equipment 45 yards and over; Loader- overhead 6 yards to, but not including 8 yards; Mucking machine, mole, tunnel, drill and/or shield; Quad 9, HD 41, D-10; Remote control operator on rubber tired earth moving equipment; Rollagon; Scrapers -self propelled 45 yards and over; Slipform pavers; Transporters, all truck or track type WA160001 Modification 4 Federal Wage Determinations for Highway Construction Page 110 GROUP 2 - Barrier machine (zipper); Batch Plant Operaor- Concrete; Bump Cutter; Cranes, 20 tons thru 44 tons with attachments; Crane -overhead, bridge type -20 tons through 44 tons; Chipper; Concrete Pump -truck mount with boom attachment; Crusher; Deck Engineer/Deck Winches (power); Drilling machine; Excavator, shovel, backhoe-3yards and under; Finishing Machine, Bidwell, Gamaco and similar equipment; Guardrail punch; Horizontal/directional drill operator; Loaders -overhead under 6 yards; Loaders -plant feed; Locomotives -all; Mechanics -all; Mixers -asphalt plant; Motor patrol graders -finishing; Piledriver (other than crane mount); Roto-mill,roto-grinder; Screedman, spreader, topside operator-Blaw Knox, Cedar Rapids, Jaeger, Caterpillar, Barbar Green; Scraper -self propelled, hard tail end dump, articulating off-road equipment -under 45 yards; Subgrade trimmer; Tractors, backhoes-over 75 hp; Transfer material service machine -shuttle buggy, blaw knox-roadtec; Truck crane oiler/driver-100 tons and over; Truck Mount portable conveyor; Yo Yo Pay dozer GROUP 3 - Conveyors; Cranes-thru 19 tons with attachments; A -frame crane over 10 tons; Drill oilers -auger type, truck or crane mount; Dozers -D-9 and under; Forklift -3000 lbs. and over with attachments; Horizontal/directional drill locator; Outside hoists -(elevators and manlifts), air tuggers, strato tower bucket elevators; Hydralifts/boom trucks over 10 tons; Loader -elevating type, belt; Motor patrol grader-nonfinishing; Plant oiler- asphalt, crusher; Pumps -concrete; Roller, plant mix or multi -lift materials; Saws -concrete; Scrpers-concrete and carry -all; Service engineer -equipment; Trenching machines; Truck Crane Oiler/Driver under 100 tons; Tractors, backhoe 75 hp and under GROUP 4 - Assistant Engineer; Bobcat; Brooms; Compressor; Concrete finish mahine-laser screed; Cranes -A frame -10 tons and under; Elevator and Manlift-permanent or shaft type; Gradechecker, Stakehop; Forklifts under 3000 lbs. with attachments; Hydralifts/boom trucks, 10 tons and under; Oil distributors, blower distribution and mulch seeding operator; Pavement breaker; Posthole digger, mechanical; Power plant; Pumps, water; Rigger and Bellman; Roller -other than plant mix; Wheel Tractors, farmall type; Shotcrete/gunite equipment operator WA160001 Modification 4 Federal Wage Determinations for Highway Construction Page 11 Category B Projects: 950 of the basic hourly reate for each group plus full fringe benefits applicable to category A projects shall apply to the following projects. A Reduced rates may be paid on the following: 1. Projects involving work on structures such as buildings and bridges whose total value is less than $1.5 million excluding mechanical, electrical, and utility portions of the contract. 2. Projects of less than $1 million where no building is involved. Surfacing and paving included, but utilities excluded. 3. Marine projects (docks, wharfs, etc.) less than $150,000. HANDLING OF HAZARDOUS WASTE MATERIALS: Personnel in all craft classifications subject to working inside a federally designated hazardous perimeter shall be elgible for compensation in accordance with the following group schedule relative' to the level of hazardous waste as outlined in the specific hazardous waste project site safety plan. H-1 Base wage rate when on a hazardous waste site when not outfitted with protective clothing H-2 Class "C" Suit - Base wage rate plus $ .25 per hour. H-3 Class "B" Suit - Base wage rate plus $ .50 per hour. H-4 Class "A" Suit - Base wage rate plus $ .75 per hour. Zone Differential (Add to Zone 1 rates): Zone 2 (26-45 radius miles) - $ .70 Zone 3 (Over 45 radius miles) - $1.00 BASEPOINTS: Aberdeen, Bellingham, Bremerton, Everett, Kent, Mount Vernon, Port Angeles, Port Townsend, Seattle, Shelton, Wenatchee, Yakima WA160001 Modification 4 Federal Wage Determinations for Highway Construction Page 112 POWER EQUIPMENT OPERATORS CLASSIFICATIONS GROUP 1AAA - Cranes -over 300 tons, or 300 ft of boom (including jib with attachments) GROUP 1AA - Cranes 200 to 300 tons, or 250 ft of boom (including jib with attachments); Tower crane over 175 ft in height, base to boom GROUP lA - Cranes, 100 tons thru 199 tons, or 150 ft of boom (including jib with attachments); Crane -overhead, bridge type, 100 tons and over; Tower crane up to 175 ft in height base to boom; Loaders -overhead, 8 yards and over; Shovels, excavator, backhoes-6 yards and over with attachments GROUP 1 - Cableway; Cranes 45 tons thru 99 tons, under 150 ft of boom (including jib with attachments); Crane -overhead, bridge type, 45 tons thru 99 tons; Derricks on building work; Excavator, shovel, backhoes over 3 yards and under 6 yards; Hard tail end dump articulating off-road equipment 45 yards and over; Loader- overhead 6 yards to, but not including 8 yards; Mucking machine, mole, tunnel, drill and/or shield; Quad 9, HD 41, D-10; Remote control operator on rubber tired earth moving equipment; Rollagon; Scrapers -self propelled 45 yards and over; Slipform pavers; Transporters, all truck or track type GROUP 2 - Barrier machine (zipper); Batch Plant Operaor- Concrete; Bump Cutter; Cranes, 20 tons thru 44 tons with attachments; Crane -overhead, bridge type -20 tons through 44 tons; Chipper.; Concrete Pump -truck mount with boom attachment; Crusher; Deck Engineer/Deck Winches (power); Drilling machine; Excavator, shovel, backhoe -3 yards and under; Finishing Machine, Bidwell, Gamaco and similar equipment; Guardrail punch; Horizontal/directional drill operator; Loaders -overhead under 6 yards; Loaders -plant feed; Locomotives -all; Mechanics -all; Mixers -asphalt plant; Motor patrol graders -finishing; Piledriver (other than crane mount); Roto-mill,roto-grinder; Screedman, spreader, topside operator-Blaw Knox, Cedar Rapids, Jaeger, Caterpillar, Barbar Green; Scraper -self propelled, hard tail end dump, articulating off-road equipment -under 45 yards; Subgrade trimmer; Tractors, backhoes-over 75 hp; Transfer material service machine -shuttle buggy, blaw knox-roadtec; Truck crane oiler/driver-100 tons and over; Truck Mount portable conveyor; Yo Yo Pay dozer WA160001 Modification 4 Federal Wage Determinations for Highway Construction Page 13 GROUP 3 - Conveyors; Cranes-thru 19 tons with attachments; A -frame crane over 10 tons; Drill oilers -auger type, truck or crane mount; Dozers -D-9 and under; Forklift -3000 lbs. and over with attachments; Horizontal/directional drill locator; Outside hoists -(elevators and manlifts), air tuggers, strato tower bucket elevators; Hydralifts/boom trucks over 10 tons; Loader -elevating type, belt; Motor patrol grader-nonfinishing; Plant oiler- asphalt, crusher; Pumps -concrete; Roller, plant mix or multi -lift materials; Saws -concrete; Scrpers-concrete and carry -all; Service engineer -equipment; Trenching machines; Truck Crane Oiler/Driver under 100 tons; Tractors, backhoe 75 hp and under GROUP 4 - Assistant Engineer; Bobcat; Brooms; Compressor; Concrete finish mahine-laser screed; Cranes -A frame -10 tons and under; Elevator and Manlift-permanent or shaft type; Gradechecker, Stakehop; Forklifts under 3000 lbs. with attachments; Hydralifts/boom trucks, 10 tons and under; Oil distributors, blower distribution and mulch seeding operator; Pavement breaker; Posthole digger, mechanical; Power plant; Pumps, water; Rigger and Bellman; Roller -other than plant mix; Wheel Tractors, farmall type; Shotcrete/gunite equipment operator CATEGORY B PROJECTS: 95% OF THE BASIC HOURLY RATE FOR EACH GROUP PLUS FULL FRINGE BENEFITS APPLICABLE TO CATEGORY A PROJECTS SHALL APPLY TO THE FOLLOWING PROJECTS. REDUCED RATES MAY BE PAID ON THE FOLLOWING: 1. Projects involving work on structures such as buildings and bridges whose total value is less than $1.5 million excluding mechanical, electrical, and utility portions of the contract. 2. Projects of less than $1 million where no building is involved. Surfacing and paving including, but utilities excluded. 3. Marine projects (docks, wharfs, ect.) less than $150,000. HANDLING OF HAZARDOUS WASTE MATERIALS: Personnel in all craft classifications subject to working inside a federally designed hazardous perimeter shall be elgible for compensation in accordance with the following group schedule relative to the level of hazardous waste as outlined in the specific hazardous waste project site safety plan. H-1 Base wage rate when on a hazardous waste site when not outfitted with protective clothing. H-2 Class "C" Suit - Base wage rate plus $.25 per hour. H-3 Class "B" Suit - Base wage rate plus $.50 per hour. H-4 Class "A" Suit - Base wage rate plus $.75 per hour. WA160001 Modification 4 Federal Wage Determinations for Highway Construction Page 114 ENGI0370-002 06/01/2015 ADAMS, ASOTIN, BENTON, CHELAN (EAST OF THE 120TH MERIDIAN), COLUMBIA, DOUGLAS (EAST OF THE 120TH MERIDIAN), FERRY, FRANKLIN, GARFIELD, GRANT, LINCOLN, OKANOGAN (EAST OF THE 120TH MERIDIAN), PEND OREILLE, SPOKANE, STEVENS, WALLA WALLA, WHITMAN AND YAKIMA (EAST OF THE 120TH MERIDIAN) COUNTIES ZONE 1: ZONE DIFFERENTIAL (Add to Zone 1 rate): Zone 2 - $2.00 Zone 1: Within 45 mile radius of Spokane, Pasco, Washington; Lewiston, Idaho Zone 2: Outside 45 mile radius of Spokane, Pasco, Washington; Lewiston, Idaho POWER EQUIPMENT OPERATORS CLASSIFICATIONS GROUP 1: Bit Grinders; Bolt Threading Machine; Compressors (under 2000 CFM, gas, diesel, or electric power); Deck Hand; Fireman & Heater Tender; Hydro -seeder, Mulcher, Nozzleman; Oiler Driver, & Cable Tender, Mucking Machine; Pumpman; Rollers, all types on subgrade, including seal and chip coatings (farm type, Case, John Deere & similar, or Compacting Vibrator), except when pulled by Dozer with operable blade; Welding Machine; Crane Oiler -Driver (CLD required) & Cable Tender, Mucking Machine WA160001 Modification 4 Federal Wage Determinations for Highway Construction Rates Fringes POWER EQUIPMENT OPERATOR GROUP 1 .....................$ 26.16 13.55 GROUP 2 .....................$ 26.48 13.55 GROUP 3 .....................$ 27.09 13.55 GROUP 4 .....................$ 27.25 13.55 GROUP 5 .....................$ 27.41 13.55 GROUP 6 .....................$ 27.69 13.55 GROUP 7 .....................$ 27.96 13.55 GROUP 8 .....................$ 29.06 13.55 ZONE DIFFERENTIAL (Add to Zone 1 rate): Zone 2 - $2.00 Zone 1: Within 45 mile radius of Spokane, Pasco, Washington; Lewiston, Idaho Zone 2: Outside 45 mile radius of Spokane, Pasco, Washington; Lewiston, Idaho POWER EQUIPMENT OPERATORS CLASSIFICATIONS GROUP 1: Bit Grinders; Bolt Threading Machine; Compressors (under 2000 CFM, gas, diesel, or electric power); Deck Hand; Fireman & Heater Tender; Hydro -seeder, Mulcher, Nozzleman; Oiler Driver, & Cable Tender, Mucking Machine; Pumpman; Rollers, all types on subgrade, including seal and chip coatings (farm type, Case, John Deere & similar, or Compacting Vibrator), except when pulled by Dozer with operable blade; Welding Machine; Crane Oiler -Driver (CLD required) & Cable Tender, Mucking Machine WA160001 Modification 4 Federal Wage Determinations for Highway Construction P a g e 115 GROUP 2: A -frame Truck (single drum); Assistant Refrigeration Plant (under 1000 ton); Assistant Plant Operator, Fireman or Pugmixer (asphalt); Bagley or Stationary Scraper; Belt Finishing Machine; Blower Operator (cement); Cement Hog; Compressor (2000 CFM or over, 2 or more, gas diesel or electric power); Concrete Saw (multiple cut); Distributor Leverman; Ditch Witch or similar; Elevator Hoisting Materials; Dope Pots (power agitated); Fork Lift or Lumber Stacker, hydra -lift & similar; Gin Trucks (pipeline); Hoist, single drum; Loaders (bucket elevators and conveyors); Longitudinal Float; Mixer (portable -concrete); Pavement Breaker, Hydra -Hammer & similar; Power Broom; Railroad Ballast Regulation Operator (self-propelled); Railroad Power Tamper Operator (self-propelled); Railroad Tamper Jack Operator (self-propelled; Spray Curing Machine (concrete); Spreader Box (self-propelled); Straddle Buggy (Ross & similar on construction job only); Tractor (Farm type R/T with attachment, except Backhoe); Tugger Operator GROUP 3: A -frame Truck (2 or more drums); Assistant Refrigeration Plant & Chiller Operator (over 1000 ton); Backfillers (Cleveland & similar); Batch Plant & Wet Mix Operator, single unit (concrete); Belt -Crete Conveyors with power pack or similar; Belt Loader (Kocal or similar); Bending Machine; Bob Cat (Skid Steer); Boring Machine (earth); Boring Machine (rock under 8 inch bit) (Quarry Master, Joy or similar); Bump Cutter (Wayne, Saginau or similar); Canal Lining Machine (concrete); Chipper (without crane); Cleaning & Doping Machine (pipeline); Deck Engineer; Elevating Belt -type Loader (Euclid, Barber Green & similar); Elevating Grader -type Loader (Dumor, Adams or similar); Generator Plant Engineers (diesel or electric); Gunnite Combination Mixer & Compressor; Locomotive Engineer; Mixermobile; Mucking Machine; Posthole Auger or Punch; Pump (grout or jet); Soil Stabilizer (P & H or similar); Spreader Machine; Dozer/Tractor (up to D-6 or equivalent) and Traxcavator; Traverse Finish Machine; Turnhead Operator GROUP 4: Concrete Pumps (squeeze -Crete, flow -Crete, pump- crete, Whitman & similar); Curb Extruder (asphalt or concrete); Drills (churn, core, calyx or diamond); Equipment Serviceman; Greaser & Oiler; Hoist (2 or more drums or Tower Hoist); Loaders (overhead & front-end, under 4 yds. R/T); Refrigeration Plant Engineer (under 1000 ton); Rubber -tired Skidders (R/T with or without attachments); Surface Heater & Plant Machine; Trenching Machines (under 7 ft. depth capacity); Turnhead (with re -screening); Vacuum Drill (reverse circulation drill under 8 inch bit) WA160001 Modification 4 Federal Wage Determinations for Highway Construction Page 116 GROUP 5: Backhoe (under 45,000 gw); Backhoe & Hoe Ram (under 3/4 yd.); Carrydeck & Boom Truck (under 25 tons); Cranes (25 tons & under), all attachments including clamshell, dragline; Derricks & Stifflegs (under 65 tons); Drilling Equipment(8 inch bit & over) (Robbins, reverse circulation & similar); Hoe Ram; Piledriving Engineers; Paving (dual drum); Railroad Track Liner Operaotr (self-propelled); Refrigeration Plant Engineer (1000 tons & over); Signalman (Whirleys, Highline Hammerheads or similar); Grade Checker GROUP 6: Asphalt Plant Operator; Automatic Subgrader (Ditches & Trimmers)(Autograde, ABC, R.A. Hansen & similar on grade wire); Backhoe (45,000 gw and over to 110,000 gw); Backhoes & Hoe Ram (3/4 yd. to 3 yd.); Batch Plant (over 4 units); Batch & Wet Mix Operator (multiple units, 2 & incl. 4); Blade Operator (motor patrol & attachments); Cable Controller (dispatcher); Compactor (self-propelled with blade); Concrete Pump Boom Truck; Concrete Slip Form Paver; Cranes (over 25 tons, to and including 45 tons), all attachments including clamshell, dragline; Crusher, Grizzle & Screening Plant Operator; Dozer, 834 R/T & similar; Drill Doctor; Loader Operator (front-end & overhead, 4 yds. incl. 8 yds.); Multiple Dozer Units with single blade; Paving Machine (asphalt and concrete); Quad -Track or similar equipment; Rollerman (finishing asphalt pavement); Roto Mill (pavement grinder); Scrapers, all, rubber -tired; Screed Operator; Shovel(under 3 yds.); Trenching Machines (7 ft. depth & over); Tug Boat Operator Vactor.guzzler, super sucker; Lime Batch Tank Operator (REcycle Train); Lime Brain Operator (Recycle Train); Mobile Crusher Operator (Recycle Train) GROUP 7: Backhoe (over 110,000 gw); Backhoes & Hoe Ram (3 yds & over); Blade (finish & bluetop) Automatic, CMI, ABC, Finish Athey & Huber & similar when used as automatic; Cableway Operators; Concrete Cleaning/Decontamination machine operator; Cranes (over 45 tons to but not including 85 tons), all attachments including clamshell and dragine; Derricks & Stiffleys (65 tons & over); Elevating Belt (Holland type); Heavy equipment robotics operator; Loader (360 degrees revolving Koehring Scooper or similar); Loaders (overhead & front-end, over 8 yds. to 10 yds.); Rubber -tired Scrapers (multiple engine with three or more scrapers); Shovels (3 yds. & over); Whirleys & Hammerheads, ALL; H.D. Mechanic; H.D. Welder; Hydraulic Platform Trailers (Goldhofer, Shaurerly andSimilar); Ultra High Pressure Wateriet Cutting Tool System Operator (30,000 psi); Vacuum Blasting Machine Operator WA160001 Modification 4 Federal Wage Determinations for Highway Construction Page 117 GROUP 8: Cranes (85 tons and over, and all climbing, overhead,rail and tower), all attachments including clamshell, dragline; Loaders (overhead and front-end, 10 yards and over); Helicopter Pilot BOOM PAY: (All Cranes, Including Tower) 180 ft to 250 ft $ .50 over scale Over 250 ft $ .80 over scale NOTE: In computing the length of the boom on Tower Cranes, they shall be measured from the base of the Tower to the point of the boom. HAZMAT: Anyone working on HAZMAT jobs, working with supplied air shall receive $1.00 an hour above classification. ---------------------------------------------------------------- ENGI0612-012 06/01/2014 LEWIS,PIERCE, PACIFIC (portion lying north of a parallel line extending west from the northern boundary of Wahkaikum County to the sea) AND THURSTON COUNTIES ON PROJECTS DESCRIBED IN FOOTNOTE A BELOW, THE RATE FOR EACH GROUP SHALL BE 90 OF THE BASE RATE PLUS FULL FRINGE BENEFITS. ON ALL OTHER WORK, THE FOLLOWING RATES APPLY. Zone 1 (0-25 radius miles): Zone Differential (Add to Zone 1 rates): Zone 2 (26-45 radius miles) = $1.00 Zone 3 (Over 45 radius miles) - $1.30 BASEPOINTS: CENTRALIA, OLYMPIA, TACOMA WA160001 Modification 4 Federal Wage Determinations for Highway Construction Rates Fringes POWER EQUIPMENT OPERATOR GROUP 1A ...................$ 38.39 17.40 GROUP 1AA..................$ 38.96 17.40 GROUP 1AAA.................$ 39.52 17.40 GROUP 1 .....................$ 37.84 17.40 GROUP 2............'.........$ 37.35 17.40 GROUP 3 .....................$ 36.93 17.40 GROUP 4 .....................$ 34.57 17.40 Zone Differential (Add to Zone 1 rates): Zone 2 (26-45 radius miles) = $1.00 Zone 3 (Over 45 radius miles) - $1.30 BASEPOINTS: CENTRALIA, OLYMPIA, TACOMA WA160001 Modification 4 Federal Wage Determinations for Highway Construction Page 118 POWER EQUIPMENT OPERATORS CLASSIFICATIONS GROUP 1 AAA - Cranes -over 300 tons or 300 ft of boom (including jib with attachments) GROUP 1AA - Cranes- 200 tonsto 300 tons, or 250 ft of boom (including jib with attachments; Tower crane over 175 ft in height, bas to boom GROUP lA - Cranes, 100 tons thru 199 tons, or 150 ft of boom (including jib with attachments); Crane -overhead, bridge type, 100 tons and over; Tower crane up to 175 ft in height base to boom; Loaders -overhead, 8 yards and over; Shovels, excavator, backhoes-6 yards and over with attachments GROUP 1 - Cableway; Cranes 45 tons thru 99 tons under 150 ft of boom (including jib with attachments); Crane -overhead, bridge type, 45 tons thru 99 tons; Derricks on building work; Excavator, shovel, backhoes over 3 yards and under 6 yards; Hard tail end dump articulating off-road equipment 45 yards and over; Loader- overhead, 6 yards to, but not including, 8 yards; Mucking machine, mole, tunnel, drill and/or shield; Quad 9 HD 41, D-10; Remote control operator on rubber tired earth moving equipment; Rollagon; Scrapers - self -propelled 45 yards and over; Slipform pavers; Transporters, all track or truck type GROUP 2 - Barrier machine (zipper); Batch Plant Operator - concrete; Bump Cutter; Cranes, 20 tons thru 44 tons with attachments; Crane -Overhead, bridge type, 20 tons through 44 tons; Chipper; Concrete pump -truck mount with boom attachment; Crusher; Deck engineer/deck winches (power); Drilling machine; Excavator, shovel, backhoe -3 yards and under; Finishing machine, Bidwell, Gamaco and similar equipment; Guardrail punch; Loaders, overhead under 6 yards; Loaders -plant feed; Locomotives -all; Mechanics- all; Mixers, asphalt plant; Motor patrol graders, finishing; Piledriver (other than crane mount); Roto -mill, roto - grinder; Screedman, spreader, topside operator-Blaw Knox, Cedar Rapids, Jaeger, Caterpillar, Barbar Green; Scraper -self- propelled, hard tail end dump, articulating off-road equipment- under 45 yards; Subgrader trimmer; Tractors, backhoe over 75 hp; Transfer material service machine -shuttle buggy, Blaw Knox- Roadtec; Truck Crane oiler/driver-100 tons and over; Truck Mount Portable Conveyor; Yo Yo pay WA160001 Modification 4 Federal Wage Determinations for Highway Construction P a -.-....... g e 19 GROUP 3 - Conveyors; Cranes through 19 tons with attachments; Crane -A -frame over 10 tons; Drill oilers -auger type, truck or crane mount; Dozer -D-9 and under; Forklift -3000 lbs. and over with attachments; Horizontal/directional drill locator; Outside Hoists -(elevators and manlifts), air tuggers, strato tower bucket elevators; Hydralifts/boom trucks over 10 tons; Loaders -elevating type, belt; Motor patrol grader-nonfinishing; Plant oiler- asphalt, crusher; Pump -Concrete; Roller, plant mix or multi-lfit materials; Saws -concrete; Scrapers, concrete and carry all; Service engineers -equipment; Trenching machines; Truck crane oiler/driver under 100 tons; Tractors, backhoe under 75 hp GROUP 4 - Assistant Engineer; Bobcat; Brooms; Compressor; Concrete Finish Machine -laser screed; Cranes A -frame 10 tons and under; Elevator and manlift (permanent and shaft type); Forklifts -under 3000 lbs. with attachments; Gradechecker, stakehop; Hydralifts/boom trucks, 10 tons and under; Oil distributors, blower distribution and mulch seeding operator; Pavement breaker; Posthole digger -mechanical; Power plant; Pumps -water; Rigger and Bellman; Roller -other than plant mix; Wheel Tractors, farmall type; Shotcrete/gunite equipment operator FOOTNOTE A- Reduced rates may be paid on the following: 1. Projects involving work on structures such as buildings and bridges whose total value is less than $1.5 million excluding mechanical, electrical, and utility portions of the contract. 2. Projects of less than $1 million where no building is involved. Surfacing and paving included, but utilities excluded. 3. Marine projects (docks, wharfs, etc.) less than $150,000. HANDLING OF HAZARDOUS WASTE MATERIALS: Personnel in all craft classifications subject to working inside a federally designated hazardous perimeter shall be elgible for compensation in accordance with the following group schedule relative to the level of hazardous waste as outlined in the specific hazardous waste project site safety plan. H-1 Base wage rate when on a hazardous waste site when not outfitted with protective clothing, Class "D" Suit - Base wage rate plus $ .50 per hour. H-2 Class "C" Suit - Base wage rate plus $1.00 per hour. H-3 Class "B" Suit - Base wage rate plus $1.50 per hour. H-4 Class "A" Suit - Base wage rate plus $2.00 per hour. WA160001 Modification 4 Federal Wage Determinations for Highway Construction ENGI0701-002 01/01/2015 CLARK, COWLITZ, KLICKKITAT, PACIFIC (SOUTH), SKAMANIA, AND WAHKIAKUM COUNTIES POWER RQUIPMENT OPERATORS: ZONE 1 Rates POWER EQUIPMENT OPERATOR GROUP 1 .....................$ 39.47 GROUP 1A ....................$ 41.44 GROUP 1B ....................$ 43.42 GROUP 2 .....................$ 37.58 GROUP 3 .....................$ 36.44 GROUP 4 .....................$ 35.36 GROUP 5 .....................$ 34.13 GROUP 6 .....................$ 30.94 Zone Differential (add to Zone 1 rates): Zone 2 - $3.00 Zone 3 - $6.00 WA160001 Modification 4 Federal Wage Determinations for Highway Construction Fringes 14.10 14.10 14.10 14.10 14.10 14.10 14.10 14.10 Page 120 Page 121 For the following metropolitan counties: MULTNOMAH; CLACKAMAS; MARION; WASHINGTON; YAMHILL; AND COLUMBIA; CLARK; AND COWLITZ COUNTY, WASHINGTON WITH MODIFICATIONS AS INDICATED: All jobs or projects located in Multnomah, Clackamas and Marion Counties, West of the western boundary of Mt. Hood National Forest and West of Mile Post 30 on Interstate 84 and West of Mile Post 30 on State Highway 26 and West of Mile Post 30 on Highway 22 and all jobs or projects located in Yamhill County, Washington County and Columbia County and all jobs or porjects located in Clark & Cowlitz County, Washington except that portion of Cowlitz County in the Mt. St. Helens "Blast Zone" shall receive Zone I pay for all classifications. All jobs or projects located in the area outside the identified boundary above, but less than 50 miles from the Portland City Hall shall receive Zone II pay for all classifications. All jobs or projects located more than 50 miles from the Portland City Hall, but outside the identified border above, shall receive Zone III pay for all classifications. For the following cities: ALBANY; BEND; COOS BAY; EUGENE; GRANTS PASS; KLAMATH FALLS; MEDFORD; ROSEBURG All jobs or projects located within 30 miles of the respective city hall of the above mentioned cities shall receive Zone I pay for all classifications. All jobs or projects located more than 30 miles and less than 50 miles from the respective city hall of the above mentioned cities shall receive Zone II pay for all classifications. All jobs or projects located more than 50 miles from the respective city hall of the above mentioned cities shall receive Zone III pay for all classifications. WA160001 Modification 4 Federal Wage Determinations for Highway Construction Page 122 POWER EQUIPMENT OPERATORS CLASSIFICATIONS Group 1 Concrete Batch Plan and or Wet mix three (3) units or more; Crane, Floating one hundred and fifty (150) ton but less than two hundred and fifty (250) ton; Crane, two hundred (200) ton through two hundred ninety nine (299) ton with two hundred foot (200') boom or less (including jib, inserts and/or attachments); Crane, ninety (90) ton through one hundred ninety nine (199) ton with over two hundred (200') boom Including jib, inserts and/or attachments); Crane, Tower Crane with one hundred seventy five foot (175') tower or less and with less than two hundred foot (200') jib; Crane, Whirley ninety (90) ton and over; Helicopter when used in erecting work Group lA Crane, floating two hundred fifty (250) ton and over; Crane, two hundred (200) ton through two hundred ninety nine (299) ton, with over two hundred foot (200') boom (including jib, inserts and/or attachments); Crane, three hundred (300) ton through three hundred ninety nine (399) ton; Crane, Tower Crane with over one hundred seventy five foot (175') tower or over two hundred foot (200') jib; Crane, tower Crane on rail system or 2nd tower or more in work radius Group 1B Crane, three hundred (300) ton through three hundred ninety nine (399) ton, with over two hundred foot (200') boom (including jib, inserts and/or attachments); Floating crane, three hundred fifty (350) ton and over; Crane, four hundred (400) ton and over Group 2 Asphalt Plant (any type); Asphalt Roto -Mill, pavement profiler eight foot (81) lateral cut and over; Auto Grader or "Trimmer"; Blade, Robotic; Bulldozer, Robotic Equipment (any type); Bulldozer, over one hundred twenty thousand (120,000) lbs. and above; Concrete Batch Plant and/or Wet Mix one (1) and two (2) drum; Concrete Diamond Head Profiler; Canal Trimmer; Concrete, Automatic Slip Form Paver (Assistant to the Operator required); Crane, Boom Truck fifty (50) ton and with over one hundred fifty foot (150') boom and over; Crane, Floating (derrick barge) thirty (30) ton but less than one hundred fifty (150) ton; Crane, Cableway twenty-five (25) ton and over; Crane, Floating Clamshell three (3) cu. Yds. And over; Crane, ninety (90) ton through one hundred ninety nine (199) ton up to and including two hundred foot (200') of boom (including jib inserts and/or attachments); Crane, fifty (50) ton through eighty nine (89) ton with over one hundred fifty foot (150') boom (including jib inserts and/or attachments); Crane, Whirley under ninety (90) ton; Crusher Plant; Excavator over one hundred thirty thousand (130,000) lbs.; Loader one hundred twenty thousand (120,000) lbs. and above; Remote Controlled Earth Moving Equipment; Shovel, Dragline, Clamshell, five (5) cu. Yds. And over; Underwater Equipment remote or otherwise, when used in construction work; Wheel Excavator any size WA160001 Modification 4 Federal Wage Determinations for Highway Construction _..-.. -.... ... - --...-------...._._._- P age 23 Group 3 Bulldozer, over seventy thousand (70,000) lbs. up to and including one hundred twenty thousand (120,000) lbs.; Crane, Boom Truck fifty (50) ton and over with less than one hundred fifty foot (150') boom; Crane, fifty (50) ton through eighty nine (89) ton with one hundred fifty foot (150') boom or less (including jib inserts and/or attachments); Crane, Shovel, Dragline or Clamshell three (3) cu. yds. but less than five (5) cu. Yds.; Excavator over eighty thousand (80,000) lbs. through one hundred thirty thousand (130,000) lbs.; Loader sixty thousand (60,000) lbs. and less than one hundred twenty thousand (120,000) lbs. Group 4 Asphalt, Screed; Asphalt Paver; Asphalt Roto -Mill, pavement profiler, under eight foot (8') lateral cut; Asphalt, Material Transfer Vehicle Operator; Back Filling Machine; Backhoe, Robotic, track and wheel type up to and including twenty thousand (20,000) lbs. with any attachments; Blade (any type); Boatman; Boring Machine; Bulldozer over twenty thousand (20,000) lbs. and more than one hundred (100) horse up to seventy thousand (70,000) lbs.; Cable -Plow (any type); Cableway up to twenty five (25) ton; Cat Drill (John Henry); Chippers; Compactor, multi -engine; Compactor, Robotic; Compactor with blade self-propelled; Concrete, Breaker; Concrete, Grout Plant; Concrete, Mixer Mobile; Concrete, Paving Road Mixer; Concrete, Reinforced Tank Banding Machine; Crane, Boom Truck twenty (20) ton and under fifty (50) ton; Crane, Bridge Locomotive, Gantry and Overhead; Crane, Carry Deck; Crane, Chicago Boom and similar types; Crane, Derrick Operator, under one hundred (100) ton; Crane, Floating Clamshell, Dragline, etc. Operator, under three (3) cu. yds. Or less than thirty (30) ton; Crane, under fifty (50) ton; Crane, Quick Tower under one hundred foot (100') in height and less than one hundred fifty foot (150') jib (on rail included); Diesel -Electric Engineer (Plant or Floating); Directional Drill over twenty thousand (20,000) lbs. pullback; Drill Cat Operator; -Drill Doctor and/or Bit Grinder; Driller, Percussion, Diamond, Core, Cable, Rotary and similar type; Excavator Operator over twenty thousand (20,000) lbs. through eighty thousand (80,000) lbs.; Generator Operator; Grade -all; Guardrail Machines, i.e. punch, auger, etc.; Hammer Operator (Piledriver); Hoist, stiff leg, guy derrick or similar type, fifty (50) ton and over; Hoist, two (2) drums or more; Hydro Axe (loader mounted or similar type); Jack Operator, Elevating Barges, Barge Operator, self -unloading; Loader Operator, front end and overhead, twenty five thousand (25,000) lbs. and less than sixty thousand (60,000) lbs.; Log Skidders; Piledriver Operator (not crane type); Pipe, Bending, Cleaning, Doping and Wrapping Machines; Rail, Ballast Tamper Multi -Purpose; Rubber -tired Dozers and Pushers; Scraper, all types; Side -Boom; Skip Loader, Drag Box; Strump Grinder (loader mounted or similar type); Surface Heater and Planer; Tractor, rubber -tired, over fifty (50) HP Flywheel; Trenching Machine three foot (3') depth and deeper; Tub Grinder (used for wood debris); WA160001 Modification 4 Federal Wage Determinations for Highway Construction Page 124 Tunnel Boring Machine Mechanic; Tunnel, Mucking Machine; Ultra High Pressure Water Jet Cutting Tool System Operator; Vacuum Blasting Machine Operator; Water pulls, Water wagons Group 5 Asphalt, Extrusion Machine; Asphalt, Roller (any asphalt mix); Asphalt, Roto -Mill pavement profiler ground man; Bulldozer, twenty thousand (20,000) lbs. or less, or one hundred (100) horse or less; Cement Pump; Chip Spreading Machine; Churn Drill and Earth Boring Machine; Compactor, self-propelled without blade; Compressor, (any power) one thousand two hundred fifty (1,250) cu. ft. and over, total capacity; Concrete, Batch Plant Quality control; Concrete, Combination Mixer and compressor operator, gunite work; Concrete, Curb Machine, Mechanical Berm, Curb and/or Curb and Gutter; Concrete, Finishing Machine; Concrete, Grouting Machine; Concrete, Internal Full Slab Vibrator Operator; Concrete, Joint Machine; Concrete, Mixer single drum, any capacity; Concrete, Paving Machine eight foot (8') or less; Concrete, Planer; Concrete, Pump; Concrete, Pump Truck; Concrete, Pumperete Operator (any type); Concrete, Slip Form Pumps, power driven hydraulic lifting device for concrete forms; Conveyored Material Hauler; Crane, Boom Truck under twenty (20) tons; Crane, Boom Type lifting device, five (5) ton capacity or less; Drill, Directional type less than twenty thousand (20,000) lbs. pullback; Fork Lift, over ten (10) ton or Robotic; Helicopter Hoist; Hoist Operator, single drum; Hydraulic Backhoe track type up to and including twenty thousand (20,000) lbs.; Hydraulic Backhoe wheel type (any make); Laser Screed; Loaders, rubber -tired type, less than twenty five thousand (25,000) lbs.; Pavement Grinder and/or Grooving Machine (riding type); Pipe, cast in place Pipe Laying Machine; Pulva-Mixer or similar types; Pump Operator, more than five (5) pumps (any size); Rail, Ballast Compactor, Regulator, or Tamper machines; Service Oiler (Greaser); Sweeper Self -Propelled; Tractor, Rubber -Tired, fifty (50) HP flywheel and under; Trenching Machine Operator, maximum digging capacity three foot (3') depth; Tunnel, Locomotive, Dinkey; Tunnel, Power Jumbo setting slip forms, etc. Group 6 Asphalt, Pugmill (any type); Asphalt, Raker; Asphalt, Truck Mounted Asphalt Spreader, with Screed; Auger Oiler; Boatman; Bobcat, skid steed (less than one (1) yard); Broom, self-propelled; Compressor Operator (any power) under 1,250 cu. ft. total capacity; Concrete Curing Machine (riding type); Concrete Saw; Conveyor Operator or Assistant; Crane, Tugger; Crusher Feederman; Crusher Oiler; Deckhand; Drill, Directional Locator; Fork Lift; Grade Checker; Guardrail Punch Oiler; Hydrographic Seeder Machine, straw, pulp or seed; Hydrostatic Pump Operator; Mixer Box (CTB, dry batch, etc.); Oiler; Plant Oiler; Pump (any power); Rail, Brakeman, Switchman, Motorman; Rail, Tamping Machine, mechanical, self-propelled; Rigger; Roller grading (not asphalt); Truck, Crane Oiler -Driver WA160001 Modification 4 Federal Wage Determinations for Highway Construction Page 125 IRON0014-005 07/01/2015 ADAMS, ASOTIN, BENTON, COLUMBIA, DOUGLAS, FERRY, FRANKLIN, GARFIELD, GRANT, LINCOLN, OKANOGAN, PEND ORIELLE, SPOKANE, STEVENS, WALLA WALLA AND -WHITMAN COUNTIES Rates Fringes IRONWORKER .......................$ 32.76 23.19 ---------------------------------------------------------------- IRON0029-002 07/01/2015 CLARK, COWLITZ, KLICKITAT, PACIFIC, SKAMANIA, AND WAHKAIKUM COUNTIES Rates Fringes IRONWORKER .......................$ 34.12 23.04 ---------------------------------------------------------------- IRON0086-002 07/01/2015 YAKIMA, KITTITAS AND CHELAN COUNTIES Rates Fringes IRONWORKER .......................$ 32.76 23.19 ---------------------------------------------------------------- IRON0086-004 07/01/2015 CLALLAM, GRAYS HARBOR, ISLAND, JEFFERSON, KING, KITSAP, LEWIS, MASON, PIERCE, SKAGIT, SNOHOMISH, THURSTON, AND WHATCOM COUNTIES Rates Fringes IRONWORKER .......................$ 40.04 23.19 ---------------------------------------------------------------- WA160001 Modification 4 Federal Wage Determinations for Highway Construction LAB00001-002 06/01/2014 ZONE 1: Rates Fringes Laborers: Page 126 CALLAM, GRAYS HARBOR, ISLAND, JEFFERSON, KING, KITSAP, LEWIS, MASON, PACIFIC (NORTH OF STRAIGHT LINE MADE BY EXTENDING THE NORTH BOUNDARY WAHKIAKUM COUNTY WEST TO THE PACIFIC OCEAN), PIERCE, SAN JUAN,SKAGIT, SNOHOMISH,THURSTON AND WHATCOM COUNTIES GROUP 1 ....................$ 22.49 10.30 GROUP 2 ....................$ 25.79 10.30 GROUP 3 ....................$ 32.29 10.30 GROUP 4 ....................$ 33.08 10.30 GROUP 5 ....................$ 33.62 10.30 CHELAN, DOUGLAS (WEST OF THE 120TH MERIDIAN), KITTITAS AND YAKIMA COUNTIES GROUP 1 ....................$ 18.95 10.30 GROUP 2 ....................$ 21.76 10.30 GROUP 3 ....................$ 23.85 10.30 GROUP 4 ....................$ 24.43 10.30 GROUP 5 ....................$ 24.85 10.30 BASE POINTS: BELLINGHAM, MT. VERNON, EVERETT, SEATTLE, KENT, TACOMA, OLYMPIA, CENTRALIA, ABERDEEN, SHELTON, PT. TOWNSEND, PT. ANGELES, AND BREMERTON ZONE 1 - Projects within 25 radius miles of the respective city hall ZONE 2 - More than 25 but less than 45 radius miles from the respective city hall ZONE 3 - More than 45 radius miles from the respective city hall ZONE DIFFERENTIAL (ADD TO ZONE 1 RATES): ZONE 2 - $1.00 ZONE 3 - $1.30 BASE POINTS: CHELAN, SUNNYSIDE, WENATCHEE, AND YAKIMA ZONE 1 - Projects within 25 radius miles of the respective city hall ZONE 2 - More than 25 radius miles from the respective city hall ZONE DIFFERENTIAL (ADD TO ZONE 1 RATES): ZONE 2 - $2.25 WA160001 Modification 4 Federal Wage Determinations for Highway Construction Page 127 LABORERS CLASSIFICATIONS GROUP l: Landscaping and Planting; Watchman; Window Washer/Cleaner (detail clean-up, such as but not limited to cleaning floors, ceilings, walls, windows, etc., prior to final acceptance by the owner) GROUP 2: Batch Weighman; Crusher Feeder; Fence Laborer; Flagman; Pilot Car GROUP 3: General Laborer; Air, Gas, or Electric Vibrating Screed; Asbestos Abatement Laborer; Ballast Regulator Machine; Brush Cutter; Brush Hog Feeder; Burner; Carpenter Tender; Cement Finisher Tender; Change House or Dry Shack; Chipping Gun (under 30 lbs.); Choker Setter; Chuck Tender; Clean-up Laborer; Concrete Form Stripper; Curing Laborer; Demolition (wrecking and moving including charred material); Ditch Digger; Dump Person; Fine Graders; Firewatch; Form Setter; Gabian Basket Builders; Grout Machine Tender; Grinders; Guardrail Erector; Hazardous Waste Worker (Level C: uses a chemical "splash suit" and air purifying respirator); Maintenance Person; Material Yard Person; Pot Tender; Rip Rap Person; Riggers; Scale Person; Sloper Sprayer; Signal Person; Stock Piler; Stake Hopper; Toolroom Man (at job site); Topper-Tailer; Track Laborer; Truck Spotter; Vinyl Seamer GROUP 4: Cement Dumper -Paving; Chipping Gun (over 30 lbs.); Clary Power Spreader; Concrete Dumper/Chute Operator; Concrete Saw Operator; Drill Operator (hydraulic, diamond, aiartrac); Faller and Bucker Chain Saw; Grade Checker and Transit Person; Groutmen (pressure) including post tension beams; Hazardous Waste Worker (Level B: uses same respirator protection as Level A. A supplied air line is provided in conjunction with a chemical "splash suit"); High Scaler; Jackhammer; Laserbeam Operator; Manhole Builder-Mudman; Nozzleman (concrete pump, green cutter when using combination of high pressure air and water on concrete and rock, sandblast, gunite, shotcrete, water blaster, vacuum blaster); Pavement Breaker; Pipe Layer and Caulker; Pipe Pot Tender; Pipe Reliner (not insert type); Pipe Wrapper; Power Jacks; Railroad Spike Puller -Power; Raker -Asphalt; Rivet Buster; Rodder; Sloper (over 20 ft); Spreader (concrete); Tamper and Similar electric, air and glas operated tool; Timber Person -sewer (lagger shorer and cribber); Track Liner Power; Tugger Operator; Vibrator; Well Point Laborer GROUP 5: Caisson Worker; Miner; Mortarman and Hodcarrier; Powderman; Re-Timberman; Hazardous Waste Worker (Level A: utilizes a fully encapsulated suit with a self-contained breathing apparatus or a supplied air line). WA160001 Modification 4 Federal Wage Determinations for Highway Construction Page 128 LAB00238-004 06/01/2014 PASCO AREA: ADAMS, BENTON, COLUMBIA,DOUGLAS (East of 120th Meridian), FERRY, FRANKLIN, GRANT, OKANOGAN, WALLA WALLA SPOKANE AREA: ASOTIN, GARFIELD, LINCOLN, PEND OREILLE, SPOKANE, STEVENS & WHITMAN COUNTIES Rates LABORER (PASCO) GROUP 1 .....................$ 22.25 GROUP 2 .....................$ 24.35 GROUP 3 .....................$ 24.62 GROUP 4 .....................$ 24.89 GROUP 5 .....................$ 25.17 LABORER (SPOKANE) GROUP 1 .....................$ 21.95 GROUP 2 .....................$ 24.05 GROUP 3 .....................$ 24.32 GROUP 4 .....................$ 24.59 GROUP 5 .....................$ 24.87 Zone Differential (Add to Zone 1 rate): $2.00 BASE POINTS: Spokane, Pasco, Lewiston Fringes 10.95 10.95 10.95 10.95 10.95 10.95 10.95 10.95 10.95 10.95 Zone 1: 0-45 radius miles from the main post office. Zone 2: 45 radius miles and over from the main post office. WA160001 Modification 4 Federal Wage Determinations for Highway Construction - -._- P a g e 29 - -- LABORERS CLASSIFICATIONS GROUP 1: Flagman; Landscape Laborer; Scaleman; Traffic Control Maintenance Laborer (to include erection and maintenance of barricades, signs and relief of flagperson); Window Washer/Cleaner (detail cleanup, such as, but not limited to cleaning floors, ceilings, walls, windows, etc. prior to final acceptance by the owner) GROUP 2: Asbestos Abatement Worker; Brush Hog Feeder; Carpenter Tender; Cement Handler; Clean-up Laborer; Concrete Crewman (to include stripping of forms, hand operating jacks on slip form construction, application of concrete curing compounds, pumperete machine, signaling, handling the nozzle of squeezcrete or similar machine,6 inches and smaller); Confined Space Attendant; Concrete Signalman; Crusher Feeder; Demolition (to include clean-up, burning, loading, wrecking and salvage of all material); Dumpman; Fence Erector; Firewatch; Form Cleaning Machine Feeder, Stacker; General Laborer; Grout Machine Header Tender; Guard Rail (to include guard rails, guide and reference posts, sign posts, and right-of-way markers); Hazardous Waste Worker, Level D (no respirator is used and skin protection is minimal); Miner, Class "A" (to include all bull gang, concrete crewman, dumpman and pumpc:rete crewman, including distributing pipe, assembly & dismantle, and nipper); Nipper; Riprap Man; Sandblast Tailhoseman; Scaffold Erector (wood or steel); Stake Jumper; Structural Mover (to include separating foundation, preparation, cribbing, shoring, jacking and unloading of structures); Tailhoseman (water nozzle); Timber Bucker and Faller (by hand); Track Laborer (RR); Truck Loader; Well -Point Man; All Other Work Classifications Not Specially Listed Shall Be Classified As General Laborer GROUP 3: Asphalt Roller, walking; Cement Finisher Tender; Concrete Saw, walking; Demolition Torch; Dope Pot Firemen, non-mechanical; Driller Tender (when required to move and position machine); Form Setter, Paving; Grade Checker using level; Hazardous Waste Worker, Level C (uses a chemical "splash suit" and air purifying respirator); Jackhammer Operator; Miner, Class "B" (to include brakeman, finisher, vibrator, form setter); Nozzleman (to include squeeze and flo-crete nozzle); Nozzleman, water, air or steam; Pavement Breaker (under 90 lbs.); Pipelayer, corrugated metal culvert; Pipelayer, multi- plate; Pot Tender; Power Buggy Operator; Power Tool Operator, gas, electric, pneumatic; Railroad Equipment, power driven, except dual mobile power spiker or puller; Railroad Power Spiker or Puller, dual mobile; Rodder and Spreader; Tamper (to include operation of Barco, Essex and similar tampers); Trencher, Shawnee; Tugger Operator; Wagon Drills; Water Pipe Liner; Wheelbarrow (power driven) WA160001 Modification 4 Federal Wage Determinations for Highway Construction Page X30 GROUP 4: Air and Hydraulic Track Drill; Aspahlt Raker;Brush Machine (to include horizontal construction joint cleanup brush machine, power propelled); Caisson Worker, free air; Chain Saw Operator and Faller; Concrete Stack (to include laborers when laborers working on free standing concrete stacks for smoke or fume control above 40 feet high); Gunite (to include operation of machine and nozzle); Hazardous Waste Worker, Level B (uses same respirator protection as Level A. A supplied air line is provided in conjunction with a chemical "splash suit"); High Scaler; Laser Beam Operator (to include grade checker and elevation control); Miner, Class C (to include miner, nozzleman for concrete, laser beam operator and rigger on tunnels); Monitor Operator (air track or similar mounting); Mortar Mixer; Nozzleman (to include jet blasting nozzleman, over 1,200 lbs., jet blast machine power propelled, sandblast nozzle); Pavement Breaker (90 lbs. and over); Pipelayer (to include working topman, caulker, collarman, jointer, mortarman, rigger, jacker, shorer, valve or meter installer); Pipewrapper; Plasterer Tender; Vibrators (all) GROUP 5 - Drills with Dual Masts; Hazardous Waste Worker, Level A (utilizes a fully encapsulated suit with a self-contained breathing apparatus or a supplied air line); Miner Class "D", (to include raise and shaft miner, laser beam operator on riases and shafts) LAB00238-006 06/01/2014 COUNTIES EAST OF THE 120TH MERIDIAN: ADAMS, ASOTIN, BENTON, CHELAN, COLUMBIA, DOUGLAS, FERRY, FRANKLIN, GARFIELD, GRANT, LINCOLN, OKANOGAN, PEND OREILLE, STEVENS, SPOKANE, WALLA WALLA, WHITMAN Rates Fringes Hod Carrier ......................$ 24.32 10.95 --------------------------------------------------------- LAB00335-001 06/01/2013 CLARK, COWLITZ, KLICKITAT, PACIFIC (SOUTH OF A STRAIGHT LINE MADE BY EXTENDING THE NORTH BOUNDARY LINE OF WAHKIAKUM COUNTY WEST TO THE PACIFIC OCEAN), SKAMANIA AND WAHKIAKUM COUNTIES Rates Fringes Laborers: ZONE 1: GROUP 1 ....................$ 28.65 10.05 GROUP 2 ....................$ 29.25 10.05 GROUP 3 ....................$ 29.69 10.05 GROUP 4 ....................$ 30.07 10.05 GROUP 5 ....................$ 26.15 10.05 GROUP 6 ....................$ 23.73 10.05 GROUP 7 ....................$ 20.53 10.05 WA160001 Modification 4 Federal Wage Determinations for Highway Construction Page 131 Zone Differential (Add to Zone 1 rates): Zone 2 $ 0.65 Zone 3 - 1.15 Zone 4 - 1.70 Zone 5 - 2.75 BASE POINTS: GOLDENDALE, LONGVIEW, AND VANCOUVER ZONE 1: Projects within 30 miles of the respective city all. ZONE 2: More than 30 miles but less than 40 miles from the respective city hall. ZONE 3: More than 40 miles but less than 50 miles from the respective city hall. ZONE 4: More than 50 miles but less than 80 miles from the respective city hall. ZONE 5: More than 80 miles from the respective city hall. LABORERS CLASSIFICATIONS GROUP 1: Asphalt Plant Laborers; Asphalt Spreaders; Batch Weighman; Broomers; Brush Burners and Cutters; Car and Truck Loaders; Carpenter Tender; Change -House Man or Dry Shack Man; Choker Setter; Clean-up Laborers; Curing, Concrete; Demolition, Wrecking and Moving Laborers; Dumpers, road oiling crew; Dumpmen (for grading crew); Elevator Feeders; Median Rail Reference Post, Guide Post, Right of Way Marker; Fine Graders; Fire Watch; Form Strippers (not swinging stages); General Laborers; Hazardous Waste Worker; Leverman or Aggregate Spreader (Flaherty and similar types); Loading Spotters; Material Yard Man (including electrical); Pittsburgh Chipper Operator or Similar Types; Railroad Track Laborers; Ribbon Setters (including steel forms); Rip Rap Man (hand placed); Road Pump Tender; Sewer Labor; Signalman; Skipman; Slopers; Spraymen; Stake Chaser; Stockpiler; Tie Back Shoring; Timber Faller and Bucker (hand labor); Toolroom Man (at job site); Tunnel Bullgang (above ground); Weight -Man- Crusher (aggregate when used) GROUP 2: Applicator (including pot power tender for same), applying protective material by hand or nozzle on utility lines or storage tanks on project; Brush Cutters (power saw); Burners; Choker Splicer; Clary Power Spreader and similar types; Clean- up Nozzleman-Green Cutter (concrete, rock, etc.); Concrete Power Buggyman; Concrete Laborer; Crusher Feeder; Demolition and Wrecking Charred Materials; Gunite Nozzleman Tender; Gunite or Sand Blasting Pot Tender; Handlers or Mixers of all Materials of an irritating nature (including cement and lime); Tool Operators (includes but not limited to: Dry Pack Machine; Jackhammer; Chipping Guns; Paving Breakers); Pipe Doping and Wrapping; Post Hole Digger, air, gas or electric; Vibrating Screed; Tampers; Sand Blasting (Wet); Stake -Setter; Tunnel-Muckers, Brakemen, Concrete Crew, Bullgang (underground) WA160001 Modification 4 Federal Wage Determinations for Highway Construction Page 132 GROUP 3: Asbestos Removal; Bit Grinder; Drill Doctor; Drill Operators, air tracks, cat drills, wagon drills, rubber -mounted drills, and other similar types including at crusher plants; Gunite Nozzleman; High Scalers, Strippers and Drillers (covers work in swinging stages, chairs or belts, under extreme conditions unusual to normal drilling, blasting, barring -down, or sloping and stripping); Manhole Builder; Powdermen; Concrete Saw Operator; Pwdermen; Power Saw Operators (Bucking and Falling); Pumperete Nozzlemen; Sand Blasting (Dry); Sewer Timberman; Track Liners, Anchor Machines, Ballast Regulators, Multiple Tampers, Power Jacks, Tugger Operator; Tunnel -Chuck Tenders, Nippers and Timbermen; Vibrator; Water Blaster GROUP 4: Asphalt Raker; Concrete Saw Operator (walls); Concrete Nozzelman; Grade Checker; Pipelayer; Laser Beam (pipelaying) -applicable when employee assigned to move, set up, align; Laser Beam; Tunnel Miners; Motorman -Dinky Locomotive -Tunnel; Powderman-Tunnel; Shield Operator -Tunnel GROUP 5: Traffic Flaggers GROUP 6: Fence Builders GROUP 7: Landscaping or Planting Laborers ---------------------------------------------------------------- LAB00335-019 09/01/2013 Rates Fringes Hod Carrier ......................$ 30.47 10.05 ---------------------------------------------------------------- PAIN0005-002 07/01/2015 STATEWIDE EXCEPT CLARK, COWLITZ, KLICKITAT, PACIFIC (SOUTH), SKAMANIA, AND WAHKIAKUM COUNTIES Rates Fringes Painters: STRIPERS ....................$ 27.44 14.09 ---------------------------------------------------------------- PAIN0005-004 03/01/2009 CLALLAM, GRAYS HARBOR, ISLAND, JEFFERSON, KING, KITSAP, LEWIS, MASON, PIERCE, SAN JUAN, SKAGIT, SNOHOMISH, THURSTON AND WHATCOM COUNTIES Rates Fringes PAINTER ..........................$ 20.82 7.44 ---------------------------------------------------------------- WA160001 Modification 4 Federal Wage Determinations for Highway Construction P a g e 133 PAIN0005-006 07/01/2015 ADAMS, ASOTIN; BENTON AND FRANKLIN (EXCEPT HANFORD SITE); CHELAN, COLUMBIA, DOUGLAS, FERRY, GARFIELD, GRANT, KITTITAS, LINCOLN, OKANOGAN, PEND OREILLE, SPOKANE, STEVENS, WALLA WALLA, WHITMAN AND YAKIMA COUNTIES Rates Fringes ' PAINTER Application of Cold Tar Products, Epoxies, Polyure thanes, Acids, Radiation Resistant Material, Water and Sandblasting ............ $ 28.15 10.85 Over 30'/Swing Stage Work..$ 22.20 7.98 Brush, Roller, Striping, Steam -cleaning and Spray .... $ 23.05 10.85 Lead Abatement, Asbestos Abatement ...................$ 21.50 7.98 *$.70 shall be paid over and above the basic wage rates listed for work on swing stages and high work of over 30 feet. ---------------------------------------------------------------- PAIN0055-003 10/01/2015 CLARK, COWLITZ, KLICKITAT, PACIFIC, SKAMANIA, AND WAHKIAKUM COUNTIES Rates Fringes PAINTER Brush & Roller ..............$ 22.97 9.85 High work - All work 60 ft. or higher ...............$ 23.72 9.85 Spray and Sandblasting ...... $ 23.57 9.85 ---------------------------------------------------------------- PAIN0055-006 11/01/2014 CLARK, COWLITZ, KLICKITAT, SKAMANIA and WAHKIAKUM COUNTIES Rates Fringes Painters: HIGHWAY & PARKING LOT STRIPER .....................$ 33.43 11.08 ---------------------------------------------------------------- WA160001 Modification 4 Federal Wage Determinations for Highway Construction PLAS0072-004 06/01/2015 ADAMS, ASOTIN, BENTON, CHELAN, COLUMBIA, DOUGLAS, FERRY, FRANKLIN, GARFIELD, GRANT, KITTITAS, LINCOLN, OKANOGAN, PEND OREILLE, SPOKANE, STEVENS, WALLA WALLA, WHITMAN, AND YAKIMA COUNTIES Rates Fringes CEMENT MASON/CONCRETE FINISHER ZONE 1 ......................$ 27.01 12.59 Zone Differential (Add to Zone 1 rate): Zone 2 - $2.00 BASE POINTS: Spokane, Pasco, Lewiston; Wenatchee Zone 1: 0 - 45 radius miles from the main post office Zone 2: Over 45 radius miles from the main post office ---------------------------------------------------------------- PLAS0528-001 06/01/2015 CLALLAM, COWLITZ, GRAYS HARBOR, ISLAND, JEFFERSON, KING, KITSAP, LEWIS, MASON, PACIFIC, PIERCE, SAN JUAN, SKAGIT, SNOHOMISH, THURSTON, WAHKIAKUM AND WHATCOM COUNTIES Rates Fringes CEMENT MASON CEMENT MASON ................$ 38.52 15.43 COMPOSITION, TROWEL MACHINE, GRINDER, POWER TOOLS, GUNNITE NOZZLE ....... $ 39.02 15.43 TROWLING MACHINE OPERATOR ON COMPOSITION ............... $ 39.02 15.43 ---------------------------------------------------------------- PLAS0555-002 06/01/2015 CLARK, KLICKITAT AND SKAMANIA COUNTIES ZONE 1: Rates CEMENT MASON CEMENT MASONS DOING BOTH COMPOSITION/POWER MACHINERY AND SUSPENDED/HANGING SCAFFOLD..$ 30.58 CEMENT MASONS ON SUSPENDED, SWINGING AND/OR HANGING SCAFFOLD ............ $ 30.58 CEMENT MASONS ...............$ 29.98 COMPOSITION WORKERS AND POWER MACHINERY OPERATORS ... $ 31.18 WA160001 Modification 4 Federal Wage Determinations for Highway Construction Fringes 18.18 18.18 18.18 18.18 Page X34 Page 135 Zone Differential (Add To Zone 1 Rates): Zone 2 - $0.65 Zone 3 - 1.15 Zone 4 - 1.70 Zone 5 - 3.00 BASE POINTS: BEND, CORVALLIS, EUGENE, MEDFORD, PORTLAND, SALEM, THE DALLES, VANCOUVER ZONE 1: Projects within 30 miles of the respective city hall ZONE 2: More than 30 miles but less than 40 miles from the respective city hall. ZONE 3: More than 40 miles but less than 50 miles from the respective city hall. ZONE 4: More than 50 miles but less than 80 miles from the respective city hall. ZONE 5: More than 80 miles from the respective city hall ---------------------------------------------------------------- TEAM0037-002 06/01/2014 CLARK, COWLITZ, KLICKITAT, PACIFIC (South of a straight line made by extending the north boundary line of Wahkiakum County west to the Pacific Ocean), SKAMANIA, AND WAHKIAKUM COUNTIES Zone Differential (Add to Zone 1 Rates): Zone 2 - $0.65 Zone 3 - 1.15 Zone 4 - 1.70 Zone 5 - 2.75 BASE POINTS: ASTORIA, THE DALLES, LONGVIEW AND VANCOUVER ZONE 1: Projects within 30 miles of the respective city hall. ZONE 2: More than 30 miles but less than 40 miles from the respective city hall. ZONE 3: More than 40 miles but less than 50 miles from the respective city hall. ZONE 4: More than 50 miles but less than 80 miles from the respective city hall. ZONE 5: More than 80 miles from the respective city hall. WA160001 Modification 4 Federal Wage Determinations for Highway Construction. Rates Fringes Truck drivers: ZONE 1 GROUP 1 ....................$ 26.90 14.37 GROUP 2 ....................$ 27.02 14.37 GROUP 3 ....................$ 27.15 14.37 GROUP 4 ....................$ 27.41 14.37 GROUP 5 ....................$ 27.63 14.37 GROUP 6 ....................$ 27.79 14.37 GROUP 7 ....................$ 27.99 14.37 Zone Differential (Add to Zone 1 Rates): Zone 2 - $0.65 Zone 3 - 1.15 Zone 4 - 1.70 Zone 5 - 2.75 BASE POINTS: ASTORIA, THE DALLES, LONGVIEW AND VANCOUVER ZONE 1: Projects within 30 miles of the respective city hall. ZONE 2: More than 30 miles but less than 40 miles from the respective city hall. ZONE 3: More than 40 miles but less than 50 miles from the respective city hall. ZONE 4: More than 50 miles but less than 80 miles from the respective city hall. ZONE 5: More than 80 miles from the respective city hall. WA160001 Modification 4 Federal Wage Determinations for Highway Construction. Page X36 TRUCK DRIVERS CLASSIFICATIONS GROUP 1: A Frame or Hydra lifrt truck w/load bearing surface; Articulated Dump Truck; Battery Rebuilders; Bus or Manhaul Driver; Concrete Buggies (power operated); Concrete Pump Truck; Dump Trucks, side, end and bottom dumps, including Semi Trucks and Trains or combinations there of: up to and including 10 cu. yds.; Lift Jitneys, Fork Lifts (all sizes in loading, unloading and transporting material on job site); Loader and/or Leverman on Concrete Dry Batch Plant (manually operated); Pilot Car; Pickup Truck; Solo Flat Bed and misc. Body Trucks, 0-10 tons; Truck Tender; Truck Mechanic Tender; Water Wagons (rated capacity) up to 3,000 gallons; Transit Mix and Wet or Dry Mix - 5 cu. yds. and under; Lubrication Man, Fuel Truck Driver, Tireman, Wash Rack, Steam Cleaner or combinations; Team Driver; Slurry Truck Driver or Leverman; Tireman GROUP 2: Boom Truck/Hydra-lift or Retracting Crane; Challenger; Dumpsters or similar equipment all sizes; Dump Trucks/Articulated Dumps 6 cu to 10 cu.; Flaherty Spreader Driver or Leverman; Lowbed Equipment, Flat Bed Semi -trailer or doubles transporting equipment or wet or dry materials; Lumber Carrier, Driver -Straddle Carrier (used in loading, unloading and transporting of materials on job site); Oil Distributor Driver or Leverman; Transit mix and wet or dry mix trcuks: over 5 cu. yds. and including 7 cu. yds.; Vacuum Trucks; Water truck/Wagons (rated capacity) over 3,000 to 5,000 gallons GROUP 3: Ammonia Nitrate Distributor Driver; Dump trucks, side, end and bottom dumps, including Semi Trucks and Trains or combinations thereof: over 10 cu. yds. and including 30 cu. yds. includes Articulated Dump Trucks; Self -Propelled Street Sweeper; Transit mix and wet or dry mix truck: over 7 cu yds. and including 11 cu yds.; Truck Mechanic -Welder -Body Repairman; Utility and Clean-up Truck; Water Wagons (rated capacity) over 5,000 to 10,000 gallons GROUP 4: Asphalt Burner; Dump Trucks, side, end and bottom cumps, including Semi -Trucks and Trains or combinations thereof: over 30 cu. yds. and -including 50 cu. yds. includes Articulated Dump Trucks; Fire Guard; Transit Mix and Wet or Dry Mix Trucks, over 11 cu. yds. and including 15 cu. yds.; Water Wagon (rated capacity) over 10,000 gallons to 15,000 gallons GROUP 5: Composite Crewman; Dump Trucks, side, end and bottom dumps, including Semi Trucks and Trains or combinations thereof: over 50 cu. yds. and including 60 cu. yds. includes Articulated Dump Trucks GROUP 6: Bulk Cement Spreader w/o Auger; Dry Pre -Batch concrete Mix Trucks; Dump trucks, side, end and bottom dumps, including Semi Trucks and Trains of combinations thereof: over 60 cu. yds. and including 80 cu. yds., and includes Articulated Dump Trucks; Skid Truck WA160001 Modification 4 Federal Wage Determinations for Highway Construction Page X37 GROUP 7: Dump Trucks, side, end and bottom dumps, including Semi Trucks and Trains or combinations thereof: over 80 cu. yds. and including 100 cu. yds., includes Articulated Dump Trucks; Industrial Lift Truck (mechanical tailgate) TEAM0174-001 06/01/2015 CLALLAM, GRAYS HARBOR, ISLAND, JEFFERSON, KING, KITSAP, LEWIS, MASON, PACIFIC (North of a straight line made by extending the north boundary line of Wahkiakum County west to the Pacific Ocean), PIERCE, SAN JUAN, SKAGIT, SNOHOMISH, THURSTON AND WHATCOM COUNTIES Rates Fringes Truck drivers: CENTRALIA RAYMOND ZONE A: EVERETT SHELTON GROUP 1 :...................$ 32.18 17.27 GROUP 2: ................... $ 31.34 17.27 GROUP 3: ................... $ 28.53 17.27 GROUP 4 :...................$ 23.56 17.27 GROUP 5: ................... $ 31.73 17.27 ZONE B (25-45 miles from center of listed cities*): Add $.70 per hour to Zone A rates. ZONE C (over 45 miles from centr of listed cities*): Add $1.00 per hour to Zone A rates. *Zone pay will be calculated from the city center of the following listed cities: BELLINGHAM CENTRALIA RAYMOND OLYMPIA EVERETT SHELTON ANACORTES BELLEVUE SEATTLE PORT ANGELES MT. VERNON KENT TACOMA PORT TOWNSEND ABERDEEN BREMERTON TRUCK DRIVERS CLASSIFICATIONS GROUP 1 - "A -frame or Hydralift" trucks and Boom trucks or similar equipment when "A" frame or "Hydralift" and Boom truck or similar equipment is used; Buggymobile; Bulk Cement Tanker; Dumpsters and similar equipment, Tournorockers, Tournowagon, Tournotrailer, Cat DW series, Terra Cobra, Le Tourneau, Westinghouse, Athye Wagon', Euclid Two and Four -Wheeled power tractor with trailer and similar top -loaded equipment transporting material: Dump Trucks, side, end and bottom dump, including semi -trucks and trains or combinations thereof with 16 yards to 30 yards capacity: Over 30 yards $.15 per hour additional for each 10 yard increment; Explosive Truck (field mix) and similar equipment; Hyster Operators (handling bulk loose aggregates); Lowbed and Heavy Duty Trailer; Road Oil Distributor Driver; Spreader, Flaherty Transit mix used exclusively in heavy construction; Water Wagon and Tank Truck -3,000 gallons and over capacity WA160001 Modification 4 Federal Wage Determinations for Highway Construction Page 138 GROUP 2 - Bulllifts, or similar equipment used in loading or unloading trucks, transporting materials on job site; Dumpsters, and similar equipment, Tournorockers, Tournowagon, Turnotrailer, Cat. D.W. Series, Terra Cobra, Le Tourneau, Westinghouse, Athye wagon, Euclid two and four -wheeled power tractor with trailer and similar top -loaded equipment transporting material: Dump trucks, side, end and bottom dump, including semi -trucks and trains or combinations thereof with less than 16 yards capacity; Flatbed (Dual Rear Axle); Grease Truck, Fuel Truck, Greaser, Battery Service Man and/or Tire Service Man; Leverman and loader at bunkers and batch plants; Oil tank transport; Scissor truck; Slurry Truck; Sno-Go and similar equipment; Swampers; Straddler Carrier (Ross, Hyster) and similar equipment; Team Driver; Tractor (small, rubber-tired)(when used within Teamster jurisdiction); Vacuum truck; Water Wagon and Tank trucks -less than 3,000 gallons capacity; Winch Truck; Wrecker, Tow truck and similar equipment GROUP 3 - Flatbed (single rear Truck. (Adjust Group 3 upward work only) GROUP 4 - Escort or Pilot Car GROUP 5 - Mechanic HAZMAT PROJECTS axle); Pickup Sweeper; Pickup by $2.00 per hour for onsite Anyone working on a HAZMAT job, where HAZMAT certification is required, shall be compensated as a premium, in addition to the classification working in as follows: LEVEL C: +$.25 per hour - This level uses an air purifying respirator or additional protective clothing. LEVEL B: +$.50 per hour - Uses same respirator protection as Level A. Supplied air line is provided in conjunction with a chemical "splash suit." LEVEL A: +$.75 per hour - This level utilizes a fully - encapsulated suit with a self-contained breathing apparatus or a supplied air line. WA160001 Modification 4 Federal Wage Determinations for Highway Construction Page 139 * TEAM0690-004 01/01/2016 ADAMS, ASOTIN, BENTON, CHELAN, COLUMBIA, DOUGLAS, FERRY, FRANKLIN, GARFIELD, GRANT KITTITAS, LINCOLN, OKANOGAN, PEND OREILLE, SPOKANE, STEVENS, WALLA WALLA, WHITMAN AND YAKIMA COUNTIES Rates Fringes Truck drivers: (AREA 1: SPOKANE ZONE CENTER: Adams,Chelan, Douglas, Ferry, Grant, Kittitas, Lincoln, Okanogan, Pen Oreille, Spokane, Stevens, and Whitman Counties AREA 1: LEWISTON ZONE CENTER: Asotin, Columbia, and Garfield Counties AREA 2: PASCO ZONE CENTER: Benton, Franklin, Walla Walla and Yakima Counties) AREA 1: GROUP 1 ....................$ 20.17 16.69 GROUP 2 ....................$ 22.44 16.69 GROUP 3 ....................$ 22.94 16.69 GROUP 4 ....................$ 23.27 16.69 GROUP 5 ....................$ 23.38 16.69 GROUP 6 ....................$ 23.55 16.69 GROUP 7 ....................$ 24.08 16.69 GROUP 8 ....................$ 24.44 16.69 AREA 2: GROUP 1 ....................$ 22.17 16.69 GROUP 2 ....................$ 24.44 16.69 GROUP 3 ....................$ 24.94 16.69 GROUP 4 ....................$ 25.27 16.69 GROUP 5 ....................$ 25.38 16.69 GROUP 6 ....................$ 25.55 16:69 GROUP 7 ....................$ 26.08 16.69 GROUP 8 ....................$ 26.44 16.69 Zone Differential (Add to Zone 1 rate: Zone 1 + $2.00) BASE POINTS: Spokane, Pasco, Lewiston Zone 1: 0-45 radius miles from the main post office. Zone 2: Outside 45 radius miles from the main post office WA160001 Modification 4 Federal Wage Determinations for Highway Construction Page X40 TRUCK DRIVERS CLASSIFICATIONS GROUP 1: Escort Driver or Pilot Car; Employee Haul; Power Boat Hauling Employees or Material GROUP 2: Fish Truck; Flat Bed Truck; Fork Lift (3000 lbs. and under); Leverperson (loading trucks at bunkers); Trailer Mounted Hydro Seeder and Mulcher; Seeder & Mulcher; Stationary Fuel Operator; Tractor (small, rubber -tired, pulling trailer or similar equipment) GROUP 3: Auto Crane (2000 lbs. capacity); Buggy Mobile & Similar; Bulk Cement Tanks & Spreader; Dumptor (6 yds. & under); Flat Bed Truck with Hydraullic System; Fork Lift (3001-16,000 lbs.); Fuel Truck Driver, Steamcleaner & Washer; Power Operated Sweeper; Rubber -tired Tunnel Jumbo; Scissors Truck; Slurry Truck Driver; Straddle Carrier (Ross, Hyster, & similar); Tireperson; Transit Mixers & Truck Hauling Concrete (3 yd. to & including 6 yds.); Trucks, side, end, bottom & articulated end dump (3 yards to and including 6 yds.); Warehouseperson (to include shipping & receiving); Wrecker & Tow Truck GROUP 4: A -Frame; Burner, Cutter, & Welder; Service Greaser; Trucks, side, end, bottom & articulated end dump (over 6 yards to and including 12 yds.); Truck Mounted Hydro Seeder; Warehouseperson; Water Tank truck (0-8,000 gallons) GROUP 5: Dumptor (over 6 yds.); Lowboy (50 tons & under); Self- loading Roll Off; Semi -Truck & Trailer; Tractor with Steer Trailer; Transit Mixers and Trucks Hauling Concrete (over 6 yds. to and including 10 yds.); Trucks, side, end, bottom and end dump (over 12 yds. to & including 20 yds.); Truck -Mounted Crane (with load bearing surface either mounted or pulled, up to 14 ton); Vacuum Truck (super sucker, guzzler, etc.) GROUP 6: Flaherty Spreader Box Driver; Flowboys; Fork Lift (over 16,000 lbs.); Dumps (Semi -end); Mechanic (Field); Semi- end Dumps; Transfer Truck & Trailer; Transit Mixers & Trucks Hauling Concrete (over 10 yds. to & including 20 yds.); Trucks, side, end, bottom and articulated end dump (over 20 yds. to & including 40 yds.); Truck and Pup; Tournarocker, DWs & similar with 2 or more 4 wheel -power tractor with trailer, gallonage or yardage scale, whichever is greater Water Tank Truck (8,001- 14,000 gallons); Lowboy(over 50 tons) GROUP 7: Oil Distributor Driver; Stringer Truck (cable oeprated trailer); Transit Mixers & Trucks Hauling Concrete (over 20 yds.); Truck, side, end, bottom end dump (over 40 yds. to & including 100 yds.); Truck Mounted Crane (with load bearing surface either mounted or pulled (16 through 25 tons); WA160001 Modification 4 Federal Wage Determinations for Highway Construction Page 141 GROUP 8: Prime Movers and Stinger Truck; Trucks, side, end, bottom and articulated end dump (over 100 yds.); Helicopter Pilot Hauling Employees or Materials Footnote A - Anyone working on a HAZMAT job, where HAZMAT certification is required, shall be compensated as a premium, in additon to the classification working in as follows: LEVEL C -D: - $.50 PER HOUR (This is the lowest level of protection. This level may use an air purifying respirator or additional protective clothing. LEVEL A -B: - $1.00 PER HOUR (Uses supplied air is conjunction with a chemical spash suit or fully encapsulated suit with a self-contained breathing apparatus. Employees shall be paid Hazmat pay in increments of four(4) and eight(8) hours. NOTE: Trucks Pulling Equipment Trailers: shall receive $.15/hour over applicable truck rate WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental. Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) (ii)). The body of each wage determination lists the classification and wage rates that have been found to be prevailing for the cited type(s) of construction in the area covered by the wage determination. The classifications are listed in alphabetical order of "identifiers" that indicate whether the particular rate is a union rate (current union negotiated rate for local), a survey rate (weighted average rate) or a union average rate (weighted union average rate). Union Rate Identifiers A four letter classification abbreviation identifier enclosed in dotted lines beginning with characters other than "SU" or "UAVG" denotes that the union classification and rate were prevailing for that classification in the survey. Example: PLUM0198-005 07/01/2014. PLUM is an abbreviation identifier of WA160001 Modification 4 Federal Wage Determinations for Highway Construction Page 142 the union which prevailed in the survey for this classification, which in this example would be Plumbers. 0198 indicates the local union number or district council number where applicable, i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination. 07/01/2014 is the effective date of the most current negotiated rate, which in this example is July 1, 2014. Union prevailing wage rates are updated to reflect all rate changes in the collective bargaining agreement (CBA) governing this classification and rate. Survey Rate Identifiers Classifications listed under the "SU" identifier indicate that no one rate prevailed for this classification in the survey and the published rate is derived by computing a weighted average rate based on all the rates reported in the survey for that classification. As this weighted average rate includes all rates reported in the survey, it may include both union and non-union rates. Example: SULA2012-007 5/13/2014. SU indicates the rates are survey rates based on a weighted average calculation of rates and are not majority rates. LA indicates the State of Louisiana. 2012 is the year of survey on which these classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination. 5/13/2014 indicates the survey completion date for the classifications and rates under that identifier. Survey wage rates are not updated and remain in effect until a new survey is conducted. Union Average Rate Identifiers Classification(s) listed under the UAVG identifier indicate that no single majority rate prevailed for those classifications; however, 100% of the data reported for the classifications was union data. EXAMPLE: UAVG-OH-0010 08/29/2014. UAVG indicates that the rate is a weighted union average rate. OH indicates the state. The next number, 0010 in the example, is an internal number used in producing the wage determination. 08/29/2014 indicates the survey completion date for the classifications and rates under that identifier. A UAVG rate will be updated once a year, usually in January of each year, to reflect a weighted average of the current negotiated/CBA rate of the union locals from which the rate is based. WA160001 Modification 4 Federal Wage Determinations for Highway Construction Page 143 WAGE DETERMINATION APPEALS PROCESS 1.) Has there been an initial decision in the matter? This can be: * an existing published wage determination * a survey underlying a wage determination • a Wage and Hour Division letter setting forth a position on a wage determination matter * a conformance (additional classification and rate) ruling On survey related matters, initial contact, including requests for summaries of surveys, should be with the Wage and Hour Regional Office for the area in which the survey was conducted because those Regional Offices have responsibility for the Davis -Bacon survey program. If the response from this initial contact is not satisfactory, then the process described in 2.) and 3.) should be followed. With regard to any other matter not yet ripe for the formal process described here, initial contact should be with the Branch of Construction Wage Determinations. Write to: Branch of Construction Wage Determinations Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W. Washington, DC 20210 2.) If the answer to the question in 1.) is yes, then an interested party (those affected by the action) can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7). Write to: Wage and Hour Administrator U.S. Department of Labor 200 Constitution Avenue, N.W. Washington, DC 20210 WA160001 Modification 4 Federal Wage Determinations for Highway Construction Page 144 The request should be accompanied by a full statement of the interested party's position and by any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue. 3.) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative Review Board (formerly the Wage Appeals Board). Write to: Administrative Review Board U.S. Department of Labor 200 Constitution Avenue, N.W. Washington, DC 20210 4.) All decisions by the Administrative Review Board are final. END OF GENERAL DECISION WA160001 Modification 4 Federal Wage Determinations for Highway Construction ADDENDUM NO. 1 To Contract Documents For Crosswalk Improvements (Federal Aid Project #STPUS-9918(015) Page 1 of 1 Issued: June 8, 2016 Contents: This Addendum No. 1 contains revisions to the Proposal. Revisions are made by re- issuing a specification page, plan sheet, OR by directing a change in writing. All revisions are listed below; bidders are cautioned to check the addendum contents carefully for the presence of all listed revisions. Distribution: This Addendum No. 1 is distributed to all planholders of record by e-mail to e- mail addresses or facsimile to numbers given when documents were purchased. The planholder will be asked to confirm receipt when e-mailed. Integration: The following changes, additions, deletions and attachments are hereby made a part of the Contract Documents for Bremerton Crosswalks Improvements as fully and completely as if the same were fully set forth therein. Acknowledgment of Receipt of Addendum: All prospective bidders are instructed to incorporate this revision into their bids and to acknowledge receipt of the Addenda in the Proposal. Failure to do so may result in the Bid being rejected as not responsive. Enclosures to Addendum 1: Proposal. Replace the Proposal in the Contract Documents with the attached. Gus Brandon Garcia Project Engineer ( Manager City of Bremerton END OF ADDENDUM NO. 1 - PROPOSAL FORM (Continued) NOTE: Unit prices for all items, all extensions and total amount of bid must be shown. Show unit prices in both words and figures and where conflict occurs the written or typed words shall prevail. Include sales tax on all appropriate bid items. DOR Rule 171 applies. kem Approz Wn wmh unit Priced Bld unk Price Amount No. Quantky Dolieni•I:Cta D61lma-10m, I 1.00 MOBILIZATION 1 L.S. PREPARATION WATER LINES 1.00 RESETTING EXISTING HYDRANTS 2 EACH ----------., --------------- ---- EROSION CONTROL AND PLANTING 11.00 INLET PROTECTION 3 EACH 1.00 EROSION/WATER POLLUTION CONTROL 4 EST. $ 1,250 Id 00 TRAFFIC 520.00 CEMENT CONC. TRAFFIC CURB AND GUTTER 5 L.F. 1.00 TRAFFIC SIGNAL SYSTEM MODIFICATIONS, KITSAP WAY / 11TH 6 L.S. 1.00 TRAFFIC SIGNAL SYSTEM MODIFICATIONS, 11TH ST / HIGH AVE 7 L.S. 1.00 RRFB SIGNAL SYSTEM COMPLETE, SR304 / 1 ST ST 8 L.S. Crosswalk Improvements Contract Documents City of Bremerton, Washington 9 Skillings Connolly, Inc. Federal Aid # STP US -9918(015) March 2016 PROPOSAL FORM (Continued) ern.. Approxi Itbih. fi`uhwPm%dsid, !tleif'Piice; �o. QWhtiijr. Dollars Cts 1.00 HAWK SIGNAL SYSTEM COMPLETE, 6TH ST / HIGH AVE 9 L.S. -- ----- -- ------•-----...._.__..—.----------------._..... 1.00 RRFB SIGNAL SYSTEM COMPLETE, KITSAP WAY ! HARLOW 10 L.S. 100.00 CEMENT CONC. TRAFFIC CURB 11 L.F. 410.00 CEMENT CONC. PEDESTRIAN CURB 12 55.00 PAINT LINE 13 L.F. - --.._._..------------------ .... --- ---- --- -._ 380.00 PLASTIC CROSSWALK LINE 14 S.F. ---------- ------------------ 40.00 PLASTIC STOP LINE 15 ----- 0.40 RAISED PAVEMENT MARKER TYPE 1 16 HUND 0.10 RAISED PAVEMENT MARKER TYPE 2 17 HUND 1.00 PERMANENT SIGNING 18 --------- 19 40.00 E PLASTIC YIELD LINE SYMBOL 11 0 EACH OTHER ITEMS 1.00 FIELD ADJUST RAMPS $2,500 .00 $2,500 .DO EST. ------- ---------------------------------- --- -- ---- Crosswalk Improvements Contract Documents City of Bremerton, {Vashington 10 Skillings Connolly, Inc. Federal Aid 9 STPUS-9918(015) March 2016 PROPOSAL FORM (Continued) Item Approx. Item with Unit Priced: Bid Unit Price Amount No: 4uantity Dollars 6% Dollars ( Cts 8.00 CEMENT CONC. CURB RAMP TYPE PARALLEL A 22 EACH-- -------------------- --- ------------ 5.00 CEMENT CONC. CURB RAMP TYPE PERPENDICULAR 23 EACH---............ ........._------.......... -... _....._.....-----------._....___. 4.00 CEMENT CONC. CURB RAMP TYPE COMBINATION 24 EACH 1.00 RESOLUTION OF UTILITY CONFLICTS 25 $2,500 .00 $2,500 .00 EST. 8.00 ADJUST CATCH BASIN 26 EACH-------------- — ------.__...----------------------.__. 1.00 ADJUST VALVE BOX 27 EACH 1.00 ROADWAY SURVEYING 28 L.S.---------- --------...--------------------- -- - -- 236.00 CEMENT CONC. SIDEWALK 29 S.Y.--------------- - --..................--._.....___......._..._.__....----•---..._ 1.00 ROADSIDE CLEANUP 1.00 MINOR CHANGE 31 EST. 515,000 .00 $15,000 .00 1.00 SPCC PLAN 11 11 H L.S. Data He- G.IPmject=15115071 Bremerton Crosswalk Improvements DesignlEstrmatelPFSDARD.MW Grand Total......... Crosnvalk hirproverrients Contract Documents Ciry of Bremerton, Washington 11 Skillings Connolly, Inc. Federal Aid 9 STPUS-9918(015) March 2016 PERFORMANCE BOND Local Agency Performance Bond PERFORMANCE BOND to [City of Bremerton or County], WA Bond No. 1065211871 The (City of Bremerton or County], Washington ([City or County]) has awarded to Massana Construction, Inc. (Principal), a contract for the construction of the project designated as Bremerton crosswalk lmprovements ,Project No. STPUS-9918(018) in Bremerton, Washington (Contract), and said Principal is required to furnish a bond for performance of all oblig-aTimns—u—nde-rthe Contract. Travelers Casualty & Surety The Principal, and Company of America (Surety), a corporation, organized under the laws of the State of Connecticut and licensed to do business in the State of Washington as surety and named in the current list of "Surety Companies Acceptable in Federal Bonds" as published in the Federal Register by the Audit Staff Bureau of Accounts, U.S. Treasury Dept., are jointly and severally held and firmly bound to the [City or County], in the sum of Six Hundred Eighty Eight Thousand Four hundred Fifty Five Dollars & no cents US Dollars ($ 688,455.00 ) Total Contract Amount, subject to the provisions herein. This statutory performance bond shall become null and void, if and when the Principal, its heirs, executors, administrators, successors, or assigns shall well and faithfully perform all of the Principal's obligations under the Contract and fulfill all terms and conditions of all duly authorized modifications, additions, and changes to said Contract that may hereafter be made, at the time and in the manner therein specified; and if such performance obligations have not been fulfilled, this bond shall remain in force and effect. The Surety for value received agrees that no change, extension of time, alteration or addition to the terms of the Contract, the specifications accompanying the Contract, or to the work to be performed under the Contract shall in any way affect its obligation on this bond, and waives notice of any change, extension of time, alteration or addition to the terms of the Contract or the work performed. The Surety agrees that modifications and changes to the terms and conditions of the Contract that increase the total amount to be paid the Principal shall automatically increase the obligation of the Surety on this bond and notice to Surety is not required for such increased obligation. This bond may be executed in two (2) original counterparts, and shall be signed by the parties' duly authorized officers. This bond will only be accepted if it is accompanied by a fully executed and original power of attorney for the office executing on behalf of the surety. PRINCIPAL _ SURETY . 06/20/16 t /,. 06/2016 Date SuretySgnature _ Principal signature Date _ Mark Massmann 06/20/16 Robert A. Yarbrough 06/20/16 Printed Name Date Printed Name Date President Attorney In Fact Title Title Name, address, and telephone of local office/agent of Surety Company is Travis Belling 1501 4th Ave. Seattle WA 98101 (206) 326-4284 Approved as to form: [City or County] Attorney/' [City DOT Form 272-002A EF 08/2012 Crosswalk Improvements City of Bremerton, Washington Federal Aid # STPUS-9918(015) or 24 nty] Date Contract Documents Skillings Connolly, Inc. March 2016 PAYMENT BOND Local Agency Payment Bond - Highway Construction PUBLIC WORKS PAYMENT BOND to [City of Bremerton or County], WA Bond No. 106521871 The rCity of Bremerton or County], Washington ([City or County]) has awarded to Massana construction Inc (Principal), a contract for the construction of the project designated as Bremertoncr—aikim,rovemera ,Project No. sTPus-9918(015) , in - I-, Washington (Contract), and said Principal is required under the terms of that Contract to furnish a payment bond in accord with Title 39.08 Revised Code of Washington (RCW) and (where applicable) 60.28 RCW. The Principal, and Ta°aiamcaa°e'tyand S-ty Umpry °fAm,ri a (Surety), a corporation organized under the laws of the State of Connecticut and licensed to do business in the State of Washington as surety and named in the current list of "Surety Companies Acceptable in Federal Bonds" as published in the Federal Register by the Audit Staff Bureau of Accounts, U.S. Treasury Dept., are jointly and severally held and firmly bound to the [City or County], in the sum of Six Hundred Eighty Eight Thousand Four hundred Fifty Five Dollars 8 no cents US Dollars ($ 688,455.00 ) Total Contract Amount, subject to the provisions herein. This statutory payment bond shall become null and void, if and when the Principal, its heirs, executors, administrators, successors, or assigns shall pay all persons in accordance with RCW 39.08, 39.12, and 60.28 including all workers, laborers, mechanics, subcontractors, and materialmen, and all person who shall supply such contractor or subcontractor with provisions and supplies for the carrying on of such work, and all taxes incurred on said Contract under Titles 50 and 51 RCW and all taxes imposed on the Principal under Title 82 RCW; and if such payment obligations have not been fulfilled, this bond shall remain in full force and effect. The Surety for value received agrees that no change, extension of time, alteration or addition to the terms of the Contract, the specifications accompanying the Contract, or to the work to be performed under the Contract shall in any way affect its obligation on this bond, and waives notice of any changes, extension of time, alteration or addition to the terms of the Contract or the work performed. The Surety agrees that modifications and changes to the terms and conditions of the Contract that increase the total amount to be paid the Principal shall automatically increase the obligation of the Surety on this bond and notice to Surety is not required for such increased obligation. This bond may be executed in two (2) original counterparts, and shall be signed by the parties' duly authorized officers. This bond will only be accepted if it is accompanied by a fully executed and original power of attorney for the office executing on behalf of the surety. PRINCIPAL SURETY "I. 06/20/16- -'/- 06/20/2016 Principal Signature Date Suret Signature Date Mark Massmann 06/20/16 Robert A. Yarbrough 06/20/2016 Printed Name Date Printed Name Date President Attorney In Fact Title Title Name, address, and telephone of local office/agent of Surety Company is ......._.......w .......... ........ ..... Travis Belling 1501 4th Ave. Seattle WA 98101 (206) 326-4284 Approved as to form: [Citk or l ounty] Attorney, [Ci, DOT Form 272-003A EF 0812012 Crosswalk Improvements City of Bremerton, Washington Federal Aid # STPUS-9918(015) or 25 County] Date Contract Documents Skillings Connolly, Inc. March 2016 WA—RNING, MIS �PW: WER OF ATTORNEY Al' Farmington Casualty Company St., PaulM.ercury Insurance Company TRAVELERS Fidelity and Guaranty Insurance Company Travelers Casualty and Surety Company Fidelity and Guaranty Insurance Underwriters, Inc. D-avelers Casualty and Surety Company of America ,St. Paul Fire and.Marine Insurance Company United States Fidelity and Guaranty ("ornpany St. Paul Guardian Insurance Company Attorney -In Fact No. 221836 Certificate No. 00Z5829330 KNOW ALL MEN BY THESE PRES]ENTS: 'that Farmington Casualty Company, St, Paul Fire and Marine Insurance Company, St, Paul Guarctian Insurance Company, St. Paul Mercury hasurance Company, Travelers Casualty and Surety Company, Travelers C'astralty and Surety Company of America, and United States Fidelity and Givaratity. Company are corporations (July orp , of Connecticut, that Fidelity and Guaranty Insurance Company is a ganized under the laws of the State corporation duly organized wider the laws of the State of Iowa, and that.iFidelity and Guaranty Insurance Underwriters, Inc., is a corporation difly organized under the laws of the State, of Wisconsin (herein collectively called the "Companies"),air.id that the Companies do hereby make, constitute and appoint Robert A. Yarbrough of the City of Atlanta State, of__ ...... .. ................ .. Georgia .................... their true and lawful. Attorneys)-in.Fact, each in their separate capacity if more than one is, named above, to sign, execute, seal and acknowledge any and all bonds, recognizances, conditional undertakings and other writings obligatory in the nature thereof on behalf of the Companies in their business, of guaranteeing the fidelity of persons, guaranteeing the perforinance of contracts and executi rig or guaranteeing bonds and undertakings required or permitted in any actions or proceedings allowed by law. IN WITNESS WHEREOF, the Companies have caused this institunent to be sipned and their corporate sends to be hereto affixed, this 12th ............... day of March 21114 . ............. .... ... . . .... Farmington Casualty Company Fidelity and Guaranty Insurance Company Fidelity and Guaranty Insurance Underwriters, Inc.. St:. Paul Fire and Marine Insurance Company St. Paul Guardian Insurance Company St. Paul Mercury Insurance Company Travelers Casualty and Surety Company Travelers Casualty and Surety Company of America United States Fidelity and Guaranty Company i_4 E KOO(, A. 0 (z' 06 77 14ARTFO 0 4 A40 Co State of Connecticut City of Hartfords,!i. By: ............... Robert L Raney, enior Vice President On this, the l2th day of March 1 . 2014 - - 1-1111-111-1-1 ............................... . ................. , before me personally appeared Robert L. Raney, who acknowledged himself to be the Senior Vice President of Farmington Casualty Company, Fidelity and Guaranty Insurance Company, Fidelity and Guaranty lrisurtmee Underwriters, Inc., St, Paul 114re and Marine.hisurance Company, St. Paul Guardian [nmrance Company, St. Paul Mercury inmnancc Company, r l'raveiers Casualty and Surety Company, Travelers Casualty and Surety Company ofArrierica, and I.Juited States 11^'idelny and Guaranty Company, and that he, w, such., being authorized %o to do, executed the foregoing instrument for the purposes therein contained by signing on behalf of the corporations by himself as a duly authorized officer. Jer In Witness Whereof, I hereunto set my hand and official seal. ........... .... .. �. . . . . ............... My Cornaussion expires the 30th day of June, 2016. Maxie C.'Fetreault, Notary Public 4 58440 8-12 Printed in U.S.A. WARNING: THIS POWER OF ATTORNEY IS INVALID WITHOUT THE RED BORDER WARNING: THIS POWER OF ATTORNEY IS INVALID WITHOUT THE RED BORDER This Power of Attorney is granted under and by the authority of the following resolutions adopted by the Boards of Directors of Farmington Casualty Company, Fidelity and Guaranty Insurance Company, Fidelity and Guaranty Insurance Underwriters, Inc., St. Paul Fire and Marine Insurance Company, St. Paul Guardian Insurance Company, St. Paul Mercury Insurance Company, Travelers Casualty and Surety Company, Travelers Casualty and Surety Company of America, and United States Fidelity and Guaranty Company, which resolutions are now in full force and effect, reading as follows: RESOLVED, that the Chairman, the President, any Vice Chairman, any Executive Vice President, any Senior Vice President, any Vice President, any Second Vice President, the Treasurer, any Assistant Treasurer, the Corporate Secretary or any Assistant Secretary may appoint Attorneys -in -Fact and Agents to act for and on behalf of the Company and may give such appointee such authority as his or her certificate of authority may prescribe to sign with the Company's name and seal with the Company's seal bonds, recognizances, contracts of indemnity, and other writings obligatory in the nature of a bond, recognizance, or conditional undertaking, and any of said officers or the Board of Directors at any time may remove any such appointee and revoke the power given him or her; and it is FURTHER RESOLVED, that the Chairman, the President, any Vice Chairman, any Executive Vice President, any Senior Vice President or any Vice President may delegate all or any part of the foregoing authority to one or more officers or employees of this Company, provided that each such delegation is in writing and a copy thereof is filed in the office of the Secretary; and it is FURTHER RESOLVED, that any bond, recognizance, contract of indemnity, or writing obligatory in the nature of a bond, recognizance, or conditional undertaking shall be valid and binding upon the Company when (a) signed by the President, any Vice Chairman, any Executive Vice President, any Senior Vice President or any Vice President, any Second Vice President, the Treasurer, any Assistant Treasurer, the Corporate Secretary or any Assistant Secretary and duly attested and sealed with the Company's seal by a Secretary or Assistant Secretary; or (b) duly executed (under seal, if required) by one or more Attorneys -in -Fact and Agents pursuant to the power prescribed in his or her certificate or their certificates of authority or by one or more Company officers pursuant to a written delegation of authority; and it is FURTHER RESOLVED, that the signature of each of the following officers: President, any Executive Vice President, any Senior Vice President, any Vice President, any Assistant Vice President, any Secretary, any Assistant Secretary, and the seal of the Company may be affixed by facsimile to any Power of Attorney or to any certificate relating thereto appointing Resident Vice Presidents, Resident Assistant Secretaries or Attorneys -in -Fact for purposes only of executing and attesting bonds and undertakings and other writings obligatory in the nature thereof, and any such Power of Attorney or certificate bearing such facsimile signature or facsimile seal shall be valid and binding upon the Company and any such power so executed and certified by such facsimile signature and facsimile seal shall be valid and binding on the Company in the future with respect to any bond or understanding to which it is attached. I, Kevin E. Hughes, the undersigned, Assistant Secretary, of Farmington Casualty Company, Fidelity and Guaranty Insurance Company, Fidelity and Guaranty Insurance Underwriters, Inc., St. Paul Fire and Marine Insurance Company, St. Paul Guardian Insurance Company, St. Paul Mercury Insurance Company, Travelers Casualty and Surety Company, Travelers Casualty and Surety Company of America, and United States Fidelity and Guaranty Company do hereby certify that the above and foregoing is a true and correct copy of the Power of Attorney executed by said Companies, which is in full force and effect and has not been revoked. IN TESTIMONY WHEREOF, I have hereunto set my hand and affixed the seals of said Companies this Z7" day of '20 f Kevin E. Hughes, Assist�Sec, 2 CSA.. yvuvq B �� 6_11(1 1482 1977 is n; ; }; _•_ o ` NAHTWRD, HARTF6pp, ' s 4 �b 1951 _ ,•;SePiLio. STS.iS.7r_i3 Z dy4""��i ..a� �w6' a' �.o's eJO�i bd a�f,o�•... .•'LD 6 L "•..�"l To verify the authenticity of this Power of Attorney, call 1-800-421-3880 or contact us at www.travelersbond.com. Please refer to the Attorney -In -Fact number, the above-named individuals and the details of the bond to which the power is attached. WARNING: THIS POWER OF ATTORNEY IS INVALID WITHOUT THE RED BORDER